2 Speaker: John Peterson Time: April 4, 2014, 9:45-10:45 a.m. Venue: Crystal 1-2 Data Center Design and Commissioning

3 High enterprise relevancy for addressing space, power, and cooling, as well as costs and skills for environments Large and enterprise-scale data center growth of 11% and 7% respectively, Data Center Trends Critical facilities design Design alterations based on density improvements In 2016, the same floor space will be able to house 22% more equipment than in 2011 More efficient data center design through modularity adoption Critical facilities strategy Optimized Critical facilities implementation According to the 2012 Uptime Institute survey, 80% of respondents have built a new data center or upgraded an existing facility within the past five years, and 30% of respondents ran out of data center capacity at one of their sites in An alarming inaccuracy for data center operators managing the thermal conditions at the room level, not the rack inlet level Available Between more than 11,000 new data centers will be constructed globally When building a new data center, around half of the respondents are interested in pursuing some kind of green certification, with the leading option being the U.S. Green Building Council s LEED program Critical facilities energy Critical facilities assurance A poorly designed data center may reduce IT and business agility Periodic refurbishment costs to upgrade and replace aging equipment, such as chillers and battery systems, driving TCO decisions

4 Forward-thinking companies have realized that to run data centers efficiently, and to extend their lives indefinitely, it is not logical to treat data center facilities and IT assets separately, because without one the other can t operate. David J. Cappuccino, Gartner, Inc. August 2011 Copyright 2012 Hewlett-Packard Development Company, L.P. The information contained herein is subject to change without notice.

5 Aiming for the data center of the future Modular and elastic Shared resource pools Right sourcing Policy-based Fully automated Green Business-centric Integrated Real-time monitoring & control Fully service-oriented Efficient and effective Mature standardized processes Fully available and resilient Self-regulating

6 IT to Facilities: Why can t facilities fix my air problem?

7 Facilities to IT: Why don t you just do this?

8 How inefficiency can cost business Business impact related to cooling issues Server or system downtime Increased operational costs Data center outage Inability to add capacity Fail to support business growth Loss of revenue Lowered customer satisfaction

9 The data center lifecycle IT failure rates and facility longevity

10 CFD Analysis

11 Energy Audit & Optimization Report Recirculation-Impact of Blanking Panels

12 Outside Air Economizer & Humidity

13 Power To IT House power Misc. power IT power In Mech. power Main power PUE (Power Usage Effectiveness) CUE (Carbon Usage Effectiveness);WUE (Water Usage Effectiveness) ERE(Energy Reuse Effectiveness); ERF(Energy Reuse Factor) Fuel Emergency generator Utility transforme r Total data center energy House energy Total Direct Water Consumption CO 2 NO x CUE WUE Main service Total data center energy House panels District steam District chilled water Natural gas Fuel PP-Gen service Generato r block Heaters & lighting Data center Lighting panel Lighting, Exit lights, BMS, EPMS & security Misc. support PUE = UPS STS PDUs RPPs IT-critical load Mech. support Mech. Swgear Data center CRAC units, AHUs, Chillers & Dry coolers Total data center energy from all fuels (kwh) Total IT energy (kwh) ERF ERE April 2014

14 Cooling and Power Systems Affect PUE Two system design concepts compared Max PUE = 1.63 Average PUE = 1.56 Annual Energy = 49 million kwh Difference is 5 million kwh ($500,000 at $0.10/kWH) Facilities Max PUE = 1.45 Average PUE = 1.41 Annual Energy = 44 million kwh April 2014

15 Indoor Temperature and Moisture Levels ASHRAE recommendations at computer equipment air intakes MAXIMUM 80 F dry-bulb 67 F wet-bulb 60 F dew point MINIMUM 65 F dry-bulb 53 F wet-bulb 43 F dew point 15

16 Climate Zone Optimization

17 HVAC-CRAH data & measurements

18 HVAC System Power Measurements

19 Air Management measurements & analysis

20 Air Management measurements & analysis

21 COOLIN G SYSTEMS CRAC FANS HUM / DEHUM FUEL OTHER MECH IT UPS LOSSES GEN PRE- HEATER LIGHTS OTHER ELEC kw Energy Audit & Optimization Report CRAC/CRAH fan power optimization Data Centre Average Power Consumption Too many CRAHs/Turn CRACs off! Controlled on return air! Low air temp & %RH set points! Controls fighting! Common issues Fixed speed fans, no VFDs! Old fan motors with low efficiency! Dual filters!

22 Energy Audit & Optimization Report Identification of overcooling & hot spots <59F 59-68F 68-77F 77-90F F >104F Overcooling Hot Spots < >40

23 Energy Audit & Optimization Report Optimizing Air Management Recirculation: results in hot spots and wastes fan energy Consider return air plenum and ductwork for the CRAC units Remove obstructions under the floor that restrict cold air to supply the server inlets Ensure as best as possible the adequate supply of cold air to the server inlets Ensure air velocities and flows from floor grilles are sufficient to reach the top of cabinet servers Fit blanking plates in cabinets where servers are not installed Close gaps between cabinets (where warm air can make its way to the server inlet) Avoid installing highly loaded servers at the end of cabinet row or at the top where recirculation is easier Consider means to physically isolate the supply (cold) and return (hot) air streams Return air Recirculated air (if servers need more air than supplied) Server CRAC Supply air

24 Energy Audit & Optimization Report Optimizing Air Management Bypass: Starves servers from air and wastes fan energy Locate floor air grills so that they supply the inlet of servers, i.e. remove floor air grills from hot aisles and other useless areas Return air Ensure air velocities from floor grilles are not too high and overshoot the cabinet height Seal air gaps in the raised floor CRAC units turned off are a source of air bypass (consider air isolation with dampers) Server Bypass Floor tiles and racks badly located/o riented CRAC High exit velocity

25 Energy Audit & Optimization Report Optimizing Air Management Negative flow: Venturi flow Return air Negative flow if high underfloor air velocity Server CRAC

26 Energy Audit & Optimization Report Air Management Metrics-Practical Applications OPPORTUNITY BP Legacy D C, particularly if not well managed, tend to have high levels of both bypass and recirculation flow rates. Cold aisle hot aisle arrangements can address the main problems of recirculation. However, particularly at low loads, there will be high levels of bypass air, unless the CRAC units have some type of variable air-flow control.

27 CRAC 1 CRAC 2 Energy Audit & Optimization Report Perforated Tiles Locations Poor location and unnecessary

28 DRY BULB TEMPERATURE - F Implementing ASHRAE conditions ASHRAE recommended & allowable ranges R ASHRAE PSYCHROMETRIC CHART NO.1 NORMAL TEMPERATURE BAROMETRIC PRESSURE: INCHES OF MERCURY Copyright 1992 AMERICAN SOCIETY OF HEATING, REFRIGERATING AND AIR-CONDITIONING ENGINEERS, INC. 794 FEET R WET BULB TEMPERATURE - F Weather Data Location: SAN_ANTONIO, TEXAS, USA 55 90% 60 Weather Hours 11 to 1 22 to to to to to to to to Class A % Class A2 70% 60% 50% 40% 30% 20% 55 Recommended Class A1 10% RELATIVE HUMIDITY Class A4 28

29 Implementing ASHRAE conditions ASHRAE recommended & allowable ranges 29

30 Case study: HVAC system upgrades & Air Side Econ. The Client The Implemented Solution Networking provider IT/Communication industry 5,000 SF raised floor Perceived UTI Tier 3 Data Center San Francisco bay area SAT reset control from 61 to 74 F Hot/cold aisle rack layout, over head cooling. High eff 483 Ton WCC (CH-1), NPLV VFD PCHWP-1- premium efficiency motor. VFD CWP-1-premium efficiency motor. VFD CT-1- premium efficiency motor. VFD WC CRAH-17 to CAH-24-prem eff motor ASE motorized damper intake hoods, VFD, premium efficiency motors. The Metrics Annual energy Savings 1,658,922 kwh Demand reduction 111 kw Carbon reduction 498 Metric Tons PUE improvement 10% The Financials Annual energy cost savings $165,892 Total incentives-pg&e $232, SPB 4.4 years NPV +28k IRR 12%

31 Case study-air management via hot aisle containment The Client The Implemented Solution National Company Communication industry 10,000 SF raised floor Perceived UTI-Tier 2 Data Center San Francisco bay area The Metrics Annual energy Savings 525,600 kwh Demand reduction 58 kw Annual Carbon reduction 158 Metric Tons PUE improvement 4% The Financials Annual energy cost savings $57,816 Total incentives-pg&e $46,216 SPB 3.8 years NPV +35k IRR 16%

32 Thank you Copyright 2012 Hewlett-Packard Development Company, L.P. The information contained herein is subject to change without notice.

33 Speaker: Raja Natarajan Time: April 4, 2014, 9:45-10:45 a.m. Venue: Crystal 1-2 Data Center Design and Commissioning

34 The Commissioning Process

35 The Process Define Owners Project Requirements Building Due Diligence Identify Performance Outcomes Lessons Learned Review Clients Brief Draft Commissioning Plan

36 The Process Commissionability & Maintainability Single Points of Failure Elimination 1:10:100 Potential Cost Savings Avoid Blind Value Engineering Thought for the Facility Manager

37 The Process Clear & Concise Tender Instructions Give the contractor a fighting chance Avoid unnecessary variations Identify on and offsite requirements

38 The Process Built for Commissioning Early Installation Fault Identification Logical Integration into Construction Schedule Clear identification of approved processes Off-Site Factory Tests

39 The Process Task Tracking and Verification All tasks identified and tracked Proactive support not bullying Aim to minimize repeat testing Witness verification

40 Testing of Major Equipment Mechanical Chillers, CRAC Units Electrical UPS, STS, Generators Fire Protection Systems Gaseous suppression systems, Pre-action Systems BMS & Controls

41 The Process Provide absolute confidence Demonstrate of performance and integration Fire and Life Safety Secure Power and Cooling Documented Audit Trail Trained to Operate

42 Heat Load Tests (HLT) To demonstrate the performance of the cooling system using a substitute load to simulate actual conditions To monitor/record the effects of simulated failures and changeover of system operation on the cooling system All testing of individual equipment to be complete prior to HLT

43

44

45

46 Integrated Systems Tests (IST) Failure conditions are simulated to ensure systems react in a manner to which they are designed Used to verify the correct integrated operation of the Data Center in various cause and effect modes of failure

47 Tests conducted during IST Electrical Simulate failure of Main Utility Power and demostrate operation of generator Simulate failure of generator power and demonstrate battery operation of UPS system Simulate failure of UPS System and demonstrate operation of STS System

48 Tests conducted during IST Mechanical Simulate failure of Chiller / Chillers and demonstrate capability of chiller control system Simulate failure of CRAC units and demonstrate capability of CRAC control system Carry out simulation of fire alarms and effect on data center

49 The Process Adjust to Suit Observe use Tune to suit Educate to avoid override

50 The Process Continuous Commissioning Defect Resolution Seasonal Adjustment Fit for purpose Transitional Commissioning

51 Commissioning Management Process Copyright: BSRIA

52 Energy Efficiency of Data Centers Due to technological advances, demand for data center space throughout the developed world will remain high. Amount of electricity consumed will be exceptionally high due to the high power demands of data centers It is important to monitor and improve the energy efficiencies of the data centers

53 Recent Government Developments Early appointment of Commissioning Agent to discuss and agree strategies to optimize energy efficiencies within data center Proper sealing of the data center environment Optimizing air flow Increasing cooling system efficiencies System of monitoring and tracking of energy efficiency parameters

54 Improving Energy Efficiency through Commissioning Management Effective commissioning has been shown to improve the operating efficiency and environmental performance of a building over its life cycle. Commissioning is growing in importance due to the growing complexity of buildings Continuous commissioning has been proven to save energy and costs throughout the life of the building

55 Thank You Raja Natarajan Commissioning Manager Commtech Asia Mobile (852) Tel (852) A, W Square, 318 Hennessey Road, Wanchai, Hong Kong

Data Centre Energy Efficiency Operating for Optimisation Robert M Pe / Sept. 20, 2012 National Energy Efficiency Conference Singapore

Data Centre Energy Efficiency Operating for Optimisation Robert M Pe / Sept. 20, 2012 National Energy Efficiency Conference Singapore Data Centre Energy Efficiency Operating for Optimisation Robert M Pe / Sept. 20, 2012 National Energy Efficiency Conference Singapore Introduction Agenda Introduction Overview of Data Centres DC Operational

More information

Energy Efficiency Opportunities in Federal High Performance Computing Data Centers

Energy Efficiency Opportunities in Federal High Performance Computing Data Centers Energy Efficiency Opportunities in Federal High Performance Computing Data Centers Prepared for the U.S. Department of Energy Federal Energy Management Program By Lawrence Berkeley National Laboratory

More information

Dealing with Thermal Issues in Data Center Universal Aisle Containment

Dealing with Thermal Issues in Data Center Universal Aisle Containment Dealing with Thermal Issues in Data Center Universal Aisle Containment Daniele Tordin BICSI RCDD Technical System Engineer - Panduit Europe Daniele.Tordin@Panduit.com AGENDA Business Drivers Challenges

More information

Case Study: Opportunities to Improve Energy Efficiency in Three Federal Data Centers

Case Study: Opportunities to Improve Energy Efficiency in Three Federal Data Centers Case Study: Opportunities to Improve Energy Efficiency in Three Federal Data Centers Prepared for the U.S. Department of Energy s Federal Energy Management Program Prepared By Lawrence Berkeley National

More information

Re Engineering to a "Green" Data Center, with Measurable ROI

Re Engineering to a Green Data Center, with Measurable ROI Re Engineering to a "Green" Data Center, with Measurable ROI Alan Mamane CEO and Founder Agenda Data Center Energy Trends Benchmarking Efficiency Systematic Approach to Improve Energy Efficiency Best Practices

More information

Managing Data Centre Heat Issues

Managing Data Centre Heat Issues Managing Data Centre Heat Issues Victor Banuelos Field Applications Engineer Chatsworth Products, Inc. 2010 Managing Data Centre Heat Issues Thermal trends in the data centre Hot Aisle / Cold Aisle design

More information

Free Cooling in Data Centers. John Speck, RCDD, DCDC JFC Solutions

Free Cooling in Data Centers. John Speck, RCDD, DCDC JFC Solutions Free Cooling in Data Centers John Speck, RCDD, DCDC JFC Solutions Why this topic Many data center projects or retrofits do not have a comprehensive analyses of systems power consumption completed in the

More information

GUIDE TO ICT SERVER ROOM ENERGY EFFICIENCY. Public Sector ICT Special Working Group

GUIDE TO ICT SERVER ROOM ENERGY EFFICIENCY. Public Sector ICT Special Working Group GUIDE TO ICT SERVER ROOM ENERGY EFFICIENCY Public Sector ICT Special Working Group SERVER ROOM ENERGY EFFICIENCY This guide is one of a suite of documents that aims to provide guidance on ICT energy efficiency.

More information

Legacy Data Centres Upgrading the cooling capabilities What are the options?

Legacy Data Centres Upgrading the cooling capabilities What are the options? Legacy Data Centres Upgrading the cooling capabilities What are the options? Presentation Structure What is a Legacy Data Centre? What is CRAC cooling? ASHRAE Standards Overview Available Cooling Systems

More information

Data Center Power Consumption

Data Center Power Consumption Data Center Power Consumption A new look at a growing problem Fact - Data center power density up 10x in the last 10 years 2.1 kw/rack (1992); 14 kw/rack (2007) Racks are not fully populated due to power/cooling

More information

Liquid Cooling Solutions for DATA CENTERS - R.M.IYENGAR BLUESTAR LIMITED.

Liquid Cooling Solutions for DATA CENTERS - R.M.IYENGAR BLUESTAR LIMITED. Liquid Cooling Solutions for DATA CENTERS - R.M.IYENGAR BLUESTAR LIMITED. Presentation Goals & Outline Power Density Where we have been- where we are now - where we are going Limitations of Air Cooling

More information

Environmental Data Center Management and Monitoring

Environmental Data Center Management and Monitoring 2013 Raritan Inc. Table of Contents Introduction Page 3 Sensor Design Considerations Page 3 Temperature and Humidity Sensors Page 4 Airflow Sensor Page 6 Differential Air Pressure Sensor Page 6 Water Sensor

More information

Data Centre Cooling Air Performance Metrics

Data Centre Cooling Air Performance Metrics Data Centre Cooling Air Performance Metrics Sophia Flucker CEng MIMechE Ing Dr Robert Tozer MSc MBA PhD CEng MCIBSE MASHRAE Operational Intelligence Ltd. info@dc-oi.com Abstract Data centre energy consumption

More information

Cooling Capacity Factor (CCF) Reveals Stranded Capacity and Data Center Cost Savings

Cooling Capacity Factor (CCF) Reveals Stranded Capacity and Data Center Cost Savings WHITE PAPER Cooling Capacity Factor (CCF) Reveals Stranded Capacity and Data Center Cost Savings By Kenneth G. Brill, Upsite Technologies, Inc. Lars Strong, P.E., Upsite Technologies, Inc. 505.798.0200

More information

Control of Computer Room Air Handlers Using Wireless Sensors. Energy Efficient Data Center Demonstration Project

Control of Computer Room Air Handlers Using Wireless Sensors. Energy Efficient Data Center Demonstration Project Control of Computer Room Air Handlers Using Wireless Sensors Energy Efficient Data Center Demonstration Project About the Energy Efficient Data Center Demonstration Project The project s goal is to identify

More information

An Introduction to Cold Aisle Containment Systems in the Data Centre

An Introduction to Cold Aisle Containment Systems in the Data Centre An Introduction to Cold Aisle Containment Systems in the Data Centre White Paper October 2010 By Zac Potts MEng Mechanical Engineer Sudlows October 2010 An Introduction to Cold Aisle Containment Systems

More information

Best Practices in HVAC Design/Retrofit

Best Practices in HVAC Design/Retrofit Best Practices in HVAC Design/Retrofit Little Server Room BIG $AVINGS Justin Lewis, P.E., LEED AP, DCEP Sr Energy Project Manager C:530.400.6042 O:530.754.4870 jlewis@ucdavis.edu 1 What s the problem here?

More information

Data Center Cooling & Air Flow Management. Arnold Murphy, CDCEP, CDCAP March 3, 2015

Data Center Cooling & Air Flow Management. Arnold Murphy, CDCEP, CDCAP March 3, 2015 Data Center Cooling & Air Flow Management Arnold Murphy, CDCEP, CDCAP March 3, 2015 Strategic Clean Technology Inc Focus on improving cooling and air flow management to achieve energy cost savings and

More information

Data Center Energy Profiler Questions Checklist

Data Center Energy Profiler Questions Checklist Data Center Energy Profiler Questions Checklist Step 1 Case Name Date Center Company State/Region County Floor Area Data Center Space Floor Area Non Data Center Space Floor Area Data Center Support Space

More information

Specialty Environment Design Mission Critical Facilities

Specialty Environment Design Mission Critical Facilities Brian M. Medina PE Associate Brett M. Griffin PE, LEED AP Vice President Environmental Systems Design, Inc. Mission Critical Facilities Specialty Environment Design Mission Critical Facilities March 25,

More information

DOE FEMP First Thursday Seminar. Learner Guide. Core Competency Areas Addressed in the Training. Energy/Sustainability Managers and Facility Managers

DOE FEMP First Thursday Seminar. Learner Guide. Core Competency Areas Addressed in the Training. Energy/Sustainability Managers and Facility Managers DOE FEMP First Thursday Seminar Achieving Energy Efficient Data Centers with New ASHRAE Thermal Guidelines Learner Guide Core Competency Areas Addressed in the Training Energy/Sustainability Managers and

More information

Improving Data Center Energy Efficiency Through Environmental Optimization

Improving Data Center Energy Efficiency Through Environmental Optimization Improving Data Center Energy Efficiency Through Environmental Optimization How Fine-Tuning Humidity, Airflows, and Temperature Dramatically Cuts Cooling Costs William Seeber Stephen Seeber Mid Atlantic

More information

Cooling Capacity Factor (CCF) Reveals Stranded Capacity and Data Center Cost Savings

Cooling Capacity Factor (CCF) Reveals Stranded Capacity and Data Center Cost Savings WHITE PAPER Cooling Capacity Factor (CCF) Reveals Stranded Capacity and Data Center Cost Savings By Lars Strong, P.E., Upsite Technologies, Inc. Kenneth G. Brill, Upsite Technologies, Inc. 505.798.0200

More information

Heat Recovery from Data Centres Conference Designing Energy Efficient Data Centres

Heat Recovery from Data Centres Conference Designing Energy Efficient Data Centres What factors determine the energy efficiency of a data centre? Where is the energy used? Local Climate Data Hall Temperatures Chiller / DX Energy Condenser / Dry Cooler / Cooling Tower Energy Pump Energy

More information

Element D Services Heating, Ventilating, and Air Conditioning

Element D Services Heating, Ventilating, and Air Conditioning PART 1 - GENERAL 1.01 OVERVIEW A. This section supplements Design Guideline Element D3041 on air handling distribution with specific criteria for projects involving design of a Data Center spaces B. Refer

More information

Green Data Centre Design

Green Data Centre Design Green Data Centre Design A Holistic Approach Stantec Consulting Ltd. Aleks Milojkovic, P.Eng., RCDD, LEED AP Tommy Chiu, EIT, RCDD, LEED AP STANDARDS ENERGY EQUIPMENT MATERIALS EXAMPLES CONCLUSION STANDARDS

More information

Self-benchmarking Guide for Data Center Infrastructure: Metrics, Benchmarks, Actions 6-28-10. Sponsored by:

Self-benchmarking Guide for Data Center Infrastructure: Metrics, Benchmarks, Actions 6-28-10. Sponsored by: Self-benchmarking Guide for Data Center Infrastructure: Metrics, Benchmarks, Actions 6-28-10 Sponsored by: Disclaimer This document was prepared as an account of work sponsored by the United States Government.

More information

The New Data Center Cooling Paradigm The Tiered Approach

The New Data Center Cooling Paradigm The Tiered Approach Product Footprint - Heat Density Trends The New Data Center Cooling Paradigm The Tiered Approach Lennart Ståhl Amdahl, Cisco, Compaq, Cray, Dell, EMC, HP, IBM, Intel, Lucent, Motorola, Nokia, Nortel, Sun,

More information

Data Center Design Guide featuring Water-Side Economizer Solutions. with Dynamic Economizer Cooling

Data Center Design Guide featuring Water-Side Economizer Solutions. with Dynamic Economizer Cooling Data Center Design Guide featuring Water-Side Economizer Solutions with Dynamic Economizer Cooling Presenter: Jason Koo, P.Eng Sr. Field Applications Engineer STULZ Air Technology Systems jkoo@stulz ats.com

More information

IMPROVING DATA CENTER EFFICIENCY AND CAPACITY WITH AISLE CONTAINMENT

IMPROVING DATA CENTER EFFICIENCY AND CAPACITY WITH AISLE CONTAINMENT DATA CENTER RESOURCES WHITE PAPER IMPROVING DATA CENTER EFFICIENCY AND CAPACITY WITH AISLE CONTAINMENT BY: STEVE HAMBRUCH EXECUTIVE SUMMARY Data centers have experienced explosive growth in the last decade.

More information

Measure Server delta- T using AUDIT- BUDDY

Measure Server delta- T using AUDIT- BUDDY Measure Server delta- T using AUDIT- BUDDY The ideal tool to facilitate data driven airflow management Executive Summary : In many of today s data centers, a significant amount of cold air is wasted because

More information

How To Improve Energy Efficiency Through Raising Inlet Temperatures

How To Improve Energy Efficiency Through Raising Inlet Temperatures Data Center Operating Cost Savings Realized by Air Flow Management and Increased Rack Inlet Temperatures William Seeber Stephen Seeber Mid Atlantic Infrared Services, Inc. 5309 Mohican Road Bethesda, MD

More information

Benefits of. Air Flow Management. Data Center

Benefits of. Air Flow Management. Data Center Benefits of Passive Air Flow Management in the Data Center Learning Objectives At the end of this program, participants will be able to: Readily identify if opportunities i where networking equipment

More information

Cooling Audit for Identifying Potential Cooling Problems in Data Centers

Cooling Audit for Identifying Potential Cooling Problems in Data Centers Cooling Audit for Identifying Potential Cooling Problems in Data Centers By Kevin Dunlap White Paper #40 Revision 2 Executive Summary The compaction of information technology equipment and simultaneous

More information

CURBING THE COST OF DATA CENTER COOLING. Charles B. Kensky, PE, LEED AP BD+C, CEA Executive Vice President Bala Consulting Engineers

CURBING THE COST OF DATA CENTER COOLING. Charles B. Kensky, PE, LEED AP BD+C, CEA Executive Vice President Bala Consulting Engineers CURBING THE COST OF DATA CENTER COOLING Charles B. Kensky, PE, LEED AP BD+C, CEA Executive Vice President Bala Consulting Engineers OVERVIEW Compare Cooling Strategies in Free- Standing and In-Building

More information

HPPR Data Center Improvements Projects Towards Energy Efficiency (CFD Analysis, Monitoring, etc.)

HPPR Data Center Improvements Projects Towards Energy Efficiency (CFD Analysis, Monitoring, etc.) HPPR Data Center Improvements Projects Towards Energy Efficiency (CFD Analysis, Monitoring, etc.) Felipe Visbal / March 27, 2013 HPPR Data Center Technologies Team Services Data Centers: Thermal Assessments

More information

Energy and Cost Analysis of Rittal Corporation Liquid Cooled Package

Energy and Cost Analysis of Rittal Corporation Liquid Cooled Package Energy and Cost Analysis of Rittal Corporation Liquid Cooled Package Munther Salim, Ph.D. Yury Lui, PE, CEM, LEED AP eyp mission critical facilities, 200 west adams street, suite 2750, Chicago, il 60606

More information

DataCenter 2020: first results for energy-optimization at existing data centers

DataCenter 2020: first results for energy-optimization at existing data centers DataCenter : first results for energy-optimization at existing data centers July Powered by WHITE PAPER: DataCenter DataCenter : first results for energy-optimization at existing data centers Introduction

More information

Verizon SMARTS Data Center Design Phase 1 Conceptual Study Report Ms. Leah Zabarenko Verizon Business 2606A Carsins Run Road Aberdeen, MD 21001

Verizon SMARTS Data Center Design Phase 1 Conceptual Study Report Ms. Leah Zabarenko Verizon Business 2606A Carsins Run Road Aberdeen, MD 21001 Verizon SMARTS Data Center Design Phase 1 Conceptual Study Report Ms. Leah Zabarenko Verizon Business 2606A Carsins Run Road Aberdeen, MD 21001 Presented by: Liberty Engineering, LLP 1609 Connecticut Avenue

More information

7 Best Practices for Increasing Efficiency, Availability and Capacity. XXXX XXXXXXXX Liebert North America

7 Best Practices for Increasing Efficiency, Availability and Capacity. XXXX XXXXXXXX Liebert North America 7 Best Practices for Increasing Efficiency, Availability and Capacity XXXX XXXXXXXX Liebert North America Emerson Network Power: The global leader in enabling Business-Critical Continuity Automatic Transfer

More information

Managing Cooling Capacity & Redundancy In Data Centers Today

Managing Cooling Capacity & Redundancy In Data Centers Today Managing Cooling Capacity & Redundancy In Data Centers Today About AdaptivCOOL 15+ Years Thermal & Airflow Expertise Global Presence U.S., India, Japan, China Standards & Compliances: ISO 9001:2008 RoHS

More information

How Eight California Data Centers Reduced Energy by 20%

How Eight California Data Centers Reduced Energy by 20% How Eight California Data Centers Reduced Energy by 20% Sponsored by the California Energy Commission Public Interest Energy Research David Weightman, Energy Commission Specialist California Energy Commission

More information

- White Paper - Data Centre Cooling. Best Practice

- White Paper - Data Centre Cooling. Best Practice - White Paper - Data Centre Cooling Best Practice Release 2, April 2008 Contents INTRODUCTION... 3 1. AIR FLOW LEAKAGE... 3 2. PERFORATED TILES: NUMBER AND OPENING FACTOR... 4 3. PERFORATED TILES: WITH

More information

Data Centre Testing and Commissioning

Data Centre Testing and Commissioning Data Centre Testing and Commissioning What is Testing and Commissioning? Commissioning provides a systematic and rigorous set of tests tailored to suit the specific design. It is a process designed to

More information

Datacenter Efficiency Program

Datacenter Efficiency Program Datacenter Efficiency Program Yuming Qiu, CLEAResult Anna Stieve, CLEAResult Michael Stachowiak, CLEAResult Abstract Worldwide, datacenter energy consumption is skyrocketing and datacenter energy efficiency

More information

How To Improve Energy Efficiency In A Data Center

How To Improve Energy Efficiency In A Data Center Google s Green Data Centers: Network POP Case Study Table of Contents Introduction... 2 Best practices: Measuring. performance, optimizing air flow,. and turning up the thermostat... 2...Best Practice

More information

Top 5 Trends in Data Center Energy Efficiency

Top 5 Trends in Data Center Energy Efficiency Top 5 Trends in Data Center Energy Efficiency By Todd Boucher, Principal Leading Edge Design Group 603.632.4507 @ledesigngroup Copyright 2012 Leading Edge Design Group www.ledesigngroup.com 1 In 2007,

More information

Case Study: Innovative Energy Efficiency Approaches in NOAA s Environmental Security Computing Center in Fairmont, West Virginia

Case Study: Innovative Energy Efficiency Approaches in NOAA s Environmental Security Computing Center in Fairmont, West Virginia Case Study: Innovative Energy Efficiency Approaches in NOAA s Environmental Security Computing Center in Fairmont, West Virginia Prepared for the U.S. Department of Energy s Federal Energy Management Program

More information

Combining Cold Aisle Containment with Intelligent Control to Optimize Data Center Cooling Efficiency

Combining Cold Aisle Containment with Intelligent Control to Optimize Data Center Cooling Efficiency A White Paper from the Experts in Business-Critical Continuity TM Combining Cold Aisle Containment with Intelligent Control to Optimize Data Center Cooling Efficiency Executive Summary Energy efficiency

More information

Education Evolution: Scalable Server Rooms George Lantouris Client Relationship Manager (Education) May 2009

Education Evolution: Scalable Server Rooms George Lantouris Client Relationship Manager (Education) May 2009 Education Evolution: Scalable Server Rooms George Lantouris Client Relationship Manager (Education) May 2009 Agenda Overview - Network Critical Physical Infrastructure Cooling issues in the Server Room

More information

Thermal Monitoring Best Practices Benefits gained through proper deployment and utilizing sensors that work with evolving monitoring systems

Thermal Monitoring Best Practices Benefits gained through proper deployment and utilizing sensors that work with evolving monitoring systems NER Data Corporation White Paper Thermal Monitoring Best Practices Benefits gained through proper deployment and utilizing sensors that work with evolving monitoring systems Introduction Data centers are

More information

AIRAH Presentation April 30 th 2014

AIRAH Presentation April 30 th 2014 Data Centre Cooling Strategies The Changing Landscape.. AIRAH Presentation April 30 th 2014 More Connections. More Devices. High Expectations 2 State of the Data Center, Emerson Network Power Redefining

More information

Analysis of data centre cooling energy efficiency

Analysis of data centre cooling energy efficiency Analysis of data centre cooling energy efficiency An analysis of the distribution of energy overheads in the data centre and the relationship between economiser hours and chiller efficiency Liam Newcombe

More information

This 5 days training Course focuses on Best Practice Data Centre Design, Operation and Management leading to BICSI credits.

This 5 days training Course focuses on Best Practice Data Centre Design, Operation and Management leading to BICSI credits. This 5 days training Course focuses on Best Practice Data Centre Design, Operation and Management leading to BICSI credits. DCD, DCOM, DCE DESIGN IMPLEMENTATION BEST PRACTICE OPERATION & MANAGEMENT DATA

More information

Using CFD for optimal thermal management and cooling design in data centers

Using CFD for optimal thermal management and cooling design in data centers www.siemens.com/datacenters Using CFD for optimal thermal management and cooling design in data centers Introduction As the power density of IT equipment within a rack increases and energy costs rise,

More information

AisleLok Modular Containment vs. Legacy Containment: A Comparative CFD Study of IT Inlet Temperatures and Fan Energy Savings

AisleLok Modular Containment vs. Legacy Containment: A Comparative CFD Study of IT Inlet Temperatures and Fan Energy Savings WH I TE PAPE R AisleLok Modular Containment vs. : A Comparative CFD Study of IT Inlet Temperatures and Fan Energy Savings By Bruce Long, Upsite Technologies, Inc. Lars Strong, P.E., Upsite Technologies,

More information

Interested in conducting your own webinar? Email webinars@bnpmedia.com

Interested in conducting your own webinar? Email webinars@bnpmedia.com Interested in conducting your own webinar? Email webinars@bnpmedia.com Improving Efficiencies by Integrating Data Center Systems August 30 th, 2012 Audio Abstract Presenter Info Slides Handouts Group Chat

More information

How Does Your Data Center Measure Up? Energy Efficiency Metrics and Benchmarks for Data Center Infrastructure Systems

How Does Your Data Center Measure Up? Energy Efficiency Metrics and Benchmarks for Data Center Infrastructure Systems How Does Your Data Center Measure Up? Energy Efficiency Metrics and Benchmarks for Data Center Infrastructure Systems Paul Mathew, Ph.D., Staff Scientist Steve Greenberg, P.E., Energy Management Engineer

More information

Maximize energy savings Increase life of cooling equipment More reliable for extreme cold weather conditions There are disadvantages

Maximize energy savings Increase life of cooling equipment More reliable for extreme cold weather conditions There are disadvantages Objectives Increase awareness of the types of economizers currently used for data centers Provide designers/owners with an overview of the benefits and challenges associated with each type Outline some

More information

DataCenter 2020: hot aisle and cold aisle containment efficiencies reveal no significant differences

DataCenter 2020: hot aisle and cold aisle containment efficiencies reveal no significant differences DataCenter 2020: hot aisle and cold aisle containment efficiencies reveal no significant differences November 2011 Powered by DataCenter 2020: hot aisle and cold aisle containment efficiencies reveal no

More information

How To Run A Data Center Efficiently

How To Run A Data Center Efficiently A White Paper from the Experts in Business-Critical Continuity TM Data Center Cooling Assessments What They Can Do for You Executive Summary Managing data centers and IT facilities is becoming increasingly

More information

80% of. 50% of. 30% of. 67% of enterprises. Environmental and business demands are converging

80% of. 50% of. 30% of. 67% of enterprises. Environmental and business demands are converging Delivering the Green Datacenter Jerome Riboulon, HP 2008 Hewlett-Packard Development Company, L.P. The information contained herein is subject to change without notice 2 24 Abril, 2008 Environmental and

More information

Data center upgrade proposal. (phase one)

Data center upgrade proposal. (phase one) Data center upgrade proposal (phase one) Executive Summary Great Lakes began a recent dialogue with a customer regarding current operations and the potential for performance improvement within the The

More information

Direct Fresh Air Free Cooling of Data Centres

Direct Fresh Air Free Cooling of Data Centres White Paper Introduction There have been many different cooling systems deployed in Data Centres in the past to maintain an acceptable environment for the equipment and for Data Centre operatives. The

More information

Data Center Planning. PUE Overview

Data Center Planning. PUE Overview Data Center Planning PUE Overview Steve Carter, Americas Managing Principal Charles Prawdzik Jr., Project Manager HP Critical Facility Services delivered by EYP Mission Critical Facilities, Inc. 2008 Hewlett-Packard

More information

Minimising Data Centre Total Cost of Ownership Through Energy Efficiency Analysis

Minimising Data Centre Total Cost of Ownership Through Energy Efficiency Analysis Minimising Data Centre Total Cost of Ownership Through Energy Efficiency Analysis Sophia Flucker CEng MIMechE Ing Dr Robert Tozer MSc MBA PhD CEng MCIBSE MASHRAE Operational Intelligence Ltd. info@dc-oi.com

More information

Choosing Close-Coupled IT Cooling Solutions

Choosing Close-Coupled IT Cooling Solutions W H I T E P A P E R Choosing Close-Coupled IT Cooling Solutions Smart Strategies for Small to Mid-Size Data Centers Executive Summary As high-density IT equipment becomes the new normal, the amount of

More information

Greening Commercial Data Centres

Greening Commercial Data Centres Greening Commercial Data Centres Fresh air cooling giving a PUE of 1.2 in a colocation environment Greater efficiency and greater resilience Adjustable Overhead Supply allows variation in rack cooling

More information

Unified Physical Infrastructure (UPI) Strategies for Thermal Management

Unified Physical Infrastructure (UPI) Strategies for Thermal Management Unified Physical Infrastructure (UPI) Strategies for Thermal Management The Importance of Air Sealing Grommets to Improving Smart www.panduit.com WP-04 August 2008 Introduction One of the core issues affecting

More information

Presentation Outline. Common Terms / Concepts HVAC Building Blocks. Links. Plant Level Building Blocks. Air Distribution Building Blocks

Presentation Outline. Common Terms / Concepts HVAC Building Blocks. Links. Plant Level Building Blocks. Air Distribution Building Blocks Presentation Outline Common Terms / Concepts HVAC Building Blocks Plant Level Building Blocks Description / Application Data Green opportunities Selection Criteria Air Distribution Building Blocks same

More information

Hot Air Isolation Cools High-Density Data Centers By: Ian Seaton, Technology Marketing Manager, Chatsworth Products, Inc.

Hot Air Isolation Cools High-Density Data Centers By: Ian Seaton, Technology Marketing Manager, Chatsworth Products, Inc. Business Management Magazine Winter 2008 Hot Air Isolation Cools High-Density Data Centers By: Ian Seaton, Technology Marketing Manager, Chatsworth Products, Inc. Contrary to some beliefs, air is quite

More information

Power and Cooling for Ultra-High Density Racks and Blade Servers

Power and Cooling for Ultra-High Density Racks and Blade Servers Power and Cooling for Ultra-High Density Racks and Blade Servers White Paper #46 Introduction The Problem Average rack in a typical data center is under 2 kw Dense deployment of blade servers (10-20 kw

More information

White Paper. Data Center Containment Cooling Strategies. Abstract WHITE PAPER EC9001. Geist Updated August 2010

White Paper. Data Center Containment Cooling Strategies. Abstract WHITE PAPER EC9001. Geist Updated August 2010 White Paper Data Center Containment Cooling Strategies WHITE PAPER EC9001 Geist Updated August 2010 Abstract Deployment of high density IT equipment into data center infrastructure is now a common occurrence

More information

Energy Efficiency Best Practice Guide Data Centre and IT Facilities

Energy Efficiency Best Practice Guide Data Centre and IT Facilities 2 Energy Efficiency Best Practice Guide Data Centre and IT Facilities Best Practice Guide Pumping Systems Contents Medium-sized data centres energy efficiency 3 1 Introduction 4 2 The business benefits

More information

Recommendations for Measuring and Reporting Overall Data Center Efficiency

Recommendations for Measuring and Reporting Overall Data Center Efficiency Recommendations for Measuring and Reporting Overall Data Center Efficiency Version 1 Measuring PUE at Dedicated Data Centers 15 July 2010 Table of Contents 1 Introduction... 1 1.1 Purpose Recommendations

More information

I-STUTE Project - WP2.3 Data Centre Cooling. Project Review Meeting 8, Loughborough University, 29 th June 2015

I-STUTE Project - WP2.3 Data Centre Cooling. Project Review Meeting 8, Loughborough University, 29 th June 2015 I-STUTE Project - WP2.3 Data Centre Cooling Project Review Meeting 8, Loughborough University, 29 th June 2015 Topics to be considered 1. Progress on project tasks 2. Development of data centre test facility

More information

Data Center Technology: Physical Infrastructure

Data Center Technology: Physical Infrastructure Data Center Technology: Physical Infrastructure IT Trends Affecting New Technologies and Energy Efficiency Imperatives in the Data Center Hisham Elzahhar Regional Enterprise & System Manager, Schneider

More information

Greening Data Centers

Greening Data Centers Greening Data Centers Dallas Thornton SDSC Division Director, Cyberinfrastructure Services March 2, 2011 Data Centers Are Enormous Users of Power US Data Centers (TeraWatt Hours per Year) 125 US Televisions

More information

Overview of Green Energy Strategies and Techniques for Modern Data Centers

Overview of Green Energy Strategies and Techniques for Modern Data Centers Overview of Green Energy Strategies and Techniques for Modern Data Centers Introduction Data centers ensure the operation of critical business IT equipment including servers, networking and storage devices.

More information

International Telecommunication Union SERIES L: CONSTRUCTION, INSTALLATION AND PROTECTION OF TELECOMMUNICATION CABLES IN PUBLIC NETWORKS

International Telecommunication Union SERIES L: CONSTRUCTION, INSTALLATION AND PROTECTION OF TELECOMMUNICATION CABLES IN PUBLIC NETWORKS International Telecommunication Union ITU-T TELECOMMUNICATION STANDARDIZATION SECTOR OF ITU Technical Paper (13 December 2013) SERIES L: CONSTRUCTION, INSTALLATION AND PROTECTION OF TELECOMMUNICATION CABLES

More information

Data Center Components Overview

Data Center Components Overview Data Center Components Overview Power Power Outside Transformer Takes grid power and transforms it from 113KV to 480V Utility (grid) power Supply of high voltage power to the Data Center Electrical Room

More information

Adaptive Cooling in Data Centers. Silicon Valley Leadership Group Energy Efficient Data Center Demonstration Project October, 2009

Adaptive Cooling in Data Centers. Silicon Valley Leadership Group Energy Efficient Data Center Demonstration Project October, 2009 Adaptive Cooling in Data Centers Silicon Valley Leadership Group Energy Efficient Data Center Demonstration Project October, 2009 Maximizing Cooling Efficiency in a Concurrently Maintainable and Fault

More information

Data Centers: How Does It Affect My Building s Energy Use and What Can I Do?

Data Centers: How Does It Affect My Building s Energy Use and What Can I Do? Data Centers: How Does It Affect My Building s Energy Use and What Can I Do? 1 Thank you for attending today s session! Please let us know your name and/or location when you sign in We ask everyone to

More information

Sealing Gaps Under IT Racks: CFD Analysis Reveals Significant Savings Potential

Sealing Gaps Under IT Racks: CFD Analysis Reveals Significant Savings Potential TECHNICAL REPORT Sealing Gaps Under IT Racks: CFD Analysis Reveals Significant Savings Potential By Lars Strong, P.E., Upsite Technologies, Inc. Bruce Long, Upsite Technologies, Inc. +1.888.982.7800 upsite.com

More information

Making Existing Server Rooms More Efficient Steve Bowes-Phipps, Data Centre Manager University of Hertfordshire. http://rare-idc.herts.ac.

Making Existing Server Rooms More Efficient Steve Bowes-Phipps, Data Centre Manager University of Hertfordshire. http://rare-idc.herts.ac. Making Existing Server Rooms More Efficient Steve Bowes-Phipps, Data Centre Manager University of Hertfordshire http://rare-idc.herts.ac.uk Making Existing Server Rooms More Efficient Reduction and Re-use

More information

Measuring Power in your Data Center: The Roadmap to your PUE and Carbon Footprint

Measuring Power in your Data Center: The Roadmap to your PUE and Carbon Footprint Measuring Power in your Data Center: The Roadmap to your PUE and Carbon Footprint Energy usage in the data center Electricity Transformer/ UPS Air 10% Movement 12% Cooling 25% Lighting, etc. 3% IT Equipment

More information

Trends in Data Center Design ASHRAE Leads the Way to Large Energy Savings

Trends in Data Center Design ASHRAE Leads the Way to Large Energy Savings Trends in Data Center Design ASHRAE Leads the Way to Large Energy Savings ASHRAE Conference, Denver Otto Van Geet, PE June 24, 2014 NREL/PR-6A40-58902 NREL is a national laboratory of the U.S. Department

More information

Energy Efficient Server Room and Data Centre Cooling. Computer Room Evaporative Cooler. EcoCooling

Energy Efficient Server Room and Data Centre Cooling. Computer Room Evaporative Cooler. EcoCooling Energy Efficient Server Room and Data Centre Cooling Computer Room Evaporative Cooler EcoCooling EcoCooling CREC Computer Room Evaporative Cooler Reduce your cooling costs by over 90% Did you know? An

More information

Capgemini UK Infrastructure Outsourcing

Capgemini UK Infrastructure Outsourcing Together. Free your energies Capgemini UK Infrastructure Outsourcing Project Arthur Improved Data Centre Efficiency Paul Feeney Capgemini Tony Mills Spie Matthew Hall Project Arthur The Toltec data centre,

More information

Using thermal mapping at the data centre

Using thermal mapping at the data centre Technical Using thermal mapping at the data centre by Gregory Stockton, CompuScanIR.com Cooling the servers in data centres efficiently is critical to increasing IT reliability, maintaining high performance,

More information

HIGHLY EFFICIENT COOLING FOR YOUR DATA CENTRE

HIGHLY EFFICIENT COOLING FOR YOUR DATA CENTRE HIGHLY EFFICIENT COOLING FOR YOUR DATA CENTRE Best practices for airflow management and cooling optimisation AIRFLOW MANAGEMENT COLD AND HOT AISLE CONTAINMENT DC ASSESSMENT SERVICES Achieving true 24/7/365

More information

Best Practices. for the EU Code of Conduct on Data Centres. Version 1.0.0 First Release Release Public

Best Practices. for the EU Code of Conduct on Data Centres. Version 1.0.0 First Release Release Public Best Practices for the EU Code of Conduct on Data Centres Version 1.0.0 First Release Release Public 1 Introduction This document is a companion to the EU Code of Conduct on Data Centres v0.9. This document

More information

Economizer Fundamentals: Smart Approaches to Energy-Efficient Free-Cooling for Data Centers

Economizer Fundamentals: Smart Approaches to Energy-Efficient Free-Cooling for Data Centers A White Paper from the Experts in Business-Critical Continuity TM Economizer Fundamentals: Smart Approaches to Energy-Efficient Free-Cooling for Data Centers Executive Summary The strategic business importance

More information

How High Temperature Data Centers & Intel Technologies save Energy, Money, Water and Greenhouse Gas Emissions

How High Temperature Data Centers & Intel Technologies save Energy, Money, Water and Greenhouse Gas Emissions Intel Intelligent Power Management Intel How High Temperature Data Centers & Intel Technologies save Energy, Money, Water and Greenhouse Gas Emissions Power and cooling savings through the use of Intel

More information

BCA-IDA Green Mark for Existing Data Centres Version EDC/1.0

BCA-IDA Green Mark for Existing Data Centres Version EDC/1.0 BCA-IDA Green Mark for Existing Data Centres Version EDC/1.0 To achieve GREEN MARK Award Pre-requisite Requirement All relevant pre-requisite requirements for the specific Green Mark Rating are to be complied

More information

The Benefits of Supply Air Temperature Control in the Data Centre

The Benefits of Supply Air Temperature Control in the Data Centre Executive Summary: Controlling the temperature in a data centre is critical to achieving maximum uptime and efficiency, but is it being controlled in the correct place? Whilst data centre layouts have

More information

News in Data Center Cooling

News in Data Center Cooling News in Data Center Cooling Wednesday, 8th May 2013, 16:00h Benjamin Petschke, Director Export - Products Stulz GmbH News in Data Center Cooling Almost any News in Data Center Cooling is about increase

More information

The Data Center Dilemma - A Case Study

The Data Center Dilemma - A Case Study Second Place: Industrial Facilities or Processes, Existing The TCS data center makes use of white cabinets and reflective surfaces as one method to reduce power for its lights and cooling. Data Center

More information

Award-Winning Innovation in Data Center Cooling Design

Award-Winning Innovation in Data Center Cooling Design Award-Winning Innovation in Data Center Cooling Design Oracle s Utah Compute Facility O R A C L E W H I T E P A P E R D E C E M B E R 2 0 1 4 Table of Contents Introduction 1 Overview 2 Innovation in Energy

More information

Best Practice Guide for Data Centres - a UH Perspective Steve Bowes-Phipps, Data Centres Manager University of Hertfordshire

Best Practice Guide for Data Centres - a UH Perspective Steve Bowes-Phipps, Data Centres Manager University of Hertfordshire Best Practice Guide for Data Centres - a UH Perspective Steve Bowes-Phipps, Data Centres Manager University of Hertfordshire http://rare idc.herts.ac.uk Best Practice Guide for Data Centres RARE-IDC Overview

More information