Environmental and Social Monitoring Report. INDONESIA: Tangguh Liquefied Natural Gas Project Compliance Monitoring Inception Report

Size: px
Start display at page:

Download "Environmental and Social Monitoring Report. INDONESIA: Tangguh Liquefied Natural Gas Project Compliance Monitoring Inception Report"

Transcription

1 Environmental and Social Monitoring Report Project Number: June 2007 INDONESIA: Tangguh Liquefied Natural Gas Project Compliance Monitoring Inception Report Prepared by GHD External Panel for Environmental and Social Monitoring This report has been submitted to ADB by GHD and is made publicly available in accordance with ADB s public communications policy (2005). It does not necessarily reflect the views of ADB.

2 Tangguh LNG Project External Panel Compliance Monitoring Inception Report June 2007

3 Contents Executive Summary i 1. Introduction 1 2. The Objectives of the External Panel 2 3. External Monitoring Scope of Work Scope of Work Specified in the TOR Detailed Scope of Work Schedule of Work Conducted 9 4. Findings Environment Involuntary Resettlement The Integrated Social Program (ISP) and Social Issues 37 Appendices A Involuntary Resettlement People Interviewed B Consultant (External Panel) Liability

4 Executive Summary This is the Executive Summary of the Compliance Monitoring Inception Report of the External Panel following the inception visit of the External Panel to the Tangguh E&S Project site in March This Executive Summary should be read with the full report. The intent of the inception visit was for the External Panel to begin their familiarisation with the project, and to undertake a first compliance monitoring of specified aspects of the environment (including health and safety), involuntary resettlement, and indigenous peoples and integrated social programs associated with the project. An inception visit is provided for in the Terms of Reference. Background The External Panel is appointed for a three year period from February 2007 to undertake regular monitoring and evaluation of the Tangguh E&S Project located in Teluk Bintuni Regency of Irian Jaya Barat Province (formerly part of Papua Province), Indonesia. The External Panel is required to satisfy the Asian Development Bank (ADB) Tranche Lender s and Japanese Bank for International Cooperation s (JBIC) policy requirements for independent external monitoring and evaluation of environmental and social aspects of the Tangguh LNG Project. This includes the requirements to verify the internal monitoring of the Operator (Tangguh Project), report regularly to the Lenders and Operators on environmental and social compliance issues, review and comment on reports from the Operator, review and comment on Corrective Actions Plans, and report and advise on an ad hoc basis on environmental and social issues. The work of the External Panel is the subject of a contract with the Asian Development Bank, the Japan International Finance Management (Tangguh) Corporation, and Mizuho Corporate Bank Ltd. The External Panel is comprised of three specialist skill areas. These include an Environmental Team, a Resettlement Specialist, and an Indigenous Peoples and Social Issues Team. This report addresses the reporting requirements under the following headings:» Environment, and Health and Safety;» Involuntary Resettlement; and» Indigenous Peoples and Integrated Social Programme. This report presents the findings of the External Panel s inception visit, which are of necessity limited. The full Terms of Reference for the External Panel will be fulfilled over the three years of the contract. The time and resources available during the inception visit could not allow the External Panel to achieve a full understanding of all dimensions of what is a very complex project. Summary of Overall Findings The External Panel finds the environmental and social compliance performance of the Tangguh E&S Project to be satisfactory overall. Nevertheless, the External Panel identifies five apparent Level 1 Non Compliance issues, and hence all are reversible. These include three for Involuntary Resettlement, one for Environment, and one for the Integrated Social Programs, concerning the following matters (see main report). i

5 » Organic waste pit condition (Section 4.1);» Tasks associate with the Dimaga Foundation (Section 4.2);» Provision of LNG construction phase employment to village households (Section 4.2);» Monitoring and evaluation (Section 4.2);» Integration of gender and development perspectives across implementation of all activities and in accordance with Lenders gender policies (Section 4.3). There are some additional issues raised in environmental, health and safety, resettlement and social programme areas that if appropriately addressed could assist performance. Environment The regional environment is a relatively robust and dynamic natural system. The surrounding environment is found to be in generally good condition. The terrestrial environment adjacent to the construction site is protected by the secure perimeter that has been fenced. The External Panel saw no evidence to suggest that the marine environment has been adversely affected by installation of structures, pipelines or shipping activity associated with the project. With respect to all activities and compliance requirements associated with the construction stage, the External Panel notes that compliance issues and need for corrective actions have been raised in recent prior AMDAL audits by the Ministry of Environment (MoE), and the Operator and contractors have demonstrated consistent action to address compliance issues raised. The External Panel notes that for such a large and complex project constant responses to environmental management challenges will continue. The External Panel makes some comment on aspects of waste management on the construction site. The existence and condition of the organic waste pit appears to constitute a Non Compliance. Health and Safety The External Panel notes that as at March 2007 there have been 25 million man hours worked without a lost time injury/illness on the Tangguh LNG project. Given that the construction phase is currently operating at peak employee levels working on the Tangguh LNG Project construction site, this is a significant achievement. The External Panel concludes that maintaining this exceptionally good rate requires continued improvements especially with respect to safety training, site safety communication and collaboration, and in the effectiveness of the Subcontractor Supervision. This is important given that in 2008 large quantities of hydrocarbons will be introduced onto the work site presenting a significant increase in the range of hazards and risks. Involuntary Resettlement The Land Acquisition and Resettlement Plan (LARAP) for the Tangguh LNG Project sets a high standard in balancing the demands of a major international investment with international best practice, Indonesian law and with the special characteristics of the traditional adat system. The Lenders conducted due diligence and found that the LARAP meets the Involuntary Resettlement Policies of both ADB and JBIC, in terms of participative planning for compensation to restore lost assets, income and livelihoods; relocation; and rehabilitation to restore, or improve, the economic ii

6 and social base of those affected (ADB Policy on Involuntary Resettlement 1995; and, for JBIC, World Bank Operational Directive (OD) ). The External Panel finds that the phases of physical construction, now almost completed, and relocation, which is fully completed, have been generally successful. Nevertheless, it is in the resettlement affected villages that the Project issues are most immediately apparent. The challenge is now to fulfil the LARAP commitments to an equally high standard. This means completing several outstanding entitlement commitments. It includes activating the Dimaga Foundation, which is designed to replace lost resources, to support the achievement of improved incomes, livelihoods and living standards amongst resettlement affected villagers. It means revitalizing agro forestry, fisheries and enterprise extension work, in anticipation of the phasing down of Project construction work; and resolving current problems in the recruitment of construction workers from resettlement affected villages. It also means attention to Handover Agreements that will ensure continued sustainable operation of the new community assets and facilities. There is a need to re focus on the commitments contained in the LARAP. Within the broader Integrated Social Program (ISP), the LARAP coordination, record keeping and reporting systems need streamlining and enhanced visibility. Monitoring and evaluation systems require special attention to meet the original LARAP commitments. A socio economic survey, conducted to professional standards, is urgently required as scheduled in the LARAP. Monitoring and evaluation data will form the necessary basis for answering those key questions that are explicit in the LARAP objectives: for example, have the livelihoods of those people displaced to make way for the Project been improved? Is their quality of life better than it was? Indigenous Peoples and Integrated Social Program The Integrated Social Program (ISP) has been developed and approved as fulfilling the social, cultural and economic commitments of the Tangguh Project s AMDAL and Lenders Indigenous Peoples policies. It describes 14 components that will be implemented (including LARAP) in order to promote the participation of indigenous people in Tangguh operations; ensure that the region s indigenous people benefit from development interventions; and to mitigate any actual or potential adverse impacts. In addition to the ISP, an Indigenous Peoples Development Framework (IPDF) has been produced which describes how any iterations of the ISP during the Project s long time frame will be managed to maintain compliance with Lenders Indigenous Peoples policies. The key function of the Indigenous Peoples and Social Issues (IPSI) Team is to review and verify compliance in the implementation of the ISP to fulfil the requirements of the Indigenous Peoples policies of ADB and JBIC. The reviews are to be undertaken at 6 monthly intervals over the 5 year period 2006 to 2010 with a mid term review in Evidence regarding implementation of the ISP during this first visit was collected from reports; field observations; presentations and discussions with personnel in Jakarta and the Tangguh site, representatives of multi lateral, national and local partners, and women, men and children in four Directly Affected Villages (DAV). iii

7 The review finds that the implementation of the ISP components is compliant with the Lenders Indigenous Peoples policies, although there are areas where efforts need to be made to ensure improved compliance with the ISP in the implementation of activities. Delays in the implementation of some component activities have been experienced and the External Panel will undertake assessment of their compliance in future visits. While the implementation of the ISP components was found to be compliant overall, a Gender and Development perspective is not being applied to all activities as is required in Section 7.4 of the ISP document. This, however, appears to be the result of an internal contradiction of the ISP document where there is no requirement within each component to integrate a gender perspective and, furthermore, the Women s Empowerment component does not address the question adequately. The women s participation targets in education, vocational education and microfinance and micro enterprise which are required in the Women s Empowerment component do not appear to have been sufficiently defined and data provided to the External Panel were not sex disaggregated nor in a form which would enable assessment of whether the participation targets are being met. In order to improve compliance with the ISP, the IPSI Team s findings include that there is a need to review procedures and ensure medical supply to village workers; to address teacher absenteeism in directly supported DAV schools; to strengthen the women s outreach and participation target activities; and to improve transparency in the CAP activities. Monitoring and evaluation of activities requires strengthening. The team found the Operator ISP staff to be committed, competent and disciplined and well received in those villages visited by the team. Papuans occupy key ISP staff positions and efforts have been made to ensure a good gender balance. The ISP is well resourced and while there is good evidence that all components are being initiated in compliance with policy, some are more advanced than others. Within each component program there are sound mechanisms to ensure continuous transfer and ownership by government and local stakeholders, though progress in that will depend on reliable monitoring and evaluation and possibly modifying some programs to keep pace with a changing socio economic and political landscape that is in turn influenced by the pace of the Tangguh LNG Project development. iv

8 1. Introduction This is the first report of the independent External Panel for the Tangguh E&S Project and is submitted as a Compliance Monitoring Inception Report resulting from the inception visit to the site. This is provided for in the Terms of Reference for the External Panel. The External Panel is engaged to assist the operator and the lenders with monitoring, reporting and advising on three aspects of the Tangguh E&S Project over the next three years. The lenders for the project include the ADB Tranche, Commercial Tranche and Japanese Tranche lenders. The operator is the Tangguh Project. The aspects to be reported on over the three year period are:» Environment, and Health and Safety;» Involuntary Resettlement; and» Indigenous Peoples and Integrated Social Programme. This report presents the findings of the first compliance monitoring of the project undertaken by the External Panel that took place in March 2007, and covers the three main aspects of the project (above) in the current construction phase of the project. The Tangguh LNG Project is located on the south side of Bintuni Bay, Teluk Bintuni Regency, Papua Barat Province (formerly part of Papua), Indonesia. The project will extract natural gas from large offshore reservoirs and pipe it to a LNG plant for conversion to LNG after which the LNG will be exported by tanker to markets in Asia and beyond. Construction commenced in 2005 and is due for completion in 2009, with production expected to commence in The project has an anticipated operational life of over 25 years. The activities associated with the development of the Tangguh LNG Project commenced in 2002/03 by starting to develop resettlement area of Tanah Merah Baru. The Tangguh LNG Project is taking place in a remote part of Indonesia with limited economic and land use development. The location has a physically challenging equatorial climate with high rainfall, and notable disease vectors (e.g. malaria). There are broad conservation and bio diversity values, and important environmental protection issues. The social and political context is complex and dynamic, with a range of governance, welfare and security issues. The LNG construction site itself, is challenging. 1

9 2. The Objectives of the External Panel The overall objectives and functions of the External Panel, as stated in the Terms of Reference (August 2006), are as follows: 1. To satisfy the ADB Tranche Lender's and JBIC's policy requirements for independent external monitoring and evaluation of environmental and social aspects of the Tangguh E&S Project; 2. To verify the internal monitoring undertaken by the Operator; 3. To report regularly to the Lenders and the Operator on environmental and social compliance issues that arise in connection with the Tangguh E&S Project, having regard to the following: 3.1 The environmental and social provisions contained in the PSC Parties Agreements; 3.2 The Environmental and Social Documents (as construed in accordance with each PSC Parties Agreement); and 3.3 The applicable environmental and social policies and safeguard requirements of the ADB Tranche Lender and JBIC (see Appendix 1 for the applicable policies as at the date of this document); 4. To review and comment (for the benefit of the Lenders and the Operator) on reports delivered by the Operator for the purposes of: 4.1 Paragraph (B) of Section 1.12 (Certain Environmental, Involuntary Resettlement and Indigenous Peoples Matters) of the PSC Parties Agreement ADB Tranche; 4.2 Paragraph (a) or (b) of Section 1.12 (Environmental Reports) of the PSC Parties Agreement Commercial Tranche; or 4.3 Paragraph (B) of Section 1.18 (Certain Environmental, Involuntary Resettlement and Indigenous Peoples Matters) of the PSC Parties Agreement Japanese Tranche; 5. To review and comment (for the benefit of the Lenders and the Operator) on Corrective Action Plans prepared by the Operator as required under the environmental and social provisions contained in the PSC Parties Agreements; and 6. To report to and advise the Operator and the Lenders on an ad hoc basis in relation to environmental and social issues that arise in connection with the Tangguh E&S Project. 2

10 3. External Monitoring Scope of Work This section presents the scope of work as specified in the External Panel Terms of Reference (August 2006), the scope of work for each of the three External Panel teams, and the schedule of work undertaken during the inception visit. 3.1 Scope of Work Specified in the TOR Environment Having regard to the RKL and RPL reports submitted to the Indonesian authorities during the relevant audit period and the environmental provisions contained in the PSC Parties Agreements, review and verify environmental compliance of the Tangguh E&S Project (including the performance of activities conducted under the Construction Documents) over the relevant audit period with the mitigation measures and related monitoring requirements prescribed in the AMDAL Documents, as well as additional mitigation measures and monitoring requirements that the Tangguh E&S Project has agreed with the Lenders to carry out; and Recommend measures or activities to be taken by the Tangguh E&S Project to improve its environmental compliance, with particular focus on Level 2 E&S Non Compliance. In addition to conducting the foregoing annual environmental compliance monitoring, the environmental team may be asked from time to time to report to or advise the Operator and the Lenders on specific environmental or health and safety issues that may arise in connection with the Tangguh E&S Project Involuntary Resettlement Resettlement external monitoring is required to assess the progress in implementing the Operator s Land Acquisition and Resettlement Action Plan (LARAP) dated 4 July 2006 that is scheduled to be completed in This includes verifying the internal monitoring undertaken by the Operator; reporting on social compliance in light of ADB and JBIC Policies on Involuntary Resettlement (IR); and reviewing reports delivered by the Operator on IR. Specifically, the IR specialist is required to: a) Review compliance of IR implementation with the LARAP and lenders IR policies; b) Review the effectiveness of measures to restore or enhance AP s quality of life and livelihood; and c) Undertake a completion audit in The LARAP focuses upon several affected groups: communities of Tanah Merah and host Saengga and Onar. 3

11 3.1.3 Indigenous Peoples and the Integrated Social Programs The key function of the IPSI Team is to verify that the implementation of the ISP by the Tangguh E&S Project adheres to the applicable indigenous peoples policies of the ADB Tranche Lender and JBIC. 3.2 Detailed Scope of Work Scope for Environment (Ecology, Waste Management, and Safety & Health) The Environment Team addressed the diverse environmental aspects of the project, including general condition of the regional and local environment, its vulnerabilities and the apparent degree of environmental risk and adverse impact. This is in addition to the specified environmental elements in various management plans, and as directed by all existing and relevant statutory compliance requirements. Additionally, the team addressed the Safety and Health activities, processes and systems associated with the project and as required under the HSE operational policies of the Operator and contractors. The AMDAL is the main reference for Environment Team (especially waste management compliance requirements). Mitigation and management of impacts have been provided for in comprehensive AMDAL documents, and especially the RKL report. The implementation of waste and other environmental management plans has been carried out continuously and monitored. The Operator has put considerable effort into implementing the AMDAL requirements particularly for waste management. General environmental management implementation can be confirmed from key reports accessed by the External Panel as references during the compliance monitoring process. These include:» AMDAL documentation;» MoE AMDAL audit reports;» TIAP reports;» Due diligent audit report, ERM Nov 2005;» Six monthly RKL RPL implementation report;» Environmental, Health and Safety Report Tangguh LNG Project, Indonesia, (Reporting Period: April October 2006);» Tangguh LNG Project: Monitoring Plan (STP monitoring, RO brine water, seawater quality, ambient air, emission monitoring); and» Tangguh LNG Project: Management Plan (environmental management, land conservation, waste management). The AMDAL (and its RKL RPL) were cross referenced to other AMDAL implementation reports and previous auditing report. In conducting its work the environment team focussed on the following aspects:» Solid waste management (collection/transportation and treatment: landfill, incinerator);» Liquid waste (sewage treatment plants);» Air emission (especially from incinerator and general ambient air monitoring); 4

12 » Diesel usage and power generation facilities;» Brine water discharge from desalination plant. Facilities observed during the first compliance monitoring include:» Landfill facilities for non hazardous waste;» Central waste accumulation area;» Incinerator for non hazardous waste;» Composting and organic waste dryer equipment;» Solid waste transportation system;» Incinerator for hazardous waste;» Hazardous waste storage facilities;» Combo docs, drilling mud processing facilities;» Brine water discharge;» Food waste landfill (organic waste pit);» Fowex (food remains processing equipment);» Sewage treatment plant (STP camp stage 3 (Zone B and C); and» Sludge filter press in STP Scope for Involuntary Resettlement The TOR requirements for the IR Specialist are set out below and compared with the scope of work as conducted by the External Panel.» Review of the Operator s semi annual progress reports The External Panel reviewed the first such semi annual progress report (April to October 2006)» Review of the Project s IR resettlement management system, resources and record keeping The External Panel reviewed the staffing chart, monthly reports and grievance records; and interviewed key resettlement staff, including the (outgoing) Vice President of Tangguh ISP and her (outgoing) Deputy VP, the (newly appointed) Senior Manager of Tangguh ISP, the Field Manager of Tangguh ISP, and the two LARAP Supervisors, who are both based at Tanah Merah village.» Review of progress with delivery of outstanding entitlements and compensation The External Panel discussed several outstanding issues with ISP staff, including the Dimaga Foundation, agathis tree compensation, completion and handover of village infrastructure, facilities and utilities. The External Panel discussed the path to sago stands at Manggosa, with ISP staff and with the Kampung Head of Tanah Merah Baru. 5

13 » Review of issues arising from rehabilitated housing in host villages The External Panel reviewed records and discussed this issue with ISP staff, but site visits were too limited for detailed assessment in Saengga and Onar Lama.» Review of progress towards sustainable operation of replacement infrastructure and services The External Panel discussed the functioning of facilities and the handover plan with ISP staff and the head of Tanah Merah Baru, and, in general terms, with the head of the Cooperatives of Tanah Merah Baru and Onar Baru. The Panel reviewed the Operator s Handover Plan Activities.» Review of progress against LARAP schedule and disbursements against budgets The External Panel reviewed progress against the LARAP implementation schedule (Table 1.4). The first six monthly report anticipates that the budget update will be included in the second six monthly report for the period November 2006 April If full year budget data are provided, this will constitute a good basis for a review of disbursements.» Assessment of extent to which households have been able to achieve access to replacement forest, garden and coastal resources The field visits focused on this issue in interviews with leaders and villagers in Tanah Merah Baru, Onar Lama and Onar Baru.» Review of progress towards effectiveness of livelihood restoration programs The field visits focused on this issue in interviews with leaders and villagers in Tanah Merah Baru, Onar Lama and Onar Baru. The Panel also reviewed reports of the Independent Advisory Panel on Resettlement.» Review of community engagement and information dissemination activities conducted in the review period and of their effectiveness The External Panel assessed community awareness and understanding of Project activities during the field visits; and discussed these activities with the LARAP supervisor. The External Panel noted earlier reports of the Independent Advisory Panel on Resettlement that found informed community participation and ownership in the relocation process to be a world class performance 1.» Review of grievance records and Project responses to ensure timely and effective closeout; and current complaints The External Panel attended a presentation by the ISP Grievance Officer on grievance; reviewed several sample records from Saengga and Onar Baru, together with the Project responses; and reviewed a Project booklet entitled Handling Community Grievances (March 2006). 1 See, for example, page 13 and Appendix page 1 of the Independent Advisory Panel on Resettlement, 2004, First Field Report on Population Displacement and Resettlement in the BP Tangguh Project, by Professor Michael Cernea and Dr. Ayse Kudat, March 31; and pages 5 and 6 of the Second Field Report, November

14 » Assessment of any external risks to resettlement program The External Panel reviewed past Project reports, the risk analysis in the Operator s sixmonthly IR report, and, through field level discussions, built up a composite picture of risks during field visits. The External Panel reviewed this picture against the LARAP analysis of impoverishment risks and livelihood restoration strategies (Chapters 6 and 9).» Recommend compliance issues or other measures that might improve the execution of the resettlement program Recommendations are presented in Section 4 of the report.» Conduct a close out presentation of findings to the project management team The External Panel presented an overview of findings and recommendations to the Operator s Project management team on 29 March in Jakarta.» Prepare semi annual reports summarizing findings and recommendations arising from reviews and tracking of close out of recommendations from previous reviews This is the first semi annual report of the External Panel on IR, which sets out a number of issues to be tracked during the next review.» Respond to ad hoc requests on IR matters. No such requests have been received to date Scope of Work of the Indigenous Peoples and Social Issues Team The objectives of the Indigenous Peoples and Social Issues (IPSI) Team are to review compliance with the ISP, IPDF and Lenders respective indigenous peoples policies; review performance in the implementation of the Integrated Social Program (ISP) components, excluding the LARAP component, and undertake a mid term review. The key function of the IPSI team is to verify that the implementation of the ISP adheres to the applicable indigenous peoples policies of the ADB Tranche Lender and JBIC. Within the ISP are 14 components that are to be implemented in fulfilling the requirements of Lenders policies. One of these components is the Land Acquisition and Resettlement Action Plan (LARAP) that is specifically monitored by the Involuntary Resettlement specialist member of the External Panel. The other 13 components to be reviewed by the IPSI team are:» Governance and revenue management;» Civil society strengthening;» Bird s Head business empowerment;» Mitigation of in migration and adverse induced impacts;» Workforce and industrial affairs;» Governance;» Integrated community based security;» Basic education;» Vocational training;» Health; 7

15 » Women s empowerment;» Micro finance and micro enterprise;» Community action plans. The policy elements that are fulfilled by the approved ISP document are described in Paragraph 58 Part VII (B) of the ADB Policy on Indigenous Peoples as follows. For development interventions it supports or assists, the Bank will ensure that affected populations and persons are at least as well off as they would have been in the absence of the intervention, or that adequate and appropriate compensation be provided. Policy should ensure quality of opportunity for indigenous peoples, and that ADB Bank interventions affecting indigenous peoples are: 1. Consistent with the needs and aspirations of affected indigenous peoples; 2. Compatible in substance and structure with affected indigenous peoples culture and social and economic institutions; 3. Conceived, planned and implemented with the informed participation of affected communities; 4. Equitable in terms of development efforts and impacts; and 5. Not imposing the negative effects of development on indigenous peoples without appropriate and acceptable compensation. The key elements of an ISP as stated in Paragraph 38, Part VII of the ADB s Policy on Indigenous Peoples are: 1. Preparation, during project design, of a development plan that takes into full account the desires and preferred options of indigenous peoples affected by the project; 2. Studies to identify potential adverse effects on indigenous peoples to be induced by the project, and to identify measures to avoid, mitigate, or compensate for these adverse effects; 3. Measures to ensure the capacity or the strengthening of the social, legal, and technical skills of government institutions to be responsible under the project for dealing with indigenous peoples; 4. Involvement of appropriate existing institutions, local organizations, and non government organizations with expertise in matters relating to indigenous peoples; 5. Consideration in project design of local patterns of social organization, cultural belief, and ancestral territory and resource use; 6. Support for viable and sustainable production systems that are adapted to the needs and local environments and circumstances of indigenous peoples; 7. Avoidance of creating or aggravating the dependency of indigenous peoples on project entities, and instead promoting self reliance among these peoples; 8. Capacity building for indigenous peoples communities and organizations to facilitate and support effective participation in development processes; and 8

16 9. Adequate lead time and arrangements for extending follow up, especially in dealing with indigenous peoples in remote or neglected areas where little previous experience is available. Consultation with indigenous peoples groups is key to developing an effective, accurate, responsive indigenous peoples development plan. The geographic extent of the ISP covers four vertically integrated geographical areas that are impacted by the project and which in turn influence one another s development. These include Irian Jaya Barat province, the Bird s Head area (including the regional centres of Sorong, Manokwari, and Fakfak), Teluk Bintuni Regency and nine Directly Affected Villages (DAV). Of these villages, three (Tanah Merah Baru, Onar Baru and Saengga) form a sub set of Resettlement Affected Villages (RAV). The 13 ISP components to be reviewed include elements of organisational capacity building as well as community development and participation. While there is the potential to focus on one or the other allowed in the scope of services, in this first visit, the IPSI Team reviewed the ISP components without focus on either capacity building or community development and participation in order to obtain an overview of all component activities, their implementation and the relationship between organisations and community development and participation. 3.3 Schedule of Work Conducted The External Panel team assembled in Jakarta on the 20 th and 21 st of March, The compliance monitoring commenced on 21 st March with a briefing by representatives of the Lenders and the Operator. For the next two to three days External Panel team members were free to review all relevant documentation associated with the project, to put questions to the Operator and the Lenders consultant. The External Panel Environment Team undertook fieldwork from Friday 23 rd March to Sunday 25 th March, returning to Jakarta on Monday 26 th March. A Close Out meeting for the fieldwork was given on Sunday 25 th March. While in the field the Environment Team visited all areas of the LNG plant, and was able to fly over the offshore gas production facilities (Decks and Castoro 8 VRB Deck and Jacket Location, exploration/production well sites, shipping areas and navigation channels, etc), and transects over the marine environment of Bintuni Bay, islands, and forest/terrestrial ecosystems. The External Panel Resettlement Team and Indigenous Peoples and Social Issues Team left for site on Friday 23 rd March travelling overnight, and undertook fieldwork from Saturday 24 th March to Tuesday 27 th March, returning to Jakarta on Wednesday 28 th March. The External Panel Resettlement Team visited Tanah Merah Baru, Onar Baru and, briefly, Onar Lama. The team was unable to visit Saengga as originally scheduled due to loss of two fieldwork days due to bad weather and logistical issues. The time at Onar Baru and Onar Lama was curtailed by tidal constraints. The External Panel IPSI Team visited the regency town of Bintuni and the DAV villages of Tomu, Ekam, Tomage and Otawary meeting with ISP staff and their village representatives, implementing partners, government and customary law officials, health workers, teachers, community leaders and ordinary villagers that included both indigenous people and migrants. 9

17 The team visited the Tangguh funded government vocational training centre (BLK) at Aranday, a Tangguh funded centre for fibreglass water tank construction, two village primary schools, a village health centre, a village malaria control project and witnessed some of the many projects funded by ISP Community Action Plan (CAP) grants. Between 21 st and 30 th March, the ISP team attended presentations from all key ISP program staff and partners USAID and UNDP that are working in areas of revenue management and civil society strengthening at both provincial and regency levels. While the Team visited and observed many village level ISP activities, poor weather meant they were unable to visit the DAV communities of Wiriagar and Mogotira scheduled for 26 th March. While at site, each team operated independently during the day, and came together in the evenings at the Babo base camp. On return to Jakarta, the collective External Panel made a Close Out presentation to the Operator on Thursday 29 th March. The various External Panel team members then undertook analysis of their findings and report writing through to departure on Wednesday 4 th April. The External Panel received full assistance from the Operator, Contractors and Sub contractors, and stakeholders in carrying out its task. Members of the community with whom the resettlement team and the indigenous and social issues team engaged also assisted the External Panel at all times. 10

18 4. Findings This section provides the principal findings of each sub team of the External Panel. The External Panel presents its advice mainly as findings, but has chosen to include some recommendations for the Land Acquisition and Resettlement Plan (LARAP) section. This is principally because the LARAP program is due to be completed in 2009 and the Resettlement team concludes that early advice in recommendation form is appropriate. In summary the External Panel finds the environmental and social compliance performance of the Tangguh E&S Project to be satisfactory overall. However, the External Panel identifies five apparent Level 1 Non Compliance issues. All are reversible. These include three for Involuntary Resettlement, one for Environment, and one for the Integrated Social Programs. 4.1 Environment The section presents the findings of the Environment team under the separate sub headings of:» Ecology;» Waste management; and» Safety and health. Ecology includes consideration of the overall construction site environment (offshore gas production facilities location and onshore LNG plant in total) as well as the external environment to construction areas (inclusive of areas within the controlled LNG Plant Fence, within the Property Boundary, and external to all of these). Waste management includes focus on the immediate construction sites (terrestrial and marine) and associated facilities, inclusive of the near shore marine environment and surrounding terrestrial environment in so far as these function as receiving environments and might be impacted upon by waste emissions (solid, liquid, particulate, and airborne emissions including noise). Safety and health focuses on all operating environments where workforce and human activity occurs, including the LNG site, offshore gas production locations, accommodation and all transport connections to and from these various sites to Babo and out of the project area Ecology The following are the observations and findings associated with the broader environmental setting of the Tangguh LNG Project. Adjacent Terrestrial Environment: The adjacent terrestrial environment includes all vegetated areas adjacent to site works, and further a field, including land areas:» Within the fenced security perimeter (LNG Fence);» Within the Property Boundary; and 11

19 » External to the Property Boundary. Site reconnaissance both on the ground and from the air (low level aerial transect by helicopter) reveals that the vegetated environment in the vicinity of the LNG Plant site is largely intact with no signs of adverse impact resulting from the Tangguh LNG project. Aerial reconnaissance reveals that the areas of Swamp Forest, Lowland Forest and Beach Forest within the LNG Plant security fence appear to be in superior condition to that outside. Visible signs of human activity in the external environment appear to cease at the perimeter fence corridor. The general state of vegetation cover appears to be in good condition within this perimeter. This is an observation only. No supporting data or survey work was obtained to validate this. In the immediate proximity of all cleared and developed sites and current construction sites associated with the LNG Plant, the immediate fringing zone and adjacent forest habitat similarly appears largely unaffected. Protection of specific terrestrial fauna and flora from workforce activities is verified as effective. Immediate action is taken against any individual found deliberately taking or harming wildlife, and the Operator staff confirmed such action in one rare incident. Emissions (dust, particulates, noise, etc) impact upon the adjacent environment appears negligible. The dilution and assimilative capacity of the terrestrial receiving environment should far exceed existing and anticipated emission levels during the construction phase. No solid waste (i.e. general rubbish) was observed to be entering the surrounding environment. The External Panel notes the total area so far cleared for the project is significantly less than that planned, owing to the a reduction in planned facilities (e.g. airstrip/landing site). Adjacent Marine Environment: The marine environment of Berau Bay and Bintuni Bay is a very dynamic and physically robust environment with significant tidal variation and strong tidal currents. Given the water depths, channel expanse and volume of in flowing rivers the External Panel concludes that this marine environment is sufficiently resilient to accommodate approved levels of construction and physical disturbance arising from the Tangguh LNG project. The External Panel notes that stringent control and monitoring of all activities in the marine environment (dredging, construction, drilling, etc) is conducted and that no adverse impacts have been identified. The External Panel notes that the Operator has various management provisions in place to protect marine fauna species, particularly dolphins known to frequent the marine environment to the west of Berau Bay. The latter includes repositioning the navigational channel for major shipping associated with the project. Other marine fauna will readily avoid disturbance and in the case of turtles, sometimes a major concern for such projects, it is noted that there are no likely or known nesting sites (requiring suitable sand beaches) in the vicinity of the project. According to the Operator, the Marine Mammals and Marine Reptile Survey confirms there is no turtle nesting at or near Tangguh site, the nearest being found in the Kokas/Pisang area more than 80 km away from the project site. The survey did not confirm the presence of whales in the vicinity of the project, the nearest sightings being at the mouth of bay far from the project site. Protection of fringing mangrove communities has been achieved through specific design and construction methods adopted for the Tangguh LNG project. This includes horizontal directional 12

20 drilling for major pipe work (from the gas fields) through the coastal fringe. It is also noted that less than the allowable area of mangrove clearance has in fact occurred. The Tangguh LNG Project is required to meet stringent requirements with respect to the disposal of various liquid wastes into the near shore marine environment. These include brine from the Reverse Osmosis Plant (ROP), treated effluent from the Sewerage Treatment Plant (STP), and some proportion of overall surface drainage. It is noted that the dilution and dispersion capacity of the Berau Bay and Bintuni Bay marine environment is high. The External Panel saw no evidence to suggest long term impacts or decline in the quality of the marine environment as a result of current construction activities, coastal engineering works, or shipping/vessel movements Site Environmental Management Surface Drainage, Slope Stabilization, Erosion Control and Top Soil Management The Tangguh LNG Plant site presents significant difficulties for construction activity, arising from very high rainfall, high surface run off, and large areas of exposed ground surface. Taking these factors into account, the External Panel concludes the management of these aspects to be effective. Slope stabilization practices were observed and it was noted that many shoulder areas and sloping ground resulting from cut and fill site earthworks were already well stabilised with vegetated ground cover, often in association with terrain fabric. Approximately 46 ha of the site are now stabilized. The External Panel understands that corrective actions have been taken to re seed and install additional surface runoff interception structures (e.g. vertical drainage) where erosion has persisted. It is also noted that a final Revegetation Plan is now completed. Surface drainage appears effective with sediment basins and discharge structures into the surrounding environment are in place throughout. High levels of surface runoff have a significant sediment load that is largely well contained. Step 1 Area: Materials Handling Jetty The existing fuel barge and fuel loading wharf are in poor condition. While a new and much improved refuelling installation is under construction the External Panel notes that it is important all facilities be appropriately maintained until decommissioned Waste Management This section provides the compliance monitoring results for waste management aspects in the Tangguh LNG Project. Generally, it was observed that overall waste management is consistent with the AMDAL requirements. The Operator has followed up the majority of recommendations from the latest environmental audit (AMDAL audit) carried out by MoE. While the audit report was provided to the Operator in early January 2007, the Operator has prepared and implemented many corrective actions with significant improvement by March Many aspects of waste management have been reviewed and improved. These include: 13

21 » Intensive campaign/dissemination of waste segregation and improvement of waste transfer mode;» Review of incinerators and their maintenance to improve burning performance with the result of significant gas emission reduction; and» Review of wastewater plants and their maintenance to improve treatment performance. The External Panel notes two matters requiring attention. These concern the management of the organic waste pit and the operation of sewage treatment plants. The ANDAL states that solid waste will be disposed to landfill or incinerator (5 71) and all solid waste management will fulfil applicable regulations in Indonesia (5 88). The ANDAL also states that solid waste disposal should not have significant impact on flora and fauna as all non hazardous waste unable to be recycled or incinerated will be suitably disposed of in a sanitary landfill site (6 66). The RKL also confirms the plan to establish a sanitary landfill site (2 36). The Panel is unable to confirm the existence of a sanitary landfill site from the site inspection. An organic waste pit was inspected and found to be substandard and a potential source of pollution and health issues. The second issue concerns the operation of sewage treatment plan (STP) facility. It is apparent from six monthly RKL and RPL implementation reports that this facility has reached a critical operating level with the effluent from several STPs tending to fluctuate around required standards. This indicates overload conditions and reduced efficiency is being experienced. Evaluation of STP performance has been carried out and follow up action to improve maintenance has been taken. However, monitoring data still indicate the overload conditions for STP Step 3 Zone C. Findings for specific waste management aspects are as follows. Solid Waste Management Management of solid waste generated during the construction stage activities from all sites and supporting facilities, including solid waste from worker base camp and canteen facilities or from construction sites, is comprehensively addressed by the Operator in various documentation. One waste management program is outlined in the report Waste Management Program for Tangguh prepared by PT Prasmanindo Boga Utama (confirmed by the Operator s Environment Team Leader and KJP Environment Manager). Similarly a waste management plan has been prepared by KJP (document number 900 PLA HS 1067, rev 5A, March 2005). Solid Waste Segregation The Operator carries out waste segregation in the CWAA. This was confirmed from site observation and the waste records. From the AMDAL Compliance Tracking, it is confirmed the Operator has followed up the MoE audit recommendations to improve segregation by an active program to raise awareness. Continued improvement is anticipated. Total Solid Waste Capacity The comment is confined to the food remains component of organic solid waste, although it is noted that other sources do exist on site. Currently, organic solid waste is disposed direct to the organic waste pit while a composting option is still on trial. Observing the composting facilities (Fowex, dryer, and mixing) raises issues concerning the current capacity of these processing facilities. A review of organic waste treatment 14

22 capacity and its treatment options in a longer term plan would be advisable and could improve current practices. Waste Transportation Waste transportation is carried out by contractors and sub contractor under supervision by the main contractor, KJP. The External Panel found that all solid waste transportation is well directed to the centralised waste treatment facilities. Documentation was reviewed that indicates corrective actions taken to improve solid waste transportation, for example by covering solid waste in vehicles to avoid spill. There is no significant issue in terms of waste collection/transportation to the final designation area. Recyclable solid wastes are collected in a specific area called Central Waste Accumulation Area (CWAA). Clear signs are in place but improvements to this collecting area could be made by installing better fencing. Landfill Landfill cover various solid waste disposal areas including inert landfill, used drilling mud (water based mud from HDD for the pipeline), and organic waste landfill. KJP s waste management plan refers to the RKL document that specifically states: The landfills are to be a double lined (clay and synthetic membrane liners or two synthetic membrane liners) with leachate collection system. The landfill will have six groundwater monitoring wells. However, implementation of these requirements could not be confirmed during the site visit. Inert Landfill The External Panel was unable to view siting and design documentation for the inert landfill site (design study and soil testing), and notes that leachate collection structures were not apparent. The landfill site visited (known as KJP landfill) has been used to dispose inert/inorganic waste, and both non combustible and non degradable wastes are understood to be buried in this inert landfill. KJP s SOP (41 06/0) specifies the type of waste allowed in this landfill. The External Panel observed that filling of the landfill site is not very systematic with disposal apparently carried out from the front of landfill, whereas the normal approach is to fill from the back. KJP s SOP does not specify the filling and covering sequences. Addressing this would help maintain effective landfill operations. Drilling Mud (water based) Landfill This landfill site will be used to dispose used water based drilling mud from the Horizontal Direct Drilling (HDD) operation which is located near the shore area at the time of the site visit. The landfill will not be used for disposing of the mud from well drilling because a DCRI technique will be used. Similar to the inert landfill, siting for used drilling mud is also necessary if landfill method is to be used. Staff on site indicated the mud is mainly bentonite (i.e. not categorised as hazardous waste). The Operator confirms that the drilling mud has been tested and test result and other record related to the mud management has been documented. The used mud landfill is situated adjacent to the inert landfill and is still under preparation. Site observation did not allow confirmation on the design of the landfill. 15

Comparison of HSESAP Revisions 2 and 3

Comparison of HSESAP Revisions 2 and 3 The structure of HSESAP Revision 3 is considerably modified from Revision 2. The following summary is provided to identify the comparative location of key information and any changes following the revision

More information

CHAPTER 24: ENVIRONMENTAL MANAGEMENT

CHAPTER 24: ENVIRONMENTAL MANAGEMENT Central Eyre Iron Project Environmental Impact Statement CHAPTER 24: ENVIRONMENTAL MANAGEMENT CHAPTER 24 ENVIRONMENTAL MANAGEMENT COPYRIGHT Copyright Iron Road Limited, 2015 All rights reserved This document

More information

LIQUID WASTE TREATMENT FACILITY MENDIS ROAD, HUDSON CREEK DRAFT GUIDELINES FOR A PUBLIC ENVIRONMENTAL REPORT

LIQUID WASTE TREATMENT FACILITY MENDIS ROAD, HUDSON CREEK DRAFT GUIDELINES FOR A PUBLIC ENVIRONMENTAL REPORT LIQUID WASTE TREATMENT FACILITY MENDIS ROAD, HUDSON CREEK DRAFT GUIDELINES FOR A PUBLIC ENVIRONMENTAL REPORT Introduction The purpose of this Public Environmental Report (PER) is to provide the Government

More information

INDONESIA - LAW ON WATER RESOURCES,

INDONESIA - LAW ON WATER RESOURCES, Environment and Development Journal Law LEAD INDONESIA - LAW ON WATER RESOURCES, 2004 VOLUME 2/1 LEAD Journal (Law, Environment and Development Journal) is a peer-reviewed academic publication based in

More information

State of Qatar. Ministry of Environment. Intended Nationally Determined Contributions (INDCs) Report. November 19 th, 2015

State of Qatar. Ministry of Environment. Intended Nationally Determined Contributions (INDCs) Report. November 19 th, 2015 State of Qatar Ministry of Environment Intended Nationally Determined Contributions (INDCs) Report November 19 th, 2015 State of Qatar is pleased to submit its Intended Nationally Determined Contributions

More information

Environmental guidelines for preparation of an Environment Management Plan

Environmental guidelines for preparation of an Environment Management Plan Environmental guidelines for preparation of an Environment Management Plan Environment Protection Authority MAY 2013 Australian Capital Territory, Canberra 2013 This work is copyright. Apart from any use

More information

TANGGUH LNG INTEGRATED SOCIAL PROGRAM (ISP) 2011-2015

TANGGUH LNG INTEGRATED SOCIAL PROGRAM (ISP) 2011-2015 TANGGUH LNG INTEGRATED SOCIAL PROGRAM (ISP) 2011-2015 Achieving Sustainable & Responsible Operation dicetak di atas kertas daur ulang Contents List of Figures...7 List of Tables...9 Acronyms and Indonesian

More information

Proposed Terms of Reference for EIA studies

Proposed Terms of Reference for EIA studies 1 Proposed Terms of Reference for EIA studies Base line data collection will be collected for the Post-Monsoon season 2016 (September to November 2016) in study area and 10 kms radius from project site.

More information

EBRD Performance Requirement 7

EBRD Performance Requirement 7 EBRD Performance Requirement 7 Indigenous Peoples Introduction 1. This Performance Requirement (PR) recognises that projects can create opportunities for Indigenous Peoples to participate in and benefit

More information

ENVIRONMENTAL AND SOCIAL RISK ASSESSMENT IN LENDING

ENVIRONMENTAL AND SOCIAL RISK ASSESSMENT IN LENDING ENVIRONMENTAL AND SOCIAL RISK ASSESSMENT IN LENDING Barclays has a strong and longstanding commitment to managing the environmental and social risks associated with commercial lending. We recognise that

More information

APPENDIX 4. Risk Tables

APPENDIX 4. Risk Tables APPENDIX 4 Tables Preliminary Qualitative Criteria The qualitative risk assessment criteria have been developed to identify key risks to the environment, society, heritage and business reputation. The

More information

TERMS OF REFERENCE FOR SCOPING OF EIA STUDY

TERMS OF REFERENCE FOR SCOPING OF EIA STUDY TERMS OF REFERENCE FOR SCOPING OF EIA STUDY Ours project is a proposed large scale unit and categorized as 5(h)-B as per the EIA notification 2006 of MoEFCC, New Delhi and subsequent amendments. Looking

More information

June 2010 HEALTH, SAFETY, AND ENVIRONMENT MANAGEMENT SYSTEM (HSEMS)

June 2010 HEALTH, SAFETY, AND ENVIRONMENT MANAGEMENT SYSTEM (HSEMS) June 2010 HEALTH, SAFETY, AND ENVIRONMENT MANAGEMENT SYSTEM (HSEMS) TABLE OF CONTENTS PAGE PART I INTRODUCTION Corporate Health, Safety and Environment Policy.. 1 Purpose... 2 HSEMS Framework... 3 PART

More information

Environmental Guidelines for Preparation of an Environmental Management Plan

Environmental Guidelines for Preparation of an Environmental Management Plan 2013 Environmental Guidelines for Preparation of an Environmental Management Plan Environmental Management Division Environmental Protection Agency 3/13/2013 ENVIRONMENTAL GUIDELINES FOR PREPARATION OF

More information

TERMS OF REFERENCE. BEFORE CONSTRUCTION: Sl No TOR RESPONSE 1. Legalities of the land: Is the land The Project is clear from all angles.

TERMS OF REFERENCE. BEFORE CONSTRUCTION: Sl No TOR RESPONSE 1. Legalities of the land: Is the land The Project is clear from all angles. TERMS OF REFERENCE Name of the Project: M/s Suadela Constructions Pvt. Ltd. Address: Sy.No. 321/2B(P),321/2C(P),322/1,323/1(P),323/1(P),323/3,323/4,323/5(P), 323/6,323/7,325/1(P),325/2,327,328/1,328/2(P),328/3,328/4,330,331,332/2

More information

Proposal for a RECOMMENDATION OF THE EUROPEAN COMMISSION

Proposal for a RECOMMENDATION OF THE EUROPEAN COMMISSION EUROPEAN COMMISSION Brussels, XXX [ ] (2013) XXX draft Proposal for a RECOMMENDATION OF THE EUROPEAN COMMISSION Providing minimum principles for the exploration and production of hydrocarbons (especially

More information

2x800 MW Thermal Power Project Near Village Paraspani, Tehsil Pathargama, Godda- District By Adani Power (Jharkhand) Limited

2x800 MW Thermal Power Project Near Village Paraspani, Tehsil Pathargama, Godda- District By Adani Power (Jharkhand) Limited (IV) Proposed Terms of Reference for EIA Studies Project Category Project Proponent Location Paraspani Thermal Power Plant (2x800 MW) Coal based Thermal Power Project A [1(d) Thermal Power Plant 500 MW]

More information

APPENDIX 2A. Shah Deniz Production Sharing Agreement Extract

APPENDIX 2A. Shah Deniz Production Sharing Agreement Extract APPENDIX 2A Shah Deniz Production Sharing Agreement Extract Shah Deniz Production Sharing Agreement Extract ARTICLE 26 - Environmental Protection and Safety 26.1 Environmental Standards Contractor shall

More information

Environmental Impact Assessment Ordinance (Cap. 499) Environmental Impact Assessment Report Sludge Treatment Facilities

Environmental Impact Assessment Ordinance (Cap. 499) Environmental Impact Assessment Report Sludge Treatment Facilities 40/F, Revenue Tower, 5 Gloucester Road, Wan Chai, Hong Kong 香 港 灣 仔 告 士 打 道 5 號 稅 務 大 樓 40 樓 ACE-EIA Paper 2/2009 For advice Environmental Impact Assessment Ordinance (Cap. 499) Environmental Impact Assessment

More information

Native Vegetation Council. Strategic Plan 2014-16

Native Vegetation Council. Strategic Plan 2014-16 Native Vegetation Council Strategic Plan 2014-16 Foreword From the Presiding Member The Native Vegetation Council (NVC) is established under the Native Vegetation Act 1991, and exists to further the objects

More information

Construction CONSTRUCTION

Construction CONSTRUCTION 135 R. English CONSTRUCTION Construction GOOD PRACTICE POINTERS Identify stakeholders most likely to be affected by construction. Notify local stakeholders of construction activities and changes to schedules.

More information

GENERAL SPECIFICATION

GENERAL SPECIFICATION R64 - PAVEMENT MARKING August 1996 GENERAL SPECIFICATION G10 CONSTRUCTION ENVIRONMENTAL MANAGEMENT PLAN Date JUNE 2012 Department 1 DOT Spec R64 of Infrastructure, Energy and Resources Index DEPARTMENT

More information

Birmingham City University / Students Union Aspects and Impacts Register. Waste. Impacts description

Birmingham City University / Students Union Aspects and Impacts Register. Waste. Impacts description Birmingham City University / Students Union and Impacts Register Waste Production of non - hazardous waste Production of hazardous waste Storage of non - hazardous waste Potential for waste to be disposed

More information

MBJ Environmental Programmes

MBJ Environmental Programmes MBJ Airports Limited Environmental Policy The following is MBJ Airports Limited s (MBJ) Environmental Policy for Sangster International Airport (SIA): Integrate environmental management measures with planning,

More information

8.0 ENVIRONMENTAL PROTECTION MONITORING AND FOLLOW-UP

8.0 ENVIRONMENTAL PROTECTION MONITORING AND FOLLOW-UP 8.0 ENVIRONMENTAL PROTECTION MONITORING AND FOLLOW-UP 8.1 INTRODUCTION Mitigation measures, monitoring and other follow-up actions identified in Chapter 7 (Environmental Effects Assessment and Mitigation)

More information

Sec. 22a-1a page 1 (4-97)

Sec. 22a-1a page 1 (4-97) Department of Environmental Protection Sec. 22a-1a page 1 (4-97) TABLE OF CONTENTS Connecticut Environmental Policy Act Definitions... 22a-1a- 1 Determination of sponsoring agency.... 22a-1a- 2 Determination

More information

This is a summarised version of 3i s full policy. Responsible Investment policy APRIL 2014

This is a summarised version of 3i s full policy. Responsible Investment policy APRIL 2014 This is a summarised version of 3i s full policy Responsible Investment policy APRIL 2014 Our policy 3i will use its influence as an investor to promote a commitment in our investee companies to: Comply,

More information

Semi Annual Environmental Monitoring Report. July 2013 L2557/2558. SRI: Greater Colombo Wastewater Management Project

Semi Annual Environmental Monitoring Report. July 2013 L2557/2558. SRI: Greater Colombo Wastewater Management Project Semi Annual Environmental Monitoring Report July 2013 L2557/2558 SRI: Greater Colombo Wastewater Management Project This environmental monitoring report is a document of the borrower. The views expressed

More information

Madagascar: Makira REDD+

Madagascar: Makira REDD+ project focus Madagascar: Makira REDD+ Madagascar is considered to be one of the top five biodiversity hotspots in the world due to more than 75% of all animal and plant species being endemic while less

More information

Devonport EfW CHP Facility. CEMP Proposal for Non Destructive Testing Activities. 1. Introduction

Devonport EfW CHP Facility. CEMP Proposal for Non Destructive Testing Activities. 1. Introduction Devonport EfW CHP Facility CEMP Proposal for Non Destructive Testing Activities. 1. Introduction This application is issued in compliance with the principles of the approved Construction Environmental

More information

SECTOR ASSESSMENT (SUMMARY): CLIMATE CHANGE. 1. Sector Performance, Problems, and Opportunities

SECTOR ASSESSMENT (SUMMARY): CLIMATE CHANGE. 1. Sector Performance, Problems, and Opportunities Climate Resilience Sector Project (RRP TON 46351) Sector Road Map SECTOR ASSESSMENT (SUMMARY): CLIMATE CHANGE 1. Sector Performance, Problems, and Opportunities 1. Tonga is being affected by climate change,

More information

This document must be read in conjunction with the Permit to Work and Service Interruption Notice policy.

This document must be read in conjunction with the Permit to Work and Service Interruption Notice policy. UNIVERSITY OF HERTFORDSHIRE HIGHER EDUCATION CORPORATION SITE RULES FOR CONTRACTORS The University s Site Rules for Contractors are issued on the authority of the Director of Estates, Hospitality and Contract

More information

Urban Environmental Management in Singapore. Jothieswaran P Chief Engineer Pollution Control Department National Environment Agency

Urban Environmental Management in Singapore. Jothieswaran P Chief Engineer Pollution Control Department National Environment Agency Urban Environmental Management in Singapore Jothieswaran P Chief Engineer Pollution Control Department National Environment Agency Introduction City state comprising a main island and some islets Land

More information

Establishing of the expansive gas supply chain that combines upstream, midstream and downstream operations

Establishing of the expansive gas supply chain that combines upstream, midstream and downstream operations We deliver a reliable supply of natural gas, a source of clean energy, with a strong supply chain that covers all steps from upstream to midstream and downstream operations. We develop gas fields in Japan

More information

Environment Situation in Timor-Leste

Environment Situation in Timor-Leste Environment Situation in Timor-Leste Historically; 1. East-Timor or Timor-Leste, the Portuguese name of the country. 2. It was colonialised by Portuguese 450 years and Occupied by Indonesian 24 years.

More information

Construction Management Statement. Residential development at Bywell House, St Mary s Hill, Ascot

Construction Management Statement. Residential development at Bywell House, St Mary s Hill, Ascot Construction Management Statement Residential development at Bywell House, St Mary s Hill, Ascot Parking of Vehicles of Site Personnel, Operatives and Visitors Site staff, visitors to the development and

More information

How To Conduct An Environmental Impact Assessment

How To Conduct An Environmental Impact Assessment Proposed Terms of Reference for EIA studies 1. Introduction The proposed expansion of Bulk Drugs & Intermediates manufacturing unit by M/s. Sri Krishna Pharmaceuticals Limited (Unit V). is located at Plot

More information

APPENDIX I (See Paragraph -6) FORM I

APPENDIX I (See Paragraph -6) FORM I APPENDIX I (See Paragraph -6) FORM I (I) Basic Information: Sl.. Item Details 1 Name of the project/s Removal of sand from Sand bar SB-G2 2 S.. in the schedule G 3 Proposed capacity / area/length / tonnage

More information

Heritage Place Code. Heritage Place Code

Heritage Place Code. Heritage Place Code 1 Application This Code will apply in assessing building work (including demolition), reconfiguring a lot or operational work where: on a premises that includes a heritage place within a heritage precinct

More information

BUILDING OVER OR NEAR WATER & SEWER MAINS POLICY

BUILDING OVER OR NEAR WATER & SEWER MAINS POLICY MURRAY SHIRE COUNCIL BUILDING OVER OR NEAR WATER & SEWER MAINS POLICY ADOPTED: 1 May 2012 1 BUILDING OVER OR NEAR WATER AND SEWER MAINS POLICY CONTENTS 1. Objective... 2 2. Requirements for Building Near

More information

Legislative Council Panel on Environmental Affairs. 209DS Outlying Islands sewerage, stage 1, phase 1 - consultants fees and investigations

Legislative Council Panel on Environmental Affairs. 209DS Outlying Islands sewerage, stage 1, phase 1 - consultants fees and investigations For discussion On 8 May 2001 Legislative Council Panel on Environmental Affairs 209DS Outlying Islands sewerage, stage 1, phase 1 - consultants fees and investigations Purpose This paper seeks Members

More information

Environmental Incident Response Procedure. Newcastle Gas Storage Facility Document Number: NGSF-PSV-NAS-EN-PLN-0024

Environmental Incident Response Procedure. Newcastle Gas Storage Facility Document Number: NGSF-PSV-NAS-EN-PLN-0024 Environmental Incident Response Procedure Newcastle Gas Storage Facility Document Number: NGSF-PSV-NAS-EN-PLN-0024 Environmental Incident Response Procedure Document Number: NGSF-PSV-NAS-EN-PLN-0024 Version:

More information

Service Level Agreement (SLA)

Service Level Agreement (SLA) Hertford College, Oxford Service Level Agreement (SLA) For Maintenance, Risk Management, and Domestic Accommodation Services At Hertford College, its residential annexes and non- residential properties

More information

Construction Services

Construction Services Construction Services Construction Turning innovative ideas into delivered solutions At Golder Associates we strive to be the most respected global company providing consulting, design, and construction

More information

23.1 RENEWABLE ENERGY

23.1 RENEWABLE ENERGY Proposed Hastings District Plan as Amended 23.1 Renewable Energy 23.1 RENEWABLE ENERGY 23.1.1 INTRODUCTION The use of energy is of fundamental importance to the function and development of our society.

More information

ENVIRONMENTAL AND SOCIAL TRAINING ACTIVITIES

ENVIRONMENTAL AND SOCIAL TRAINING ACTIVITIES ENVIRONMENTAL AND SOCIAL TRAINING ACTIVITIES 5 A construction worker sits on machinery on the ROW in Azerbaijan Warning sign along the pipeline 5 5 ENVIRONMENTAL AND SOCIAL TRAINING ACTIVITIES 5.1 PROJECT

More information

Pre-Feasibility Study Bhopal Solid Waste Management. May 2015 Executive Summary

Pre-Feasibility Study Bhopal Solid Waste Management. May 2015 Executive Summary Pre-Feasibility Study Bhopal Solid Waste Management May 2015 Executive Summary Cities Development Initiative for Asia P a g e 2 A. Rationale i. The Project 1. Bhopal is the capital and second largest city

More information

Performance Standard 8:

Performance Standard 8: Overview of Performance Standards on Environmental and Social Sustainability 1. IFC s Sustainability Framework articulates the Corporation s strategic commitment to sustainable development, and is an integral

More information

THE NATURAL RESOURCES AND ENVIRONMENT ORDINANCE (CAP. 84 - LAWS OF SARAWAK, 1958 Ed.)

THE NATURAL RESOURCES AND ENVIRONMENT ORDINANCE (CAP. 84 - LAWS OF SARAWAK, 1958 Ed.) THE NATURAL RESOURCES AND ENVIRONMENT ORDINANCE (CAP. 84 - LAWS OF SARAWAK, 1958 Ed.) THE NATURAL RESOURCES AND ENVIRONMENT (PRESCRIBED ACTIVITIES) ORDER, 1994 (Made under section 11A(1)) (Incorporating

More information

SCHEDULE 2 TO THE DEVELOPMENT PLAN OVERLAY Shown on the planning scheme map as DPO2 WAVERLEY GOLF COURSE, LYSTERFIELD VALLEY

SCHEDULE 2 TO THE DEVELOPMENT PLAN OVERLAY Shown on the planning scheme map as DPO2 WAVERLEY GOLF COURSE, LYSTERFIELD VALLEY SCHEDULE 2 TO THE DEVELOPMENT PLAN OVERLAY Shown on the planning scheme map as DPO2 WAVERLEY GOLF COURSE, LYSTERFIELD VALLEY 1.0 Conditions and requirements for permits A permit to use and develop the

More information

Liquid Effluent Treatment Plant (LETP) Land Clean-Up

Liquid Effluent Treatment Plant (LETP) Land Clean-Up Liquid Effluent Treatment Plant (LETP) Land Clean-Up Frequently Asked Questions What is proposed? Magnox Ltd is proposing to remove the redundant Liquid Effluent Treatment Plant (LETP) at Harwell and to

More information

NEWMONT GHANA GOLD LTD. AHAFO SOUTH PROJECT COMPLETION AUDIT TERMS OF REFERENCE ENVIRONMENTAL, HEALTH, AND SAFETY

NEWMONT GHANA GOLD LTD. AHAFO SOUTH PROJECT COMPLETION AUDIT TERMS OF REFERENCE ENVIRONMENTAL, HEALTH, AND SAFETY NEWMONT GHANA GOLD LTD. AHAFO SOUTH PROJECT COMPLETION AUDIT TERMS OF REFERENCE ENVIRONMENTAL, HEALTH, AND SAFETY November 2009 Completion Audit November 2009 Terms of Reference Environmental, Health and

More information

COASTAL APPLICATION FOR A MAJOR SITING PERMIT

COASTAL APPLICATION FOR A MAJOR SITING PERMIT Frank M. Rabauliman Administrator Commonwealth of the Northern Mariana Islands OFFICE OF THE GOVERNOR Bureau of Environmental and Coastal Quality Division of Coastal Resources Management Gualo Rai Center

More information

TOWNSVILLE WATER Customer Service Standards

TOWNSVILLE WATER Customer Service Standards TOWNSVILLE WATER Customer Service Standards CONTENTS Townsville Water who are we? 3 What is the Customer Service Standard? 3 >> Does the Customer Service Standard apply to me? 3 >> What will Townsville

More information

ASEAN GREEN HOTEL STANDARD

ASEAN GREEN HOTEL STANDARD FINAL ASEAN GREEN HOTEL STANDARD Presented to the Thirty-Fifth Meeting of the ASEAN National Tourism Organization (35 th ASEAN NTOs) 8-9 January 2012 Manado, Indonesia INDEX PAGE 1. Foreword... 1 2. Introduction...

More information

MLD: Domestic Maritime Transport Project

MLD: Domestic Maritime Transport Project Environmental Monitoring Report Project Number: 37265 December 2010 MLD: Prepared by Japan Port Consultants Co., Ltd. Malé, Maldives For Ministry of Finance and Treasury Ministry of Transport and Communication

More information

1. What is a biodiversity offset?

1. What is a biodiversity offset? How can BBOP help companies? This document is intended for developers who are considering undertaking a biodiversity offset and may welcome help from the Business and Biodiversity Offsets Programme (BBOP).

More information

Proposed General Plan Update Goals, Policies, and Implementation Actions

Proposed General Plan Update Goals, Policies, and Implementation Actions Proposed General Plan Update Goals, Policies, and Implementation Actions The construction and maintenance of infrastructure is necessary to support existing and planned land uses and to achieve Environmental

More information

AGENCY SUMMARY NARRATIVE

AGENCY SUMMARY NARRATIVE AGENCY SUMMARY Mission Statement and Statutory Authority DEQ s mission is to be a leader in restoring, maintaining and enhancing the quality of Oregon s air, water and land. The Department of Environmental

More information

CONSERVATION AREAS ACT

CONSERVATION AREAS ACT CONSERVATION AREAS ACT CAP. 30.15 Conservation Areas Act CAP. 30.15 Arrangement of Sections CONSERVATION AREAS ACT Arrangement of Sections Section 1 Short title... 5 2 Interpretation... 5 3 Declaration

More information

Key things to Know About Environment as a. Cross Cutting Issue In Early Recovery

Key things to Know About Environment as a. Cross Cutting Issue In Early Recovery Key things to Know About Environment as a Cross Cutting Issue In Early Recovery This brief note provides an overview of key things to know about environment for early recovery actors, including Early Recovery

More information

Finance, Mining & Sustainability. The Gamsberg Zinc Project South Africa

Finance, Mining & Sustainability. The Gamsberg Zinc Project South Africa Finance, Mining & Sustainability The Gamsberg Zinc Project South Africa Project Summary Discovered in 1971 Anglo American purchased 33% interest in 1974 and increased interest to 100% in 1998 Feasibility

More information

1. Name of the Project 2. Necessity and Relevance of JBIC s Assistance

1. Name of the Project 2. Necessity and Relevance of JBIC s Assistance Ex-ante Evaluation 1. Name of the Project Country: India Project: Goa Water Supply and Sewerage Project (Loan Agreement: 09/14/2007; Loan Amount: 22,806 million yen; Borrower: The President of India )

More information

3. Given the geographic extent of the area, amendments have been made to the following regional planning documents

3. Given the geographic extent of the area, amendments have been made to the following regional planning documents AMENDMENTS TO THE REGIONAL PLANS RELATING TO LAND REPAIR ON EARTHQUAKE DAMAGED RESIDENTIAL LAND UNDER s27 OF THE CANTERBURY EARTHQUAKE RECOVERY ACT 2011 1. This memorandum outlines the specific changes

More information

SITE-SPECIFIC BEST MANAGEMENT PRACTICES (SSBMP) PLAN/STORM WATER POLLUTION PREVENTION PLAN (SWPPP) REVIEW CHECKLIST

SITE-SPECIFIC BEST MANAGEMENT PRACTICES (SSBMP) PLAN/STORM WATER POLLUTION PREVENTION PLAN (SWPPP) REVIEW CHECKLIST This checklist may be used by applicants for encroachment permits, and contractors in development of Site Specific Best Management Practice (SSBMP) Plans or Storm Water Pollution Prevention Plans (SWPPP)

More information

Extraction Oil and Gas, LLC. Diamond Valley Central Oil Terminal Waste Management Plan

Extraction Oil and Gas, LLC. Diamond Valley Central Oil Terminal Waste Management Plan Extraction Oil and Gas, LLC. Diamond Valley Central Oil Terminal Waste Management Plan Scope: This Extraction Oil and Gas Waste Management Plan has been prepared to provide operations personnel at the

More information

Triton Knoll Offshore Wind Farm Limited Electrical System. Outline Traffic Management Plan

Triton Knoll Offshore Wind Farm Limited Electrical System. Outline Traffic Management Plan Triton Knoll Offshore Wind Farm Limited Electrical System Outline Traffic Management Plan October 2014 RWE Innogy UK Triton Knoll TMP Copyright 2014 RWE Innogy UK Ltd All pre-existing rights reserved.

More information

Table of International Standards Related to Human Rights at the Marlin Mine

Table of International Standards Related to Human Rights at the Marlin Mine APPENDIX E Table of International Standards Related to Human Rights at the Marlin Mine Consultation International Human Right Instruments International Good Practice Standards and Guidance GRI (G3 & MMSS)

More information

Guide to agrichemical use in Resource Management Plans Northland Region as at October 2011

Guide to agrichemical use in Resource Management Plans Northland Region as at October 2011 Guide to agrichemical use in Resource Management Plans Northland Region as at October 2011 Northland Regional Air Quality Plan Note: This guide is intended to assist users and applicators understanding

More information

Health, Safety and Environment Management System

Health, Safety and Environment Management System Health, Safety and Environment Management System For Bridgeport Energy Ltd Level 7, 111 Pacific Highway North Sydney 2011 June, 2010 DOCUMENT CONTROL Title: Document Number: Health, Safety and Environmental

More information

./01&2/M./T34 1MP36T ST3T.M./T. 1a$t3l$4 536e-al4 13$7363 83%3te9. Sol9ara 1 Pro;ect. !"l$%e ( Mai$ &e(ort. Te-t. )e*te%,e- 2//0 :; <//0=>=?

./01&2/M./T34 1MP36T ST3T.M./T. 1a$t3l$4 536e-al4 13$7363 83%3te9. Sol9ara 1 Pro;ect. !l$%e ( Mai$ &e(ort. Te-t. )e*te%,e- 2//0 :; <//0=>=? ./01&2/M./T34 1MP36T ST3T.M./T 1a$t3l$4 536e-al4 13$7363 83%3te9 Sol9ara 1 Pro;ect!"l$%e ( Mai$ &e(ort Te-t )e*te%,e- 2//0 :; =?@ ENVIRONMENTAL IMPACT STATEMENT VOLUME A: MAIN REPORT TEXT CR 7008_09_v4

More information

ENVIRONMENTAL & SOCIAL IMPACT ASSESSMENT (ESIA) FOR PRINOS OFFSHORE DEVELOPMENT PROJECT ANNEX 15: TRAFFIC MANAGEMENT PLAN

ENVIRONMENTAL & SOCIAL IMPACT ASSESSMENT (ESIA) FOR PRINOS OFFSHORE DEVELOPMENT PROJECT ANNEX 15: TRAFFIC MANAGEMENT PLAN : Pioneer in integrated consulting services March 2016 PRINOS OFFSHORE DEVELOPMENT PROJECT THIS PAGE IS LEFT INTENTIONALLY BLANK Page ii Environmental Consultant: LDK Engineering Consultants SA Date: 04/03/2016

More information

Civil Engineering Sector Labour-Management Health and Safety Committee

Civil Engineering Sector Labour-Management Health and Safety Committee PROCEDURE FOR THE STORAGE AND HANDLING OF FUEL ON CONSTRUCTION SITES Civil Engineering Sector Labour-Management Health and Safety Committee July 2008 PROCEDURE FOR THE STORAGE AND HANDLING OF FUEL ON CONSTRUCTION

More information

NAPCS Product List for NAICS 54162: Environmental Consulting Services

NAPCS Product List for NAICS 54162: Environmental Consulting Services NAPCS List for NAICS : Environmental Consulting Services National 1 Environmental consulting Providing objective information, advice, and guidance to clients concerning the preservation of air, water,

More information

National Planning Policy for Waste

National Planning Policy for Waste National Planning Policy for Waste October 2014 Department for Communities and Local Government Crown copyright, 2014 Copyright in the typographical arrangement rests with the Crown. You may re-use this

More information

Sediment and Dredged Material Management - Relevance and Objectives 18 September 2003

Sediment and Dredged Material Management - Relevance and Objectives 18 September 2003 - Relevance and Objectives 1. Scope of the Dutch German Exchange (DGE) The Netherlands and Germany have large river systems such as Danube, Rhine, Meuse, Elbe, Weser and Ems, which have important hydrological

More information

NAPA COUNTY WATERSHED SYMPOSIUM

NAPA COUNTY WATERSHED SYMPOSIUM Planning, Building, and Environmental Services NAPA VALLEY GROWTH NAPA COUNTY WATERSHED SYMPOSIUM Plunging Forward May 15, 2015 1 YOU CAN T CROSS THE SEA MERELY BY STANDING AND STARING AT THE WATER. Rabindranath

More information

Climate Change and Sri Lanka. Ajith Silva Director/ Policy and Planning Ministry of Environment and Natural Resources Sri Lanka

Climate Change and Sri Lanka. Ajith Silva Director/ Policy and Planning Ministry of Environment and Natural Resources Sri Lanka Climate Change and Sri Lanka Ajith Silva Director/ Policy and Planning Ministry of Environment and Natural Resources Sri Lanka Asia Total Area: 65610 Km Land Area : 62705 Km Inland water : 2905 Km 2 Coastal

More information

5. Environmental Analysis

5. Environmental Analysis 5.11 The potential for adverse impacts on utilities and service systems was evaluated based on information concerning current service levels and the ability of the service providers to accommodate the

More information

Rural Development Strategy Network Utilities: Issues and Options

Rural Development Strategy Network Utilities: Issues and Options Rural Development Strategy Network Utilities: Issues and Options Prepared by Carine Andries, Policy Planner Table of contents 1 Introduction... 3 2 Policy Framework... 3 2.1 National Level Policy... 3

More information

Environmental Law Enforcement in Zimbabwe. Farai Michael Nyahwa

Environmental Law Enforcement in Zimbabwe. Farai Michael Nyahwa Environmental Law Enforcement in Zimbabwe By Farai Michael Nyahwa Presentation Breakdown Institutional Arrangement for Environmental Law Enforcement in Zimbabwe Major Environmental Issues of Concern In

More information

Kingfisher Global Reporting Initiative Index

Kingfisher Global Reporting Initiative Index Kingfisher Global Reporting Initiative Index Our report contains some standard disclosures from the Global Reporting Initiative Sustainability Reporting Guidelines. This Index is intended to aid comparison

More information

13 ENVIRONMENTAL AND SOCIAL MANAGEMENT SYSTEM

13 ENVIRONMENTAL AND SOCIAL MANAGEMENT SYSTEM 13 ENVIRONMENTAL AND SOCIAL MANAGEMENT SYSTEM This ESIA has identified impacts (both positive and negative) to the physical, natural and socio-economic environments, as well as to community and worker

More information

CALDER PARK PROJECT STAGE 1. EPBC Act Approval Compliance Report (EPBC 2012/6439)

CALDER PARK PROJECT STAGE 1. EPBC Act Approval Compliance Report (EPBC 2012/6439) CALDER PARK PROJECT STAGE 1 EPBC Act Approval Compliance Report (EPBC 2012/6439) Prepared for: METRO TRAINS MELBOURNE Level 28, 80 Collins Street, Melbourne, VIC 3000 Prepared by: Kellogg Brown & Root

More information

Northern Territory Fisheries Resource Sharing Framework

Northern Territory Fisheries Resource Sharing Framework Northern Territory Fisheries Resource Sharing Framework Page 1 of 11 Introduction Fishing is important in the Northern Territory (Territory). Coastal Aboriginal people recognise sea country out to the

More information

Module No. # 02. Impact of oil and gas industry on marine environment

Module No. # 02. Impact of oil and gas industry on marine environment Health, Safety and Environmental Management in Petroleum and offshore Engineering Dr. Srinivasan Chandrasekaran Department of Ocean Engineering Indian Institute of Technology, Madras Module No. # 02 Lecture

More information

APPENDIX I. (See Paragraph-6) FORM 1

APPENDIX I. (See Paragraph-6) FORM 1 APPENDIX I (See Paragraph-6) FORM 1 (I) Basic Information S.. Item Details 1. Name of the Project/s Dankari Granite Black Stone Quarry 2. Sl. in the schedule Sairat case no- 91/ 12-13 3. Proposed capacity

More information

Grievance Management Guidance Note

Grievance Management Guidance Note May 2012 1 Grievance Management Guidance Note 1 EBRD S REQUIREMENTS 1.1 PERFORMANCE REQUIREMENT (PR) 10 INFORMATION DISCLOSURE AND STAKEHOLDER ENGAGEMENT Key Bank requirements relating to grievance management

More information

Environmental Policy 2014-2016

Environmental Policy 2014-2016 Environmental Policy 2014-2016 Our responsibility to the environment is a sustainable commitment inscribed in AREVA's Value Charter. The deep involvement of AREVA sites in improving environmental risk

More information

CHAPTER 372-68 WAC WATER POLLUTION CONTROL AND ABATEMENT PLANS FOR SEWAGE DRAINAGE BASINS

CHAPTER 372-68 WAC WATER POLLUTION CONTROL AND ABATEMENT PLANS FOR SEWAGE DRAINAGE BASINS CHAPTER 372-68 WAC WATER POLLUTION CONTROL AND ABATEMENT PLANS FOR SEWAGE DRAINAGE BASINS Last Update: 6/8/88 WAC 372-68-010 Authority. 372-68-020 Purpose. 372-68-030 Definitions. 372-68-040 Planning guide.

More information

Exploration for natural gas

Exploration for natural gas FACT SHEET NO. 42 Exploration for natural gas Quick facts QGC holds licences from the Queensland Government called Authorities to Prospect that allow us to explore in areas known as tenements We work with

More information

First Cargo from Indonesia s Tangguh LNG Project

First Cargo from Indonesia s Tangguh LNG Project 6 July, 2009 First Cargo from Indonesia s Tangguh LNG Project Mitsubishi Corporation, INPEX CORPORATION, Nippon Oil Corporation, MITSUI & CO., LTD., LNG JAPAN CORPORATION, Sumitomo Corporation, Sojitz

More information

Department of the Environment and Local Government. Project Management. Public Private Partnership Guidance Note 7. 14 April 2000

Department of the Environment and Local Government. Project Management. Public Private Partnership Guidance Note 7. 14 April 2000 Project Management Project Management Public Private Partnership Guidance Note 7 14 April 2000 Guidance Note 7 14 April 2000 Project Management Contents Section Page I INTRODUCTION...1 SCOPE AND PURPOSE

More information

Contents 1 Editorial Policy 2 Overview of Honda 3 Message from the President and CEO 4 Special Feature 5 Sustainability Management

Contents 1 Editorial Policy 2 Overview of Honda 3 Message from the President and CEO 4 Special Feature 5 Sustainability Management Performance Report 1 Environment 2 Safety 3 Quality 4 Human Resources 5 Social Activity Supply Chain 7 8 Assurance 9 Financial Data General Standard Disclosures 7 Strategy and Analysis Organizational Profile

More information

SHE Standards. Safety, Health and Environmental Protection Standards

SHE Standards. Safety, Health and Environmental Protection Standards SHE Standards Safety, Health and Environmental Protection Standards Revision 2.01 December 2010, Valid from December 01, 2010 2 Contents SHE Standards Contents Foreword 3 1 Management Process 1.1 Policy,

More information

APPLICATION PROCESS FOR LAND DISTURBING PERMIT

APPLICATION PROCESS FOR LAND DISTURBING PERMIT PREFACE: APPLICATION PROCESS FOR LAND DISTURBING PERMIT The property owner, developer and designated planners and engineers shall review the general development plans and detailed plans of the Local Issuing

More information

Permitting of Development and Infrastructure Projects in Abu Dhabi

Permitting of Development and Infrastructure Projects in Abu Dhabi Table of Contents 1.0 Purpose... 4 1.1 What Is a Objection Certificate for Development and Infrastructure Projects?... 4 1.2 Why Is an NOC Required?... 4 2.0 Scope... 4 2.1 What Development and Infrastructure

More information

Environmental Assessment

Environmental Assessment OP 4.01 Page 1 of 5 Environmental Assessment Note: OP 4.01 replaces the policy elements of IFC s Environmental Analysis and Review of International Finance Corporation Projects (Washington, D.C.: IFC,

More information

CHAGUARAMAS TERMINALS LTD.

CHAGUARAMAS TERMINALS LTD. POLICY MANUAL All rights reserved to CrewsInn Limited. No part of this document may be reproduced in any form or by any means, without permission in writing from the company CHAGUARAMAS TERMINALS LTD.

More information

Land Disturbance, Erosion Control and Stormwater Management Checklist. Walworth County Land Conservation Department

Land Disturbance, Erosion Control and Stormwater Management Checklist. Walworth County Land Conservation Department Land Disturbance, Erosion Control and Stormwater Management Checklist Walworth County Land Conservation Department The following checklist is designed to assist the applicant in complying with the Walworth

More information