1 Data Center Migration Primer Mark Smith Wednesday, June 27, 2012 General Information Share the webinar Ask a question Votes (polling questions) Rate (before you leave) Attachments (you can download today s presentation) Experis Wednesday, June 27,

2 Meet our presenter Mark Smith Infrastructure and Data Solutions Senior Technical Manager - Experis Experis Wednesday, June 27, Agenda Overview Of A Data Center Reference Migration Process Identification and Review of Key Drivers for Migration Projects Review Common Migration Issues and Solutions Experis Wednesday, June 27,

3 A Data Center Migration Reference Process Polling Question #1: What are your data center migration plans? We are moving right now! Moving sometime in the next three months Moving sometime in the next three to six months Moving sometime in the next six to 12 months Moving sometime but it is a year or more away Experis Wednesday, June 27,

4 Characteristics of a Data Center Migration Potential for extreme disruption to existing services and infrastructure Impacts Business Applications Technology Governance Capital Migrations Have Potential for: Cross functional integration Geographically diverse collaboration Effects get amplified quickly Migrations are few and far between but hold great opportunity Experis Wednesday, June 27, Importance of Leveraging a Migration Framework First step in developing a detailed project plan Creates a common vision Institutes a common language Facilitates problem solving and reporting Designates a preferred approach Clarifies important relationships and identifies key stakeholders Lays the foundation for managing risk Experis Wednesday, June 27,

5 Experis Migration Framework Experis Wednesday, June 27, Avoid the Boil the Ocean Syndrome What is Boil the Ocean? Multi-layered planning is required Start with framework planning to create a context for all other detailed planning Restrict initial discovery and planning activities to the degree needed to accomplish context creation Complete detailed planning once the context (when and where) is understood and approved Scheduled detailed planning is imperative Experis Wednesday, June 27,

6 Initiation Phase Defining the Drivers, Scope and Vision Identify key constraints time, resources, business impact Identify potential move types for key components Create context for the amount of architectural transformation Identify project governance requirements for planning phases of project Define High Level scope Identify stakeholders Experis Wednesday, June 27, Assessment Phase Determine what is needed to prepare the organization for migration activities Determine what type and the extent of program governance Complete top down discovery Create inventory application portfolio and align with business context Complete bottom up discovery Automated discovery and assisted dependency mapping Complete application performance analysis Align top down and bottom up discoveries Define best fit future state topologies Determine what is needed to prepare target data center Determine what is needed to prepare core infrastructure Determine what is needed to prepare applications Experis Wednesday, June 27,

7 Plan Development Phase Develop a migration program governance framework and plan to implement Identify reference move types Determine move packages and requirements Define future state capabilities Evaluate current state vs. future state Develop designs and plans for target data center and/or services Develop designs and plans for future state core services Develop Engineering Designs for Core Services Map move packages to target t move types Draft move package charters Experis Wednesday, June 27, Program Build Phase Specific plans developed in earlier phases are energized At close of build phase all of the following must be complete and ready for the migration kick off: All get ready work is complete Full migration program governance is in effect Data Center space procured, built out and ready to receive hardware Core infrastructure designed and built out ready to receive application hardware/software. This may include cloud services, farms and other public or private leveraged or shared infrastructure t Chartered move groups, moves with agreed on move types, outage windows, transformation scope defined and resource estimates. Conduct pilot moves Experis Wednesday, June 27,

8 Migrate Phase This is the traditional phase most think off when discussing a migration The Migrate phase will get bogged down if items from the earlier phases have not been completed Move groups typically follow a waterfall methodology Detailed Design Detailed Planning Procurement and Build Testing and Acceptance Cut over Reporting is made consistent and clear if all move groups follow the same waterfall Experis Wednesday, June 27, Polling Question #2: Why are you moving your data center? Contractual reason A result of merger and acquisition activity Limited capacity at current data center Technology upgrade Experis Wednesday, June 27,

9 Why move at all? Why move a data center? Migrations are complex Migrations are expensive Migrations can be disruptive Why move? Experis Wednesday, June 27,

10 Why Move? Cost savings A primary driver to many migration projects Reduce costs by reducing the number of data centers Operating costs are directly proportional to the number of data centers operated Reduce costs by consolidating to least expensive space Reduce costs by moving to least expensive power This is a very common justification for move Typical project life cycles include preliminary phases to justify move expense with reduced operational expenses Experis Wednesday, June 27, Mergers, Acquisitions and Divestitures M&A activity may create migration activities Many M&A projects avoid big changes leaving the consolidation project for the blended organization. When an M&A project kicks off a migration, it s typically in parallel with other M&A activities and very sensitive to schedule and costs M&A migrations benefit most from application rationalization projects All divestitures create migration projects Many times, the divestiture does not properly scope what is required at a data center layer to spin off a company or business creating a project sensitive to schedule and costs Experis Wednesday, June 27,

11 Moves due to legal or regulatory requirements Leases expiring cause a large number of moves You may have visibility to your organizations leases but what about your hosting provider s lease? Managed hosting contracts ending Your hosting contract has ended and you plan to move to a new vendor for any number of reasons Regulatory requirements Regulatory or legal requirements are forcing a move Experis Wednesday, June 27, Why move? Resource constrained! Space, power or cooling constraints Technical constraints Experis Wednesday, June 27,

12 Why move? Enhanced availability and business continuity This is one of the most difficult use cases to justify Risk avoidance use case is difficult to map to specific cost savings Risk avoidance may satisfy a significant regulatory requirement Enhanced availability is typically sold as a target of opportunity for most migrations Enhanced availability is positioned as a side benefit with little added cost Typically, y significant cost is required to remediate the infrastructure and applications to take full advantage of new availability capabilities. This cost is often unanticipated and at risk of not being realized by the migration project Experis Wednesday, June 27, Common Migration Issues and Best Practices 12

13 Drawn out planning cycles Analysis paralysis has many causes Verify planning tasks are broken down to smaller tasks and scheduled per the framework Rapidly develop and pilot the proposed migration process. Lessons learned can be immediately applied for process improvement with subsequent pilots until the process is ready Plan on at least two pilots Do not neglect a robust discovery Project teams and engineers tend to over compensate for what they don t know by drawing out planning. An aggressive and robust discovery can short circuit this tendency Experis Wednesday, June 27, Losing site of the business drivers This is a very common issue since the migration is the risk everyone is focused on All business value expected of a migration is typically realized at the close of the migration If the business value is to get out of a data center then a key metric should show diminishing hardware counts at the legacy site If the business driver is to consolidate data centers, then a key metric should be a count of the disposed-ofof or repurposed data center space over time. What are the exit criteria? Have plans accounted for the time needed to totally clear the building? Experis Wednesday, June 27,

14 Early on, develop a migration business impact analysis Very similar to a BIA developed for disaster recovery but tactical in scope Migration recovery time objectives should be generous compared to ones of an unplanned outage and set by disaster recovery planning Migration recovery point objectives should be shorter than an unplanned outage Used to align move groups to move techniques Experis Wednesday, June 27, Early on, determine scope of Architectural change One of the biggest issues facing all migration projects is scope-creep Architectural change is the single biggest contributor to scope-creep for most migration projects It s understandable, most IT leaders see a migration as an opportunity to fix all the systemic issues they have been fighting over the years The most successful approach is to draw a hard line to what change is allowed and leverage a robust change control process to manage the flood of suggestions and recommendations that will emerge. This allows control with the most impact and allows best ideas to be vetted and brought in-scope Experis Wednesday, June 27,

15 Limited Discovery and Dependency Mapping Many organizations short-cut or fast path the discovery and dependency mapping The current CMDB or inventory is deemed sufficient A discovery based on self disclosure is considered sufficient Documentation is typically self styled and adhoc. If your primary repository of information is tribal knowledge a discovery and dependency mapping is required Why a rigorous discovery is required You can t manage what you can t measure Risk mitigation starts with understanding the business context of an app, transparency of the apps infrastructure and dependency mapping Proper migration planning is based on identifying move groups which are not apparent with out the dependency mapping Experis Wednesday, June 27, Rationalize your application portfolio Don t move or consolidate what you do not need Can we consolidate applications, if so, where and at what level? Dispose of hardware no longer in use. It s surprising the amount of hardware and circuits that are never properly disposed of in an enterprise An aggressive rationalization project could postpone the need to move to a new data center if the driver is space constraints Experis Wednesday, June 27,

16 Consider a project database A key challenge for all migrations is managing the data generated over the course of the project. Typical approaches are characterized by growing a repository organically Enterprise projects can justify the expense of creating a data repository for project decisions and tracking No off the shelf products are available but some are close such as Adaptivity s Blueprint4IT products Experis Wednesday, June 27, Application Performance Risk of application performance issues are high and particularly so in more complex infrastructures It s unrealistic to baseline performance of all applications prior to moving Leverage the business impact analysis to prioritize what applications require a baseline performance analysis Utilize cutting edge tools to model current and expected performance of the application to identify risks early in the planning Critical applications may warrant a greenfield approach with user acceptance certification at the target site prior to cut over Experis Wednesday, June 27,

17 Formalize Communication Plans Most migrations originate as a bottom up project reversing the traditional communications paths in an I&O organization Migrations are always cross functional complicating communication requirements Robust communication planning is essential Business community will assume the worst without being informed A key risk avoidance technique means transparency is imperative Formal communication channels will minimize adhoc requests for reporting Transparent communications will improve cycle time for approvals at all levels Experis Wednesday, June 27, Aggressive Schedule Management A vast majority of migrations are schedule sensitive Traditional project management trims scope to salvage schedule Migration scope can be managed by changing the move types and the level of transformation allowed prior to or during the move Delays in schedule create significant cost over-runs Fines and penalties A bubble in the resource plan Maintaining duplicate sites Delays in schedule increase risk of lost data and unplanned outages As project teams are required to do more with the same number of resources, corners are often cut that can lead to unplanned outages or lost data Experis Wednesday, June 27,

18 Create specific migration strategies Base move strategies on resource and technical capabilities of current and target environments Typical strategies: Two examples below Fork Lift migrations. Also known as cold moves or lift and shift An economical approach provided the financial impacts of the outage are factored in It s critical to pre-build and label everything Do not re-use wire or fiber cables Pre move QA includes IP address change test, unassisted reboot test, backup and restore test. Swing Migrations: Build a parallel environment on new or leased hardware at the target site and swing the data and DNS at a cut over event. It s possible to achieve a very low outage on a swing migration Experis Wednesday, June 27, Creating move groups Many names, same concept Move groups Migration groups Move packages Move bundles Move groups created based on several requirements Application boundaries Outage windows Complexities and dependencies Development schedules 80/20 rule works well with defining move groups There are often conflicting requirements Experis Wednesday, June 27,

19 Incorporate QA testing at multiple levels in the migration process Each migration strategy must have a corresponding testing strategy and approach. Once a move package is mapped to a specific migration strategy, specific test cases can be developed. Be careful not to allow traditional QA process reign supreme Experis Wednesday, June 27, Be Pragmatic on Internal Experience Levels Are your internal resources up to the task? Are project tasks assigned to operations resources or dedicated project resources? Has your organization s project capabilities been trimmed to the bare bones by cost savings measures? Engage outside help earlier rather than later Form cross functional, dedicated teams to plan, build and execute the migration Experis Wednesday, June 27,

20 Disaster Recovery Considerations Disaster Recovery has multiple meanings for a migration How do you recover if a move fails? How do you maintain an applications disaster recovery infrastructure/replication over the time period of the move? For swing migrations you may need to move both the primary and DR sites at the same time Will the migration generate an event requiring a DR exercise outside of the normal DR exercise calendar? Will the DR capabilities of the application change over the course of the migration? Will the backup infrastructure change between the current and target sites? If so, what is the impact on retained backups? Experis Wednesday, June 27, Polling Question #3: How do you plan to incorporate partner or vendors in your migration project s resource plan? Staff augmentation only Outsource the entire data center migration Selectively outsource sub projects Consulting services and project management Other Experis Wednesday, June 27,

21 To Summarize Start migration planning early, dedicate cross functional teams and seek outside help early if needed Time-box the migration planning and use pilots to work out the kinks Commit to a robust discovery and dependency mapping phase Embrace application rationalization and trim the waste Manage scope aggressively with robust change control Formalize communication plans and engage all stakeholders Don t lose sight of why you are migrating Manage risk from the start Leverage the migration types to manage risks of unplanned outages and lost data Factor disaster recovery into your plans Experis Wednesday, June 27, Questions Mark Smith Infrastructure and Data Solutions Senior Technical Manager - Experis Experis Wednesday, June 27,

22 Thank you! 22

AN APPLICATION-CENTRIC APPROACH TO DATA CENTER MIGRATION

AN APPLICATION-CENTRIC APPROACH TO DATA CENTER MIGRATION AN APPLICATION-CENTRIC APPROACH TO DATA CENTER MIGRATION Five key success factors IT organizations today are under constant business pressure to transform their infrastructure to reduce costs, increase

More information

Datacenter Migration Think, Plan, Execute

Datacenter Migration Think, Plan, Execute Datacenter Migration Think, Plan, Execute Datacenter migration is often regarded as a purely technical, almost trivial side-project, to be delivered by existing IT staff alongside their day jobs. With

More information

DCM 18.1 How to Prepare a Data Center Strategy

DCM 18.1 How to Prepare a Data Center Strategy DCM 18.1 How to Prepare a Data Center Strategy What you need to know to build a business case for data center sourcing Presented by: Steve Miano, Managing Principal, & Gary Davis, Principal/Director, Data

More information

Services Providers. Ivan Soto

Services Providers. Ivan Soto SOP s for Managing Application Services Providers Ivan Soto Learning Objectives At the end of this session we will have covered: Types of Managed Services Outsourcing process Quality expectations for Managed

More information

AN APPLICATION-CENTRIC APPROACH TO DATA CENTER MIGRATION

AN APPLICATION-CENTRIC APPROACH TO DATA CENTER MIGRATION AN APPLICATION-CENTRIC APPROACH TO DATA CENTER MIGRATION Five key success factors Whether the decision to relocate or consolidate a data center is driven by cost pressure or the need for greater IT efficiency,

More information

Real World Strategies for Migrating and Decommissioning Legacy Applications

Real World Strategies for Migrating and Decommissioning Legacy Applications Real World Strategies for Migrating and Decommissioning Legacy Applications Final Draft 2014 Sponsored by: Copyright 2014 Contoural, Inc. Introduction Historically, companies have invested millions of

More information

www.pwc.com Business Resiliency Business Continuity Management - January 14, 2014

www.pwc.com Business Resiliency Business Continuity Management - January 14, 2014 www.pwc.com Business Resiliency Business Continuity Management - January 14, 2014 Agenda Key Definitions Risks Business Continuity Management Program BCM Capability Assessment Process BCM Value Proposition

More information

HP Service Manager software

HP Service Manager software HP Service Manager software The HP next generation IT Service Management solution is the industry leading consolidated IT service desk. Brochure HP Service Manager: Setting the standard for IT Service

More information

HOW TO PREPARE A DATA CENTER STRATEGY. What you need to know to build a business case for Data Center sourcing

HOW TO PREPARE A DATA CENTER STRATEGY. What you need to know to build a business case for Data Center sourcing HOW TO PREPARE A DATA CENTER STRATEGY What you need to know to build a business case for Data Center sourcing Presented by: Gary Davis Principal PlanNet Consulting (714) 982-5886 Steve Miano Principal

More information

Application Overhaul. Key Initiative Overview

Application Overhaul. Key Initiative Overview Scott D. Nelson Research Managing Vice President This overview provides a high-level description of the Application Overhaul Key Initiative. IT leaders can use this guide to understand how to develop an

More information

Federal Data Center Consolidation Initiative

Federal Data Center Consolidation Initiative Federal Data Center Consolidation Initiative Data Center Consolidation Plan for the U.S. Small Business Administration Maintained by: The Office of the Chief Information Officer Paul Christy, CIO Revised:

More information

State of Oregon. State of Oregon 1

State of Oregon. State of Oregon 1 State of Oregon State of Oregon 1 Table of Contents 1. Introduction...1 2. Information Asset Management...2 3. Communication Operations...7 3.3 Workstation Management... 7 3.9 Log management... 11 4. Information

More information

Software Asset Management on System z

Software Asset Management on System z Software Asset Management on System z Mike Zelle Tivoli WW IT Asset Management Marketing SAM in SHARE Project Manager mzelle@us.ibm.com Agenda Why Software Asset Management (SAM) The Discipline of Software

More information

WHY GOOD DATA IS A MUST

WHY GOOD DATA IS A MUST WHY GOOD DATA IS A MUST Asset Management Oversight is Essential to Effective Governance By Terri Hart-Sears www.isg-one.com INTRODUCTION Asset Management is a set of business practices that join financial,

More information

Software Licensing and Pricing Best Practices. Stewart Buchanan June 3, 2009 Gartner Webinar

Software Licensing and Pricing Best Practices. Stewart Buchanan June 3, 2009 Gartner Webinar Software Licensing and Pricing Best Practices Stewart Buchanan June 3, 2009 Gartner Webinar How to Participate Today Audio Announcement You have joined the audio muted using your computer s speaker system

More information

and the world is built on information

and the world is built on information Let s Build a Smarter Planet Starting with a more dynamic and the world is built on information Guy England Storage sales manager CEEMEA englag@ae.ibm.com Tel: +971 50 55 77 614 IBM Building a Smarter

More information

Best Practices for Consolidation Projects

Best Practices for Consolidation Projects Best Practices for Consolidation Projects Lynne Glickman Solution Architect Hewlett-Packard 2004 Hewlett-Packard Development Company, L.P. The information contained herein is subject to change without

More information

WHY DO I NEED A PROGRAM MANAGEMENT OFFICE (AND HOW DO I GET ONE)?

WHY DO I NEED A PROGRAM MANAGEMENT OFFICE (AND HOW DO I GET ONE)? WHY DO I NEED A PROGRAM MANAGEMENT OFFICE (AND HOW DO I GET ONE)? Due to the often complex and risky nature of projects, many organizations experience pressure for consistency in strategy, communication,

More information

IT Cost Reduction. Doing More with Less. Anita Ballaney, Vishwanath Shenoy, Michael Gavigan. Strategic IT cost reduction - Doing More with Less

IT Cost Reduction. Doing More with Less. Anita Ballaney, Vishwanath Shenoy, Michael Gavigan. Strategic IT cost reduction - Doing More with Less IT Cost Reduction Doing More with Less Anita Ballaney, Vishwanath Shenoy, Michael Gavigan Strategic IT cost reduction - Doing More with Less The current economic climate will force all businesses to thoroughly

More information

Data Center Consolidation

Data Center Consolidation Data Center Consolidation With computers spread across the enterprise, and the number of networked databases and applications growing at an exponential rate, the challenges of efficient networking, data

More information

2014 Service Availability Benchmark Survey. Published by

2014 Service Availability Benchmark Survey. Published by 2014 Service Availability Benchmark Survey Published by Executive Summary This benchmark survey presents service availability metrics that allow IT infrastructure, business continuity, and disaster recovery

More information

Driving Business Value. A closer look at ERP consolidations and upgrades

Driving Business Value. A closer look at ERP consolidations and upgrades IT advisory SERVICES Driving Business Value A closer look at ERP consolidations and upgrades KPMG LLP Meaningful business decisions that help accomplish business goals and growth objectives may call for

More information

Windows 7 Upgrade Risk Mitigation Planning: Ensuring Windows 7 Upgrade Success

Windows 7 Upgrade Risk Mitigation Planning: Ensuring Windows 7 Upgrade Success November 2010 Windows 7 Upgrade Risk Mitigation Planning: Ensuring Windows 7 Upgrade Success By: Robert Schaper, Laplink Software Enterprise Solutions Contents Introduction 2 Risk and Cost 2 Upgrade Strategies

More information

SMART Considerations for Active Directory Migration. A Strategic View and Best Practices for Migrating the Corporate Directory

SMART Considerations for Active Directory Migration. A Strategic View and Best Practices for Migrating the Corporate Directory SMART Considerations for Active Directory Migration A Strategic View and Best Practices for Migrating the Corporate Directory Table of Contents Introduction: The Strategic View of Active Directory Migrations...

More information

Oracle Data Centre Rationalisation

Oracle Data Centre Rationalisation Ian Gardner - Oracle Applications Architect 2012-06-13 Oracle Data Centre Rationalisation A Practical View Ian.Gardner@uk.ibm.com Tel. 07740 923060 2012 IBM Corporation Why perform Oracle Data Centre Rationalisations...

More information

Business Plan: Information Technology Services (ITS)

Business Plan: Information Technology Services (ITS) Business Plan: Information Technology Services (ITS) How does this service contribute to the results identified in the City of London Strategic Plan? A Sustainable Infrastructure A Caring Community Fundamental

More information

Modern Data Centers: Creating a New Value Proposition

Modern Data Centers: Creating a New Value Proposition Modern Data Centers: Creating a New Value Proposition América Latina 2008 Inter-secretarial Commission for the Development of Electronic Government Mexico City 24 May 2013 Data Center Consolidation Consolidating

More information

Enterprise Information Management and Business Intelligence Initiatives at the Federal Reserve. XXXIV Meeting on Central Bank Systematization

Enterprise Information Management and Business Intelligence Initiatives at the Federal Reserve. XXXIV Meeting on Central Bank Systematization Enterprise Information Management and Business Intelligence Initiatives at the Federal Reserve Kenneth Buckley Associate Director Division of Reserve Bank Operations and Payment Systems XXXIV Meeting on

More information

Disaster recovery strategic planning: How achievable will it be?

Disaster recovery strategic planning: How achievable will it be? Disaster recovery strategic planning: How achievable will it be? Amr Ahmed Ernst & Young Advisory Services, Executive Director amr.ahmed@ey.com Christopher Rivera Ernst & Young Advisory Services, Manager

More information

The following is intended to outline our general product direction. It is intended for information purposes only, and may not be incorporated into

The following is intended to outline our general product direction. It is intended for information purposes only, and may not be incorporated into The following is intended to outline our general product direction. It is intended for information purposes only, and may not be incorporated into any contract. It is not a commitment to deliver any material,

More information

IT Asset Management Strategies

IT Asset Management Strategies IT Asset Strategies 31 August 2016 2016 ServiceNow All Rights Reserved Disclaimer "The views expressed in this presentation are those of the author and do not necessarily reflect the official policy or

More information

+ OFFICE RELOCATION. BEST PRACTICES Moving Your Office

+ OFFICE RELOCATION. BEST PRACTICES Moving Your Office + OFFICE RELOCATION BEST PRACTICES Moving Your Office Preparing for an Office Move? Moving to a new location communicates a lot about your company and impacts your company s brand. It also plays a huge

More information

How Cisco IT Standardizes the Acquisition Integration Process

How Cisco IT Standardizes the Acquisition Integration Process How Cisco IT Standardizes the Acquisition Integration Process Cisco IT develops standards for assimilating newly acquired companies rapidly, consistently, and with minor disruption Cisco IT Case Study

More information

HOW TO PREPARE A DATA CENTER STRATEGY. What you need to know to build a business case for Data Center sourcing

HOW TO PREPARE A DATA CENTER STRATEGY. What you need to know to build a business case for Data Center sourcing HOW TO PREPARE A DATA CENTER STRATEGY What you need to know to build a business case for Data Center sourcing Presented by: Gary Davis Principal PlanNet Consulting (714) 982-5886 Steve Miano Principal

More information

The business value of improved backup and recovery

The business value of improved backup and recovery IBM Software Thought Leadership White Paper January 2013 The business value of improved backup and recovery The IBM Butterfly Analysis Engine uses empirical data to support better business results 2 The

More information

The Power to Take Control of Software Assets

The Power to Take Control of Software Assets The Software Asset Management Specialists 781-569-0410 www.aid.com The Power to Take Control of Software Assets The Benefits of SAM: Building the case for Conducting a SAM Assessment and Implementing a

More information

A comprehensive strategy for successful data center consolidation

A comprehensive strategy for successful data center consolidation Experience the commitment WHITE PAPER A comprehensive strategy for successful data center consolidation To mitigate risk and maximize the benefits of data center consolidation, state and local governments

More information

OnX Oracle Cloud Services

OnX Oracle Cloud Services OnX Oracle Cloud Services BUSINESS CHALLENGES There are several business challenges that drive the cloud discussion and cloud infrastructure market. These business challenges are very different from the

More information

Private & Hybrid Cloud: Risk, Security and Audit. Scott Lowry, Hassan Javed VMware, Inc. March 2012

Private & Hybrid Cloud: Risk, Security and Audit. Scott Lowry, Hassan Javed VMware, Inc. March 2012 Private & Hybrid Cloud: Risk, Security and Audit Scott Lowry, Hassan Javed VMware, Inc. March 2012 Private and Hybrid Cloud - Risk, Security and Audit Objectives: Explain the technology and benefits behind

More information

CGS Technology Outsourcing

CGS Technology Outsourcing CGS Technology Outsourcing Project Management Best Practices; Modernizing Enterprise Infrastructure presented by Michael Brandi, Vice President 16 September 2015 2015 CGS Computer Generated Solutions.

More information

Application Value Assessment

Application Value Assessment Value Assessment Journey to Realising the Value of an Organisation s Portfolio Fujitsu UK & Ireland - Business & Services By Chris Waite, Fujitsu Businesses today operate in highly competitive environments

More information

IT Disaster Recovery Services Program

IT Disaster Recovery Services Program Summary Overview of 2016-2018 Program v.20160526 IT Disaster Recovery Strategy Implementation 2008 Data Center Strategic Plan Part 1 Part 2 Disaster Recovery Strategic Plan Part 1 Part 2 2016 2019 Implementation

More information

Outsourcing and Offshoring A Case Study: Zurich Financial Services

Outsourcing and Offshoring A Case Study: Zurich Financial Services Group IT Outsourcing and Offshoring A Case Study: Zurich Financial Services Sechster Schweizer Ökonomentag Michael Paravicini Chief Information Technology Officer Zurich, 4 March, 2005 Agenda 1. Zurich

More information

WAN Migration Techniques

WAN Migration Techniques Jan 2014, HAPPIEST MINDS TECHNOLOGIES WAN Migration Techniques Lalit Kumar SHARING. MINDFUL. INTEGRITY. LEARNING. EXCELLENCE. SOCIAL RESPONSIBILITY. 2 Copyright Information This document is exclusive property

More information

zoomlens January 2012 Why General Counsel should care about Software Asset Management

zoomlens January 2012 Why General Counsel should care about Software Asset Management zoomlens January 2012 Why General Counsel should care about Software Asset Management An organization s ability to maintain compliance with its contractual obligations and manage costs depends on whether

More information

ENTERPRISE RISK MANAGEMENT FOR BANKS

ENTERPRISE RISK MANAGEMENT FOR BANKS ENTERPRISE RISK MANAGEMENT FOR BANKS Seshagiri Rao Vaidyula, Senior Manager, Governance, Risk and Compliance Jayaprakash Kavala, Consultant, Banking and Financial Services 1 www.wipro.com/industryresearch

More information

IIA OC CHAPTER OCTOBER 2010 BREAKFAST EVENT. The Risks of Outsourcing: Considerations for IT and Operational Auditors.

IIA OC CHAPTER OCTOBER 2010 BREAKFAST EVENT. The Risks of Outsourcing: Considerations for IT and Operational Auditors. SHARED SERVICES AND OUTSOURCING ADVISORY IIA OC CHAPTER OCTOBER 2010 BREAKFAST EVENT The Risks of Outsourcing: Considerations for IT and Operational Auditors October 13, 2010 K P M G L L P (U S) Introductions

More information

GETTING THE MOST FROM THE CLOUD. A White Paper presented by

GETTING THE MOST FROM THE CLOUD. A White Paper presented by GETTING THE MOST FROM THE CLOUD A White Paper presented by Why Move to the Cloud? CLOUD COMPUTING the latest evolution of IT services delivery is a scenario under which common business applications are

More information

Estimating Cloud Computing Costs: Practical Questions for Programs

Estimating Cloud Computing Costs: Practical Questions for Programs Estimating Cloud Computing Costs: Practical Questions for Programs Kathryn Connor RAND Corporation June 2014 In 2010, the OMB proposed Federal Agencies consolidate data centers to save money. In 2013,

More information

Estimating Cloud Computing Costs: Practical Questions for Programs. Kathryn Connor

Estimating Cloud Computing Costs: Practical Questions for Programs. Kathryn Connor Estimating Cloud Computing Costs: Practical Questions for Programs Kathryn Connor RAND Corporation June 2014 In 2010, the OMB proposed Federal Agencies consolidate data centers to save money. In 2013,

More information

The University of Alabama at Birmingham. Information Technology. Strategic Plan 2011 2013

The University of Alabama at Birmingham. Information Technology. Strategic Plan 2011 2013 The University of Alabama at Birmingham Information Technology Strategic Plan 2011 2013 Table of Contents Message from the Vice President... 3 About UAB... 4 About UAB Information Technology Meeting needs

More information

Disaster Recovery Policy

Disaster Recovery Policy Disaster Recovery Policy INTRODUCTION This policy provides a framework for the ongoing process of planning, developing and implementing disaster recovery management for IT Services at UCD. A disaster is

More information

Accenture cloud application migration services

Accenture cloud application migration services Accenture cloud application migration services A smarter way to get to the cloud Cloud computing can help make your apps extraordinarily agile and scalable. You know this. Your competitors know this. And

More information

Applying CMMI SM In Information Technology Organizations SEPG 2003

Applying CMMI SM In Information Technology Organizations SEPG 2003 Applying CMMI SM In Information Technology Organizations Mark Servello, Vice President Jim Gibson, Senior Consultant ChangeBridge, Incorporated Page 1 Portions Copyright 2002 Carnegie Mellon University

More information

Smart Choice Business Consulting Data Centre Migration Story Board

Smart Choice Business Consulting Data Centre Migration Story Board Smart Choice Business Consulting Data Centre Migration Story Board Introduction A data center relocation can be best described as a controlled disaster that involves high risk and requires a minute to

More information

Leveraging Virtualization for Disaster Recovery in Your Growing Business

Leveraging Virtualization for Disaster Recovery in Your Growing Business Leveraging Virtualization for Disaster Recovery in Your Growing Business Contents What is Disaster Recovery?..................................... 2 Leveraging Virtualization to Significantly Improve Disaster

More information

Server Consolidation. Report to the Joint Legislative Oversight Committee on Information Technology

Server Consolidation. Report to the Joint Legislative Oversight Committee on Information Technology Server Consolidation Report to the Joint Legislative Oversight Committee on Information Technology Chris Estes State Chief Information Officer December 2013 This page left blank intentionally Contents

More information

Delivering Cost Effective IT Services

Delivering Cost Effective IT Services M2 Technology Delivering Cost Effective IT Services Defense agencies have been directed to move towards cloud and shared service models by the Federal Data Center Consolidation Initiative (FDCCI), the

More information

CLARIFYING ANSWERS TO COMMON QUESTIONS

CLARIFYING ANSWERS TO COMMON QUESTIONS tech line / mar 2014 CLARIFYING ANSWERS TO COMMON QUESTIONS What are the technology topics and issues that keep you up at night? By Matt Morey and Ken Barton, Strategic Contact Inc. Pipeline Articles www.contactcenterpipeline.com

More information

AUTHOR: REVISION BY: ADS Lead/Manager ESYS Windows OSA

AUTHOR: REVISION BY: ADS Lead/Manager ESYS Windows OSA INFORMATION RESOURCES APPLICATIONS AND DATA SERVICES PROCESS NAME: ADS Web Application Release Management ORIGINAL DOCUMENT DATE: 10/2/2014 AUTHOR: Jim Nelson PROCESS OWNERS: ADS Lead/Manager LAST REVISION:

More information

14 TRUTHS: How To Prepare For, Select, Implement And Optimize Your ERP Solution

14 TRUTHS: How To Prepare For, Select, Implement And Optimize Your ERP Solution 2015 ERP GUIDE 14 TRUTHS: How To Prepare For, Select, Implement And Optimize Your ERP Solution Some ERP implementations can be described as transformational, company-changing events. Others are big disappointments

More information

PROJECT MANAGEMENT PLAN Outline VERSION 0.0 STATUS: OUTLINE DATE:

PROJECT MANAGEMENT PLAN Outline VERSION 0.0 STATUS: OUTLINE DATE: PROJECT MANAGEMENT PLAN Outline VERSION 0.0 STATUS: OUTLINE DATE: Project Name Project Management Plan Document Information Document Title Version Author Owner Project Management Plan Amendment History

More information

BMC and ITIL: Continuing IT Service Evolution. Why adopting ITIL processes today can save your tomorrow

BMC and ITIL: Continuing IT Service Evolution. Why adopting ITIL processes today can save your tomorrow BMC and ITIL: Continuing IT Service Evolution Why adopting ITIL processes today can save your tomorrow What does it mean to adopt ITIL? Implementing ITIL? Don t. That s outdated thinking. Today s successful

More information

Unlock the code IT Asset Management

Unlock the code IT Asset Management HP Software: Apps meet Ops 2015 Unlock the code IT Asset Management Luc Landuyt/ April 2 nd, 2015 Copyright 2015 Hewlett-Packard Development Company, L.P. The information contained herein is subject to

More information

Cost Reduction for Financial Services Organizations

Cost Reduction for Financial Services Organizations Cost Reduction for Financial Services Organizations Abstract Faced with one of the worst economic downturns in recent times, organizations are focusing on cost reductions as never before.infosys assessment

More information

Cost of Poor Quality:

Cost of Poor Quality: Cost of Poor Quality: Analysis for IT Service Management Software Software Concurrent Session: ISE 09 Wed. May 23, 8:00 AM 9:00 AM Presenter: Daniel Zrymiak Key Points: Use the Cost of Poor Quality: Failure

More information

ADM The Architecture Development Method

ADM The Architecture Development Method ADM The Development Method P Preliminary Phase Preliminary Phase Determine the Capability desired by the organization: Review the organizational context for conducting enterprise architecture Identify

More information

Cisco Change Management: Best Practices White Paper

Cisco Change Management: Best Practices White Paper Table of Contents Change Management: Best Practices White Paper...1 Introduction...1 Critical Steps for Creating a Change Management Process...1 Planning for Change...1 Managing Change...1 High Level Process

More information

Specialist Cloud Services Lot 4 Cloud EDRM Consultancy Services

Specialist Cloud Services Lot 4 Cloud EDRM Consultancy Services Specialist Cloud Services Lot 4 Cloud EDRM Consultancy Services Page 1 1 Contents 1 Contents... 2 2 Transcend360 Introduction... 3 3 Service overview... 4 3.1 Service introduction... 4 3.2 Service description...

More information

Using MSBA as the Foundation for SOA

Using MSBA as the Foundation for SOA SOA Challenges Why is Business Architecture Important What is MSBA Using MSBA as the Foundation for SOA SOA in context 1 SOA holds out enormous promise to revitalise the business value of IT... but early

More information

KMS Implementation Roadmap

KMS Implementation Roadmap KMS Implementation Roadmap Sample Excerpt Prepared by: The Knowledge Compass, Inc. TABLE OF CONTENTS 1. EXECUTIVE SUMMARY 5 1.1 Overview 5 1.2 Project Goals & Objectives 5 1.3 Implementation Approach 5

More information

Application Outsourcing: The management challenge

Application Outsourcing: The management challenge White Paper Application Outsourcing: The management challenge Embedding software quality management for mutual benefit Many large organizations that rely on mainframe applications outsource the management

More information

ConsumerLab Emerging App Culture 1

ConsumerLab Emerging App Culture 1 Data Center Consolidation is fundamental to being prepared for the dramatic evolution in ICT technology, as well as fluctuating and unpredictable business demands. Avoiding the potential pitfalls is of

More information

Cloud Computing Safe Harbor or Wild West?

Cloud Computing Safe Harbor or Wild West? IT Best Practices Series Cloud Computing Safe Harbor or Wild West? With IT expenditures coming under increasing scrutiny, the cloud is being sold as an oasis of practical solutions. It s true that many

More information

{The High Cost} of Legacy ERP Systems. plantemoran.com

{The High Cost} of Legacy ERP Systems. plantemoran.com {The High Cost} of Legacy ERP Systems plantemoran.com Many organizations have come to realize that while ERP software doesn t appear to generate direct revenue, it can significantly impact financial performance.

More information

Data Center Consolidation: Lessons From The Field. John Tsiofas, Kraft Kennedy David Carlson, Kraft Kennedy

Data Center Consolidation: Lessons From The Field. John Tsiofas, Kraft Kennedy David Carlson, Kraft Kennedy Data Center Consolidation: Lessons From The Field John Tsiofas, Kraft Kennedy David Carlson, Kraft Kennedy Agenda Factors to consider Technology strategy Building a project team How to use vendors wisely

More information

Contents. Evolving Trends in Core Banking Transformation (CBT) Challenges Faced in Core Banking Transformation (CBT)

Contents. Evolving Trends in Core Banking Transformation (CBT) Challenges Faced in Core Banking Transformation (CBT) Contents Preface From the Editor s Desk Evolving Trends in Core Banking Transformation (CBT) 01. Customer Expectations and Next Generation Banking 05 02. Survival Driving Core Banking Transformation (CBT)

More information

Dynamic Service Desk. Unified IT Management. Solution Overview

Dynamic Service Desk. Unified IT Management. Solution Overview I T S E R V I C E + I T A S S E T M A N A G E M E N T INFRASTRUCTURE MANAGEMENT Dynamic Service Desk Unified IT Management Achieving business and IT alignment requires having insight into hardware and

More information

Building a Disaster Recovery Program By: Stieven Weidner, Senior Manager

Building a Disaster Recovery Program By: Stieven Weidner, Senior Manager Building a Disaster Recovery Program By: Stieven Weidner, Senior Manager Part two of a two-part series. If you read my first article in this series, Building a Business Continuity Program, you know that

More information

Solution brief. HP solutions for IT service management. Integration, automation, and the power of self-service IT

Solution brief. HP solutions for IT service management. Integration, automation, and the power of self-service IT Solution brief HP solutions for IT service management Integration, automation, and the power of self-service IT Make IT indispensable to the business. Turn IT staff into efficient, cost-cutting rock stars.

More information

W H I T E P A P E R. Reducing Server Total Cost of Ownership with VMware Virtualization Software

W H I T E P A P E R. Reducing Server Total Cost of Ownership with VMware Virtualization Software W H I T E P A P E R Reducing Server Total Cost of Ownership with VMware Virtualization Software Table of Contents Executive Summary............................................................ 3 Why is

More information

BRIDGE. the gaps between IT, cloud service providers, and the business. IT service management for the cloud. Business white paper

BRIDGE. the gaps between IT, cloud service providers, and the business. IT service management for the cloud. Business white paper BRIDGE the gaps between IT, cloud service providers, and the business. IT service management for the cloud Business white paper Executive summary Today, with more and more cloud services materializing,

More information

Project Type Guide. Project Planning and Management (PPM) V2.0. Custom Development Version 1.1 January 2014. PPM Project Type Custom Development

Project Type Guide. Project Planning and Management (PPM) V2.0. Custom Development Version 1.1 January 2014. PPM Project Type Custom Development Project Planning and Management (PPM) V2.0 Project Type Guide Custom Development Version 1.1 January 2014 Last Revision: 1/22/2014 Page 1 Project Type Guide Summary: Custom Development Custom software

More information

The future of application outsourcing: making the move from tactical to strategic

The future of application outsourcing: making the move from tactical to strategic IBM Global Business Services White Paper The future of application outsourcing: making the move from tactical to strategic Application Services Page 2 Contents 2 Introduction 2 Success brings new challenges

More information

Enterprise IT Portfolio Governance and Management Model

Enterprise IT Portfolio Governance and Management Model STATE OF MICHIGAN Department of Information Technology Enterprise IT Portfolio Governance and Management Model NASCIO 2007 RECOGNITION AWARDS CATEGORY: IT PROJECT AND PORTFOLIO MANAGEMENT Enterprise IT

More information

White Paper. Managed IT Services as a Business Solution

White Paper. Managed IT Services as a Business Solution White Paper Managed IT Services as a Business Solution 1 TABLE OF CONTENTS 2 Introduction... 2 3 The Need for Expert IT Management... 3 4 Managed Services Explained... 4 5 Managed Services: Key Benefits...

More information

Managing Data Center Growth Explore Your Options

Managing Data Center Growth Explore Your Options Managing Growth Explore Your Options Managing Growth: Managing The increasing demand on data centers has forced many IT managers to look for new ways to manage data center growth, either by consolidating,

More information

Serena Dimensions CM. Develop your enterprise applications collaboratively securely and efficiently SOLUTION BRIEF

Serena Dimensions CM. Develop your enterprise applications collaboratively securely and efficiently SOLUTION BRIEF Serena Dimensions CM Develop your enterprise applications collaboratively securely and efficiently SOLUTION BRIEF Move Fast Without Breaking Things With Dimensions CM 14, I am able to integrate continuously

More information

FTA Technology 2009 IT Modernization and Business Rules Extraction

FTA Technology 2009 IT Modernization and Business Rules Extraction FTA Technology 2009 IT Modernization and Business Rules Extraction August 5th, 2009 _experience the commitment TM Agenda IT Modernization Business Rules Extraction Automation Tools for BRE BRE Cost and

More information

Global Financial Institution Selects Software-Defined Data Center

Global Financial Institution Selects Software-Defined Data Center Selects Software-Defined Data Center VMware Accelerate Advisory Services recommends a software-defined data center (SDDC) architecture that delivers substantial operating savings as much as 75 percent

More information

IT ASSET MANAGEMENT SELECTED BEST PRACTICES. Sherry Irwin

IT ASSET MANAGEMENT SELECTED BEST PRACTICES. Sherry Irwin IT ASSET MANAGEMENT SELECTED BEST PRACTICES Sherry Irwin IT ASSET MANAGEMENT SELECTED BEST PRACTICES By Sherry Irwin INTRODUCTION As the discipline of IT asset management (ITAM) began to evolve in the

More information

Au t o n o m i c s - Ap p l i e d Ap p l i c a t i o n M a n agement

Au t o n o m i c s - Ap p l i e d Ap p l i c a t i o n M a n agement I D C T E C H N O L O G Y S P O T L I G H T Au t o n o m i c s - Ap p l i e d Ap p l i c a t i o n M a n agement October 2015 Sponsored by Capgemini Expectations on delivering business value from application

More information

Information Security Management System for Microsoft s Cloud Infrastructure

Information Security Management System for Microsoft s Cloud Infrastructure Information Security Management System for Microsoft s Cloud Infrastructure Online Services Security and Compliance Executive summary Contents Executive summary 1 Information Security Management System

More information

Data Governance. Unlocking Value and Controlling Risk. Data Governance. www.mindyourprivacy.com

Data Governance. Unlocking Value and Controlling Risk. Data Governance. www.mindyourprivacy.com Data Governance Unlocking Value and Controlling Risk 1 White Paper Data Governance Table of contents Introduction... 3 Data Governance Program Goals in light of Privacy... 4 Data Governance Program Pillars...

More information

HIPAA CRITICAL AREAS TECHNICAL SECURITY FOCUS FOR CLOUD DEPLOYMENT

HIPAA CRITICAL AREAS TECHNICAL SECURITY FOCUS FOR CLOUD DEPLOYMENT HIPAA CRITICAL AREAS TECHNICAL SECURITY FOCUS FOR CLOUD DEPLOYMENT A Review List This paper was put together with Security in mind, ISO, and HIPAA, for guidance as you move into a cloud deployment Dr.

More information

U.S. Nuclear Regulatory Commission

U.S. Nuclear Regulatory Commission U.S. Nuclear Regulatory Commission 2011 Data Center Consolidation Plan and Progress Report Version 2.0 September 30, 2011 Enclosure Contents 1 Introduction... 2 2 Agency Goals for Data Center Consolidation...

More information

The facility in a converged infrastructure Michalis Kefalakis HP Data Centre Facilities Strategy Lead EMEA

The facility in a converged infrastructure Michalis Kefalakis HP Data Centre Facilities Strategy Lead EMEA The facility in a converged infrastructure Michalis Kefalakis HP Data Centre Facilities Strategy Lead EMEA Agenda Introduction A typical data centre facility program A converged approach The data centre

More information

Functions & Importance of a Strategic Business Plan

Functions & Importance of a Strategic Business Plan Functions & Importance of a Strategic Business Plan Komal A Gulich, CRM, IGP Manager, Enterprise Records Management FirstEnergy Service Co April 15, 2014 Agenda Brief recap of Workshop Look at Function

More information

At the Heart of Virtualizing Insurance

At the Heart of Virtualizing Insurance At the Heart of Virtualizing Insurance New Era in Property and Casualty (P&C) Insurance Cloud Computing Strategic Implementation of Cloud Computing Services Adds Effectiveness and Efficiency to the Insurance

More information

Benefits of Deploying VirtualWisdom with HP Converged Infrastructure March, 2015

Benefits of Deploying VirtualWisdom with HP Converged Infrastructure March, 2015 Benefits of Deploying VirtualWisdom with HP Converged Infrastructure March, 2015 Version 1 Introduction: Yesterday was Silos, Today is integrated! Business needs today can't be met with yesterday's IT.

More information