Caribbean Regional Electricity Generation, Interconnection, and Fuels Supply Strategy. Final Report Executive Summary. Submitted to: World Bank

Size: px
Start display at page:

Download "Caribbean Regional Electricity Generation, Interconnection, and Fuels Supply Strategy. Final Report Executive Summary. Submitted to: World Bank"

Transcription

1 The Power of Experience Submitted to: World Bank Caribbean Regional Electricity Generation, Interconnection, and Fuels Supply Strategy Final Report Executive Summary Submitted By: March 2010

2 Contents Section Page Section 1 Executive Summary Introduction Approach Load Forecast Fuel Supply Project and Technology Analysis Regional Strategies Country Summaries Recommendations Table Page Acronyms and Abbreviations... ii Table 1-1 Net Peak Demand Load Forecast (MW) Table 1-2 Net Generation Forecast (GWh) Table 1-3 Fuel Prices Based on Yearly Demand Table 1-4 Scenario NPV Cost Differences - Base Case Minus Other Scenario Costs (million US$) Figure Page Figure 1-1 Caribbean Regional Map Figure 1-2 Countries Included in the Study Figure 1-3 Other Relevant Countries Addressed in the Study Figure 1-4 Fossil LCL for Dominican Republic Figure 1-5 Other Options for Dominican Republic Figure 1-6 Eastern Caribbean Gas Pipeline (ECGP) Proposed Route Figure 1-7 Dominica Interconnections Figure 1-8 Nevis Puerto Rico and Nevis US Virgin Islands Interconnections Figure 1-9 Saba St. Maarten Interconnection Figure 1-10 Haiti Dominican Republic Interconnection Figure 1-11 United States (Florida) Cuba Interconnection Figure 1-12 Northern Ring Set of Interconnections Figure 1-13 Northern Ring Interconnections Alternative Figure 1-14 Distillate LCL vs. Renewable Energy Options Figure 1-15 Barbados LCL vs. Renewable Energy Options Caribbean Regional Electricity Generation, Interconnection, and Fuels Supply Strategy Final Report i

3 Contents Acronyms and Abbreviations APC APUA BL&P CC, CCGT CFB CNG CO2 CSP CT DOMLEC DR ECGP EDH, EdH GJ GRENLEC GT GWH, GWh HFO IBRD IDA JPS km kv kw kwh LCL LNG LSD LUCELEC m MEM MSD MVA MW NPV O&M PV USA US$ V VINLEC yr Antigua Power Company Antigua Public Utility Authority Barbados Light and Power Combined cycle gas turbine Circulating fluidized bed Compressed natural gas Carbon dioxide Concentrating solar power Combustion turbine Dominica Electricity Services Limited Dominican Republic Eastern Caribbean Gas Pipeline Electricite d'haiti Gigajoule Grenada Energy Services Ltd. Gas turbine Gigawatt-hour Heavy fuel oil International Bank for Reconstruction and Development International Development Association Jamaica Public Service Kilometer Kilovolt Kilowatt Kilowatt-hour Least cost line Liquefied natural gas Low speed diesel St. Lucia Electricity Services Ltd. Meter Ministry of Energy and Mining (Jamaica) Medium speed diesel Megavolt-ampere Megawatt Net present value Operations and maintenance Photovoltaic United States of America United States dollar Volt St. Vincent Electricity Service Ltd. Year Caribbean Regional Electricity Generation, Interconnection, and Fuels Supply Strategy Final Report ii

4 Section 1 Executive Summary 1.1 INTRODUCTION The objective of this Caribbean Regional Electricity Generation, Interconnection, and Fuels Supply Strategy (the Study) is to analyze the availability of technically and financially sound regional and sub-regional energy solutions for power generation rather than specific energy solutions for each Caribbean country. The energy solutions involve new fuels or fuel transport modes (pipeline gas, compressed natural gas [CNG], liquefied natural gas [LNG], coal), new energy resources for power generation (primarily wind and geothermal), and new electrical interconnections among islands, none of which are presently interconnected. The immediate goal of studying these areas was to reduce the Caribbean islands dependence on high price imported distillate and heavy fuel oil (HFO). A related goal was that solutions would emerge that reduced costs, reduced environmental impacts, and increased the integration of the Caribbean islands. The entire Caribbean region is presented on Figure 1-1. We note at the outset that we have identified no truly regional energy solutions, not even one covering the nine countries of primary emphasis mentioned in the second paragraph below. We have identified and analyzed, to varying degrees of detail, 11 submarine cable electrical interconnections between two countries and one land-based interconnection. Some of these twocountry sub-regional interconnections are part of larger schemes involving three or more countries. The only sub-regional fuel project the Study evaluated was the five-country Eastern Caribbean Gas Pipeline (ECGP). Schemes involving LNG or CNG implicitly or explicitly rely on some common facilities when more than one country is a user, but in that sense they are not different from the current delivery modes for distillate and HFO and were analyzed on a countryby-country basis. It is interesting that the goal of reducing dependence on high price imported oil products and the goal of reducing environmental impacts and increasing the integration of the region turned out to be complementary. The most direct benefit of an interconnection comes when one country has a source of low cost power and its neighbor does not. The three lowest cost resources for operation at capacity factors above about 30% are renewables: geothermal, wind (including the cost of backup generation), and small hydro. This assumes that high quality sites can be identified and acquired. Geothermal is the source of generation and drives the benefits for many of the interconnections. Thus geothermal on a local and sub-regional basis, and wind on a local basis, provide a path toward a less oil-dependent, lower cost, lower environmental impact, more sustainable future. The primary emphasis of the Study is on the nine countries in the Caribbean eligible for support from the International Development Association (IDA) and/or the International Bank for Reconstruction and Development (IBRD). Those countries are presented, together with their relative electricity market share, on Figure 1-2. These nine include: Caribbean Regional Electricity Generation, Interconnection, and Fuels Supply Strategy Final Report 1-1

5 Six small countries in the Lesser Antilles: St. Lucia, St. Vincent and the Grenadines, Grenada, Antigua and Barbuda, St. Kitts and Nevis, and Dominica, total combined population about 600,000 Three countries located on two of the four islands in the Greater Antilles: Haiti and the Dominican Republic, both on the island Hispaniola, and Jamaica, total population about 22,000,000 The Study also considered other relevant countries, presented on Figure 1-3, that might be part of a regional energy solution. In addition to the nine countries mentioned above, we visited or obtained significant data on Barbados 1, Trinidad and Tobago, and Martinique; somewhat less on Guadeloupe; and cursory information on Puerto Rico, Sint Maarten, and Cuba. We also obtained cursory information on power generation in Florida. 1 Barbados was addressed in more details as par of the Eastern Caribbean Gas Pipeline project analysis. Caribbean Regional Electricity Generation, Interconnection, and Fuels Supply Strategy Final Report 1-2

6 Figure 1-1 Caribbean Regional Map Caribbean Regional Electricity Generation, Interconnection, and Fuels Supply Strategy Final Report 1-3

7 Figure 1-2 Countries Included in the Study Caribbean Regional Electricity Generation, Interconnection, and Fuels Supply Strategy Final Report 1-4

8 Figure 1-3 Other Relevant Countries Addressed in the Study Caribbean Regional Electricity Generation, Interconnection, and Fuels Supply Strategy Final Report 1-5

9 1.2 APPROACH Our approach included the following main steps: Collect the foundation data needed to conduct the work Prepare a peak and energy demand forecast for each country and the Study countries as a whole Forecast fuel costs for all fuels used, including pipeline gas, LNG, CNG, and coal Estimate fuel transportation costs for each fuel to each country and determine effective fuel price Determine the performance and cost parameters of all existing power generation units Determine the performance and cost parameters of power generation units suitable for meeting future demand Evaluate the cost and performance parameters for power generation from renewable energy, and estimate the availability of renewable energy resources Evaluate submarine cable technology Identify and evaluate submarine cable and land-based transmission interconnections Develop scenarios that include a range of approaches to regional power generation, and combine the most attractive components in an proposed scenario Report on and present the results (such as in this report) 1.3 LOAD FORECAST Tables 1-1 and 1-2 provides peak and energy demand forecasts for each country / island and for the region as a whole. Caribbean Regional Electricity Generation, Interconnection, and Fuels Supply Strategy Final Report 1-6

10 Table 1-1 Net Peak Demand Load Forecast (MW) Year Antigua and Barbuda Barbados Dominica Dominican Republic Grenada Haiti Jamaica St. Kitts Nevis St. Lucia St. Vincent and Martinique Guadeloupe Grenadines , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , ,109 Growth Rate 3.3% 3.5% 2.7% 3.4% 5.4% 5.0% 4.3% 3.5% 5.9% 3.8% 6.9% 2.5% 2.5% 3.6% Total Caribbean Regional Electricity Generation, Interconnection, and Fuels Supply Strategy Interim Report 1-7

11 Table 1-2 Net Generation Forecast (GWh) Year Antigua and Barbuda Barbados Dominica Dominican Republic Grenada Haiti Jamaica St. Kitts Nevis St. Lucia St. Vincent and Martinique Guadeloupe Grenadines , , , ,575 1,663 23, , , , ,620 1,720 24, , , , ,672 1,775 25, , , , ,727 1,832 26, , , , ,783 1,888 27, , , ,063 5, ,840 1,947 28, , , ,169 5, ,900 2,003 29, , , ,286 5, ,938 2,060 30, , , ,415 6, ,978 2,117 31, , , ,556 6, ,018 2,174 32, , , ,712 6, ,058 2,233 33, , , ,883 7, ,100 2,284 35, , , ,977 7, ,142 2,337 36, , , ,076 7, ,186 2,390 37, , , ,180 8, ,230 2,445 39, , , ,289 8, ,275 2,501 40, , , ,403 8, ,321 2,559 41, , , ,523 9, ,368 2,618 43, , , ,650 9, ,416 2,679 44, , , ,782 9, ,465 2,741 46,490 Growth Rate 3.9% 3.2% 2.5% 3.4% 5.3% 7.9% 4.3% 2.9% 5.2% 3.1% 6.9% 2.4% 2.7% 3.7% Total Caribbean Regional Electricity Generation, Interconnection, and Fuels Supply Strategy Interim Report 1-8

12 1.4 FUEL SUPPLY The forecast levelized price of distillate over , the assumed study period for the new projects being considered, is US$22.45/GJ. Each country except Dominica has at least one lower cost fuel option, and many countries have more than one. Table 1-3 provides the comparative prices. Distillate, LNG, and pipeline gas can be compared directly because they can fuel the same generators. Coal fuels generators with higher capital costs and higher heat rates, which must be taken into account in comparing fuel options. The prices of all fuels except distillate vary from country to country because they include transportation costs that vary. Table 1-3 Fuel Prices Based on Yearly Demand Fuels Selected in Addition to Coal and Distillate Levelized Fuel Price, US$/GJ Fuel Selected Coal Distillate Country Antigua and Barbuda None N/A Barbados Pipeline Gas Dominica Distillate only N/A N/A Dominican Republic LNG Grenada None N/A Guadeloupe Pipeline Gas Haiti LNG Jamaica LNG Jamaica North LNG Martinique Pipeline Gas St. Kitts and Nevis None N/A St. Lucia Pipeline Gas St. Vincent and Grenadines None N/A Coal is an optional fuel for every country except Dominica, where preliminary analysis showed it to be more costly than distillate on a US$/GJ basis. Table 1-3 shows the following: Every country except Dominica has at least one fuel option lower in price than distillate Pipeline gas is the lowest cost natural gas option for every country reached by the ECGP: Barbados, Martinique, St. Lucia, and Guadeloupe Coal is the only optional fuel for Antigua and Barbuda, Grenada, St. Kitts and Nevis, and St. Vincent and Grenadines LNG is the lowest cost natural gas option for Dominican Republic, Haiti, Jamaica, and Jamaica North Caribbean Regional Electricity Generation, Interconnection, and Fuels Supply Strategy Final Report 1-9

13 CNG was considered and was the lowest cost gas option for several countries, but for those countries was always higher in cost than distillate and therefore does not appear in Table It was considerably lower than distillate for some countries, but was more costly than LNG in those countries. Though not studied in the same detail as the other fuel options, mid-scale LNG may provide an economically attractive option for some countries. 1.5 PROJECT AND TECHNOLOGY ANALYSIS Screening analysis is an approach to comparing the costs of different technologies to determine the least cost technology across the range of annual capacity factors: Uses simplified representations of generation costs to help identify least cost generating technologies Plots annual cost in $/kw-year vs. capacity factor for a set of power plant and/or fuel options The cost in $/kw-yr can also be easily expressed in cents/kwh, which are also of interest but are curved and somewhat harder to interpret than the straight lines in $/kw-yr Annual cost is sum of: Annualized investment-related costs based on initial capital investment, discount rate, and plant lifetime Fixed annual operation and maintenance (O&M) Variable cost (includes fuel cost and variable O&M costs) per kwh times capacity factor times hours per year Selects lowest cost resources at each capacity factor, producing the least-cost line for that set of resources Isolated Countries / Islands Figure 1-4 illustrates the screening analysis approach. It presents the Fossil Least Cost Line (Fossil LCL) that applies for the Dominican Republic. The word Fossil means that only fossil fueled generation is included in determining the LCL. The scale in $/kw-yr for the solid lines is on the left, the scale in cents/kwh for the dotted lines is on the right. The Fossil LCL comprises 50 MW GT on LNG for capacity factors of zero through 20%, the 300 MW CC on LNG for capacity factors from 25% through 40%, and the conventional coal plant for capacity factors from 45% through 90%. In other words, the generation expansion plan based on this analysis would include gas turbines for peaking duty, combined cycles for mid-range duty, and conventional coal for base load duty. In order to achieve the Fossil LCL the Dominican Republic would have to undertake large capital investments for expansion related to coal and LNG transportation, and for coal plants themselves. This may pose a challenge, even if the desire to do so exists. LNG is preferable for application at lower capacity factors, coal for application at higher capacity factors. The scenario analysis provides more information on which is preferable overall, if doing both is not feasible. Caribbean Regional Electricity Generation, Interconnection, and Fuels Supply Strategy Final Report 1-10

14 Figure 1-5 expands upon Figure 1-4 by adding wind, small hydro, and fossil options to the graph of Figure 1-1. The small hydro line coincidentally overlaps with the wind with backup line at capacity factors from 30% to 40%. Wind with backup, which is typically a better comparison than wind without backup, is now marginally economic at the capacity factors where it might operate at a good site. Wind with backup simply adds the full cost of operation of a 50 MW gas turbine at 5% capacity factor to the costs of wind without backup, which also adds 5% to the capacity factor. Figure 1-5 also illustrates what might occur if neither coal nor LNG is available for future generation for the Dominican Republic. The periwinkle line represents the cost of a 300 MW HFO-fueled steam plant. Without expanded supplies of LNG or coal, costs will more than triple at high capacity factors. Dominican Republic has under construction or planned considerable new small hydro and wind generation. Figure 1-5 illustrates the desirability of such an approach where good sites can be identified. Annual Cost, $/kw-year 2,500 2,000 1,500 1, Fossil Least Cost Line, US/kW-yr 50 MW GT LNG US$/kW-yr 300 MW CC LNG US$/kW-yr 300 MW Conv Coal, US$/kW-yr Fossil LCL, US cents/kwh Cost, US cents/kwh 0 0 0% 10% 20% 30% 40% 50% 60% 70% 80% 90% Capacity Factor, % Figure 1-4 Fossil LCL for Dominican Republic Caribbean Regional Electricity Generation, Interconnection, and Fuels Supply Strategy Final Report 1-11

15 2, Annual Cost, $/kw-year 2,000 1,500 1, Fossil Least Cost Line, US/kW-yr 1.5 MW Wind US$/kW-yr 1.5 MW Wind w/backup US$/kW-yr 300 MW ST HFO DR US$/kW-yr Small Hydro US$/kW-yr Fossil LCL, US cents/kwh Cost, US cents/kwh 0 0 0% 10% 20% 30% 40% 50% 60% 70% 80% 90% Capacity Factor, % Figure 1-5 Other Options for Dominican Republic The bullets below summarize the least cost technology/fossil fuel combination by country as determined by screening analysis. This considers the countries and islands as isolated systems. For some countries, imports via submarine cable (to be discussed later) provide a lower cost solution. We eliminated the technology/fuel combinations that were least cost at only one annual capacity factor, such as zero or 90%. Scenario analysis generally supports these conclusions, though multiple fuels were not used as much. Individual Countries Antigua and Barbuda, Grenada, and St. Vincent and Grenadines: 10 MW MSD on distillate for peaking and mid-range duty, and the coal-fueled CFB for base load duty Coal-fueled CFB is only marginally more economic than distillate fueled medium speed diesels (MSD) plants; CO2 costs of US$50/tonne would make the distillatefueled units more economic than the coal-fueled units Dominica, St. Kitts, and Nevis: 5 MW MSD on distillate for peaking, mid-range, and base load duty St. Kitts and Nevis are fortunate that a geothermal resource sufficient to serve all their demand has been confirmed and is in the process of development. For Dominica it seems highly probable that a geothermal resource sufficient to serve at least local demand will be confirmed and developed. None of these islands may not need to install any new distillate-fueled generation. Dominican Republic: 50 MW GT on LNG for peaking duty, 300 MW CC on LNG for mid-range duty, and 300 MW conventional coal plant for base load duty Caribbean Regional Electricity Generation, Interconnection, and Fuels Supply Strategy Final Report 1-12

16 The Dominican Republic already has an LNG terminal and coal-fueled power plants. Scenario analysis shows that coal is preferred if only one fuel can be selected for future additions. However, incorporating CO2 costs in the analysis would compromise coal s advantage. With the Dominican Republic s large demand, expanding the use of both fuels may be feasible, even if new facilities are needed. Haiti: 20 MW LSD on LNG for peaking, mid-range, and base load duty. LNG provides very large benefits but requires significant up-front capital expenditures Jamaica and Jamaica North: 50 MW GT on LNG for peaking duty, 20 MW LSD on LNG for mid-range duty, and 50 MW coal-fueled CFB base load duty Today Jamaica and Jamaica North have neither fuel. It seems unlikely that they would want to develop both fuels. If only one is to be developed, LNG is preferred, and its advantage would increase if CO2 costs are incorporated in the analysis. We emphasize that for some countries, imports via submarine cable provide a lower cost solution. This is addressed in the next subsection. Sub-regional Gas Market The ECGP links the markets of the four countries and provides the benefits of economies of scale compared to individual development. Barbados, Guadeloupe, Martinique, and St. Lucia: 20 MW GT on pipeline gas for peaking duty and 20 MW LSD on pipeline gas for mid-range and base load duty For all four countries the pipeline gas is less than half as costly as distillate. For all but St. Lucia, LNG is more costly than pipeline gas but significantly less costly than distillate. The low gas price reduces the benefits of renewables and for Martinique and Guadeloupe makes importing geothermal power from Dominica via submarine cable marginal. Figure 1-6 illustrates the ECGP gas connections among the countries. Caribbean Regional Electricity Generation, Interconnection, and Fuels Supply Strategy Final Report 1-13

17 Figure 1-6 Eastern Caribbean Gas Pipeline (ECGP) Proposed Route Sub-regional Electricity Markets The first three bullets below show the interconnections studied with greatest emphasis. All the interconnections were submarine cables except the Dominican Republic Haiti link noted in the bottom bullet. The interconnections are presented in Figures 1-7 to For each interconnection we note its capacity in MW, length in km, cost per kw for interconnection and related facilities only, source of export power, and economic attractiveness. Caribbean Regional Electricity Generation, Interconnection, and Fuels Supply Strategy Final Report 1-14

18 Nevis St. Kitts, 50 MW submarine cable capacity, 5 km submarine cable length, US$328/kW (interconnection and related facilities only), geothermal power export, highly economic Dominica Martinique, 100 MW, 70 km, US$588/kW (interconnection and related facilities only), geothermal power export, marginally economic if displaced fuel is gas from ECGP, more economic if displaced fuel is higher cost Dominica Guadeloupe, 100 MW, 70 km, US$588/kW (interconnection and related facilities only), geothermal power export, moderately economic if displaced fuel is gas from ECGP, more economic if displaced fuel is higher cost Nevis Puerto Rico, 400 MW, 400 km, US$1,791/kW (interconnection and related facilities only), geothermal power export, highly economic if displaced fuel is HFO, not economic if displaced fuel is LNG Nevis US Virgin Islands, 80 MVA, 320 km, US$3,541/kW (interconnection and related facilities only), geothermal power export, only marginally economic even though the displaced fuel is distillate Saba St. Maarten, 100 MW, 60 km, US$528/kW (interconnection and related facilities only), geothermal power export, highly economic if displaced fuel is distillate and St. Maarten can accept 100 MW United States (Florida) Cuba, 400 MW, 400 km, US$1,791/kW (interconnection and related facilities only), export from coal-fueled steam plant or gas-fueled combined cycle, highly economic if displaced fuel is HFO Dominican Republic Haiti, 250 MW, 563 km, US$1,899/kW (interconnection and related facilities only), land interconnection, export from HFO fueled steam plant, not economic unless export is from lower cost unit/fuel combination We also developed basic data and cost estimates for four potential interconnections that might form part of a Northern Ring, a conceptual set of interconnections in the northern Caribbean, potentially linking Florida Cuba Haiti Dominican Republic Puerto Rico Nevis, or some subset of those areas. The Northern Ring interconnections not covered above include: Puerto Rico Dominican Republic, 400 MW, 150 km, US$705/kW (interconnection and related facilities only) Haiti Cuba, 400 MW, 200 km, US$705/kW (interconnection and related facilities only) Haiti Jamaica, 400 MW, 250 km, US$998/kW (interconnection and related facilities only) Florida Haiti, 400 MW, 1,100 km, US$3,488/kW (interconnection and related facilities only We did not conduct economic analysis on these four interconnections. The cost per kw for the three shorter interconnections is in what might be an economically viable range if the sending country had low power costs and the importing country s displaced fuel was distillate, HFO, or crude. The Florida Haiti interconnection appears to be outside that range. Costs for the middle Caribbean Regional Electricity Generation, Interconnection, and Fuels Supply Strategy Final Report 1-15

19 islands would involve their sharing some of the costs of interconnections closer to the low-cost source, making favorable economics more difficult to achieve. Figure 1-7 Dominica Interconnections Caribbean Regional Electricity Generation, Interconnection, and Fuels Supply Strategy Final Report 1-16

20 Figure 1-8 Nevis Puerto Rico and Nevis US Virgin Islands Interconnections Caribbean Regional Electricity Generation, Interconnection, and Fuels Supply Strategy Final Report 1-17

21 Figure 1-9 Saba St. Maarten Interconnection Caribbean Regional Electricity Generation, Interconnection, and Fuels Supply Strategy Final Report 1-18

22 Figure 1-10 Haiti Dominican Republic Interconnection Caribbean Regional Electricity Generation, Interconnection, and Fuels Supply Strategy Final Report 1-19

23 Figure 1-11 United States (Florida) Cuba Interconnection Caribbean Regional Electricity Generation, Interconnection, and Fuels Supply Strategy Final Report 1-20

24 Figure 1-12 Northern Ring Set of Interconnections Caribbean Regional Electricity Generation, Interconnection, and Fuels Supply Strategy Final Report 1-21

25 Figure 1-13 Northern Ring Interconnections Alternative Caribbean Regional Electricity Generation, Interconnection, and Fuels Supply Strategy Final Report 1-22

26 1.5.3 Renewable Energy Wind, geothermal, small hydro, and biomass technology/fuel combinations have the potential, at a good site, to be considerably less costly than distillate fueled power generation. The three lowest cost resources for operation at capacity factors above about 30% are renewables: geothermal, wind (including the cost of backup generation), and small hydro. This assumes that high quality sites can be identified and acquired. Solar PV and solar trough CSP are not competitive for bulk power generation. There are many small solar PV installations in Martinique due to subsidies, and solar PV is competitive for off-grid locations. If a lower cost fuel such as pipeline gas were the competitive fuel, the advantage of the renewable technology would be less. Figure 1-14 compares renewable technologies to the Distillate LCL that results when distillate is the only fuel available. The scale in $/kw-yr for the solid lines is on the left, the scale in cents/kwh for the dotted lines is on the right. The Distillate LCL, in blue, represents the benefit of a renewable energy option. Its generation would displace generation at a cost along that line. Where a renewable energy option s line is below the blue line, there is a net benefit. It reduces costs elsewhere that are more than its own costs. Where it is above the blue line, it represents a net cost. Most of the renewable technologies are shown at a range of capacity factors they might reasonably achieve at a good site. Geothermal is also based on a good site, and is shown over the entire capacity factor range because it is not limited by resource availability once the resource has been defined. Wind with backup simply adds the full cost of operation of a 20 MW LSD at 5% capacity factor to the costs of wind without backup, which also adds 5% to the capacity factor. Biomass costs assume that biomass costs the same as export coal in the US. Figure 1-14 shows that all but two of the renewable energy technologies have the potential, at a good site, to be considerably less costly than distillate fueled power generation. Solar PV and solar trough with six hour storage are above the Distillate LCL. If a lower cost fuel such as pipeline gas were the competitive fuel, the advantage of the renewable technology would be less and might disappear. Figure 1-15 compares renewable technologies to the Fossil LCL for Barbados, which has the lowest cost gas fuel of any of the countries studied. The renewable technologies offer much smaller net benefits, small hydro and wind with storage are marginally economic, biomass is not economic, and the technologies that were not economic before are less competitive. Caribbean Regional Electricity Generation, Interconnection, and Fuels Supply Strategy Final Report 1-23

27 Annual Cost, $/kw-year 2,500 2,000 1,500 1, Distillate LCL, US$/kW-yr 1.5 MW Wind Turbine 1.5 MW Wind w/backup Commercial PV 500 kw 20 MW Geothermal Small Hydro Biomass Solar Trough 6 hr Storage Distillate LCL, US cents/kwh Cost, US cents/kwh % 10% 20% 30% 40% 50% 60% 70% 80% 90% Capacity Factor, % Figure 1-14 Distillate LCL vs. Renewable Energy Options Annual Cost, $/kw-year 2,000 1,500 1, Fossil Least Cost Line, US/kW-yr 1.5 MW Wind Turbine 1.5 MW Wind w/backup Solar Trough 6 hr Storage Series6 Commercial PV 500 kw 20 MW Geothermal Small Hydro Biomass Fossil LCL, US cents/kwh Cost, US cents/kwh 0 0 0% 10% 20% 30% 40% 50% 60% 70% 80% 90% Capacity Factor, % Figure 1-15 Barbados LCL vs. Renewable Energy Options Caribbean Regional Electricity Generation, Interconnection, and Fuels Supply Strategy Final Report 1-24

28 1.5.4 CO2 Costs If a tax or similar levy were attributed to each tonne of CO2 emissions, the cost of using fuels would increase. This would open wider the economic window for technologies that produce lower or no CO2 emissions. However, all the countries today primary fuel is distillate and/or HFO, so the window is already quite wide. We investigated the impact if a cost of US$50/tonne were attributed to CO2 emissions. At US$50/tonne, the effective price of fuels would increase in a range from US$2.52 for distillate to US$4.41 for coal, representing increases ranging from 15% for distillate to 91% for the lowest cost coal for the Study islands. In the bullets below we measure the impact of CO2 costs by how technology choices change when it is applied. Countries with small demand: The fuel prices are high even when coal fuels some of the least-cost generation. For Antigua and Barbuda, Grenada, and St. Vincent and Grenadines, the preferred fuel would switch from coal to distillate. The renewable energy resources that were economic before are now somewhat more economic, and those that were not economic edge closer to being competitive. Countries with medium or high demand. The fuels are much less expensive than distillate and therefore the displaced generation is lower in cost, narrowing the economic window for alternatives. For the Dominican Republic, Jamaica, and Jamaica North, incorporating CO2 costs in the analysis would probably eliminate coal s advantage over LNG or increase LNG s advantage over coal. With no CO2 cost the renewables that were economic for the islands with small demand are still economic, though in some cases only marginally so. Incorporating CO2 costs makes renewables more competitive. 1.6 REGIONAL STRATEGIES For all Study countries combined, costs including fuel savings from exports and interconnection costs were: US$31,985 million for the Base Case Scenario US$29,424 million for the Fuel Scenario US$29,415 million for the Interconnection/Renewable Scenario US$27,619 million for the Integrated Scenario Table 1-4 presents cost differences among Scenarios by system as well as differences in Scenario total costs. The Fuel Scenario and Interconnection/Renewable Scenarios both reduce costs by about US$2.5 billion compared to the Base Case. The Integrated Scenario reduces costs by Caribbean Regional Electricity Generation, Interconnection, and Fuels Supply Strategy Final Report 1-25

29 about US$ 4.3 billion, showing that the Integrated Scenario captures most of the individual benefits of each of the other two Scenarios. Table 1-4 Scenario NPV Cost Differences - Base Case Minus Other Scenario Costs (million US$) Fuel Scenario Interconnection/ Renewable Scenario Integrated Scenario Antigua and Barbuda Barbados Dominica Dominican Republic Grenada Haiti Jamaica St. Kitts Nevis 0 1,135 1,135 St. Lucia St. Vincent and Grenadines Total 2,561 2,570 4,365 The costs of the interconnections and the fuel savings from the exports of geothermal power are attributed to Dominica and Nevis. All numbers in Table 15-2 have positive values (except for zeros for Dominica, St. Kitts, and Nevis for the Fuel Scenario), meaning that each Scenario and each country in each Scenario provides cost savings compared to the Base Case. 1.7 COUNTRY SUMMARIES Each country summary below presents paragraphs on: Overview Current and Forecast Load Fossil Fuel Options Renewable Generation Potential Development Scenarios (development plans for the Base Case Scenario, the Fuel Scenario, the Interconnection/Renewable Scenario, and the Integrations Scenario) Discussion of Country Results Antigua and Barbuda Overview: Antigua Public Utility Authority (APUA) is responsible for the power generation, transmission, and distribution of electricity in Antigua and Barbuda. APUA purchases most of the power from Antigua Power Company (APC), a private company. Antigua and Barbuda Caribbean Regional Electricity Generation, Interconnection, and Fuels Supply Strategy Final Report 1-26

30 currently rely exclusively on diesel for power generation. Efforts are underway to convert some of the diesel engines to HFO as an alternate fuel. Current and Forecast Load: The country s 2009 peak demand is just over 50 MW, with net generation of over 300 GWh. By 2028 peak demand is projected to increase to around 100 MW, with net generation increasing to around 650 GWh (increase rate of 3.9% per year). Losses in the transmission and distribution system are projected to decrease from over 30% in 2009 to around 10% by Fossil Fuel Options: Imported coal was considered as an alternative fuel. Due to the location and electricity demand on the island, the Study did not find natural gas to be an economically viable fuel option. Renewable Generation Potential: Wind is the most promising renewable resource for Antigua and Barbuda. A 2008 Energy Engineering Corp. report indicated that up to 400 MW of wind power can be developed on the islands, primarily on Barbuda. Solar PV potential is estimated at 27 MW of installed capacity, but bulk power development would not be economic based on current estimates. Development Scenarios: All four Study Scenarios assumed that the committed system additions of the Casada Gardens units will be installed during With those unit additions, system reserve margin requirements would be satisfied until During the system demand growth will require building additional generation units. For the Base Case Scenario, new unit additions are assumed to be 10 MW medium speed diesel units using distillate oil. By 2028 the system will need another 30 MW (3 x 10 MW units) to meet the required capacity. For the Fuel Scenario, coal-fueled circulating fluidized bed (CFB) plants are marginally more economic than distillate fueled medium speed diesels (MSD) plants; new unit additions are assumed to be 10 MW CFB units using imported coal. CO2 costs of US$50/tonne would make the distillate-fueled units more economic than the coal-fueled units. Conventional (large-scale) LNG is more costly than either (distillate or coal) option. Though not studied in the same detail as the other fuel options, mid-scale LNG may provide an economically attractive option. By 2028 the system will need another 30 MW (3 x 10 MW units) to meet the required capacity. The Fuel Scenario results show that the introduction of coal provides net present worth savings of US$12 million compared to the Base Case Scenario. The Interconnection/Renewable Scenario assumed development of new diesel units as in the Base Case Scenario, with the addition of 14 MW of new wind units. This assumes that sites with good winds and low development costs can be identified and acquired. There is no electrical interconnection. The Interconnection/Renewable Scenario results show that the introduction of wind generation provides net present worth savings of US$20 million compared to the Base Case Scenario. The Integrated Scenario assumed new generation units are 10 MW CFB units, as in the Fuel Scenario, and the addition of 14 MW of new wind units, as in the Interconnection/Renewable Scenario. The Integrated Scenario results show that including both coal as a fuel and wind Caribbean Regional Electricity Generation, Interconnection, and Fuels Supply Strategy Final Report 1-27

31 generation provides combined savings of US$31 million over the Base Case Scenario. The Integrated Scenario results show savings close to the sum of the savings of other two Scenarios. Discussion of Country Results Adding coal-fueled CFB technology reduces net present worth costs by US$12 million compared to the Base Case Scenario, with a cost advantage compared to distillate-fueled MSD technology ranging from 2% at 55% capacity factor to 10% at 80% capacity factor. That cost advantage disappears if costs of US$50/tonne are attributed to CO2 emissions. Conventional LNG is more costly than distillate, but mid-scale LNG might be a viable fuel option, justifying a more detailed analysis. Development of wind generation reduces net present worth costs by US$20 million compared to the Base Case Scenario, assuming that sites with good winds and low development costs can be identified and acquired. With that assumption wind is much lower in cost than distillate fueled generation. Small hydro and biomass would also be economic, if good sites can be identified. The benefits are relatively unaffected by the choice of fuel for the country s fossil units Barbados Overview: Barbados Light and Power (BL&P), a private company, is responsible for power generation, transmission, and distribution of electricity in Barbados. Existing installed generation of around 240 MW, mostly comprising of low and medium speed diesel units, substantially exceeds peak demand and provides a comfortable reserve margin. BL&P is looking to diversify its fuel mix which is mostly dependent on imported oil products. Current and Forecast Load: The country s 2008 peak demand was 164 MW, with net generation of over 1,000 GWh. By 2028 peak demand is projected to double to around 325 MW, with net generation increasing to around 1,900 GWh (increase rate of 3.5% per year). Fossil Fuel Options: Natural gas, delivered as LNG or through the Eastern Caribbean Gas Pipeline (ECGP), and imported coal were considered as alternative fuel options. Due to the location and electricity demand on the island, the Study found natural gas delivered through ECGP to be the most economically attractive fuel option. Renewable Generation Potential: No studies on country-specific overall wind and solar potential are available. We estimated Barbados wind potential to be at least 10 MW based on an already approved project. Solar PV potential is estimated at 26 MW of installed capacity, but bulk power development would not be economic based on current estimates. Development Scenarios: All four Scenarios assumed that the committed system additions of the nine 16 MW Trent units will be installed. The first six units were added during while the next three units were added when required to match the load growth. All Trent unit additions would satisfy reserve margin requirements until During the Barbados system will require new capacity additions. Caribbean Regional Electricity Generation, Interconnection, and Fuels Supply Strategy Final Report 1-28

32 For the Base Case Scenario, new additions are assumed to be 20 MW low speed diesel units using distillate oil. By 2028 the system will need another 40 MW (2 x 20 MW units) to meet the required capacity. For the Fuel Scenario, assumed system additions are the same as for the Base Case Scenario. The difference is that in this scenario most existing and all new units are assumed to use natural gas as a fuel, supplied through the ECGP. The Fuel Scenario shows that the introduction of ECGP natural gas provides net present worth savings of US$906 million compared to the Base Case Scenario.. For the Interconnection/Renewable Scenario, most assumed system additions are the same as for the Base Case Scenario. The difference in this Scenario is the addition of 45 MW of new wind units. This assumes that sites with good winds and low development costs can be identified and acquired. There is no electrical interconnection. The Interconnection/Renewable Scenario shows that the introduction of wind generation provides net present worth savings of US$39 million compared to the Base Case Scenario. For the Integrated Scenario, the availability of natural gas is assumed, as in the Fuel Scenario, combined with the addition of 45 MW of new wind units, as in the Interconnection/Renewable Scenario. The Integrated Scenario results show net present worth savings of US$912 million over the Base Scenario, only slightly more than for the Fuel Scenario. Discussion of Country Results Barbados has four fossil fuel options that offer significant economic benefits compared to continued reliance on oil products: natural gas via the ECGP, LNG, CNG, and coal. By far the most attractive is the ECGP option, which provides net present worth savings of $906 million compared to the Base Case Scenario. Its cost per kwh compared to distillate fueled generation ranges from less than half at 20% capacity factor to less than 40% at 80% capacity factor. If the ECGP does not materialize, the other fuel options should be considered. They would offer significant savings compared to distillate, though not as dramatic as ECGP gas offers. Development of wind generation reduces Interconnection/Renewable Scenario net present worth costs by US$39 million compared to the Base Case Scenario, assuming that sites with good winds and low development costs can be identified and acquired. However, when ECGP gas is available, as is assumed in the Integrated Scenario, adding wind generation increases savings by only US$6 million. Wind is only marginally economic, as would be small hydro if good sites can be identified, but biomass would be marginally uneconomic. This illustrates the high dependence of wind generation savings on the assumed fuel supply option, and the possibility that wind generation penetration might be limited to only a few of the best wind sites Dominica Overview: Dominica Electricity Services Limited (DOMLEC) is a sole producer responsible for the power generation, transmission, and distribution of electricity in Dominica. Existing installed generation, comprising high and medium speed diesel units and hydro units, exceeds peak Caribbean Regional Electricity Generation, Interconnection, and Fuels Supply Strategy Final Report 1-29

33 demand by 35% providing a comfortable reserve margin. Dominica is looking to diversify its fuel mix, which is mostly dependent on imported oil products. Current and Forecast Load: The country s current peak demand is around 15 MW, with net generation of around 90 GWh. By 2028 peak demand is projected to increase to 25 MW, with net generation increasing to around 150 GWh (increase rate of 2.5% per year). Fossil Fuel Options: Due to the low electricity demand on the island, the least-cost fuel is distillate because the fixed costs associated with all other fuels produce higher unit costs in US$/GJ. Renewable Generation Potential: Based on the ongoing assessment of potential at the Watton Waven field in central Dominica, and West Indies Power s exploration in the Soufriere area, geothermal potential is estimated to be adequate to supply 100 MW of geothermal power plants. Drilling of the first three slim (exploratory) wells is scheduled to start in June 2010 in the Soufriere area near the southern coast. Solar PV potential is estimated at 45 MW of installed capacity, but bulk power development would not be economic based on current estimates. Dominica also has small-size hydro and wind potential. Development Scenarios: Starting in 2012 Dominica will require new capacity additions. For the Base Case Scenario, new additions are assumed to be 5 MW medium speed diesel units using distillate oil. By 2028 the system will need another 15 MW (3 x 5 MW units) to meet the required capacity. Dominica does not have a potentially less expensive fossil fuel option. The Interconnection/Renewable Scenario assumes the addition of a 20 MW geothermal unit in 2012 to satisfy local needs. It also assumes submarine cable electrical interconnections with Martinique and Guadeloupe, and the addition of two 92.5 MW units in 2014 to support exports to those two countries. The results show large benefits of geothermal development in this Scenario, with net present worth savings of US$604 million compared with the Base Case Scenario. The Integrated Scenario assumed assumes the same geothermal additions as in the Interconnection/Renewable Scenario. The key is the assumed fuel savings due to energy exports to Martinique and Guadeloupe. The Integrated Scenario assumes construction of the ECGP and natural gas deliveries to those two countries, so fuel savings on Martinique and Guadeloupe are reduced because the imports are replacing lower cost natural gas (rather than distillate) based generation. The Integrated Scenario result shows combined savings of only US$10 million, demonstrating that savings are highly dependent on the assumed fuel supply option for Martinique and Guadeloupe. Savings of US$10 million is considerably less than the savings from the much smaller supply to Dominica alone. Discussion of Country Results: Because its low demand means that no fossil fuel options appear economic compared to distillate, geothermal development is particularly important for Dominica. It seems probable that a geothermal resource at least large enough to serve Dominica s demand will be confirmed. This would be the most important result from the country s point of view, as it would insulate the Caribbean Regional Electricity Generation, Interconnection, and Fuels Supply Strategy Final Report 1-30

34 country from the high price of distillate, and the uncertainty associated with variation in that price over time. It would also reduce CO2 emissions. Considering the low cost of power of geothermal power, wind generation is only marginally economic compared to geothermal for domestic consumption on Dominica. Small hydro also would be marginally economic if good sites can be identified, but biomass would be marginally uneconomic. Confirmation of a resource sufficient to serve exports to Martinique and/or Guadeloupe is less certain. The benefits of such development are also less certain. Almost US$600 million in savings when distillate is the displaced fuel disappear when ECGP gas is assumed to be the displaced fuel. Martinique and Guadeloupe have another fossil fuel option, LNG, with lower cost than distillate. In the Fuel Scenario, LNG would provide significant savings compared to the Base Case Scenario, though less than the savings with ECGP gas. It is not clear how much the savings would be in the Integrated Scenario, but they would be higher than US$10 million. It is clear that more detailed analysis of the Martinique and Guadeloupe systems would be required to determine the desirability of developing geothermal power on Dominica for export to those countries. That will depend on the fuel supply (continuing with distillate, ECGP, LNG) they select as well as factors such as costs and the number of units that could be converted to natural gas Dominican Republic Overview: Prior to 1997 all the generation, transmission, and distribution assets of the Dominican Republic (DR) were owned by the state owned company CDE. In 1997 a capitalization process divided the three entities and the stocks of the companies were sold t private investors. Now the DR has eleven different private thermal power generating companies and a government owned hydroelectric entity, Empresa de Generación Hidroeléctrica Dominicana (EGEHID). AES Dominica, the largest thermal power generator, is owned by AES an international utility company. Other generation companies are La Empresa Generadora de Electricidad Haina (EGE Haina), Generadora Palamara La Vega (GPLV), La Compañía De Electricidad De San Pedro De Macorís (CESPM) and five smaller companies. There are three private and one public distribution companies and a public owned transmission company. Current and Forecast Load: The country s 2008 peak demand was 2,168 MW, with net generation of over 11,600 GWh, making it by far the largest power market of all studied countries. By 2028 peak demand is projected to double to over 4,400 MW, with net generation increasing to around 23,750 GWh (increase rate of 3.4% per year). Fossil Fuel Options: Today the DR has power plants using coal and natural gas derived from LNG, but most of its existing generation uses HFO. Expanding the use of coal and LNG offers the potential to reduce costs and were considered as alternative fuel options. Renewable Generation Potential: The government enacted a law in 2007 defining goals for future renewable energy development. The goal is to have 25% renewable energy by About 350 MW of wind projects have already been approved. In addition, there is significant additional wind potential based on provisional studies. There are also estimates of 2,899 MW of Caribbean Regional Electricity Generation, Interconnection, and Fuels Supply Strategy Final Report 1-31

Caribbean Regional Electricity Generation, Interconnection, and Fuels Supply Strategy. Final Report. Submitted to: World Bank.

Caribbean Regional Electricity Generation, Interconnection, and Fuels Supply Strategy. Final Report. Submitted to: World Bank. The Power of Experience Submitted to: World Bank Caribbean Regional Electricity Generation, Interconnection, and Fuels Supply Strategy Final Report Submitted By: March 2010 Contents Section Page Section

More information

Geysir Green Energy. Iceland. March 2008

Geysir Green Energy. Iceland. March 2008 Geysir Green Energy Iceland March 2008 THE COMPANY Geysir Green Energy was founded in January 2007 by several Icelandic investors. Company founders provide firm backing and have a long term view of the

More information

GENERATION TECHNOLOGY ASSESSMENT

GENERATION TECHNOLOGY ASSESSMENT SPO PLANNING ANALYSIS GENERATION TECHNOLOGY ASSESSMENT Technology Cost & Performance Milestone 2 Public Technical Conference OCTOBER 30, 2014 NOTE: ALL IRP MATERIALS ARE PRELIMINARY & SUBJECT TO CHANGE

More information

Levelized Cost and Levelized Avoided Cost of New Generation Resources in the Annual Energy Outlook 2015

Levelized Cost and Levelized Avoided Cost of New Generation Resources in the Annual Energy Outlook 2015 June 2015 Levelized Cost and Levelized Avoided Cost of New Generation Resources in the Annual Energy Outlook 2015 This paper presents average values of levelized costs for generating technologies that

More information

Climate finance as an instrument to enhance renewable energy technologies

Climate finance as an instrument to enhance renewable energy technologies Climate finance as an instrument to enhance renewable energy technologies Dr. Karla Solís-García Team Lead Regional Collaboration Centre St. George s 18 September 2013 CARILEC Renewable Energy Forum September,

More information

Options to Bring Down the Cost of Electricity in Jamaica

Options to Bring Down the Cost of Electricity in Jamaica Options to Bring Down the Cost of Electricity in Jamaica Final Report 23 June 2011 Options to Bring Down the Cost of Electricity in Jamaica Final Report 23 June 2011 Copyright Castalia Limited. All rights

More information

THE MULTILATERAL INVESTMENT FUND (MIF) CLEAN & EFFICIENT ENERGY: BUSINESS CASES

THE MULTILATERAL INVESTMENT FUND (MIF) CLEAN & EFFICIENT ENERGY: BUSINESS CASES THE MULTILATERAL INVESTMENT FUND (MIF) CLEAN & EFFICIENT ENERGY: BUSINESS CASES JENNIFER BALDWIN Georgetown, Guyana April 18, 2012 1. WHAT IS THE MIF? 2. LESSONS FROM CHILE 3. OPORTUNITIES 4. MIF PROJECTS

More information

k k k k a aa a a a a aea a EEnE n E EEE 0 00 0000 k 3333

k k k k a aa a a a a aea a EEnE n E EEE 0 00 0000 k 3333 k k k k a a a a a aea a EEnE n E EEE 0 00 0000 n a aa a a k 3333 n a aa a a k k k k 3333 0 a a a 0 a aa a 0 0 aa a a a a a E aa 0 a 3033 0 a aa 0 a a 0 aa a a 0 0 0 a 0 a aa a 0 0 a a a E 0 a0 a0 0 000

More information

SECTOR ASSESSMENT (SUMMARY): ENERGY. 1. Sector Performance, Problems, and Opportunities

SECTOR ASSESSMENT (SUMMARY): ENERGY. 1. Sector Performance, Problems, and Opportunities Country Operations Business Plan: Philippines, 2013 2015 SECTOR ASSESSMENT (SUMMARY): ENERGY 1. Sector Performance, Problems, and Opportunities 1. Challenges. Economic growth has been impeded in the Philippines

More information

Electricity Insight NEW ZEALAND S ENERGY OUTLOOK. Preview of key insights: Exploring the uncertainty in future electricity demand and supply

Electricity Insight NEW ZEALAND S ENERGY OUTLOOK. Preview of key insights: Exploring the uncertainty in future electricity demand and supply NEW ZEALAND S ENERGY OUTLOOK Electricity Insight Exploring the uncertainty in future electricity demand and supply Preview of key insights: Lower demand growth and excess supply should put strong downward

More information

Solar PV in the Caribbean Opportunities and Challenges

Solar PV in the Caribbean Opportunities and Challenges Solar PV in the Caribbean Opportunities and Challenges Also See: Latin America PV Playbook The Latin America PV Playbook explores the budding Latin American PV Market, specifically Mexico, Brazil, Chile,

More information

A Guide to Competition and Regulatory Policy During Interesting Times

A Guide to Competition and Regulatory Policy During Interesting Times Appendix Figures for the White Paper: Allocating Investment Risk in Today s Uncertain Electric Industry: A Guide to Competition and Regulatory Policy During Interesting Times Susan Tierney Analysis Group

More information

Australian Remote Renewables: Opportunities for Investment

Australian Remote Renewables: Opportunities for Investment Australian Remote Renewables: Opportunities for Investment The largely untapped remote clean energy market and funding support available from the Australian Government creates an attractive opportunity

More information

Electric Utilities. Introduction to the module

Electric Utilities. Introduction to the module Introduction to the module The electric utilities module is based on a reporting framework produced by the Institutional Investors Group on Climate Change (IIGCC), Ceres, and the Investor Group on Climate

More information

SECTOR ASSESSMENT (SUMMARY): ENERGY 1. 1. Sector Performance, Problems, and Opportunities

SECTOR ASSESSMENT (SUMMARY): ENERGY 1. 1. Sector Performance, Problems, and Opportunities Country Partnership Strategy: Bangladesh, 2011 SECTOR ASSESSMENT (SUMMARY): ENERGY 1 Sector Road Map 1. Sector Performance, Problems, and Opportunities 1. Power generation gap. Bangladesh endures long

More information

FIXED CHARGE: This is a cost that goes towards making the service available, including

FIXED CHARGE: This is a cost that goes towards making the service available, including ELECTRICITY BILL COMPONENTS FIXED CHARGE: This is a cost that goes towards making the service available, including installation and maintenance of poles, power lines and equipment, and 24-hour customer

More information

Electric Utilities. Introduction to the module

Electric Utilities. Introduction to the module Introduction to the module The electric utilities module is based on a reporting framework produced by the Institutional Investors Group on Climate Change (IIGCC), Ceres, and the Investor Group on Climate

More information

Port Jackson Partners

Port Jackson Partners Port Jackson Partners NOT JUST A CARBON HIT ON ELECTRICITY PRICES Many factors will drive a doubling of electricity prices in many states by 15. This will have a major impact on virtually all businesses.

More information

Levelised Unit Electricity Cost Comparison of Alternate Technologies for Baseload Generation in Ontario

Levelised Unit Electricity Cost Comparison of Alternate Technologies for Baseload Generation in Ontario Canadian Energy Research Institute Levelised Unit Electricity Cost Comparison of Alternate Technologies for Baseload Generation in Ontario Matt Ayres Senior Director, Research Electricity Morgan MacRae

More information

the cost of electricity

the cost of electricity the cost of electricity IN JAMAICA WHY ARE THE prices SO HIGH? Contents Overview What about Policy Decisions? Pricing Policy: Tariff Structure of the Electricity Bill System Distribution Losses Diseconomies

More information

Energy [R]evolution vs. IEA World Energy Outlook scenario

Energy [R]evolution vs. IEA World Energy Outlook scenario Energy [R]evolution vs. IEA World Energy Outlook scenario New set of scenarios takes climate crisis into account World Energy Outlook (WEO) 2008 for the first time takes the climate crisis really into

More information

Photovoltaic in Mexico Recent Developments and Future

Photovoltaic in Mexico Recent Developments and Future Photovoltaic in Mexico Recent Developments and Future Rodolfo Martínez Strevel Berlin, Germany May 23th, 2013 Bufete de Tecnología Solar, S.A. (BUTECSA) Production of Primary Energy in Mexico, 2011 % 7,0

More information

2000 Fuel Share of World Total Primary Energy Supply

2000 Fuel Share of World Total Primary Energy Supply על מה נדבר היום? האם היציאה מפחם לייצור חשמ ל מוצדקת? האם גז טבעי הינה חלופה טובה? האם קיימות אפשרויות אחרות? 2000 Fuel Share of World Total Primary Energy Supply Oil 34.8% Coal 23.5% Other 0.5% Hydro

More information

Off-grid Hybrid Solar: Market Overview, Business Case & Technical Considerations

Off-grid Hybrid Solar: Market Overview, Business Case & Technical Considerations Off-grid Hybrid Solar: Market Overview, Business Case & Technical Considerations Craig Chambers AECOM Australia Pty Ltd of 420 George Street, Sydney, NSW 2000 Australia Keywords : Solar PV, sustainability,

More information

Some micro- and macro-economics of offshore wind*

Some micro- and macro-economics of offshore wind* Some micro- and macro-economics of offshore wind* EPSRC SUPERGEN Wind Energy Hub University of Strathclyde May 2016 Fraser of Allander Institute Energy Modelling Team Fraser of Allander Institute Department

More information

Glossary of Energy Terms. Know Your Power. Towards a Participatory Approach for Sustainable Power Development in the Mekong Region

Glossary of Energy Terms. Know Your Power. Towards a Participatory Approach for Sustainable Power Development in the Mekong Region Glossary of Energy Terms Know Your Power 2012 Towards a Participatory Approach for Sustainable Power Development in the Mekong Region List of terms Terms Page Terms Page Avoided cost 10 Installed capacity

More information

Electric Power Annual 2013

Electric Power Annual 2013 Electric Power Annual 2013 March 2015 Independent Statistics & Analysis www.eia.gov U.S. Department of Energy Washington, DC 20585 This report was prepared by the U.S. Energy Information Administration

More information

Electric Power Annual 2014

Electric Power Annual 2014 Electric Power Annual 2014 February 2016 Independent Statistics & Analysis www.eia.gov U.S. Department of Energy Washington, DC 20585 This report was prepared by the U.S. Energy Information Administration

More information

GLOBAL RENEWABLE ENERGY MARKET OUTLOOK 2013

GLOBAL RENEWABLE ENERGY MARKET OUTLOOK 2013 GLOBAL RENEWABLE ENERGY MARKET OUTLOOK 213 FACT PACK GUY TURNER HEAD OF ECONOMICS AND COMMODITIES APRIL 26, 213 GLOBAL RENEWABLE ENERGY MARKET OUTLOOK, 26 APRIL 213 1 INTRODUCTION This year s Global Renewable

More information

Levelized Cost of New Electricity Generating Technologies

Levelized Cost of New Electricity Generating Technologies Levelized Cost of New Electricity Generating Technologies The Energy Information Administration (EIA) produces forecasts of energy supply and demand for the next 20 years using the National Energy Modeling

More information

Overview of Renewable Energy Development in Caribbean SIDS

Overview of Renewable Energy Development in Caribbean SIDS Overview of Renewable Energy Development in Caribbean SIDS Roland R. Clarke Ph.D. Caribbean Renewable Energy Development Programme, CREDP CARICOM Secretariat, Georgetown, Guyana Tel: 592 222 0079, rclarke@caricom.org,,

More information

International Solar Energy Arena January 23rd, 2009, Istanbul STEAM (Strategic Technical Economic Research Center)

International Solar Energy Arena January 23rd, 2009, Istanbul STEAM (Strategic Technical Economic Research Center) International Solar Energy Arena January 23rd, 2009, Istanbul STEAM (Strategic Technical Economic Research Center) Good morning. Sayin Bakanım. Members of Parliament. Ladies and Gentlemen. Slide 1: Opening

More information

The role of gas in New Zealand s energy future?

The role of gas in New Zealand s energy future? The role of gas in New Zealand s energy future? PLACE IMAGE HERE Mike Underhill, Chief Executive Gas Industry Conference 24 October 2013 Global perspective what s happening with energy? Global recession

More information

Mongolian power sector:

Mongolian power sector: Mongolian power sector: Background and current policy Kh.Erdenechuluun Representing UBEDN, Mongolia BRIEFLY ABOUT MONGOLIA Territory: 1.564 million km 2 Population: 2.7 million Capital city: Ulaanbaatar

More information

SOLARRESERVE. BASELOAD SOLAR Power. Improving Mining Economics with Predictable Energy Costs

SOLARRESERVE. BASELOAD SOLAR Power. Improving Mining Economics with Predictable Energy Costs SOLARRESERVE BASELOAD SOLAR Power Improving Mining Economics with Predictable Energy Costs UNDERSTANDING THE POWER REQUIREMENTS OF THE MINING INDUSTRY Mining operations, particularly those operating off-grid,

More information

A Discussion of PEM Fuel Cell Systems and Distributed Generation

A Discussion of PEM Fuel Cell Systems and Distributed Generation A Discussion of PEM Fuel Cell Systems and Distributed Generation Jeffrey D. Glandt, M. Eng. Principal Engineer, Solutions Engineering May 2011 The information contained in this document is derived from

More information

Success story: Feed-In Tariffs Support renewable energy in Germany

Success story: Feed-In Tariffs Support renewable energy in Germany Success story: Feed-In Tariffs Support renewable energy in Germany This document will show how this success story has been brought about and is made up of the following sections: 1. What is a Feed-In Tariff?

More information

From today s systems to the future renewable energy systems. Iva Ridjan US-DK summer school AAU Copenhagen 17 August 2015

From today s systems to the future renewable energy systems. Iva Ridjan US-DK summer school AAU Copenhagen 17 August 2015 From today s systems to the future renewable energy systems Iva Ridjan US-DK summer school AAU Copenhagen 17 August 2015 STRUCTURE OF ENERGY SYSTEMS 8/17/2015 Copenhagen, Denmark 2 Components Demand Heat

More information

Natural Gas and Electricity Coordination Experiences and Challenges

Natural Gas and Electricity Coordination Experiences and Challenges 1 Natural Gas and Electricity Coordination Experiences and Challenges Challenges Facing the New England Power System Gordon van Welie, President and CEO, ISO New England 2015 IEEE Power & Energy Society

More information

Electricity Rates Forecasting:

Electricity Rates Forecasting: Electricity Rates Forecasting: Muskrat Falls Will Options: Stabilize Rates for Consumers Legal S92A, Good Faith and Regulatory Proceedings in Quebec Department of Natural Resources October 2012 Department

More information

Prospects and Incentives for Use of Alternative Energy Technologies in the Arab Electric Power Generation Sector

Prospects and Incentives for Use of Alternative Energy Technologies in the Arab Electric Power Generation Sector Prospects and Incentives for Use of Alternative Energy Technologies in the Arab Electric Power Generation Sector Samir AlKotob Arab Fund for Economic and Social Development Objectives To overview the Arab

More information

Levelised Cost of Electricity for a Range of New Power Generating Technologies. Sciences and Engineering (ATSE)

Levelised Cost of Electricity for a Range of New Power Generating Technologies. Sciences and Engineering (ATSE) New power cost comparisons Levelised Cost of Electricity for a Range of New Power Generating Technologies Report by the Australian Academy of Technological Sciences and Engineering (ATSE) MaRch 211 New

More information

Comparison of Renewable Portfolio Standards (RPS) Programs in PJM States

Comparison of Renewable Portfolio Standards (RPS) Programs in PJM States Regulation or Legislation Geographic Eligibility Reporting Period Banking Credit Multipliers Technology - Specific (set asides) NJ MD DC PA DE HB 1308 / SB 869 (2004) Bill 15-747 (4/12/2005) SB 1030/Act

More information

WIND AND SOLAR ENERGY DEVELOPMENTS IN IRAN

WIND AND SOLAR ENERGY DEVELOPMENTS IN IRAN WIND AND SOLAR ENERGY DEVELOPMENTS IN IRAN H. Kazemi Karegar a,b, A.Zahedi a,v. Ohis a, G. taleghani b and M. Khalaji b a Department of Electrical & Computer Systems Engineering, PO Box 35, Monash University,

More information

THE NET BENEFITS OF LOW AND NO-CARBON ELECTRICITY TECHNOLOGIES

THE NET BENEFITS OF LOW AND NO-CARBON ELECTRICITY TECHNOLOGIES GLOBAL ECONOMY & DEVELOPMENT WORKING PAPER 73 MAY 2014 Global Economy and Development at BROOKINGS THE NET BENEFITS OF LOW AND NO-CARBON ELECTRICITY TECHNOLOGIES Charles R. Frank, Jr. Global Economy and

More information

The Economics of Nuclear Power: Is New Nuclear Competitive?

The Economics of Nuclear Power: Is New Nuclear Competitive? The Economics of Nuclear Power: Is New Nuclear Competitive? Craig A. Severance CPA Author, Business Risks and Costs of New Nuclear Power (2009) Co-Author, The Economics of Nuclear and Coal Power (1976)

More information

Project Idea Note: Solar Water Heating Fee-For-Service Program in the Caribbean

Project Idea Note: Solar Water Heating Fee-For-Service Program in the Caribbean PROJECT IDEA NOTE (Based on the World Bank s PIN Template, with Some Adaptations) A. Project description, type, location and schedule Name of Project: Solar Water Heating Fee-for-Service Program in the

More information

Investigating a Higher Renewables Portfolio Standard in California

Investigating a Higher Renewables Portfolio Standard in California Investigating a Higher Renewables Portfolio Standard in California January 2014 Investigating a Higher Renewables Portfolio Standard in California January 2014 2013 Copyright. All Rights Reserved. Energy

More information

4. Comparison with DECC (2014) Estimated impacts of energy and climate change policies on energy prices and bills

4. Comparison with DECC (2014) Estimated impacts of energy and climate change policies on energy prices and bills Energy prices and bills - supplementary tables Contents: 1. Energy prices and bills 2. Assumptions 3. Scenarios to 2030 4. Comparison with DECC (2014) Estimated impacts of energy and climate change policies

More information

CHP - The Business Case

CHP - The Business Case CHP - The Business Case An Introduction to Combined Heat and Power CHP 100 1 Acknowledgements 2 Overview! When Does CHP Make Sense! Where is CHP Practical?! Problems in CHP Economic Analysis 3 When Does

More information

Report to AGEA. Comparative Costs of Electricity Generation Technologies. February 2009. Ref: J1721

Report to AGEA. Comparative Costs of Electricity Generation Technologies. February 2009. Ref: J1721 Report to AGEA Comparative Costs of Electricity Generation Technologies February 2009 Ref: J1721 Project Team Walter Gerardi Antoine Nsair Melbourne Office Brisbane Office 242 Ferrars Street GPO Box 2421

More information

Present and Future Cost of New Utility- Scale Electricity Generation

Present and Future Cost of New Utility- Scale Electricity Generation Present and Future Cost of New Utility- Scale Electricity Generation Version 1.0 July 10 Matt Croucher and Tim James L. William Seidman Research Institute W. P. Carey School of Business Arizona State University

More information

Projected Costs of Generating Electricity

Projected Costs of Generating Electricity Executive Summary Projected Costs of Generating Electricity 2015 Edition Projected Costs of Generating Electricity 2015 Edition INTERNATIONAL ENERGY AGENCY NUCLEAR ENERGY AGENCY ORGANISATION FOR ECONOMIC

More information

Transforming America s Energy Future. Kentucky. Energy Statistics. Developed by

Transforming America s Energy Future. Kentucky. Energy Statistics. Developed by Transforming America s Energy Future Kentucky Energy Statistics Developed by 2 2 Summary The first edition of Kentucky Energy Statistics is offered by the National Association for State Energy Officials

More information

Your Global Solution For Medical Flights Caribbean, Americas and Transatlantic

Your Global Solution For Medical Flights Caribbean, Americas and Transatlantic Air Ambulance CARIBBEAN AIR MEDICAL ASSISTANCE Your Global Solution For Medical Flights Caribbean, Americas and Transatlantic ABOUT US JetBudget is an air operator based in St Maarten / St Martin specializing

More information

Opportunity, Policy, and Practice for Renewable Energy: New Mexico Case Study

Opportunity, Policy, and Practice for Renewable Energy: New Mexico Case Study Opportunity, Policy, and Practice for Renewable Energy: New Mexico Case Study 1 Federal policy: RPS, RES, CES Program Design Element S 3813 Renewable Energy Promotion Act 2010 (Bingaman) S. 1462 American

More information

Annual Electricity and Heat Questionnaire

Annual Electricity and Heat Questionnaire Annual Electricity and Heat Questionnaire IEA Statistics Course Pierre Boileau International Energy Agency OVERVIEW Global trends in electricity production 1973-2009 IEA Annual Electricity and Heat Questionnaire

More information

A Cheaper Renewable Alternative for Belarus

A Cheaper Renewable Alternative for Belarus A Cheaper Renewable Alternative for Belarus Issue paper from INFORSE-Europe 1, by Gunnar Boye Olesen, July 2011 Summary Following the increasing fossil energy prices, the country of Belarus is struggling

More information

Alternative RE Approach Technical Support Document

Alternative RE Approach Technical Support Document Alternative RE Approach Technical Support Document 1.1. Introduction Renewable energy (RE) is a cost-effective approach for reducing carbon dioxide (CO 2) emissions from fossil fuel-fired electric generating

More information

Appendix F Alternatives for Estimating Energy Consumption

Appendix F Alternatives for Estimating Energy Consumption Appendix F Alternatives Estimating Energy Consumption This appendix is reprinted from the Annual Energy Review 200. EIA continues to review alternative options accounting energy consumption and related

More information

DEADLINE: 01 April 2015, 4:30PM (AST) CARIBBEAN EXPORT DEVELOPMENT AGENCY REQUEST FOR PROPOSALS NOTICE

DEADLINE: 01 April 2015, 4:30PM (AST) CARIBBEAN EXPORT DEVELOPMENT AGENCY REQUEST FOR PROPOSALS NOTICE DEADLINE: 01 April 2015, 4:30PM (AST) CARIBBEAN EXPORT DEVELOPMENT AGENCY REQUEST FOR PROPOSALS NOTICE TITLE: Lead generation, pre-qualification and short-listing of foreign companies identified as potential

More information

Renewable Technologies

Renewable Technologies RPS Data Form 1: Renewable Generating Technologies Applicable Utility Service Area: All Service Territories Statewide Renewable Technologies Solar Other Other Photovoltaic (PV) Solar Water Heating Hybrid

More information

FEED-IN TARIFF (FiT) IN MALAYSIA www.seda.gov.my

FEED-IN TARIFF (FiT) IN MALAYSIA www.seda.gov.my IN MALAYSIA www.seda.gov.my 1 Introduction to Feed-in Tariff Mechanism Feed-in Tariff mechanism oblige energy utilities to buy renewable energy from producers, at a mandated price. By guaranteeing access

More information

THE COSTS OF DECARBONISING ELECTRICITY GENERATION

THE COSTS OF DECARBONISING ELECTRICITY GENERATION THE COSTS OF DECARBONISING ELECTRICITY GENERATION This technical annex to Building a low-carbon economy presents further details on the analysis underlying the estimates of the costs of decarbonising the

More information

Energy Storage Activities at New York Power Authority

Energy Storage Activities at New York Power Authority Energy Storage Activities at New York Power Authority Li Kou, Ph.D. PE Sr. R&TD Engineer New York Power Authority APPA National Conference, Seattle, WA June 19, 2012 1 New York Power Authority Highlights

More information

Self-Direction of Public Purpose Charges for Renewable Power Purchases, Renewable Tags or On-Site Generation From Renewable Resources

Self-Direction of Public Purpose Charges for Renewable Power Purchases, Renewable Tags or On-Site Generation From Renewable Resources Self-Direction of Public Purpose Charges for Renewable Power Purchases, Renewable Tags or On-Site Generation From Renewable Resources Statutory Requirements Expenditures for electricity from renewable

More information

Determination of the CO2 Emissions Factor the electrical system of the Dominican Republic

Determination of the CO2 Emissions Factor the electrical system of the Dominican Republic VI International Symposium on Energy & Innovation & Entrepreneurship Forum San Juan, Puerto Rico [20.feb.2014] Determination of the CO2 Emissions Factor the electrical system of the Dominican Republic

More information

Asian Journal on Energy and Environment

Asian Journal on Energy and Environment As. J. Energy Env. 2005, 6(02), 139-144 Asian Journal on Energy and Environment ISSN 1513-4121 Available online at www.asian-energy-journal.info The Small Hydropower Project as the Important Renewable

More information

Blueprint. Uralla Case Study

Blueprint. Uralla Case Study Blueprint Uralla Case Study SO if uralla wants To Take Action To become a Z-NET... What can contribute to Zero Net Energy USING less energy at home and at work Generating energy On-site Import Sustainable

More information

Renewable Energy in the manufacturing and tourism industry in Egypt. Regulatory Framework and market potential

Renewable Energy in the manufacturing and tourism industry in Egypt. Regulatory Framework and market potential Renewable Energy in the manufacturing and tourism industry in Egypt Regulatory Framework and market potential Part 1 Electricity Self-consumption 2 Egypt s Electricity Sector Figures 2013 27 GW Peak Load

More information

KAYA IDENTITY ANALYSIS OF DECARBONIZATION OF THE NY ECONOMY REQUIRED FOR CLIMATE ACTION PLAN GOAL OF 40% REDUCTION BY 2030

KAYA IDENTITY ANALYSIS OF DECARBONIZATION OF THE NY ECONOMY REQUIRED FOR CLIMATE ACTION PLAN GOAL OF 40% REDUCTION BY 2030 KAYA IDENTITY ANALYSIS OF DECARBONIZATION OF THE NY ECONOMY REQUIRED FOR CLIMATE ACTION PLAN GOAL OF 40% REDUCTION BY 2030 Roger Caiazza Not representing EEANY DISCLAIMERS The following analysis does not

More information

Kyrgyzstan: Power Generation & Transmission

Kyrgyzstan: Power Generation & Transmission Kyrgyzstan: Power Generation & Transmission October, 2010 Author: Artyom Zozulinsky, Business & Commercial Assistant, US Embassy Bishkek Contents SUMMARY... 2 POWER SECTOR OVERVIEW... 2 Infrastructure...

More information

Renewable Energy Research

Renewable Energy Research Renewable Energy Research Georgia Power and Southern Company have been active in renewable energy research for many years. Over the last five years we have invested six million dollars in renewable energy

More information

SECTOR ASSESSMENT (SUMMARY): ENERGY 1

SECTOR ASSESSMENT (SUMMARY): ENERGY 1 Country Partnership Strategy: Kazakhstan 2012 2016 SECTOR ASSESSMENT (SUMMARY): ENERGY 1 Sector Road Map 1. Sector Performance, Problems, and Opportunities 1. Overview. Oil accounts for about a quarter

More information

CDM Loan Scheme DNA Help Desk CDM Help Desk

CDM Loan Scheme DNA Help Desk CDM Help Desk CDM Loan Scheme DNA Help Desk CDM Help Desk Regional DNA Training for Latin America and the Caribbean Best Western Belize Biltmore Plaza Hotel Belize City, Belize 23 October 2012 Fatima-Zahra Taibi, Programme

More information

SECTOR ASSESSMENT (SUMMARY): ENERGY 1

SECTOR ASSESSMENT (SUMMARY): ENERGY 1 Country Partnership Strategy: Uzbekistan 2012 2016 SECTOR ASSESSMENT (SUMMARY): ENERGY 1 Sector Road Map 1. Sector Performance, Problems, and Opportunities 1. The energy sector underpins Uzbekistan s sustained

More information

Powering NSW. March 2009

Powering NSW. March 2009 Powering NSW March 2009 Executive Summary The NSW Business Chamber is concerned about the future of electricity supply in NSW. The failure to privatise the electricity generators in NSW means the State

More information

Planning for Arizona s Energy Future

Planning for Arizona s Energy Future Planning for Arizona s Energy Future Brad Albert, General Manager of Renewable Resources Arizona Public Service Co. National Conference of State Legislators (NCSL), Energy Task Force December 8, 2010 Regulatory

More information

Emissions Comparison for a 20 MW Flywheel-based Frequency Regulation Power Plant

Emissions Comparison for a 20 MW Flywheel-based Frequency Regulation Power Plant Emissions Comparison for a 20 MW Flywheel-based Frequency Regulation Power Plant Beacon Power Corporation KEMA Project: BPCC.0003.001 May 18, 2007 Final Report with Updated Data Emissions Comparison for

More information

Energy Options in a Carbon Constrained World. Martin Sevior, School of Physics, University of Melbourne http://nuclearinfo.net

Energy Options in a Carbon Constrained World. Martin Sevior, School of Physics, University of Melbourne http://nuclearinfo.net Energy Options in a Carbon Constrained World. Martin Sevior, School of Physics, University of Melbourne Energy underpins our Civilization Imagine one week without Electricity Imagine one week without Motorized

More information

A Plan For a Sustainable Future

A Plan For a Sustainable Future A Plan For a Sustainable Future Mark Z. Jacobson Atmosphere/Energy Program Dept. of Civil & Environmental Engineering Stanford University Using Economics to Confront Climate Change, SIEPR Policy Forum

More information

Greenhouse gas abatement potential in Israel

Greenhouse gas abatement potential in Israel Greenhouse gas abatement potential in Israel Israel s GHG abatement cost curve Translated executive summary, November 2009 1 Executive Summary Background At the December 2009 UNFCCC Conference in Copenhagen,

More information

RENEWABLE ENERGY DEVELOPMENT IN LITHUANIA ACHIEVEMENTS AND DRAWBACKS

RENEWABLE ENERGY DEVELOPMENT IN LITHUANIA ACHIEVEMENTS AND DRAWBACKS RENEWABLE ENERGY DEVELOPMENT IN LITHUANIA ACHIEVEMENTS AND DRAWBACKS Ieva Kuodė Ministry of Energy of the Republic of Lithuania SOLINVEST 2015-06-02 RES TARGETS BY 2020 23% the share of energy from renewable

More information

Draft consolidated baseline and monitoring methodology ACM00XX

Draft consolidated baseline and monitoring methodology ACM00XX Draft consolidated baseline and monitoring methodology ACM00XX Consolidated baseline and monitoring methodology for new grid connected fossil fuel fired power plants using a less GHG intensive technology

More information

The economic impact. of current Investment Trends in. Infrastructure

The economic impact. of current Investment Trends in. Infrastructure Failure to Act The economic impact of current Investment Trends in Electricit y Infrastructure This report was prepared for the American Society of Civil Engineers by Economic Development Research Group,

More information

Fuel cell microchp: Greener and cheaper energy for all

Fuel cell microchp: Greener and cheaper energy for all Fuel cell microchp: Greener and cheaper energy for all Paddy Thompson General Manager Business Development Ceramic Fuel Cells Ltd. May 2013 1 What does our generation mix look like today? 2 Will the lights

More information

FULL SOLAR SUPPLY OF INDUSTRIALIZED COUNTRIES - THE EXAMPLE JAPAN

FULL SOLAR SUPPLY OF INDUSTRIALIZED COUNTRIES - THE EXAMPLE JAPAN FULL SOLAR SUPPLY OF INDUSTRIALIZED COUNTRIES - THE EXAMPLE JAPAN Dr. Harry Lehmann 1 It has long been known that to protect people and the environment from both nuclear risks and dangerous levels of climate

More information

How To Plan For A New Power Plant In Manitoba

How To Plan For A New Power Plant In Manitoba Meeting Manitobans Electricity Manitoba is growing and is expected to continue doing so. Over the last years the province has enjoyed an expanding population and economy. These increases have led to many

More information

COMPETITIVE ELECTRIC ENERGY MARKET IN GREECE

COMPETITIVE ELECTRIC ENERGY MARKET IN GREECE NATIONAL TECHNICAL UNIVERSITY OF ATHENS (NTUA) GREECE COMPETITIVE ELECTRIC ENERGY MARKET IN GREECE EVANGELOS DIALYNAS Professor NTUA Director of Electric Power Division 1 Competitive Electric European

More information

Understanding and Measuring School Electronics

Understanding and Measuring School Electronics Understanding and Measuring School Electronics MATERIALS NEEDED: 1. 6 energy monitoring devices (note: these can be obtained from a variety of sources, i.e., local hardware stores, internet [average cost

More information

The Real Cost of Electrical Energy. Outline of Presentation

The Real Cost of Electrical Energy. Outline of Presentation 2 Outline of Presentation Data Sources Electricity Demand and Supply Cost to Meet Demand Profile Electricity Pricing Cost Impact of Dispatching Generation (Load Following) Simplifying Assumptions Electricity

More information

Ministry of Power & Energy

Ministry of Power & Energy Ministry of Power & Energy Institutional Frame work Power sector overview Renewable energy policy Major issues and barriers Institutional Framework Sustainable Energy Authority The Sri Lanka Sustainable

More information

Energy: renewable sources of energy. Renewable Energy Sources

Energy: renewable sources of energy. Renewable Energy Sources Energy: renewable sources of energy Energy Sources 1 It is technically and economically feasible to phase out net greenhouse gas (GHG) emissions almost entirely by 2050. A report by energy consulting firm

More information

Assessment of Solar-Coal Hybrid Electricity Power Generating Systems 13

Assessment of Solar-Coal Hybrid Electricity Power Generating Systems 13 Journal of Energy and Power Engineering 6 (2012) 12-19 D DAVID PUBLISHING Assessment of Solar-Coal Hybrid Electricity Power Generating Systems Moses Tunde Oladiran 1, Cheddi Kiravu 1 and Ovid Augustus

More information

Wind and solar reducing consumer bills An investigation into the Merit Order Effect

Wind and solar reducing consumer bills An investigation into the Merit Order Effect Switch for Good Wind and solar reducing consumer bills An investigation into the Merit Order Effect Executive summary Concerns over the cost of renewable subsidy schemes have led to significant policy

More information

Adapting Gas-Power Generation to New Role in Low-Carbon Energy Systems

Adapting Gas-Power Generation to New Role in Low-Carbon Energy Systems Adapting Gas-Power Generation to New Role in Low-Carbon Energy Systems Sandra Scalari Enel Ingegneria e Ricerca SpA Copenhagen, May 27-28 th 2014 Enel Presentation Generation Shift & Market in Europe Enel

More information

Energy for Sustainable Development in the Caribbean

Energy for Sustainable Development in the Caribbean Energy for Sustainable Development in the Caribbean Mark Lambrides Department of Sustainable Development Organization of American States 27 March 2008 Power Generation in the Caribbean Country Thermal

More information

VGB Congress Power Plants 2001 Brussels October 10 to 12, 2001. Solar Power Photovoltaics or Solar Thermal Power Plants?

VGB Congress Power Plants 2001 Brussels October 10 to 12, 2001. Solar Power Photovoltaics or Solar Thermal Power Plants? VGB Congress Power Plants 2001 Brussels October 10 to 12, 2001 Solar Power Photovoltaics or Solar Thermal Power Plants? Volker Quaschning 1), Manuel Blanco Muriel 2) 1) DLR, Plataforma Solar de Almería,

More information

Sustainable Schools 2009. Renewable Energy Technologies. Andrew Lyle RD Energy Solutions

Sustainable Schools 2009. Renewable Energy Technologies. Andrew Lyle RD Energy Solutions Sustainable Schools 2009 Renewable Energy Technologies Andrew Lyle RD Energy Solutions RD Energy Solutions Energy efficiency and renewable energy consultancy Project management of installations Maintenance

More information

WHEN AN EFFECTIVE EU ENERGY POLICY?

WHEN AN EFFECTIVE EU ENERGY POLICY? WHEN AN EFFECTIVE EU ENERGY POLICY? A. Clerici ABB Italy Honorary Chairman of WEC Italy Chairman of WEC WG The future role of nuclear in Europe 1 INDEX 1. General Comments 2. Vulnerability 3. Transmission

More information