Asbestos Abatement Bid Specifications

Size: px
Start display at page:

Download "Asbestos Abatement Bid Specifications"

Transcription

1 Asbestos Abatement Bid Specifications For: Mansfield Foundry 500 North Main Street Mansfield, Ohio Prepared For: City of Mansfield 30 North Diamond Street Mansfield, Ohio McCabe Engineering & Contracting 3470 Brecksville Road Richfield, Ohio March 2014

2 Table of Contents 1.0 GENERAL INFORMATION PROJECT SUMMARY SITE INFORMATION AND HISTORY REGULATIONS SUPERVISION PERMITS, FEES, AND NOTICES GENERAL WORK PRACTICES SCHEDULE MANDATORY SITE VISIT & QUESTION/ANSWER PERIOD OWNER S RIGHT TO STOP THE WORK OWNER S RIGHT TO CARRY OUT THE WORK REVIEW OF CONTRACT DOCUMENTS/SPECIFICATIONS DAILY LOGS SUBMITTALS ASBESTOS ABATEMENT GENERAL PREPARATION PREPARATION FOR FRIABLE OR NONFRIABLE ACM ACM TYPES, QUANTITIES & LOCATIONS ACM REMOVAL PROCESS Asbestos Removal, Friable Materials Asbestos Removal, Nonfriable Materials Asbestos Removal, Mastic Asbestos Removal, Exterior Transite Siding PREPARATION FOR GLOVE BAG PROCEDURE Asbestos Removal with Glove Bag INSPECTIONS, MANAGEMENT, & MONITORING INSPECTIONS PRIOR TO AND DURING WORK FINAL VISUAL INSPECTIONS AIR MONITORING General Background Air Testing Personal Air Sampling Conditions for Final Air Testing Air Clearance Criteria Final Air Testing Final Air Testing: Exterior Areas Final Air Testing: Glove Bag Procedure Failure of Final Air Tests COMPLETION BID INFORMATION McCabe Engineering & Contracting March 2014 i Mansfield Foundry Asbestos Abatement Bid Specifications

3 Figure 1 - Figure 2 - Exhibit 1 - Exhibit 2 - Exhibit 3 - Site Location Map Location of Asbestos Map ACM Survey Bid Form City Instructions to Bidder Figures Exhibits McCabe Engineering & Contracting March 2014 ii Mansfield Foundry Asbestos Abatement Bid Specifications

4 1.1 Project Summary 1.0 General Information McCabe Engineering & Contracting (McCabe), on behalf of the City of Mansfield (Owner), has prepared the following bid specifications for asbestos abatement at the Mansfield Foundry located at 500 North Main Street in Mansfield, Ohio (Site). The company that is successfully awarded the contract by the Owner will be responsible for implementing these asbestos abatement bid specifications and will be known throughout the remainder of the document (i.e. specifications) as the Contractor. The Owner is actively seeking proposals for a Contractor that will abate the asbestos containing materials (ACM) identified within this document at the Site. The work includes, but is not limited to, removal and proper disposal of ACM at the Site. The Contractor will be responsible for all work that is required to complete the work to the satisfaction of the Owner. The Contractor is to follow regulations referred to in Section 1.3 and receive approval from the Owner for any deviation from these specifications. The Contractor will be responsible for furnishing all labor, equipment, personnel protective equipment, air testing, air monitoring, and materials required for conducting the work described in these specifications. Arranging for electricity, water, or other utilities will be the responsibility of the Contractor, and costs for such should be reflected in bids submitted to the Owner. The Contractor will be responsible for securing the work areas at the Site and posting all notices. Posting notices shall also be performed in a manner compliant with all applicable federal, state, and local regulations. Please refer to Section 2 for details on the asbestos abatement. Please refer to Section 3 for details on inspections, air monitoring, and completion. Please refer to Section 4 for bid information. 1.2 Site Information and History The Site is approximately 18.5 acres in size that ceased operations in 2002 and consists of 22 buildings with the majority of the buildings sharing a common wall. The City of Mansfield purchased the Site in 2003 from the Mansfield Foundry Corporation/Citation Corporation. All the buildings at the Site are currently not in use except for Building 61, which is being used for storage. Please see Figure 1 for the Site Location Map. In November 2003, McCabe conducted an ACM Survey that concluded the presence of ACM at the Site. The following building materials were identified during the ACM Survey as containing asbestos: black mastic, floor tile, and pipe insulation, ceiling panels, and siding. The exact location and quantity of the ACM is discussed in Section 2.3. Refer to Exhibit 1 for ACM Survey. Please note that some of the building numbers referenced in the ACM Survey where the ACM is located differs from the building numbers noted in Section 2.3. The building numbers were McCabe Engineering & Contracting March Mansfield Foundry Asbestos Abatement Bid Specifications

5 updated after the ACM Survey was completed. Please refer to Section 2.3 for the correct building numbers and ACM locations. 1.3 Regulations The Contractor will be responsible for adhering to all federal, state, and local laws and regulations. Below is a list of applicable regulations and standards, which include, but not limited to, the following: 1. U.S. National Archives and Records Administration (NARA) a. 40 CFR 61- Subpart M; National Emission Standard for Asbestos 2. U.S. Department of Labor, Occupational Safety & Health Administration (OSHA) a. 29 CFR part 1910, subpart D: Occupational Exposure to Asbestos; Final Rule 3. U.S. Department of Labor, OSHA a. 29 CFR part : Occupational Exposure to Asbestos; Construction Industry Standard 4. U.S. E.P.A. a. 40 CFR part 61, subpart A: Regulation for Asbestos 5. U.S. E.P.A. a. 40 CFR 763 subpart G: Asbestos Abatement Projects; Worker Protection 6. U.S. Department of Labor, OSHA a. OSHA 29 CFR part : Respiratory Protection 7. U.S. Department of Transportation a. 49 CFR parts 171 and 172: Hazardous Substances Transportation: Asbestos; Final Rule 8. Ohio Department of Health a. Ohio Administrative Code (OAC) : Asbestos Hazard Abatement Contractors, Specialists & Other Professionals 9. Ohio E.P.A. a. OAC : Asbestos Emission Control 1.4 Supervision The Contractor shall provide a Supervisor that is qualified, certified, and capable of overseeing the asbestos abatement activities. The Supervisor must be capable of identifying existing and predictable hazards in the surroundings or working conditions which are unsanitary, hazardous, or dangerous to employees, and who has authorization to take prompt corrective measures. The Supervisor shall also be at the Site whenever work activities are being performed. The Contractor shall be responsible for all precautions as may be necessary to fully protect his work both during its execution and until its final acceptance or the Contractor shall be held responsible for all damages incurred. The Contractor shall be responsible to the Owner for the acts and omissions of his employees, subcontractors and their agents and employees, and other persons performing any of the work under a contract with the Contractor. McCabe Engineering & Contracting March Mansfield Foundry Asbestos Abatement Bid Specifications

6 The Owner or Owner s representatives shall have access to the Site at all times and the Contractor shall be available to assist, if necessary, the Owner or Owner s representative during any visits. 1.5 Permits, Fees, and Notices The Contractor shall secure and pay for all permits, governmental fees including Ohio EPA removal fees, licenses, and inspections necessary for the proper execution of the contract. Permits, fees, and notices include, but are not limited to, asbestos abatement notifications. The Contractor shall give all notices and comply with all laws, ordinances, rules, regulations, and lawful orders of any public authority bearing on the performance of the work. If the Contractor performs any work knowing it to be contrary to such laws, ordinances, rules, and regulations, and without such notice to the Owner Owner s representative, he shall assume full responsibility therefore and shall bear all cost attributable thereto. 1.6 General Work Practices The Contractor, at all times, shall keep the premises free from accumulation of waste materials or rubbish caused by his operations. At the completion of the work, he shall remove all his waste materials and rubbish from and about the Site as well as all his tools and equipment. The Contractor will prevent the spread of dust to neighboring sites and properties and avoid the creation of a nuisance or hazard in the surrounding area. The Contractor shall not perform any work that is not included specifically in this document without submitting a change order in writing describing the additional work and cost to the Owner or Owner s representative. The Contractor will not perform any work described in a change order without receiving prior written approval from the Owner or Owner s representative. The Contractor will dispose of all ACM waste removed during the project at an approved licensed disposal facility that accepts friable and nonfriable ACM waste. Prior to disposal of any ACM waste, the Contractor will notify the Owner or Owner s representative of the licensed disposal facility and receive approval from the Owner or Owner s representative. 1.7 Schedule The Contractor shall submit a schedule of all services to be performed with the bid. The schedule shall include work durations for all services and subtasks. Services and subtasks may be performed concurrently. Additionally, the schedule will include a detailed description of methods and equipment to be used for each operation and of the sequence of operations. The schedule shall be related to the entire project to the extent required by the specifications and shall provide for expeditious and practicable execution of the work. McCabe Engineering & Contracting March Mansfield Foundry Asbestos Abatement Bid Specifications

7 The Contractor shall maintain at the Site, for the Owner or Owner s representative, one record copy of specifications, change orders, and other modifications, in good order and marked currently to record all changes made during work activities. The Contractor shall not be relieved of responsibility for any deviation from the requirements of the specifications unless the Contractor has specifically informed the Owner or Owner s representative in writing of such deviation at the time of submission and the Owner or Owner s representative has given written approval to the specific deviation. The Contractor shall not be relieved from responsibility for errors or omissions. 1.8 Mandatory Site Visit & Question/Answer Period A mandatory pre-bid Site walk will be held on March 25, 2014 between 9:00 am and 12:00 pm. Bidders not attending the pre-bid Site walk will be excluded from evaluation. Bidders will be responsible for confirming estimated quantities provided in these specifications prior to submitting bids. Bidders, if applicable, will be responsible for submitting any questions to the Owner in writing by March 28, The Owner will respond to all questions by all potential bidders by April 1, All Bidders are responsible for reviewing these specifications along with all Exhibits thoroughly and submitting any questions regarding these specifications or work activities described below to the Owner during the question/answer period discussed above. The Contractor that is awarded the contract will be expected to understand the work scope described in these specifications completely. 1.9 Owner s Right to Stop the Work If the Contractor fails to correct defective work as required or persistently fails to carry out the work in accordance with the contract documents, the Owner or Owner s representative, may order the Contractor to stop the work, or any portion thereof, until the cause for such order has been eliminated Owner s Right to Carry out the Work If the Contractor defaults or neglects to carry out the work in accordance with the contract documents and fails, within seven days after receipt of notice from the Owner or Owner s representative, to commence and continue correction of such default or neglect with diligence and promptness, the Owner may, after seven days following receipt by the Contractor of an additional written notice and without prejudice to any other remedy he may have, make good such deficiencies. In such case, an appropriate change order shall be issued, deducting from the payments then or thereafter due the Contractor the cost of correcting such deficiencies, including compensation for additional services made necessary by such default, neglect, or failure. If the payments then or thereafter due the Contractor are not sufficient to cover such amount, the Contractor shall pay the difference to the Owner Review of Contract Documents/Specifications The Contractor shall carefully study and compare the contract documents and shall at once report to the Owner any error, inconsistency, or omission he may discover. The Contractor shall not be McCabe Engineering & Contracting March Mansfield Foundry Asbestos Abatement Bid Specifications

8 liable to the Owner for any damage resulting from any such errors, inconsistencies, or omissions in the contract documents. The Contractor shall perform no portion of the work, at any time, without contract documents for such portion of the work Daily Logs The Contractor will be responsible for completing daily work and activity logs that include the following: 1. The name of each person, and description of the type of respiratory protection worn by each person entering containment or work area; 2. Descriptions of meetings or discussions regarding the job, special or unusual events, records of daily containment inspections, records of waste removal from containment, the chart from the recording manometer, and air monitoring results; and 3. A copy of this daily work log, signed by the Contractor must be submitted to the Owner or Owner s representative no later than the end of the following working day Submittals The Contractor shall submit the following to the Owner prior to commencing work: 1. The resumes of the person(s) who are employed by the Contractor and are licensed as asbestos abatement contractors in the State of Ohio where work will take place, and all accredited Supervisors that will be used in the asbestos abatement project. 2. A copy of the training certificates for all personnel to be employed on the asbestos abatement project. 3. A copy of Contractor's Respiratory Protection Program that includes: a. A statement of Respiratory Protection Training; b. Current copies of qualitative and/or quantitative respirator fit test results for all employees to be used on the asbestos abatement project. Respirator fit tests must be performed using respirator brands worn by Contractor's employees; and c. A copy of the current medical certificates for all employees to be used on the asbestos abatement project. The certificates must have the name of the medical center, name of attending physician, and signature of attending physician, and some indication that the individual is physically capable of performing asbestos abatement work. 4. Refer to Exhibit 3 for City Instructions to Bidder. McCabe Engineering & Contracting March Mansfield Foundry Asbestos Abatement Bid Specifications

9 2.1 General Preparation 2.0 Asbestos Abatement Proper preparation of the work area prior to asbestos abatement is crucial to the success of asbestos abatement projects. The following will be performed, but not limited to, by the Contractor in preparation of the work area: 1. Critical Barriers: All asbestos abatement work involving friable ACM and nonfriable ACM shall require the installation of critical barriers at all penetrations to the work area. 2. Pre-cleaning: Debris from work areas may need to be removed prior to ACM abatement activities can commence. Debris will not need to be disposed of by the Contractor, only relocated to access the ACM. 3. Polyethylene Sheeting: In general, all fixed objects and architectural surfaces in the work area must be protected from contamination during asbestos removal. 4. Pressure Differential: All work areas must be placed under a pressure differential of at least minus 0.02 inches of water column, with respect to outside areas, prior to disturbance of ACM. In instances where mastic materials are the only type of ACM disturbed in the work area, a pressure differential within the work area will not be necessary. Instead, the intake of a HEPA-filtered exhaust unit or HEPA-filtered vacuum may be placed close to the area where asbestos is being disturbed. 5. There is no power at the Site; therefore, the Contractor will need to provide temporary power and lighting and ensure safe installation of temporary power sources and equipment per applicable electric code requirements. There is no water at the Site; therefore, the Contractor will need to bring water to the Site. 2.2 Preparation for Friable or Nonfriable ACM The following will be performed, but not limited to, by the Contractor in preparation of abating friable or nonfriable ACM: 1. Post warning signs and barrier tape in and around work area as required by all applicable regulatory agencies. 2. Seal off all openings, including but not limited to: corridors, doorways, elevators, skylights, ducts, grills, diffusers, and any other penetrations of work areas 3. Doorways and corridors that will not be used for passage during work must be sealed with critical barriers. These seals must be left in place until final air testing is complete and the results received and approved. Allowances must be made for emergency exits. 4. If appropriate, cover surfaces in the proposed work area, which do not require asbestos removal, with polyethylene sheeting in the following manner: a. Cover walls or erect temporary walls with 2 layers of (4 mil minimum thickness) polyethylene sheeting sealed with tape. This sheeting must be secured by staples and tension nails as necessary to maintain the integrity of containment throughout removal and testing process. The two layers of polyethylene sheeting must be placed so the upper layer can be removed without damaging the integrity of the lower layer. b. Cover floors with 2 layers of (6 mil minimum thickness) polyethylene sheeting sealed with tape, when appropriate. The floor covering must extend at least 12" up the wall to contain leakage. The wall covering must overlap the floor covering. McCabe Engineering & Contracting March Mansfield Foundry Asbestos Abatement Bid Specifications

10 c. Cover ceilings with 2 layers of (4 mil minimum thickness) polyethylene sheeting, sealed with tape, when appropriate. This sheeting must be secured in a manner that shall maintain the integrity of containment throughout removal and testing process. d. For work areas that do not have an adequately flat surface, or have extensive mechanical and/or electrical fixtures attached to the ceiling. The Contractor shall perform initial cleaning of the exposed surfaces at the ceiling prior to removal, and perform wet-cleaning and HEPA-vacuuming during final cleanup. The ceiling area shall be encapsulated prior to final air testing. 2.3 ACM Types, Quantities & Locations The following is a summary of the ACM types, quantities, and locations described in the ACM survey that requires removal by the Contractor: 1. Black mastic under brown floor tile, approximately 450 square feet in Building 61; 2. Black mastic under brown floor tile, approximately 1,440 square feet in Building 39A; 3. 2 Pipe insulation, approximately 40 linear feet in Building 33A; 4. 4 Pipe insulation, approximately 100 linear feet in Building 33; 5. 9 x 9 Green floor tile, approximately 240 square feet in Building 38; 6. Black mastic under brown 12 x 12 floor tile, approximately 1,600 square feet in Building 38; 7. Transite ceiling, approximately 500 square feet in Building 33B1; 8. Pipe insulation, approximately 30 linear feet in Building 33B1; and 9. Transite siding, approximately 14,560 square feet on Building 58, 35A, 33A, 33B, and 33B1. a. Transite siding is located along the exterior and interior walls depending on the building. Please refer to Figure 2 for a Location of Asbestos Map. The condition of the ACM referenced above is likely to be in worse condition since the ACM Survey due to weather and vandalism. Therefore, ACM may no longer be in its original position and now located on the floor beneath its original position. 2.4 ACM Removal Process Asbestos Removal, Friable Materials The Contractor will perform, but is not limited to, the following procedures when removing friable ACM: 1. Prepare Site per Section 2.1 and Spray ACM with amended water using spray equipment capable of providing a mist application to reduce the release of fibers. Saturate friable ACM sufficiently to wet the substrate without causing excessive wetting, dripping, or delamination of the material. 3. Spray the asbestos ACM repeatedly during removal process to maintain wet condition and minimize asbestos fiber dispersion. The spraying must not be used as a technique to remove or dislodge ACM. 4. Remove saturated ACM in small sections. As the ACM is removed pack the material in sealable 6 mil polyethylene bags and place in appropriately labeled containers for McCabe Engineering & Contracting March Mansfield Foundry Asbestos Abatement Bid Specifications

11 transport. Material must be placed in containers in a prompt manner consistent with federal, state, and local regulations. 5. Waste Load-out Procedure a. Seal bags or containers. Clean external surfaces of bags or containers thoroughly by wet cleaning in the work area. b. Move bags or containers to washroom, wet-clean each container thoroughly, and move to clean room area pending removal to uncontaminated areas. The material must be placed in a clean bag or container as it exits the washroom and enters clean room area. c. Ensure that containers are removed from clean room areas by workers who have entered from uncontaminated areas, dressed in clean coveralls. Ensure that workers do not enter from uncontaminated areas into washroom or work area. d. When disposal bags are used, the bagged material must be placed within a second bag in equipment decontamination unit. The second, outer bag must be labeled with all applicable warnings and D.O.T. labeling. 6. Secondary Removal a. After completion of gross removal work, all surfaces from which asbestos has been removed must be wet-brushed with a wire brush and/or wet-cleaned by an equivalent method to remove all visible material. During this work the surfaces being cleaned must be kept wet Asbestos Removal, Nonfriable Materials The Contractor will perform, but is not limited to, the following procedures when removing nonfriable ACM: 1. Prepare site as per section 2.1 and Wet nonfriable ACM with amended water and remove with appropriate equipment. 3. Spray the ACM repeatedly during removal process to maintain wet condition and minimize asbestos fiber dispersion. The spraying must not be used as a technique to remove or dislodge ACM. 4. Remove material in small sections. As it is removed place the material in sealable 6 mil polyethylene bags and place in appropriately labeled container for transport. Material must be placed in containers in a prompt manner consistent with federal, state, and local regulations. 5. Waste Load-out Procedure a. Refer to Section Secondary Removal a. Refer to Section Asbestos Removal, Mastic The Contractor will perform, but is not limited to, the following procedures when removing mastic: 1. Apply solvent to remaining mastic and allow an appropriate period of time for the solvent to dissolve the mastic. 2. Remove mastic floor tile material in small sections. As the mastic is removed place the material in sealable 6 mil polyethylene bags and place in appropriately labeled container McCabe Engineering & Contracting March Mansfield Foundry Asbestos Abatement Bid Specifications

12 for transport. Material must be placed in containers in a prompt manner consistent with federal, state, and local regulations. 3. Refer to Section Asbestos Removal, Exterior Transite Siding The Contractor will perform, but is not limited to, the following procedures when removing transite siding: 1. Provide suitable tools for removal of transite siding. 2. For transite siding, spray panels with amended water using spray equipment capable of providing a mist application to reduce the release of fibers. Saturate the transite siding sufficiently to wet the material without causing excess dripping. 3. Remove wet transite siding in small sections. As the transite siding is removed wrap the material in 6 mil polyethylene sheeting and place in appropriately labeled containers lined with 6 mil polyethylene sheeting for transport. 4. Transite siding must be removed carefully and in complete sections. Breakage of the panels must be minimized, and must not be used as a method of removal without written approval from the Owner or Owner s representative. 2.5 Preparation for Glove Bag Procedure 1. Post warning signs and barrier tape in and around work area as required by all applicable regulatory agencies. 2. Seal vents within work area with, at least, tape and polyethylene sheeting during the work. 3. Cover areas beneath and adjacent to the proposed work using 6 mil polyethylene sheeting, as appropriate. Cover scaffolding with at least one layer of 6 mil polyethylene sheeting, when appropriate. 4. Prepare curtained doorways at entrances to and exits from work area Asbestos Removal with Glove Bag The Contractor will perform, but is not limited to, the following procedures when removing ACM with a glove bag: 1. Install glove bag according to manufacturer s recommendations. 2. Cut covering on insulation along the top seam to allow wetting of the insulation, and cut cover all around section to be removed. 3. Remove ACM in small sections. Lower the insulation carefully in the bottom of the glove bag. Do not drop material. One glove bag must be used for each section of ACM to be removed. Sliding or re-use of a single glove bag is strictly prohibited. Use appropriate size bag for the dimensions of the material to be removed to ensure economy of materials. 4. Prior to removal of the glove bag, ensure that all surfaces from which asbestos has been removed are clean of all visible material, and that the upper portion of the bag is clean of all visible waste. Spray all surfaces and tools in the glove bag with amended water. Wipe all sections of pipe with rag or appropriate material. Wipe upper section of bag as well. 5. Use appropriate encapsulant on all surfaces inside the bag. 6. Place tools inside sleeves of glove bag and isolate from interior of glove bag. Collapse bag using HEPA-filtered vacuum. Squeeze and twist bag at mid-level to isolate waste McCabe Engineering & Contracting March Mansfield Foundry Asbestos Abatement Bid Specifications

13 from upper portion of bag. Seal bag with duct tape or locking ties. Vacuum the unsealed upper portion. Keep HEPA-filtered vacuum connected until the glove bag is removed. Cut the glove bag along the top and sides, and then remove from pipe. Cut off isolated sleeves containing any tools or supplies from bag and place in bucket of water. Clean the tools in equipment room of decontamination unit. 7. Disposal of glove bag, material, and waste water (Refer to Section ) McCabe Engineering & Contracting March Mansfield Foundry Asbestos Abatement Bid Specifications

14 3.1 Inspections Prior to and During Work 3.0 Inspections, Management, & Monitoring Contractor shall make all work areas available to inspection at all times. Each work area will be inspected by the Owner or Owner s representative accompanied by Contractor: 1. Immediately after initial cleaning has been completed and prior to the application of polyethylene sheeting to exposed surfaces. 2. Immediately prior to the commencement of removal of ACM (after preparation of work area is complete). 3. After removal is complete but prior to the application of any encapsulant to the exposed substrates, and pre-encapsulation air testing. 4. Regular inspections of the HEPA-filtered ventilation system will be performed by the Owner or Owner s representative to ensure filters are not excessively loaded with particulate debris, and are properly seated in HEPA-filtered exhaust units. 3.2 Final Visual Inspections If Owner or Owner s representative finds visible accumulations of asbestos debris in work area after the completion work, the Contractor shall repeat wet-cleaning until work area is in compliance, at Contractor's expense. When an inspection by the Owner or Owner s representative in the presence of Contractor determines that the area is free of accumulations of dust and visible asbestos debris and the final air clearance has been met, decontamination unit shall be removed, the area thoroughly wetcleaned, and materials from equipment room and shower room disposed of as contaminated waste. A final visual inspection will be made after all Contractors materials have been removed from work area and all removal, encapsulation, disposal, and related work is completed. Work area must be well lighted for inspection by Owner or Owner s representative. Insufficient lighting may result in delay of the final visual inspection. All polyethylene sheeting must be removed from work area, with the exception of critical barriers, and decontamination unit. HEPA-filtered exhaust units must remain operational, and pressure differential maintained until final clearance by Transmission Electron Microscopy (TEM) or phase contrast microscopy (PCM) is obtained. 3.3 Air Monitoring General The Contractor is responsible for all air sampling required by federal, state, and local agencies. Personal, area, and pre-encapsulation air samples will be analyzed by an NVLAP- McCabe Engineering & Contracting March Mansfield Foundry Asbestos Abatement Bid Specifications

15 accredited laboratory using NIOSH method 7400 using PCM. In some cases, PCM may be used for final air testing. Final air samples will be analyzed by a laboratory accredited by NVLAP for TEM, using the AHERA Mandatory Transmission Electron Microscopy Method in Appendix A of 40 CFR 763, subpart E Background Air Testing Background air testing will be carried out by the Contractor prior to initiation of work in order to establish background levels of contamination. If air monitoring, during work by the Contractor, shows an increase in airborne fiber concentrations outside containment system, work shall cease until the source of the contamination is found and remedied to the Owner s or Owner s representative satisfaction. Any areas that have been contaminated as a result of Contractor's work shall be cleaned by Contractor at the expensive of the Contractor. Background air samples will be analyzed by PCM. TEM analysis of questionable samples will be made available at the expense of Contractor should he request it Personal Air Sampling Personal air monitoring will be performed by the Contractor and consist of: 1. An 8 hour time weighted average (TWA) for samples collected on 25% of the work force during each 8 hour shift for the duration of the project. 2. Continuous personal monitoring to be conducted during preparation, removal, and final cleanup, unless Type C pressure demand respiratory protection is used. 3. Excursion limit or short term exposure limit (STEL) sampling shall be performed during all phases of the asbestos abatement project to establish the STEL for each job function Conditions for Final Air Testing Final air testing shall take place when removal is complete, the polyethylene sheeting not necessary to the integrity of containment removed, and a visual inspection of work area shows that work area is clean and dry Air Clearance Criteria All clearance samples must pass the criteria set forth by applicable standards Final Air Testing After work area has met the 0.01 fibers/cc standard for the pre-encapsulation test, final air testing will be conducted and analyzed by TEM, when the amount of ACM removed in work area is greater than 160 square feet or 260 linear feet. Final air testing will consist of five TEM samples inside work area and five TEM samples outside work area. The sampling procedures and guidelines in EPA 40 CFR 763 part III will be followed. McCabe Engineering & Contracting March Mansfield Foundry Asbestos Abatement Bid Specifications

16 When the amount of ACM removed in work area is less than 160 square feet or 260 linear feet, the results of the pre-encapsulation PCM air test will be considered as the criteria for Contractor compliance Final Air Testing: Exterior Areas Final air testing will not be required for exterior, open work areas. Instead, a thorough and meticulous inspection will be performed by the Contractor with the Owner or Owner s representative present to determine Contractor compliance Final Air Testing: Glove Bag Procedure Each work area in which glove bag removal has occurred will be visually inspected by the Owner or Owner s representative prior to final air testing. Aggressive sampling procedures will not be used unless work areas are fully contained by critical barriers. Each work area will be tested and analyzed by the PCM method, using static sampling procedures. A TEM final air test of the general areas of glove bag removal may be performed at Owner s or Owner s representative discretion upon failure of a PCM final Failure of Final Air Tests When the results of the final air test show values of airborne asbestos in excess of the final air standard, the Contractor must re-clean work area. The final air testing procedure shall then be repeated at Contractor's expense. 3.4 Completion Upon completion of the asbestos abatement project, the Contractor must submit the following to the Owner or Owner s representative: a. All disposal receipts for asbestos-containing materials acquired during the asbestos abatement project; b. A copy of all daily logs, sign-in sheets, and daily reports; c. The original daily chart recordings from manometers used during the asbestos abatement project; d. A list of the names and signatures of all persons involved in the asbestos removal. Include state of accreditation and accreditation number for each person; e. A certification of compliance statement that all asbestos-containing materials related to these specifications have been removed and disposed of in accordance with all applicable federal, state, and local regulations for asbestos abatement; f. All analytical and air monitoring results; and g. All submittals to the Owner or Owner s representative are expected to be neat, complete, accurate, and readable. McCabe Engineering & Contracting March Mansfield Foundry Asbestos Abatement Bid Specifications

17 After final inspections and final air testing are complete and the results known, the Owner or Owner s representative will advise Contractor of any additional requirements. When a work area fails either the inspection or the final air testing, the area must be re-cleaned, re-inspected and re-tested. The sequence of re-cleaning and re-testing shall continue until the area passes the inspection and the final air test. McCabe Engineering & Contracting March Mansfield Foundry Asbestos Abatement Bid Specifications

18 4.0 Bid Information This project is being funded under a State of Ohio Clean Ohio Assistance Fund grant, and prevailing wage is not applicable to the distribution of funds under the City s Agreement with the State. The anticipated start date for the project is April 28, 2014 with a project completion date of May 30, One original and one copy of the Contractor s sealed bid will be due to the City of Mansfield on April 4, A bid bond in the amount of 10% of the total estimated project cost will be required of the Contractor. The Contractor shall provide copies of their current certificate of insurance and current worker s compensation certificate with bids. Bids must be completed on the bid form provided in Exhibit 2 and become the property of the Owner once submitted, along with all other supporting documents required of the bidders. The Owner reserves the right to accept/reject any and all bids. All bids are to be submitted by 12:00 pm on April 4, 2014, in which all the bids will be opened and a Contractor will be selected. Sealed bids will be sent to the following address: Office of Economic Development 30 North Diamond Street 8th Floor Mansfield, Ohio McCabe Engineering & Contracting March Mansfield Foundry Asbestos Abatement Bid Specifications

19 Figure 1 Site Location Map

20

21 Figure 2 Location of Asbestos Map

22 Legend PPB Fence Line PPB Property Boundary Rocky Fork Mohican River VAP VAP VAP Property Boundary PPB Transite Siding (Approximately 14,560 sq') VAP VAP PPB PPB/VAP N MAIN STREET 60' R/W (SR 13) Building 47 (Firebrick Shed) Building 41 (Sand Storage) (Quonset Hut) VAP PPB Scale Scale Building Concrete Ramp Building 32 Elv. (Core Building) Building 32A (Manufacturing) PPB Building 63 (Shipping & Receiving) Building 39-2 (Warehouse/QC) Building 39A (Manufacturing) Building 61 (Maintenance & Parts) Offices 450 Square Feet of Black Mastic Under Brown Floor Tile Building 39-1 (Warehouse/QC) R.R. Offices 40 Linear Feet of 2" Pipe Insulation 100 Linear Feet of 4" Pipe Insulation Building 33 (Manufacturing) Building 38 (Offices) Building 35 (Factory) Building 34 (Factory) 240 Square Feet of Green 9"x9" Floor Tile 1,600 Square Feet of Black Mastic Under Brown 12"x12" Floor Tile Building 33A (Factory) Building 35A (Annealing Room Extension) Building 33B (Factory) Building 33B1 (Factory) Electrical Substation 500 Square Feet of Transite Ceiling 30 Linear Feet of Pipe Insulation VAP VAP PPB/VAP PPB/VAP PPB/VAP Crane Gantry Electrical Substation PPB Rocky Fork Mohican River VAP Harker St 1,440 Square Feet of Black Mastic Under Brown Floor Tile Building 36 (Soft Metal Finishing) PPB Building 58 (Manufacturing) PPB/VAP Building 37 (Compressor Building) PPB/VAP Engineering & Contracting 3470 Brecksville Road Richfield, Ohio Mansfield Foundry 500 North Main Street Mansfield, Ohio Location of Asbestos Map DRAWN KDN DATE APPROVED - SCALE 1" = 120' PROJECT NO FIGURE 2

23 Exhibit 1 ACM Survey

24 Asbestos Containing Materials Survey For the: Former Mansfield Foundry 500 North Main Street Mansfield, Ohio Prepared for: City of Mansfield 30 North Diamond Street Mansfield, Ohio Prepared By: McCabe Engineering & Contracting 3470 Brecksville Road Richfield, Ohio November 2003

25 Introduction McCabe Engineering & Contracting was contracted by the City of Mansfield to perform a predemolition/renovation asbestos survey of the Former Mansfield Foundry Property located at 500 North Main Street, Mansfield, Richland County, Ohio. Please see Figure 1 for site location. The survey was conducted in order to identify and quantify the potential Asbestos Containing Materials (ACM) at the facility. Mr. Jim Smart conducted an initial reconnaissance of the site in August Samples were obtained from readily observable suspected ACM and transported to EA Group, Mentor, Ohio for analysis. The results of the preliminary sampling effort have been included in this report. Mr. Jim Smart (Certified Asbestos Hazard Evaluation Specialist, # 32566) and Edward M. McCabe of McCabe conducted the asbestos survey on September 10, The survey was conducted using non-destructive methods of investigation. Bulk samples were taken of all accessible suspect-building materials and sent to Environmental Hazard Services, Richmond, Virginia, for analysis. A total of fifty-three (53) samples were taken during the course of the main site inspection and initial site reconnaissance. Of the samples analyzed, nine (9) samples were identified as containing asbestos above the regulatory limit of 1%. Two samples, B-61-1 Mastic and 02-1 Mastic, contained 2% Chrysotile and were subsequently point counted to more accurately identify the percentage of asbestos in each. The point count results returned asbestos levels at 1.00% for B61-1 Mastic and 7.25% for 02-1 Mastic. Samples containing more than 1% ACM are identified as: B61-1 Mastic Black adhesive mastic (under and adhered to floor tile) contained 2% Chrysotile, approximately 450 square feet present in Building 61. Due to the asbestos content being close to the regulatory limit of 1%, a point count was performed on this sample to verify the asbestos content of the sample. Point count results returned asbestos levels of exactly 1%, verifying the material to be ACM. B39-A2 Mastic Black adhesive mastic (under and adhered to floor tile) contained 5% Chrysotile, approximately 1,440 square feet is present in Building 39. Siding 1 (also sample #5 from preliminary reconnaissance) Exterior transite siding contained 20% Chrysotile, approximately 14,560 square feet of transite siding is present on the exterior of the facility. The transite starts at the northwest corner of Building 38 between 10 and 12 feet off the ground and extends south then east around the main structure and then to the north encompassing Buildings 35A, 33A, 33B, and 65. B33-1 Pipe insulation contained 35% Chrysotile, approximately 100 linear feet of 4-inch piping is present in Building 33. B33-2 Pipe insulation contained 30% Chrysotile, approximately 40 linear feet of 2-inch piping is present in Building Black adhesive mastic (under and adhered to floor tile) contained 2% Chrysotile, approximately 1,600 square feet is present in a second floor office located in the central portion of the main foundry structure. Due to the asbestos content being close to the regulatory limit of 1%, a point count was performed on this sample to verify the asbestos content of the sample. Point count results returned asbestos levels of 7%, well above the regulatory limit of 1%. 1

26 02-2 Green 9 x9 vinyl floor tile contained 5% Chrysotile, approximately 240 square feet is present in the second floor office of the main foundry structure. B65-1 Transite switchgear ceiling panels contained 40% Amosite, approximately 500 square feet is present in the sub-basement of building 68. The material is in very poor condition. #8 Pipe insulation contained 85% Chrysotile, approximately 30 linear feet was observed in Building 65 during an initial site walk conducted in August All sampling locations are exhibited on the site plan provided as Figure 2. The laboratory data from the subsequent analysis of all samples is provided as Table 1. The hard copy laboratory analytical reports are included as Attachment 1. Site photographs are provided in Attachment 2. Recommendations The sample methodology presumed a homogeneous material. That is to say it was presumed for this sampling event and subsequent report that all similar ceiling tile, siding, and vinyl floor tile (VFT) was the same. Four samples of VFT and mastic returned results above 1% rendering the material ACM. Two of the samples, B61-1 Mastic and 02-1 Mastic, were point counted to verify the asbestos content of each due to the original analytical results returning near 1%. Point count results retuned at 1% and 7% respectively, verifying both to be considered ACM. VFT and mastics, which adhere to their substrates, are listed as Category 1 non-friable materials. Category 1 non-friable materials do not need to be removed prior to demolition if the work area is kept adequately wet during the demolition activities. This would include the four samples of the floor tile and mastic that were identified as ACM. The sample of the transite siding, Siding-1, returned results of 25% Chrysotile, rendering the material ACM. Transite is considered Category 2 non-friable asbestos and would have to be removed prior to demolition activities or activities that may result in the material becoming friable. The piping insulation, samples B33-1, B33-2, and #8 (located in Building 65), present within the facility is considered friable asbestos. The material is listed in poor condition and no longer in use, therefore, should be scheduled for removal as time and funds are available. As renovations and/or demolition occur within the buildings, the probability of those materials to become more damaged is likely. Further, the switchgear ceiling tile located in the sub-basement of Building 65, sample B65-1, contained 40% Amosite and is also considered friable and listed in poor condition. The material should be scheduled for removal with the piping insulation. Now that ACM has been identified in the facility, if the buildings remain and re-development occurs and the asbestos is not removed, according to 29 CFR , a building owner has certain responsibilities to the employees that would perform work related to asbestos containing materials (Class III and IV work defined in Paragraph B, Definitions: and Paragraph K Section 9, Information and Training) and those employees which work adjacent to asbestos containing materials. As outlined in the above referenced standard, certain job tasks, which occur in the identified facility, need to be performed by individuals that have received a certain level of competent training (labeling of materials defined in Paragraph K, Communications of Hazards, Sections 7 and 8). 2

27 Further, the building owner/employer needs to identify/label the location of ACM (friable and non-friable) in the facilities in the form of a written or personal communication as well as actual labeling of accessible ACM and areas where it is likely that ACM will be encountered. Should redevelopment occur, a comprehensive Operations and Maintenance (O&M) program would need to be initiated pending the specific areas and work that would be occurring in the facility. The components of an O&M program are outlined in the Guidance for Controlling Asbestos Containing Materials in Buildings (EPA Purple Book). This document is published by the USEPA, Office of Pesticides and Toxic Substances (EPA 560/ , June 1985). Demolition of the on site structures would necessitate the removal of all of the identified friable asbestos (i.e. pipe wrap and transite ceiling tile) as well as the transite siding, which is considered Category 2 Non-friable requiring its removal due to the material becoming friable during demolition. The floor tiling and mastic samples, considered Category 1 non-friable asbestos, would not have to be removed prior to demolition activities. Limitations The conclusions and recommendations presented herein are based on the level of effort and investigative techniques referenced in the report. McCabe has conducted this investigation in a manner consistent with sound engineering practices and with professional judgment. No other warranty or guarantee, expressed or implied, is made. This report does not attempt to evaluate past or present compliance with Federal, State and Local environmental or land use laws and regulations. Furthermore, McCabe makes no guarantees regarding the completeness or accuracy of any information obtained in review of public or private files or previous investigations conducted at the site. Reliance or any use of this report by any one other than the City of Mansfield, for whom it was prepared, is prohibited. Reliance or use by any such third party without explicit authorization in the report does not make said third party a third party beneficiary. Any such unauthorized reliance on or use of this report, including any of the information or conclusions, will be at the third party's risk. No warranties or representations, expressed or implied in this report, are made to any such third party. 3

28 Figures

29

30 First Floor Office Third Floor Office Second Floor Office Building 32 Building 32A B32-A1 B64-1 Building 64 B64-2 B39-2 Building 61 B61-1 B61-2 B39-1 Building 39 B39-3 B39-A4 B39-A2 Building 39A B39-A3 B39-A1 Building 33 B33-1 B33-2 First, Second, and Third Floor Offices Building 34 Building 35 Building 36 Building 33A Building 33B Building 35A B65-1 Building 65 #8 Siding-1 Legend B39-A1 Transite Siding Asbestos Sample B38-2 B38-1 Building 38 Figure 2 Summary of Asbestos Sampling Locations Mansfield Foundry Property Mansfield, Ohio McCabe Engineering & Contracting November 2003

31 Table

32 Table 1: Summary of Asbestos Samples Results and Quantification Sample I.D. Location Shown on Figure 2 Description Est. Quantity Condition % Asbestos B64-1 Building 64 Yes White VFT 600 square feet Good NAD B64-1 Building 64 Yes Black Mastic 600 square feet Good NAD B64-2 Building 64 Yes Ceiling Tile 2'x4' Unknown Unknown NAD B61-1 Building 61 Yes Brown VFT 450 square feet Good NAD B61-1 Building 61 Yes Black Mastic 450 square feet Good 2% Chrysotile B61-2 Building 61 Yes Ceiling Tile 450 square feet Good NAD B39-1 Building 39 Yes Block Floor 8,000 square feet Good NAD B39-2 Building 39 Yes White 3'x5'x3/4" Sheeting 60 square feet Good NAD B39-3 Building 39 Yes Ceiling Plaster 2,000 square feet Good NAD B39A-1 Building 39 Yes Ceiling Tile 1,440 square feet Good NAD B39A-2 Building 39 Yes Brown VFT 1,440 square feet Good NAD B39A-2 Building 39 Yes Black Mastic 1,440 square feet Good 5% Chrysotile B39A-3 Building 39 Yes Ceiling Tile 1,440 square feet Good NAD B39A-4 Building 39 Yes Brown VFT 1,440 square feet Good NAD Siding - 1 (i.e. #5) Exterior Siding Yes Gray Cementitious 14,560 square feet Good 20% Chrysotile B32A-1 Building 32A Yes Piping Elbows 10 Elbows Good NAD B38-1 Building 38 Yes Pipe Insulation 250 linear feet Poor NAD B38-2 Building 38 Yes Ceiling Tile 900 square feet Good NAD B33-1 Building 33 Yes Pipe Insulation 100 linear feet 4" pipe Poor 35% Chrysotile B33-2 Building 33 Yes Pipe Insulation 40 linear feet 2" pipe Poor 30% Chrysotile rd Floor Office No Ceiling Tile 1,600 square feet Good NAD rd Floor Office No White VFT 12"x12" 1,600 square feet Good NAD rd Floor Office No Black Mastic 1,600 square feet Good NAD nd Floor Office No Brown VFT 12"x12" 1,600 square feet Good NAD nd Floor Office No Black Mastic 1,600 square feet Good 2% Chrysotile nd Floor Office No Green VFT 9"x9" 240 square feet Good 5% Chrysotile nd Floor Office No Brown Mastic 240 square feet Good NAD 01-1 First Floor Office No White VFT 18"x18" 800 square feet Good NAD 01-1 First Floor Office No Black Mastic 800 square feet Good NAD 01-2 First Floor Office No Beige VFT 12"x12" 2000 square feet Good NAD 01-2 First Floor Office No Black Mastic 2000 square feet Good NAD 01-3 First Floor Office No Gray VFT 12"x12" 1900 square feet Good NAD 01-3 First Floor Office No Black Mastic 1900 square feet Good NAD 01-4 First Floor Office No Brown VFT 12"x12" 200 square feet Good NAD 01-4 First Floor Office No Black Mastic 200 square feet Good NAD 01-5 First Floor Office No Ceiling Tile 2'x2' 1800 square feet Good NAD 01-6 First Floor Office No Ceiling Tile 2'x4' 1800 square feet Good NAD B65-1 Basement Yes Switch Gear Transite Ceiling 500 square feet Poor 40% Amosite #8 Building 65 Yes Pipe Insulation 30 linear feet Poor 85 % Chrysotile #1 Unknown No Unknown Unknown Unknown NAD #2 Unknown No Unknown Unknown Unknown NAD #3 Unknown No Unknown Unknown Unknown NAD #4 Unknown No Unknown Unknown Unknown NAD #5 (i.e. Siding -1) Exterior Siding Yes Gray Cementitious 14,560 square feet Good 20% Chrysotile #6 Unknown No Unknown Unknown Unknown NAD #7 Unknown No Unknown Unknown Unknown NAD #10 Unknown No Unknown Unknown Unknown NAD #11 Unknown No Unknown Unknown Unknown NAD #12 Unknown No Unknown Unknown Unknown NAD #13 Unknown No Unknown Unknown Unknown NAD #14 Unknown No Unknown Unknown Unknown NAD #15 Unknown No Unknown Unknown Unknown NAD #16 Unknown No Unknown Unknown Unknown NAD 1 of 1

Asbestos Abatement Work Plan for the Carter Carburetor Superfund Site

Asbestos Abatement Work Plan for the Carter Carburetor Superfund Site for the Prepared for: ACF Industries LLC 101 Clark Street St. Charles, Missouri 63301 Prepared by: AMEC Environment & Infrastructure, Inc. 15933 Clayton Road, Suite 215 Ballwin, Missouri 63011 Project

More information

SECTION 02 8213 ASBESTOS ABATEMENT

SECTION 02 8213 ASBESTOS ABATEMENT PART 1 GENERAL 1.01 RELATED DOCUMENTS A. Drawings and general provisions of Contract, including General and Supplementary Conditions and Division 1 specification sections shall apply to work of this section.

More information

ASBESTOS MANAGEMENT PROGRAM

ASBESTOS MANAGEMENT PROGRAM ASBESTOS MANAGEMENT PROGRAM Prepared By: Triumvirate Environmental Program Approval Developed: August 2011 Updated: June 2015 Associate Vice President of Public Safety & Administrative Services Date Associate

More information

ASBESTOS MANAGEMENT PROGRAM

ASBESTOS MANAGEMENT PROGRAM ASBESTOS MANAGEMENT PROGRAM September 2015 Asbestos Management Program Table of Contents I. Purpose II. III. IV. Definitions Identification of Asbestos Asbestos Sampling V. Notification and Labeling VI.

More information

University of Pittsburgh Safety Manual. EH&S Guideline Number: 01-007 ASBESTOS

University of Pittsburgh Safety Manual. EH&S Guideline Number: 01-007 ASBESTOS Page 1 of 5 The inhalation of asbestos fibers in excess amounts can lead to chronic lung disease. Our knowledge of these health effects comes from studies of workers exposed routinely to high concentrations

More information

ASBESTOS IN ROOFING SYSTEMS WORK PRACTICES AND DISPOSAL IN ASSOCIATION WITH ROOFING PROJECTS

ASBESTOS IN ROOFING SYSTEMS WORK PRACTICES AND DISPOSAL IN ASSOCIATION WITH ROOFING PROJECTS ASBESTOS IN ROOFING SYSTEMS WORK PRACTICES AND DISPOSAL IN ASSOCIATION WITH ROOFING PROJECTS 1.0 GENERAL 1.1 SUMMARY A. The following procedures apply to the project manual and drawings for asbestos in

More information

UNOFFICIAL. 1. Owner: Delaware Department of Transportation (DelDOT) WEBSITE

UNOFFICIAL. 1. Owner: Delaware Department of Transportation (DelDOT) WEBSITE SECTION 01013 - SUMMARY OF THE WORK - ASBESTOS ABATEMENT PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other

More information

Asbestos in the Workplace: A Guide to Removal of Friable Asbestos Containing Material

Asbestos in the Workplace: A Guide to Removal of Friable Asbestos Containing Material Asbestos in the Workplace: A Guide to Removal of Friable Asbestos Containing Material Revised November 21, 2013 Application Code of Practice Where asbestos is present or believed to be present in a workplace

More information

British Columbia Institute of Technology. BCIT Safety Manual ASBESTOS MANAGEMENT

British Columbia Institute of Technology. BCIT Safety Manual ASBESTOS MANAGEMENT BCIT Safety Manual Contents 1. Purpose... 3 2. Definitions... 3 2.1 Asbestos... 3 2.2 Asbestos Containing Material (ACM)... 3 2.3 Friable Material... 3 2.4 Low Risk Work Activity... 3 2.5 Moderate Risk

More information

OGS LIMITED ASBESTOS & LEAD SURVEY REPORT

OGS LIMITED ASBESTOS & LEAD SURVEY REPORT our people and our passion in every project OGS LIMITED ASBESTOS & LEAD SURVEY REPORT Building 44 Willard Drug Treatment Center 7116 County Road 132 Willard, NY Prepared for: NYSOGS 33 rd Floor, Corning

More information

Asbestos Work Permit Procedures

Asbestos Work Permit Procedures These procedures are to be followed by all persons required to perform the following work: Handling, installation or removal of non-friable manufactured products known to contain asbestos provided no sanding,

More information

Asbestos Inspection Project Procedure

Asbestos Inspection Project Procedure EOSMS 402 Date: 01/13/2014 Page 1 of 6 1) Purpose This document is intended to specify the scope of services required of Asbestos Contractor in asbestos inspection projects at Kennesaw State University

More information

ASBESTOS MANAGEMENT INTRODUCTION

ASBESTOS MANAGEMENT INTRODUCTION SECTION: II. General Hygiene/ Safety Chapter: 7. Asbestos Management Revision Date: 12/05/2013 Review Date: ASBESTOS MANAGEMENT INTRODUCTION PURPOSE This policy has been developed to ensure that hazardous

More information

UI Procedures for Asbestos Management

UI Procedures for Asbestos Management UI Procedures for Asbestos Management The University of Iowa Rev.12/12/2012 These procedures apply to employees and contractors involving the identification, work on, removal, or repair of asbestos-containing

More information

SPECIFICATION DIVISION 2 NUMBER SECTION DESCRIPTION DIVISION 02 EXISTING CONDITIONS SECTION 028214 ASBESTOS REMEDIATION FLOOR TILE AND MASTIC

SPECIFICATION DIVISION 2 NUMBER SECTION DESCRIPTION DIVISION 02 EXISTING CONDITIONS SECTION 028214 ASBESTOS REMEDIATION FLOOR TILE AND MASTIC ARCHITECTURE, ENGINEERING AND CONSTRUCTION P00000000 0000 DOCUMENTS ARCHITECTURE & ENGINEERING 326 East Hoover, Mail Stop B Ann Arbor, MI 48109-1002 Phone: 734-764-3414 Fax: 734-936-3334 SPECIFICATION

More information

North Carolina State University. Asbestos Management Plan

North Carolina State University. Asbestos Management Plan North Carolina State University 1.0 Introduction Purpose The purpose of this plan is to establish the polices and procedures to be used at North Carolina State University (NCSU) in the management of building

More information

Standards for Asbestos Abatement

Standards for Asbestos Abatement 19a-332a-1. Definitions Standards for Asbestos Abatement 19a-332a-1. Definitions The following definitions shall apply for the purpose of Section 19a-332a-1 to Section 19a-332a- 16 inclusive. (a) "Adequately

More information

Specifications for Asbestos Abatement

Specifications for Asbestos Abatement Specifications for Asbestos Abatement Virginia Department of Health Henry/Martinsville Health Department 295 Commonwealth Boulevard Martinsville, Virginia Prepared for City of Martinsville, Virginia 300

More information

CONTROL METHODS. There are five ways to control the release of asbestos fibers:

CONTROL METHODS. There are five ways to control the release of asbestos fibers: Control Methods CONTROL METHODS When asbestos containing materials are found in a building, the owner must decide which method or methods will be used to deal with the asbestos. The decision will be based

More information

How To Perform A Limited Asbestos Survey

How To Perform A Limited Asbestos Survey Limited Asbestos Survey Report Presented To: Barbara Wethington Project Manager Weston Solutions, Inc. 960 West Elliot Road, Suite 201 Tempe, Arizona 85284 Project: Southeast Corner of Arizona Highway

More information

ASBESTOS and LEAD-BASED PAINT INVESTIGATION TOWN OF ST. PAUL WILLIS BUILDING ST. PAUL, VIRGINIA

ASBESTOS and LEAD-BASED PAINT INVESTIGATION TOWN OF ST. PAUL WILLIS BUILDING ST. PAUL, VIRGINIA ASBESTOS and LEAD-BASED PAINT INVESTIGATION TOWN OF ST. PAUL WILLIS BUILDING ST. PAUL, VIRGINIA May 22, 2013 Robert R. Jones, Ph.D., REM, AHERA Asbestos Inspector, 5/22/13 Signature Date Asbestos Virginia

More information

EXHIBIT A SCOPE OF SERVICES

EXHIBIT A SCOPE OF SERVICES EXHIBIT A SCOPE OF SERVICES 1.0 INTRODUCTION Asbestos consulting services are required for Item/Segment No. 227775-1, SR-7 (US 441) from Fillmore Street to South of Stirling Road, Hollywood, Broward County,

More information

EVERYONE'S RESPONSIBILITY

EVERYONE'S RESPONSIBILITY EVERYONE'S RESPONSIBILITY Guidelines for an Asbestos Operations and Maintenance Program February 2007 Guidelines for an Asbestos Operations and Maintenance Program Workplace Safety & Health Division 200

More information

LEGAL REVIEW & UPDATE

LEGAL REVIEW & UPDATE LEGAL REVIEW & UPDATE There are lots of laws and regulations designed to protect workers, the general public, and the environment. However, not everyone follows the laws. Many people deliberately break

More information

asbestos management SECTION 21 SECTION CONTENTS ADDITIONAL READING Asbestos Management / Page1 / SECTION 21 TULANE UNIVERSITY

asbestos management SECTION 21 SECTION CONTENTS ADDITIONAL READING Asbestos Management / Page1 / SECTION 21 TULANE UNIVERSITY SECTION 21 asbestos management TULANE UNIVERSITY ENVIRONMENTAL HEALTH AND SAFETY POLICIES AND PROCEDURES MANUAL REVISION DATE: 9/1/03 Return to Table of Contents, EH&S Policies & Procedures Manual SECTION

More information

Addendum 1 Clarifications

Addendum 1 Clarifications Addendum 1 Clarifications Asbestos 1. Clarifications CONTRACTOR is instructed to incorporate standard abatement procedures as mandated by the Federal OSHA Construction Industry Standard; 29 CFR 1926.1101,

More information

ASBESTOS CONTAINING MATERIALS OPERATIONS & MAINTENANCE PLAN 2015

ASBESTOS CONTAINING MATERIALS OPERATIONS & MAINTENANCE PLAN 2015 ASBESTOS CONTAINING MATERIALS OPERATIONS & MAINTENANCE PLAN 2015 Prepared For: (School Name) PREPARED BY: DIOCESE OF JOLIET ENVIRONMENTAL OFFICE FOR ANY ENVIRONMENTAL RELATED EMERGENCY CONTACT: RICHARD

More information

DIVISION 248 ASBESTOS REQUIREMENTS. Asbestos Emission Standards and Procedural Requirements 340-248-0250. Asbestos Abatement Project Exemptions

DIVISION 248 ASBESTOS REQUIREMENTS. Asbestos Emission Standards and Procedural Requirements 340-248-0250. Asbestos Abatement Project Exemptions DIVISION 248 ASBESTOS REQUIREMENTS Asbestos Emission Standards and Procedural Requirements 340-248-0250 Asbestos Abatement Project Exemptions (1) Any person who conducts or provides for the conduct of

More information

ADVANCED ENVIRONMENTAL ANALYSIS, INC. 25694 NELSON ROAD HEMPSTEAD, TEXAS 77445

ADVANCED ENVIRONMENTAL ANALYSIS, INC. 25694 NELSON ROAD HEMPSTEAD, TEXAS 77445 ADVANCED ENVIRONMENTAL ANALYSIS, INC. 25694 NELSON ROAD HEMPSTEAD, TEXAS 77445 August 3, 2010 PROJECT SPECIFICATIONS In accordance with the Texas Department of State Health Services Regulation 295.34,

More information

Asbestos Abatement Management Program. Facilities Operations and Development Environmental Health & Safety

Asbestos Abatement Management Program. Facilities Operations and Development Environmental Health & Safety Asbestos Abatement Management Program Facilities Operations and Development Environmental Health & Safety November 7, 2012 INTRODUCTIONS David Kos (EHS) Director of Environmental Affairs David Kehl (EHS)

More information

Preparing the Work Area

Preparing the Work Area Preparing the Work Area Work Area Preparation Objectives of Work Area Prep Sequence and Methods for Prep Engineering Controls: Negative Pressure Requirements, Equipment and Set-up Purpose of Area Prep

More information

ASBESTOS AWARENESS PLAN

ASBESTOS AWARENESS PLAN Asbestos Operations and Maintenance Program ASBESTOS AWARENESS PLAN Bryan V. Jandreau, Facilities Manager Dan Bouchard, Superintendent of Buildings Christina Theriault, Human Resource Coordinator Developed

More information

HART ENVIRONMENTAL RESOURCES

HART ENVIRONMENTAL RESOURCES HART ENVIRONMENTAL RESOURCES 262 Hedge Dr. Springfield, OH 45504 (937) 325-8777 (937) 324-0288 FAX ASBESTOS INSPECTION REPORT 933 Xenia Ave. Dayton, Ohio 45410 PREPARED FOR: Mr. Dennis Zimmer Montgomery

More information

Asbestos Management POLICY

Asbestos Management POLICY Asbestos Management POLICY All Asbestos Containment Material (ACM) removal activities shall comply with applicable federal, state, and local regulations. Areas of responsibility of Facilities Management

More information

SUBPART 6 - ASBESTOS SOURCES 2105.60 ASBESTOS ABATEMENT CONTRACTOR LICENSES

SUBPART 6 - ASBESTOS SOURCES 2105.60 ASBESTOS ABATEMENT CONTRACTOR LICENSES SUBPART 6 - ASBESTOS SOURCES 2105.60 ASBESTOS ABATEMENT CONTRACTOR LICENSES a. General. In addition to the accreditation and permit requirements under 2105.61 and 2105.62, respectively, of this Article,

More information

NDSU TABLE OF CONTENTS

NDSU TABLE OF CONTENTS NDSU TABLE OF CONTENTS 1.0 INTRODUCTION 2.0 DEFINITIONS AND DESCRIPTIONS 3.0 OPERATIONS AND MAINTENANCE PROCEDURES FOR ACM 4.0 FIBER RELEASE EPISODES 5.0 DEMOLITION INFORMATION 6.0 REMARKS 1.0 INTRODUCTION

More information

Characteristics/Applications

Characteristics/Applications Facilities Operations and Development Environmental Health & Safety 1314 Kinnear Rd. Columbus, Ohio 43212 Phone (614) 292-1284 Fax (614) 292-6404 http://fod.osu.edu The Ohio State University Asbestos Management

More information

Loss Control TIPS Technical Information Paper Series

Loss Control TIPS Technical Information Paper Series Loss Control TIPS Technical Information Paper Series Innovative Safety and Health Solutions SM Asbestos-Containing Material (ACM) In Buildings The presence of asbestos in buildings, particularly those

More information

Specifications for Removal and Replacement of Water Damaged/Mold Impacted Materials

Specifications for Removal and Replacement of Water Damaged/Mold Impacted Materials Specifications for Removal and Replacement of Water Damaged/Mold Impacted Materials Park Potomac Place 12500 Park Potomac Avenue Potomac, Maryland 20854 KEM Project # 21703 Prepared for: Park Potomac Place

More information

Asbestos Management. 2. Introduction. Contents

Asbestos Management. 2. Introduction. Contents Asbestos Management Contents 1. Policy 2. Introduction 3. Scope 4. Definitions 5. Asbestos Inventory and Identification 6. Inspection 7. Access Control 8. Repair and Maintenance of Asbestos-Containing

More information

Asbestos. from the Home. Removing. Read this booklet for:

Asbestos. from the Home. Removing. Read this booklet for: Removing Asbestos from the Home Read this booklet for: steps and care you should take if your home has asbestos-containing material (ACM) advice about protective gear. How to get ACM removed from your

More information

AHERA 3-Year Asbestos Re-Inspection

AHERA 3-Year Asbestos Re-Inspection AHERA 3-Year Asbestos Re-Inspection Denver 940 Fillmore Street Denver, Colorado 80206 Report Date: November 20, 2013 OEI Project No. 13.159 Prepared For: John Lewis Denver 940 Fillmore Street Denver, CO

More information

THE RICHARD STOCKTON UNIVERSITY OF NEW JERSEY ASBESTOS ABATEMENT CONTINGENCY PLAN. February 2015

THE RICHARD STOCKTON UNIVERSITY OF NEW JERSEY ASBESTOS ABATEMENT CONTINGENCY PLAN. February 2015 THE RICHARD STOCKTON UNIVERSITY OF NEW JERSEY ASBESTOS ABATEMENT CONTINGENCY PLAN February 2015 Risk Management and Environmental Health and Safety Office RMEHS ASBESTOS ABATEMENT CONTINGENCY PLAN Table

More information

have been provided with information on whether they do or do not contain asbestos before starting work;

have been provided with information on whether they do or do not contain asbestos before starting work; Health Effects of Asbestos If your work involves possible exposure to asbestos, you should: be aware of the risks from asbestos exposure; understand the importance of keeping exposure as low as possible;

More information

ALBERT EINSTEIN COLLEGE of MEDICINE of YESHIVA UNIVERSITY. MANAGING ASBESTOS at EINSTEIN. Prepared by: Department of Environmental Health and Safety

ALBERT EINSTEIN COLLEGE of MEDICINE of YESHIVA UNIVERSITY. MANAGING ASBESTOS at EINSTEIN. Prepared by: Department of Environmental Health and Safety ALBERT EINSTEIN COLLEGE of MEDICINE of YESHIVA UNIVERSITY Prepared by: Department of Environmental Health and Safety Revised: August, 2013 ALBERT EINSTEIN COLLEGE of MEDICINE of YESHIVA UNIVERSITY DEPARTMETN

More information

Building Owners Responsibilities for Asbestos

Building Owners Responsibilities for Asbestos Building Owners Responsibilities for Asbestos August 2012 Minnesota Department of Labor and Industry Occupational Safety and Health Division This material can be provided to you in a different format (Braille,

More information

TAMPA ELECTRIC COMPANY ENERGY SUPPLY ASBESTOS AWARENESS PROGRAM

TAMPA ELECTRIC COMPANY ENERGY SUPPLY ASBESTOS AWARENESS PROGRAM ASBESTOS AWARENESS PROGRAM TABLE OF CONTENTS TITLE PAGE # PURPOSE / INTRODUCTION 1 RESPONSIBILITY 2 EMPLOYEE TRAINING AND DOCUMENTATION 2-4 MEDICAL SURVEILLANCE 4 UNPLANNED DISTRUBANCE OF ASBESTOS CONTAINING

More information

SPECIFICATION DIVISION 2 NUMBER SECTION DESCRIPTION DIVISION 02 EXISTING CONDITIONS SECTION 028215 ASBESTOS REMEDIATION ROOFING MATERIAL

SPECIFICATION DIVISION 2 NUMBER SECTION DESCRIPTION DIVISION 02 EXISTING CONDITIONS SECTION 028215 ASBESTOS REMEDIATION ROOFING MATERIAL ARCHITECTURE, ENGINEERING AND CONSTRUCTION P00000000 0000 DOCUMENTS ARCHITECTURE & ENGINEERING 326 East Hoover, Mail Stop B Ann Arbor, MI 48109-1002 Phone: 734-764-3414 Fax: 734-936-3334 SPECIFICATION

More information

Asbestos Containing Material MANAGEMENT PLAN

Asbestos Containing Material MANAGEMENT PLAN Asbestos Containing Material MANAGEMENT PLAN Introduction Extensive research has shown exposure to asbestos containing material (ACM) when it becomes airborne (commonly referred to as friable) poses a

More information

REMOVAL OF ASBESTOS-CONTAINING MASTIC. The Sherman School 2 Route 37 East Sherman, Connecticut 06784

REMOVAL OF ASBESTOS-CONTAINING MASTIC. The Sherman School 2 Route 37 East Sherman, Connecticut 06784 REMOVAL OF ASBESTOS-CONTAINING MASTIC at The Sherman School 2 Route 37 East Sherman, Connecticut 06784 OWNER: Town of Sherman 9 Route 39 North P.O. Box 39 Sherman, Connecticut 06784 (860)355-1139 State

More information

IWU PHYSICAL PLANT SAFETY PROGRAM. Toxic and Hazardous Substances, Title 29 Code of Federal Regulations (CFR) Part 1910.1001, Subpart Z Asbestos

IWU PHYSICAL PLANT SAFETY PROGRAM. Toxic and Hazardous Substances, Title 29 Code of Federal Regulations (CFR) Part 1910.1001, Subpart Z Asbestos STANDARDS Toxic and Hazardous Substances, Title 29 Code of Federal Regulations (CFR) Part 1910.1001, Subpart Z Asbestos 1. INTRODUCTION IWU has a responsibility to provide a safe environment for students,

More information

Sprayed vermiculite ceiling coating management plan, Condell Park High School, Condell Park, NSW

Sprayed vermiculite ceiling coating management plan, Condell Park High School, Condell Park, NSW Sprayed vermiculite ceiling coating management plan, Condell Park High School, Condell Park, NSW August 2006 NSW Department of Commerce Parsons Brinckerhoff Australia Pty Limited ACN 078 004 798 and Parsons

More information

Questions & Answers (Q & A) Regarding Asbestos Treatment with the Fire Suppression and Renovation Project

Questions & Answers (Q & A) Regarding Asbestos Treatment with the Fire Suppression and Renovation Project Questions & Answers (Q & A) Regarding Asbestos Treatment with the Fire Suppression and Renovation Project The Watergate Community is currently in the process with the fire suppression and interior renovations

More information

ASBESTOS CONTROL PROGRAM

ASBESTOS CONTROL PROGRAM WESTERN UNIVERSITY OCCUPATIONAL HEALTH AND SAFETY ASBESTOS CONTROL PROGRAM Last Update: August 2012 TABLE OF CONTENTS 1.0 INTRODUCTION AND SCOPE... 3 2.0 DEFINITIONS... 4 3.0 HISTORICAL INFORMATION...

More information

(A) All asbestos-containing waste material shall be deposited as soon as is practical by the waste generator at:

(A) All asbestos-containing waste material shall be deposited as soon as is practical by the waste generator at: 3745-20-05 Standard for asbestos waste handling. [Comment: For dates of non-regulatory government publications, publications of recognized organizations and associations, federal rules, and federal statutory

More information

ASBESTOS CONTROL PLAN

ASBESTOS CONTROL PLAN ASBESTOS CONTROL PLAN POLICY It is the long term plan of Emily Carr University to have an asbestos free workplace. In the interim, The University plans to manage asbestos hazards based on prioritization

More information

Click to edit Master title style Maricopa County Asbestos NESHAP Overview. Valerie Brodeur Asbestos NESHAP Inspector

Click to edit Master title style Maricopa County Asbestos NESHAP Overview. Valerie Brodeur Asbestos NESHAP Inspector Click to edit Master title style Maricopa County Asbestos NESHAP Overview Valerie Brodeur Asbestos NESHAP Inspector Click to edit Master title style Some Asbestos Facts Asbestos is a proven human carcinogen

More information

Miami University s Asbestos Operations & Maintenance Program Administered by

Miami University s Asbestos Operations & Maintenance Program Administered by Miami University s Asbestos Operations & Maintenance Program Administered by ENVIRONMENTAL SAFETY & RISK MANAGEMENT 529-2829 Table of Contents Purpose 2 Personnel Covered Under the Asbestos Mangement Plan

More information

100 North Senate Avenue, Indianapolis, IN 46204 Phone: (317) 308-3103 Toll Free: (800) 451-6027

100 North Senate Avenue, Indianapolis, IN 46204 Phone: (317) 308-3103 Toll Free: (800) 451-6027 GUIDANCE OLQ GENERAL ID #003-02-SW INDIANA DEPARTMENT OF ENVIRONMENTAL MANAGEMENT OFFICE OF LAND QUALITY ASBESTOS HANDLING AND DISPOSAL REQUIREMENTS www.idem.in.gov Mitchell E. Daniels, Jr. Thomas W. Easterly

More information

ASBESTOS MANAGEMENT PLAN

ASBESTOS MANAGEMENT PLAN ASBESTOS MANAGEMENT PLAN SAN JOSE STATE UNIVERSITY Environmental Health & Occupational Safety Asbestos Management Plan 1.0 Introduction 2.0 Policy 3.0 Responsibilities 4.0 Contract Administration 5.0 In-House

More information

June 27, 2013. Project GSA1570019. Rhonda Rance U.S. General Services Administration 450 Golden Gate Avenue, Floor 4 San Francisco, California 94102

June 27, 2013. Project GSA1570019. Rhonda Rance U.S. General Services Administration 450 Golden Gate Avenue, Floor 4 San Francisco, California 94102 June 27, 2013 Project GSA1570019 Rhonda Rance U.S. General Services Administration 450 Golden Gate Avenue, Floor 4 San Francisco, California 94102 Subject: Determination of Asbestos Conditions Former USDA

More information

Approved by: UBC ACT Committee

Approved by: UBC ACT Committee The University of British Columbia Asbestos Safety Policy Prepared by: Russell R. English Policy Approved by: UBC ACT Committee Issue Date: April 1, 2004 Replaces: March, 1989 I-B-05 1.0 Policy: This policy

More information

Syracuse University s Guidelines for Work Involving Materials Containing Trace Asbestos (Asbestos at a Concentration Less than 1%)

Syracuse University s Guidelines for Work Involving Materials Containing Trace Asbestos (Asbestos at a Concentration Less than 1%) Syracuse University s Guidelines for Work Involving Materials Containing Trace Asbestos (Asbestos at a Concentration Less than 1%) I. Asbestos Survey Requirements Prior to performing any construction,

More information

The Richard Stockton University ASBESTOS MANAGEMENT PLAN

The Richard Stockton University ASBESTOS MANAGEMENT PLAN The Richard Stockton University ASBESTOS MANAGEMENT PLAN January 2015 Asbestos Management Plan Table of Contents I. Introduction II. III. IV. Definitions Identification of Asbestos Notification and Labeling

More information

Draft ABCA : USEPA 2015 Brownfields Cleanup Grant Application for Former Hudepohl Brewery Site by Port of Greater Cincinnati Development Authority

Draft ABCA : USEPA 2015 Brownfields Cleanup Grant Application for Former Hudepohl Brewery Site by Port of Greater Cincinnati Development Authority Analysis of Brownfield Cleanup Alternatives (ABCA) for Hudepohl Brewery Site Introduction & History The Port of Greater Cincinnati Development Authority (Port Authority) has developed a draft proposal

More information

NARRATIVE REPORT. The Asbestos Bulk Sample Results Table includes asbestos sampling data.

NARRATIVE REPORT. The Asbestos Bulk Sample Results Table includes asbestos sampling data. NARRATIVE REPORT 1.0 BUILDING INFORMATION The original date of construction for Construction Management Engineering was not immediately available; the building has had no major renovations. Construction

More information

DUST AND DEBRIS MANAGEMENT PROCEDURES HPD HOUSING REHABILITATION PROGRAMS

DUST AND DEBRIS MANAGEMENT PROCEDURES HPD HOUSING REHABILITATION PROGRAMS DUST AND DEBRIS MANAGEMENT PROCEDURES HPD HOUSING REHABILITATION PROGRAMS Dust and Debris Management Procedures refers to preventive measures that shall be undertaken by the contractor to prevent exposure

More information

Wellesley College Asbestos Management Program

Wellesley College Asbestos Management Program Wellesley College Asbestos Management Program Table of Contents Page Policy 2 Impacts of Asbestos Containing Materials (ACM)... 3 Compliance... 3 Objectives... 4 Operational Controls Standard Operating

More information

ASBESTOS OPERATIONS AND MAINTENANCE PLAN

ASBESTOS OPERATIONS AND MAINTENANCE PLAN UNIVERSITY OF FLORIDA ASBESTOS OPERATIONS AND MAINTENANCE PLAN Administered by: Environmental Health and Safety Building 179 PO Box 112190 Gainesville, Florida 32611 Introduction The following document

More information

Asbestos Survey. for. Commercial Building TCA Building T-187, Pasco Airport Pasco, Washington. May 1, 2014. Project #A2014/0406.

Asbestos Survey. for. Commercial Building TCA Building T-187, Pasco Airport Pasco, Washington. May 1, 2014. Project #A2014/0406. Asbestos Survey for Commercial Building TCA Building T-187, Pasco Airport Pasco, Washington May 1, 2014 Project #A2014/0406 prepared for: Port of Pasco PO Box 769 Pasco, WA 99301 prepared by: Blue Mountain

More information

ASBESTOS BUILDING INSPECTION REPORT. for. Michigan State University Office of Environmental and Occupational Safety East Lansing, Michigan 48823

ASBESTOS BUILDING INSPECTION REPORT. for. Michigan State University Office of Environmental and Occupational Safety East Lansing, Michigan 48823 ASBESTOS BUILDING INSPECTION REPORT for Michigan State University Office of Environmental and Occupational Safety East Lansing, Michigan 48823 at Bailey Hall Building #315 East Lansing, Michigan 48823

More information

Asbestos Management Plan EC 45 Page 1

Asbestos Management Plan EC 45 Page 1 Name: Asbestos and ACBM (asbestos containing building material) Management Plan Areas Affected: All buildings that contain asbestos and ACBM on campus Effective Date: 1/1/09 Reviewed/Revised: 12/15/12

More information

MARYLAND DEPARTMENT OF THE ENVIRONMENT 1800 Washington Boulevard Baltimore MD 21230 410-537-3000 1-800-633-6101 www.mde.state.md.

MARYLAND DEPARTMENT OF THE ENVIRONMENT 1800 Washington Boulevard Baltimore MD 21230 410-537-3000 1-800-633-6101 www.mde.state.md. MARYLAND DEPARTMENT OF THE ENVIRONMENT 1800 Washington Boulevard Baltimore MD 21230 410-537-3000 1-800-633-6101 www.mde.state.md.us/asbestos Martin O Malley Governor Robert M. Summers, Ph.D. Secretary

More information

Asbestos Licensure Law. Code of West Virginia Chapter 16, Article 32 (As amended by the 1993 Legislative Session)

Asbestos Licensure Law. Code of West Virginia Chapter 16, Article 32 (As amended by the 1993 Legislative Session) Asbestos Licensure Law Code of West Virginia Chapter 16, Article 32 (As amended by the 1993 Legislative Session) Be it enacted by the Legislature of West Virginia: That chapter sixteen of the code of West

More information

Control Provisions under the Air Pollution Control Ordinance

Control Provisions under the Air Pollution Control Ordinance ProPECC PN 2/97 ENVIRONMENTAL PROTECTION DEPARTMENT PRACTICE NOTE FOR PROFESSIONAL PERSONS Handlin of Asbestos Containin Materials in Buildins Introduction Asbestos is a generic name given to a group of

More information

Asbestos Building Inspection Report Oak Forest Gun Club 4001 W Fieldcrest Drive Markham, Illinois 60452 Project No.: 1403308

Asbestos Building Inspection Report Oak Forest Gun Club 4001 W Fieldcrest Drive Markham, Illinois 60452 Project No.: 1403308 Asbestos Building Inspection Report Oak Forest Gun Club 4001 W Fieldcrest Drive Markham, Illinois 60452 Project No.: 1403308 557 West Polk Street, Suite 201 Chicago, IL 60607 312.447.1200 p 312.447.0922

More information

Asbestos Management Procedures

Asbestos Management Procedures Asbestos Management Procedures Introduction Asbestos is a naturally occurring mineral which has commonly been used in a variety of building materials due to its strength and unique fire and chemical resistant

More information

2. 40 CFR Part 763; The Asbestos Hazard Emergency Response Act (AHERA), EPA Worker Protection Rule, February 25, 1987.

2. 40 CFR Part 763; The Asbestos Hazard Emergency Response Act (AHERA), EPA Worker Protection Rule, February 25, 1987. Penn State University Environmental Health and Safety Asbestos Management Program I. Introduction Over the past several decades the hazards of asbestos exposure have become well known. With this influx

More information

Guidelines for Mold Remediation (Removal)

Guidelines for Mold Remediation (Removal) Guidelines for Mold Remediation (Removal) Indoor mold growth, water damage, or musty odors should be addressed quickly. Removing mold growth and correcting the underlying cause of water accumulation can

More information

SUBJECT: Kittredge West and Kittredge Commons, Addendum #1 University of Colorado

SUBJECT: Kittredge West and Kittredge Commons, Addendum #1 University of Colorado Memorandum TO: CC: FROM: JE Dunn Kiewit Whiting-turner Marina Florian, UCB Mike Yanker, UCB Thomas S. Norman, CTL Thompson DATE: August 9, 2011 SUBJECT: Kittredge West and Kittredge Commons, Addendum #1

More information

LIMITED ASBESTOS INSPECTION POLICE DEPARTMENT - ROOFING 434 SOUTH 1 ST STREET MONTROSE, COLORADO

LIMITED ASBESTOS INSPECTION POLICE DEPARTMENT - ROOFING 434 SOUTH 1 ST STREET MONTROSE, COLORADO LIMITED ASBESTOS INSPECTION POLICE DEPARTMENT - ROOFING 434 SOUTH 1 ST STREET MONTROSE, COLORADO Inspected by Grande River Environmental, LLC CDPHE CONSULTING FIRM #18631 October 15, 2014 LIMITED ASBESTOS

More information

UNIVERSITY OF ROCHESTER ENVIRONMENTAL HEALTH & SAFETY

UNIVERSITY OF ROCHESTER ENVIRONMENTAL HEALTH & SAFETY Revision No.: 1 Page 1 of 6 I. PURPOSE This procedure establishes the process to conduct asbestos work as it applies to Operation and Maintenance activities, including emergencies. II. PERSONNEL AFFECTED

More information

CONNECTICUT STATUTES : (4)

CONNECTICUT STATUTES : (4) CONNECTICUT STATUTES : (4) TITLE 20 PROFESSIONAL AND OCCUPATIONAL LICENSING, CERTIFICATION, TITLE PROTECTION AND REGISTRATION. EXAMINING BOARDS CHAPTER 400K INDUSTRIAL HYGIENE AND SAFETY INSPECTOR TITLE

More information

SECTION 16 ASBESTOS MANAGEMENT

SECTION 16 ASBESTOS MANAGEMENT SECTION 16 ASBESTOS MANAGEMENT 16.1 Asbestos Management Procedure 16.2 Asbestos O&M Procedure Reviewed: October 2008 Revised: February 2003 Date Accepted: April 2002 Draft Date: December 2001 16.1 ASBESTOS

More information

DRAFT Analysis of Brownfields Cleanup Alternatives City of Olympia Isthmus Properties 505/529 4 th Avenue West

DRAFT Analysis of Brownfields Cleanup Alternatives City of Olympia Isthmus Properties 505/529 4 th Avenue West DRAFT Analysis of Brownfields Cleanup Alternatives City of Olympia Isthmus Properties 505/529 4 th Avenue West December 2013 Prepared by: Kip Summers, P.E. City of Olympia Table of Contents Introduction...

More information

Washington University Asbestos Operations and Maintenance Plan

Washington University Asbestos Operations and Maintenance Plan 1. Purpose Washington University Asbestos Operations and Maintenance Plan 1.1. The purpose of this Asbestos Operations and Maintenance (O&M) Plan is to minimize the potential for exposure to airborne asbestos

More information

Asbestos Policy & Procedure

Asbestos Policy & Procedure Asbestos Policy & Procedure 1. Purpose & Introduction This policy and procedure sets out Octavia s commitment and approach to ensuring, so far as reasonably practicable, that residents, contractors and

More information

Vermont Regulations for Asbestos Control

Vermont Regulations for Asbestos Control Vermont Regulations for Asbestos Control V.S.A. Title 18, Chapter 26 Effective February 1987; Amended November 1995 Vermont Department of Health 1 08 Cherry Street, Box 70 Burlington, VT 05402 Agency of

More information

ENVIRONMENTAL OPERATIONS & MAINTENANCE GUIDANCE MANUAL BACKGROUND INFORMATION ON ASBESTOS AND LEAD BASED PAINT

ENVIRONMENTAL OPERATIONS & MAINTENANCE GUIDANCE MANUAL BACKGROUND INFORMATION ON ASBESTOS AND LEAD BASED PAINT ENVIRONMENTAL OPERATIONS & MAINTENANCE GUIDANCE MANUAL I. INTRODUCTION BACKGROUND INFORMATION ON ASBESTOS AND LEAD BASED PAINT Asbestos Asbestos is a naturally occurring fibrous mineral that is mined from

More information

If the address on this form is different than the address of the building, submit a written explanation.

If the address on this form is different than the address of the building, submit a written explanation. ILLINOIS DEPARTMENT OF PUBLIC HEALTH AHERA THREE YEAR REINSPECTION ASBESTOS ABATEMENT PROGRAM SCHOOL INFORMATION FORM SECTION I NAME OF SCHOOL DISTRICT: SCHOOL ID NUMBER: SCHOOL NAME: ADDRESS OF SCHOOL:

More information

Policy on the Management of Asbestos

Policy on the Management of Asbestos WISHAW AND DISTRICT HOUSING ASSOCIATION Policy on the Management of Asbestos As with all the Association s policies and procedures, this document, where required, may be able to be translated into other

More information

Georgia State University. Urban Life Building Roof Replacement

Georgia State University. Urban Life Building Roof Replacement ENGINEERING AND ENVIRONMENTAL 140 DECATUR STREET SE, ATLANTA, GA 30303 GEORGIA STATE UNIVERSITY - FACILITIES DESIGN & CONSTRUCTION 34 BROAD STREET, SUITE 100 ATLANTA, GA 30303 DRAWING INDEX A-0 PROJECT

More information

SECTION 807 PUMP STATION REHABILITATION

SECTION 807 PUMP STATION REHABILITATION SECTION 807 PUMP STATION REHABILITATION 807-1 DESCRIPTION: Rehabilitation of pump stations shall be defined as the cleaning, removal, repair and/or replacement of any and/or all components including but

More information

Procedures for Cutting and Handling of Asbestos Cement Pipe. City of Richmond Public Works Operations

Procedures for Cutting and Handling of Asbestos Cement Pipe. City of Richmond Public Works Operations Procedures for Cutting and Handling of Asbestos Cement Pipe City of Richmond Public Works Operations Version 2.0 Updates to: November 1995 Procedures Prepared by: AMEC Earth & Environmental a division

More information

Asbestos frequently asked questions

Asbestos frequently asked questions Asbestos frequently asked questions Asbestos is the name given to a group of fibrous silicate minerals which were mined in Australia and overseas and used for a range of products. All forms of asbestos

More information

Administrative Procedure. Asbestos

Administrative Procedure. Asbestos Administrative Procedure FT107 Asbestos Board Received: January 30, 2012 Review Date: February 2015 Accountability: 1. Frequency of Reports As needed 2. Severity Threshold As needed (eg. Ministry of Labour

More information

Lead Exposure Management Plan

Lead Exposure Management Plan Lead Exposure Management Plan 1.0. Policy CSUF has developed the Lead Exposure Management Plan to reduce occupational and environmental exposure to lead, a potent neurotoxin and carcinogen that causes

More information

Department of Environmental Health & Safety. Asbestos Management Program

Department of Environmental Health & Safety. Asbestos Management Program Department of Environmental Health & Safety Asbestos Management Program Issued by: Nathan Rath Date Effective: December 2010 OHIO University Asbestos Management Program Table of Contents Section/Title

More information

Part 2. Overview. Risk management. Workplace health and safety legislation. How should asbestos exposure be managed? Identifying asbestos hazards

Part 2. Overview. Risk management. Workplace health and safety legislation. How should asbestos exposure be managed? Identifying asbestos hazards Part 2. Overview Risk management Workplace health and safety legislation How should asbestos exposure be managed? identify hazards assess risk decide on control measures implement control measures monitor

More information