1 Environmental Permit Considerations / Requirements for Natural Gas Pipeline Installation Gathering Lines Presented by: John J. Keeling, PE, QEP For WVU Extension Service Agriculture and Natural Resources Natural Gas Education Team Kingwood, WV Office

2 NOTE: Disclaimer I am NOT an attorney and this is not legal advice. Do not represent USEPA or WVDEP There slides are accurate to the best of my ability. However, if there are any concerns or questions, please contact John Keeling of MSES. While I believe that there are no discrepancies or perceived discrepancies between the information presented here, and the rules, regulations, or policies; MSES does not take responsibility for your use of this information. Review and determine requirements with your company consultant or attorney!

3 Types of Natural Gas Pipelines Gathering Well pads to sales point or processing facility Transportation From sales point/processing facility to storage or distribution center Distribution From transportation or gathering to commercial/residential end-user

4 Gathering Lines Supporting Shale Gas Production Typical Diameter 12 inch to 24 inch Construction Right-of-Way Width 12 inch 75 feet 24 inch 100 feet

5 Environmental Considerations 1. Wetlands Avoidance 2. Stream/River Crossings 3. Erosion Prevention 4. Sedimentation Control 5. Endangered Species Indiana Bat Freshwater Mussels Others

6 Environmental Considerations 6. Archeologically Sensitive Areas 7. Route that can be reasonable constructed and well maintained Slip prevention Adequate cover/protection 8. Access Roads Construction and/or maintenance

7 Special Installation Approaches for Environmentally Sensitive Areas 1. If possible, horizontal directionally drilling under large streams/rivers or wetlands 2. Reduction in disturbance width for sensitive areas 3. Work matts for equipment/soil placement 4. Robust erosion prevention/sedimentation control

8 Enforcement Agency Requirements U.S. Army Corp of Engineers Nationwide 12 permit for pipelines Nationwide 14 permit for access roads U.S. Fish and Wildlife/WV DNR Tree removal limitations/timing Sensitive/endangered species Additional studies may be required Clearance letters from agencies

9 WV DEP Enforcement Agency Requirements (continued) Stormwater Construction permits for areas of vegetation disturbance Includes pipeline route and access roads Note: this new permit will be required later in 2013 WV DNR Office of Land and Streams Stream crossing license 10 year license for both pipelines and access roads

10 Enforcement Agency Requirements (continued) WV State Historic Preservation Office Clearance letter from agency

11 Public Notice Requirements 1. Stormwater Construction Permit Application. 2. Signage at stream crossings and at road crossings. 3. If US Army Corps of Engineers permit is required.

12 Pipeline Route Fine Tuning Selection Process for Environmental Considerations 1. Once feasible route is selected, it is ground surveyed and survey crew will make minor changes for constructability 2. Environmental screen of route for wetlands and stream crossings 3. If environmental issues are identified, route changes are recommended 4. Once approach for environmental issues is selected, permits/licenses are applied for

13 Photo Examples of Construction

14 Photo Examples of Construction

15 Photo Examples of Construction

16 Photo Examples of Construction

17 Photo Examples of Construction

18 Photo Examples of Construction

19 Photo Examples of Construction

20 QUESTIONS

The Basics of Chapter 105 Waterways and Wetlands Permitting in PA

The Basics of Chapter 105 Waterways and Wetlands Permitting in PA The Basics of Chapter 105 Waterways and Wetlands Permitting in PA April 17, 2013 Goal To develop a basic understanding of PA Department of Environmental Protection (DEP) and US Army Corps of Engineers

More information

U.S. Fish & Wildlife Service West Virginia Ecological Services Field Office

U.S. Fish & Wildlife Service West Virginia Ecological Services Field Office Slide 1 West Virginia Ecological Services Field Office Liz Stout Fish and Wildlife Biologist 694 Beverly Pike Elkins, West Virginia 26241 elizabeth_stout@fws.gov 304-636-6586 x 15 Slide 2 Today s Goals

More information

For additional information on qualifications and experience of representative EDGE senior staff members, please contact us.

For additional information on qualifications and experience of representative EDGE senior staff members, please contact us. About Us Edge Engineering & Science, LLC (EDGE) is a privately owned professional services firm headquartered in Houston, Texas. EDGE was established with the primary goal of providing high quality environmental

More information

Natural Gas Pipelines

Natural Gas Pipelines Natural Gas Pipelines Excerpt from Report 2 of the Pennsylvania Energy Impacts Assessment December 16, 2011 Authors: Nels Johnson, Tamara Gagnolet, Rachel Ralls, and Jessica Stevens The Nature Conservancy

More information

Testimony on. Marcellus Shale Natural Gas Drilling and Philadelphia s Drinking water Supplies. Before the Environmental Resources and Energy Committee

Testimony on. Marcellus Shale Natural Gas Drilling and Philadelphia s Drinking water Supplies. Before the Environmental Resources and Energy Committee Testimony on Marcellus Shale Natural Gas Drilling and Philadelphia s Drinking water Supplies Before the Environmental Resources and Energy Committee Pennsylvania House of Representatives Howard M. Neukrug,

More information

Chapter 11 Outfall Systems

Chapter 11 Outfall Systems Chapter 11 Outfall Systems This section presents the methods, criteria and details for analysis and design of outfall systems. Properly designed outfalls are critical to reducing the chance of adverse

More information

Michigan Department of Natural Resources Oil and Gas Leases Frequently Asked Questions

Michigan Department of Natural Resources Oil and Gas Leases Frequently Asked Questions What is the DNR s authority for leasing oil and gas? How are state-owned oil and gas rights leased? Who decides which state-owned oil and gas rights will be offered for lease at the auction? How often

More information

ASWM State/Tribal/Federal Coordination Meeting March 24-26, 2015

ASWM State/Tribal/Federal Coordination Meeting March 24-26, 2015 Pennsylvania s 401 Certification Program for FERC for Pipeline Projects ASWM State/Tribal/Federal Coordination Meeting March 24-26, 2015 Ken Murin Pennsylvania Department of Environmental Protection Bureau

More information

Back Creek Watershed Protection Plan

Back Creek Watershed Protection Plan Back Creek Watershed Protection Plan Potomac Direct Drains Berkeley County, WV HUC code: 02070004 WV Stream code: WVP-6 West Virginia Conservation Agency February 15, 2011 Funding Amount 319 funds $30,000

More information

35CSR8 TITLE 35 LEGISLATIVE RULE DEPARTMENT OF ENVIRONMENTAL PROTECTION OIL AND GAS SERIES 8 RULES GOVERNING HORIZONTAL WELL DEVELOPMENT

35CSR8 TITLE 35 LEGISLATIVE RULE DEPARTMENT OF ENVIRONMENTAL PROTECTION OIL AND GAS SERIES 8 RULES GOVERNING HORIZONTAL WELL DEVELOPMENT TITLE 35 LEGISLATIVE RULE DEPARTMENT OF ENVIRONMENTAL PROTECTION OIL AND GAS SERIES 8 RULES GOVERNING HORIZONTAL WELL DEVELOPMENT 35-8-1. General 1.1 Scope. This rule shall govern and apply to permit application

More information

Comanche Trail Pipeline Project. September 2015

Comanche Trail Pipeline Project. September 2015 Comanche Trail Pipeline Project September 2015 2 Comanche Trail Pipeline Project The Comanche Trail Pipeline is a Texas intrastate pipeline (1) designed to transport 1.1 billion cubic feet per day of clean-burning

More information

Chapter 3 SENSITIVE AREAS AND VEGETATED CORRIDORS

Chapter 3 SENSITIVE AREAS AND VEGETATED CORRIDORS Chapter 3 3.01 General Provisions 3.01.1 Introduction 3.01.2 Application and Interpretation of Chapter 3.01.3 Unbuildable Lots 3.01.4 Other Permits 3.01.5 Prohibited Activities 3.02 Service Provider Letter

More information

Land Disturbance, Erosion Control and Stormwater Management Checklist. Walworth County Land Conservation Department

Land Disturbance, Erosion Control and Stormwater Management Checklist. Walworth County Land Conservation Department Land Disturbance, Erosion Control and Stormwater Management Checklist Walworth County Land Conservation Department The following checklist is designed to assist the applicant in complying with the Walworth

More information

CITY UTILITIES DESIGN STANDARDS MANUAL

CITY UTILITIES DESIGN STANDARDS MANUAL CITY UTILITIES DESIGN STANDARDS MANUAL Book 2 (SW) SW9 June 2015 SW9.01 Purpose This Chapter provides information for the design of open channels for the conveyance of stormwater in the City of Fort Wayne.

More information

Estabrook Dam A Discussion of Alternatives. Public Scoping Meeting June 5, 2014

Estabrook Dam A Discussion of Alternatives. Public Scoping Meeting June 5, 2014 Estabrook Dam A Discussion of Alternatives Public Scoping Meeting June 5, 2014 Presenters Kevin Haley, PLA, Milwaukee County Don Pirrung, P.E., PH, AECOM Mike Hahn, P.E., PH, Southeastern Wisconsin Regional

More information

Goal READING AND INTERPRETING SITE PLANS. Learn to identify key aspects of a sound and viable site plan. Learn what elements compose a site plan

Goal READING AND INTERPRETING SITE PLANS. Learn to identify key aspects of a sound and viable site plan. Learn what elements compose a site plan READING AND INTERPRETING SITE PLANS Goal Learn to identify key aspects of a sound and viable site plan Presented by: Glenn D. Cooley, PE E&M Engineers and Surveyors, PC PO Box 159 Springville, NY 14141-0159

More information

Celebrating over 50 years of service MEMORANDUM

Celebrating over 50 years of service MEMORANDUM Celebrating over 50 years of service MEMORANDUM TO: Town of Tyre Ronald F. McGreevy, Supervisor JN. 1650.001.001 FROM: Adam Cummings, P.E., BCEE DATE: 3 September 2015 SUBJECT: Project Proposal SEQRA Documentation

More information

OVERVIEW ABOUT WBI ENERGY

OVERVIEW ABOUT WBI ENERGY OVERVIEW The proposed Demicks Lake Pipeline Project involves approximately 22 miles of 24-inch diameter natural gas pipeline between a natural gas processing plant proposed by ONEOK Rockies Midstream (ONEOK)

More information

Door County. Zoning. Does the ordinance include shoreland-wetland district requirements that exceed State minimum standards? Yes. See responses below.

Door County. Zoning. Does the ordinance include shoreland-wetland district requirements that exceed State minimum standards? Yes. See responses below. Door County Zoning Introduction Door County has a comprehensive Zoning Ordinance that contains wetland conservation provisions. Shoreland-Wetland zoning provisions are enforced in all unincorporated areas

More information

Frequently Asked Transmission Pipeline Questions

Frequently Asked Transmission Pipeline Questions Frequently Asked Transmission Pipeline Questions Who is PennEast, LLC? PennEast was formed by the partnership of AGL Resources, NJR Pipeline Company, South Jersey Industries and UGI Energy Services (UGIES).

More information

GROWER ADVISORY Agriculture Regulations of the Wetlands Protection Act

GROWER ADVISORY Agriculture Regulations of the Wetlands Protection Act Cape Cod Cranberry Growers Association GROWER ADVISORY Agriculture Regulations of the Wetlands Protection Act Cranberry Bogs and the Agricultural Exemption The Massachusetts Wetlands Protection Act (WPA)

More information

Miquon Creek STREAM RESTORATION PROJECT WHO WE ARE

Miquon Creek STREAM RESTORATION PROJECT WHO WE ARE Miquon Creek STREAM RESTORATION PROJECT WHO WE ARE Introductions Brett Long, PE Project Permitting & Construction Oversight Chris Streb, PE Project Designer & Construction Oversight Assistance WHO WE ARE

More information

sdci Seattle Permits Tip Tree Protection Regulations in Seattle CATEGORIES OF TREES AFFECTED IDENTIFYING TREE TYPES ON YOUR PROPERTY

sdci Seattle Permits Tip Tree Protection Regulations in Seattle CATEGORIES OF TREES AFFECTED IDENTIFYING TREE TYPES ON YOUR PROPERTY sdci Seattle Department of Construction and Inspections Tip 242 Seattle Permits part of a multi-departmental City of Seattle series on getting a permit Updated May 12, 2011 Tree Protection Regulations

More information

REFERENCE. All National Grid personnel who plan and perform work involving protected water resources are responsible for:

REFERENCE. All National Grid personnel who plan and perform work involving protected water resources are responsible for: EG-30NY ENVIRONMENTAL GUIDANCE PAGE 1 of 9 DATE 10/1/10 EP 3 Natural Resource Protection 1.0 SCOPE AND RESPONSIBILITIES National Grid s New York service territory encompasses thousands of wetlands, lakes,

More information

United States Department of the Interior

United States Department of the Interior United States Department of the Interior Ms. Valerie Clarkston Environmental Solutions & Innovations, Inc. 4525 Este Avenue Cincinnati, OH 45232 FISH AND WILDLIFE SERVICE Virginia Field Office 6669 Short

More information

Landscaping Regulations

Landscaping Regulations 1003.162 Landscaping Regulations 1. Scope of Provisions. This section contains the landscaping regulations that apply to all zoning districts. Developments subject to the conditional use permit procedure

More information

The answers to some of the following questions are separated into two major categories:

The answers to some of the following questions are separated into two major categories: Following the recent flooding events for Front Range communities in Colorado, property owners, communities, and the National Flood Insurance Program are being presented with some new challenges in the

More information

Natural Gas Summit 11/14/12

Natural Gas Summit 11/14/12 Natural Gas Summit 11/14/12 1 Natural Gas Summit 11/14/12 Maureen Ball Joined Central New York Oil and Gas (Inergy) in 1999. Participated in the development and construction of various storage, compression,

More information

Plan Groundwater Procurement, Implementation and Costs, prepared for the Brazos River Authority, July 2005.

Plan Groundwater Procurement, Implementation and Costs, prepared for the Brazos River Authority, July 2005. 6 Conjunctive Use 6.1 Lake Granger Augmentation 6.1.1 Description of Option Rapid population growth and development in Williamson County require additional water supplies throughout the planning period.

More information

COMMUNITY CERTIFICATIONS

COMMUNITY CERTIFICATIONS National Flood Insurance Program Community Rating System COMMUNITY CERTIFICATIONS Public reporting burden for this form is estimated to average 4 hours for annual recertification, per response. The burden

More information

Stream Crossings. The GP s. During this presentation, we will cover: 2012 Industry Training Workshops

Stream Crossings. The GP s. During this presentation, we will cover: 2012 Industry Training Workshops 2012 Industry Training Workshops Jim Kline Environmental Group Manager Bureau of Regulatory and Resources Enhancement Office of Oil and Gas Management Stream Crossings During this presentation, we will

More information

Negotiating Pipeline Easements

Negotiating Pipeline Easements FACT SHEET Ohio State University Extension, 2120 Fyffe Road, Columbus, OH 43210 Introduction Shale Oil and Gas Development Fact Sheet Series Negotiating Pipeline Easements Peggy Kirk Hall Director, OSU

More information

WATER QUALITY CERTIFICATE. Installation of 24-inch diameter natural gas pipeline, 8.26 miles

WATER QUALITY CERTIFICATE. Installation of 24-inch diameter natural gas pipeline, 8.26 miles 79 Elm Street Hartford, CT 06106-5127 www.ct.gov/deep Affirmative Action/Equal Opportunity Employer WATER QUALITY CERTIFICATE Permittee: Attn: Tennessee Gas Pipeline Company LLC 1001 Louisiana Street Houston

More information

Environmental Impacts of Marcellus Natural Gas Drilling in the Chesapeake Bay Watershed

Environmental Impacts of Marcellus Natural Gas Drilling in the Chesapeake Bay Watershed Environmental Impacts of Marcellus Natural Gas Drilling in the Chesapeake Bay Watershed Comments of Harry Campbell Pennsylvania Senior Scientist, Chesapeake Bay Foundation to the House Majority Policy

More information

EROSION & SEDIMENT CONTROL (E&S) PLAN For projects disturbing less than one (1) acre

EROSION & SEDIMENT CONTROL (E&S) PLAN For projects disturbing less than one (1) acre Revised September 2014 EROSION & SEDIMENT CONTROL (E&S) PLAN For projects disturbing less than one (1) acre According to state regulations, any earth disturbance activity totaling 5,000 square feet or

More information

E&SC Training & Certification

E&SC Training & Certification E&SC Training & Certification 5 Chapter E&SC training involves educating, training and certifying individuals involved with managing stormwater, erosion and sediment on NCDOT construction projects. The

More information

Sample Questions to Ask of Pipeline Companies Proposal New or Expanding Pipeline Projects for Your Community

Sample Questions to Ask of Pipeline Companies Proposal New or Expanding Pipeline Projects for Your Community Sample Questions to Ask of Pipeline Companies Proposal New or Expanding Pipeline Projects for Your Community We understand that in the FERC process, landowners have the right to await the outcome of the

More information

PIPELINE ROUTING PERMIT. For A NATURAL GAS PIPELINE DAKOTA AND RAMSEY COUNTIES ISSUED TO NORTHERN STATES POWER COMPANY D/B/A XCEL ENERGY

PIPELINE ROUTING PERMIT. For A NATURAL GAS PIPELINE DAKOTA AND RAMSEY COUNTIES ISSUED TO NORTHERN STATES POWER COMPANY D/B/A XCEL ENERGY PIPELINE ROUTING PERMIT For A NATURAL GAS PIPELINE IN DAKOTA AND RAMSEY COUNTIES ISSUED TO NORTHERN STATES POWER COMPANY D/B/A XCEL ENERGY PUC DOCKET No. G002/GP-05-1706 In accordance with the requirements

More information

DRAFT Non-Surface Disturbance Leasing and Review Criteria DCNR State Park and Forest Lands

DRAFT Non-Surface Disturbance Leasing and Review Criteria DCNR State Park and Forest Lands DRAFT Non-Surface Disturbance Leasing and Review Criteria DCNR State Park and Forest Lands July 2014 The Department of Conservation and Natural Resources (DCNR) manages approximately 2.5 million acres

More information

CONSTRUCTION STORMWATER POLLUTION PREVENTION PLAN TEMPLATE

CONSTRUCTION STORMWATER POLLUTION PREVENTION PLAN TEMPLATE CONSTRUCTION STORMWATER POLLUTION PREVENTION PLAN TEMPLATE The following template may be used as a general guide for development of a Stormwater Pollution Prevention Plan (SWPPP) for construction activities.

More information

Mission Creek Flood Control & Restoration Project. City of Fremont, Alameda County

Mission Creek Flood Control & Restoration Project. City of Fremont, Alameda County Mission Creek Flood Control & Restoration Project City of Fremont, Alameda County Agenda Background Why are proposed improvements necessary? Proposed project components Challenges Construction schedule/phasing

More information

PLANNED UNIT DEVELOPMENT & SIDEWALK WAIVER REQUEST STAFF REPORT Date: November 7, 2013

PLANNED UNIT DEVELOPMENT & SIDEWALK WAIVER REQUEST STAFF REPORT Date: November 7, 2013 PLANNED UNIT DEVELOPMENT & SIDEWALK WAIVER REQUEST STAFF REPORT Date: November 7, 2013 NAME LOCATION Audubon Properties, LLC. 4700 & 4960 Dauphin Island Parkway West side of Dauphin Island Parkway, 580

More information

30-DAY PUBLIC NOTICE CHELSEA RIVER, EAST BOSTON MASSACHUSETTS EMERGENCY STREAMBANK PROTECTION PROJECT

30-DAY PUBLIC NOTICE CHELSEA RIVER, EAST BOSTON MASSACHUSETTS EMERGENCY STREAMBANK PROTECTION PROJECT PUBLIC NOTICE Engineering/Planning 696 Virginia Road Concord, MA 01742 Date: 10 November, 2015 Comment Period Ends: 10 December, 2015 In Reply, Refer To: Robert Russo Or by e-mail: Robert.S.Russo@usace.army.mil

More information

Liquid Capital. Cochran s Creek: A Case Study in Stream Mitigation Banking in Georgia

Liquid Capital. Cochran s Creek: A Case Study in Stream Mitigation Banking in Georgia Liquid Capital Cochran s Creek: A Case Study in Stream Mitigation Banking in Georgia Basic Bank Permitting Process Submit Prospectus to IRT. If approved then: Conduct site visit with IRT. If approved then:

More information

JOINT PUBLIC NOTICE June 28, 2016

JOINT PUBLIC NOTICE June 28, 2016 DEPARTMENT OF THE ARMY NEW ORLEANS DISTRICT CORPS OF ENGINEERS REGULATORY FUNCTIONS BRANCH P.O. BOX 60267 NEW ORLEANS, LA 70160 JOINT PUBLIC NOTICE June 28, 2016 STATE OF LOUISIANA DEPARTMENT OF ENVIRONMENTAL

More information

Backyard Buffers. Protecting Habitat and Water Quality

Backyard Buffers. Protecting Habitat and Water Quality Backyard Buffers Protecting Habitat and Water Quality What is a buffer? A buffer (also called a riparian buffer area or zone) is the strip of natural vegetation along the bank of a stream, lake or other

More information

Frequently Asked Questions About PennEast Pipeline Project

Frequently Asked Questions About PennEast Pipeline Project Frequently Asked Questions About PennEast Pipeline Project Who is PennEast Pipeline Company, LLC? AGL Resources, NJR Pipeline Company, South Jersey Industries, PSEG Power LLC and UGI Energy Services (UGIES)

More information

STORMWATER POLLUTION PREVENTION PLAN TEMPLATE. 1.0 SITE DESCRIPTION 1.1 Project Name and Location Date

STORMWATER POLLUTION PREVENTION PLAN TEMPLATE. 1.0 SITE DESCRIPTION 1.1 Project Name and Location Date STORMWATER POLLUTION PREVENTION PLAN TEMPLATE Disclaimer: This template was developed for guidance purposes only in an effort to assist Construction Storm Water permit applicants in meeting state and local

More information

FAIRFAX WATER OCCOQUAN RESERVOIR SHORELINE EASEMENT POLICY. February 17, 2011

FAIRFAX WATER OCCOQUAN RESERVOIR SHORELINE EASEMENT POLICY. February 17, 2011 FAIRFAX WATER OCCOQUAN RESERVOIR SHORELINE EASEMENT POLICY February 17, 2011 I. Purpose The Occoquan Reservoir (the "Reservoir"), located in Fairfax and Prince William Counties, Virginia, was constructed

More information

GAO PIPELINE PERMITTING. Interstate and Intrastate Natural Gas Permitting Processes Include Multiple Steps, and Time Frames Vary

GAO PIPELINE PERMITTING. Interstate and Intrastate Natural Gas Permitting Processes Include Multiple Steps, and Time Frames Vary GAO United States Government Accountability Office Report to Congressional Committees February 2013 PIPELINE PERMITTING Interstate and Intrastate Natural Gas Permitting Processes Include Multiple Steps,

More information

Remaining Wetland Acreage 1,500,000 915,960 584,040-39%

Remaining Wetland Acreage 1,500,000 915,960 584,040-39% NEW JERSEY Original Wetland Acreage Remaining Wetland Acreage Acreage Lost % Lost 1,500,000 915,960 584,040-39% New Jersey Wetlands: Nearly 99 percent of New Jersey s wetlands are palustrine or estuarine.

More information

ODOT/ACEC Partnering Conference 2015

ODOT/ACEC Partnering Conference 2015 ODOT/ACEC Partnering Conference 2015 Recent Environmental Developments New Endangered Species Listings and requirements These ESA requirements overlap with Section 404 Permit requirements Geotechnical

More information

Proposed Pipeline to Serve the Community of Fenelon Falls

Proposed Pipeline to Serve the Community of Fenelon Falls Welcome Thank you for coming! The purpose of today s meeting is to provide area residents with an opportunity to find out more about the potential expansion of the proposed natural gas distribution system,

More information

1.7.0 Floodplain Modification Criteria

1.7.0 Floodplain Modification Criteria 1.7.0 Floodplain Modification Criteria 1.7.1 Introduction These guidelines set out standards for evaluating and processing proposed modifications of the 100- year floodplain with the following objectives:

More information

Phases of Wind Energy Project Development

Phases of Wind Energy Project Development Produced in Consultation with Verterra Group Phases of Wind Energy Project Development How long between project planning and generating electricity? It usually takes three to four years from initial project

More information

The West Virginia Stream and Wetland Valuation Metric

The West Virginia Stream and Wetland Valuation Metric The West Virginia Stream and Wetland Valuation Metric Background As indicated in the U.S. Army Corps of Engineer s (USACE) regulations [33 CFR 332.8(b)], the district engineer will establish an Interagency

More information

5901 Milwaukee Street Planned Unit Development (GDP) (Second Addition to Grandview Commons)

5901 Milwaukee Street Planned Unit Development (GDP) (Second Addition to Grandview Commons) DATE: March 8, 2006 TO: FROM: SUBJECT: Plan Commission Larry D. Nelson, P.E., City Engineer 5901 Milwaukee Street Planned Unit Development (GDP) (Second Addition to Grandview Commons) The City Engineering

More information

Chapter 8. List of Preparers

Chapter 8. List of Preparers Chapter 8 List of Preparers This page intentionally left blank. 8 List of Preparers Name and DEIS Responsibility and Qualifications United States Fish and Wildlife Service Megan Seymour Wildlife Biologist,

More information

OSU Extension FACT SHEET

OSU Extension FACT SHEET OHIO STATE UNIVERSITY EXTENSION! OSU Extension FACT SHEET Ohio State University Extension, 2120 Fyffe Road, Columbus, OH 43210 Shale Oil and Gas Development Fact Sheet Series A Landowner s Guide to Understanding

More information

Article 44-5: Resource Management Provisions

Article 44-5: Resource Management Provisions Article 44-5: Sections: 44-5.10: 44-5.20: 44-5.30: 44-5.40: Agricultural Buffers Wetlands, Waterways, Riparian Habitat, and Sensitive Habitat Habitat Mitigation Banks and Habitat Management Areas Hillside

More information

MASSACHUSETTS COASTAL NONPOINT PROGRAM NOAA/EPA DECISIONS ON CONDITIONS OF APPROVAL

MASSACHUSETTS COASTAL NONPOINT PROGRAM NOAA/EPA DECISIONS ON CONDITIONS OF APPROVAL MASSACHUSETTS COASTAL NONPOINT PROGRAM NOAA/EPA DECISIONS ON CONDITIONS OF APPROVAL FOREWORD This document contains the basis for NOAA and EPA s decision to fully approve Massachusetts Coastal Nonpoint

More information

APPLICATION FOR OIL AND GAS WELL DRILLING AND OPERATIONS

APPLICATION FOR OIL AND GAS WELL DRILLING AND OPERATIONS APPLICATION FOR OIL AND GAS WELL DRILLING AND OPERATIONS Oil Well Permit Gas Well Permit Combined Well Permit Before completing application, please review attached instruction sheet APPLICANT / OPERATOR

More information

TENNESSEE GAS PIPELINE COMPANY 300 LINE PROJECT Vernon, West Milford Townships and Ringwood Borough, New Jersey

TENNESSEE GAS PIPELINE COMPANY 300 LINE PROJECT Vernon, West Milford Townships and Ringwood Borough, New Jersey Prepared for: Houston, TX COMPREHENSIVE MITIGATION PLAN HIGHLANDS REGION TENNESSEE GAS PIPELINE COMPANY 300 LINE PROJECT Vernon, West Milford Townships and Ringwood Borough, New Jersey AECOM, Inc. September

More information

Carlton Fields Memorandum

Carlton Fields Memorandum Carlton Fields Memorandum TO: FROM: RE: DAN WEEDE FRED RUSHING RIPARIAN BUFFER DATE: JULY 26, 2013 BACKGROUND Both the state of Georgia and the city of Atlanta 1 have certain guidelines that must be followed

More information

Single-Family Permit Handbook. City of Bellevue. Welcome! When is a permit required? Development Services Handout P-1

Single-Family Permit Handbook. City of Bellevue. Welcome! When is a permit required? Development Services Handout P-1 City of Bellevue Development Services Handout P-1 Single-Family Permit Handbook July 2006 Welcome! For the single-family homeowner, going to City Hall for a permit can be a bit intimidating. The City of

More information

TREE PROTECTION ORDINANCE CITY OF BUFORD, GEORGIA

TREE PROTECTION ORDINANCE CITY OF BUFORD, GEORGIA TREE PROTECTION ORDINANCE CITY OF BUFORD, GEORGIA This Ordinance shall apply to all properties or portions thereof located within the incorporated areas of the City of Buford, Georgia, to the extent of

More information

Using Aerial Photography to Measure Habitat Changes. Method

Using Aerial Photography to Measure Habitat Changes. Method Then and Now Using Aerial Photography to Measure Habitat Changes Method Subject Areas: environmental education, science, social studies Conceptual Framework Topic References: HIIIB, HIIIB1, HIIIB2, HIIIB3,

More information

Potholing Practice. 1. Objective The purpose of this practice is to describe potholing methods and recommend procedures for potholing.

Potholing Practice. 1. Objective The purpose of this practice is to describe potholing methods and recommend procedures for potholing. Potholing Practice 1. Objective The purpose of this practice is to describe potholing methods and recommend procedures for potholing. 2. Requirements Potholing is accomplished through various types of

More information

Prepared By: Eric Chamberlain

Prepared By: Eric Chamberlain Prepared By: Eric Chamberlain Drainage 101 So, What s a Municipal Drain??? It is a Drainage System either open ditch or enclosed pipe system or any other water control structure Petitioned for by landowners

More information

Project Purpose. Environmental Assessment

Project Purpose. Environmental Assessment Page 2, 3/30/2009 NYCDEP in partnership with local watershed community officials, stakeholders and regulatory agencies proposes to develop and implement through a collaborative process an expanded boating

More information

GAS WELL DRILLING AND YOUR PRIVATE WATER SUPPLY

GAS WELL DRILLING AND YOUR PRIVATE WATER SUPPLY GAS WELL DRILLING AND YOUR PRIVATE WATER SUPPLY About Cooperative Extension Providing factual information and education from unbiased research Private Water System Basics Wells Springs Cisterns Wells and

More information

Environmental Issues Associated with Oil and Natural Gas Extraction in the Marcellus and Utica Shale Region of Ohio Joe Bonnell, Program Director

Environmental Issues Associated with Oil and Natural Gas Extraction in the Marcellus and Utica Shale Region of Ohio Joe Bonnell, Program Director Environmental Issues Associated with Oil and Natural Gas Extraction in the Marcellus and Utica Shale Region of Ohio Joe Bonnell, Program Director School of Environment and Natural Resources Unconventional

More information

Citizen s Guide to the Permitting and Approval Process for Land Development in Pennsylvania

Citizen s Guide to the Permitting and Approval Process for Land Development in Pennsylvania Citizen s Guide to the Permitting and Approval Process for Land Development in Pennsylvania Prepared by: Matthew B. Royer, Staff Attorney Citizens for Pennsylvania s Future 610 N. Third Street, Harrisburg

More information

MIDSTREAM DEVELOPMENT IN PENNSYLVANIA

MIDSTREAM DEVELOPMENT IN PENNSYLVANIA MIDSTREAM DEVELOPMENT IN PENNSYLVANIA Midstream infrastructure consists of pipelines, processing facilities, compressor stations, and related infrastructure for transporting natural gas from well sites

More information

SECTION EROSION AND SEDIMENTATION CONTROL

SECTION EROSION AND SEDIMENTATION CONTROL SECTION 31 25 00 EROSION AND SEDIMENTATION CONTROL PART 1 GENERAL 1.01 SECTION INCLUDES A. This WORK shall consist of temporary measures needed to control erosion and water pollution. These temporary measures

More information

Living on the Fox River

Living on the Fox River This information could save you money! Living on the Fox River A Riverfront Property Owners Guide This brochure was developed by Fox River Ecosystem Partnership in cooperation with the Kane-DuPage Soil

More information

MARCELLUS SHALE NATURAL GAS DEVELOPMENT IN THE SHENANDOAH VALLEY. OPPORTUNITIES & ISSUES October 28, 2010

MARCELLUS SHALE NATURAL GAS DEVELOPMENT IN THE SHENANDOAH VALLEY. OPPORTUNITIES & ISSUES October 28, 2010 MARCELLUS SHALE NATURAL GAS DEVELOPMENT IN THE SHENANDOAH VALLEY OPPORTUNITIES & ISSUES October 28, 2010 Department of Mines, Minerals and Energy Division of Gas and Oil Virginia s Natural Gas Regulatory

More information

Tree Protection Regulations in Seattle

Tree Protection Regulations in Seattle City of Seattle Department of Design, Construction and Land Use CLIENT ASSISTANCE MEMO 242 February 2002 Tree Protection Regulations in Seattle Trees are valued in Seattle and are legally protected in

More information

DEPARTMENT OF ENVIRONMENTAL QUALITY

DEPARTMENT OF ENVIRONMENTAL QUALITY PROJECT IDENTIFICATION DEPARTMENT OF ENVIRONMENTAL QUALITY City of Burton Sanitary Sewer Collection System Improvements State Revolving Fund (SRF) Environmental Assessment April 2015 Applicant: Authorized

More information

Restoring Anadromous Fish Habitat in Big Canyon Creek Watershed. Summary Report 2002

Restoring Anadromous Fish Habitat in Big Canyon Creek Watershed. Summary Report 2002 Restoring Anadromous Fish Habitat in Big Canyon Creek Watershed Summary Report 2002 DOE/BP-00005268-5 November 2002 This Document should be cited as follows: "Restoring Anadromous Fish Habitat in Big Canyon

More information

APPLICATION FOR OIL AND GAS WELL DRILLING AND OPERATIONS

APPLICATION FOR OIL AND GAS WELL DRILLING AND OPERATIONS APPLICATION FOR OIL AND GAS WELL DRILLING AND OPERATIONS Gas Well Permit Combined Well Permit Pad Site Permit Before completing application, please review attached instruction sheet APPLICANT / OPERATOR

More information

Virginia Department of Transportation Rural Rustic Road Program Manual

Virginia Department of Transportation Rural Rustic Road Program Manual Virginia Department of Transportation Rural Rustic Road Program Manual Prepared by Local Assistance Division Virginia Department of Transportation 1401 East Broad Street Richmond, Virginia 23219 Jennifer

More information

Application For Lot Line Revision

Application For Lot Line Revision CITY OF MERCER ISLAND, DEVELOPMENT SERVICES GROUP 9611 S.E. 36 ST., MERCER ISLAND, WA 98040 (206) 236-5300 FAX: (206) 236-3599 Application For Lot Line Revision A Lot Line Revision is an adjustment of

More information

Stream Crossings and Corps Permits

Stream Crossings and Corps Permits Stream-Smart Road Crossing Workshops January 26; February 16 & 24; and March 23, 2012 Stream Crossings and Corps Permits U.S. Army Corps of Engineers New England District Jay Clement PRESENTATION OBJECTIVE

More information

The checklist utilized by the Authority will be similar to that which is shown below. Project Name: Location: Consulting Engineering Firm:

The checklist utilized by the Authority will be similar to that which is shown below. Project Name: Location: Consulting Engineering Firm: Page 1 of 6 Section 1. PURPOSE This policy is an Engineering checklist of the Local Review Program for sanitary sewer improvement projects by the Bedford Regional Water Authority ( Authority ). Section

More information

TENNESSEE GAS PIPELINE COMPANY, L.L.C.

TENNESSEE GAS PIPELINE COMPANY, L.L.C. TENNESSEE GAS PIPELINE COMPANY, L.L.C. SILT FENCE DESIGN CRITERIA AND METHODOLOGY FOR THE ACCESS ROADWAYS CONNECTICUT PIPELINE EXPANSION PROJECT CONNECTICUT LOOP Submitted by: Tennessee Gas Pipeline Company,

More information

Northern Middlesex Council of Governments

Northern Middlesex Council of Governments Northern Middlesex Council of Governments The Federal Energy Commission (FERC) is the agency charged with evaluating whether the proposed route should be approved Cooperating agencies generally include

More information

SPA Annual Report for 2002 September, 2003 Montgomery County Department of Environmental Protection Page 125. Evaluation and Recommendations

SPA Annual Report for 2002 September, 2003 Montgomery County Department of Environmental Protection Page 125. Evaluation and Recommendations Montgomery County Department of Environmental Protection Page 125 Evaluation and Recommendations Monitoring efforts in the Special Protection Areas continue to provide the kind of information needed to

More information

March 11, Re: Additional Comments on Dakota Access Pipeline Draft Environmental Assessment

March 11, Re: Additional Comments on Dakota Access Pipeline Draft Environmental Assessment UNITED STATES ENVIRONMENTAL PROTECTION AGENCY REGION 8 1595 Wynkoop Street Denver, CO 80202-1129 Phone 800-227-8917 www.epa.gov/region08 March 11, 2016 Ref: 8EPR-N U.S. Army Corps of Engineers, Omaha District

More information

STATEMENT OF ACKNOWLEDGMENT

STATEMENT OF ACKNOWLEDGMENT General Permit for the Discharge of Stormwater and Dewatering Wastewaters from Construction Activities, issued 8/21/13, effective 10/1/13 Stormwater Monitoring Report SITE INFORMATION Permittee: BNE Energy

More information

City of Shelbyville Site Inspection Checklist

City of Shelbyville Site Inspection Checklist City of Shelbyville Site Inspection Checklist General Information Project Name: KYR10 Permit Number: Date: Project Location: Contractor: Conractor Representative: Inspector's Name: Title: Signature : Weather

More information

#613 Planning Basics Chapter 4: Component 1 Planning Module

#613 Planning Basics Chapter 4: Component 1 Planning Module CHAPTER OBJECTIVES After completing this chapter, you will be able to... Explain how the Component 1 affects a municipality s offi cial plan. List the criteria that must be met to use a Component 1 planning

More information

Installing Your Bat House - Wooden Post or Steel Pole Installation-

Installing Your Bat House - Wooden Post or Steel Pole Installation- Installing Your Bat House - Wooden Post or Steel Pole Installation- Choose a sunny location to install your bat house pole. Bat houses work best with at least 6-8 hours of direct sunlight (if only partial

More information

NRCS EQIP Technical and Financial Support for Organic Farmers

NRCS EQIP Technical and Financial Support for Organic Farmers NRCS EQIP Technical and Financial Support for Organic Farmers Sarah Brown, Organic Conservation Specialist, March 29, 2012 http://www.extension.org/organic_production Sarah Brown, Organic Conservation

More information

MONTGOMERY COUNTY DEPARTMENT OF PARKS

MONTGOMERY COUNTY DEPARTMENT OF PARKS MATTHEW HENSON TRAIL MONTGOMERY COUNTY DEPARTMENT OF PARKS The Maryland-National Capital Park and Planning Commission NRPA 2011 Award Submission - March 2011 The Matthew Henson Trail is a 4.2-mile regional

More information

Rhode Island NRCS received approximately $2.4 million in ARRA funds to implement four floodplain easement projects.

Rhode Island NRCS received approximately $2.4 million in ARRA funds to implement four floodplain easement projects. American Recovery and Reinvestment Act (ARRA) Emergency Watershed Protection Program Floodplain Easements Rhode Island Natural Resources Conservation Service Rhode Island NRCS received approximately $2.4

More information

AGENCY COORDINATION AND PUBLIC INVOLVEMENT

AGENCY COORDINATION AND PUBLIC INVOLVEMENT 5 AGENCY COORDINATION AND PUBLIC INVOLVEMENT 5.1 AGENCY COORDINATION As part of the planning process for the Oregon Avenue Final EA, DDOT conducted an agency coordination program. This coordination included

More information

DRAFT. USDA NRCS Conservation Practices that Maintain or Enhance Agriculture Viability and Critical Areas

DRAFT. USDA NRCS Conservation Practices that Maintain or Enhance Agriculture Viability and Critical Areas USDA NRCS Conservation Practices that Maintain or Enhance Agriculture Viability and Critical Areas Wetlands Areas that are inundated or saturated by surface water or groundwater supporting a prevalence

More information

Guidance for Temporary Housing Associated with Oil and Natural Gas Drilling Operations

Guidance for Temporary Housing Associated with Oil and Natural Gas Drilling Operations Guidance for Temporary Housing Associated with Oil and Natural Gas Drilling Operations May 2012 Table of Contents Introduction... 1 Employee Housing... 1 Manufactured Home Parks... 1 Combined Park Camps...

More information

GUIDELINES FOR PARALLEL CONSTRUCTION OF PIPELINES

GUIDELINES FOR PARALLEL CONSTRUCTION OF PIPELINES GUIDELINES FOR PARALLEL CONSTRUCTION OF PIPELINES Technical support to The INGAA Foundation, Inc. by: Process Performance Improvement Consultants 1200 Post Oak Road, Suite 2705 Houston, TX 77056 USA F-2008-05

More information