1 For the period ending 30 June 2008 Exploration and Development Activity Over the last year, exploration and development work at the Company s Nullagine Gold Project in Western Australia s eastern Pilbara has been focused on increasing the resource base of the highgrade Blue Spec deposit to underpin Northwest s development strategy together with building up a pipeline of high priority gold targets as a basis for future exploration success. The Company s current global JORC resource for the Nullagine Gold Project totals 1.33 Mt grading 8.3 g/t gold for 353,000 oz and 7,300 tonnes of antimony grading 1.02%. The global resource comprises: The advanced Blue Spec deposit (323,000t grading 24.3 g/t gold for 253,000 oz and 5,550t of antimony grading 1.72%). A series of satellite deposits within development distance of Blue Spec (738,000t grading 3.9g/t gold for 92,000 oz of gold and 1,550t of antimony grading 1.13%). Assessment of updated Blue Spec JORC resource The updated Blue Spec resource is divided into two zones (the Upper Zone and Lower Zone) based on contained metal and drilling density. The Upper Zone of the Blue Spec deposit ( m vertical) contains greater than 1,000 ounces per vertical metre of gold over 120m immediately below the existing underground access. The Lower Zone of the Blue Spec deposit ( m vertical), whilst defining highgrade mineralisation down to the 850m vertical level, indicates a resource containing approximately 320 ounces per vertical metre of gold over a depth extent of 410m. The Company s assessment of the updated resource for the Blue Spec deposit indicated that there is some uncertainty in relation to the current grade estimation in the Lower Zone of the resource primarily related to low drilling density. Figure 1. (Opposite) Blue Spec deposit showing the existing shaft and decline (green) and indicative decline design (purple) over the m vertical zone Northwest Resources Limited ACN ASX code: NWR
2 During drilling, the Company experienced difficulties successfully targeting the interpreted highergrade zones of mineralisation within the Lower Zone from surface. Accordingly, the gold grade estimation in the Lower Zone may not reflect the true potential of the Blue Spec ore body at depth. Further opportunities at Blue Spec Following the assessment of the updated Blue Spec JORC resource and the Company s review of a number of potential development options for the Blue Spec deposit, the Company believes that there are significant opportunities to increase the current JORC resource at the Blue Spec deposit by undertaking further exploration and development, including: 1. Underground drilling aimed at confirming higher grade mineralisation in the Lower Zone resource (234,000t grading 17.5 g/t gold for 132,000 oz from m vertical) which could contribute to a resource upgrade The Company has identified several areas within the Lower Zone which it considers have the potential for higher grade mineralisation if subjected to additional successful drill testing. This could contribute to an upgrade of the resource estimation within the Lower Zone. Extensional diamond drilling of the Lower Zone has recorded some very significant intersections, including 2.5m grading g/t Au & 14.75% Sb from 715m downhole. The difficulties associated with successfully targeting the interpreted highergrade zones of mineralisation within the Lower Zone from surface could be addressed by underground drilling following on from developing the Upper Zone of the Blue Spec resource. 2. Drilling and bulk sampling aimed at converting nonjorc Remnant Zone target mineralisation potential (85100,000t grading 1418 g/t gold for 4550,000 oz from surface to 180m vertical) into JORC resources. The Company has also identified a significant amount of remnant mineralisation potential within the historical upper levels of the Blue Spec underground (referred to as the Remnant Zone). This is thought to reflect a combination of poor development in the historical upper levels of the underground and a poor understanding of the ore body morphology with depth. A target mineralization (nonjorc) of approximately 4550,000 ounces (grading 1418g/t gold) of remaining gold has been projected for the Remnant Zone 1. The quantification of mineralization (nonjorc) in four pillars in the Remnant Zone has been completed by previous owners from historical surface drilling. The pillars which have been drilled are estimated to contain 1416,000 oz of gold mineralisation with pillar grades averaging 16g/t gold. Future development plans In order to realise the full potential of the Blue Spec deposit, the Company has decided to seek a coventurer with underground mining expertise to progress the development of the Blue Spec deposit. The Company believes that the involvement of a coventurer will minimize development and production risk to the Company whilst enabling it to benefit from any development success. This decision has been reinforced by the industry wide shortage of suitably qualified mining engineers and skilled underground miners available in Western Australia. The Company is in discussions with a number of parties who have expressed an interest in participating in the project s development. The Company proposes to undertake further engineering and preliminary metallurgical investigations as part of scoping studies on development options for the Blue Spec deposit. Page 2 of 11
3 The Company will also continue its review of a proposal to increase project revenue in a production scenario by employing conventional electrowinning of antimony concentrates to produce a higher value antimony metal together with increased gold recoveries. Antimony market fundamentals are very positive with industry forecasts indicating that the current metal price of over US$6,000 per tonne is sustainable over the medium term. Project well positioned for development The Company s Nullagine Gold Project is located approximately two hours drive from the Pilbara hub of Newman and is very well served by existing infrastructure, including: 1. Underground shaft and decline development at Blue Spec A triple compartment shaft down to 195m vertical and a decline from the 165m vertical level of the shaft to 310m vertical level was installed by Anglo American. Future refurbished of the existing underground infrastructure would allow direct access to Blue Spec s current resources. Figure 1. Anglo decline and shaft at Blue Spec in Treatment plant The conventional CIP plant located adjacent to the Blue Spec deposit was commissioned in 1988 and was specifically designed to deal with goldstibnite ores. The CIP plant has a crushing and grinding circuit capacity of 100,000t per annum with leaching and CIP facilities capable of 38,000t per annum throughput. Future refurbishment, together with the installation of additional float cells could result in the plant's throughput being increased to 100,000t per annum without the need for extensive redesigning. The plant s unit processes employed for gold and antimony recovery from ore consist of two stage crushing; conventional ball milling; cyclone classification with gravity separation on the circulating load; float cells; pressure leach vessels and carbon in pulp (CIP) adsorption. 3. Camp A fully serviced mining camp with accommodation and ancillary facilities for up to 32 men is located on site. The camp includes offices, generator facilities, storage facilities and phone and internet connection. Page 3 of 11
4 4. Bore field and pipes The plant and camp are connected to a bore field located 12kms to the east of the project and the Company has a licence to extract up to 100,000t of water per annum from the field which is anticipated to be sufficient to enable the processing of up to 100,000t of ore per annum. A second bore field and water storage dam are also located within the project. Figure 2. The treatment plant, offices and storage facilities New Exploration Results The Company has identified an exciting new gold target 12 km to the west of its highgrade Blue Spec deposit within the Company s Nullagine Gold Project. The target, named Red Dragon, is over 450m in strike length and is hosted along the interpreted western extension of the Blue Spec Shear. A map showing the Red Dragon target is overleaf. Red Dragon was identified by Northwest s team following analysis of data collected from the Company s innovative airborne HYMAP survey carried out over the entire Mosquito Creek basin (an area of approximately 3,000 km 2 ) which hosts the Nullagine goldfield. The HYMAP survey identified a number of significant alteration anomalies within the goldfield. The Red Dragon target was prioritised owing to the large size of the alteration anomaly and its location along the interpreted western extension of the Blue Spec Shear. Detailed structural mapping over the southern half of the Red Dragon target has confirmed a wide zone of structural complexity in association with multiple zones of quartzcarbonate veining. An extensive follow up geochemical soil sampling and rock chipping programme delineated a +50ppb gold anomaly over 450m in strike length. The potential of HYMAP surveying for remote detection of gold bearing alteration systems Northwest completed its HYMAP survey over the entire Mosquito Creek basin as part of an innovative study to determine the alteration signature of gold mineralisation within the Nullagine goldfield. The Company undertook a rigorous study of existing gold resources, involving the spectral analysis of thousands of drill samples, which resulted in a definitive alteration foot printing model being developed for the goldfield. Using the same response signal recognised around the existing resources, Northwest believes it is able to utilise the HYMAP dataset to remotely detect gold bearing alteration systems within the goldfield. The application of spectral alteration mapping (HYMAP) is unique to the Nullagine goldfield and gives Northwest a competitive exploration advantage. Page 4 of 11
5 Page 5 of 9 Page 5 of 11
6 Red Dragon For the period ending 31 March 2008 The very close correlation between the gold alteration signature identified by the HYMAP survey, the structural complexity recognised from surface mapping and the positive gold assays from the geochemical sampling programme over the target suggest the Red Dragon target is an important new find. The Red Dragon target is interpreted to represent a significant splay position along the western extension of the Blue Spec Shear. Northwest s highgrade Blue Spec deposit is localised by a similar splay structure and these splays are recognised by Northwest as an important structural control for locating highgrade shoot positions along the shear. The Red Dragon target is now being prioritised and included in a list of 17 highpriority targets that are being progressed to drill ready status. Corporate Activity During the, the Company appointed Mr. Peter Richard as a nonexecutive director. Mr. Richard, 62, is a former stockbroker with over 35 years experience in Australian capital markets. During a long career in the stock markets, Mr Richard was a director of Jacksons Ltd, then the largest underwriter of mining and exploration floats in Australia. Mr Richard currently provides consulting services to emerging mining and technology companies. He has previously been a director of a number of listed public companies in Australia and most recently he was a director of Magnum Exploration NL. The information in this report that relates to exploration results or mineral resources is based on information compiled by Mr. Christian Easterday, who is a Member of the Australian Institute of Geoscientists. Mr. Easterday is employed by Mining Technical Solutions Pty Ltd and has sufficient experience which is relevant to the style of mineralisation and type of deposit under consideration and to the activity which he is undertaking to qualify as a Competent Person as defined in the 2004 Edition of the Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves. Mr. Easterday consents to the inclusion in the report of the matters based on his information in the form and context in which it appears. Note 1: Target mineralisation in the Remnant Zone of the Blue Spec deposit should not be misunderstood or misconstrued as a mineral resource or mining reserve as defined by the JORC Code. It is uncertain if further exploration or feasibility studies will result in the determination of a mineral resource or mining reserve in respect of remnant mineralisation. Page 6 of 11
7 ASX Listing Rules Appendix 5B Mining exploration entity ly cash flow report Name of entity Northwest Resources Limited ABN Quarter ended ( current ) June 2008 Consolidated statement of cash flows Cash flows related to operating activities Current Year to date (12 months) 1.1 Receipts from product sales and related debtors 1.2 Payments for: (a) exploration and evaluation (1,170) (5,453) (b) development (c) production (d) administration (212) (972) 1.3 Dividends received 1.4 Interest and other items of a similar nature received 1.5 Interest and other costs of finance paid 1.6 Income taxes paid 1.7 GST Net Operating Cash Flows (1,173) (6,039) Cash flows related to investing activities 1.8 Payment for purchase of: (a) prospects (b) equity investments (c) other fixed assets (2) (20) 1.9 Proceeds from sale of: (a) prospects (b) equity investments 1 (c) other fixed assets Loans to other entities 1.11 Loans repaid by other entities 1.12 Other (provide details if material) Net investing cash flows (2) Total operating and investing cash flows (carried forward) (1,175) (6,031) 1.14 Total operating and investing cash flows (brought forward) (1,175) (6,031) Page 7 of 11
8 Cash flows related to financing activities 1.14 Proceeds from issues of shares, options, etc. 8, Proceeds from sale of forfeited shares 1.16 Proceeds from borrowings Repayment of borrowings (7) (68) 1.18 Dividends paid 1.19 Other (provide details if material) Net financing cash flows (7) 8,914 Net increase (decrease) in cash held (1,182) 2, Cash at beginning of /year to date 9,472 5, Exchange rate adjustments to item Cash at end of 8,290 8,290 Payments to directors of the entity and associates of the directors Payments to related entities of the entity and associates of the related entities Current $A' Aggregate amount of payments to the parties included in item Aggregate amount of loans to the parties included in item Explanation necessary for an understanding of the transactions NonExecutive director s fees and Executive directors salaries Non cash financing and investing activities 2.1 Details of financing and investing transactions which have had a material effect on consolidated assets and liabilities but did not involve cash flows Nil 2.2 Details of outlays made by other entities to establish or increase their share in projects in which the reporting entity has an interest Nil Page 8 of 11
9 Financing facilities available Add notes as necessary for an understanding of the position. Amount available Amount used 3.1 Loan facilities 3.2 Credit standby arrangements Estimated cash outflows for next 4.1 Exploration and evaluation Development Total 250 Reconciliation of cash Reconciliation of cash at the end of the (as shown in the consolidated statement of cash flows) to the related items in the accounts is as follows. Current Previous 5.1 Cash on hand and at bank Deposits at call 7,790 9, Bank overdraft 5.4 Other (provide details) Total: Cash at end of (item 1.22) 8,290 9,472 Changes in interests in mining tenements 6.1 Interests in mining tenements relinquished, reduced or lapsed 6.2 Interests in mining tenements acquired or increased Tenement reference Nil Nil Nature of interest (note (2)) Interest at beginning of Interest at end of Page 9 of 11
10 Issued and quoted securities at end of current Description includes rate of interest and any redemption or conversion rights together with prices and dates. 7.1 Preference + securities (description) 7.2 Changes during (a) Increases through issues (b) Decreases through returns of capital, buybacks, redemptions Ordinary securities 7.4 Changes during (a) Increases through issues (b) Decreases through returns of capital, buybacks Convertible debt securities (description) 7.6 Changes during (a) Increases through issues (b) Decreases through securities matured, converted 7.7 Options (description and conversion factor) 7.8 Issued during 7.9 Exercised during 7.10 Expired during 7.11 Debentures (totals only) 7.12 Unsecured notes (totals only) Total number Number quoted Issue price per security (see note 3) (cents) 132,770, ,770,418 Exercise price Amount paid up per security (see note 3) (cents) Expiry date Page 10 of 11
11 Compliance statement 1. This statement has been prepared under accounting policies which comply with accounting standards as defined in the Corporations Act or other standards acceptable to ASX. 2. This statement does give a true and fair view of the matters disclosed. Date: 31 July 2008 John J. Merity Managing Director Notes 1. The ly report provides a basis for informing the market how the entity s activities have been financed for the past and the effect on its cash position. An entity wanting to disclose additional information is encouraged to do so, in a note or notes attached to this report. 2. The Nature of interest (items 6.1 and 6.2) includes options in respect of interests in mining tenements acquired, exercised or lapsed during the reporting period. If the entity is involved in a joint venture agreement and there are conditions precedent which will change its percentage interest in a mining tenement, it should disclose the change of percentage interest and conditions precedent in the list required for items 6.1 and Issued and quoted securities: The issue price and amount paid up is not required in items 7.1 and 7.3 for fully paid securities. 4. The definitions in, and provisions of, AASB 1022: Accounting for Extractive Industries and AASB 1026: Statement of Cash Flows apply to this report. 5. Accounting Standards: ASX will accept, for example, the use of International Accounting Standards for foreign entities. If the standards used do not address a topic, the Australian standard on that topic (if any) must be complied with. Northwest Resources Limited ACN Corporate Office: Suite 3, 9 Banksia Road, Bellevue Hill, Sydney NSW 2023 Tel: (02) Fax: (02) Exploration Office: Level 6, 256 Adelaide Terrace, Perth WA 6000 Tel: (08) Fax: (08) info@nwresources.com.au Web:
Appendix 5B. Mining exploration entity quarterly report. Quarter ended ( current quarter ) 108 476 384 30 September 2015
Mining exploration entity ly report Appendix 5B Rule 5.3 Mining exploration entity ly report Introduced 1/7/96. Origin: Appendix 8. Amended 1/7/97, 1/7/98, 30/9/2001, 01/06/10. Name of entity Aurelia Metals
More informationAppendix 5B. Mining exploration entity quarterly report. Quarter ended ( current quarter ) 65 094 206 292 30 June 2013
Mining exploration entity ly report Appendix 5B Rule 5.3 Mining exploration entity ly report Introduced 01/07/96 Origin Appendix 8 Amended 01/07/97, 01/07/98, 30/09/01, 01/06/10, 17/12/10 Name of entity
More informationFor personal use only
Mining exploration entity and oil and gas exploration entity ly report Rule 5.5 Mining exploration entity and oil and gas exploration entity ly report Introduced 01/07/96 Origin Appendix 8 Amended 01/07/97,
More informationAppendix 5B. Introduced 01/07/96 Origin Appendix 8 Amended 01/07/97, 01/07/98, 30/09/01, 01/06/10, 17/12/10, 01/05/2013
Appendix 5B Rule 5.5 Mining exploration entity and oil and gas exploration entity ly report Introduced 01/07/96 Origin Appendix 8 Amended 01/07/97, 01/07/98, 30/09/01, 01/06/10, 17/12/10, 01/05/2013 Name
More informationAppendix 5B. Quarter ended ( current quarter ) 51 153 918 257 31 December 2013
Appendix 5B Rule 5.3 Introduced 1/7/96. Origin: Appendix 8. Amended 1/7/97, 1/7/98, 30/9/2001, 01/06/10. Name of entity HIGHFIELD RESOURCES LIMITED ABN Quarter ended ( current quarter ) 51 153 918 257
More informationFor personal use only
Rule 5.3 Introduced 1/7/96. Origin: Appendix 8. Amended 1/7/97, 1/7/98, 30/9/2001, 01/06/10. Name of entity WOLF PETROLEUM LIMITED ABN Quarter ended ( current quarter ) 35 116 249 060 31 MARCH 2014 Consolidated
More informationAppendix 5B. Mining exploration entity quarterly report. Quarter ended ( current quarter ) 38 119 047 693 30 September 2011
Appendix 5B Rule 5.3 Introduced 1/7/96. Origin: Appendix 8. Amended 1/7/97, 1/7/98, 30/9/2001, 01/06/10. Name of entity COPPER RANGE LIMITED ABN Quarter ended ( current quarter ) 38 119 047 693 30 September
More informationAppendix 5B. Mining exploration entity quarterly report
Mining exploration entity ly report Appendix 5B Rule 5.3 Mining exploration entity ly report Introduced 01/07/96 Origin Appendix 8 Amended 01/07/97, 01/07/98, 30/09/01, 01/06/10, 17/12/10 Name of entity
More informationFor personal use only
Appendix 5B Mining exploration entity quarterly report Introduced 01/07/96 Origin Appendix 8 Amended 01/07/97, 01/07/98, 30/09/01, 01/06/10, 17/12/10 Name of entity Vital Metals Ltd ABN Quarter ended (
More informationAppendix 5B Mining exploration entity and oil and gas exploration entity quarterly report. Appendix 5B
Mining exploration entity and oil and gas exploration entity ly report Appendix 5B Rule 5.5 Mining exploration entity and oil and gas exploration entity ly report Introduced 01/07/96 Origin Appendix 8
More informationAppendix 5B. Quarter ended ( current quarter ) 68 064 120 896 31 December 2015. Net Operating Cash Flows (568) (1,210)
Appendix 5B Rule 5.3 Introduced 01/07/96 Origin Appendix 8 Amended 01/07/97, 01/07/98, 30/09/01, 01/06/10, 17/12/10 Name of entity GLOBAL PETROLEUM LIMITED ABN Quarter ended ( current ) 68 064 120 896
More informationAppendix 5B. Quarter ended ( current quarter ) 68 064 120 896 31 March 2015. Net Operating Cash Flows (512) (2,380)
Appendix 5B Rule 5.3 Introduced 01/07/96 Origin Appendix 8 Amended 01/07/97, 01/07/98, 30/09/01, 01/06/10, 17/12/10 Name of entity GLOBAL PETROLEUM LIMITED ABN 68 064 120 896 31 March 2015 Quarter ended
More informationAppendix 5B. Mining exploration entity and oil and gas exploration
Appendix 5B Rule 5.5 Mining exploration entity and oil and gas exploration entity quarterly report Introduced 01/07/96 Origin Appendix 8 Amended 01/07/97, 01/07/98, 30/09/01, 01/06/10, 17/12/10, 01/05/2013
More informationAppendix 5B. Introduced 01/07/96 Origin Appendix 8 Amended 01/07/97, 01/07/98, 30/09/01, 01/06/10, 17/12/10. Quarter ended ( current quarter )
Mining exploration entity ly report Appendix 5B Rule 5.3 Mining exploration entity ly report Introduced 01/07/96 Origin Appendix 8 Amended 01/07/97, 01/07/98, 30/09/01, 01/06/10, 17/12/10 Name of entity
More informationFor personal use only
Rule 5.3 Mining exploration entity quarterly report Introduced 1/7/96. Origin: Appendix 8. Amended 1/7/97, 1/7/98, 30/9/2001. Name of entity Enterprise Metals Limited ABN Quarter ended ( current quarter
More informationAppendix 5B. Mining exploration entity quarterly report. Quarter ended ( current quarter ) 44 009 163 919 31 December 2015
Mining exploration entity ly report Appendix 5B Rule 5.3 Mining exploration entity ly report Introduced 1/7/96. Origin: Appendix 8. Amended 1/7/97, 1/7/98, 30/9/2001. Name of entity NIUMINCO GROUP LIMITED
More informationAppendix 5B Mining exploration entity quarterly report
Name of entity Appendix 5B SEGUE RESOURCES LTD Rule 5.3 ABN Quarter ended ("current quarter") 49 112 609 846 31 December 2015 Consolidated statement of cash flows Cash flows related to operating activities
More informationQuarterly Report Highlights. Ulysses Gold Project, Western Australia. Viking Gold Project, Western Australia
ASX Announcement Quarterly Activities Report For the Quarter Ended 31 December 2015 29 January 2016 Genesis Minerals Limited ASX Code: GMD Issued Capital 446 million shares 27.2 million options Current
More informationAppendix 5B. Mining exploration entity quarterly report. Quarter ended ( current quarter ) 68 073 914 191 31 December 2015
Appendix 5B Rule 5.3 Name of entity AUSTRALIAN MINES LIMITED AUZ ABN Quarter ended (current quarter ) 68 073 914 191 31 December 2015 Consolidated statement of cash flows Cash flows related to operating
More informationAppendix 5B. Mining exploration entity and oil and gas exploration entity quarterly report
Mining exploration entity and oil and gas exploration entity ly report Appendix 5B Mining exploration entity and oil and gas exploration entity ly report Introduced 01/07/96 Origin Appendix 8 Amended 01/07/97,
More informationAppendix 5B. Mining exploration entity quarterly report LACONIA RESOURCES LIMITED 29 137 984 297 31 DECEMBER 2015
Appendix 5B Rule 5.3 Introduced 01/07/96 Origin Appendix 8 Amended 01/07/97, 01/07/98, 30/09/01, 01/06/10, 17/12/10 Name of entity LACONIA RESOURCES LIMITED ABN Quarter ended ( current quarter ) 29 137
More informationAppendix 5B Mining exploration entity and oil and gas exploration entity quarterly report. Appendix 5B. Mining exploration entity quarterly report
Mining exploration entity and oil and gas exploration entity ly report Appendix 5B Rule 5.5 Mining exploration entity ly report Introduced 01/07/96 Origin Appendix 8 Amended 01/07/97, 01/07/98, 30/09/01,
More informationFor personal use only
Rule 5.5 Introduced 01/07/96 origin Appendix 8 Amended 01/07/97, 01/07/98, 30/09/01, 01/06/10, 17/12/10, 01/05/2013 Name of entity EQUUS MINING LIMITED ABN Quarter ended ( current ) 44 065 212 679 31 December
More informationAppendix 5B. Mining exploration entity quarterly report. Quarter ended ( current quarter ) 46 168 910 978 31 December 2015
Appendix 5B Rule 5.3 Introduced 01/07/96 Origin Appendix 8 Amended 01/07/97, 01/07/98, 30/09/01, 01/06/10, 17/12/10 Name of entity TIAN POH RESOURCES LIMITED ABN Quarter ended ( current ) 46 168 910 978
More informationQUARTERLY ACTIVITIES REPORT FOR PERIOD ENDED 30 SEPTEMBER 2015
ASX RELEASE ASX:AWV 30 October 2015 QUARTERLY ACTIVITIES REPORT FOR PERIOD ENDED 30 SEPTEMBER 2015 HIGHLIGHTS Pit optimisation and final mine design completed Metallurgical test work completed Engineering
More informationAppendix 5B Mining exploration entity and oil and gas exploration entity quarterly report. Appendix 5B. Mining exploration entity quarterly report
Mining exploration entity and oil and gas exploration entity ly report Appendix 5B Rule 5.5 Mining exploration entity ly report Introduced 01/07/96 Origin Appendix 8 Amended 01/07/97, 01/07/98, 30/09/01,
More informationAPPENDIX 5B Mining exploration entity quarterly report
1 of 5 APPENDIX 5B Mining exploration entity quarterly report TORO ENERGY LTD Quarter ended ABN. 48 117 127 590 June 2015 Consolidated statement of cash flows (Note 6.0) Cash flows related to operating
More informationACTIVITIES REPORT FOR THE QUARTER ENDED 31 DECEMBER 2014
Second Floor, 9 Havelock Street West Perth WA 6005 Postal Address: PO Box 689, West Perth WA 6872 ABN 60 060 628 524 Telephone: (618) 9481 8444 Facsimile: (618) 9481 8445 Email: info@hamptonhill.com.au
More informationJohnnycake (EPM 18986) - background
Forte Consolidated Limited QUARTERLY REPORT 1 October 2015 to 31 December 2015 ASX: FRC Forte Consolidated Limited ABN 37 148 168 825 Board of Directors Chairman Executive Director John Terpu Non-Executive
More informationJUNE 2015 QUARTERLY REPORT
ANNOUNCEMENT TO THE AUSTRALIAN SECURITIES EXCHANGE: 31 JULY 2015 JUNE 2015 QUARTERLY REPORT WCP Resources Limited ( WCP or Company ) presents its June 2015 quarterly report. Highlights during the quarter
More informationAppendix 5B. Mining exploration entity quarterly report. Crusader Resources Limited. 94 106 641 963 30 Sept 2015
Appendix 5B Mining exploration entity ly report Mining exploration entity ly report Introduced 1/7/96. Origin: Appendix 8. Amended 1/7/97, 1/7/98, 30/9/2001. Name of entity Crusader Resources Limited ABN
More informationFor personal use only
Rule 5.3 Introduced 1/7/96. Origin: Appendix 8. Amended 1/7/97, 1/7/98, 30/9/2001, 01/06/10. Name of entity THE CARAJAS COPPER COMPANY LIMITED ABN Quarter ended ( current quarter ) 88 076 390 451 30 SEPTEMBER
More informationAppendix 5B Mining exploration entity and oil and gas exploration entity quarterly report. Appendix 5B
Appendix 5B Mining exploration entity and oil and gas exploration entity quarterly report Introduced 01/07/96 Origin Appendix 8 Amended 01/07/97, 01/07/98, 30/09/01, 01/06/10, 17/12/10, 01/05/2013 Rule
More informationSeptember 2010 Quarterly Report
September 2010 Quarterly Report 25th October 2010 Corporate Details ASX Code: RCO Issued Capital: 52,714,183 Shares 2,950,000 Options @ 40c, 31/3/2011 (Unlisted) 510,000 Options @ 42c, 31/3/2011 (Unlisted)
More informationASX ANNOUNCEMENT JUNE 2015 QUARTERLY REPORT 31 JULY 2015
ASX ANNOUNCEMENT 31 JULY 2015 JUNE 2015 QUARTERLY REPORT The Directors of Odyssey Energy Limited ( Odyssey or Company ) are pleased to present the June 2015 ly report. Highlights during, and subsequent
More informationAppendix 5B. Mining exploration entity quarterly report. Quarter ended ( current quarter ) 85 003 257 556 30 September 2013
Appendix 5B Rule 5.3 Introduced 1/7/96. Origin: Appendix 8. Amended 1/7/97, 1/7/98, 30/9/2001, 01/06/10. Name of entity MILLENNIUM MINERALS LIMITED ABN Quarter ended ( current ) 85 003 257 556 30 September
More informationQUARTERLY ACTIVITIES REPORT FOR PERIOD ENDED 31 DECEMBER 2015
ASX RELEASE ASX:AWV 29 January 2015 QUARTERLY ACTIVITIES REPORT FOR PERIOD ENDED 31 DECEMBER 2015 HIGHLIGHTS Review of updated pit optimisation undertaken Metallurgical testwork report received confirming
More informationAppendix 5B. Mining exploration entity quarterly report. Quarter ended ( current quarter ) 85 126 379 646 31 December 2015
Appendix 5B.Rule 5.3 Introduced 1/7/96. Origin: Appendix 8. Amended 1/7/97, 1/7/98, 30/9/2001. Name of entity AVANCO RESOURCES LIMITED ABN Quarter ended ( current ) 85 126 379 646 31 December 2015 Consolidated
More informationAppendix 5B. Mining exploration entity quarterly report. Quarter ended ( current quarter ) 70 121 539 375 31 DECEMBER 2015
Mining exploration entity ly report Appendix 5B Rule 5.3 Mining exploration entity ly report Introduced 01/07/96 Origin Appendix 8 Amended 01/07/97, 01/07/98, 30/09/01, 01/06/10, 17/12/10 Name of entity
More informationQUARTERLY ACTIVITIES AND CASH FLOW REPORT. PERIOD ENDED 31 March 2015
30 April 2015 QUARTERLY ACTIVITIES AND CASH FLOW REPORT PERIOD ENDED 31 March 2015 Baraka Energy & Resources Limited Contacts: Collin Vost Issued Capital: 2,225,337,344 Ordinary Shares Telephone: 08 6436
More informationAppendix 5B. Quarter ended ( current quarter )
Appendix 5B Rule 5.5 Introduced 01/07/96 Origin Appendix 8 Amended 01/07/97, 01/07/98, 30/09/01, 01/06/10, 17/12/10, 01/05/2013 Name of entity WPG Resources Ltd ABN Quarter ended ( current quarter ) 51
More informationAppendix 5B Mining exploration entity quarterly report
Appendix 5B Rule 5.3 Name of entity YILGARN GOLD LIMITED ABN Quarter ended ("current quarter") 34 002 527 906 31 December 2004 Consolidated statement of cash flows Cash flows related to operating activities
More informationReport for the Quarter Ended 30 September 2015
Report for the Quarter Ended 30 September 2015 ASX: KIS Market Capitalisation $18.2 million Shares on Issue 165.3 million 52 Week High 16.5 cents 52 Week Low 8.9 cents Share Price Board of Directors Johann
More informationAppendix 5B. RNI NL and its controlled entities. Quarter ended ( current quarter ) 77 085 806 284 30 Jun 2016
Appendix 5B Rule 5.3 Introduced 1/7/96. Origin: Appendix 8. Amended 1/7/97, 1/7/98, 30/9/2001, 01/06/10. Name of entity RNI NL and its controlled entities ABN Quarter ended ( current quarter ) 77 085 806
More informationDECEMBER 2015 QUARTERLY REPORT HIGHLIGHTS
29 th January 2016 DECEMBER 2015 QUARTERLY REPORT HIGHLIGHTS Minerals Development Licence (MDL) formal application lodged with all requested associated technical documentation, awaiting Departmental approval
More informationSeptember 2015 Quarterly Activities Report
ASX RELEASE 31 OCT 2015 September 2015 Quarterly Activities Report Expansion of Premier JV Gold Mine to 40,000ozpa production rate on track and future production growth plans advanced Highlights Production
More informationAppendix 5B. Mining exploration entity and oil and gas exploration entity quarterly report
Mining exploration entity and oil and gas exploration entity ly report Appendix 5B Mining exploration entity and oil and gas exploration entity ly report Introduced 01/07/96 Origin Appendix 8 Amended 01/07/97,
More informationQUARTERLY REPORT FOR THE PERIOD TO 31 MAY 2012
QUARTERLY REPORT FOR THE PERIOD TO 31 MAY 2012 Metals Finance Limited (ASX: MFC) is pleased to provide its Quarterly Activities Report for the three month period ending 31 May 2012. HIGHLIGHTS Separate
More informationAppendix 5B Mining exploration entity and oil and gas exploration entity quarterly report. Appendix 5B
Mining exploration entity and oil and gas exploration entity ly report Appendix 5B Rule 5.5 Mining exploration entity and oil and gas exploration entity ly report Introduced 01/07/96 Origin Appendix 8
More informationReport for the Quarter Ended 31 December 2015
Report for the Quarter Ended 31 December 2015 ASX: KIS Market Capitalisation $13.2 million Shares on Issue 165.3 million 52 Week High 16.5 cents 52 Week Low 7.5 cents Share Price Board of Directors Johann
More informationThe significant milestones achieved by New Age Exploration Limited ( NAE or the Company ) during this period include:
Quarterly Report To 31 December 2015 New Age Exploration Limited ( NAE or "the Company") is pleased to provide shareholders the Company s Quarterly Report for the period ending 31 December 2015. Highlights
More informationMGT Resources Limited 1305/109 Pitt St Sydney NSW 2000 Australia. December Quarterly Report QUARTERLY REPORT
QUARTERLY REPORT December 2015 December Quarterly Report Exploration Activities Report Quarter ended 31 st December 2015 During the December, MGT Resources Limited (MGT, ASX:MGS) worked towards finalising
More informationAppendix 5B. Mining exploration entity quarterly report
Appendix 5B Rule 5.3 Introduced 01/07/96 Origin Appendix 8 Amended 01/07/97, 01/07/98, 30/09/01, 01/06/10, 17/12/10 Name of entity Australian Bauxite Limited ABN Quarter ended ( current ) 14 139 494 885
More informationAppendix 5B. Mining exploration entity quarterly report. Crusader Resources Limited. Quarter ended ( current quarter ) 94 106 641 963 31 Dec 2015
Mining exploration entity ly report Appendix 5B Mining exploration entity ly report Introduced 1/7/96. Origin: Appendix 8. Amended 1/7/97, 1/7/98, 30/9/2001, 01/05/2013 Name of entity Crusader Resources
More informationQuarterly Activities Report - for the period ended 31 December 2015
ASX Release: 27 January 2016 Quarterly Activities Report - for the period ended 31 December 2015 ASX Code: WRM Issued Securities Shares: 271.9 million Options: 7 million Cash on hand (31 Dec 2015) $0.4M
More informationRuby Joint Venture commenced to explore Montepuez East Ruby Project in Mozambique Kroussou Zinc-Lead Project in Gabon advancing
ASX Announcement 29 January 2016 ACTIVITIES FOR THE QUARTER ENDED 31 DECEMBER 2015 The 31 December 2015 capped off what has been an exceptional year for Metals of Africa Limited (ASX: MTA) ( the Company
More informationQuarterly Report. For the Quarter Ended 30 June 2004. Vulcan is maintaining its low cost exposure to West Australian gold exploration.
Quarterly Report For the Quarter Ended 30 June 2004 Vulcan is maintaining its low cost exposure to West Australian gold exploration. Yerilla Joint Venture (Sons of Gwalia earning 75%) Sons of Gwalia are
More informationAppendix 5B. Mining exploration entity quarterly report. Quarter ended ( current quarter ) 64 065 480 453 31 December 2013
The Waterberg Coal Company Limited (formerly Range River Gold Limited) (Incorporated in Australia) (Registration number ABN 64 065 480 453) ASX: WCC JSE: WCC ISIN: AU000000WCC9 ( WCC or the Company ) Appendix
More informationAppendix 5B. Mining exploration entity and oil and gas exploration entity quarterly report
Appendix 5B Rule 5.5 Mining exploration entity and oil and gas exploration entity quarterly report Introduced 01/07/96 Origin Appendix 8 Amended 01/07/97, 01/07/98, 30/09/01, 01/06/10, 17/12/10, 01/05/2013
More informationQUARTERLY ACTIVITES AND CASH FLOW REPORT PERIOD ENDED
21 st January 2016 QUARTERLY ACTIVITES AND CASH FLOW REPORT PERIOD ENDED 31 st DECEMBER 2015 CONTACTS: Collin Vost Telephone: 08 6436 2350 ISSUED CAPITAL: 2,225,337,344 Ordinary Shares Directors: Collin
More informationAppendix 5B. Mining exploration entity quarterly report. Quarter ended ( current quarter ) 64 065 480 453 31 March 2014
Appendix 5B Rule 5.3 Introduced 1/7/96. Origin: Appendix 8. Amended 1/7/97, 1/7/98, 30/9/2001. Name of entity THE WATERBERG COAL COMPANY LIMITED ABN Quarter ended ( current ) 64 065 480 453 31 March 2014
More informationQUARTERLY REPORT FOR THE QUARTER ENDED 31 DECEMBER 2015
QUARTERLY REPORT FOR THE QUARTER ENDED 31 DECEMBER 2015 KIHABE ZINC LEAD SILVER PROJECT BOTSWANA On 11 November 2015, the Company received an email from the Assistant Permanent Secretary, Ministry of Minerals
More informationMerlin Diamonds Limited
Merlin s Limited 29 January 2016 Manager Companies Australian Securities Exchange Level 6, 20 Bridge Street Sydney NSW 2000 By ELodgement REPORT FOR THE QUARTER ENDED 31 DECEMBER 2015 Merlin s Limited
More informationQUARTERLY ACTIVITY REPORT FOR THE PERIOD ENDED 31 st December 2015
STRATEGIC MINERALS CORPORATION N.L. 29th January 2016 ASX Release ASX Code: SMC QUARTERLY ACTIVITY REPORT FOR THE PERIOD ENDED 31 st December 2015 WOOLGAR GOLD PROJECT QUEENSLAND (100% SMC) Highlights
More informationFor personal use only
SEPTEMBER 2011 QUARTERLY REPORT AND STATEMENT OF CASHFLOWS About TriAusMin (ASX:TRO) (TSX:TOR) TriAusMin Limited ( TriAusMin ) is an Australian development stage base and precious metals company focused
More informationQuarterly Activities Report For the quarter to 31 December 2015
Tawana Resources NL (Incorporated in Australia) (Registration number ACN 085 166 721) Share code on the JSE Limited: TAW ISIN: AU000000TAW7 Share code on the Australian Stock Exchange Limited: TAW ISIN:
More informationHighlights. Completion of farm-out in Tanzania. Drill support contract awarded in Tanzania. Competent Person s Report commissioned
FOR THE QUARTER ENDED 31 December 2015 Swala Energy Limited ACN 161 989 546 Level 4, 21 Kintail Road Applecross WA 6153 Australia TEL +61 (0) 8 6270 4700 FAX +61 (0) 8 6314 4675 EML info@swalaenergy.com
More informationQuarterly Activities Report
ASX Release Thursday 28 January 215 Quarterly Activities Report ASX Code: SAU Issued Shares: 36.53M Directors Greg Boulton AM (Chair) Simon Mitchell (MD) Michael Billing David Turvey Head Office Southern
More informationHighlights. Metro Mining Limited (ASX:MMI) Quarterly Activities Report September 2015. Successful Share Issue Raises A$5.6 Million
Metro Mining Limited (ASX:MMI) Quarterly Activities Report September 2015 Highlights Successful Share Issue Raises A$5.6 Million Successful Share Issue raises A$5.6 Million Non-binding bauxite Off-Take
More informationMarch 2015 Quarterly Activity Report and Appendix 5B
ABN 90 118 710 508 Ground Floor 1 Havelock Street West Perth WA 6000 t: +61 8 9488 5220 f: +61 8 324 2400 www.citation.net.au info@citation.net.au 30 April 2015 ASX Announcement March 2015 Quarterly Activity
More informationALCYONE REPORTS JORC SILVER RESOURCES
ASX ANNOUNCEMENT & MEDIA RELEASE 29 March 2010 ALCYONE REPORTS JORC SILVER RESOURCES +15Moz RESOURCE INVENTORY UNDERPINS PROGRAM TARGETING RESUMPTION OF SILVER PRODUCTION AT TEXAS PROJECT LATER THIS YEAR
More informationRC drilling identifies high grade gold in bedrock at Pacific Dunes Corkwood Camp Scale Target
ASX Announcement 29 January 2016 Quarterly Report For the period ending 31 December 2015 ASX Code GOR ABN 13 109 289 527 Highlights Solid progress on Gruyere Pre Feasibility Study Gruyere PFS remains on
More informationAppendix 5B Mining exploration entity and oil and gas exploration entity quarterly report. Appendix 5B
Appendix 5B Rule 5.5 Mining exploration entity and oil and gas exploration entity ly report Introduced 01/07/96 Origin Appendix 8 Amended 01/07/97, 01/07/98, 30/09/01, 01/06/10, 17/12/10, 01/05/2013 Name
More informationActivities Report & Cash Flow Statement For the 3 months ending 30 September 2015
Activities Report & Cash Flow Statement For the 3 months ending 30 September 2015 Page 1 Quarterly Activities and Cash Flow Statement For the 3 months ending 30 September 2015 (Period) Red Gum Resources
More informationFor personal use only
December 2015 Quarterly Activities Report Rumble Resources Ltd (ASX: RTR) ( Rumble or the Company ) is pleased to provide an update of the Company s activities during the December 2015. Rumble Resources
More information* Excluding unspent cash deposited by the Company in Joint Venture accounts
Quarterly Report For the period ended 30 September 2015 HIGHLIGHTS Closing cash of $6.2 million* Completion of MZ1 deep water exploration well offshore Morocco and postwell evaluation is underway ahead
More informationQUARTERLY ACTIVITIES REPORT FOR THE PERIOD ENDED 30 SEPTEMBER 2015
ASX ANNOUNCEMENT MEDIA RELEASE 30 October 2015 QUARTERLY ACTIVITIES REPORT FOR THE PERIOD ENDED 30 SEPTEMBER 2015 HIGHLIGHTS RC drilling identified wide mineralised gold zones north of original Namdini
More informationDECEMBER 2015 QUARTERLY ACTIVITIES REPORT
29 January 2016 DECEMBER 2015 QUARTERLY ACTIVITIES REPORT CORPORATE On the 14 December 2015, Namibian Copper NL (ASX Code: NCO) (Namibian Copper or the Company) announced that the Company had entered into
More informationMAXIMUS RESOURCES LIMITED QUARTERLY REPORT
MAXIMUS RESOURCES LIMITED QUARTERLY REPORT PERIOD ENDING 31 December 2015 SUMMARY CORPORATE Private share placement to sophisticated Investors was completed with $200,000 received A Share Purchase Plan
More informationSeptember 2015 Quarterly Report
September 2015 Quarterly Report 30 October 2015 The effects of industrial action on the Weeks Royalty in Bass Strait diminished through the with petroleum production moving back to more normal levels.
More informationFalcon Minerals Ltd ACN 009 256 535 Company Announcement
Falcon Minerals Ltd ACN 009 256 535 Company Announcement First Floor, 14 Outram Street, West Perth WA 6005 Telephone: +61 8 9481 3322 PO Box 913 West Perth WA 6872 Facsimile: +61 8 9481 3330 Date: 30 April
More informationDecember 2015 Quarterly Report
December 2015 Quarterly Report 29 January 2016 The downward spiral in oil prices coupled with ongoing industrial action in Bass Strait continues to impact receipts from the Weeks Royalty interest. Income
More informationFor personal use only
For personal use only 29 April 2011 Report on activities for the Quarter ended 31 March 2011 Highlights Africa: Morocco Tarfaya Offshore Block Awarded Tarfaya 2D and 3D seismic reprocessing contract to
More informationFor personal use only
1 QUARTERLY REPORT Atlantic Limited (ASX: ATI; Atlantic or the Company) is pleased to present its report for the ended 31 December 2010. HIGHLIGHTS WINDIMURRA Major sales agreement signed for 100% of ferrovanadium
More informationQUARTERLY REPORT FOR THE PERIOD ENDING 30 JUNE 2015
FOR THE PERIOD ENDING 30 JUNE 2015 30 July 2015 ASX Code: AGS No. of pages: 11 QUARTERLY REPORT FOR THE PERIOD ENDED 30 JUNE 2015 DETAILS OF ANNOUNCEMENT Quarterly Activity Report for the period ending
More informationHORSE WELL GOLD PROJECT W.A
December 2015 Quarterly Activities Report ABN 20 109 361 195 ASX Release 29 January 2016 Alloy Resources Ltd Suite 6, 7 The Esplanade Mount Pleasant WA 6153 Tel: +61 8 9316 9100 Fax: +61 8 9315 5475 Email:
More informationD e c e m b e r 2 0 1 5 Q u a r t e r l y A c t i v i t y R e p o r t
29 January 2016 ASX Release ASX Code: CXX D e c e m b e r 2 0 1 5 Q u a r t e r l y A c t i v i t y R e p o r t Highlights Final stage Pilot Plant progressing well Definitive Feasibility Study on track
More informationDecember 2015 Quarterly Report & Appendix 5B
December 2015 Quarterly Report & Appendix 5B 29 January 2016 Highlights: Completed the R1 workover program for all five Glenaras wells. Commenced testing of the R1 seam at Glenaras, with initial gas desorption
More informationQUARTERLY ACTIVITIES REPORT For the period ending 31 December 2013
HIGHLIGHTS QUARTERLY ACTIVITIES REPORT For the period ending 31 December 2013 MOORLANDS PROJECT Moorlands Mine Scoping Study completed by Xenith Mining Consultancy in November 2013, confirming robust project
More informationQUARTERLY ACTIVITIES REPORT TO 30 SEPTEMBER 2015
29 October 2015 QUARTERLY ACTIVITIES REPORT TO 30 SEPTEMBER 2015 Scoping Study Highlights Mt Morgans Gold Project (MMGP) Scoping Study was released during the quarter. Key outcomes include: An estimated
More informationMineralisation remains open in all directions with an untested downhole EM conductor at depth
Quarterly Report For the Period Ending 31 December 2015 Key Points Nanadie Well Project (CopperNickelPGE s) Latest drill results double strike extent of copper nickel PGE mineralised massive sulphides
More informationQuarterly Report December 2015
Quarterly Report December 2015 Highlights Major Asset Acquisition In October TGN announced that it had agreed terms for the acquisition of the Australian tungsten exploration assets of Hazelwood Resources
More informationFor personal use only
For persal use ly Mining explorati entity and oil and gas explorati entity ly report Rule 5.5 Mining explorati entity and oil and gas explorati entity ly report Introduced 01/07/96 Origin Appendix 8 Amended
More informationQueensland Mining Corporation L I M I T E D. Maiden JORC Resources Estimate for Horseshoe Copper Deposit, Duck Creek, South Cloncurry District
ASX Release 12 October 2012 Maiden JORC Resources Estimate for Horseshoe Copper Deposit, Duck Creek, South Cloncurry District Total mineral resource at Duck Creek Project area of 960,000t @ 1.47% Cu (0.2%
More informationRENOUNCEABLE RIGHTS ISSUE, BRIDGING LOAN FACILITY, and APPENDIX 4C Gage Roads Brewing Co Limited (ASX Code: GRB)
31 October 2008 Company Announcements Office Australian Stock Exchange Exchange Centre 20 Bridge Street SYDNEY NSW 2000 RENOUNCEABLE RIGHTS ISSUE, BRIDGING LOAN FACILITY, and APPENDIX 4C Gage Roads Brewing
More informationINVESTOR PRESENTATION JULY 2013
INVESTOR PRESENTATION JULY 2013 DISCLAIMER This presentation contains only a brief overview of Millennium Minerals Limited. The contents of this presentation, including matters relating to the geology
More informationFor personal use only
Alcyone Resources Ltd Directors: Charles Morgan Non Exec Chairman Andrew King Managing Director Andrew Richards Non Exec Director Silver Production Ramps Up as Alcyone Commences Mining HIGHLIGHTS Successful
More informationAppendix 4C. Quarterly report for entities admitted on the basis of commitments. Quarter ended ( current quarter )
Appendix 4C Rule 4.7B Quarterly report for entities admitted on the basis of commitments Introduced 31/03/00 Amended 30/09/01, 24/10/05, 17/12/10 Name of entity 1Page Limited ABN Quarter ended ( current
More informationDECEMBER 2015 QUARTERLY REPORT
NEWS RELEASE 29 JANUARY 2016 DECEMBER 2015 QUARTERLY REPORT Prairie Mining Limited is pleased to present its quarterly report for the period ending 31 December 2015. Highlights during, and subsequent to,
More informationQuarterly Report For the 3 Months ended December 2015
Quarterly Report For the 3 Months ended December 2015 This Quarterly Report updates activities undertaken during the period 1 October 2015 to 31 December 2015. OVERVIEW During the period, NuCoal continued
More information