How to win in mediation Accceleration - more haste, less speed Limitation: time to revisit an old friend?

Size: px
Start display at page:

Download "How to win in mediation Accceleration - more haste, less speed Limitation: time to revisit an old friend?"

Transcription

1 Building On... KNOWLEDGE EXPERIENCE BEST PRACTICE Issue 04 - Autumn 2009 This issue How to win in mediation Accceleration - more haste, less speed Limitation: time to revisit an old friend? Possession is 9/10ths of the law As the saying goes, possession is 9/10th of the law and a contractor with exclusive possession of a site during the course of construction works needs to be careful not to lose that right as it can have unintended consequences, particularly in relation to the amount of liquidated damages that are payable in the event that completion is delayed. Equally an unwary employer may lose its right to damages for delay by entering the site too early. Welcome Welcome to the fourth edition of our construction and engineering newsletter, "Building On". There have been a number of Court decisions in the last few years which have considered this issue and provide a useful lesson in the problems that can occur. Types of possession There are essentially three types of possession over the course of a construction project: exclusive possession by the contractor during construction exclusive possession by the contractor but allowing the employer to use or occupy part or all of the site and partial possession which involves the employer taking possession of part of the works before the project has been fully completed. Construction contracts treat the latter two types of possession very differently to the first. 'Use and occupation' In Impresa Castelli SPA v Cola Holdings Ltd, Impresa agreed to build a large 4-star hotel in London for Cola under a JCT 1981 contract. Delays occurred and the date for completion passed. The parties entered into several agreements delaying the date for completion including a written agreement on 1 September 1999, in which they agreed that Impresa would allow Cola staged "access" to the site so that by 12 September 1999 it could operate as a hotel. Such access was, however, not to be regarded as amounting to practical completion. The agreement also listed a number of works, including the air conditioning system, which were not yet complete. The works remained incomplete and by 21 May 2001, Cola alleged that Impresa had abandoned site. Cola claimed liquidated damages and Impresa defended Cola's claim by arguing that the grant of "access" by the September agreement amounted to Cola taking partial possession of the greater part of the works with the resultant effect that Cola should not be able to recover the full rate of liquidated damages. In this issue, Alex Grant looks at the difference between the types of 'possession' that can occur during a construction project and resident editor, Kevin Joyce, discusses acceleration in the context of major construction or engineering projects. Neal Morris sets out his thoughts on how to get the best out of mediation and James Ladner considers the recent proposals by the Law Commission to reform the law on the limitation periods. Finally, Shy Jackson rounds off with a digest of the latest case law. We do hope you find the newsletter enjoyable and informative. Andrew Hibbert Head of UK Construction and Engineering

2 ...continued from page 1 The key clause of the contract was clause 17.1 (similar to clause 2.33 of JCT05 form). This entitled Cola, with the reasonable consent of Impresa, to take possession of part of the Works (referred to as the "relevant part"). In such circumstances, practical completion in relation to the relevant part would be deemed to have occurred with the result that a mini defects liability period would begin to run, there would be a partial payment of retention, a reduction in the liability to pay liquidated damages, and the employer would be obliged to maintain joint names insurance and reinstate the works if damaged in respect of the relevant part. In contrast, under clause of the contract (the equivalent of clause 2.6 in the JCT05 form) Cola, with the reasonable consent of Impresa, could use or occupy the whole or part of the site before practical completion, without any of the consequences of partial possession. The judge therefore had to decide whether partial possession had occurred under clause 17.1 or whether Cola's presence was merely use or occupation under clause The judge noted that if Cola had intended to take back exclusive possession, despite the fact that certain works were incomplete the September agreement could have used the words partial possession instead of referring to access. The judge found nothing to suggest that partial possession had occurred. In looking at the factual background to the problems with the air conditioning system and Cola's need to have the hotel operational by 12 September as well as the intention of the parties as evidenced through the wording of the September agreement, the judge concluded that the word "access" in the September agreement implied "use and occupation" as referred to in clause rather than "partial possession" as referred to in clause As a result, Cola s presence did not amount to partial possession, Impresa s liability for damages was not reduced and Cola s claim was enforceable. Indeed, despite the fact that Cola was able to access and make use of the works for the very purposes for which they were intended (i.e. as a hotel), Cola was able to recover the full amount of liquidated damages. 'Partial possession' Shortly after Impresa came the decision in Skanska Construction (Regions) Ltd v Anglo-Amsterdam Corporation Ltd. Skanska was employed by Anglo- Amsterdam to construct a purpose built office facility in Edinburgh. As in Impresa the contract was a JCT 1981 standard form. Anglo- Amsterdam alleged that Skanska was late in the completion of the works and applied liquidated damages. Skanska argued it had achieved practical completion on time, or alternatively that Anglo- Amsterdam had taken partial possession. The operation of clause 17.1 meant that Skanska was not liable to pay liquidated damages. Clause 16 of the contract was amended to impose a more stringent test for establishing practical completion. Under the test it appeared that in two ways the works were not complete: the air conditioning system was not functioning and Skanska had not produced operating and maintenance manuals. The arbitrator appointed by the parties to determine the dispute decided that practical completion had not occurred. Anglo-Amsterdam had written to Skanska confirming that the proposed tenant for the building, ICL, would commence fitting out works on the disputed date of practical completion. ICL was charged with responsibility for security once it entered into this non-exclusive possession and Skanska was allowed access to carry out work, subject to making the necessary security and access arrangements with ICL. Skanska argued that once ICL had started its fit-out of the building, the employer had taken partial possession of the entirety of the works and Skanska no longer had to pay damages for delay. The arbitrator disagreed and took the view that the purpose of clause 17.1 was to deal with the situation in which an employer takes partial, not complete, possession. The clause could not apply where the entirety of the works had been given over to a tenant for fit-out. Skanska was therefore liable to pay liquidated damages until practical completion was achieved under clause 16. On appeal to the Court, the judge overturned the arbitrator s decision. He found that clause 17.1 could operate when possession had been taken of all parts of the works and was not limited to possession of part. He concluded that partial possession of the entirety of the works had been taken as a result of the employer agreeing to ICL starting the fit-out. Consequently Skanska was entitled to repayment of the damages. Conclusion Often on construction projects a developer will be keen to get on site to commence fit out or start operating their business and contractors trying to be helpful will try and facilitate this. However employers and contractors need to beware of the unintended consequences of inadvertently taking possession of a site and the impact this can have on the operation of their contract. alexander.grant Key points There are three types of possession of the site: exclusive possession, exclusive possession with use/occupation by the client and partial possession. The consequences of each (under the JCT contract) are very different: partial possession relieves the contractor of part of its liquidated damages (and other) risk but granting use of part of the site does not. When giving consent for partial possession or allowing the employer use and occupation, a contractor should be clear as to exactly which consent it is granting. Clear and unambiguous written consent is vital in achieving this aim. It is possible to have partial possession of the whole of the works. 2

3 How to win in mediation Mediation is now firmly established in the UK construction and engineering sectors for the cost-effective resolution of disputes. But how do you ensure you get the best result? Mediation is concerned with achieving "win-win" solutions, where both parties consider the settlement which they arrive at to be a success. But there is a difference between a narrow win and a convincing one - winning in mediation is concerned with achieving the best winning results. This best result may be in terms of the intangible benefits which mediation brings to the resolution. It is not limited simply to how much to pay or to be paid. Given mediation's increased use in the construction industry, how do participants get the best out of it? Is mediation the right method of dispute resolution? The first consideration is to ensure that mediation is the right method of dispute resolution and that it is used at the right time in the dispute. Mediation is not the best process for all disputes. As no settlement can be guaranteed, adjudication or expert determination may be preferable if certainty and cash flow are vital. A party is also unlikely to achieve its best commercial settlement through mediation if the process takes place before it has had an opportunity to convey some of the strengths of its case to the other side, or to understand some of its weaknesses. Knowledge is power Mediation is known as an assisted negotiation. As in any negotiation, knowledge is power, so arm yourself with as much knowledge about your dispute and the other party as possible. The key to this is to understand what the issues will be: What are each parties' strengths and weaknesses on those issues? Most importantly, what will happen if the dispute is not settled? In mediation jargon, the acronyms BATNA and WATNA are used. They mean "Best" and "Worse" Alternative To a Negotiated Agreement. Make sure you collect as much advice as possible specific to likely recovery/payment levels, chances of success, timescales and budgeting. This enables you to carry out a risk assessment and to negotiate confidently at the mediation. Your mediation team The next step is to select your mediation team. Choose the members of your organisation and its advisers who can put you in the best negotiating position. This team is kept as small as possible and must include your commercial decision maker. In disputes involving large sums, it is often helpful to involve expert witnesses. With a good mediator's assistance and direction they can play a helpful part in persuading the other party of the strengths of your case and also in helping their own party understand its weaknesses. Employing experts requires judgement as to whether they will bring the parties closer together and towards your viewpoint. Bear in mind that an unfettered, adversarial approach by experts can be counterproductive, as well as a waste of time and costs. Similar considerations apply to involving Counsel in the mediation team. In some cases, where parties appear to have opposing views on points of law, a frank discussion between Counsel can crack a dispute and produce a settlement far more economically than a full trial or preliminary issue. The other side's team You then need to ensure that the other party has the right mediation team. Do they have their ultimate decision-maker involved in the preparation and present in person at the mediation? Only if the person who authorises the cheque is in the room will your persuasive arguments have their best effect and produce the best result. Similarly, there is no point preparing your experts to persuade their counterparts if the other party intends the mediation only to be a commercial discussion of settlement figures. He who prepares best usually gets the best result. The negotiation plan The next step is to prepare a negotiation plan. Think about: How will you persuade the other party of the strengths of your case in the early phases of the mediation? How will you deal with its weaknesses when the other side raise them? What negotiating tactics will work best? Do you make the first offer to control expectations, or is this a sign of weakness? At what level will you pitch your offer? What is your plan for movement from that opening gambit? In practice, a reasoned approach, which you have thought through and rehearsed in advance, is very effective and can often lead to a better settlement than bargaining. Rehearsing these arguments in advance, putting yourself in the other party's shoes, preparing for unorthodox solutions, is all time very well spent. And finally One final practical tip. All mediations reach a stage of deadlock. Be ready for this. Plan for it. Do not abandon hope. Be ready with some final arguments or unorthodox solution to break that deadlock and get what you want. Mediation works. Try it! neal.morris 3

4 Acceleration - more haste, less speed Given the vagaries of construction or engineering processes and the uncertainties into which projects often launch, progress is invariably different to planned intention. The concept of 'acceleration' is therefore relevant to all construction and engineering contracts. If progress is slow, acceleration is often considered as an option by which the project team can claw-back time that has been lost and not rely solely on the hope that things will improve later on in the project and result in completion on time. What is 'acceleration'? Acceleration is where the contractor takes steps, despite a change to the works, to achieve the original completion date or to achieve an earlier completion date than would otherwise be the case. It is an increase in the intensity of the work being carried out with the aim of bringing the job in on time and should not be confused with mitigation which is simply reallocation of existing assets in order to minimise cost and delay under the changed conditions on the site. If the contractor has accelerated, it will want to recover the costs it inevitably occurs in: Adopting increased working hours Working weekends Instigating double or triple shifts or Bringing in extra equipment or other resources to speed up the work. In circumstances where the employer expressly instructs the contractor to accelerate and where the need to accelerate does not arise from the contractor's own delay, then the right to recover the acceleration costs is often relatively straightforward. More difficult, but probably more common, is the situation where there is no clear instruction to accelerate. This sort of situation may arise where for example the contractor thinks he has a valid claim for an extension of time and notifies the employer of this; the employer (or his Project Manager or Contract Administrator) refuses or fails to grant an extension of time and the contractor, rather than risk being wrong and having to pay liquidated damages, decides to accelerate to make up the delay. On the other hand, the employer may want the contractor to accelerate, not just to achieve an earlier completion date but to make up delays so that the original completion date can be met. If the building or engineering contract is silent on this type of acceleration then the employer will have no right to issue such an instruction and will 4 have to reach a side agreement with the contractor. The contract terms The GC/Works and JCT05 contracts contain relatively structured procedures enabling the parties to accelerate to achieve completion before the completion date specified in the contract based on a quotation and acceptance procedure. By comparison, the NEC3 adopts a relatively simple procedure for acceleration (again, based on quotation and acceptance). However, these forms only provide for acceleration to achieve an earlier completion and not acceleration to make up delay and achieve the existing completion date. Constructive acceleration What happens where the employer refuses to grant an extension of time and the contractor considers it is obliged to accelerate in order to hit the original completion date? This is what is known as "constructive acceleration", a principal recognised in the United States and Australia. In these jurisdictions, if a contractor can prove that a delaying event was one for which it ought to have been awarded an extension of time and the certifier under the contract refuses to grant an extension of time either promptly or at all, a contractor may be permitted to claim acceleration costs on the basis of an implied instruction to the contractor to accelerate, overcome delays and finish the project by the contractual completion date. In the UK, however, the Courts do not as openly accept the principle of 'constructive acceleration'. The conventional position is that the parties have included provisions for extensions of time in the contract and if the employer fails to grant an appropriate extension, the dispute resolution provisions should be used to correct such failure. In reality, however, there will often be significant commercial pressures on the Contractor if it continues at its normal rate of progress and becomes liable to pay liquidated damages while the Project Manager or Engineer makes up its mind as to the contractor's entitlements and/or the parties follow the dispute resolution procedures in the contract. These commercial pressures often outweigh the risk of accelerating to bring the job to a timely conclusion in the hope that some allowance for acceleration costs will be made in the final account. In Ascon Contracting Limited v Alfred McAlpine Construction Isle of Man Limited and Motherwell Bridge v Micafil Vacuum Technik the Courts appeared to suggest that there are certain limited circumstances where the contractor may be able to recover its acceleration costs even where there has been no express instruction to accelerate and where there is no agreement as to which party is responsible for the delay which the contractor is attempting to make up. However, the position remains unclear.

5 Best practice - the contractor s perspective Given the uncertainty surrounding the authorities in English law on the circumstances in which a claim for acceleration costs will be successful, the best advice for the contractor remains to attempt to resolve extension of time claims promptly and/or obtain from the employer a written instruction to accelerate before undertaking such works. Where that is not possible but where the contractor decides that nonetheless he will take accelerative measures, he needs to set out clearly beforehand, the basis of the steps he is going to take, explaining what it is about the conduct of the Employer which leaves the Contractor to consider that he is effectively being instructed to accelerate. If it is subsequently established that the causes of delay are the responsibility of the Employer, there is a prospect that the Contractor may be able to recover its costs, either as loss and expense, damages for breach or on the basis of unjust enrichment. Once the principle of whether acceleration costs can be recovered has been established the Contractor then needs to be able to prove what these costs are. Its chances of success will be greatly enhanced the better the records it has kept. Best practice - the employer s perspective From the employer's point of view, the contractor's entitlements to an extension of time should be addressed promptly and agreement sought in relation to the value of acceleration if possible. If you do not intend to instruct acceleration then extreme care needs to be taken with written and oral communication as an inadvertent reference to it could result in arguments from the contractor that it has actually been so instructed. Once again, ensure that good records are maintained so that the additional costs can be traced back to additional resource not instructed. kevin.joyce Limitation: time to revisit an old friend? When a problem arises on an old job, everyone knows that the time limit for bringing a claim depends on whether the contract was a simple contract, where the claimant has six years from the date of breach to make a formal claim or where the contract was executed as a deed where the limit is 12 years. But is it really that straightforward? The answer is a resounding "no". The six/twelve year rule is only the position in relation to most breaches of contract; the position in tort (for example, in negligence cases) differs, here the law allows six years from the date when the damage is suffered, which may be a long time after the breach of duty occurred. This is particularly relevant in relation to claims against consultants. The six year / twelve year rule does not take into account deliberately concealed breaches (such as those sometimes alleged in relation to defects) or where the future defendant has agreed that money is due (as is often seen on final account disputes). Both extend the period in accordance with the detailed facts. As a result of these and other peculiarities, the time at which a claim becomes barred can vary by years in the sorts of disputes that we regularly come across in the construction world. In light of this complex legal framework, the Law Commission has recommended to the Ministry of Justice that the law on limitation be reformed and the Ministry has issued an 5

6 informal consultation asking for views. These will be published along with the draft bill later this year. The proposal The Commission has recommended a core limitation period applicable to the majority of cases in contract and tort (not including personal injury) of three years, with the three year period commencing from when the claimant acquired sufficient knowledge to bring the claim. The three year count down from this date of knowledge starts running when the claimant knows or ought to have known: (i) the facts that give rise to the claim; (ii) the identity of the defendant; and (iii) that the injury, loss or damage is significant. The proposal also includes a "long stop date" of ten years from when the act or omission complained of occurred (or should have occurred), after which the claim becomes barred. The Commission accepts that these time limits can be extended in cases of concealment. A three year period for claims is somewhat shorter than the 12 years that the industry is used to. The Commission implicitly recognise this and propose that both the core period and long stop period can be modified by agreement. However, such bespoke arrangements would be subject to statutory rules on fairness to militate against the risk of unreasonably long or short periods. Consequences Many have argued, in the current depressed market, that the proposed regime will result in longer limitation periods leading to increased risk for contractors and difficulties or additional expense in purchasing insurance. This may be the case but it seems that the proposal could also allow the opposite with a statutory basis for parties to agree periods less than the 12 year norm resulting from contracting by deed. This flexibility may allow reduced project insurance costs. The other major change, claims running from the date of knowledge, seems more likely to be a cause of future difficulties as claimants will often be in the best position to make out the facts which could lead to uncertainty as to the end of the limitation period to the detriment of defendants. When examined, the simplified scheme appears to have almost as many caveats as the existing position and it is therefore doubtful (flexibility aside) that the perceived benefits of the proposed legislation outweigh the new issues raised by it. james.ladner Case law update Chartbrook Limited v Persimmon Homes Limited (1 July 2009) On 30 July 2009 the House of Lords handed down its final judgment and from 1 October 2009 was replaced by the Supreme Court. This was one of the last decisions by the House of Lords and it deals with interpreting contracts. The specific issue was the extent to which a complicated payment formula could be interpreted by using pre-contractual correspondence. It was argued that the pre-contractual correspondence should be taken into account, since it was clearly identified the correct interpretation. The House of Lords held that it is necessary to take an objective approach and to construe the specific term in the context of the contract as a whole and its "business purpose". It was confirmed that pre-contractual correspondence could not be taken into account when interpreting contracts. This was because such correspondence was subjective and would result in greater uncertainty. The lesson is therefore to ensure that everything that has been 6

7 agreed is clearly set out in the contract. It will not be possible, except in rare cases, to rely on pre-contract negotiations to explain what the contract means. Siemens Building Technologies FE Ltd v Supershield Ltd (1 May 2009) Construction claims often involve more than one party and following a settlement there will sometimes be an attempt to recover the settlement sum, or part of it, from a third party. The key to such claims is proving that the settlement was reasonable and this case provides useful guidance on how such reasonableness is determined. The court made it clear that the test is whether the settlement was, in all circumstances, within the range of settlements which reasonable people in the position of the settling party might have made. The Court gave examples of such circumstances, including the strength of the claim, whether the settlement was the result of legal advice, the uncertainties and expenses of litigation and the benefits of settling the case rather than disputing it. This case demonstrates the difficulty of challenging a settlement as unreasonable. However, such challenges can be avoided by ensuring that there is a contemporaneous written record, such as an internal memo, setting out the background and the commercial and legal reasons for the settlement. Estor Ltd v Multifit (UK) Ltd (12 August 2009) In this case, the main contractor fell out with the employer and left the site. The sub-contractor, who carried out most of the works, agreed to complete the works on the basis of a quote sent and accepted by . Although the quote excluded part of the works, it appears that the sub-contractor paid the other sub-contractor who was carrying out the excluded works. A formal contract was never executed. The sub-contractor then obtained an adjudication decision in its favour. The employer resisted enforcement on the basis that it was the parent company who was named as the employer in the adjudication rather than the subsidiary company, although both were represented by the same person. The judge held that which company was the employer was a question of fact, which could not decided as part of the summary judgment application. As a result, the sub-contractor could not enforce the adjudication decision. This judgment demonstrates the importance of identifying the precise party to the contract, especially when dealing with individuals who may act for several group companies, and the scope of works. Such uncertainties can be avoided by executing a formal contract. shy.jackson Pinsent Masons LLP 2009 This note does not constitute legal advice. Specific legal advice should be taken before acting on any of the topics covered. LONDON DUBAI BEIJING SHANGHAI HONG KONG SINGAPORE OTHER UK LOCATIONS: BIRMINGHAM BRISTOL EDINBURGH GLASGOW LEEDS MANCHESTER T Pinsent Masons LLP is a limited liability partnership registered in England & Wales (registered number: OC333653) and regulated by the Solicitors Regulation Authority. The word 'partner', used in relation to the LLP, refers to a member of the LLP or an employee or consultant of the LLP or any affiliated firm who is a lawyer with equivalent standing and qualifications. Singapore location in association with MPillay. A list of members of the LLP, and of those non-members who are designated as partners, is displayed at the LLP's registered office: CityPoint, One Ropemaker Street, London, EC2Y 9AH, United Kingdom. We use Pinsent Masons to refer to Pinsent Masons LLP and affiliated entities that practise under the name Pinsent Masons or a name that incorporates those words. Reference to Pinsent Masons is to Pinsent Masons LLP and/or one or more of those affiliated entities as the context requires. For important regulatory information please visit:

Advice Note. An overview of civil proceedings in England. Introduction

Advice Note. An overview of civil proceedings in England. Introduction Advice Note An overview of civil proceedings in England Introduction There is no civil code in England; English civil law comprises of essentially legislation by Parliament and decisions by the courts.

More information

Pinsent Masons. Competition Law Dawn Raid Checklist & Guidelines. What to do in the first hour of a dawn raid

Pinsent Masons. Competition Law Dawn Raid Checklist & Guidelines. What to do in the first hour of a dawn raid Pinsent Masons Competition Law Dawn Raid Checklist & Guidelines What to do in the first hour of a dawn raid What to do in the first hour of a Competition Dawn Raid Checklist Action Point Done? The Officials

More information

ENA SHE12 Major Incident H&S Aspects a Lawyer s perspective. Kevin Bridges Partner and Chartered Safety and Health Practitioner

ENA SHE12 Major Incident H&S Aspects a Lawyer s perspective. Kevin Bridges Partner and Chartered Safety and Health Practitioner ENA SHE12 Major Incident H&S Aspects a Lawyer s perspective Kevin Bridges Partner and Chartered Safety and Health Practitioner Implement an Incident Response Protocol Covering: - Escalating incidents internally

More information

CONTRACTING HINTS AND TIPS

CONTRACTING HINTS AND TIPS CONTRACTING HINTS AND TIPS Contents 1. Contract formation 2. Entire agreement clauses 3. Warranties and indemnities 4. Time of the essence 5. Contract variation 6. Exclusion and limitation clauses 7. Exercising

More information

Alternative Dispute Resolution (ADR) Procedures

Alternative Dispute Resolution (ADR) Procedures Alternative Dispute Resolution (ADR) Procedures The background Traditional dispute resolution procedures Private Negotiation 1. A lost skill, negotiation is a process of the parties themselves or via skilled

More information

Business leases guide

Business leases guide Business leases guide BUSINESS LEASES GUIDE Contents What is a business "tenancy"? Creation of a tenancy Common terms in lease Repairing liability FRI terms Landlord's covenants Insurance Tenant's continuing

More information

Insurance claims and losses in Spain. Procedural aspects of the Spanish legal system

Insurance claims and losses in Spain. Procedural aspects of the Spanish legal system Insurance claims and losses in Spain. Procedural aspects of the Spanish legal system Further information If you would like further information, please contact a person mentioned below or the person with

More information

Shared Services Toolkit

Shared Services Toolkit Shared Services Toolkit Shared Services Toolkit Introduction Sharing services is essential if Government is to meet its financial targets. Whether you do this as a group of central or local Government

More information

Thames Water Utilities Limited. Settlement deed

Thames Water Utilities Limited. Settlement deed Thames Water Utilities Limited Settlement deed DATED [ ] THAMES WATER UTILITIES LIMITED the Undertaker [ ] the Owner DEED relating to the mitigation of the effects of settlement arising from the construction

More information

PRODUCT RULING BR PRD 15/04

PRODUCT RULING BR PRD 15/04 Office of the Chief Tax Counsel Te Tari o te Rōia Tāke Matua Asteron Centre 55 Featherston Street PO Box 2198 Wellington 6140 New Zealand Telephone: 04 890-1500 Facsimile Numbers: Chief Tax Counsel: 04

More information

BSkyB v EDS judgment at long last

BSkyB v EDS judgment at long last BSkyB v EDS judgment at long last a dodgy degree, a dog called Lulu and some lessons for both customers and suppliers This is a briefing on the long-awaited judgment in BSkyB s claim against what was Electronic

More information

Heslop & Platt Solicitors Limited

Heslop & Platt Solicitors Limited TERMS OF BUSINESS Heslop & Platt Solicitors Limited 1. Introduction and Definitions 1.1 In these terms of business, the following words and phrases have the following meanings: Initial Client Letter Client

More information

At first sight Wellesley Partners LLP v Withers LLP [2015] EWCA Civ 1146 is just

At first sight Wellesley Partners LLP v Withers LLP [2015] EWCA Civ 1146 is just TWO IMPORTANT CASES WELLESLEY PARTNERS LLP the test of remoteness. At first sight Wellesley Partners LLP v Withers LLP [2015] EWCA Civ 1146 is just another slightly dreary solicitors negligence case where

More information

LEGAL SCHEME REGULATIONS

LEGAL SCHEME REGULATIONS LEGAL SCHEME REGULATIONS These Regulations came into force on 1 July 2014. 1 Introduction 1.1 These Regulations govern the Union s legal Scheme. The Rules of the Union set out your other rights and entitlements.

More information

Taking Action. Dispute resolution, legal action and claims for negligence

Taking Action. Dispute resolution, legal action and claims for negligence Taking Action Dispute resolution, legal action and claims for negligence Taking Action Part 3: Dispute Resolution, taking legal action and claims for negligence Introduction If you believe an architect

More information

B R e s t o R i n g C o n f i d e n C e

B R e s t o R i n g C o n f i d e n C e B u i l d i n g B C Options for Resolving Residential Construction Disputes R e s t o r i n g C o n f i d e n c e Canadian Cataloguing in Publication Data Main entry under title: Options for resolving

More information

CONDITIONAL FEE AGREEMENTS GUIDANCE

CONDITIONAL FEE AGREEMENTS GUIDANCE Disclaimer In all cases solicitors must ensure that any agreement with a client is made in compliance with their professional duties, the requirements of the SRA and any statutory requirements depending

More information

TEMPLE LITIGATION ADVANTAGE INSURANCE FOR DISBURSEMENTS AND OPPONENT S COSTS Certificate of Insurance

TEMPLE LITIGATION ADVANTAGE INSURANCE FOR DISBURSEMENTS AND OPPONENT S COSTS Certificate of Insurance TEMPLE LITIGATION ADVANTAGE INSURANCE FOR DISBURSEMENTS AND OPPONENT S COSTS Certificate of Insurance In return for the payment of the Premium specified in the Schedule and based on any Information that

More information

GUIDE TO FUNDING YOUR MEDICAL NEGLIGENCE CLAIM

GUIDE TO FUNDING YOUR MEDICAL NEGLIGENCE CLAIM GUIDE TO FUNDING YOUR MEDICAL NEGLIGENCE CLAIM Because of the expert knowledge and depth of investigation required in order to bring a successful claim, negligence litigation can be expensive. Understandably,

More information

Risks in International Consultancy Appointments: The FIDIC White Book

Risks in International Consultancy Appointments: The FIDIC White Book Risks in International Consultancy Appointments: The FIDIC White Book An increasing number of UK based consultants are involved in international projects. Given the forecasted growth in global construction

More information

Recovery of Overhead and Profit when delay occurs

Recovery of Overhead and Profit when delay occurs Recovery of Overhead and Profit when delay occurs When a Contractor has established a right to an extension of time which also carries a right to reimbursement of costs for the delay to his Works, then

More information

Knowhow briefs Without Prejudice

Knowhow briefs Without Prejudice Knowhow briefs Without Prejudice Executive Summary: Without Prejudice ( WP ) communications made in a genuine attempt to settle a dispute may not be used in court as evidence of an admission. WP communications

More information

Conditional Fee Arrangements, After the Event Insurance and beyond!

Conditional Fee Arrangements, After the Event Insurance and beyond! Conditional Fee Arrangements, After the Event Insurance and beyond! CFAs, ATEs, DBAs Let s de-mystify the acronyms! 1. Conditional Fee Arrangements 1.1. What is a Conditional Fee Arrangement A conditional

More information

IMF (Australia) Ltd. Combined Financial Services Guide and Product Disclosure Statement

IMF (Australia) Ltd. Combined Financial Services Guide and Product Disclosure Statement IMF (Australia) Ltd Combined Financial Services Guide and Product Disclosure Statement Dated the 18th day of January 2010 FINANCIAL SERVICES GUIDE & PRODUCT DISCLOSURE STATEMENT PAGE 2 1. Introduction

More information

Dispute Resolution Bringing A Small Claim

Dispute Resolution Bringing A Small Claim Dispute Resolution Bringing A Small Claim Kirwans is one of the North West s most forward thinking law firms. As an allservicing firm, our success has been built upon delivering expert knowledge and expertise

More information

AE RISK REVIEW A PUBLICATION FOR DESIGN PROFESSIONALS YOUR RISK MANAGEMENT CONNECTION. Prevailing Opinions on Prevailing Party Contract Clauses

AE RISK REVIEW A PUBLICATION FOR DESIGN PROFESSIONALS YOUR RISK MANAGEMENT CONNECTION. Prevailing Opinions on Prevailing Party Contract Clauses AE RISK REVIEW A PUBLICATION FOR DESIGN PROFESSIONALS YOUR RISK MANAGEMENT CONNECTION This material is provided for informational purposes only. Before taking any action that could have legal or other

More information

Back to Basics: Professional Indemnity Construction and Engineering

Back to Basics: Professional Indemnity Construction and Engineering Back to Basics: Professional Indemnity Construction and Engineering December 2015 Table of Contents Table of Contents... 2 Introduction... 3 Part A - Understanding the construction industry... 4 1 Construction

More information

Sample Arbitration Clauses with Comments

Sample Arbitration Clauses with Comments Sample Arbitration Clauses with Comments BRIEF DESCRIPTION Arbitrations are creatures of contract. Thus, the parties can shape an arbitration proceeding to a great extent in their arbitration agreements.

More information

Clinical Negligence: A guide to making a claim

Clinical Negligence: A guide to making a claim : A guide to making a claim 2 Our guide to making a clinical negligence claim At Kingsley Napley, our guiding principle is to provide you with a dedicated client service and we aim to make the claims process

More information

Conditional Fee Agreement ( CFA ) [For use in personal injury and clinical negligence cases only].

Conditional Fee Agreement ( CFA ) [For use in personal injury and clinical negligence cases only]. Disclaimer This model agreement is not a precedent for use with all clients and it will need to be adapted/modified depending on the individual clients circumstances and solicitors business models. In

More information

The arbitration world is, I understand, flourishing in Australia. There has been an increase

The arbitration world is, I understand, flourishing in Australia. There has been an increase The London 2016 International and Commercial Law Conference Is Commercial Arbitration the Future of Commercial Justice? Intervention by the Rt Hon Lady Justice Arden DBE June 2016 The arbitration world

More information

ICE Legal Notes Series

ICE Legal Notes Series ICE Legal Notes Series Legal Notes Reviewing the work of another Engineer and replacing another Engineer Institution of Civil Engineers www.ice.org.uk Published by the Institution of Civil Engineers (ICE).

More information

Clinical Negligence. Issue of proceedings through to Trial

Clinical Negligence. Issue of proceedings through to Trial Clinical Negligence Issue of proceedings through to Trial Lees Solicitors LLP 44/45 Hamilton Square Birkenhead Wirral CH41 5AR Tel: 0151 647 9381 Fax: 0151 649 0124 e-mail: newclaim@lees.co.uk 1 1 April

More information

Commercial leases and insurance claims

Commercial leases and insurance claims Commercial leases and insurance claims by the CILA Property Special Interest Group 31st May 2016 Introduction This paper is intended as a guidance document to understanding commercial leases, particularly

More information

1.2 Analyse matters to be considered by the judge when awarding damages for pain, suffering and loss of amenity

1.2 Analyse matters to be considered by the judge when awarding damages for pain, suffering and loss of amenity Title Damages, Settlement and Costs in Personal Injury Cases Level 4 Credit value 8 Learning outcomes The learner will: Assessment criteria The learner can: Knowledge, understanding and skills 1 Understand

More information

The Commercial Agents Regulations.DOC. The Commercial Agents Regulations

The Commercial Agents Regulations.DOC. The Commercial Agents Regulations The Commercial Agents Regulations.DOC The Commercial Agents Regulations Contents 1. Introduction... 1 2. The Previous Position... 1 3. Commercial Agent... 2 4. Rights and Duties... 3 5. Remuneration...

More information

Avant welcomes the opportunity to provide input into the Productivity Commission s draft report on Access to Justice Arrangements.

Avant welcomes the opportunity to provide input into the Productivity Commission s draft report on Access to Justice Arrangements. 21 May 2014 Access to Justice Productivity Commission GPO Box 1428 Canberra City ACT 2601 Access to Justice Arrangements Draft Report Avant welcomes the opportunity to provide input into the Productivity

More information

Personal Injury Accreditation. Initial application guidance notes

Personal Injury Accreditation. Initial application guidance notes Contents Overall guidance... 3 Glossary of terms... 4 About the accreditation... 5 Eligibility to apply... 5 Expected standards of competence... 5 Application form guidance... 6 Section 1 - General information...

More information

CONTRACT FOR THE APPOINTMENT OF AN APPROVED INSPECTOR

CONTRACT FOR THE APPOINTMENT OF AN APPROVED INSPECTOR CONTRACT FOR THE APPOINTMENT OF AN APPROVED INSPECTOR CIC/AppInsp The Construction Industry Council - Association of Consultant Approved Inspectors contract for the appointment of an approved inspector

More information

Legal Watch: Personal Injury

Legal Watch: Personal Injury Legal Watch: Personal Injury 2nd July 2014 Issue: 025 Part 36 As can be seen from the case of Supergroup Plc v Justenough Software Corp Inc [Lawtel 30/06/2014] Part 36 is still the subject of varying interpretations.

More information

CLINICAL NEGLIGENCE SCHEME FOR TRUSTS

CLINICAL NEGLIGENCE SCHEME FOR TRUSTS CLINICAL NEGLIGENCE SCHEME FOR TRUSTS MEMBERSHIP RULES April 2001 (Revised 1 May 2014 following the coming into force of The National Health Service (Clinical Negligence Scheme) (Amendment) Regulations

More information

TERMS & CONDITIONS CONTRACTOR SERVICES

TERMS & CONDITIONS CONTRACTOR SERVICES TERMS & CONDITIONS CONTRACTOR SERVICES Hahn Electrical Contracting Pty Ltd EC003930 ACN 009 434 904 ABN 23 364 787 165 Hahn Electrical Contracting Pty Ltd Terms& Conditions Contracting EC 003930 ABN 23

More information

Clinical Negligence. Investigating Your Claim

Clinical Negligence. Investigating Your Claim www.lees.co.uk Clinical Negligence Investigating Your Claim Lees Solicitors LLP 44/45 Hamilton Square Birkenhead Wirral CH41 5AR Tel: 0151 647 9381 Fax: 0151 649 0124 e-mail: newclaim@lees.co.uk 1 The

More information

www.mcdermottqc.com Legal Aid, Sentencing and Punishment of Offenders Bill: Implications for Personal Injury Litigation

www.mcdermottqc.com Legal Aid, Sentencing and Punishment of Offenders Bill: Implications for Personal Injury Litigation www.mcdermottqc.com Legal Aid, Sentencing and Punishment of Offenders Bill: Legal Aid, Sentencing and Punishment of Offenders Bill: The Legal Aid, Sentencing and Punishment of Offenders Bill covers a wide

More information

making a road traffic accident claim

making a road traffic accident claim W E L C O M E P A C K making a road traffic accident claim T H A N K Y O U A N D W E L C O M E Thank you for instructing Colemans-ctts solicitors. We have been helping people claim compensation for over

More information

JRI S STANDARD TERMS OF PURCHASE. Business Day: a day (other than a Saturday, Sunday or public holiday) when banks in London are open for business.

JRI S STANDARD TERMS OF PURCHASE. Business Day: a day (other than a Saturday, Sunday or public holiday) when banks in London are open for business. JRI S STANDARD TERMS OF PURCHASE 1. INTERPRETATION 1.1 Definitions. In these Conditions, the following definitions apply: Business Day: a day (other than a Saturday, Sunday or public holiday) when banks

More information

AN END TO BEING KNOCKED OUT ON PENALTIES?

AN END TO BEING KNOCKED OUT ON PENALTIES? BRIEFING AN END TO BEING KNOCKED OUT ON PENALTIES? NOVEMBER 2015 ON 4 NOVEMBER 2015 THE RULE AGAINST PENALTIES IN COMMERCIAL CONTRACTS CAME UNDER THE SCRUTINY OF A SEVEN JUDGE PANEL OF THE SUPREME COURT.

More information

Website Disclaimer http://www.website-law.co.uk/ourdocumentlicence.html. Disclaimer 1

Website Disclaimer http://www.website-law.co.uk/ourdocumentlicence.html. Disclaimer 1 Website Disclaimer http://www.website-law.co.uk/ourdocumentlicence.html (1) Introduction Disclaimer 1 This disclaimer governs your use of our website; by using our website, you accept this disclaimer in

More information

STRUCTURING A BUSINESS AS A LIMITED LIABILITY PARTNERSHIP (LLP)

STRUCTURING A BUSINESS AS A LIMITED LIABILITY PARTNERSHIP (LLP) STRUCTURING A BUSINESS AS A LIMITED LIABILITY PARTNERSHIP (LLP) CORPORATE LAW INTRODUCTION Partnerships have been used for many years as flexible business vehicles for enterprises, especially where they

More information

GADSBY WICKS SOLICITORS EXPLANATION OF LEGAL TERMS

GADSBY WICKS SOLICITORS EXPLANATION OF LEGAL TERMS EXPLANATION OF LEGAL TERMS Affidavit: After the event litigation insurance: Application notice: Bar Council: Barrister: Basic Charges: Before the Event Legal Expenses Insurance: Bill of costs: Bolam test:

More information

Newsletter No. 194 (EN) Directors and Officers (D&O) Liability Insurance in Hong Kong

Newsletter No. 194 (EN) Directors and Officers (D&O) Liability Insurance in Hong Kong Newsletter No. 194 (EN) Directors and Officers (D&O) Liability Insurance in Hong Kong December 2015 All r ig ht s r e ser ved Lo r e nz & P art ner s 2015 Although Lorenz & Partners always pays great attention

More information

Claims Management Services Regulation. Conduct of Authorised Persons Rules 2013 (2)

Claims Management Services Regulation. Conduct of Authorised Persons Rules 2013 (2) Claims Management Services Regulation Conduct of Authorised Persons Rules 2013 (2) Effective from 8 July 2013 Contents Introduction 1 Definitions 1 General Rules Principles 2 Conduct of Business 2 Professional

More information

MODEL DIRECTIONS FOR CLINICAL NEGLIGENCE CASES (2012) - before Master Roberts and Master Cook

MODEL DIRECTIONS FOR CLINICAL NEGLIGENCE CASES (2012) - before Master Roberts and Master Cook MODEL DIRECTIONS FOR CLINICAL NEGLIGENCE CASES (2012) - before Master Roberts and Master Cook Introductory note. These are the Model Directions for use in the first Case Management Conference in clinical

More information

Management liability - Employment practices liability Policy wording

Management liability - Employment practices liability Policy wording Special definitions for this section Benefits Claim Defence costs The General terms and conditions and the following terms and conditions all apply to this section. Any compensation awarded to an employee

More information

NATIONAL INSURANCE BROKERS ASSOCIATION OF AUSTRALIA (NIBA) Submission to WorkCover Western Australia. Legislative Review 2013

NATIONAL INSURANCE BROKERS ASSOCIATION OF AUSTRALIA (NIBA) Submission to WorkCover Western Australia. Legislative Review 2013 NATIONAL INSURANCE BROKERS ASSOCIATION OF AUSTRALIA (NIBA) ABOUT NIBA Submission to WorkCover Western Australia Legislative Review 2013 February 2014 NIBA is the peak body of the insurance broking profession

More information

This document contains important details about the compensation scheme. Explanatory Statement

This document contains important details about the compensation scheme. Explanatory Statement This document contains important details about the compensation scheme Explanatory Statement This document contains further details about the compensation scheme mentioned in the letter enclosed with this

More information

Conditional Fee Agreement (CFA)

Conditional Fee Agreement (CFA) Conditional Fee Agreement (CFA) This agreement is a binding legal contract between you and your solicitor/s. Before you sign, please read everything carefully. This agreement must be read in conjunction

More information

Expert advice. Practical solutions. Personal service. 1

Expert advice. Practical solutions. Personal service. 1 Debt recovery talk In these uncertain economic times, it is very important that businesses make sure that their credit control is properly organised and enforced. Failure to do this will result in substantial

More information

BMT Tax Depreciation Pty Ltd - Terms of Engagement

BMT Tax Depreciation Pty Ltd - Terms of Engagement BMT Tax Depreciation Pty Ltd - Terms of Engagement 1.0 Definitions and Interpretation 1.1 In this document, unless the context indicates a contrary intention: Agreement means these Terms of Engagement

More information

INCOME MANAGEMENT POLICY

INCOME MANAGEMENT POLICY INCOME MANAGEMENT POLICY 1. Principles 2. Aims 3. Methods * Arrears Prevention * Debt Recovery * Rent Accounting 4. Statutory and Regulatory Requirements 5. Performance Monitoring 6. Review 7. Date of

More information

Pros and cons of common ADR processes

Pros and cons of common ADR processes Pros and cons of common ADR processes es/1692727_1 1 Pros and cons of common ADR processes We set out in this document a short discussion of the advantages and disadvantages of some of the most common

More information

MODEL CONTRACTS FOR SMALL FIRMS LEGAL GUIDANCE FOR DOING INTERNATIONAL BUSINESS

MODEL CONTRACTS FOR SMALL FIRMS LEGAL GUIDANCE FOR DOING INTERNATIONAL BUSINESS MODEL CONTRACTS FOR SMALL FIRMS LEGAL GUIDANCE FOR DOING INTERNATIONAL BUSINESS International Trade Centre, August 2010 Contents Foreword Acknowledgements Chapter 1 International Contractual Alliance ITC

More information

Litigation schemes and proof of debt schemes: Managing conflicts of interest

Litigation schemes and proof of debt schemes: Managing conflicts of interest REGULATORY GUIDE 248 Litigation schemes and proof of debt schemes: Managing conflicts of interest April 2013 About this guide This guide sets out our approach on how a person who provides a financial service

More information

MUSIC RESOURCES TERMS AND CONDITIONS FOR SCHOOLS ( Conditions )

MUSIC RESOURCES TERMS AND CONDITIONS FOR SCHOOLS ( Conditions ) MUSIC RESOURCES TERMS AND CONDITIONS FOR SCHOOLS ( Conditions ) Please ensure all relevant staff have read and understood these Conditions before signing. Please complete, sign and return the Music Resources

More information

CIVIL JUSTICE COUNCIL THE IMPACT OF THE JACKSON REFORMS ON COSTS AND CASE MANAGEMENT

CIVIL JUSTICE COUNCIL THE IMPACT OF THE JACKSON REFORMS ON COSTS AND CASE MANAGEMENT Introduction CIVIL JUSTICE COUNCIL THE IMPACT OF THE JACKSON REFORMS ON COSTS AND CASE MANAGEMENT Submission by the Motor Accident Solicitors Society (MASS) March 2014 1. This response is prepared on behalf

More information

Your Van Insurance Motor Legal Protection Policy Booklet

Your Van Insurance Motor Legal Protection Policy Booklet Your Van Insurance Motor Legal Protection Policy Booklet Contents Motor Legal Protection Insurance...3 Motor Legal Expenses...3 Helpline Services...3 Motor Legal Expenses Policy Summary...4 Cancellation

More information

PRACTICE DIRECTIONS IMMIGRATION AND ASYLUM CHAMBERS OF THE FIRST- TIER TRIBUNAL AND THE UPPER TRIBUNAL

PRACTICE DIRECTIONS IMMIGRATION AND ASYLUM CHAMBERS OF THE FIRST- TIER TRIBUNAL AND THE UPPER TRIBUNAL Tribunals b Judiciary PRACTICE DIRECTIONS IMMIGRATION AND ASYLUM CHAMBERS OF THE FIRST- TIER TRIBUNAL AND THE UPPER TRIBUNAL Contents PART 1 PRELIMINARY 1 Interpretation, etc. PART 2 PRACTICE DIRECTIONS

More information

Varying a contract of employment

Varying a contract of employment Varying a contract of employment Acas can help with your employment relations needs Every year Acas helps employers and employees from thousands of workplaces. That means we keep right up to date with

More information

QBE European Operations Professional practices update

QBE European Operations Professional practices update QBE European Operations Professional practices update Undertakings - a guide QBE Professional practices update - Undertakings - a guide/jan 2013 1 Undertakings - a guide Introduction Undertakings given

More information

LAW REFORM (CONTRIBUTORY NEGLIGENCE) AMENDMENT BILL 2001

LAW REFORM (CONTRIBUTORY NEGLIGENCE) AMENDMENT BILL 2001 1 LAW REFORM (CONTRIBUTORY NEGLIGENCE) AMENDMENT BILL 2001 EXPLANATORY NOTES GENERAL OUTLINE OBJECTIVES OF THE LEGISLATION The purpose of this Bill is to address the impact of the decision of the High

More information

THE IMPACT OF THE JACKSON REFORMS ON COSTS AND CASE MANAGEMENT

THE IMPACT OF THE JACKSON REFORMS ON COSTS AND CASE MANAGEMENT THE IMPACT OF THE JACKSON REFORMS ON COSTS AND CASE MANAGEMENT 1. It has now been almost one year since the introduction of the Jackson reforms. The impact of these reforms has been far reaching in certain

More information

Bar Council response to the Reducing Legal Costs in Clinical Negligence Claims pre-consultation paper

Bar Council response to the Reducing Legal Costs in Clinical Negligence Claims pre-consultation paper Bar Council response to the Reducing Legal Costs in Clinical Negligence Claims pre-consultation paper 1. This is the response of the General Council of the Bar of England and Wales (the Bar Council) to

More information

Expert evidence. A guide for expert witnesses and their clients (Second edition)

Expert evidence. A guide for expert witnesses and their clients (Second edition) Expert evidence A guide for expert witnesses and their clients (Second edition) Addendum, June 2009 1. Introduction 1.1 The second edition of this Guide was published in October 2003, in order to set out

More information

Enhanced court fees - briefing for MPs and Peers

Enhanced court fees - briefing for MPs and Peers Enhanced court fees - briefing for MPs and Peers For further information please contact: Iana Vidal (Public Affairs Adviser, the Law Society) T: 020 7316 5581, E: iana.vidal@lawsociety.org.uk Key Points

More information

Claims Management Services Regulation. Conduct of Authorised Persons Rules 2014

Claims Management Services Regulation. Conduct of Authorised Persons Rules 2014 Claims Management Services Regulation Conduct of Authorised Persons Rules 2014 Effective from 1 October 2014 Contents Introduction 1 Definitions 1 General Rules Principles 2 Conduct of Business 2 Professional

More information

ICE CLEAR EUROPE LIMITED. - and - COMPANY NAME

ICE CLEAR EUROPE LIMITED. - and - COMPANY NAME Dated 20 ICE CLEAR EUROPE LIMITED - and - COMPANY NAME SPONSOR AGREEMENT LNDOCS01/795343.7 TABLE OF CONTENTS Clause Page PURPOSE OF THE AGREEMENT... 3 1. INTERPRETATION... 3 2. OBLIGATIONS OF THE COMPANY...

More information

DENTISTRY, A SUITABLE CASE STUDY FOR ADR CONTENTS

DENTISTRY, A SUITABLE CASE STUDY FOR ADR CONTENTS By Gareth R Thomas & Corbett Haselgrove- Spurin CONTENTS Page Topic 1 Aims and Objects Introduction What is ADR? Mediation 2 Ground rules for mediation 3 Steps in a mediation Advantages of mediation Why

More information

Implementation of the Jackson Reforms. The key changes.

Implementation of the Jackson Reforms. The key changes. March 2013 Implementation of the Jackson Reforms. The key changes. Introduction On 1 April 2013, a large tranche of the reforms proposed by the 2010 review of civil litigation costs by Lord Justice Jackson

More information

CONSULTATION RESPONSE BY THOMPSONS SOLICITORS SCOTLAND

CONSULTATION RESPONSE BY THOMPSONS SOLICITORS SCOTLAND CONSULTATION RESPONSE BY THOMPSONS SOLICITORS SCOTLAND SCOTTISH GOVERNMENT CONSULTATION ON THE DRAFT ORDER IN COUNCIL FOR THE TRANSFER OF SPECIFIED FUNCTIONS OF THE EMPLOYMENT TRIBUNAL TO THE FIRST TIER

More information

A brief guide to professional negligence claims

A brief guide to professional negligence claims A brief guide to professional negligence claims Contents Introduction Do I have a claim? Important considerations Pre-action protocol procedure Court proceedings Contact information Introduction Claims

More information

Client Information. Terms & Conditions. www.nockolds.co.uk

Client Information. Terms & Conditions. www.nockolds.co.uk Client Information Terms & Conditions? www.nockolds.co.uk 1. Introduction As from 1 June 2012 all work we do for you is governed by these terms of business. Attached to these terms is a letter that contains

More information

briefing Guide to litigation funding

briefing Guide to litigation funding briefing Guide to litigation funding The potential cost of litigation can be a major deterrent to bringing or defending legal proceedings even where there is a good chance of succeeding. Cost can be the

More information

Insider. Damages-Based Agreements: potential or potential pitfall? Don McCue March 2013

Insider. Damages-Based Agreements: potential or potential pitfall? Don McCue March 2013 Our members review the latest legal developments in their specialist areas of law in an easy-to-read, digestible format. Damages-Based Agreements: potential or potential pitfall? Don McCue March 2013 As

More information

How To Amend The Civil Procedure Rules

How To Amend The Civil Procedure Rules EXPLANATORY MEMORANDUM TO THE CIVIL PROCEDURE (AMENDMENT No.8) RULES 2014 2014 No. 3299 (L. 36) 1. This explanatory memorandum has been prepared by the Ministry of Justice and is laid before Parliament

More information

MEDIATORS DECLARATION PEACEWISE MASTER POLICY

MEDIATORS DECLARATION PEACEWISE MASTER POLICY Marsh Pty Ltd ABN 86004651512 PO Box H176 AUSTRALIA SQUARE NSW 1215 PROFESSIONAL INDEMNITY INSURANCE MEDIATORS DECLARATION PEACEWISE MASTER POLICY Professional Indemnity Declaration for Mediators who have

More information

Conditional Fee Agreement: What You Need to Know

Conditional Fee Agreement: What You Need to Know Conditional Fee Agreement: What You Need to Know This document forms an important part of your agreement with us. Please read it carefully. Definitions of words used in this document and the accompanying

More information

STITT & C Ọ SOLICITORS 11 Gough Square, London EC4A 3DE Tel: 020 7832 0840 Fax: 020 7832 0865 email: info@stitt.co.uk

STITT & C Ọ SOLICITORS 11 Gough Square, London EC4A 3DE Tel: 020 7832 0840 Fax: 020 7832 0865 email: info@stitt.co.uk STITT & C Ọ SOLICITORS 11 Gough Square, London EC4A 3DE Tel: 020 7832 0840 Fax: 020 7832 0865 email: info@stitt.co.uk TERMS OF ENGAGEMENT 1. Service Commitment We aim to offer our clients quality legal

More information

The Enforceability of Mediated Settlement Agreements. By: Thomas J. Smith The Law Offices of Thomas J. Smith San Antonio, Texas

The Enforceability of Mediated Settlement Agreements. By: Thomas J. Smith The Law Offices of Thomas J. Smith San Antonio, Texas The Enforceability of Mediated Settlement Agreements By: Thomas J. Smith The Law Offices of Thomas J. Smith San Antonio, Texas NIGHTMARE ON MEDIATION STREET You mediate a case where the Plaintiff is suing

More information

Paper in response to the issues raised in the Panel on Administration of Justice and Legal Services meeting on 26 April 2004

Paper in response to the issues raised in the Panel on Administration of Justice and Legal Services meeting on 26 April 2004 LC Paper No. CB(2)2582/03-04(01) Paper in response to the issues raised in the Panel on Administration of Justice and Legal Services meeting on 26 April 2004 Review of Professional Indemnity Scheme of

More information

Preliminary Considerations. This chapter will enable you to achieve the following learning outcomes from the CILEx syllabus:

Preliminary Considerations. This chapter will enable you to achieve the following learning outcomes from the CILEx syllabus: Chapter 2: Preliminary Considerations Outline 2.1 Introduction 2.2 Limitation 2.3 Calculating limitation periods 2.4 Viability 2.5 Financing litigation 2.6 Summary Aims of this Chapter This chapter will

More information

Terms of business agreement - Commercial clients

Terms of business agreement - Commercial clients Terms of business agreement - Commercial clients Please read this document carefully. It sets out the terms on which Finch Insurance Brokers Ltd agree to act for clients and contains details of our responsibilities

More information

Am I in a Partnership?

Am I in a Partnership? magrath LLP Am I in a Partnership? Many people do not realise how easy it is to form a legal partnership and indeed, may be in a partnership without realising it! What is a partnership? It has become common

More information

Executive summary and overview of the national report for Denmark

Executive summary and overview of the national report for Denmark Executive summary and overview of the national report for Denmark Section I Summary of findings There is no special legislation concerning damages for breach of EC or national competition law in Denmark,

More information

The Foundation of the International Association of Defense Counsel SURVEY OF INTERNATIONAL LITIGATION PROCEDURES: A REFERENCE GUIDE

The Foundation of the International Association of Defense Counsel SURVEY OF INTERNATIONAL LITIGATION PROCEDURES: A REFERENCE GUIDE Responses submitted by: Name: Roddy Bourke Law Firm/Company: McCann FitzGerald Location: Dublin, Ireland 1. Would your jurisdiction be described as a common law or civil code jurisdiction? The Republic

More information

Before : Mr Justice Morgan - - - - - - - - - - - - - - - - - - - - - Between :

Before : Mr Justice Morgan - - - - - - - - - - - - - - - - - - - - - Between : Neutral Citation Number: [2014] EWHC 3848 (Ch) IN THE HIGH COURT OF JUSTICE CHANCERY DIVISION 1 Case No: HC12A02388 Royal Courts of Justice, Rolls Building Fetter Lane, London, EC4A 1NL Date: Tuesday,

More information

The New Standard Construction Contracts: NZS3910, 3916 and 3917

The New Standard Construction Contracts: NZS3910, 3916 and 3917 The New Standard Construction Contracts: NZS3910, 3916 and 3917 Brian Clayton, Partner FEBRUARY 2014 3258689.3 Chapman Tripp Introduction Standards New Zealand has recently completed the first review of

More information

Limitation of Liability

Limitation of Liability Limitation of Liability Submission to the Attorney-General (Western Australia) July 2000 The Institution of Engineers, Australia Institution of Engineers, Australia 11 National Circuit, Barton, ACT, 2604

More information

Client Contracts: Business Risk, Professional Liability & Insurance Coverage

Client Contracts: Business Risk, Professional Liability & Insurance Coverage Hanover Architects & Engineers Advantage Client Contracts: Business Risk, Professional Liability & Insurance Coverage Many client-drafted contracts endeavor to transfer unreasonable risk to the design

More information

ODT SOLICITORS LLP. Terms of Business. 1. ODT Solicitors LLP is a limited liability partnership incorporated in England.

ODT SOLICITORS LLP. Terms of Business. 1. ODT Solicitors LLP is a limited liability partnership incorporated in England. ODT SOLICITORS LLP Terms of Business ODT Solicitors LLP 1. ODT Solicitors LLP is a limited liability partnership incorporated in England. 2. It is ODT Solicitors LLP which accepts your instructions to

More information