1 1 Danish Experiences from Offshore Wind Danish Experiences from Offshore Wind Development

2 Danish Experiences from Offshore Wind 2 TABLE OF CONTENTS 1. INTRODUCTION KEY LEARNINGS 4 2. HISTORY AND BACKGROUND OF WIND ENERGY IN DENMARK 6 3. OFFSHORE WIND IN DENMARK 7 4. PERFORMANCE AND TARIFFS FOR DANISH OFFSHORE WIND FARMS 9 5. OPERATORS AND TURBINE TYPES IN DANISH OFFSHORE WIND DANISH PLANNING FOR OFFSHORE WIND FARMS KEY LEARNINGS CONSENTING PROCEDURE OFFSHORE TENDERING OPEN DOOR THE DANISH GRID AND ELECTRICITY MARKET ECONOMICS OF OFFSHORE WIND IN DENMARK INVESTMENT CLIMATE APPENDICES & LINKS 36 This publication was prepared by the Danish Energy Agency, part of the Ministry of Climate, Energy and Building in Denmark. The aim of the publication is to convey experiences from the 25-year long development of the Danish offshore wind industry, in particular the regulatory side. Comments to the report are welcome, and can be adressed to the authors Ms Mette Cramer Buch (mcb@ens.dk) and Mr Erik Kjaer (ekj@ens.dk), both from the Danish Energy Agency. Updated May 2015

3 3 Danish Experiences from Offshore Wind

4 Danish Experiences from Offshore Wind 4 1. INTRODUCTION In spite of Denmark s limited size, the country has had tremendous success with the development of its offshore wind industry. Its natural resources such as a long coastline, excellent wind resources and shallow waters have provided a solid starting point for a new industry born 25 years ago. On the back of broad and long term political commitment, an evolving sophistication in the regulatory framework has provided the backbone for a Danish offshore wind success story. History shows, that it takes unwavering political support to create an offshore industry. However, globally this is an industry still in its infancy with around 8 GW of installed capacity presently. LCoE. If governments sit back and wait for lower LCoE, it may never happen. Denmark is carrying its fair share of this burden with ambitions for a doubling of its off-shore capacity by As offshore wind is inherently still a risky business, planning procedures and allocation of risks are both important issues when designing a regulatory framework. This report describes the Danish journey for offshore wind up to now with an emphasis on what governments can do when aspiring to creating a new industry. It is our ambition that you will find inspiration in the Danish thinking. One of the prominent challenges still facing the industry is to lower the Levelized Cost of Energy (LCoE) from offshore wind. This is a process largely driven by volume, R&D and to a less degree time. Therefore, there is a collective burden on governments of this world with offshore wind ambitions, to contribute to creating volume on the journey towards lower

5 5 Danish Experiences from Offshore Wind 1.2 KEY LEARNINGS Prices of offshore wind may be driven down by preparing and providing the preliminary surveys to the investor. This will allow the investor to know the site intimately before planning the actual project. This will allow the investor to give a cost price rather than an estimate for the price of the production. Prices of offshore wind may be driven down if the investor has certainty that the grid connection can offtake the production as soon as the park starts producing. Consider establishing a one-shop-stop for investors, planners and contractors, i.e. providing one primary government entry point. Consider to have all preliminary investigations including EIAs carried out before the investor will set the price, so that the designated areas are ready with limited risks for investors and developers. The advantage is that the time when the price is calculated is very close to the time of contracting with the sub suppliers. The risk of price volatility in the market is thus significantly reduced.

6 Photo credit: DONG Energy A/S

7 7 Danish Experiences from Offshore Wind 2. HISTORY AND BACKGROUND OF WIND ENERGY IN DENMARK The first batch-produced Danish wind turbines from the late-1970s had an output of 22 kw, and the wind turbines were gradually scaled up to 55, 75 and 95 kw through the course of the 1980s. Alongside this commercial production, a government-funded development programme was undertaken by the electricity companies to test considerably larger pilot wind turbines. Since the 1980s, the wind turbine industry s commercial products have become increasingly larger-scale. Today s largest turbine, currently undergoing prototype testing is an 8 MW unit with a rotor diameter of 164 m. The number of wind turbines in Denmark peaked in the year 2000 at more than 6,200 installed turbines, of which more than half were older wind turbines with an electrical output of less than 500 kw. Almost all installed capacity was on land at this time. Since then, the number of wind turbines has decreased by around 1,000, while the total installed output has doubled from just less than 2,400 MW in 2000 to over 4,800 MW by April The wind power share of the domestic electricity supply has been growing steadily since In 1990, the share was 1.9%, and since then it has increased sharply. In 1999 the figure topped 10%, and in 2008 it reached 19.1% of the electricity supply. The wind penetration* in 2014 amounted to 39% of Danish power supply. PUBLIC INVOLVEMENT The development of wind power in Denmark has been characterised by strong public involvement. It was small machinery manufacturers that created the established wind turbine industry, and only after the consolidation of the industry through the 1990s did it become dominated by large, partly internationally owned and listed companies. Similarly, on the customer side numerous jointly owned wind turbines were established in the period The majority of wind turbines erected since 1995 are owned by individuals, energy companies and other commercial wind power companies. The progression towards fewer jointly owned and relatively large wind turbines has made it difficult to maintain local support for new wind power projects. But to ensure continued development of wind power, it is essential to have backing in the local community. The Energy Policy Agreement of 21 February 2008 therefore stipulated that a range of new initiatives should be undertaken to promote local acceptance, including options to purchase wind turbines shares of new wind power projects. Future projections show that with the planned wind farms amounting to 1400 MW installed capacity, the wind penetration will be over 50% by In 2014, the wind turbine industry s Danish production sites had a gross turnover of DKK 84 billion, and overall exports reached DKK 54 billion. * Wind penetration is defined as total yearly generation from wind as a percentage of total domestic consumption.

8 Danish Experiences from Offshore Wind 8 3. OFFSHORE WIND IN DENMARK In 1991 Denmark became the first country in the world to take wind turbines out to sea with 11 x 450 kw turbines in the Vindeby offshore wind farm. This was followed by a number of smaller demonstration projects, leading to the first two large offshore wind farms Horns Rev I and Nysted with outputs of 160 and 165 MW respectively. Some offshore wind farms have been built because power companies were given political orders to do so or via tenders, while others are wholly or partly owned by local wind turbine owners associations such as Middelgrunden and Samsø. With almost 1,300 MW offshore wind turbines connected to the electricity grid in 2013, Denmark is still one of the largest developers of offshore wind farms. Only the United Kingdom has a larger capacity. It is considerably more expensive to build and operate offshore wind turbines than onshore wind turbines. On the other hand, the wind production conditions are better at sea with higher wind speeds and more stable wind conditions. In Denmark, the wind farms are commissioned in a competitive tender process, and the cost of production of electricity is reflected in a feed-in tariff given per kwh produced. Name of ofshore wind farm Year of Commissioning Number of Turbines Total Capacity Vindeby MW Tunø Knob MW Middelgrunden MW Horns Rev MW Samsø MW Rønland MW Frederikshavn MW Nysted MW Horns Rev MW Avedøre Holme 2009/ MW Sprogø MW Rødsand MW Anholt MW Horns Rev N.A. 400 MW Nearshore (max 6 projects) 2019 N.A. 350 MW Kriegers Flak 2021 N.A. 600 MW Operating offshore wind farms in Denmark by end Upcoming wind farms shown in red.

9 9 Danish Experiences from Offshore Wind The offshore wind farms Rødsand II, Horns Rev II and Anholt were established on the basis of tenders. These projects are the result of the Energy Policy Agreement of 29 March 2004 and the Energy Policy Agreement of 21 February 2008 respectively. Early in 2015, it was announced that Vattenfall had won the concession for the 400 MW Horns Rev 3 at a price of 0.77 DKK/kWh for the first 20 TWh of energy generated. This marks a significant price reduction compared to Anholt and is considered a trendsetting price level at a challenging North Sea site. DONG Energy, which is the concessionaire for Horns Rev II, receives DKK 0.52 per kwh for 10 TWh, corresponding to around 50,000 full-load hours, after which the electricity produced has to be sold under market conditions. E.ON AB from Sweden, who won the tender for Rødsand II, receives DKK 0.63 per kwh for 10 TWh, corresponding to around 50,000 full-load hours. The Anholt project was awarded 1,05 DKK/kWh for the first 20 TWh, corresponding to full-load hours. Operating offshore wind farms in Denmark by end 2013.

10 Danish Experiences from Offshore Wind PERFORMANCE AND TARIFFS FOR DANISH OFFSHORE WIND FARMS Name Total Capacity Feed-in load hours *) Feed-in load hours*) Prod (kwh) Full load hours 2012 Prod 2013 (kwh) Full load hours 2013 Vindeby 5 MW N.A. 8,796,253 1,759 8,227,484 1,645 Tunø Knob 5 MW N.A. 14,325,790 2,865 13,334,401 2,667 Middelgrunden 40 MW 0,43 DKK/kWh@10 years 90,741,980 2,269 77,714,701 1,943 Horns Rev 1 #) 160 MW 0,35 DKK/kWh@42,000 hours 675,995,150 4, ,396,325 3,846 Samsø 23 MW 0,36 DKK/kWh@10 years 85,274,406 3,708 77,621,801 3,375 Rønland 17 MW 0,36 DKK/kWh@10 years 73,209,394 4,306 62,778,739 3,693 Frederikshavn 8 MW 0,36 DKK/kWh@10 years 20,556,019 2,70 21,849,069 2,731 Nysted #) 165 MW 0,35 DKK/kWh@42,000 hours Horns Rev 2 #) 209 MW 0,52 DKK/kWh@50,000 hours Avedøre Holme 11 MW 0,27 DKK/kWh@22,000 hours Sprogø 21 MW 0,27 DKK/kWh@22,000 hours Rødsand 2 #) 207 MW 0,63 DKK/kWh@53,000 hours Anholt #) 400 MW 1,05 DKK/kWh@50,000 hours Horns Rev 3 #) 400 MW 0,77 DKK/kWh@50,000 hours 575,157,364 3, ,868,598 3, ,027,802 4, ,055,183 4,306 38,050,937 3,759 35,109,531 3,192 67,059,773 3,193 62,226,853 2, ,745,838 4, ,511,986 3,568 31,812, ,205,398,737 3,013 N.A. N.A. N.A. N.A. Nearshore (Max 6 projects) 350 MW Auction Capped at 0,70DKK/kWh@50,000 hours N.A. N.A. N.A. N.A. Kriergers Flak #) 600 MW N.A. N.A. N.A. N.A. N.A. Notes to table: *) The feed-in tariffs in black font are fixed payments granted the owner for the equivalent number of full load hours. E.g. 50,000 equivalent full load hours equates to years of operation, depending on wind resource and operational performance etc. After this period, the wind farm is paid market price only. The tariffs in red font are feed-in premiums, paid on top of market prices for a number of equivalent full load hours. After this period, the wind farm is paid market price only. The market price level is currently around DKK/kWh in average, with substantial variations. The Danish authorities do not require developers to report investment costs. Capital expenditure numbers are therefore not available to Danish authorities. #) Projects marked have had grid connections costs paid by all electricity consumers, i.e. grid costs are not to be paid through feed-in tariff. These grid connections are designed, constructed, owned and operated by the national TSO as an integral part of the Danish backbone electricity grid. Capacity factors can easily be calculated from full load hours, by use of this formula: (No. of full load hours in a year)/8760 * 100%. E.g. 4,125 full load hours corresponds to a capacity factor of 47.09%.

11 11 Danish Experiences from Offshore Wind 5. OPERATORS AND TURBINE TYPES IN DANISH OFFSHORE WIND Name Operator *) Capacity No of turbines Brand/type Foundation type Vindeby DONG Energy 4.95 MW 11 Bonus 450 kw/37 Gravity based Tunø Knob DONG Energy 5 MW 10 Vestas V kw Gravity based Middelgrunden DONG Energy 40 MW 20 Bonus 2,0 MW/76 Gravity based Horns Rev 1 Vattenfall 160 MW 80 Vestas V MW Monopiles Samsø Samsø Havvind 23 MW 10 Bonus 2.3 MW/82 Monopiles Rønland Vindenergi/ Harboøre Møllelaug + Thyborøn-Harboøre Vindmøllelaug 17.2 MW 8 Vestas V MW / Bonus 2.3 MW/82 Gravity based / Gravity based Frederikshavn DONG Energy 7.6 MW 3 Nordex N90/2300 / Vestas V MW / Bonus 2.3 MW/82 Monopiles / Suction bucket / Monopiles Nysted 1 DONG Energy MW 72 Bonus 2.3 MW/82 Gravity based Horns Rev 2 DONG Energy MW 91 Siemens SWT Monopiles Avedøre Holme DONG Energy 10.8 MW 3 Siemens SWT Gravity based Sprogø Sund & Bælt 21 MW 7 Vestas V MW Gravity based Rødsand 2 E,ON 207 MW 90 Siemens SWT Gravity based Anholt DONG Energy MW 111 Siemens SWT Monopiles Horns Rev 3 Vattenfall 400 MV N.A. N.A. N.A. Nearshore (Max. 6 projects) N.A. 350 MW N.A. N.A. N.A. Kriegers Flak N.A. 600 MW N.A. N.A. N.A. The table shows the operating offshore wind farms (as of end 2014), including operator, turbine type and foundation type. Notes to table: *) Operator not to be confused with owner. The operator will normally make up a part of the investor group. As a result of Denmark s first-mover status within wind power, on- and offshore, Denmark is home to an advanced supply chain within wind energy. The industry employs around 28,000 people. The world s largest turbine supplier, Vestas Wind Systems A/S, is listed on the Nasdaq OMX Copenhagen Stock Exchange and has its corporate headquarters in Denmark. Siemens Wind Power (formerly Bonus Wind) has the majority of its manufacturing footprint in Denmark.

12

13 13 Danish Experiences from Offshore Wind 6. DANISH PLANNING FOR OFFSHORE WIND FARMS The main driver for Denmark to move offshore is the scarcity of land for onshore sites, and the abundance of shallow waters with ample wind resources. Since 1991 offshore wind has purposely been placed in large wind farms evenly distributed between East and West with due consideration to the power output and build-up of experience. In 1985 the 2 large vertically integrated power utilities (i.e. having ownership of production and transmission/distribution) were given an obligation to engage in large scale offshore wind power in order to gain experience. The objective was also to research the impacts of large scale offshore wind on the environment. An environmental monitoring programme was undertaken on the two farms, which investigated the different offshore conditions i.e. different salinity, currents and tides, and different locations providing for different species, habitats and impact on migratory patterns etc. The purpose was to ensure that offshore wind power does not have damaging effects on the natural ecosystems and to provide a solid basis for decisions about further development of offshore wind power. The measurement and monitoring programme has been considered important for both the extension of the offshore wind farms at the specific sites, and for the establishment of additional large scale offshore wind farms. All information has been published in English and placed in the public domain. The power utilities obligation to build offshore wind farms was realised by 2 pilot projects in Eastern and Western Denmark respectively. The geographically different locations in the North Sea and Baltic Sea also gave opportunity to obtain experience in the Western and Eastern transmission grids both in relation to handling grid connection from offshore transformer platforms and in relation to system operation, i.e. managing the variable power. Large offshore wind farms are usually located far from major centres of consumption and are connected to the transmission grid in sparsely populated areas. The transmission grid must therefore also be able to transport the power from the offshore wind farms over long distances. Spatial planning has subsequently been used to identify potential locations for offshore wind farms taking into account grid connection routes and other areas of interests. In A visionary Danish energy policy 2025 from 2007 the Danish Government formulated an objective of more wind power through strategic planning of wind turbine development. Strategic planning includes a good spatial planning framework for Danish wind capacity and the promotion of onshore and offshore demonstration and pilot sites as well as the drafting of an infrastructure plan for offshore wind turbines. MARINE SPATIAL PLANNING FOR OFFSHORE WIND FARMS While offshore wind is an attractive energy alternative, development of offshore wind farms should be based on thorough and well considered planning. This should involve a planning approach, which respects the vulnerability of the marine environment, and takes all sea uses into account. Wind farms cannot be seen in isolation from the natural and anthropogenic landscape in which they are constructed. Therefore planning systems are necessary to reveal the multitude of pressures on the sea space. It is important in planning to observe the multitude of interests at sea and to attempt to mitigate the effects. This is the only way to secure appropriate sites for offshore wind farms while respecting the environment and other users the same time.

14 Danish Experiences from Offshore Wind 14 In 1995, a spatial planning committee for offshore wind was established and it still exists. The committee is led by the Danish Energy Agency and consists of government authorities responsible for the natural environment, safety at sea and navigation, offshore resources extraction, visual interests and grid transmission conditions. Furthermore, the committee comprises expertise within the technical fields of wind power as well as turbine, foundation and grid technologies. Emphasis is also put on ensuring a planned and coordinated development of offshore wind farms and the associated transmission grid. Subsequently, the suggested sites are discussed with the remaining marine authorities and the affected municipalities onshore. When all public authorities agree to appropriate placements of offshore wind farms, these are sent into public hearing. A hearing of relevant neighbouring countries is also carried out when appropriate. This may lead to further adjustments of the plans. This process was carried out in 1997, 2007, 2011 and The committee is dormant between planning exercises, but is revived when new planning needs arise. The committee examines the engineering, economic and planning options for landing power and the consequences for the underlying grid. The committee assesses on a regular basis the siting of offshore wind farms with respect of other interests at sea and appropriate sea uses. The committee is tasked with finding appropriate sites for offshore wind farms, i.e. sites where the impact on nature and other sea uses is expected to be low, whilst suitable for harvesting offshore wind. When these sites are found, they are reserved for the establishment of offshore wind farms. In actual terms the committee works with GIS mapping. Each governmental authority has their own reserved areas charted in a GIS map, such as sailing routes and environmental protection sites, cables, etc. When the maps are collated on top of each other, a picture of the areas with no reservations become apparent. These are then evaluated in relation to distance to shore, wind speeds, water depth, etc. The sites which are identified as useful and available for offshore wind farms according to wind speed, grid transmission, naval and air navigation, nature, landscape, raw material extraction, are assessed according to the anticipated cost of establishing and operating the offshore wind farms. The committee attaches importance to a planned and coordinated expansion of wind power and the transmission network with a view to obtain the greatest possible economic benefits from the greatest wind speeds and the lowest construction costs.

15 15 Danish Experiences from Offshore Wind Figure 1: Example of a spatial planning map detailing relevant sea uses and distances to shore

16 Danish Experiences from Offshore Wind 16 THE ORIGINAL PLANNING EXERCISE - THE ACTION PLAN IN 1997 An action plan for offshore wind farms from 1997 recommended to concentrate large offshore development within a few areas and to carry out a large-scale demonstration programme to show the environmental and grid related effects of large scale wind. In the action plan five areas were identified as suitable for future offshore wind farms. The selection was based on experiences from the first two small pilot projects (Vindeby and Tunø) and the recommendations from the work of the governmental committee, which included wind speed measurements, mapping of water depths, visual impact on the coastal landscapes and an assessment of other interests in Danish waters. The objective of the program was to investigate economic, technical and environmental issues and speed up offshore development to open up the selected areas for future wind farms. Three of the identified areas were subsequently ruled out as being less attractive due to other area interests such as sailing routes and potentially environmental unacceptable impact on certain species etc. For the remaining two areas Horns Rev and Rødsand (Nysted) a comprehensive environmental measurement and monitoring programme was initiated to investigate the effects on the environment before, during and after the completion of the wind farms.

17 17 Danish Experiences from Offshore Wind MARINE SPATIAL PLAN OF 2007 AND 2011 The report Future Offshore Wind Turbine Locations 2025 was first published in April The committee examined in detail 23 specific possible locations, each of 44 square kilometers. This report was subsequently updated in April The update was necessary due to the ever changing framework conditions for developing offshore wind farms caused by the emergence of new interests such as bridges, pipelines, harbours, fishing quotas. In other words the update recognised that mapping is a dynamic process. The reports chart a number of possible offshore areas where offshore turbines could be built to deliver an overall capacity of app. 4,200 MW. The sites correspond to app. 50% of Danish electricity consumption. Several of the sites identified are currently being developed for large-scale wind farms, e.g. Horns Rev 3 (400 MW) and Kriegers Flak (600 MW). PLANNING IN 2012 FOR NEARSHORE WIND SITES As nearshore wind farms are expected to be cheaper than offshore wind farms, a planning exercise was launched in order to find the most suitable sites for nearshore wind farms. In addition to the large offshore areas, 15 suitable nearshore sites have been identified in a mapping exercise carried out in The 15 sites were submitted to a strategic environmental assessment in order to prevent any future conflicts with environmental and natural interests. In 2012 the spatial planning committee for offshore wind published the results of a planning exercise aiming at identifying the most suitable sites for nearshore offshore wind farms. 15 areas were selected, each with a possible capacity of up to 200 MW. Knowledge from the environmental monitoring programme for large-scale offshore wind farms, and the knowledge collected in environmental impact assessments have continually been fed into the spatial planning process.

18 Danish Experiences from Offshore Wind 18 WIND RESOURCE MAPPING Wind is the most important factor for the income from a wind farm, so it has always been given special attention in Danish wind power planning. Since the 1980s wind resource mapping has been developed and included in wind power planning both at national and municipal level. A refined wind atlas for Denmark identifying national wind resources was published in The wind atlas is used in the planning process when assessing the wind resource potential in a given area and to assess identification of potential wind development zones in line with the strategic environmental framework or assessments studies. Also it provides wind speeds prediction with known and traceable accuracy for developers and allows them to calculate the potential yield of the wind energy resources. In addition it gives the TSO ability to handle variable wind resources and it gives input to long-term grid planning. Figure 2: Wind Speeds in Denmark, 100 meter above sea level

19 19 Danish Experiences from Offshore Wind 6.1 KEY LEARNINGS Carry out a thorough screening and planning before designating areas for offshore wind turbines. Take wind conditions, sea depths, grid connection options, seabed conditions, marine life etc. into consideration when screening for suitable sites for offshore wind farms. Consult all relevant authorities with interests at sea, in order to avoid future conflicting interests. Often compromises can be found. Consider also as a minimum competing interests such as shipping routes, environmentally sensitive sites, fishing areas, resources and extraction up front in the planning. Involve all affected parties with interests at sea at government level already at the beginning of the planning procedure. This will create ownership of the process and commitment to the sites chosen. Consult with evidence from effect studies on environmental impacts already assessed and accessible in the public domain before requiring expensive and time consuming analysis as part of the EIA requirements. Consider to set up a general framework for environmental impact assessments (EIAs).

20

21 21 Danish Experiences from Offshore Wind 7. CONSENTING PROCEDURE BACKGROUND The Danish Energy Agency (DEA) has been given the mandate to plan for and issue licenses and production approvals to offshore wind turbines and is thus the responsible authority for planning and commissioning. DEA also approves new grid connections. 4 licences are required to establish an offshore wind project in Denmark. Other licences are required for the grid connection. All licences are granted by the Danish Energy Agency, which serves as a One-stop shop for the project developer in relation to the many often opposing interests connected to the establishment of offshore wind power projects. The 4 licences are: 1. License to carry out preliminary investigations. 2. License to establish offshore wind turbines. Before this license can be granted, an Environmental Impact Assessment (EIA) must be carried out. 3. License to exploit wind power for 25 years. This license may be prolonged. 4. Approval for electricity production in compliance with the electricity legislation. The 4 licenses are given successively for a specific project. The license for grid connection can be included in the license to establish the offshore wind turbines when the project is small. For larger project an approval for the grid connection is given separately. Licenses from other authorities may also be necessary; however these are usually not blocking the project if a license to establish the offshore wind farm can be given. In the Danish case, new offshore wind farm projects can be established according to two different procedures: a government tender or an open door procedure. The procedures have been gradually developed as experience has been gained since the first off-shore wind power projects. APPEAL For all types of offshore and nearshore projects, individuals, that are significantly and individually affected, as well as relevant environmental organisations may appeal the project to the Energy Board of Appeal within four weeks of the publication of the decision to establish a project. Likewise the onshore infrastructure may be appealed to the Environmental Board of Appeal. Due to the thorough strategic planning in identifying suitable locations offshore ahead of the EIA for concrete projects evidence show that projects are rarely appealed. ONE STOP SHOP In order to ensure rapid and unbureaucratic application processing, enterprises or consortia awarded concession contracts will be using the Danish Energy Agency as single point of access to assistance on issues related to all permitting. The Danish Energy Agency will grant the required permits, and will coordinate these with other relevant authorities. This means that the permits granted by the Danish Energy Agency also contain terms and conditions from other authorities, such as the Danish Nature Agency, the Danish Maritime Authority, the Danish Coastal Authority, the Danish Agency for Culture, the Ministry of Defence, etc. This, however, can be supplemented by licences from other authorities.

22 Danish Experiences from Offshore Wind 22 GOVERNMENT CALL FOR TENDERS A government tender is carried out to realise a political decision to establish a new offshore wind farm at the lowest possible cost. In the typical government tender procedure, the Danish Energy Agency announces a tender for an offshore wind turbine project of a specific size, e.g. 600 MW, within a specifically defined geographical area. Depending on the nature of the project, the Danish Energy Agency invites applicants to submit a quotation for the price at which the bidders are willing to produce electricity in the form of a fixed feed-in tariff for a certain amount of produced electricity, calculated as number of full-load hours. The winning price will differ from project to project because the result of a tender depends on the project location, the wind conditions at the site, the competitive situation in the market at the time, etc. Offshore Wind Power Sites 2025 from April 2007 and the follow-up to this from Before the Danish Energy Agency actually begins processing an application, as part of the onestop shop concept, it initiates a hearing of other government bodies to clarify whether there are other major public interests that could block implementation of the project. On this basis, the Danish Energy Agency decides whether the area in the application can be developed, and in the event of a positive decision it issues an approval for the applicant to carry out preliminary investigations, including an EIA. If the result of the preliminary investigations shows that the suggested project can be approved, the project developer can obtain a license to establish the project. In projects covered by a government tender, Energinet.dk typically constructs, owns and maintains both the transformer station and the underwater cable that carries the electricity to land from the offshore wind farm. Energinet.dk is responsible for the electricity infrastructure in Denmark and act as an independent system operator (TSO) OPEN-DOOR PROCEDURE In the open-door procedure, the project developer takes the initiative to establish an offshore wind farm of a chosen size in a specific area. This is done by submitting an unsolicited application for a license to carry out preliminary investigations in the given area. The application must as a minimum include a description of the project, the anticipated scope of the preliminary investigations, the size and number of turbines, and the limits of the project s geographical siting. In an open-door project, the developer pays for the transmission of the produced electricity to land. An open-door project cannot expect to obtain approval in areas that are designated for offshore wind farms in the report Future

23 23 Danish Experiences from Offshore Wind

24 Danish Experiences from Offshore Wind OFFSHORE TENDERING A political decision has been taken by a broad majority in the Danish Parliament to significantly expand offshore wind capacity up to A doubling of offshore capacity and a significant expansion of onshore capacity, will secure that 50% of total electricity consumption by 2020 comes from wind power - making Denmark a world leader within this area. The existing capacity will be expanded by 1400 MW through tenders for offshore wind turbines. The procedure will be characterised by openness and transparency and that all potential applicants are treated equal. The areas that are offered for tender are the sites identified in the spatial planning pro-cess. The fact that other government authorities have been involved in the process of identifying the sites for new offshore wind farms and have approved the final report, creates commitment to securing the sites. This, in turn, creates great investor security and up front knowledge about the sites. The Danish independent system operator (TSO) is responsible for the Environmental Impact Assessment; geophysical surveys as well some geotechnical surveys to be carried out in the planning phase ahead of the call for tenders. These in-depth studies of the physical features of the site deepen the knowledge of the sites, and give future investors an insight into the technology choices they can take in the bidding procedure. This early action is implemented in order to reduce the length of the approval process and to give applicants better possibilities to offer a price that is real-cost based. At the same time it provides potential bidders with a high investment security and thus supports a reduced risk premium. The purpose of the geological preliminary surveys is to generate knowledge about geological conditions, undetonated explosives (from World War II) and other man-made obstructions, biological aspects (for example bubbling reefs, stone reefs and sub-merged/ benthic vegetation), as well as objects of marine archaeological interest (such as wrecks and ancient monuments) on the seabed. The preliminary surveys will contribute to a detailed survey of seabed conditions. They will be included in the EIA reports and will ensure accurate and optimal planning and construction of the technical electricity transmission installations to be established on the seabed in connection with the establishment of the offshore wind farms. The preliminary surveys will also provide knowledge about requirements for the design of the wind farms, including the choice of foundations. The results of the preliminary investigations will be published in good time before completion of the tendering procedure. The costs of the preliminary investigations will subsequently be refunded by the owner of the concession. Also the costs will be published well before tenders for the wind farm are to be made. Simultaneously with the preliminary surveys the TSO also undertakes planning, procure-ment, and financing of the substation and sea cable to shore. This important part of the project must be ready by the time the offshore wind farm is up and running. If this should not be the case, the wind farm is entitled to compensation by the TSO. Two sites - Horns Rev 3 and Krieger s Flak have been identified as best suited for the next tenders. These areas have average wind speeds of around 10 metres per second. The good wind conditions at the chosen sites will allow offshore wind farms to produce for around 4,000 fullload hours a year. With sea depths of metres, good wind speeds and a distance to the coast of kilometres in the mapped suitable sites, a balance has been struck between economic considerations and the visual impact

25 25 Danish Experiences from Offshore Wind observed from the shoreline. The tender documents will provide drafts of the four necessary permits: a preliminary investigation permit, an establishment permit, an electricity production permit and an electricity production authorisation. The enterprises or consortia awarded concession contracts can expect to obtain a preliminary investigations permit and an establishment permit soon after completion of the tendering procedure. The preliminary investigations permit will allow enterprises or consortia awarded concession contracts to conduct further geotechnical and geophysical surveys to supplement the surveys already carried out. Similarly, enterprises or consortia with an establishment permit will be able to commence detailed planning activities and prepare the final project in detail. The final project has to be approved before actual construction work can commence. Furthermore, enterprises or consortia also need to obtain a permit to exploit the wind resources in a given area to produce electricity (electricity production permit). The permit is not usually issued until after construction work has commenced and no later than after grid connection of the first turbine. Compliance with the terms of the construction permit must be documented. Before the installation is connected to the grid, authorization to produce electricity must be granted. A certain level of technical and financial capacity is required in order to obtain this permit. All of the permits mentioned above will be included in the tender specifications as draft permits. They will be issued by the Danish Energy Agency which, by that time, will have consulted all other relevant authorities in advance, or when the need arises during the construction phase. OTHER CONDITIONS AND REQUIREMENTS Tender specifications also states that the successful tenderer will be subject to normal company taxation, i.e. no special tax rules apply. In terms of insurance requirements, a liability insurance covering the concession-holder as well as his sub-suppliers must be documented. A parent company guarantee covering i.a. decommissioning costs must be in place before final award of the concession. How the successful tenderer chooses to finance the offshore wind farm, is entirely up to him. Bearing in mind, that the pre-qualification step has established his financial capability to finance the wind farm construction and operation, the Danish authorities will not put further requirements on him related to financing. This means that authorities are not informed about the tenderer s detailed business case assumptions, such as Capex, Opex, Risk premiums, IRR etc. When contracts for components like foundations, cables and turbines are placed by the concession holder or the operator responsible, terms and conditions in these contracts will remain commercial secrets, not to be reported to authorities. TYPICAL COMPANY STRUCTURE OF CONCESSION HOLDER It is common, that the successful bidder will register a Special Purpose Vehicle (SPV), a company which single mission is to build, own and operate the offshore wind farm in question. Such structure will ease any limited recourse finance (project finance) the owners may wish to obtain. In case the bidder is a joint venture (JV) between two or more companies, it is common to see JV contracts inspired by the oil and gas industry. This entails naming an operator, who will be the party taking on e.g. the construction task on behalf of the JV.

26 Danish Experiences from Offshore Wind 26 THE TENDERING PROCEDURE IN BRIEF 1. Technical dialogue with interested tenderers and investors. The Danish Energy Agency is inviting potential tenderers and investors to a bilateral technical dialogue. This will enable adjustment of preliminary surveys and tender specifications to market requirements. The dialogue will take into account the principles on equal treatment, transparency and proportionality. 2. Publication of the contract notice and the full tender specifications. The contract notice notifies the market that the Danish Energy Agency wants to enter into a concession contract. The Danish Energy Agency will draw up technical and financial criteria for pre-qualification of potential tenderers suitable for meeting the concession contract. The full tender specifications will list the terms of the tendering procedure, framework conditions for establishing the offshore wind farms, draft permits for preliminary surveys, establishment and operation of the offshore wind farms, as well as a draft concession contract. 3. Negotiation with prequalified tenderers. Potential tenderers express their interest in participating in the tendering procedure by submitting an application for prequalification. Applicants for prequalification must submit documentation that they meet the suitability conditions. On the basis of the first proposed tenders by the prequalified tenderers, the Danish Energy Agency will negotiate the final design of specification requirements, contract proposal, etc. with the pre-qualified tenderers. The reason for the negotiations is that the Danish Energy Agency must be able to clarify, specify and adjust the tender documents, if necessary. Negotiations will be carried out without the risk of distorting competition. Prior to the negotiations, the Danish Energy Agency will provide information about which items are open for negotiation. The items open for negotiation will primarily concern whether and how the tender documents can be improved with a view to lowering prices. 4. Final call for tender. On the basis of the negotiations, the tender documents will be adjusted within the framework of the published tender documents. Submission of final tenders based on the final tender documents. 5. Selection of winner and drafting of contract. The final winner will be selected on the basis of the award criteria in the tender documents. Danish Energy Agency can enter into the concession contract with the winner and award permits for preliminary surveys and establishment.

27 27 Danish Experiences from Offshore Wind NEW TENDER MODEL UNDERWAY FOR NEARSHORE WIND FARMS It is expected that nearshore wind farms will be cheaper to build due to the shallower waters and the shorter cabling to shore. The nearshore sites in question are a minimum of 4 km from shore. Therefore, a political decision has been taken by a broad majority in the Danish Parliament that 6 nearshore sites that can hold up to 200 MW each will compete to host a total of 350 MW. The areas will be in competition with each other thus it is not expected that more than 3 sites are to be developed in this round. The near shore wind farms will be visible from shore. Therefore local support for the projects is very important. Thus the 6 areas have been selected partly because there is already significant municipal support for the wind farm project in these areas. In order to maintain local support, it has been decided that concession owners will be required to offer at least 20% of each project to local residents and enterprises like in the case for onshore projects. Note that there is only an obligation to offer this share, not to achieve it. In order to give an additional incentive for gaining public support a higher feed-in tariff will be available to projects that achieve at least 30% community ownership on the date of grid connection. MetOcean surveys (wind, current, tidal waters and wave conditions). The preliminary surveys have been planned so that the results will be published in good time before completion of the tendering procedure. This means that the enterprises submitting tenders to construct, own and operate the nearshore wind turbines will know the conditions and risks of building in the area. The concessionaire that wins the tender will have to refund the costs of the preliminary survey. This applies to the geological surveys as well as the MetOcean and EIA reports. The size of these costs will be published well before the submission of tenders. The developer must pay for grid connection to the nearest coast. From that point, costs will be carried by electricity consumers as part of the Public Service Obligation (PSO) fee. The reason for this is that it is unknown until after the tender, how large the wind farm will be or in which areas they will be constructed. In this case it is better to let the grid connection be a part of the project and let the planning and the cost of grid connection and transformer substations be covered by the concessionaire. The TSO will carry out EIAs for all 6 sites. The Danish TSO Energinet.dk will conduct preliminary surveys in the six areas in the tender for 350 MW nearshore wind turbines. Preliminary surveys comprise geophysical, geotechnical surveys, EIA reports and

28 Photo credit: DONG Energy A/S

29 29 Danish Experiences from Offshore Wind 9. OPEN DOOR In the open-door procedure, the project developer takes the initiative to establish an offshore wind farm in a particular area. This is done by submitting an unsolicited application for a license to carry out preliminary investigations in the given area, outside areas that already are designated wind power areas found in the spatial planning process. The application must as a minimum include a description of the project, the anticipated scope of the preliminary investigations, the size and number of turbines, and the limits of the project s geographical siting. Before the Danish Energy Agency actually begins processing an application, a hearing of other government bodies is initiated to clarify whether there are other major public interests that could block the implementation of the project. On this basis, the Danish Energy Agency decides whether the area in the application can be developed, and in the event of a positive decision it issues an approval for the applicant to carry out preliminary investigations, including an environmental impact assessment (EIA). The preliminary investigations include as a minimum an EIA as well as geophysical and geotechnical surveys of the seabed to clarify what type of foundation should be used. The EIA must assess the offshore wind farm s impacts on the environment. On the basis of responses from the initial consultation of authorities and other stakeholders, the Danish Energy Agency determines what the EIA should include offshore. As an EIA needs to examine the total coherent project i.e. also the onshore infrastructure necessary, hence the Danish Nature Agency and municipalities are the EIA authority regarding what to include for these parts. The EIA must demonstrate, describe and assess the environmental consequences of implementing the project in respect of: people, fauna and flora, seabed, water, air, climate and landscape, tangible property and Danish cultural heritage. Furthermore, the EIA must describe proposals for alternative siting and proposals for how demonstrated environmental nuisances can be prevented or reduced. The project developer s application to establish the offshore wind farm must therefore include a full description of the project s expected scope, size, geographical location, coordinates for turbines, grid connection plans and cable trace, etc., as well as the results of the preliminary investigations. Once the Danish Energy Agency has received the EIA together with a final application to establish the offshore wind farm, it sends both for public consultation with a deadline for reply of at least eight weeks. The consultation is announced on the Danish Energy Agency s website and in national and local newspapers. This gives other authorities, interested organisations and citizens the opportunity to voice objections and other comments, which the Danish Energy Agency includes in its processing of the application and the EIA. If the Danish Energy Agency does not receive any objections with weighty arguments for cancelling the project such as detrimental impact on a protected species, it grants a license to establish the offshore wind farm. In this regard, the Danish Energy Agency will generally require the project developer to document, prior to starting the construction work, a detailed project description. Finally, the project developer must apply for a license to exploit wind power from the offshore wind farm and, in the case of wind farms of more than 25 MW, for an authorisation to produce electricity. This must be done after the installation work has begun and at the latest two months before the first wind turbine is ready to begin operating. The offshore wind farm must not supply electricity to the grid until the license

30 Danish Experiences from Offshore Wind 30 has been granted. In this way it is assured that all obligations given in the consented document is fulfilled. In open door concessions in locations outside designated offshore wind areas the project developer receives the same price premium as for new onshore wind turbines. In offshore open door concessions and near shore concessions the developer finances the grid connection up to the nearest shore. TURBINES FOR TEST AND DEMONSTRATION 50 MW for test turbines is also planned. The test projects are not tied to the designated areas, and can be located anywhere conditions allow for it. Furthermore, the test element is not tied to the actual turbine the test element could be testing of new foundation types, new installation methods, new cables, etc. Test projects can include up to eight turbines. The projects must have a clear technological development object aiming at reducing the future costs of offshore wind turbines. Test turbines are typically allocated according to the open door regime.

31 31 Danish Experiences from Offshore Wind 10. THE DANISH GRID AND ELECTRICITY MARKET Denmark has a well-functioning and efficient power market. As much as 39% wind power (out of total consumption 2014) has already been integrated into the market without any disruptions to operations. Thorough planning, along with initiatives already adopted to improve the market, will ensure that approximately 50% wind will have been integrated into the system by 2020 while maintaining the high security of supply. The Danish Energy Agency makes projections of how energy consumption, energy production, electricity market prices etc. will develop, assuming that no new energy policy initiatives are decided. This development is often referred to as the business-as-usual scenario. Actual developments will be influenced by new energy policy initiatives. ELECTRICITY GRID, ELECTRICITY PRICES AND SETTLEMENT, WHAT MAKES IT WORK? Denmark is among the founding members of the Nordic cooperation within electricity. The cooperation started in the monopoly days before the year 2000 and in those days exchange of electricity took place whenever two countries saw a mutual financial interest. If the marginal price in one country was x (the higher of the two) and y (the lower of the two) in the other, then electricity was exchanged at the price y+(x-y)/2, splitting the price difference evenly. Since 2000, all EU-member countries liberalised their electricity markets, and this process gave birth to the Nordic electricity market Nordpool. Today it is a highly sophisticated marketplace trading several products. The spot market (dayahead market) is considered the world s most liquid electricity market and owned jointly by the Nordic TSOs. Sellers and buyers will trade themselves into overall balance through an intra-day market with a regulated balancing market as support. detail with the market itself. It is however important to note that due to the cross-border trading both before and after liberalisation, Denmark has strong interconnectors to the neighbouring countries. Theoretically, the interconnector capacity is so high, that Denmark would be able to import close to all of its electricity consumption, with the exception of some of the highest peaks. Construction of even more crossborder interconnector capacity continues, as this is an important prerequisite for integration of a growing share of fluctuating renewables, on- and offshore wind in particular. THE TSO IN DENMARK According to EU requirements, Denmark has an independent TSO, which is not allowed to own or operate generation capacity. One of the TSO s important roles is to secure a transparent and non-discriminatory day-ahead market as a socalled playmaker. The TSO owns and operates the high voltage network (132 kv up to 400 kv) as well as interconnectors to neighbours. The TSO is now fully state owned, has its own planning with strategic outlook as well as strong project management skills in terms of new infrastructure. The structure of the electricity sector is so that all generation is fully commercialised, whereas distribution is regulated business. Priority access to the grid serves as assurance for renewable power generators that they will always be able to sell and transmit their power in accordance with current connection rules. In case of curtailment, which happens extremely seldom, the TSO carries an obligation to fully compensate curtailed generation for loss of revenue. It is beyond the purpose of this report to go into

32 Danish Experiences from Offshore Wind 32 GRID CONNECTIONS FOR OFFSHORE WIND FARMS In Denmark (as well as in Germany), the grid connections for large offshore wind farms is planned, procured, installed, operated and paid for by the TSO. This was described in more detail in the section Offshore Tendering. This choice of model has the advantage that it preserves the electrical integrity of the high voltage grid as the responsibility remains with the TSO. It also means that the responsibility for the EIAs for the grid connection and the wind farm rests with one single party, namely the TSO and thus may be combined. Figure 3: Structure of the grid in Denmark.

33 33 Danish Experiences from Offshore Wind 11. ECONOMICS OF OFFSHORE WIND IN DENMARK MACRO-ECONOMIC DRIVERS FOR OFFSHORE WIND IN DENMARK Since the start of deployment of wind energy in Denmark, onshore wind has undergone a tremendous technical development. It is now the cheapest renewable technology, with a potential for being able to generate without subsidies on good wind locations within half a decade. It is this impressive development, offshore wind will hopefully replicate. The political rationale for offshore wind in Denmark includes the following: Overall good wind resources, on- and offshore first-mover advantages in deployment of wind energy considerable job creation and exports of components for wind energy Denmark has limited onshore land resources and is relatively densely populated Denmark has a very long coastline (> 7,300 km) and plentiful shallow waters Earlier in this report, we have shown the feedin tariffs achieved for Danish offshore wind farms (chapter 4). It is clear that these tariffs are well above average wholesale market prices for electricity. This differential is captured in the so-called PSO-cost (Public Service Operation), levied on all sold electricity. The graph below shows the development of the PSO costs since PSO cost data for offshore wind alone is not available. Comparing Danish residential consumers prices with other EU countries, gives the below picture: All commercial consumers in Denmark are exempted from an energy tax element. Certain heavy industry will further enjoy Million DKK PSO costs (million DKK) and wholesale electricity price variation DKK/MWh Total PSO costs Wholesale electricity price in Denmark Figure 4: The development in Danish PSO costs since PSO costs cover all renewable generation subsidies. Source: The Danish Energy Agency.

34 Danish Experiences from Offshore Wind 34 exemption from other elements of the energy taxes. Therefore the above residential price is not to be confused with commercial rates. Part of the explanation why Denmark has the consumption. Figure 5: Average residential electricity prices including taxes (2012). Source: HEPI by Energie Control Austria and VaasaETT Ltd highest prices is high taxation and high PSO costs. This is shown in the below normalized graph As can be seen, the energy price itself is the lowest of all countries shown. Denmark has chosen to recover subsidies for renewables through electricity prices, but this is not the case for all countries, making comparisons somewhat difficult. Denmark s way of recovering these costs is arguably the most fair, as the burden is apportioned according to electricity Figure 6: Residential electricity price breakdown ( average 2012)

Future Offshore Wind Power Sites -2025

Future Offshore Wind Power Sites -2025 Danish Energy Authorithy Amaliegade 44 DK-1256 Copenhagen K Tel 33 92 67 00 Fax 33 11 47 43 CVR-nr: 59 77 87 14 ens@ens.dk www.ens.dk Rubrik Verdana Bold 18 punkt Underrubrik Verdana 18 punkt Brødtekst

More information

Offshore Wind Energy Status and Future Prospects

Offshore Wind Energy Status and Future Prospects SDU Symposium August 18 2009 Offshore Wind Energy Status and Future Prospects Morten Holmager Offshore Center Danmark The copyright of this entire presentation vests by Offshore Center Danmark. All rights

More information

ACCELERATING GREEN ENERGY TOWARDS 2020. The Danish Energy Agreement of March 2012

ACCELERATING GREEN ENERGY TOWARDS 2020. The Danish Energy Agreement of March 2012 ACCELERATING GREEN ENERGY TOWARDS The Danish Energy Agreement of March 2012 The most ambitious energy plan of the world In March 2012 a historic new Energy Agreement was reached in Denmark. The Agreement

More information

Translating ecological research results into wind farm practice The Danish experience. Niels-Erik Clausen. 2 Risø DTU

Translating ecological research results into wind farm practice The Danish experience. Niels-Erik Clausen. 2 Risø DTU Translating ecological research results into wind farm practice The Danish experience Niels-Erik Clausen We@Sea Conference, Den Helder Holland 12-13 February 2009 Outline The Danish offshore monitoring

More information

THE GREEN ELECTRCITY MARKET IN DENMARK: QUOTAS, CERTIFICATES AND INTERNATIONAL TRADE. Ole Odgaard Denmark

THE GREEN ELECTRCITY MARKET IN DENMARK: QUOTAS, CERTIFICATES AND INTERNATIONAL TRADE. Ole Odgaard Denmark Workshop on Best Practices in Policies and Measures, 11 13 April 2000, Copenhagen THE GREEN ELECTRCITY MARKET IN DENMARK: QUOTAS, CERTIFICATES AND INTERNATIONAL TRADE Ole Odgaard Denmark Abstract: The

More information

DONG Energy offshore wind experience

DONG Energy offshore wind experience DONG Energy offshore wind experience Future Tendering Process for Offshore Wind Energy February 10th 2011 Per Hjelmsted Pedersen Head of Project Development DONG Energy Renewables DONG Energy Renewables

More information

Strategy of the German Government on the use of off-shore wind energy

Strategy of the German Government on the use of off-shore wind energy Strategy of the German Government on the use of off-shore wind energy in the context of its national sustainability strategy Ministries involved: Federal Ministry for the Environment, Nature Conservation

More information

Wind Farm Zone. Offshore wind energy. in the Netherlands. Project & Site Description. # Borssele

Wind Farm Zone. Offshore wind energy. in the Netherlands. Project & Site Description. # Borssele # Borssele Offshore wind energy Wind Farm Zone in the Netherlands Project & Site Description The roadmap from 1,000 to 4,500 MW offshore wind capacity >> Sustainable. Agricultural. Innovative. International.

More information

Figure 1: The existing 12 300 kw turbines with the Avedøre power plant, source [3].

Figure 1: The existing 12 300 kw turbines with the Avedøre power plant, source [3]. HVIDOVRE OFFSHORE WIND FARM Hans Christian Sørensen SPOK ApS / Hvidovre Vindmøllelaug I/S, Blegdamsvej 4, DK 2200, Copenhagen N, Denmark, E-mail: consult@spok.dk, Phone: +45 35360219/+45 28110219, Fax:

More information

Electricity in Egypt

Electricity in Egypt T: (+20) 2 3760 4592 F: (+20) 2 3760 4593 A: 16 Hussein Wassef Street, Messaha Square Dokki, Giza, Egypt 12311 www.ide.com.eg Electricity in Egypt Policy and Regulatory Reform November 2015 Electricity

More information

The Liberalized Electricity Market

The Liberalized Electricity Market 1. The market When the electricity market is liberalized, electricity becomes a commodity like, for instance, grain or oil. At the outset, there is as in all other markets a wholesale market and a retail

More information

Renewable Electricity and Liberalised Markets REALM. JOULE-III Project JOR3-CT98-0290 GREECE ACTION PLAN. By ICCS / NTUA K. Delkis

Renewable Electricity and Liberalised Markets REALM. JOULE-III Project JOR3-CT98-0290 GREECE ACTION PLAN. By ICCS / NTUA K. Delkis Renewable Electricity and Liberalised Markets REALM JOULE-III Project JOR3-CT98-0290 GREECE ACTION PLAN By ICCS / NTUA K. Delkis October 1999 INTRODUCTION AND BACKGROUND Background to Renewable Energy

More information

OFFSHORE WIND ENERGY IS GETTING CHEAPER

OFFSHORE WIND ENERGY IS GETTING CHEAPER OFFSHORE WIND ENERGY IS GETTING CHEAPER Market foresight and scale drive the cost down Dansk Energi, January 14, 2016 Sune Strøm, Manager, Regulatory Affairs Wind Power Offshore wind is closing in on the

More information

The Nordic Electricity Exchange and The Nordic Model for a Liberalized Electricity Market

The Nordic Electricity Exchange and The Nordic Model for a Liberalized Electricity Market The Nordic Electricity Exchange and The Nordic Model for a Liberalized Electricity Market 1 The market When the electricity market is liberalized, electricity becomes a commodity like, for instance, grain

More information

Grid connection of near shore wind farms

Grid connection of near shore wind farms Grid connection of near shore wind farms methods, preconditions and results Rene Starup 5. Marts 2015 1 Topics Methods Preconditions Technical and socio-economic analysis 5. Marts 2015 2 60, 150 and 400

More information

BMP Guidelines. Environmental Impact Assessment (EIA) report for activities related to hydrocarbon exploration and exploitation offshore Greenland

BMP Guidelines. Environmental Impact Assessment (EIA) report for activities related to hydrocarbon exploration and exploitation offshore Greenland BMP Guidelines for preparing an Environmental Impact Assessment (EIA) report for activities related to hydrocarbon exploration and exploitation offshore Greenland Danish National Environmental Research

More information

Preliminary Information Memorandum. Thanet Offshore Transmission Assets. July 2009

Preliminary Information Memorandum. Thanet Offshore Transmission Assets. July 2009 Preliminary Information Memorandum Thanet Offshore Transmission Assets July 2009 SUMMARY In April 2009 Ofgem distributed a teaser document, UK Offshore Transmission Investment Opportunity, to investors

More information

Results and Challenges 2012

Results and Challenges 2012 Results and Challenges 2012 Contents Profile 3 Preface 4 Summary 7 Energy prices 8 The Danish Energy Regulatory Authority is developing new electricity price statistics 20 The electricity bill incomprehensible

More information

Energinet.dk and the Danish Energy System

Energinet.dk and the Danish Energy System Energinet.dk and the Danish Energy System South African delegation Fredericia, 22 October 2015 Peter Jørgensen, Vice President 22 October 2015 Energinet.dk and the Danish Energy System 1 Agenda Introduction

More information

TOWARDS AN AUCTION SYSTEM FOR RENEWABLE ENERGY REMUNERATION: KEY POINTS PAPER PUBLISHED

TOWARDS AN AUCTION SYSTEM FOR RENEWABLE ENERGY REMUNERATION: KEY POINTS PAPER PUBLISHED ENERGY BRIEFING TOWARDS AN AUCTION SYSTEM FOR RENEWABLE ENERGY REMUNERATION: KEY POINTS PAPER PUBLISHED AUGUST 2015 FROM 2017, AN AUCTION SYSTEM WILL APPLY TO RENEWABLE ENERGY REMUNERATION THE KEY POINTS

More information

FOR USE WITH PPP PROJECTS 1 SAMPLE GUIDELINES FOR PRE-QUALIFICATION AND COMPETITIVE BIDDING PROCESS 2

FOR USE WITH PPP PROJECTS 1 SAMPLE GUIDELINES FOR PRE-QUALIFICATION AND COMPETITIVE BIDDING PROCESS 2 FOR USE WITH PPP PROJECTS 1 SAMPLE GUIDELINES FOR PRE-QUALIFICATION AND COMPETITIVE BIDDING PROCESS 2 1. PRE-QUALIFICATION 1.1 The requirements for pre-qualifications will be reasonable and efficient and

More information

The Status of the Wind Power Market in Egypt. Dr. Walid El-Khattam Ain Shams University (Cairo, Egypt) The Egyptian Electricity Regulator (EgyptERA)

The Status of the Wind Power Market in Egypt. Dr. Walid El-Khattam Ain Shams University (Cairo, Egypt) The Egyptian Electricity Regulator (EgyptERA) The Status of the Wind Power Market in Egypt Dr. Walid El-Khattam Ain Shams University (Cairo, Egypt) The Egyptian Electricity Regulator (EgyptERA) Berlin, June 11 th, 2013 1 Contents Key Challenges for

More information

Dansk Offshore Netværk, Lindø Industripark, 21. April 2015 The Road to Below 10 ct /kwh

Dansk Offshore Netværk, Lindø Industripark, 21. April 2015 The Road to Below 10 ct /kwh Dansk Offshore Netværk, Lindø Industripark, 21. April 2015 The Road to Below 10 ct /kwh, Head of Cost of Energy Siemens AG, Wind Power and Renewables Answers for energy. Introduction Siemens Wind Power

More information

The Electricity Supply Bill 1

The Electricity Supply Bill 1 Bill no. 234 Folketinget (Danish Parliament) 1998-99 Unauthorised translation 30 June 1999 Submitted on 29 April 1999 by the Minister for Environment and Energy (Svend Auken) Adopted by Folketinget on

More information

Latest Offshore Developments in Sweden

Latest Offshore Developments in Sweden Latest Offshore Developments in Sweden Conference Copenhagen Offshore Wind, Offshore Wind Markets Myths and Realities Bella Center, 27 October 2005 Kenneth Averstad, Vattenfall AB Renewable Energy within

More information

Tidal Energy. Wind Energy. Transmission & Distribution Network. Offshore Substation. Onshore Substation. Tidal Stream Energy.

Tidal Energy. Wind Energy. Transmission & Distribution Network. Offshore Substation. Onshore Substation. Tidal Stream Energy. Offshore Renewables Tidal Energy Transmission & Distribution Network Offshore Substation Wind Energy Onshore Substation Tidal Stream Energy Consumer Atkins in Offshore Renewables The offshore wind journey

More information

Developing Ocean Energy in Ireland. Belmullet Wave Energy Test Site

Developing Ocean Energy in Ireland. Belmullet Wave Energy Test Site Developing Ocean Energy in Ireland Belmullet Wave Energy Test Site Where does our energy come from? Most of the energy we use in Ireland comes from fossil fuels such as oil, coal, peat and gas. We burn

More information

Council of the European Union Brussels, 20 May 2016 (OR. en)

Council of the European Union Brussels, 20 May 2016 (OR. en) Council of the European Union Brussels, 20 May 2016 (OR. en) 8673/1/16 REV 1 ER 141 CLIMA 43 NOTE From: To: Subject: General Secretariat of the Council Delegations Political declaration on energy cooperation

More information

Renewable Energy Strategy for 2020 and Regulatory Framework. Eng. Hatem Amer Egyptian Electric Regulatory and Consumer Protection Agency

Renewable Energy Strategy for 2020 and Regulatory Framework. Eng. Hatem Amer Egyptian Electric Regulatory and Consumer Protection Agency Renewable Energy Strategy for 2020 and Regulatory Framework Eng. Hatem Amer Egyptian Electric Regulatory and Consumer Protection Agency Objectives of the Agency Regulate, supervise, and control all matters

More information

The UK Offshore Wind Experience

The UK Offshore Wind Experience The UK Offshore Wind Experience Tom Simchak Policy Advisor, Energy British Embassy, Washington EESI Briefing, 28 September 2015 UNCLASSIFIED The United Kingdom is The global market leader in offshore wind:

More information

Viking Link Interconnector

Viking Link Interconnector Viking Link Interconnector Public information event for Bicker Parish Why we re here today We re here today to introduce the Viking Link project, to explain what we want to build and to answer any questions

More information

Renewable Energies WIND

Renewable Energies WIND WIND International Master in Sustainable Development and CR 2011-2012 Marcos López-Brea Index 1. Technical description: technology options, learning curve and grid integration. 2. Regulatory framework:

More information

https://www.ofgem.gov.uk/publications-and-updates/ofto-build-providing-additional-flexibility-through-extendedframework

https://www.ofgem.gov.uk/publications-and-updates/ofto-build-providing-additional-flexibility-through-extendedframework All interested parties Direct Dial: 020 7901 1849 Email: transmissioncompetition@ofgem.gov.uk Date: 17 November 2015 Dear Colleague EPC Contract Principles for OFTO Build Tenders This letter provides guidance

More information

A sustainable energy and climate policy for the environment, competitiveness and long-term stability

A sustainable energy and climate policy for the environment, competitiveness and long-term stability 2009-02-05 A sustainable energy and climate policy for the environment, competitiveness and long-term stability The party leaders of Alliance for Sweden entered into an agreement today on a long-term,

More information

Investing in renewable technologies CfD contract terms and strike prices

Investing in renewable technologies CfD contract terms and strike prices Investing in renewable technologies CfD contract terms and strike prices December 2013 Crown copyright 2013 You may re-use this information (not including logos) free of charge in any format or medium,

More information

THE AMENDED RENEWABLE ENERGY SOURCES ACT 2014 (EEG 2014)

THE AMENDED RENEWABLE ENERGY SOURCES ACT 2014 (EEG 2014) THE AMENDED RENEWABLE ENERGY SOURCES ACT 2014 (EEG 2014) 18.08.2014 Energy Regulatory & Governmental Affairs The Amended Renewable Energy Sources Act 2014 (EEG 2014) With the most recent amendment of the

More information

RGI Cable Workshop Understanding Underground Cables 13 and 14 February in Spreitenbach, Switzerland A workshop kindly hosted by Swissgrid

RGI Cable Workshop Understanding Underground Cables 13 and 14 February in Spreitenbach, Switzerland A workshop kindly hosted by Swissgrid RGI Cable Workshop Understanding Underground Cables 13 and 14 February in Spreitenbach, Switzerland A workshop kindly hosted by Swissgrid During the 1.5 day workshop, more than 70 participants from industry,

More information

Procurement Strategy 2013-2017 Delivering Social Value for our Community

Procurement Strategy 2013-2017 Delivering Social Value for our Community Procurement Strategy 2013-2017 Delivering Social Value for our Community Making Bath & North East Somerset an even better place to live, work and visit 1 Picture courtesy of Bath & News Media Group Our

More information

FRANCE: UPDATE ON THE SUPPORT MECHANISM FOR RENEWABLE ENERGY PROJECTS

FRANCE: UPDATE ON THE SUPPORT MECHANISM FOR RENEWABLE ENERGY PROJECTS BRIEFING FRANCE: UPDATE ON THE SUPPORT MECHANISM FOR RENEWABLE ENERGY PROJECTS SEPTEMBER 2015 ENERGY TRANSITION ACT ADOPTED ON 22 JULY 2015 NEW SUPPORT MECHANISM THE CONTRACT FOR DIFFERENCE CALCULATION

More information

ELECTRICITY MARKET ACT

ELECTRICITY MARKET ACT 1 NB: Unofficial translation Ministry of Trade and Industry, Finland ELECTRICITY MARKET ACT (386/1995; amendments up to 1172/2004 included) In accordance with a decision by Parliament, the following is

More information

Monobuckets and the competitiveness versus monopiles and jacket structures.

Monobuckets and the competitiveness versus monopiles and jacket structures. Monobuckets and the competitiveness versus monopiles and jacket structures. Lars Bo Ibsen, Aalborg University, Professor. Foundation concepts for offshore Wind Turbines The Universal Foundation Carbon

More information

Electricity market drivers

Electricity market drivers Daniel Assandri Head of Power Systems ABB (China) Ltd Electricity market drivers March 2008 Global T&D Market Drivers ABB Power Systems division - slide # 2 ABB s view on and market drivers The Americas

More information

EURELECTRIC presentation. EURELECTRIC contribution to a reference model for European capacity markets. DG COMP workshop 30 June 2015

EURELECTRIC presentation. EURELECTRIC contribution to a reference model for European capacity markets. DG COMP workshop 30 June 2015 EURELECTRIC presentation EURELECTRIC contribution to a reference model for European capacity markets DG COMP workshop 30 June 2015 EURELECTRIC believes that energy, flexibility and capacity are all needed

More information

7: The electricity market

7: The electricity market 7: The electricity market 94 : Facts 2008 : Energy and Water Resources in Norway The power sector in Norway is regulated by the Energy Act. Market-based power trading is one of the principles incorporated

More information

EUROPEAN COMMISSION. State aid No SA.36204 2013/N Denmark Aid to photovoltaic installations and other renewable energy installations

EUROPEAN COMMISSION. State aid No SA.36204 2013/N Denmark Aid to photovoltaic installations and other renewable energy installations EUROPEAN COMMISSION Bruxelles, 24.10.2014 C(2014) 8004 corr. PUBLIC VERSION This document is made available for information purposes only. Subject: State aid No SA.36204 2013/N Denmark Aid to photovoltaic

More information

Experience from the first large scale tidal turbine EIA in Europe. How do we work towards effective and proportionate EIA?

Experience from the first large scale tidal turbine EIA in Europe. How do we work towards effective and proportionate EIA? Independent, integrated thinking Experience from the first large scale tidal turbine EIA in Europe How do we work towards effective and proportionate EIA? Liz Foubister IEMA Webinar 30 th July 2014 What

More information

Renewable Energy Promotion Policies in Chinese Taipei

Renewable Energy Promotion Policies in Chinese Taipei Renewable Energy Promotion Policies in Chinese Taipei Bureau of Energy, Ministry of Economic Affairs Chinese Taipei November 12, 2014 RE for CT - 1 Current Development of Renewables in Chinese Taipei RE

More information

August 2000. A Review of the Development of Competition in the Industrial and Commercial Gas Supply Market

August 2000. A Review of the Development of Competition in the Industrial and Commercial Gas Supply Market August 2000 A Review of the Development of Competition in the Industrial and Commercial Gas Supply Market Executive summary This document explains the conclusions of Ofgem s 1999 review of the development

More information

CALL FOR PROPOSALS FOR BASREC PROJECT ACTIVITY: THE STUDY ON THE DEVELOPMENT OF REGIONAL GAS MARKET IN THE EASTERN BALTIC SEA REGION

CALL FOR PROPOSALS FOR BASREC PROJECT ACTIVITY: THE STUDY ON THE DEVELOPMENT OF REGIONAL GAS MARKET IN THE EASTERN BALTIC SEA REGION CALL FOR PROPOSALS FOR BASREC PROJECT ACTIVITY: THE STUDY ON THE DEVELOPMENT OF REGIONAL GAS MARKET IN THE EASTERN BALTIC SEA REGION At the Baltic Sea Region Energy Co-operation (BASREC) Meeting of Energy

More information

A Green Sector Overview

A Green Sector Overview A Green Sector Overview Micro Hydro Electric Power Ontario's Waterpower Resources: Past and Present The first hydroelectric generator in Canada was installed near Ottawa, which was the first city in North

More information

Germany. Key issues. 1. General overview

Germany. Key issues. 1. General overview Germany Key issues High volumes of renewables have changed the way the electricity market in Germany operates. In 2012 direct marketing increased, in particular in onshore wind, due to a change of the

More information

OFFSHORE WIND TOWARD 2020 ON THE PATHWAY TO COST COMPETITIVENESS

OFFSHORE WIND TOWARD 2020 ON THE PATHWAY TO COST COMPETITIVENESS 1 OFFSHORE WIND TOWARD 2020 ON THE PATHWAY TO COST COMPETITIVENESS April 2013 Contents A B C Offshore market volume of EUR 130 bn by 2020 Agenda 2020 Markets Trends Competition Page 3 Value chain evaluation

More information

The Role of a Pension Fund in Renewable Energy Investments. Transformational NAMA in the Renewable Energy Sector May 2013

The Role of a Pension Fund in Renewable Energy Investments. Transformational NAMA in the Renewable Energy Sector May 2013 The Role of a Pension Fund in Renewable Energy Investments Transformational NAMA in the Renewable Energy Sector May 2013 PensionDanmark at a Glance Industry-wide pension fund established in the early 1990

More information

Energy Trading. Jonas Abrahamsson Senior Vice President Trading. E.ON Capital Market Day Nordic Stockholm, July 3, 2006

Energy Trading. Jonas Abrahamsson Senior Vice President Trading. E.ON Capital Market Day Nordic Stockholm, July 3, 2006 Energy Trading Jonas Abrahamsson Senior Vice President Trading E.ON Capital Market Day Nordic Stockholm, July 3, 2006 Agenda The Nordic Power Market The Role of Energy Trading within E.ON Nordic Page 2

More information

Draft law on Renewable Energy Sources - Update January 2014

Draft law on Renewable Energy Sources - Update January 2014 Draft law on Renewable Energy Sources - Update January 2014 On 3 January 2014 another draft of new law on Renewable Energy Sources ( RES ) was published by the Polish Ministry of Economy ( MoE ). Additionally,

More information

Offshore Wind: some of the Engineering Challenges Ahead

Offshore Wind: some of the Engineering Challenges Ahead Offshore Wind: some of the Engineering Challenges Ahead David Infield CDT in Wind Energy Systems Institute of Energy and Environment University of Strathclyde International context (from IPCC report) Greenhouse

More information

Fish benefits from offshore wind farm development

Fish benefits from offshore wind farm development Downloaded from orbit.dtu.dk on: Jul 02, 2016 Fish benefits from offshore wind farm development Leonhard, Simon B.; Stenberg, Claus; Støttrup, Josianne Gatt; Deurs, Mikael van; Christensen, Asbjørn; Pedersen,

More information

Cable action plan. 132-150 kv grids March 2009

Cable action plan. 132-150 kv grids March 2009 Cable action plan 132-150 kv grids March 2009 Table of contents 1. Summary of the cable action plan 3 2. Introduction 7 3. Planning scenarios 8 4. Existing overhead lines 8 4.1 Economically optimal dismantling

More information

EIA case for Hiiumaa offshore wind farm in Estonia

EIA case for Hiiumaa offshore wind farm in Estonia EIA case for Hiiumaa offshore wind farm in Estonia Georg Martin & Liis Rostin With contributions from Aune Aunapuu, Ramboll Eesti and materials from Nelja Energia Seminar on Environmental Impact Assessment

More information

Submarine Power Cables. State-of-the-art production facility, more than 100 years of experience and reference installations around the world.

Submarine Power Cables. State-of-the-art production facility, more than 100 years of experience and reference installations around the world. Submarine Power Cables State-of-the-art production facility, more than 100 years of experience and reference installations around the world. Reliable submarine power cables ABB is one of the world s most

More information

Environment and energy briefing from Burges Salmon published in the March 2014 issue of The In-House Lawyer:

Environment and energy briefing from Burges Salmon published in the March 2014 issue of The In-House Lawyer: Environment and energy briefing from Burges Salmon published in the March 2014 issue of The In-House Lawyer: Electricity market reform: an update on contracts for difference Electricity market reform:

More information

Who are we? *Based on an average annual domestic household electricity consumption of 4,700KWh (DECC).

Who are we? *Based on an average annual domestic household electricity consumption of 4,700KWh (DECC). Who are we? We re one of the world s leading power and gas companies. Here in the UK, we supply energy to more than 5 million customers, generate enough electricity for around 8 million homes and employ

More information

SAMPLE TERMS OF REFERENCE FOR ELECTRICITY SECTOR PRIVATIZATION TRANSACTION ADVISORY SERVICES

SAMPLE TERMS OF REFERENCE FOR ELECTRICITY SECTOR PRIVATIZATION TRANSACTION ADVISORY SERVICES SAMPLE TERMS OF REFERENCE FOR ELECTRICITY SECTOR PRIVATIZATION TRANSACTION ADVISORY SERVICES Table of Contents 1st. INTRODUCTION... 3 2nd. ELECTRICITY SECTOR BACKGROUND. 4 3rd. SCOPE OF WORK. 6 PHASE :

More information

EcoGrid EU NEWSLETTER No 1

EcoGrid EU NEWSLETTER No 1 EcoGrid EU NEWSLETTER No 1 February 2012 EcoGrid EU POWER MARKET OPERATION IN REAL TIME The objective of EcoGrid EU is ambitious to develop a prototype of a European Smart Grid market platform. The demonstration

More information

Offshore Wind. IEEE Boston PES - November 16, 2010

Offshore Wind. IEEE Boston PES - November 16, 2010 Offshore Wind IEEE Boston PES - November 16, 2010 Offshore Wind A high-level overview of offshore wind project development identifying current technologies, challenges, risks and costs. Presented by: Brook

More information

Developing Estonian energy policy hand in hand with EU energy packages

Developing Estonian energy policy hand in hand with EU energy packages Developing Estonian energy policy hand in hand with EU energy packages Einari Kisel Secretary General of Energy of the Estonian Ministry of Economic Affairs and Communications 2008 will go down in history

More information

Security of electricity supply

Security of electricity supply Security of electricity supply Definitions, roles & responsibilities and experiences within the EU Thomas Barth Chairman of Energy Policy & Generation Committee EURELECTRIC Outline Security of Supply a

More information

Danish Energy Model RE Policy Tools MAIN Asian Dialog, Bali January 20-22 2014. Mr. Henrik Breum Special Advisor

Danish Energy Model RE Policy Tools MAIN Asian Dialog, Bali January 20-22 2014. Mr. Henrik Breum Special Advisor Danish Energy Model RE Policy Tools MAIN Asian Dialog, Bali January 20-22 2014 Mr. Henrik Breum Special Advisor Agenda Danish Energy Model RE Policy Tools Introduction The Danish Energy Model Past, now

More information

Data Communications Company (DCC) price control guidance: process and procedures

Data Communications Company (DCC) price control guidance: process and procedures Guidance document Contact: Tricia Quinn, Senior Economist Publication date: 27 July 2015 Team: Smarter Metering Email: tricia.quinn@ofgem.gov.uk Overview: The Data and Communications Company (DCC) is required

More information

Skyrocketing Electricity Cost in Denmark

Skyrocketing Electricity Cost in Denmark 1 Skyrocketing Electricity Cost in Denmark There is a lot of evidence that electricity for households is more expensive in Denmark than anywhere else in the EU. However, most of the household price is

More information

A new electricity market for Northern Ireland and Ireland from 2016 - Integrated Single Electricity Market (I-SEM)

A new electricity market for Northern Ireland and Ireland from 2016 - Integrated Single Electricity Market (I-SEM) A new electricity market for Northern Ireland and Ireland from 2016 - Integrated Single Electricity Market (I-SEM) Non-technical summary High level design Draft Decision Paper SEM -14-047 June 2014 1 INTRODUCTION

More information

Why wind power works for Denmark

Why wind power works for Denmark Proceedings of ICE Civil Engineering 158 May 25 Pages 66 72 Paper 13663 Keywords electrical engineering & distribution; power stations (non-fossil fuel); weather Why wind power works for Denmark Hugh Sharman

More information

Non Traditional Business Models: Supporting transformative change in the energy market

Non Traditional Business Models: Supporting transformative change in the energy market Non Traditional Business Models: Supporting transformative change in the energy market Response by Community Energy England, Regen SW, Community Energy Coalition and 10:10 SUMMARY This is a collaborative

More information

The Energy Triangle Wind Power

The Energy Triangle Wind Power Wind Power The Energy Triangle Wind Power In supplying society with its energy needs, a balance must be struck between three key dimensions: competitiveness, security of supply, and environment and climate.

More information

SWEDISH COMPETITION AUTHORITY. Deregulation of the Swedish Electricity Market

SWEDISH COMPETITION AUTHORITY. Deregulation of the Swedish Electricity Market SWEDISH COMPETITION AUTHORITY Deregulation of the Swedish Electricity Market Swedish Competition Authority November 1996 ISSN 1401-8438 Tryckgruppen AB, Stockholm 1996 Contents: 1 Rules for the Swedish

More information

1. EXECUTIVE SUMMARY AND KEY RECOMMENDATIONS

1. EXECUTIVE SUMMARY AND KEY RECOMMENDATIONS 1. EXECUTIVE SUMMARY AND KEY RECOMMENDATIONS EXECUTIVE SUMMARY Energy policy in Greece has the potential to make a significant contribution to the country s economic recovery. Increasing competition and

More information

TENDER INSTRUCTIONS Consulting services and auction software in connection with the 1800 MHz auction. 23 March 2015 Case no.

TENDER INSTRUCTIONS Consulting services and auction software in connection with the 1800 MHz auction. 23 March 2015 Case no. TENDER INSTRUCTIONS Consulting services and auction software in connection with the 1800 MHz auction 23 March 2015 Case no. 2015-2800 Table of contents List of annexes... 3 1. The overall framework for

More information

Offshore Wind Energy and Industrial Development in the Republic of Ireland

Offshore Wind Energy and Industrial Development in the Republic of Ireland Offshore Wind Energy and Industrial Development in the Republic of Ireland Offshore Wind Energy and Industrial Development in the Republic of Ireland Report prepared by Risø National Laboratory on behalf

More information

A Gazprom A Energy Gazprom whitepaper Energy Guide. Energy. What are you paying for?

A Gazprom A Energy Gazprom whitepaper Energy Guide. Energy. What are you paying for? A Gazprom A Energy Gazprom whitepaper Energy Guide Energy What are you paying for? 2 Introduction According to government statistics, the cost of buying electricity to businesses in the UK has increased

More information

Price developments on the EU retail markets for electricity and gas 1998 2011

Price developments on the EU retail markets for electricity and gas 1998 2011 Price developments on the EU retail markets for electricity and gas 1998 2011 The Market Observatory for Energy has analysed price developments on the retail markets for electricity and natural gas (domestic

More information

Green or black windpower? Salzburg 30 August 2011

Green or black windpower? Salzburg 30 August 2011 Green or black windpower? Salzburg 30 August 2011 Frede Hvelplund Aalborg Universitet Department of Development and Planning Ownership and marketconstruction I. Ownership construction ( Ownership for efficient

More information

How To Join The Uk International Management Association

How To Join The Uk International Management Association UK International Healthcare Management Association Prospectus and call for founder members 2 3 Do you want to win new international business? Would your organisation benefit from market intelligence, strategic

More information

COMPETITIVE ELECTRIC ENERGY MARKET IN GREECE

COMPETITIVE ELECTRIC ENERGY MARKET IN GREECE NATIONAL TECHNICAL UNIVERSITY OF ATHENS (NTUA) GREECE COMPETITIVE ELECTRIC ENERGY MARKET IN GREECE EVANGELOS DIALYNAS Professor NTUA Director of Electric Power Division 1 Competitive Electric European

More information

Opportunities for the Georgian Hydropower industry to benefit from Directive 2009/28EC of the European Parliament

Opportunities for the Georgian Hydropower industry to benefit from Directive 2009/28EC of the European Parliament Promotion hidroenergetikasi Project investiciebis (HIPP) Opportunities for the Georgian Hydropower industry to benefit from Directive 2009/28EC of the European Parliament What Europe wants to do Comply

More information

Optimization of the coupled grid connection of offshore wind farms

Optimization of the coupled grid connection of offshore wind farms Optimization of the coupled grid connection of offshore wind farms Dirk Schoenmakers Graduation project at Evelop Netherlands BV Technical University of Eindhoven September 2008 Supervisors: TU Eindhoven

More information

UK renewable energy an update

UK renewable energy an update UK renewable energy an update 30 October 2014 Robert Hull, Managing Director Renewable energy key challenges 1 2 3 Costs to Climate change: Risks to security consumers: decarbonising of supply: short affordability

More information

ESRI Research Note. The Irish Electricity Market: New Regulation to Preserve Competition Valeria di Cosmo and Muireann Á. Lynch

ESRI Research Note. The Irish Electricity Market: New Regulation to Preserve Competition Valeria di Cosmo and Muireann Á. Lynch ESRI Research Note The Irish Electricity Market: New Regulation to Preserve Competition Valeria di Cosmo and Muireann Á. Lynch Research Notes are short papers on focused research issues. They are subject

More information

Standard conditions of the Electricity Distribution Licence

Standard conditions of the Electricity Distribution Licence Gas and Electricity Markets Authority ELECTRICITY ACT 1989 Standard conditions of the Electricity Distribution Licence Standard conditions of the Electricity Distribution Licence 30 October 2015 SECTION

More information

Tufts Consulting Group: Macedonian Energy

Tufts Consulting Group: Macedonian Energy March 2010 CENTER FOR EMERGING MARKETS ENTERPRISES STUDENT RESEARCH SERIES Tufts Consulting Group: Macedonian Energy An Executive Summary Opportunity In the more than 18 years since its independence from

More information

An energy of the future coming from the sea

An energy of the future coming from the sea An energy of the future coming from the sea MAP showing the location of the Calvados offshore wind farm Why do we install off the coast of Calvados? Calvados offshore 75 PIONEER location of offshore wind

More information

The installation and servicing

The installation and servicing European Forum for Renewable Energy Sources The installation and servicing of offshore wind farms Kaj Lindvig, CSO, A2SEA A/S 16 th September 2010 A2SEA Started 1 st July 2000 100% dedicated offshore wind

More information

Recent developments of feed-in systems in the EU A research paper for the International Feed-In Cooperation

Recent developments of feed-in systems in the EU A research paper for the International Feed-In Cooperation 1 Recent developments of feed-in systems in the EU A research paper for the International Feed-In Cooperation January 2012 A report commissioned by the Ministry for the Environment, Nature Conservation

More information

COWI offshore wind marine engineering services

COWI offshore wind marine engineering services COWI offshore wind marine engineering services 2 COWI expertise COWI is a highly versatile and multidisciplinary company. We provide services within engineering, environment and economics and operate worldwide

More information

R&D in Vattenfall Johan Söderbom

R&D in Vattenfall Johan Söderbom R&D in Vattenfall Johan Söderbom Agenda 1 2 3 Vattenfall in brief R&D portfolio Smart Grids Vattenfall in brief Net sales 2011: 181 billion SEK (20 billion ) Electricity Generation: 166,7 TWh 7.8 million

More information

National Report 2014 to the Agency for the Cooperation of Energy Regulators and to the European Commission

National Report 2014 to the Agency for the Cooperation of Energy Regulators and to the European Commission Ref: 1602/601/2014 10.7.2014 National Report 2014 to the Agency for the Cooperation of Energy Regulators and to the European Commission Finland National Report 2014 - Energy Authority, Finland 1 CONTENT

More information

AN INDEPENDENT ANALYSIS COMMISSIONED BY STATKRAFT UK

AN INDEPENDENT ANALYSIS COMMISSIONED BY STATKRAFT UK OFFSHORE WIND: DELIVERING MORE FOR LESS AN INDEPENDENT ANALYSIS COMMISSIONED BY STATKRAFT UK JULY 2015 BVG Associates BVG Associates is a technical consultancy with expertise in wind and marine energy

More information

Profile. Marine ingenuity In just two words, we show what we do, how we do it, and what makes us different. Dredging and Marine Contractors

Profile. Marine ingenuity In just two words, we show what we do, how we do it, and what makes us different. Dredging and Marine Contractors Profile Marine ingenuity In just two words, we show what we do, how we do it, and what makes us different Dredging and Marine Contractors Company profile Artemis is one of the most powerful self-propelled

More information

Renewable energy. Impact report

Renewable energy. Impact report Renewable energy Impact report Prepared by Audit Scotland May 2015 Audit Scotland is a statutory body set up in April 2000 under the Public Finance and Accountability (Scotland) Act 2000. It provides services

More information

English text only DIRECTORATE FOR FINANCIAL AND ENTERPRISE AFFAIRS COMPETITION COMMITTEE ANNUAL REPORT ON COMPETITION POLICY DEVELOPMENTS IN DENMARK

English text only DIRECTORATE FOR FINANCIAL AND ENTERPRISE AFFAIRS COMPETITION COMMITTEE ANNUAL REPORT ON COMPETITION POLICY DEVELOPMENTS IN DENMARK Unclassified DAF/COMP(2005)18/05 DAF/COMP(2005)18/05 Unclassified Organisation de Coopération et de Développement Economiques Organisation for Economic Co-operation and Development 26-May-2005 English

More information

JEDI Capital Expenditure Update

JEDI Capital Expenditure Update JEDI Capital Expenditure Update U.S. Offshore Wind Market and Supply Chain Workshop Presented by Aaron Smith National Renewable Energy Laboratory Brent Cooper Ocean & Coastal Consultants, Inc. 2014 Navigant

More information