February 26, 2016 REQUEST FOR PROPOSAL FOR MODULAR EXPANSION PROJECT ATLANTA CLASSICAL ACADEMY FULTON COUNTY, GEORGIA
|
|
- Julian Tucker
- 7 years ago
- Views:
Transcription
1 February 26, 2016 REQUEST FOR PROPOSAL FOR MODULAR EXPANSION PROJECT ATLANTA CLASSICAL ACADEMY FULTON COUNTY, GEORGIA Atlanta Classical Academy (ACA) is soliciting proposals from interested firms to aid in the site work, emplacement, construction, and completion of an 8-classroom modular and covered pavilion project. All work related to this project must be complete by July 18, I. Project Description and Details ACA is installing an 8-classroom modular building and connected covered pavilion in order to accommodate school expansion. The modular building and pavilion will be located at the southern end of the school property located at 3260 Northside Drive NW, Atlanta, GA The scope of work for this RFP is generally spread across three main areas: (1) all site preparation, site work (to include preparing the pad for the modular building), and final site finishing, (2) preparing and connecting all utilities to the modular building in order to make it operational, and (3) construction of and finish work related to the attached pavilion. For specific project design details, please refer to the construction documents provided by Breedlove Land Planning, TSW and Mobile Modular. Mobile Modular will be responsible for delivering, emplacing and completing all work related to the modular building (except as annotated below). For general questions regarding this project and the request for proposal, please contact Mr. Stephen Lambert at: Cellular: Proposals should include the following components (as required and applicable): a. General conditions (labor and non-labor) b. Site preparation and site work (pre/post-delivery of the modular building), to include: Site work mobilization Erosion, sediment, and pollution control Demolition and removal Tree removal! 1!
2 Grading and foundation work Storm system installation Hard surface work to include curbs, paving, and concrete (as required) Utilities (including sanitary lift station) Landscaping (trees, shrubs, groundcover, sodding and mulching) Irrigation of all newly sodded and planted areas (design build) Site clean up c. Modular work and materials, to include: Plumbing connections (water/sewer/manifold work) Electrical connections (distribution/subpanels/exterior lights/transformers/ poles/final hookup) Gas connections (install tank and make connections to science lab) Science lab vent hood connections Gutters and downspouts (termination/manifold) Steps, ramps, and connections (as applicable and integrated with the pavilion) d. Pavilion work and materials e. Unit prices for all materials f. Specialties g. Equipment h. Special construction i. Allowances j. Contractor construction contingency k. Provision and management of all required site inspections l. Insurance (see section VI below) m. At least three (3) references for similar work n. Short resumes of key personnel o. Overhead and profit II. Project Timeline The general sequencing of the project is as follows: 1. Phase 1: Preparatory Site Work (grading/storm water system/utilities/pad) 2. Phase 2: Modular Emplacement (delivery/install by Mobile Modular) 3. Phase 3: Pavilion Construction and Finish Work (for modular building and site) The goal is to start delivery of the modular building by no later than May 16, 2016, and to complete all work related to this project by no later than July 18, 2016.! 2!
3 III. Project Partners ACA has engaged the following primary partners in conjunction with this project: Mobile Modular is supplying and emplacing the modular buildings. Mr. Clinton Buchanan, Project Manager Cellular: TSW is providing overarching architectural and design services. Mr. Jerry Spangler, Director Cellular: Breedlove Land Planning is providing overarching civil engineering services. Mr. Reece Parker, Principal Cellular: IV. Submission Instructions Please submit a comprehensive response to this RFP no later than Wednesday, March 9, 2016 at 5:00pm EST. Please carefully review all plan and design documents prior to submission. The package of construction documents may be obtained by contacting TSW (Mr. Jerry Spangler, jspangler@tsw-design.com). Mr. Spangler will provide the password for access to the Dropbox account that contains the bid documents. A non-mandatory, pre-bid site visit will be held at Atlanta Classical Academy on Friday, March 4, at 2:00pm EST, during which representatives from all parties including Breedlove Land Planning, TSW, and Mobile Modular will be present. Bidders interested in attending this meeting should forward their intentions to Mr. Stephen Lambert (slambert@atlantaclassical.org). Submit your final RFP via to: Mr. Matthew Kirby (mkirby@atlantaclassical.org) Mr. Scott Yates (syates@atlantaclassical.org) Mr. Stephen Lambert (slambert@atlantaclassical.org) Mr. Ray Crowell (rcrowell@atlantaclassical.org)! 3!
4 V. Award of Contract Any contracts awarded pursuant to the RFP will be awarded based on the bids or offers which are responsive to the RFP and are most advantageous to ACA with respect to price, quality, confidence to complete the work no later than July 18, 2016, and other factors that ACA may consider. ACA reserves the right to reject any and all proposal received as a result of this RFP. VI. Insurance Requirements At a minimum, the selected firm(s) must carry the following insurance for the entire period of the awarded contract, and must name ACA as an additional Insured. A. Commercial General Liability Insurance (including Liability assumed under an Insured Contract, Independent Contractors) in the following limits: a. General Aggregate $2,000,000 b. Products/Complete Operations Aggregate $2,000,000 c. Each Occurrence $1,000,000 d. Personal/Advertising Injury $1,000,000 e. Damage to Premise Rented to You $50,000 f. Medical Payments $5,000 Policy shall be endorsed to amend the general aggregate limit to apply separately to this project with form ISO CG2503 (11/85) or equivalent. B. Builders Risk or Installation Floater to cover materials and labor for contractor s work and any such policies shall waive rights of subrogation in favor of ACA. All policy deductibles are to be the responsibility of the Contractor for all damages resulting from the work of the Contractor. Subcontractor shall determine for itself the adequacy for their own coverage for damage to materials, equipment, and their work. C. Umbrella Excess Liability in the following limits: a. Each Occurrence $5,000,000 b. General Aggregate $5,000,000 c. Products/Completed Operations Aggregate $5,000,000 D. Worker's Compensation in the following limits: a. Workers Compensation Statutory b. Employers Liability Each Accident $1,000,000 c. Employers Liability Policy Limit Disease $1,000,000 d. Employers Liability Each Employee Disease $1,000,000! 4!
5 A Waiver of Subrogation in ACA s favor with respect to injuries/illness to vendor's employees is required. E. Commercial Automobile Liability (including owned, non-owned and hired vehicles) in the following limits: Bodily Injury/Property Damage (CSL, Each Incident) $1,000,000. Such coverage shall remain in effect for the term of the contract and any extension thereof. ACA shall be named as an additional insured on all coverages (with the exception of Worker s Compensation) for the length of the contract. All policies will be on a primary basis, non-contributory with any other insurance coverages carried by ACA. All liability policies must provide cross-liability coverage as would be achieved under the standard ISO separation of insureds clause. Liability coverages must be provided on an occurrence policy form only. Claims made policy form insurance will not be acceptable. Each insurance company must be rated not less than A-, VII by A.M. Best. All policies shall be endorsed for 30 days written notice of cancelation to ACA, except 10 days notice for non-payment of premium. Contractor shall in writing notify at least 30 days in advance of any material change, cancellation or non-renewal of any required insurance and failure to provide written notice shall entitle ACA to withhold any and all payments due. Furthermore, issuance of written notice shall not relieve the subcontractor of its obligation under this Agreement. The Contractor shall maintain all of the above insurance at all times until final completion of the work, including completed operations general liability and umbrella liability which shall be maintained for three years after final completion of the work, and include ACA as additional insured during this period. Maintenance of insurance by the Contractor shall in no way be interpreted as relieving the Contractor of any responsibility and shall not in any manner limit or qualify the liability and obligation of the Contractor whatsoever. The Contractor may carry at its own expense such additional coverage as it deems necessary. The Contractor shall require all of its subcontractors, unless otherwise approved by ACA, to also carry insurance equal in kind and amount for workers compensation, commercial general liability, and business automobile, or at other limits and amounts as required by ACA.! 5!
6 ADDENDUM #1 (3/9/2016) I. Relating to the response deadline for this RFP: The new submission deadline is: Monday, March 14, at 5:00 pm CST. II. Relating to Architectural Documents (provided by TSW): 1. The following roofing manufactures will be accepted as long as the proposed product is 45 mil TPO; 15 year warranty; and a fully adhered product (Genflex and Versico). 2. TSW has revised the Pavilion floor framing detail where the flooring touches the Modular Building. Please see attached revised sheet S-4. As a clarification note, the top of the 2x6 pavilion decking boards must sit tight against the underside of all door thresholds at the Modular Building. 3. The following clarification statement regarding work by Georgia Power is provided: Please see Sheet E1.1; Meter Rack Elevations; Note #2. The General Contractor is to contact the Georgia Power Company and verify connection feed. TSW s MEP engineer has discussed this connection feed with Ryan Hatcher at Georgia Power and it is TSW s understanding that a new power pole will be set due east of the proposed Utility Meters within the ROW on the school s side of North Side Drive. Furthermore, it is TSW s understanding that Georgia Power will provide the underground service connector to the meters, but you are to verify this along with the approximate pole location. III. Relating to Civil Documents (provided by Breedlove Land Planning): 1. Regarding allowances and unit pricing, what are you looking for from an allowance and unit price standpoint? We have not identified the need for allowances. We recommend the bidders submit unit prices in accordance with the following guidelines. Unit prices are amounts to be used for work that will be added to or deleted from Contract by Change Order in the event such additional work or work removal may be required. Unit prices are complete for labor, equipment, material, the transporting of needed material and the hauling off and disposal of excess and unsuitable material, installation, taxes, overhead and profit, and all incidental costs. Furnish and install non-woven geotextile fabric ($ per 8 oz/sq yd) Haul in, furnish, and install stone stabilization material including: i. Graded Aggregate Base (including compaction) ($ per ton) ii. No 57 Stone ($ per ton) iii. No 4 Stone ($ per ton) iv. Surge Stone ($ per ton)! 6!
7 v. Rip-rap ( lb) ($ per ton) vi. Furnish and install Bermuda Sod ($ per sq ft) Rock and unsuitable soils i. Remove rock and haul off-site ($ per cu yd) ii. Remove unsuitable soils and haul off-site ($ per cu yd) iii. Haul-in suitable soils and place/compact ($ per cu yd) 2. Regarding the new chain link fence, reference page C200, it looks as if the chain link fence should extend to the back of the site. Is this correct? Yes the fence needs to extend to rear of the property. Refer to plan revision, Sheet C200. It shall be 11 ga wire, black vinyl coated and shall include one 12 wide double leaf gate at the new sidewalk. See added Detail 12 on Sheet C Regarding the demo plan, reference C100 note 8, which site features are you wishing to retain? All site features shall remain unless otherwise noted. 4. Do we provide NDPES monitoring? Yes. 5. Do we need to provide an irrigation system? Yes, the bid shall include a complete irrigation system utilizing the design/ build method of delivery. The irrigation design for the site shall be based on appropriate materials, design concept and program. This will include head location, pipe routings, pipe and wire sizing based on design program. The system shall be adequately zoned. All plant material installed for the project, including turf and groundcovers, shall be irrigated by the irrigation system. 6. Are we to provide soil testing for bearing capacities? Yes For the irrigation line, referencing C500, it is called out as designed by others. What would you like us to include in our pricing? Please refer to #5 above. 8. Can we have more details regarding the propane tank and the pit it sits into? Please refer to plan revision, Sheet C500 and added Detail 13 on Sheet C Clarification and confirmation of sewer line routing. Please see attached revised Sheet C501 for revised force main routing and installation information. 10. Add Sheets C800, C801, and C802 attached, all of which contain technical specifications for the project.! 7!
Exhibit B (Incorporated into Construction Purchase Order Terms and Conditions) CONSTRUCTION CONTRACT INSURANCE REQUIREMENTS
Exhibit B (Incorporated into Construction Purchase Order Terms and Conditions) CONSTRUCTION CONTRACT INSURANCE REQUIREMENTS 1.1. Contractor shall maintain insurance underwritten by solvent insurance companies
More informationINSURANCE REQUIREMENTS (A) This insert applies to the following State Contracts:
INSURANCE REQUIREMENTS (A) This insert applies to the following State Contracts: General Conditions of the Construction Contract Design/Bid/Build (SC-6.23), or Contractors Agreement Design/Bid/Build (SC-6.21),
More information14RFP00721B-WL, Small Business Market Availability Study
August 12, 2014 Re: 14RFP00721B-WL, Small Business Market Availability Study Dear Proposers: Attached is one (1) copy of Addendum 1, hereby made a part of the above referenced Request for Proposal #14RFP00721B-WL,
More informationSHORENSTEIN REALTY SERVICES, L.P VENDOR INSURANCE REQUIREMENTS CATEGORY D VENDORS
NAME AND ADDRESS OF AGENCY: NAME AND ADDRESS OF INSURED: Certificate of Insurance COMPANIES AFFORDING COVERAGES INSURANCE COMPANY S DESIGNATED MUST HAVE A MINIMUM OF A- VIII AM BEST RATING COMPANY A COMPANY
More informationGordon L. Mountjoy & Associates, Inc.
INSURANCE REQUIREMENTS CHECKLIST Submit an Acord 25 form and the endorsements as required below. Your insurance must be in compliance immediately after you sign your subcontract and before you start work.
More informationARTICLE 11. INSURANCE AND BONDS
Provide submittals to Architect / Engineer that are required by any governing body or other authorities. Upon receipt of the Contractor s list, the Architect will make an inspection to determine whether
More informationRequest for Statements of Qualifications # 27676 for Electric Motor Repair
Request for Statements of Qualifications # 27676 for Electric Motor Repair PURPOSE: The City is requesting Statements of Qualifications (SOQ s) from Qualified and Fully Equipped Electric Motor Repair shops
More informationMATTCON GENERAL CONTRACTORS, INC. INSURANCE SPECIFICATIONS EXHIBIT B INSURANCE Subcontractor shall obtain insurance of the types and in the amounts
MATTCON GENERAL CONTRACTORS, INC. INSURANCE SPECIFICATIONS EXHIBIT B INSURANCE Subcontractor shall obtain insurance of the types and in the amounts described below. The insurance shall be written by insurance
More informationPHILADELPHIA REDEVELOPMENT AUTHORITY INSURANCE REQUIREMENTS
PHILADELPHIA REDEVELOPMENT AUTHORITY INSURANCE REQUIREMENTS The individual or entity seeking to enter into a contract with the Philadelphia Redevelopment Authority or who is entering into a contract with
More informationSAMPLE VERBIAGE OF SUBCONTRACT AGREEMENT INSURANCE REQUIREMENTS (PLEASE REFER TO YOUR STRUCTURE HOME SUBCONTRACT AGREEMENT)
SAMPLE VERBIAGE OF SUBCONTRACT AGREEMENT INSURANCE REQUIREMENTS (PLEASE REFER TO YOUR STRUCTURE HOME SUBCONTRACT AGREEMENT) INSURANCE REQUIREMENTS A. COVERAGE: Subcontractor and its subcontractors and
More informationINVITATION TO BID. Contractor Services Associated with:
INVITATION TO BID Contractor Services Associated with: COMMUNITY CENTER AT 330 WINDSOR AVENUE ROOF REPAIR AND RESTORATION PROJECT 330 WINDSOR AVENUE WINDSOR, CT 06095 THIS IS A REQUEST FOR PROPOSALS AND
More informationCURRENT SPECIAL PROVISIONS FOR LIABILITY INSURANCE
CURRENT SPECIAL PROVISIONS FOR LIABILITY INSURANCE NDOR Projects The special provision which begins on the following page ---- (A-55-0414) --- became effective beginning with projects let in the letting
More informationRequest for Proposals Westchase District Monument Signs Repaneling Date Issued: August 10, 2015
Request for Proposals Westchase District Monument Signs Repaneling Date Issued: August 10, 2015 Westchase District is seeking proposals to replace the colored vinyl and acrylic sections of all its 41 monuments
More informationDepartment of Purchasing & Contract Compliance
Department of Purchasing & Contract Compliance Fulton County, GA August 8, 2014 Re: 14RFP070714K-NH 2015 STANDBY ENGINEERING SERVICES Dear Vendors: Attached is one (1) copy of Addendum 2, hereby made a
More informationCURRENT SPECIAL PROVISIONS FOR LIABILITY INSURANCE
CURRENT SPECIAL PROVISIONS FOR LIABILITY INSURANCE Local Public Agency (LPA) Projects The special provision which begins on the following page ---- (A-54-0414) --- became effective beginning with projects
More informationW.E. O NEIL CONSTRUCTION CO. OF COLORADO INSURANCE REQUIREMENTS. Project Name Project Address City, State Zip
W.E. O NEIL CONSTRUCTION CO. OF COLORADO INSURANCE REQUIREMENTS Project Name Project Address Subcontractor SHALL NOT COMMENCE WORK at the site until it has obtained and provided all insurance required
More informationSUBCONTRACTOR PREQUALIFICATION FORM
SUBCONTRACTOR PREQUALIFICATION FORM Instructions: Please fill out the following information and return via email to info@norconinc.com or mail to Norcon, Inc. 661 W. Ohio Street, Chicago, IL 60654, Attention
More informationAttachment 04 Contractor s Insurance Requirements
GROUP 31503 BITUMINOUS CONCRETE Page 1 of 5 Attachment 04 Contractor s Insurance Requirements The prospective awardee shall be required to procure, at its sole cost and expense, all insurance required
More informationSchedule Q (Revised 1/5/15)
Schedule Q (Revised 1/5/15) CONSTRUCTION CONTRACTOR INSURANCE REQUIREMENTS Section 0.0 Introduction of the Owner-Controlled Insurance Program The City of Oakland (City) has implemented an Owner-Controlled
More informationW.E. O NEIL CONSTRUCTION CO.
W.E. O NEIL CONSTRUCTION CO. INSURANCE REQUIREMENTS Project Name Project Address Subcontractor SHALL NOT COMMENCE WORK at the site until it has obtained and provided all insurance required by the Contract
More informationNew Hanover County. Request for Qualifications. Crime Scene Investigation (CSI) Building Expansion
New Hanover County Request for Qualifications Crime Scene Investigation (CSI) Building Expansion General Information The purpose of this Request for Qualifications is to solicit qualifications from qualified
More informationAttachment 4: Insurance Requirements
The prospective awardee shall be required to procure, at its sole cost and expense, all insurance required by this Section and, unless otherwise required by this Section, provide proof of the same within
More informationCharlie Crockett Charlie Crockett, APA Assistant Purchasing Agent
September 12, 2011 Re: 11ITB80101A-CJC-Locum Tenens Positions Staffing Services Dear Bidders: Attached is one (1) copy of Addendum 1, hereby made a part of the above referenced ITB. Except as provided
More informationLiability Insurance Guidelines For Water Restoration and Mold Contractors April 2013
Liability Insurance Guidelines For Water Restoration and Mold Contractors April 2013 Disclaimer: The following is a draft of suggested language for incorporation into construction insurance specifications.
More informationCURRENT SPECIAL PROVISIONS FOR LIABILITY INSURANCE
CURRENT SPECIAL PROVISIONS FOR LIABILITY INSURANCE NDOR Projects The special provision which begins on the following page ---- (A-55-0611) --- became effective beginning with projects let in the letting
More informationAttachment 4. Contractor Insurance Requirements
GROUP 33700 FINE & COARSE AGGREGATES Page 1 of 7 Attachment 4 Contractor Insurance Requirements The prospective awardee shall be required to procure, at its sole cost and expense, all insurance required
More informationBuyer: Daniels, Joan E Phone (248)858-5481. Fax: (248)858-1677 Email: danielsj@oakgov.com
PROPOSAL FORM L. BROOKS PATTERSON - OAKLAND COUNTY EXECUTIVE OAKLAND COUNTY PURCHASING DIVISION PROPOSAL COVER SHEET Contact Information: Oakland County Purchasing Division Building 41 West - Lower Level
More informationADDENDUM A1. Subcontractor Insurance Requirements
ADDENDUM A1 Subcontractor Insurance Requirements Certificates and endorsements must be received and approved prior to the start of any work. No payments will be released until all insurance documents are
More information2 nd Notice AHCCCS Insurance Requirements ACTION REQUIRED September 29, 2014 Page 1 of 5
Dear Providers and Staff: 2 nd Notice ACTION REQUIRED September 29, 2014 Page 1 of 5 We distributed a blast fax communication to you on July 16 explaining that effective October 1, 2013 AHCCCS updated
More informationH. The Contractor shall not begin work under the contract until the required insurance has been obtained and approved by the Contracting Agency.
Insurance Requirements (1) General Requirements A. The Contractor shall obtain the insurance described in this section from insurers approved by the State Insurance Commissioner pursuant to RCW Title 48.
More informationSAMPLE CONSTRUCTION INSURANCE REQUIREMENTS
SAMPLE CONSTRUCTION INSURANCE REQUIREMENTS A. In General The shall purchase and continuously maintain in full force and effect for the policy periods specified below the insurance policies specified in
More informationEXHIBIT C CONSULTANT INSURANCE REQUIREMENTS SACRAMENTO AREA FLOOD CONTROL AGENCY
EXHIBIT C CONSULTANT INSURANCE REQUIREMENTS SACRAMENTO AREA FLOOD CONTROL AGENCY Revised: February 23, 2008 EXHIBIT C INSURANCE REQUIREMENTS Without limiting Consultant s indemnification, Consultant shall
More informationSCHEDULE 17. Insurance Requirements. Part 1 Insurance Requirements applicable to the Phase 2 Work
SCHEDULE 17 Insurance Requirements Part 1 Insurance Requirements applicable to the Phase 2 Work Capitalized terms used in this Schedule which are not otherwise defined shall have the meanings given to
More informationTOWN OF FARMINGTON, CT REQUEST FOR PROPOSALS FOR CONSTRUCTION EQUIPMENT RENTALS AND ON CALL CONSTRUCTION SERVICES
TOWN OF FARMINGTON, CT REQUEST FOR PROPOSALS FOR CONSTRUCTION EQUIPMENT RENTALS AND ON CALL CONSTRUCTION SERVICES The Town of Farmington Department of Public Works is seeking proposals for the purpose
More informationINSURANCE AND INDEMNIFICATION REQUIREMENTS. RE: CCTV system for bus shelters at the Economy Lot PAGE 1 OF 4
1THE PHILADELPHIA PARKING AUTHORITY RE: CCTV system for bus shelters at the Economy Lot PAGE 1 OF 4 Prior to commencement of the contract and until completion of your work, shall, at its sole expense,
More information2014/2015 PAVING PROJECT MILLING AND PATCHING BID DOCUMENTS JASPER COUNTY, GEORGIA
2014/2015 PAVING PROJECT MILLING AND PATCHING BID DOCUMENTS JASPER COUNTY, GEORGIA Issued on January 7, 2015 1 ADVERTISEMENT FOR BIDS 2014/2015 ROADWAY PATCHING PROJECT JASPER COUNTY, GEORGIA Separate,
More informationGasparilla Island Bridge Authority REQUEST FOR PROPOSALS LANDSCAPE SERVICES
Gasparilla Island Bridge Authority REQUEST FOR PROPOSALS LANDSCAPE SERVICES RFP #2016-03 P.O. Box 1918 Boca Grande, Florida 33921 www.giba.us Kathy Banson-Verrico, Executive Director INTRODUCTION The State
More informationDemo Existing Curb Demo Existing Asphalt Roadway Demo Asphalt Saw Cutting Protection Fence - 4 Snow Fence with T posts
SECTION 00300 BID FORM S For additions and deletions to the Contract, the following unit prices shall be applicable for the specific items listed. Unit Prices shall be complete, in place including required
More informationRequest for Qualifications
Request for Qualifications Architectural and Engineering Services associated with WINDSOR ANIMAL SHELTER DESIGN TOWN OF WINDSOR, CT 06095 GENERAL The Town of Windsor is accepting qualification proposals
More informationAppendix J Contractor s Insurance Requirements
Appendix J Contractor s Insurance Requirements Page 1 of 7 Appendix J Contractor s Insurance Requirements During the term of this Contract, the Contractor shall maintain in force, at its sole cost and
More informationExhibit 1 to Part 3 Project-Specific Terms
Exhibit 1 to Part 3 Project-Specific Terms (Date of Standard Exhibit 1 to Part 3: May 2014) Part 3 (2013 Lump Sum Agreement Between Department and Design-Builder), Part 4 (2013 General Conditions of Contract
More informationPREQUALIFICATION APPLICATION REQUIREMENTS
PREQUALIFICATION APPLICATION REQUIREMENTS To be eligible to bid and contract work with Webcor, subcontractors are required to be prequalified annually. If you have any questions, please contact Webcor
More informationHow To Insure A Project In The United States
Recommended Liability Insurance Guidelines For Custom Applicators and Certified Crop Advisors May 2015 Disclaimer: The following is a draft of suggested language for incorporation into services procurement
More informationATTACHMENT A.6 INSURANCE REQUIREMENTS ROUTINE CONSTRUCTION, MAINTENANCE AND REPAIR PROJECTS
ATTACHMENT A.6 INSURANCE REQUIREMENTS ROUTINE CONSTRUCTION, MAINTENANCE AND REPAIR PROJECTS Contractor shall obtain insurance of the types and in the amounts listed below. A. COMMERCIAL GENERAL AND UMBRELLA
More informationCITY OF LAREDO PURCHASING DIVISION TERMS AND CONDITIONS OF INVITATIONS FOR BIDS
TERMS AND CONDITIONS OF INVITATIONS FOR BIDS GENERAL CONDITIONS Bidders are required to submit bids upon the following expressed conditions: (a) Bidders shall thoroughly examine the specifications, schedule
More informationREQUEST FOR PROPOSALS CLOSED CAPTIONING SERVICES FOR NEW HANOVER COUNTY GOVERNMENT
REQUEST FOR PROPOSALS CLOSED CAPTIONING SERVICES FOR NEW HANOVER COUNTY GOVERNMENT WOODY WHITE, CHAIRMAN BETH DAWSON, VICE-CHAIRMAN JONATHAN BARFIELD, JR. BRIAN BERGER THOMAS WOLFE CHRIS COUDRIET, COUNTY
More informationHURRICANE PROTECTION AND SEVERE WEATHER PLAN INFORMAL REQUEST FOR PROPOSALS FOR NEW HANOVER COUNTY EMERGENCY MANAGEMENT
HURRICANE PROTECTION AND SEVERE WEATHER PLAN INFORMAL REQUEST FOR PROPOSALS FOR NEW HANOVER COUNTY EMERGENCY MANAGEMENT Proposals will be received in the New Hanover County Finance, 230 Government Center
More informationRequest for Quote. LETTERING REPLACEMENT At Tulsa International Airport
Request for Quote LETTERING REPLACEMENT At Tulsa International Airport 7777 East Apache Street Room A217 Tulsa OK 74115 Attn: Mark Soltero Airports Facilities Engineer Office (918)838-5603 Email marksoltero@tulsaairports.com
More informationREQUEST FOR PROPOSAL LARIMER COUNTY COLORADO 200 W. OAK ST., SUITE 4000 FORT COLLINS, COLORADO
REQUEST FOR PROPOSAL LARIMER COUNTY COLORADO 200 W. OAK ST., SUITE 4000 FORT COLLINS, COLORADO PROPOSAL NUMBER: 13-02 DESCRIPTION: Administration of 401(a) and 457 Plans RECORDING DATE: 2/25/2013 The Board
More informationAPPENDIX B INSURANCE & BONDING REQUIREMENTS FC-5801
APPENDIX B INSURANCE & BONDING REQUIREMENTS ARCHITECTURAL AND ENGINEERING DESIGN SERVICES AT HARTSFIELD- JACKSON ATLANTA A. Preamble The following requirements apply to all work under the agreement. Compliance
More informationDepartment of Purchasing & Contract Compliance
Department of Purchasing & Contract Compliance Felicia Strong-Whitaker, Interim Director REQUEST FOR E-QUOTE NUMBER: 12CT86224YA PROJECT TITLE: Maintenance contract for MicroStation Software for Water
More informationSAN ANTONIO WATER SYSTEM PURCHASING DEPARTMENT FORMAL INVITATION FOR BEST VALUE BID (BVB) FOR PRESCRIPTION SAFETY EYEWEAR PROGRAM ADDENDUM NO.
SAN ANTONIO WATER SYSTEM PURCHASING DEPARTMENT Issued By: Joseph Ramon Date Issued: June 15, 2015 BID NO.: 15-0118 FORMAL INVITATION FOR BEST VALUE BID (BVB) FOR PRESCRIPTION SAFETY EYEWEAR PROGRAM ADDENDUM
More informationA. Project Name: NEW POLICE STATION HARRISON TOWNSHIP
1.1 PROJECT INFORMATION A. Project Name: NEW POLICE STATION HARRISON TOWNSHIP B. Owner: Harrison Township, New Jersey C. Owner Representative Dennis M. Chambers Deputy Administrator, Certified Public Works
More informationEXHIBIT 1 SEMINOLE ELECTRIC COOPERATIVE, INC. (SECI) CONTRACTOR S INSURANCE REQUIREMENTS
EXHIBIT 1 SEMINOLE ELECTRIC COOPERATIVE, INC. (SECI) CONTRACTOR S INSURANCE REQUIREMENTS Acceptable certificate(s) of insurance and policy endorsements, as specified below, showing that Contractor s insurance
More informationExhibit 1 to Part 3 Project-Specific Terms
Exhibit 1 to Part 3 Project-Specific Terms (Date of Standard Exhibit 1 to Part 3: July 2013) This Exhibit 1 to Part 3 (2013 Lump Sum Design-Build Agreement Between Department and Design-Builder) contains
More informationSANTA BARBARA METROPOLITAN TRANSIT DISTRICT. Invitation for Bids for Architectural & Engineering Services. Addendum Number 1 Issued August 5, 2013
SANTA BARBARA METROPOLITAN TRANSIT DISTRICT Invitation for Bids for Architectural & Engineering Services Addendum Number 1 Issued August 5, 2013 The Santa Barbara Metropolitan Transit District (MTD) herewith
More informationConstruction Management At-Risk
Oconee County Schools P.O. Box 146, 34 School Street Watkinsville, GA 30677 706-769-5130 706-769-3513 REQUEST FOR PROPOSALS ISSUE DATE: March 10, 2016 RFP REF: Construction Management At-Risk Construction
More informationEXHIBIT D. Insurance and Bond Requirements
EXHIBIT D Insurance and Bond Requirements A. General Requirements YMCA shall forward certificates of insurance with the endorsements required below to the City as verification of coverage within 5 calendar
More informationInsurance Requirements Professional Services
Insurance Requirements Professional Services A. REQUIRED INSURANCE. Without limiting any of the other obligations or liabilities of the vendor/contractor, the vendor/contractor shall, at their sole expense,
More informationREQUEST FOR PROPOSALS
ROWAN COUNTY 130 West Innes Street Salisbury, NC 28144 Tel: (704) 216-8174 Email: david.sifford@rowancountync.gov REQUEST FOR PROPOSALS FOR REPLACEMENT OF COMMERCIAL ROOFTOP AIR CONDITIONING UNIT Issued
More informationMINNESOTA STATE COLLEGES AND UNIVERSITIES General Insurance Requirements for Contractors & Vendors
Certificate of Liability Insurance, Form ACORD25: Following are the insurance requirements of the State of Minnesota acting through its Board of Trustees of the Minnesota State Colleges and Universities,
More informationREQUEST FOR PROPOSAL
REQUEST FOR PROPOSAL PURCHASING DEPARTMENT P.O. BOX 1349 300 N. PATTERSON ST. VALDOSTA, GEORGIA 31601 #LC-2016-09R FOR: Security Guard Services DUE DATE: April 20, 2016 Proposals Due By: 10:00 am EST Amy
More informationINSURANCE REQUIREMENTS FOR ALL CITY CONTRACTS
INSURANCE REQUIREMENTS FOR ALL CITY CONTRACTS 1. GENERAL PROVISIONS A. Indemnification. The Contractor shall indemnify and save harmless the City of Lincoln, Nebraska from and against all losses, claims,
More information2001 Main, Kansas City, MO 64108 Hilton Home 2 Suites
REQUEST FOR PROPOSALS 2001 Main, Kansas City, MO 64108 Hilton Home 2 Suites This RFP is open only to contractors prequalified by Port KC at the time of RFP issuance DATE OF ISSUANCE: January 8 th, 2016
More informationThe West Lafayette Engineering Department is requesting quotes for sidewalk repairs needed in the Barbarry Subdivision.
May 19th, 2016 RE: REQUEST FOR QUOTES 2016 Sidewalk Replacement The West Lafayette Engineering Department is requesting quotes for sidewalk repairs needed in the Barbarry Subdivision. The enclosed Quote
More informationRequest for Quotation (RFQ) Hydrilla management via benthic matting in Henrietta, NY. Re-Release Date: Monday, December 7, 2015
New York State Department of Environmental Conservation Division of Lands and Forests Invasive Species Coordination Unit 625 Broadway, Floor 5 Albany, NY 12233-4250 Request for Quotation (RFQ) Hydrilla
More informationHow To Insure Construction Contracts In Northern California Schools Insurance Group
NORTHERN CALIFORNIA SCHOOLS INSURANCE GROUP Cover Note to NCSIG Members & Their Architects/Engineers Insurance Recommendations for Construction Contracts Applicable to New Construction & Modernization/Remodeling
More informationINSURANCE AND SURETY INFORMATION SHEET
INSURANCE AND SURETY INFORMATION SHEET In order for your company to comply with the bonding and insurance requirements per your contract with the City of Elk Grove there are several things that we require.
More informationEXHIBIT B-1 INSURANCE REQUIREMENTS FOR CONSTRUCTION CONTRACTS ABOVE $30,000
INSURANCE REQUIREMENTS F CONSTRUCTION CONTRACTS ABOVE $30,000 Indemnity To the fullest extent allowed by law, the Contractor shall indemnify, defend, and hold harmless the County of Santa Clara (hereinafter
More informationDepartment of Purchasing & Contract Compliance
Department of Purchasing & Contract Compliance Felicia Strong-Whitaker, Interim Director REQUEST FOR E-QUOTE NUMBER: 12CT85408YA PROJECT TITLE: Tree Removal Service for Water Resources Department DUE DATE:
More informationTown of Somers, Connecticut Geographic Information Consulting Services Request for Proposals
Town of Somers, Connecticut Geographic Information Consulting Services Request for Proposals The Town of Somers invites proposals for Geographic Information System consultation/ implementation services.
More informationWASHINGTON SUBURBAN SANITARY COMMISSION
APPENDI B WASHINGTON SUBURBAN SANITARY COMMISSION PROCUREMENT OFFICE INSURANCE AND BONDING CONTRACT NO. 1. INSURANCE REQUIREMENTS A. INSURANCE: The Contractor shall be required to maintain insurance for
More informationREQUEST FOR QUALIFICATIONS CONSULTANT ARCHITECTURAL SERVICES FOR VARIOUS TOWN BUILDINGS FOR THE PUBLIC WORKS DEPARTMENT, TOWN OF GROTON, CT
REQUEST FOR QUALIFICATIONS CONSULTANT ARCHITECTURAL SERVICES FOR VARIOUS TOWN BUILDINGS FOR THE PUBLIC WORKS DEPARTMENT, TOWN OF GROTON, CT Statements of Qualification for the selection of on-call architectural
More informationSECTION 00 73 16 INSURANCE REQUIREMENTS
SECTION 00 73 16 INSURANCE REQUIREMENTS PART 1 GENERAL 1.01 SECTION INCLUDES 1.02 Insurance Requirements 1.02 INSURANCE REQUIREMENTS A. The successful Contractor shall procure and maintain for the duration
More informationMAIN CIVIL WORKS CONTRACT SCHEDULE 13 INSURANCE TABLE OF CONTENTS
MAIN CIVIL WORKS CONTRACT SCHEDULE 13 INSURANCE TABLE OF CONTENTS 1 INTERPRETATION... 1 1.1 Definitions... 1 2 CONTRACTOR PROVIDED INSURANCE COVERAGE... 1 3 BC HYDRO PROVIDED INSURANCE COVERAGE... 2 4
More informationEXHIBIT B. Insurance Requirements for Construction Contracts
EXHIBIT B Insurance Requirements for Construction Contracts Contractor shall procure and maintain for the duration of the contract, and for x years thereafter, insurance against claims for injuries to
More informationAttachment 12 Insurance
Attachment 12 Insurance PART A DESIGN/BUILD PERIOD INSURANCES PART A(I): RTD DESIGN/BUILD PERIOD INSURANCES 1. OWNER CONTROLLED INSURANCE PROGRAM 1.1 Eligibility and Enrollment RTD shall procure an owner
More informationKALEIDA HEALTH INSURANCE REQUIREMENTS SERVICE PROVIDERS. Bodily Injury and Property Damage Limit occurrence. General Aggregate $2,000,000
1. INSURANCE TO BE MAINTAINED BY VENDOR/SERVICE PROVIDER Prior to providing products/equipment and/or services under this Agreement, Vendor/Service Provider, at its own cost and expense, shall procure
More informationCONTRACTOR SAFETY LIMITING YOUR LIABILITY MARCH 20, 2013
CONTRACTOR SAFETY LIMITING YOUR LIABILITY MARCH 20, 2013 Scott C. Bellack Senior Vice President Cleveland, Ohio Questions Who is in the audience? Who is responsible for the contractor selection process
More information1. Subcontractor Prequalification Questionnaire a. Please complete with assistance from your insurance agent(s)
3208 Tazewell Pike, Suite 103 Tel: 865.688.1335 / Fax: 865.688.9291 www.creativestructuresinc.com Attention: Prospective Subcontractors Re: Prequalification Applications Creative Structures, Inc., appreciates
More informationADVERTISEMENT FOR BIDS
ADVERTISEMENT FOR BIDS Bids will be received at the office of the Niles City School District, 100 West Avenue, Niles, Ohio, 44446 until 12:00 PM on Friday, March 22, 2013 and will be opened and read immediately
More informationINSURANCE REQUIREMENTS FOR CONSTRUCTION CONTRACTS ABOVE $25,000
Page 1 of 9 DOCUMENT 00850 INDEMNIFICATION AND INSURANCE REQUIREMENTS EXHIBIT B-1 INSURANCE REQUIREMENTS FOR CONSTRUCTION CONTRACTS ABOVE $25,000 Indemnity The Contractor shall indemnify, defend, and hold
More informationTROUP COUNTY COMPREHENSIVE HIGH SCHOOL
TROUP COUNTY BOARD OF EDUCATION REQUEST FOR SEALED COMPETITIVE PROPOSALS FOR CONSTRUCTION OF: RE-FLOORING TO: TROUP COUNTY COMPREHENSIVE HIGH SCHOOL LAGRANGE, GEORGIA TROUP COUNTY SCHOOL SYSTEM LAGRANGE,
More informationL ARAMIE C OUNTY C OMMUNITY C OLLEGE Cheyenne Wyoming
L ARAMIE C OUNTY C OMMUNITY C OLLEGE Cheyenne Wyoming Request for Proposals to provide Landscape Architect Due Date Proposal Submissions Monday, June 15, 2015 by 5:00 p.m. RFP15-15008 Solicited by: Department
More informationADDENDUM TO SUBCONTRACT [Contractor s Consolidated Insurance Program]
ADDENDUM TO SUBCONTRACT [Contractor s Consolidated Insurance Program] The Subcontract Agreement between LAYTON CONSTRUCTION COMPANY, INC., a Utah corporation ( Contractor ) and, a ( Subcontractor ) dated
More informationD3 Bus Wash Rehabilitation AC Transit Contract #2016-1372 SECTION 007316 INSURANCE REQUIREMENTS
SECTION 007316 INSURANCE REQUIREMENTS PART 1 - INSURANCE REQUIREMENTS 1.01 GENERAL A. Any person, firm or corporation Contractor authorizes to work upon the Property, including any subcontractor, shall
More informationGENERAL INSTRUCTIONS AND REQUIREMENTS
CHICAGO TRANSIT AUTHORITY INSURANCE AND BOND REQUIREMENTS [Short Form rev. 12/04/02] REQUISITION NUMBER: SPECIFICATION NUMBER CTA: PART I. GENERAL INSTRUCTIONS AND REQUIREMENTS A. WAYS TO COMPLY WITH CTA
More informationSolicitation Addendum
Hillsborough County Aviation Authority Solicitation Addendum Addendum No.: 1 Solicitation No.: 14-411-018 Project No.: N/A Solicitation Title: Continuing Environmental Engineering Consulting Services Addendum
More informationRequired Insurance Language for PRF Construction Contracts
Required Insurance Language for PRF Construction Contracts When working with legal counsel to affect a construction contract for new construction or for build-outs the Purdue Risk Management Department
More informationSTATE OF GEORGIA DEPARTMENT OF TRANSPORTATION OPEN AGENCY SERVICE CONTRACT
STATE OF GEORGIA DEPARTMENT OF TRANSPORTATION OPEN AGENCY SERVICE CONTRACT Contract #: Total Obligation: AGREEMENT BETWEEN: The Georgia Department of Transportation s location identified in Paragraph 101A
More informationREQUEST FOR VENDOR PROPOSALS CHINATOWN TEMPORARY HOUSING UNITS
REQUEST FOR VENDOR PROPOSALS CHINATOWN TEMPORARY HOUSING UNITS INTRODUCTION Chinatown Community Development Center (Chinatown CDC) is soliciting proposals from firms to provide, deliver, install, and remove
More informationISLAMORADA, VILLAGE OF ISLANDS FLORIDA. REQUEST FOR QUOTES for NEW HVAC UNITS (RFQ-16-11) May 11, 2016
ISLAMORADA, VILLAGE OF ISLANDS FLORIDA REQUEST FOR QUOTES for NEW HVAC UNITS May 11, 2016 Islamorada, Village of Islands Village Administrative Center 86800 Overseas Highway Islamorada, Florida 33036 ISLAMORADA,
More informationNEWBURGH ENLARGED CITY SCHOOL DISTRIST NEWBURGH, NEW YORK REQUEST FOR PROPOSAL ARCHITECTURE SERVICES 2015 2016
NEWBURGH ENLARGED CITY SCHOOL DISTRIST NEWBURGH, NEW YORK REQUEST FOR PROPOSAL ARCHITECTURE SERVICES 2015 2016 Notice is hereby given that the Board of Education of the Newburgh Enlarged City School District,
More informationADDENDUM # 1. Revised Due Date Now 4/29/2014, no later than 11:00 AM (Originally due on 4/22/2014, no later than 11:00 AM)
PROCUREMENT DEPARTMENT 2 MONTGOMERY STREET, 3 RD FL. JERSEY CITY, NJ 07302 4/18/2014 ADDENDUM # 1 To prospective Bidder for Bid # 37328 entitled, Fire Extinguisher and Equipment Service at Newark Liberty
More informationUNIVERSITY OF CALIFORNIA - INSURANCE REQUIREMENTS FOR CONSTRUCTION-RELATED CONTRACTS / SERVICE AGREEMENTS
UNIVERSITY OF CALIFORNIA - INSURANCE S FOR CONSTRUCTION-RELATED CONTRACTS / SERVICE AGREEMENTS Page 1 of 6 Note to User: The following matrix is intended to provide guidelines to those who have responsibility
More informationMULTI- PURPOSE HALL. College Station, Texas January 17, 2015
BID SOLICITATION FOR CONSTRUCTION PROJECT MANAGEMENT MULTI- PURPOSE HALL College Station, Texas January 17, 2015 A. PURPOSE Islamic Community of Bryan- College Sation, Texas (ICBCS) solicits bids for Project
More informationRequest For Quotes Professional General Contractor Services Wilson Road Park Repair
Request For Quotes Professional General Contractor Services Wilson Road Park Repair 3/25/15 Planning & Community Development Department 971 Wilson Road Riverdale, GA 30274 Tel. # (770) 996-3397 Fax # (770)
More informationAlterations to Building Request Form
Alterations to Building Request Form This form is required for all Organizational Housing Facilities that wish to request any changes, updates, or overall alterations to the facility or surrounding area.
More informationINSURANCE GUIDE I - MINOR CONTRACTS FOR SERVICE
INSURANCE GUIDE I - MINOR CONTRACTS FOR MEETING GUIDE I SPECIFICATIONS DURATION: Project will not exceed 30 calendar days COST: Project cost will not exceed $50,000 RISK: Low, No unusual or high hazards
More informationInsurance Policy Statement
Insurance Policy Statement Any company or individual performing work for the City of Coos Bay (hereinafter the City ) or hosting a special event on City property shall be required to provide proof of insurance
More information