Project Charter. Office Migrations Document Version 2.0 Prepared by Sabina Winters, ITS Last Edited February 19, 2015
|
|
- Tyrone Reed
- 8 years ago
- Views:
Transcription
1 Prepared by Sabina Winters, ITS Last Edited February 19, 2015 SOLUTION PLAN REQUIREMENTS ANALYSIS DESIGN BUILD TEST TRAIN/DEPLOY MAINTENANCE Executive Summary In December of 2014, the IT Governance Architecture and Infrastructure Committee (AIC) endorsed a strategy of pursuing a cloud- based platform for calendaring and business class users (primarily faculty and staff) in order to deliver the functional requirements desired and needed by those users. The Office Migration project has been launched in support of this strategy. The goal of this effort is an organized and well- planned migration of mailboxes from volunteer Colleges, Schools, and Units (CSUs) from UT Austin s on- premise Microsoft Exchange environment, Austin Exchange Messaging Service (AEMS), to Microsoft s Office 365 cloud- hosted calendaring and environment. Business Need and Background The Austin Exchange Messaging Service (AEMS) is UT Austin s locally hosted Microsoft Exchange environment. The existing AEMS infrastructure will need to be refreshed or retired no later than FY AEMS was originally sized to accommodate 25,000 mailboxes at a maximum individual mailbox size of 2G. Because of the impending infrastructure expenses, the IT Governance Architecture and Infrastructure Committee (AIC) approved migration to Microsoft s Office 365 hosted Exchange in February That initial migration ran into various project, service and technical challenges and was placed on hold in January 2014 with 60% of migrations completed. Those challenges have now been addressed sufficiently to resume the project. With the December 2014 AIC endorsement to continue pursuing cloud- based calendaring and solutions for UT Austin s faculty and staff members, ITS was authorized to assemble a project team to continue large- scale mailbox migrations from AEMS to Office 365 for as many of the remaining 40% of mailboxes as possible. The need to complete migrations is multi- faceted. Firstly, groups that routinely share calendaring and tasks, normally within a College, School, or Unit (CSU), and have mailboxes located in different environments, encounter difficulty collaborating when doing their daily work. Bringing all of those mailboxes into a single environment (Office 365) enables those groups to once again to do shared calendaring and , as well as delegation tasks. Secondly, mailbox size in the on- premise environment is limited to 2G, whereas it is 50G in the cloud. Thirdly, Microsoft has begun releasing new feature functionality, such as the new version of Outlook for Mac, to only Office 365 users initially. To take advantage of these new features, an individual s mailbox must be in the cloud. Lastly, the existing AEMS hardware will need to be refreshed and right- sized for the few remaining mailboxes, or retired outright, no later than FY ITS has received an increase in the Page 1 of 6
2 number of requests from the campus community to move their College, School, or Unit (CSU) to the cloud, and planning for these moves to occur within a common timeframe allows ITS to optimize the resources and costs needed for the project. Project Description and Scope This project will concentrate on providing guidance on pre- migration tasks, migrating mailboxes from AEMS to Office 365, and providing post- migration support. To support these primary goals, we will also send timely and complete communications about the migrations, keep online documentation on the Office 365 product and migration FAQs up- to- date, and work with each CSU migrating, to ensure their mailboxes are migrated on a date that they approve in advance. In Scope The following deliverables or tasks are in scope for this project: Pre- migration instructions and support will be provided to the CSU s site champion, ordinarily a Technical Support Contact (TSC), on the hardware, software, and calendaring and hygiene tasks that are required to be completed prior to migration. The project team will work with each CSU to develop a communication plan to ensure appropriate migration related communications for that business unit. The project team will work with each CSU to identify mailboxes that should be migrated and develop a migration date for those mailboxes. The project team will work with each CSU to delete obsolete resource accounts and migrate EID based mailboxes to resource accounts where appropriate, prior to migration to Office 365. ITS will apply Microsoft ProPlus licenses to all new Office 365 accounts. These licenses allow TSCs to determine if and when a CSU or individual user will use any or all new Microsoft features and functionality reserved for Office 365 customers. Onsite post- migration support will be provided the morning after migrations for each CSU. Out of Scope The following deliverables or tasks are out- of- scope for this project: Migrating a CSU off its own server and onto Office 365. Due to the complexity of migrating from a non- ITS server to Office 365, individual project plans need to be created jointly by ITS and the CSU for each of these migrations. Large- scale data remediation in Exchange for a CSU. Downloading, installing, or authorizing any new feature or functionality available to Microsoft ProPlus licensees including, but not limited to, the new Outlook for Mac. While a ProPlus license allows access to features and functionality, the installation and management of those features and functionality belongs to the individual TSCs and is outside the scope of this project. Strategy or implementation regarding other Office 365 related services (e.g., Office Web Apps, Sharepoint Online, Lync, OneDrive, or Project Online) Page 2 of 6
3 Project Goals The primary goals of this project are: Conduct migrations from AEMS to Office 365 on an opt- in basis. Provide each College, School, or Unit s (CSU s) Technical Support Contact (TSC) information, support, and guidance as they complete pre- and post- migration tasks. Ensure that 100% of mailboxes that are migrated are functional post- migration, including being able to send and receive s and perform all standard calendaring functions in Office 365. Ensure that 100% of non- resource mailboxes that are migrated and accessed with mobile devices are functional post- migration on those mobile devices, including being able to send and receive s and perform all standard calendaring functions. Have no more than a 5% mailbox failure rate during mailbox migrations. Project Schedule PHASE FTE Q Q Jan Feb Mar Apr May Plan Solution Analysis & Tools Testing Pre- migration Tasks Mailbox Migrations Update Documentation Project Closeout Project Roles and Responsibilities Role Name(s)/Organization(s) Responsibilities Governance Committee Executive Sponsor Customer Steering Committee Architecture and Infrastructure Committee (AIC) Brad Englert, CIO Charles Soto, Communication Michael Bos, Athletics Cesar de la Garza, Development Ruby Philipose, ITS Help Desk Endorse the project charter and provide approval for the project. Approve major project scope or schedule changes. Responsible for the success of the project. Review project charter Review project timelines and progress Review and accept project deliverables Page 3 of 6
4 Terry Gibson, ITS Managed IT Support Trice Humpert, ITS Systems Sandra Germenis, ITS User Services Jamie Southerland, Shared Services Brad Van Schouwen, ATS Project Manager Sabina Winters, PMP, ITS Systems Provide project planning, coordination, and communication. Provide overall status reporting of deliverables. Track progress toward completion of the identified project goals. Technical Lead Glen Martin, ITS Systems Lead solutions analysis and design efforts. Project Team Stephen Walker, ITS Systems Don Nash, ITS Systems Larry Liberty, ITS Systems Evan Rabinowitz, ITS Help Desk Andrew Fogelsong, ITS Managed IT Support Connie Lobb, ITS Communications Avanade Professional Services Team Departmental TSC s to be identified Produce deliverables, create documentation, and provide technical assistance to contracted Professional Services resources. Information Security Officer Networking Point of Contact Stakeholder(s) Cam Beasley William Green Architecture and Infrastructure Committee ITS Help Desk ITS Managed IT Support Academic Technology Services Faculty and Staff AEMS mailbox users Act as security consultant and assess security needs for the project. Act as networking consultant and assess networking needs for the project. Page 4 of 6
5 Project Facilities and Resources The following facilities and resources will be required for this project: The virtual machine utilized during by the Office 365 project prior to project suspension in January 2014 that can run the existing Avanade Accelerate tool. Professional Services staff sufficient to run the Avanade Accelerate tool and to assist ITS resources where necessary. Full engagement of multiple departments to support the project, including ITS Help Desk, Managed IT Support (MITS), and ITS Systems. Full engagement of Academic Technology Support (ATS) before, during and after the migration of customers that ATS supports, such as College of Liberal Arts and Provost s Office. Customer and TSC action and engagement before, during, and after migrations, including active participation in planning and communications to the members of the College, School, or Unit (CSU), preparing the mailboxes to migrate, and testing that the migrations have been successful. Impact Analysis This project has the following potential areas of impact: Individual or departmental mailbox owners that are hosted on Office 365. Individual or departmental mailbox owners that will continue to be hosted on AEMS. Any systems that rely upon connection to, or data exchange with, AEMS. Assumptions This project has the following assumptions: This project will be the last large- scale migration of mailboxes to Office 365 for UT Austin. However, it is expected that a small number of on- premise mailboxes will remain after this project is concluded. It is expected that ad hoc mailbox migrations will continue as a normal course of ITS- Systems and Help Desk business throughout 2015 as needed. Avanade has been selected as the Professional Services Partner for this project due to their previous successful experience with UT Austin on Phase 1 of the project. Avanade and ITS- Systems will be able to re- use tools, technologies, processes, and communications created and perfected during the previous Office 365 migration project with limited changes required. All required staff members, both at UT Austin and professional services firms, will be available and fully staffed for the duration of the project. TSCs and the ITS Help Desk (as appropriate) will handle Tier 1 and Tier 2 support for this project and in general. ITS- Systems (as appropriate) will handle Tier 3 support for this project and in general. Constraints This project has the following constraints: Page 5 of 6
6 Academic units migrating will be completed prior to the last day of classes during the spring semester 2015 (May 8 th ), unless an Academic Unit specifically requests to go later and the project team agrees to that request. Some administrative units require migration activities to begin after the last day of classes during the spring semester 2015 (May 8 th ) due to administrative activities that must be completed prior to graduation. Risks This project carries the following risks: If insufficient qualified resources are assigned to the project at any point during the project, the project quality, timeline, and/or budget will be negatively impacted. Successful mailbox migrations are dependent on individual CSUs fully completing the pre- migration work required. If pre- migration work for a CSU is not completed, the migration for that CSU could have a sub- optimal outcome or migration of those mailboxes may be removed from scope at the project team s discretion. Unsuccessful mailbox migrations may have a detrimental and potentially catastrophic impact on a CSU s business processes. The mailbox migration process has been optimized for the Microsoft Exchange and Office 365 environment as of early spring If Microsoft makes any large material changes to that technology or environment, the migration tools used during migrations may be detrimentally affected. Revision History Version Date Updater Name Description V 1.0 February 9, 2015 V 2.0 February 12, 2015 Sabina L Winters Sabina L Winters Initial draft completed with feedback incorporated Updated roles and responsibilities, updated project schedule, grammar corrections Document Approvals Name Architecture and Infrastructure Committee (AIC) Version Approved Approval Method 2.0 Unanimous committee approval in AIC meeting Date February 13, 2015 Page 6 of 6
DESIGN BUILD TEST TRAIN/DEPLOY MAINTENANCE
SOLUTION PLAN REQUIREMENTS ANALYSIS DESIGN BUILD TEST TRAIN/DEPLOY MAINTENANCE Executive Summary The project will document campus requirements for IAM functionality and select and procure one or more technology
More informationCalendaring and Email Strategy Recommendation Summary
Calendaring and Email Strategy Recommendation Summary AIC Calendaring and Email Strategy Version 1.0 Prepared by Connie Lobb, ITS Approved by AIC, December 12, 2014 Last Edited January 8, 2015 Executive
More informationDESIGN BUILD TEST TRAIN/DEPLOY MAINTENANCE
Prepared by Jenn Coast and Christina Konstantinidou, ITS Last Edited May 8, 2015 SOLUTION PLAN REQUIREMENTS ANALYSIS DESIGN BUILD TEST TRAIN/DEPLOY MAINTENANCE Project Charter Executive Summary With the
More informationVoIP Deployment Committee Charter
Version 1.6 Prepared by William Green, ITS Last Edited October 30, 2012 Charter Summary A task force and executive committee of representatives from the College of Natural Sciences, Cockrell School of
More informationCASI Project Charter. Centralized Authentication System Implementation. Executive Summary. Business Need and Background
Prepared by Kara Nicholas, ITS Executive Summary The (CASI) project involves the development and release of a new UT EID- based authentication, to replace the aging Central Web Authentication (CWA). CASI
More informationOPERATIONAL IT COMMITTEE MEETING AGENDA WEDNESDAY, MAY 23, 2012 3:00 4:00 p.m. FAC 228D
OPERATIONAL IT COMMITTEE MEETING AGENDA WEDNESDAY, MAY 3, 01 3:00 4:00 p.m. FAC 8D I. Cloud File Sharing Task Force Recommendations (Ryan Baldwin) II. UDC Printer Repair Transition to Campus Store (Michael
More information1 ERP_GEUPD (Group Email Upgrade) Project Charter Version 1.4 Prepared by Cooper Henson, ITS Last Edited November 15, 2012
1 ERP_GEUPD (Group Prepared by Cooper Henson, ITS Last Edited November 15, 2012 Project Charter Group Email Conversion Project ID ERP_GEUPD Business need The Group Email application allows users to send
More informationRESEARCH AND EDUCATIONAL TECHNOLOGY COMMITTEE MEETING AGENDA Thursday, May 17, 2012 8:00-9:00 a.m. FAC 228D
RESEARCH AND EDUCATIONAL TECHNOLOGY COMMITTEE MEETING AGENDA Thursday, May 17, 2012 8:00-9:00 a.m. FAC 228D I. Learning Management System (David Moss Dennis Klenk, Mario Guerra) II. My Edu (Brad Englert)
More informationSharePoint 2013 Project Charter
Prepared by David Moss Last Edited June 27, 2014 SOLUTION PLAN REQUIREMENTS ANALYSIS DESIGN BUILD TEST TRAIN/DEPLOY MAINTENANCE SharePoint 2013 Project Charter Executive Summary The SharePoint 2013 project
More informationSTRATEGIC IT ACCOUNTABILITY BOARD (SITAB) AGENDA WEDNESDAY, JUNE 15, 2011 2:30 3:30 p.m. STARK LIBRARY
STRATEGIC IT ACCOUNTABILITY BOARD (SITAB) AGENDA WEDNESDAY, JUNE 15, 2011 2:30 3:30 p.m. STARK LIBRARY Attendees: William Powers Alex Albright, Jay Boisseau, Pat Clubb, Brad Englert, Rod Hart, Kevin Hegarty,
More informationIT Architecture and Infrastructure Committee
IT Architecture and Infrastructure Committee 9:00 10:30 a.m., September 11, 2015, FAC 228D I. Committee Member Introductions II. IT Governance Overview (Brad Englert) III. Building Access Control System
More informationProject Charter. Identity & Access Management Strategy. Executive Summary. Business Need and Background. Document Version 1.
August 30, 2012 Executive Summary The Identity and Access (IAM) Strategy project will provide a roadmap for implementing a comprehensive and full- featured set of IAM services to encourage collaboration,
More informationDrupal Foundation Project Charter
Prepared by Christina Konstantinidou, ITS Last Edited February 10, 2014 SOLUTION PLAN REQUIREMENTS ANALYSIS DESIGN BUILD TEST TRAIN/DEPLOY MAINTENANCE Drupal Foundation Project Charter Executive Summary
More informationIAM Committee Meeting Agenda 3/14/2016
IAM Committee Meeting Agenda 3/14/2016 Attending: Thomas Beard, Cam Beasley, CW Belcher, Michael Bos, Bill Bova, John Chambers, Fred Gilmore, Ty Lehman, Andy Loomis, Shelley Powers, Steve Rung, Karen Weisbrodt
More informationDESIGN BUILD TEST TRAIN/DEPLOY MAINTENANCE
Prepared by Paul Grotevant and Christina, ITS Last Edited May 8, 2015 SOLUTION PLAN REQUIREMENTS ANALYSIS DESIGN BUILD TEST TRAIN/DEPLOY MAINTENANCE Project Charter Executive Summary The campus Drupal
More informationSTRATEGIC IT ACCOUNTABILITY BOARD AGENDA Tuesday, July 30, 2013 4:00 5:00 p.m. STARK LIBRARY
STRATEGIC IT ACCOUNTABILITY BOARD AGENDA Tuesday, July 30, 2013 4:00 5:00 p.m. STARK LIBRARY I. Learning Management System Strategy Endorse (Pat Davis) II. Email Strategy Update (Brad Englert) III. Administrative
More informationProject Charter. UT Web Infrastructure Project Document Version 9.0 Prepared by John Lovelace & David Moss Last Edited March 13, 2012
Prepared by John Lovelace & David Moss Last Edited March 13, 2012 Project Charter UT Web Infrastructure Project Executive Summary The goal of this project is to select and implement a solution that will
More informationProject Charter. VoIP Plan Task Force Document Version 3 Prepared by Sandra Germenis, ITS Last Edited October 19, 2010. VoIP Plan Task Force
Prepared by Sandra Germenis, ITS Last Edited October 19, Project Charter Summary A task force of representatives from McCombs School of Business, The College of Natural Sciences, the College of Liberal
More informationI. Administrative Systems Master Plan Update (Mary Knight)
ARCHITECTURE & INFRASTRUCTURE COMMITTEE MEETING AGENDA FRIDAY, February 10, 2012 9:00-10:30 AM I. Administrative Systems Master Plan Update (Mary Knight) II. Cloud File Sharing Task Force Update (Ryan
More informationBruinTech Vendor Meet & Greet
BruinTech Vendor Meet & Greet Cloud Services Update Microsoft Office 365 Google Apps for UCLA Mark Bower IT Services June 25, 2014 1 Cloud Email and Collaboration Services Roadmap Google Apps available
More informationOPERATIONAL IT COMMITTEE MEETING AGENDA Wednesday, February 27, 2013 3:00 4:00 p.m., FAC 228D
OPERATIONAL IT COMMITTEE MEETING AGENDA Wednesday, February 27, 2013 3:00 4:00 p.m., FAC 228D I. Service Retirement Strategy (Brad Englert) II. Office 365 - Update (Pei Chen) III. Technology Enhanced Education
More informationOPERATIONAL IT COMMITTEE MEETING AGENDA Wednesday, September 26, 2012 3:00 p.m., FAC 228D
OPERATIONAL IT COMMITTEE MEETING AGENDA Wednesday, September 26, 2012 3:00 p.m., FAC 228D I. Welcome and Introductions II. 2012-2013 OIT Chair II. Governance Overview III. OIT Priority Topics for 2012-2013
More informationDESIGN BUILD TEST TRAIN/DEPLOY MAINTENANCE. This project is part of the Identity and Access Management Roadmap.
April 5, 2015 SOLUTION PLAN REQUIREMENTS ANALYSIS DESIGN BUILD TEST TRAIN/DEPLOY MAINTENANCE Executive Summary The (CARE) project will improve the resiliency of the UTLogin, Shibboleth, and Active Directory
More informationCOMMUNICATIONS & COLLABORATION. Ryan Lenger Scott Fuller. Isaac Podolefsky
COMMUNICATIONS & COLLABORATION Project Information Project Team Leads: Project Manager: Ryan Lenger Scott Fuller Isaac Podolefsky TeamDynamix Project Number: 241101 Project Overview Modernize and improve
More informationTask Force Charter. Mobile Strategy Document Version 3.0 Chief Information Officer, ITS Last Edited December 17, 2012.
Chief Information Officer, ITS Last Edited December 17, 2012 Task Force Charter Mobile Strategy Executive Summary The mobile strategy will provide the policies, best practices, mobile website and application
More informationProject Charter. Secure Message System Upgrade
Prepared by Cooper Henson, ITS Last Edited March 24, 2014 Project Charter Secure Message System Executive Summary The Secure Message System provides authorized employees in The University of Texas System
More informationRESEARCH AND EDUCATIONAL TECHNOLOGY COMMITTEE MEETING AGENDA Thursday, April 18, 2013 8:00-9:15 a.m. FAC 228D
RESEARCH AND EDUCATIONAL TECHNOLOGY COMMITTEE MEETING AGENDA Thursday, April 18, 2013 8:00-9:15 a.m. FAC 228D I. LIFT Recipients Present a. APPSOMA (Pei Chen, Zach Booth-Simpson, Scott Hunicke-Smith) b.
More informationCommunication and Collaboration. Ryan Lenger, Scott Fuller. Isaac Podolefsky
Project Name: Project Team Leads: Project Manager: Communication and Collaboration Ryan Lenger, Scott Fuller Isaac Podolefsky TeamDynamix Project Number: 241101 Project Overview Modernize and improve user
More informationARCHITECTURE)&)INFRASTRUCTURE)COMMITTEE)MEETING)AGENDA)) Friday,)April)11,)2014) 9:00) )10:30)AM) FAC)228D!!!! I.!9:00!!9:15!IT!Shared!
ARCHITECTURE)&)INFRASTRUCTURE)COMMITTEE)MEETING)AGENDA)) Friday,)April)11,)2014) 9:00) )10:30)AM) FAC)228D I.9:00 9:15ITSharedServices Update II.9:15 9:30VoIPUpdate(John%Lovelace) III.9:30 9:50OpenSSLUpdate(Cam%Beasley)
More informationARCHITECTURE & INFRASTRUCTURE COMMITTEE MEETING AGENDA FRIDAY, December 14, 2012 9:00 10:30 AM FAC 228D
ARCHITECTURE & INFRASTRUCTURE COMMITTEE MEETING AGENDA FRIDAY, December 14, 2012 9:00 10:30 AM FAC 228D I. Mobile Strategy Update (Mike Horn) II. Application Team Priorities (Julienne VanDerZiel) III.
More informationMicrosoft Office 365 Request For Proposal
Microsoft Office 365 Request For Proposal A survey of the formal RFP process currently underway at The Scripps Research Institute to migrate from on premise Exchange 2007 to Office 365 Current Exchange
More informationMicrosoft Premier Deployment. Office 365 Service Description
Microsoft Premier Deployment Office 365 Service The information contained in this document represents the current view of Microsoft Corporation on the issues discussed as of the date of publication and
More informationELECTRONIC FILE STORAGE. Laurie Hafner Dahms Mark Wilson. David Bronder
ELECTRONIC FILE STORAGE Project Information Project Team Leads: Project Manager: Laurie Hafner Dahms Mark Wilson David Bronder TeamDynamix Project Number: 241112 Project Overview Centralize standard electronic
More informationCloud Based Email and Collaboration Project Charter
Cloud Based Email and Collaboration Project Charter Business Case Analysis Phase Version 0.9.5 May 23, 2012 Prepared by: Carol Gravatt Project Directors: Bob Micielli, DNR Dave Kirk, OCIO Document Revision
More informationMoving to the Cloud: A Practical Guide Community IT
Moving to the Cloud: A Practical Guide Community IT rev 2014 About Community IT Community IT Innovators partners with nonprofits to help them solve their strategic & day-to-day IT challenges. Strategic
More informationThe Butterfly Initiative
The Butterfly Initiative Executive Summary met-a-mor-pho-sis a profound change in form from one stage to the next in the life history of an organism, as from the caterpillar to the pupa and from the pupa
More informationHow To Write A System Replacement Plan
BUSINESS SERVICES COMMITTEE (BSC) Meeting Agenda May 11, 2012 2:00 pm to 3:30 pm FAC 228D I. Identity Management Strategy (C.W. Belcher) II. imodules (John McCall) III. Administrative System Master Plan
More informationIII. 9:35-9:50 Retirement of Web Space- Communication Plan Endorse (Dave Moss)
ARCHITECTURE & INFRASTRUCTURE COMMITTEE MEETING AGENDA FRIDAY, October 11, 2013 9:00-10:30 AM FAC 228D I. 9:00-9:15 Administrative Systems Update (Mary Knight) II. 9:15-9:35 Priorities Finalization Endorse
More informationIAM Committee Meeting Notes 11/9/2015
IAM Committee Meeting Notes 11/9/2015 Attendees: Thomas Beard, CW Belcher, Michael Bos, John Chambers, Cesar de la Garza, Fred Gilmore, Ty Lehman, Andy Loomis, Darin Mattke, Michelle McKenzie, Shelley
More informationDrupal Services Program Charter
Prepared by Christina Konstantinidou, ITS Last Edited January 3, 2014 SOLUTION PLAN REQUIREMENTS ANALYSIS DESIGN BUILD TEST TRAIN/DEPLOY MAINTENANCE Drupal Services Program Charter Executive Summary The
More informationProject Report and Recommendations
Prepared by Jennifer Jobst, ITS Last Edited July 1, 2011 Project Executive Summary In March 2011, Information Technology Services (ITS) and the Center for Teaching and Learning (CTL) jointly released a
More informationEND USER SUPPORT: DEVICE MANAGEMENT SUBPROJECT PLAN. Rick Bennett Tim Wolf. Mike Frangi
END USER SUPPORT: DEVICE MANAGEMENT SUBPROJECT PLAN Project Information Project Team Leads: Project Manager: Rick Bennett Tim Wolf Mike Frangi TeamDynamix Project Number: 241065 Project Overview The Device
More informationInformation Technology Governance Accountability Report OCTOBER 2014
Information Technology Governance Accountability Report OCTOBER 2014 Table of Contents Executive Summary 3 Status of IT Governance Priorities - FY 2013-2014 4 ITS Capital Budget in Support of Governance
More informationJamie Mathews Tracy Scott. Mike Frangi
END USER SUPPORT: SERVICE DESK UNIFICATION SUBPROJECT PLAN Project Information Project Team Leads: Project Manager: Jamie Mathews Tracy Scott Mike Frangi TeamDynamix Project Number: 241065 Project Overview
More informationBased on this request, below is the current CHA Exchange environment:
PROJECT BACKGROUND The Chicago Housing Authority ("CHA") is in the process of migrating our users to Microsoft's Office 365. CHA has implemented a Directory Synchronization server and has successfully
More informationCommunication Plan. Administrative Information Technology Services University of Illinois. December, 2015
Communication Plan Administrative Information Technology Services University of Illinois December, 2015 Table of Contents Executive Summary... 3 Quick Reference Guide... 3 Purpose... 4 Goals and Objectives...
More informationConsulting Guide: Microsoft Exchange Solutions on VMware
Microsoft Exchange Solutions on VMware Contents 1. Overview... 3 2. Service Offerings... 4 2.1. Performance POC in a box... 4 2.1.1. Why Performance POC in a box?... 4 2.1.2. Objectives... 4 2.1.3. Success
More informationMontgomery County Office 365 (O365) - Outlook Migration. Frequently Asked Questions (FAQ s)
Montgomery County Office 365 (O365) - Outlook Migration Frequently Asked Questions (FAQ s) Preparation for Migration 1) How do I determine which version of Office I have? a. On the Office 365 transition
More informationProject Management Plan. Project Management Plan Guide. Strategic Capital, Infrastructure and Projects
Project Management Plan Guide A guide to completing the Project Management Plan Strategic Capital, Infrastructure and Projects Prepared by: Andrew Segrott / Strategic Capital, Infrastructure and Projects
More informationDRAFT. FY15 UW-Stout Institutional IT Plan
DRAFT FY15 UW-Stout Institutional IT Plan A. & University Strategic Objectives [1-2 pages] 1. How was the plan developed? The UW-Stout IT Planning is tightly integrated into the campus planning model.
More informationGTA Board of Directors September 4, 2014
GTA Board of Directors September 4, 2014 Our Strategic Vision Our Mission A transparent, integrated enterprise where technology decisions are made with the citizen in mind To provide technology leadership
More informationEnterprise Email in the Cloud. Consolidating 21 email systems into an enterprise system using Cloud Services. March 8, 2011
Enterprise Email in the Cloud Consolidating 21 email systems into an enterprise system using Cloud Services March 8, 2011 U.S. Department of Agriculture, Office of the Chief Information Officer 1 Executive
More informationUniversity of Wisconsin Platteville IT Governance Model Final Report Executive Summary
University of Wisconsin Platteville IT Governance Model Final Report Executive Summary February 2013 Project Objectives & Approach Objectives: Build on the efforts of the Technology Oversight Planning
More informationExecutive Branch IT Reorganization Project Plan
Office of Information Resource Management Executive Branch Project Plan Work Program Funded by for IT Appropriations Reorganization 2007, 2009 and Five Small Projects Date: August 2009 Version: 1.3 Revision
More informationACTION ITEM: Approval of the W.P. Carey School of Business Online MBA Program Outsourcing Project - ASU
Page 1 of 5 EXECUTIVE SUMMARY ACTION ITEM: Approval of the W.P. Carey School of Business Online MBA Program Outsourcing Project - ASU ISSUE: ASU seeks approval for the $1 million project to outsource the
More informationLOOK TO THE CLOUD: Cloud Computing Primer An ebook
LOOK TO THE CLOUD: Cloud Computing Primer An ebook Contents 1. What Is the Cloud?... Pg. 3 2. What is Office 365?... Pg. 3 2-1. Exchange Online... Pg. 4 2-2. SharePoint Online... Pg. 5 2-3. Lync Online...
More informationOffice 365 Tim McGeary Stan Waddell. CTC Update
Office 365 Tim McGeary Stan Waddell CTC Update Agenda Exchange Lifecycle IT Transformation Review Process Proposal Service Highlights Possible Downsides Possible Rollout its.unc.edu 2 Lifecycle The university
More informationA Ready Business takes their office wherever they go
A Ready Business takes their office wherever they go Microsoft from Vodafone Vodafone Power to you This has made a massive impact on our business. It s given us a competitive edge in a crowded marketplace.
More informationThe Small/Medium Business (SMB) Essential Guide to Licensing Microsoft Office 365
The Small/Medium Business (SMB) Essential Guide to Licensing Microsoft Office 365 Today, SMBs are working differently, leveraging cloud and mobile technology to improve efficiency, productivity, flexibility
More informationGlendale Community College Microsoft Office SharePoint Server 2007 Initiative Vision/Scope Document. Version 1.0
ware Architects, Inc. Proposal to XXXXX Date Glendale Community College Microsoft Office SharePoint Server 2007 Initiative Vision/Scope Document Software Architects, Inc. Proposal to XXXXX Date Version
More informationBuilding an Effective Email Migration Communication Plan
Building an Effective Email Migration Communication Plan Contents Building an Effective Email Migration Communication Plan... 3 Identify Your Key Stakeholders and their Communication Objective... 3 Determine
More informationOPERATIONAL IT COMMITTEE (OIT) MEETING NOTES WEDNESDAY, JANUARY 27, 2010
OPERATIONAL IT COMMITTEE (OIT) MEETING NOTES WEDNESDAY, JANUARY 27, 2010 Attendees: Liz Aebersold, Alex Albright, Tony Ambler, Danielle Brown, Fred Chang, Brad Englert, Mike Harvey, Fred Heath, John McCall,
More informationCase Study Cloud Computing
Case Study Cloud Computing Rotterdam Juli 2013 Robeco Ton Ligtvoet, Manager IT Contracts and Infra Projects For institutional investors 1 Facts and figures Robeco IT Servicing Asset Management, Pension
More informationThe File Frontier A Web-Based File Storage Solution for Students and Faculty. PJ Abrams Senior Systems Analyst The University of Texas at Austin
The File Frontier A Web-Based File Storage Solution for Students and Faculty PJ Abrams Senior Systems Analyst The University of Texas at Austin Overview Background Requirements System Overview User Stats
More informationCommunication and Collaboration: Email Migration Project Team Leads:
Project Details Project Name: Communication and Collaboration: Email Migration Project Team Leads: Ryan Lenger, Scott Project Manager: Isaac Podolefsky TeamDynamix Project Number: 241101 Project Overview
More informationNovell to Microsoft Conversion: Business Case
Novell to Microsoft Conversion: Business Case Presented To: 3/11/2011 1215 Hamilton Lane, Suite 200 Naperville, IL 60540 www.morantechnology.com Voice & Fax: 877-212-6379 Version History Ver. # Ver. Date
More informationE-mail, Calendar, and Contacts Transition Project. IT Town Hall
E-mail, Calendar, and Contacts Transition Project IT Town Hall The Blue Print Employees (Faculty, Staff and Student-Employees) Students Email Aliases Received when admitted gtaccount@gatech.edu Office365
More informationKnights Email What is Office 365?
Knights Email What is Office 365? Logging into your Knights Email via Outlook Web Access opens up the ability to use Office 365. Office 365 allows you to monitor your inbox, create new events on your calendar,
More informationStatement of Work. Exchange Online Migration. Prepared for University of Arizona Wednesday, 26 May 2010 Version 1.0 Final.
Statement of Work Exchange Online Migration Prepared for University of Arizona Wednesday, 26 May 2010 Version 1.0 Final Prepared by Richard Wakeman Program Manager rwakeman@microsoft.com Contributors Richard
More informationHow To Write A Project Management Plan
Enter Project Name Project Management Plan (PMP) Kickoff Month, Day, Year 1 Purpose The Project Management Plan (PMP) is a formal, approved document used to manage project execution. The PMP documents
More informationIT Consulting Services Desktop Support Service Levels are available online. IT Consulting Services Comparison
Computing Services - Desktop Support & [Organization] Information Technology (IT) Service Level Agreement for Fiscal Year 2013 This document outlines the services provided by the Desktop Support Program
More informationFinal. North Carolina Procurement Transformation. Governance Model March 11, 2011
North Carolina Procurement Transformation Governance Model March 11, 2011 Executive Summary Design Approach Process Governance Model Overview Recommended Governance Structure Recommended Governance Processes
More informationPROJECT MANAGEMENT PLAN <PROJECT NAME>
PROJECT MANAGEMENT PLAN TEMPLATE This Project Management Plan Template is free for you to copy and use on your project and within your organization. We hope that you find this template useful and welcome
More informationSix Steps to a Successful Email Migration to Exchange 2013. Step 1: Migration Project Assessment, Planning and Design
Six Steps to a Successful Email Migration to Exchange 2013 Six Steps to a Successful Email Migration to Exchange 2013 Migrating your organization s email to Exchange 2013, whether it be on premises or
More informationService Desk Readiness
Service Desk Readiness Service Desk Readiness Workshop Topics Review requirements for Service Desk readiness Assess how current support processes should be adapted to support cloud services incident management
More informationOffice 365 Fall Updates FAQ: New Office 365 Plans for SMBs and more!
Office 365 Fall Updates FAQ: New Office 365 Plans for SMBs and more! Table of Contents Overview... 1 Overview of new Office 365 Business plans... 4 Implications for existing customers Open, Advisor, Direct...
More informationState of Alaska Enterprise Messaging and Directory Services Strategy Vision and Scope
State of Alaska Enterprise Messaging and Directory Services Strategy Vision and Scope State of Alaska Document ID: Title: Supersedes: Status: 1010 Enterprise Messaging and Directory Services Strategy Vision
More informationDIANNA SADLOUSKOS BACKGROUNDER www.sadlouskos.com EXPERIENCE
EXPERIENCE SADLOUSKOS CONSULTING SERVICES March 2006 to present FOUNDER, PRINCIPAL CONSULTANT Dianna Sadlouskos is a management consultant with twenty years experience supporting higher education institutions
More informationOverview of products, services and capabilities
Overview of products, services and capabilities Enterprise Agreement Capabilities Enterprise Agreement Subscription Desktop (Common) Perpetual Server and Additional Product For desktop enterprise products
More informationResearch Office Implementation Communication Plan
Research Office Implementation Communication Plan Version 1-24 June 2011 TABLE OF CONTENTS 1. Purpose... 2 2. Scope... 3 3. Assumptions... 3 4. Constraints... 3 5. Communication Management... 3 6. Information
More informationProject management best practices
Project management best practices Project management processes and techniques are used to coordinate resources to achieve predictable results. All projects need some level of project management. The question
More informationOffice 365 Licenties
Office 365 Licenties Tim ter Haar Microsoft Licensing Consultant Software Solutions Group Tim.ter.Haar@Copaco.com a-titerh@microsoft.com 06-27861357 Office 365 Pro Plus Exchange Online Lync Online Sharepoint
More informationPartnering with Simply Mail Solutions. www.simplymailsolutions.com/resellers. Padgate Business Park, Green lane, Warrington.
Partnering with Simply Mail Solutions Reseller programme Helping you stand out Becoming a hosted services reseller opens up additional revenue streams for your company without the hurdle of running in-house
More informationUITS Strategic Plan. Annual Review and Progress Report. October 2015
UITS Strategic Plan Annual Review and Progress Report October 2015 University Information Technology Services (UITS) finalized and made widely available our five year strategic plan in October 2014. In
More informationPROJECT CHARTER DOMINO APPLICATIONS MIGRATION
PROJECT CHARTER DOMINO APPLICATIONS MIGRATION STONY BROOK UNIVERSITY STONY BROOK, NY 11794 Project Charter Version Control Version Date Author Change Description 1.0 11/14/2011 Raymond Chan First Draft
More informationHow To Cloud Or Not To Cloud
To Cloud or Not to Cloud: It s Your Business Decision March 31, 2015 Presented By: Curtis McCallister, MCSE, CCA Manager of Technology Solutions Click HERE to listen to the webinar. Providing Tax, Auditing,
More informationMicrosoft Office 365 how to make a booking for meeting rooms and resource calendars
Microsoft Office 365 how to make a booking for meeting rooms and resource calendars 1 Contents Purpose... 3 Document Support Boundaries... 3 Meeting Rooms what has changed?... 4 How to get access to make
More informationModule 11 Stakeholder Management PMP Exam Questions
Module 11 Stakeholder Management PMP Exam Questions PMP, PMBOK and the Registered Education Provider logo are registered marks of the Project Management Institute, Inc Question 1 You are the project manager
More informationTechnical Writing - A Guide to the Najobe System
CS 4500 Software Engineering Laboratory Team Najobe: Customer Relationship Management Benjamin J. Smith Joseph Engh Nathan Thomas Version 1.0 February26, 2007 Document Change Record Version Number Date
More informationProject Charter IDENTITY AND ACCESS MANAGEMENT. Project Information. Project Overview. Project Purpose and Benefits to Campus. Project Scope Statement
IDENTITY AND ACCESS MANAGEMENT Project Information Project Team Leads: Project Manager: Mike, Noel, Brandon Mills, Jordan O Konek, Chris Pruess Kris Halter TeamDynamix Project Number: 241151 Project Overview
More informationOffice 365 for businesses. Stay connected on the go
Office 365 for businesses Stay connected on the go Welcome to Office 365 Office 365 is a cloud-based service hosted by Microsoft that brings together familiar Microsoft Office desktop applications with
More informationService Level Documentation April, 2015
Service Level Documentation April, 2015 Purpose of the Service Level Document The purpose of this Service Level Document is to outline the relationship and responsibilities between Information Technology
More informationFederal Cloud Computing Initiative Overview
Federal Cloud Computing Initiative Overview Program Status To support the Federal Cloud Computing Direction and Deployment Approach, the ITI Line of Business PMO has been refocused as the Cloud Computing
More informationIntroducing OneDrive for Business
Introducing OneDrive for Business OneDrive for Business is Microsoft s cloud storage service, which comes as part of the Conservatoire s Office365 subscription. OneDrive for Business allows you to access
More informationBid/Proposal No. P15/9888 Business Intelligence Management
Answers to Vendor Questions Questions are in black, Answers are in red 1. Who is the Executive Sponsor(s) for this project Information not available at this time 2. Will PCC provide the selected consultant
More informationStatement of Work. Catapult Systems. The Microsoft Consulting Co. May 6, 2015. This document was developed specifically far Williamson County.
The Microsoft Consulting Co Exchange to Exchange Online Statement of Work For Williamson County May 6, 2015 This document was developed specifically far Williamson County. The concepts and methodologies
More informationHOW TO ACCESS YOUR ONEDRIVE FOR BUSINESS DOCUMENTS
HOW TO ACCESS YOUR ONEDRIVE FOR BUSINESS DOCUMENTS There are three ways to access your OneDrive for Business documents. Through your browser Through your OneDrive Sync folder Through your Office applications
More informationMicrosoft Office 365 From Vodafone 2015 Update
Microsoft Office 365 From Vodafone 2015 Update What is Microsoft Office 365? Microsoft Office 365 offered by Vodafone is a hosted, cloud-based IT solution that combines Microsoft s suite of communication
More informationConfiguring Outlook 2002-2003 for IMAP. Creating a New IMAP Account. Modify an Existing Account
mai l. uml. edu mai l. uml. edu Configuring Outlook 2002-2003 for IMAP This document will show you how to setup or modify Outlook 2003 as an IMAP client. It is intended for Faculty and Staff whose mailboxes
More information