River Bank & Bed Restoration Works for Bridge Pier Protection Bowmans Crossing & Luskintyre Bridges NSW

Size: px
Start display at page:

Download "River Bank & Bed Restoration Works for Bridge Pier Protection Bowmans Crossing & Luskintyre Bridges NSW"

Transcription

1 River Bank & Bed Restoration Works for Bridge Pier Protection Bowmans Crossing & Luskintyre Bridges NSW Richard Lane 1, Phanta Khamphounvong 2, Sisira Mabotuwana 2 1 NSW Public Works 2 Roads and Traffic Authority of NSW Abstract In June 2007, a severe storm over the Hunter Valley caused extensive damage to private and public infrastructure throughout the Hunter Valley. Moderate flooding caused damage to the abutments of the nominated bridges. The NSW RTA engaged the NSW Public Works to design the rectification works at Bowman s Crossing Bridge and to Project Manage the design and construction of restoration works at Luskintyre Bridge. The paper discusses and illustrates design, construction, cost and time considerations for the rectification to the bridge abutments for the Bowman s Crossing and Luskintyre Bridges. As part of the oral presentation, construction photographs shall be presented of the various phases of work for the Luskintyre Bridge. The restoration works at Bowman s Crossing were moderate at a cost of less than $160k (Incl. GST). The river bank and pier restoration works at Luskintyre Bridge were far more extensive and entailed realigning the river bank some 80 metres up stream of the bridge with the placement of approximately 9,000 tonnes of rock, 5,500 cubic metres of sand, 300 cu metres of top soil and 3,300 square metres of turf. Bowmans Crossing Bridge : Bridge No 1 This bridge crosses the upper reaches of the Hunter River near Jerry s Plain. The flood gradient at the site is reasonably steep where stream velocity is expected to be high. V. Ponnampalam, H. Madrio and E. Ancich 304 Sustainable Bridges: The Thread of Society AP-G90/11_081 ABC 2011

2 River Bank & Bed Restoration Works for Bridge Pier Protection Bowmans Crossing & Luskintyre Bridges NSW 305 Table I. Configuration of the bridge crossing is given below. Bridge Length 180m Depth of Super Structure 900mm No of Spans 10 Design Deck Level RL Span Length 18m Design Flood 1 in 20 Bridge Type PSC Planks Year Built 1996 The bridge and its approaches are on a flat grade. The road approaches and bridge overtop simultaneously during flood. As the river level rises above the soffit level of the bridge the increased head on the upstream side causes the water velocity to accelerate allowing it to pass through the bridge opening. This flow pattern occurs until with a very large flood, such as in 1955, when the complete bridge is submerged. Fig. 1. Bowmans Bridge Crossing ( Cross Section)

3 306 Richard Lane, Phanta Khamphounvong and Sisira Mabotuwana Fig. 2. Comparison of Bed profiles between 1996 and Considerable erosion of up to 3 metres occurred in the river bed around Piers 3, 4 & 5. Original stone protection works around these piers was eroded away. The bed of the river in this area is mobile sand. Flood Event The June 2007 flood level was reported as being approximately 0.5 metres above the deck level. The flood is rated as being an average Recurrence Interval of 25 to 30 years. The data for the 2007 flood is set out in Table II. The peak discharge for the 2007 flood was calculated based on the open channel flow using Manning s formula. For flood level (m AHD) Table II. Velocities & Discharges based upon the bed slope of the river Bed Slope of the River (m/m) Total Discharge (m3/sec) Effective Water Way area ( m2) Average Velocity (m/sec)

4 River Bank & Bed Restoration Works for Bridge Pier Protection Bowmans Crossing & Luskintyre Bridges NSW 307 Proposed Restoration Works It was proposed to streamline the left side of the riverbank where Piers 3, 4 and 5 had suffered severe scour. The objective of the re alignment is to provide an embankment with few irregularities and to gently guide the water flow in the required direction. This re-alignment will reduce turbulent flow conditions that increase erosion and scour effects. The channel profile was surveyed between 100m upstream and downstream of the bridge. The following works were proposed. 1. The regrading of the eastern river embankment to a slope of 1 to Construction of Rock Blanket revetment on the eastern intermediate embankment protecting Pier rows 3 and 4. The revetment is basically a blanket or layer of rock to prevent erosion around the piers. 3. Construction of isolated rock blanket around Pier 5. Rock Blanket Design Based upon the above hydraulic data, and the proposed rock blanket slopes of 1 in 5.3 and 1 in 1.33, a D50 rock size of 0.8 m was established. Fig 3 shows the recommended D50 rock size required to protect an embankment for a range of flow velocities. The graph has been based on three other projects where the side slopes of the rock berm or rock blanket were approximately 1vertical (v) to 1.5 horizontal (h). At Bowmans Crossing the slope of the rock blanket is approximately 1v to 4h. It is much more difficult to erode or dislodge rocks from an embankment with side slope of 1 in 4, rather than a steeper side slope of 1 in 1.5. Therefore in the assessment of the required rock size, the effective velocity, for interpretation from the graph, was reduced to 4.05 m/sec. The rock size was determined both on the velocity analysis (Fig 3) and a review of the size of rocks that were not eroded from the site during the 2007 flood event. The rock weight of 0.8 tonnes also corresponds to a 0.8 metre diameter rock. D50 Rock Size The rock diameter D50 represents the size of a rock from a rock sample where the combined weight of all rocks having a larger diameter than the D50, weigh 50% of the total sample weight.

5 308 Richard Lane, Phanta Khamphounvong and Sisira Mabotuwana Fig. 3 Assessment of D50 Rock Size Note: The above Graph is a basic design tool giving approximate results for relatively small projects. The Graph was prepared by Author 1 based upon the review of other rock embankment works carried out at Blandford [1] via Murrurundi, Singleton [2] and Maitland [3], also in the Hunter Valley. Where larger works are being considered, reference should be made to appropriately experienced waterway design engineers. Rock Blankets Used Main Blanket Piers 3 & 4 Blanket size; approximate plan dimension 31m by 26 m. he extent of the rock blanket was based upon practical considerations. Length 31m; If the sand erodes at the edge of the blanket, the edges of the blanket will collapse until a stable situation is achieved. It is unlikely that a scour hole of more than 3 metres shall occur. This still leaves 5 metres of rock blanket in this direction beyond the piles.

6 River Bank & Bed Restoration Works for Bridge Pier Protection Bowmans Crossing & Luskintyre Bridges NSW 309 Width 26m; On the low side the rock blanket depth is 1.5 metres allowing for a considerable quantity of rock to be lost in a collapsing toe situation without adverse affect on the pile. The top of the blanket was taken beyond the extent of erosion during the 2007 flood event. Pier 5 Isolated Rock blanket; Blanket size 7m by 15m. The isolated rock blanket around the piles of pier 5 was based on similar considerations with the blanket being taken beyond the extent of scour of the 2007 flood event. Blanket Thicknesses The main blanket Toe Section (3 metres wide) thickness = 1.5 metres (Approximately equal to 2*D50 allowing for the inter positioning of the top layer of rocks on the base layer). The double layer of rock was considered to be adequate to allow for any collapsing toe situations the may occur through scouring. Normal Blanket thickness = 1.2 metres ( 1.5*D50) The thickness was based upon other rock embankment works carried out at Murrurundi [1], Singleton [2] and Maitland [3], also in the Hunter Valley. Also upon the practical consideration that if the D50 size is 0.8 metres, some of the delivered rocks are likely to be in the order of 1.0 to 1.2 metres in size. These can be accommodated in the full depth of 1.2 metres The sourcing of rocks of this size and required strength quality is difficult. Care must be taken to ensure the constructed blanket meets the required minimum dimensions. The total quantity of rock placed was approximately 1850 tonnes.

7 310 Richard Lane, Phanta Khamphounvong and Sisira Mabotuwana Geotextile: A heavy duty Class 1 Geotextile similar to Bidim A64 was selected as part of the design and was designated below all of the rock blankets. This is a heavy duty Geotextile and construction experience has shown that if this grade of Geotextile is not used, tears and rips occur when the large rocks are being placed. For further details of the rock blankets refer to Figures 6 and 7. Figure 6 Plan of Constructed Rock Mattresses Figure 7 Drawing of Blanket Sections Project Timing and Funding 1. 1/12/2008; NSW Public Works engaged by RTA to prepare concept sketches 2. 5/2/2009; NSW Public Works, Newcastle Regional Office, prepares and forwards concept sketches to the RTA. 3. 1/6/2009; RTA (Newcastle Office) uses concept sketches to gain competitive Tenders and awards contract /6/2009 Contractor; The JDS Group Pty Ltd completed the work. This project was Funded from the Natural Disaster Relief Assistance Program. The Program is funded by both the Australian Federal Government and the NSW Government. The construction cost was in the order of $160,000 (incl. GST).

8 River Bank & Bed Restoration Works for Bridge Pier Protection Bowmans Crossing & Luskintyre Bridges NSW Fig. 4 Debris on Top of Bridge Deck ; June 2007 Fig. 5 No : 4/8/2009 Rock Blanket around Piers 3 &

9 312 Richard Lane, Phanta Khamphounvong and Sisira Mabotuwana Fig. 6 Plan of Rock Blankets : Bowmans Crossing

10 River Bank & Bed Restoration Works for Bridge Pier Protection Bowmans Crossing & Luskintyre Bridges NSW 313 Section No.2 Cross Section 5 Sheet 8 Sheet 9 Fig. 7 Section for Rock Blankets; Bowmans Crossing

11 314 Richard Lane, Phanta Khamphounvong and Sisira Mabotuwana Luskintyre Bridge : Bridge No 2 This Bridge is on a local road (Luskintyre Road) over the Hunter River and is approx 3.5 kilometres from Lockinvar on the New England Highway and some 50 kilometres downstream of Bowmans Crossing Bridge. This bridge has two major steel truss spans and when constructed in 1901 was one of the largest road bridges in NSW. The Bridge is listed as an Item of state significance under the RTA s heritage and conservation register under Section 170 of the NSW Heritage Act 1977, for its historical, aesthetic and social significance. Erosion at the north western abutment has been occurring over many flood events and the concern was being shown over the structural integrity of the two round steel caissons (pier 10) on this embankment Fig. 8 No ; 25/2/2011: Portion of Luskintyre Bridge with work on the rock berm having commenced.

12 River Bank & Bed Restoration Works for Bridge Pier Protection Bowmans Crossing & Luskintyre Bridges NSW 315 Table III: Bridge Configurations Total Bridge Length 292m Pier Length 15m Number of Span 17 Exposed Pile Length 5m Year Built 1901 Pile Embedment Length Before Flood 10m Pier No. 10 Pile Embedment Length After Flood 7.4m Fig. 9 Erosion that had taken place: June 2007 Hydraulic Data After consideration of water flow velocities associated with river heights of RL 21 to 24 metres an average velocity in the main channel of 2.5 m/sec was adopted for the new embankment design.

13 316 Richard Lane, Phanta Khamphounvong and Sisira Mabotuwana Proposed Solutions The following stabilisation solutions were considered by the RTA. 1. Th RTA requested NSW Public Works (Newcastle Regional Office) to prepare concept sketches for a bank stabilisation solution. Est. $960, In house, the RTA Bridge Design Section worked out a structural solution to reinforce the two main piles on the North Western abutment. Est. $800,000. The RTA chose to implement Solution1 because even if the structural solution (Solution 2) was implemented, some form of bank stabilisation works around the bridge piers would have to take place to prevent further erosion from occurring. If this were not done the timbers piles supporting the timber spans on the landward side of the steel piers would ultimately be undermined. Embankment Stability Analysis and Rock Sizing All embankment stability analysis work was carried out by Dams and Civil, Water Solutions, NSW Public Works. SLOPE/W (Geo Slope International, 2007) computer program was used for the SS (Steady State) and RDD (Rapid Draw Down) computer models to check the pseudo static slope stability for the designed slopes. The computer models calculate Factors of Safety for the embankment failing in the slip circle mode. The Steady State condition simulates the situation when the embankment is inundated with flood waters and the level of the water is in a Steady State. The Rapid Draw condition simulates the situation when the peak of the flood waters have passed and the flood waters are receding. Pore pressures can still be present in the embankment material which reduce the shear strength of the materials and reduce the Factor of Safety against slip circle failure. The following sized rock rip rap was adopted in the design of the rock berm and rock blanket. Rock Berm: Graded rock with D50 = 350mm with minimum thickness 1500mm. Rock Blanket: Graded rock with D50 = 350mm with minimum thickness 750 mm.

14 River Bank & Bed Restoration Works for Bridge Pier Protection Bowmans Crossing & Luskintyre Bridges NSW 317 In making the final decision for the size of this rock recognition was given to the size of the rocks used at Singleton (upstream) and Maitland (downstream) over the past years. Rock Berm. The other important property of the rock berm is the total mass of the berm to assist in the achievement of the required stability factors of safety for the embankment. The cost per tonne of specified rock of D50 = 900 mm is only marginally dearer (5 to 10%) than the smaller rock specified in the design. It was considered prudent to use the larger rock for the rock berm at minimal additional cost and considerably more extensive resistance to erosion. Rock Blanket: Again it was decide to use rock marginally larger and thicker than that specified by Dams and Civil to allow for possible construction abnormalities. The blanket rock was specified as D50 = 500 at a thickness of 900 mm. Design Cross Section and Bank Alignment As part of the early concept designs the proposed bank stabilisation works were based on the philosophy of trying to establish a new embankment alignment which would lead to more streamlined flow patterns for the flood waters passing under the bridge. Therefore the new embankment was designed with a very slightly curved section upstream of the bridge and then a 27 metre transition section back to the embankment. This was in contrast to the almost nodal bumps that are seen around some bridge abutments. Such nodes form intrusions into the flow paths of flood waters which cause turbulent flow that result in erosion and scouring. The final design incorporated; 1. A rock berm with an effective crest width of 6.0 metres (2 metres of this was covered by the sloped embankment). Rock size D50 = 0.9M 2. Toe cut off trench, 1 m deep and 2 metres wide. 3. Sand was transported from an upstream accretion shoal on the opposite side of the river and placed to form the earth embankment. 4. A heavy duty layer of Geotextile similar to Bidim A64 was placed on top of the sand embankment prior to the rock blanket being placed. 5. Full height Rock Blanket 0.9m thick with D50 = 0.5M 6. Sand was then placed in between the rocks of the rock blanket. 7. A layer of topsoil 100 to 200mm thick was then placed above the rock blanket. 8. Horizontal 500 mm wide layers of turf were then placed on a 50 % basis with grass seeds being sown in between the rows of turf.

15 318 Richard Lane, Phanta Khamphounvong and Sisira Mabotuwana A diagrammatic representation of the embankment cross section is shown in Figure 10. Fig. 10. Design Section of Embankment used for Construction

16 River Bank & Bed Restoration Works for Bridge Pier Protection Bowmans Crossing & Luskintyre Bridges NSW 319 Table V: The following quantities of materials were incorporated the works Material Class A rock, Berm Rock (D50 = 900 mm) Class 2A rock. Rock Blanket (D50 = 500 mm) Embankment sand Sand in Blanket Class 1 Geotextile Turf and seed area Quantity 5,529 tonnes 3,745 tonnes 4,560 cu m 1,021 cu m 3,260 Sq m 3,300 Sq m Due to an error in the contract document the rock berm was constructed to a height of RL 9.0 rather than RL 10.0 intended in the design. The main consequences of this change are as follows. 1. The constructed gradient of the embankment is 1 V : 2 H 2. The preferred design had a bank gradient of 1 V: 2.2 H 3. The preferred design with rock berm at RL 10.0 AHD had higher Factors of Safety for the embankment in relation to slip failure. In July/August 2011 NSW Dams & Civil, Water Solutions, re- assessed the stability analysis for the constructed embankment based upon new permeability test results for the sand material used in the embankment construction and a more appropriate shear capacity factor (Ø = 40 degrees) for the berm rock material. The re- assessed factors of safety for the embankment are as follows; Table V: Re- Assessed Factors of Safety August 2011 Stability Condition Actual F of S Required F of S Steady State with Rock Berm at RL Rapid Draw with Rock Berm at RL The re- assessed Factors of Safety for the constructed embankment confirmed that there are no adverse stability issues with the embankment. Design Modifications during the Construction Phase As work progressed on the rock berm at the base of the embankment it became evident that it may be possible to extend the main section of the embankment a

17 320 Richard Lane, Phanta Khamphounvong and Sisira Mabotuwana further 10 metres upstream and therefore the transition section also became straighter and less pronounced. Thus the completed embankment works appear to be a continuation of the river bank and not just another isolated bump on the river bank. The final Contract amount to carry out the work was $680,000. Incl. GST. The Contractor for the works was the JDS Group P/L from Cooma NSW. The restoration works were again funded by the Natural Disaster Relief Assistance program. Outcomes of the Project 1. The completion of the detailed investigation, design and construction in 15 months is an excellent result and would not have occurred without the cooperation and effort on the part of all people involved including the RTA, Landowners, NSW Public Works and the Contractor. 2. In designing concept drawings for future works, where the waterway area permits, embankment slopes of 1v to 2.25h or 1v to 2.5h should be considered. 3. These slopes shall make the construction and maintenance much easier and assist in maintaining turf lawn/ grass ground cover. 4. A final rock berm width of 5.0 metres should be allowed which would give more adequate room for a 25 to 30 tonne excavator to operate. 5. The lower gradient slopes of Point 2 above and the berm width of 5.0 metres shall also assist in more readily attaining the required Factors of Safety for embankment stability. 6. The cost of additional materials for the above recommendations would be minimal in comparison to the gains. References [1] Design of Blandford Bridge Abutment Protection Works, NSW: Author 1 and Dams and Civil, Water Solutions, NSW Public Works: 2003; for RTA (NSW). [2] Design of River Bank restoration works between the two Road Bridges at Singleton, NSW; Author 1and Dams and Civil, Water Solutions, NSW Public Works: 2008 for Dept of Environment and Climate Change (NSW). [3] Design of Maitland Levee Rehabilitation Works, NSW; Patterson Britton and Partners Pty Ltd. 2000; for Dept of Land & Water Conservation (NSW).

Emergency Spillways (Sediment basins)

Emergency Spillways (Sediment basins) Emergency Spillways (Sediment basins) DRAINAGE CONTROL TECHNIQUE Low Gradient Velocity Control Short-Term Steep Gradient Channel Lining Medium-Long Term Outlet Control Soil Treatment Permanent [1] [1]

More information

Welded Mesh Gabions and Mattresses River Protection Design Guide HY-TEN GABION SOLUTIONS Dunstall Hill Trading Estate, Gorsebrook Road,

Welded Mesh Gabions and Mattresses River Protection Design Guide HY-TEN GABION SOLUTIONS Dunstall Hill Trading Estate, Gorsebrook Road, Welded Mesh Gabions and Mattresses River Protection Design Guide HY-TEN GABION SOLUTIONS Dunstall Hill Trading Estate, Gorsebrook Road, Wolverhampton, WV6 0PJ Tel 01902 712200 Fax 01902 714096 e-mail sales@hy-tengabions.com

More information

Index. protection. excavated drop inlet protection (Temporary) 6.50.1 6.51.1. Block and gravel inlet Protection (Temporary) 6.52.1

Index. protection. excavated drop inlet protection (Temporary) 6.50.1 6.51.1. Block and gravel inlet Protection (Temporary) 6.52.1 6 Index inlet protection excavated drop inlet protection (Temporary) 6.50.1 HARDWARE CLOTH AND GRAVEL INLET PROTECTION Block and gravel inlet Protection (Temporary) sod drop inlet protection ROCK DOUGHNUT

More information

Safe & Sound Bridge Terminology

Safe & Sound Bridge Terminology Safe & Sound Bridge Terminology Abutment A retaining wall supporting the ends of a bridge, and, in general, retaining or supporting the approach embankment. Approach The part of the bridge that carries

More information

Outlet stabilization structure

Outlet stabilization structure Overview of Sedimentation and Erosion Control Practices Practice no. 6.41 Outlet stabilization structure Erosion at the outlet of channels, culverts, and other structures is common, and can cause structural

More information

How To Check For Scour At A Bridge

How To Check For Scour At A Bridge Case Studies Bridge Scour Inspection and Repair Edward P. Foltyn, P.E. Senior Hydraulic Engineer ODOT Bridge Unit 2013 PNW Bridge Inspectors Conference April 2013 REFERENCES Stream Stability at Highway

More information

CITY UTILITIES DESIGN STANDARDS MANUAL

CITY UTILITIES DESIGN STANDARDS MANUAL CITY UTILITIES DESIGN STANDARDS MANUAL Book 2 (SW) SW9 June 2015 SW9.01 Purpose This Chapter provides information for the design of open channels for the conveyance of stormwater in the City of Fort Wayne.

More information

BRIDGES ARE relatively expensive but often are

BRIDGES ARE relatively expensive but often are Chapter 10 Bridges Chapter 10 Bridges Bridg Bridges -- usually the best, but most expensive drainage crossing structure. Protect bridges against scour. BRIDGES ARE relatively expensive but often are the

More information

Final. Contact person: Colin Whittemore Aurecon Centre 1 Century City Drive Waterford Precinct, Century City Cape Town, South Africa

Final. Contact person: Colin Whittemore Aurecon Centre 1 Century City Drive Waterford Precinct, Century City Cape Town, South Africa Review Report and Recommendations for the Remediation of Flood Damage at the Berg River Causeway and the Dam Bypass Channel on Portion of Farms 1646 and 1014, Franschhoek Contact person: Colin Whittemore

More information

Emergency repair of Bridge B421

Emergency repair of Bridge B421 Emergency repair of Bridge B421 over the Olifants River after fl ood damage INTRODUCTION AND BACKGROUND Bridge B421 is located on the R555 at km 5.03 on Section 01E between Witbank (now known as emalahleni)

More information

June 2007 CHAPTER 7 - CULVERTS 7.0 CHAPTER 7 - CULVERTS 7.1 GENERAL

June 2007 CHAPTER 7 - CULVERTS 7.0 CHAPTER 7 - CULVERTS 7.1 GENERAL 7.0 7.1 GENERAL For the purpose of this manual, culverts are defined as structures that are completely surrounded by soil and located below the surface of the roadway parallel to the general direction

More information

Watershed Works Manual

Watershed Works Manual National Rural Employment Guarantee Act Watershed Works Manual DRAINAGE LINE TREATMENT: GABION STRUCTURE Baba Amte Centre for People s Empowerment Samaj Pragati Sahayog September 2006 Drainage Line Treatment:

More information

Prattsville Berm Removal Project. 1.0 Project Location

Prattsville Berm Removal Project. 1.0 Project Location Prattsville Berm Removal Project 1.0 Project Location The project site is located between the New York State Route 23 Bridge over the Schoharie Creek and the Schoharie Reservoir. The restoration plan encompassed

More information

3. Design Procedures. Design Procedures. Introduction

3. Design Procedures. Design Procedures. Introduction Design Procedures 3. Design Procedures Introduction This chapter presents a procedure for the design of natural channels. The chapter primarily focuses on those physical properties of the channel required

More information

Construction Site Inspection Checklist for OHC000004 By making use of some simple Best Management Practices (BMPs) a construction site operator can

Construction Site Inspection Checklist for OHC000004 By making use of some simple Best Management Practices (BMPs) a construction site operator can Construction Site Inspection Checklist for OHC000004 By making use of some simple Best Management Practices (BMPs) a construction site operator can do his or her share to protect Ohio's water resources

More information

Scour and Scour Protection

Scour and Scour Protection Design of Maritime Structures Scour and Scour Protection Steven A. Hughes, PhD, PE Coastal and Hydraulics Laboratory US Army Engineer Research and Development Center Waterways Experiment Station 3909 Halls

More information

CHAPTER 3A Environmental Guidelines for STREAM CROSSING BY ALL-TERRAIN VEHICLES

CHAPTER 3A Environmental Guidelines for STREAM CROSSING BY ALL-TERRAIN VEHICLES GOVERNMENT OF NEWFOUNDLAND AND LABRADOR DEPARTMENT OF ENVIRONMENT AND LABOUR CHAPTER 3A Environmental Guidelines for STREAM CROSSING BY ALL-TERRAIN VEHICLES WATER RESOURCES MANAGEMENT DIVISION Water Investigations

More information

RIPRAP From Massachusetts Erosion and Sediment Control Guidelines for Urban and Suburban Areas http://www.mass.gov/dep/water/laws/policies.

RIPRAP From Massachusetts Erosion and Sediment Control Guidelines for Urban and Suburban Areas http://www.mass.gov/dep/water/laws/policies. RIPRAP From Massachusetts Erosion and Sediment Control Guidelines for Urban and Suburban Areas http://www.mass.gov/dep/water/laws/policies.htm#storm Definition: A permanent, erosion-resistant ground cover

More information

CHALLENGES AND INNOVATIVE SOLUTIONS FOR BRIDGE FOUNDATION REPAIRS

CHALLENGES AND INNOVATIVE SOLUTIONS FOR BRIDGE FOUNDATION REPAIRS CHALLENGES AND INNOVATIVE SOLUTIONS FOR BRIDGE FOUNDATION REPAIRS Drew Monnier 1, P.Eng. (Presenting) Kimberly Yathon 2, B.Sc. CE (Presenting) Ruth Eden 1, M.Sc., P.Eng. Randy Fingas 1, P.Eng. Emile Shehata

More information

Riprap-lined Swale (RS)

Riprap-lined Swale (RS) Riprap-lined Swale (RS) Practice Description A riprap-lined swale is a natural or constructed channel with an erosion-resistant rock lining designed to carry concentrated runoff to a stable outlet. This

More information

Stream Rehabilitation Concepts, Guidelines and Examples. Objectives. Pierre Y. Julien. Three Laws of Stream Restoration

Stream Rehabilitation Concepts, Guidelines and Examples. Objectives. Pierre Y. Julien. Three Laws of Stream Restoration Stream Rehabilitation Concepts, Guidelines and Examples Pierre Y. Julien Wuhan 2005 Objectives Part I - Stream restoration and rehabilitation: 1. Present and discuss important concepts, laws, criteria

More information

Various options are discussed below.these low cost, low impact interventions can also be applied as general erosion control methods.

Various options are discussed below.these low cost, low impact interventions can also be applied as general erosion control methods. Week 10 River Hydraulics Rehabilitating Urban Waterways (From http://hubpages.com/hub/river-bank-erosion-control-methods) See also the resources placed on Moodle. Water channels should be viewed as a resource

More information

Temporary Erosion-Control Measures

Temporary Erosion-Control Measures A Guide to Temporary Erosion-Control Measures for Contractors, Designers and Inspectors June 2001 North Dakota Department of Health Division of Water Quality A Guide to Temporary Erosion-Control Measures

More information

CHAPTER 9 CHANNELS APPENDIX A. Hydraulic Design Equations for Open Channel Flow

CHAPTER 9 CHANNELS APPENDIX A. Hydraulic Design Equations for Open Channel Flow CHAPTER 9 CHANNELS APPENDIX A Hydraulic Design Equations for Open Channel Flow SEPTEMBER 2009 CHAPTER 9 APPENDIX A Hydraulic Design Equations for Open Channel Flow Introduction The Equations presented

More information

Report to INFRASTRUCTURE SERVICES Committee for noting

Report to INFRASTRUCTURE SERVICES Committee for noting 15-377 Subject: Prepared by: Capital Works Programme 2015/16 Tairāwhiti Roads Alexios Kavallaris (Capital Manager - Tairāwhiti Roads) Meeting Date: 22 October 2015 Report to INFRASTRUCTURE SERVICES Committee

More information

City of Shelbyville Site Inspection Checklist

City of Shelbyville Site Inspection Checklist City of Shelbyville Site Inspection Checklist General Information Project Name: KYR10 Permit Number: Date: Project Location: Contractor: Conractor Representative: Inspector's Name: Title: Signature : Weather

More information

Managing Our Water Retention Systems

Managing Our Water Retention Systems Managing Our Water Retention Systems 29th Annual USSD Conference Nashville, Tennessee, April 20-24, 2009 Hosted by Corps of Engineers On the Cover Wolf Creek Dam is on the Cumberland River in South Central

More information

TECHNICAL SPECIFICATION SERIES 8000 PRECAST CONCRETE

TECHNICAL SPECIFICATION SERIES 8000 PRECAST CONCRETE TECHNICAL SPECIFICATION SERIES 8000 PRECAST CONCRETE TECHNICAL SPECIFICATION PART 8000 - PRECAST CONCRETE TABLE OF CONTENTS Item Number Page 8100 PRECAST CONCRETE CONSTRUCTION - GENERAL 8-3 8101 General

More information

Coldwater Heritage Partnership Implementation Grant Final Report Morrison Run Watershed Restoration Project Western Pennsylvania Conservancy Project Summary The goal of the Morrison Run Watershed Restoration

More information

CODE OF PRACTICE - VOLUME TWO - TRAIN SYSTEM [CP2] TRANSADELAIDE INFRASTRUCTURE SERVICES. Issue: 2 Date: 26/09/08 Page: 1 of 21

CODE OF PRACTICE - VOLUME TWO - TRAIN SYSTEM [CP2] TRANSADELAIDE INFRASTRUCTURE SERVICES. Issue: 2 Date: 26/09/08 Page: 1 of 21 Issue: 2 Date: 26/09/08 Page: 1 of 21 TRACK AND CIVIL INFRASTRUCTURE CODE OF PRACTICE VOLUME TWO - TRAIN SYSTEM [CP2] DRAINAGE 2004 No part of this document may be reproduced without prior written consent

More information

How To Write A Watercourse Crossing

How To Write A Watercourse Crossing Code of Practice for Watercourse Crossings Made under the Water Act and the Water (Ministerial) Regulation Consolidated to include amendments in force as of June 24, 2013 Office Consolidation Published

More information

Chapter 3 CULVERTS. Description. Importance to Maintenance & Water Quality. Culvert Profile

Chapter 3 CULVERTS. Description. Importance to Maintenance & Water Quality. Culvert Profile Chapter 3 CULVERTS Description A culvert is a closed conduit used to convey water from one area to another, usually from one side of a road to the other side. Importance to Maintenance & Water Quality

More information

STRUCTURES. 1.1. Excavation and backfill for structures should conform to the topic EXCAVATION AND BACKFILL.

STRUCTURES. 1.1. Excavation and backfill for structures should conform to the topic EXCAVATION AND BACKFILL. STRUCTURES 1. General. Critical structures may impact the integrity of a flood control project in several manners such as the excavation for construction of the structure, the type of foundation, backfill

More information

GEOSYNTHETICS ENGINEERING: IN THEORY AND PRACTICE

GEOSYNTHETICS ENGINEERING: IN THEORY AND PRACTICE GEOSYNTHETICS ENGINEERING: IN THEORY AND PRACTICE Prof. J. N. Mandal Department of civil engineering, IIT Bombay, Powai, Mumbai 400076, India. Tel.022-25767328 email: cejnm@civil.iitb.ac.in Module - 4

More information

Nepean River Bridge. The NSW Government is building a new pedestrian and cyclist bridge over the Nepean River to connect Penrith and Emu Plains.

Nepean River Bridge. The NSW Government is building a new pedestrian and cyclist bridge over the Nepean River to connect Penrith and Emu Plains. Nepean River Bridge May 2016 The NSW Government is building a new pedestrian and cyclist bridge over the Nepean River to connect Penrith and Emu Plains. The new bridge will provide a safe crossing for

More information

Catchment Scale Processes and River Restoration. Dr Jenny Mant Jenny@therrc.co.uk. The River Restoration Centre therrc.co.uk

Catchment Scale Processes and River Restoration. Dr Jenny Mant Jenny@therrc.co.uk. The River Restoration Centre therrc.co.uk Catchment Scale Processes and River Restoration Dr Jenny Mant Jenny@therrc.co.uk The River Restoration Centre therrc.co.uk 3 Main Catchment Elements Hydrology Energy associated with the flow of water affects

More information

A CASE-STUDY OF CUA_DAT CFRD IN VIETNAM

A CASE-STUDY OF CUA_DAT CFRD IN VIETNAM A CASE-STUDY OF CUA_DAT CFRD IN VIETNAM Giang Pham Hong, Michel Hotakhanh, Nga Pham Hong, Hoai Nam Nguyen, Abstract:Dams have been taken an important role in time and surface redistribution of water for

More information

Unit Price Averages Reports

Unit Price Averages Reports Unit Price Averages Reports 12/7/2015 UNIT PRICE AVERAGES REPORT Disclaimer The information provided in the following Unit Price Averages Report is only for the use of Alberta Infrastructure & Transportation

More information

6.0 Results of Risk Analyses

6.0 Results of Risk Analyses 6. Results of Risk Analyses A risk analysis of the optimized embankment designs for the Salton Sea restoration project was conducted jointly by Kleinfelder and representatives from Reclamation. A risk

More information

How To Build A Road Into A Lake In The North Of The Korean Island Of Hongkoon

How To Build A Road Into A Lake In The North Of The Korean Island Of Hongkoon 3D view of intake - looking upstream from the west bank New intake access track forming upstream bund The intake is located at grid ref 204791,888654. The intake screen arrangement is a drop bar type screen

More information

Module 7: Hydraulic Design of Sewers and Storm Water Drains. Lecture 7 : Hydraulic Design of Sewers and Storm Water Drains

Module 7: Hydraulic Design of Sewers and Storm Water Drains. Lecture 7 : Hydraulic Design of Sewers and Storm Water Drains 1 P age Module 7: Hydraulic Design of Sewers and Storm Water Drains Lecture 7 : Hydraulic Design of Sewers and Storm Water Drains 2 P age 7.1 General Consideration Generally, sewers are laid at steeper

More information

Evaluating the Condition of Seawalls/Bulkheads

Evaluating the Condition of Seawalls/Bulkheads Volume 2 Evaluating the Condition of Seawalls/Bulkheads By: Coastal Systems International, Inc. Typical bulkhead under construction Seawalls and bulkheads (walls) provide shoreline stabilization for many

More information

Chaudière Crossing Bridge Rehabilitation

Chaudière Crossing Bridge Rehabilitation Chaudière Crossing Bridge Rehabilitation Douglas K. Lowry P. Eng., Armtec Infrastructure Incorporated David Delicate, P.Eng. Public Works and Government Services Canada (Retired) Prepared for presentation

More information

Evaluation of Open Channel Flow Equations. Introduction :

Evaluation of Open Channel Flow Equations. Introduction : Evaluation of Open Channel Flow Equations Introduction : Most common hydraulic equations for open channels relate the section averaged mean velocity (V) to hydraulic radius (R) and hydraulic gradient (S).

More information

Storm Drain Inlet Protection

Storm Drain Inlet Protection Objectives EC Erosion Control SE Sediment Control TR Tracking Control WE Wind Erosion Control Non-Stormwater NS Management Control Waste Management and WM Materials Pollution Control Legend: Primary Objective

More information

Storm Protection. Storm Protection

Storm Protection. Storm Protection Storm Protection Storm Protection About Skyline Steel A premier steel foundation supplier serving the U.S., Canada, Mexico, the Caribbean, Central America, and Colombia markets, Skyline Steel is a wholly-owned

More information

Tobique Employment & Training

Tobique Employment & Training APPENDICES 3 Tobique Employment & Training Flood Mitigation July 30, 2012 Overview This proposal outlines the work required and budget for flood mitigation measures on Tobique First Nation which is required

More information

EPR Exempt Flood Risk Activities: descriptions and conditions

EPR Exempt Flood Risk Activities: descriptions and conditions EPR Exempt Flood Risk Activities: descriptions and conditions Version 1 April 2016 We are the Environment Agency. We protect and improve the environment. Acting to reduce the impacts of a changing climate

More information

Neversink River East Branch

Neversink River East Branch Neversink River East Branch Management Unit 10 Summary of Post-Flood Recommendations Intervention Level Full restoration of the stream reach including the eroding bank site between Station 38380 and Station

More information

HYDRAULICS. H91.8D/C - Computerized Open Surface Tilting Flow Channel - 10, 12.5, 15 and 20 m long

HYDRAULICS. H91.8D/C - Computerized Open Surface Tilting Flow Channel - 10, 12.5, 15 and 20 m long HYDRAULICS H91.8D/C - Computerized Open Surface Tilting Flow Channel - 10, 12.5, 15 and 20 m long 1. General The series of channels H91.8D has been designed by Didacta Italia to study the hydrodynamic

More information

Guo, James C.Y. (2004). Design of Urban Channel Drop Structure, J. of Flood Hazards News, December,

Guo, James C.Y. (2004). Design of Urban Channel Drop Structure, J. of Flood Hazards News, December, Guo, James C.. (004). esign of Urban Channel rop Structure, J. of Flood azards News, ecember, Guo, James C.., (009) Grade Control for Urban Channel esign, submitted to Elsevier Science, J. of ydro-environmental

More information

Open Channel Flow 2F-2. A. Introduction. B. Definitions. Design Manual Chapter 2 - Stormwater 2F - Open Channel Flow

Open Channel Flow 2F-2. A. Introduction. B. Definitions. Design Manual Chapter 2 - Stormwater 2F - Open Channel Flow Design Manual Chapter 2 - Stormwater 2F - Open Channel Flow 2F-2 Open Channel Flow A. Introduction The beginning of any channel design or modification is to understand the hydraulics of the stream. The

More information

SUSTAINABLE DESIGN FOR THE SOLDIER CREEK LEVEE REPAIR. John Ruhl 1 Seth Laliberty 2 ABSTRACT

SUSTAINABLE DESIGN FOR THE SOLDIER CREEK LEVEE REPAIR. John Ruhl 1 Seth Laliberty 2 ABSTRACT SUSTAINABLE DESIGN FOR THE SOLDIER CREEK LEVEE REPAIR John Ruhl 1 Seth Laliberty 2 ABSTRACT The Soldier Creek Diversion Unit Repair Project represents the latest USACE Kansas City District investment in

More information

The students will be working in and alongside the stream, so safety is a consideration. Suitable sites should have the following characteristics:

The students will be working in and alongside the stream, so safety is a consideration. Suitable sites should have the following characteristics: Measuring Stream Banks: Height and Slope Stream bank heights and slopes are of interest because they yield information relevant to bank erosion and stability. A high, steep bank is likely to be unstable

More information

State of Illinois Department Of Transportation CONSTRUCTION INSPECTOR S CHECKLIST FOR STORM SEWERS

State of Illinois Department Of Transportation CONSTRUCTION INSPECTOR S CHECKLIST FOR STORM SEWERS State of Illinois Department Of Transportation CONSTRUCTION INSPECTOR S CHECKLIST FOR STORM SEWERS While its use is not required, this checklist has been prepared to provide the field inspector a summary

More information

Experiment (13): Flow channel

Experiment (13): Flow channel Introduction: An open channel is a duct in which the liquid flows with a free surface exposed to atmospheric pressure. Along the length of the duct, the pressure at the surface is therefore constant and

More information

SECTION 6A STORM DRAIN DESIGN Mar. 2002 S E C T I O N 6A STORM DRAIN - DESIGN

SECTION 6A STORM DRAIN DESIGN Mar. 2002 S E C T I O N 6A STORM DRAIN - DESIGN S E C T I O N 6A STORM DRAIN - DESIGN 6A.l Scope 6A.2 Storm Water Quantity 6A.3 Storm Drain Hydraulics 6A.4 Depths 6A.5 Locations 6A.6 Curved Storm Drains 6A.7 Manholes 6A.8 Catch basins 6A.9 Storm Drain

More information

Design Charts for Open-Channel Flow HDS 3 August 1961

Design Charts for Open-Channel Flow HDS 3 August 1961 Design Charts for Open-Channel Flow HDS 3 August 1961 Welcome to HDS 3-Design Charts for Open-Channel Flow Table of Contents Preface DISCLAIMER: During the editing of this manual for conversion to an electronic

More information

BRIDGE SCOUR INVESTIGATION: DEVELOPING A SCREENING AND HYDRAULIC VULNERABILITY RATING SYSTEM FOR BRIDGES B.HERON 1 & C.BOWE 2

BRIDGE SCOUR INVESTIGATION: DEVELOPING A SCREENING AND HYDRAULIC VULNERABILITY RATING SYSTEM FOR BRIDGES B.HERON 1 & C.BOWE 2 BRIDGE SCOUR INVESTIGATION: DEVELOPING A SCREENING AND HYDRAULIC VULNERABILITY RATING SYSTEM FOR BRIDGES B.HERON 1 & C.BOWE 2 1 O Connor Sutton Cronin Consulting Engineers, Dublin, Ireland 2 Iarnród Éireann,

More information

Vermont Economic Resiliency Initiative (VERI) Community Forum Barre City & Barre Town

Vermont Economic Resiliency Initiative (VERI) Community Forum Barre City & Barre Town Vermont Economic Resiliency Initiative (VERI) Community Forum Barre City & Barre Town MEETING NOTES April 16, 2015 6:00 8:00 PM VERI Project Overview With funding from the US Economic Development Administration

More information

APPLICATION PROCEDURES FOR PLACEMENT OF UNDERGROUND WATER AND SEWER PIPELINES IN THE VICINITY OF TRANSPORTATION FACILITIES UNDER THE

APPLICATION PROCEDURES FOR PLACEMENT OF UNDERGROUND WATER AND SEWER PIPELINES IN THE VICINITY OF TRANSPORTATION FACILITIES UNDER THE APPLICATION PROCEDURES FOR PLACEMENT OF UNDERGROUND WATER AND SEWER PIPELINES IN THE VICINITY OF TRANSPORTATION FACILITIES UNDER THE JURISDICTION OF ALBERTA TRANSPORTATION 1.0 Application Procedures 2.0

More information

Section 2100-Trenching and Tunneling

Section 2100-Trenching and Tunneling SECTION 5200 - STORM SEWER PART 1 - GENERAL 1.01 SCOPE: This Section covers installation of storm sewer mains and culverts. Topics include permits and fees, trench widths, pipe laying, bedding, initial

More information

EN 1997-1 Eurocode 7. Section 10 Hydraulic Failure Section 11 Overall Stability Section 12 Embankments. Trevor L.L. Orr Trinity College Dublin Ireland

EN 1997-1 Eurocode 7. Section 10 Hydraulic Failure Section 11 Overall Stability Section 12 Embankments. Trevor L.L. Orr Trinity College Dublin Ireland EN 1997 1: Sections 10, 11 and 12 Your logo Brussels, 18-20 February 2008 Dissemination of information workshop 1 EN 1997-1 Eurocode 7 Section 10 Hydraulic Failure Section 11 Overall Stability Section

More information

Settlement of Precast Culverts Under High Fills; The Influence of Construction Sequence and Structural Effects of Longitudinal Strains

Settlement of Precast Culverts Under High Fills; The Influence of Construction Sequence and Structural Effects of Longitudinal Strains Settlement of Precast Culverts Under High Fills; The Influence of Construction Sequence and Structural Effects of Longitudinal Strains Doug Jenkins 1, Chris Lawson 2 1 Interactive Design Services, 2 Reinforced

More information

US Army Corps of Engineers BUILDING STRONG

US Army Corps of Engineers BUILDING STRONG Fort Worth District Public Meeting 20 August 2013 US Army Corps of Engineers Lewisville Dam - Authorization Authorized by the River and Harbor Act, approved 2 March 1945 (Public Law 14, 79th Congress,

More information

SE-10 STORM DRAIN INLET PROTECTION. Objectives

SE-10 STORM DRAIN INLET PROTECTION. Objectives STORM DRAIN INLET PROTECTION SE-10 Objectives Erosion Control - EC Sediment Control - SE Tracking Control - TC Wind Erosion Control - WE Non-Storm Water Management - NS Waste and Materials Management -

More information

Lower Breton Sound Sediment Diversion Conceptual Engineering Design Presentation

Lower Breton Sound Sediment Diversion Conceptual Engineering Design Presentation EXPERT PANEL ON DIVERSION PLANNING AND IMPLEMENTATION Lower Breton Sound Sediment Diversion Conceptual Engineering Design Presentation February 12, 2015 Topics I. Introduction II. Geotechnical Study III.

More information

SECTION 5. Sediment Control Measures

SECTION 5. Sediment Control Measures SECTION 5 Sediment Control Measures 60. STORM DRAIN INLET PROTECTION When Runoff from earth change activities will discharge to a catch basin or storm drain inlet. A newly constructed catch basin or storm

More information

Moving Small Mountains Vesuvius Dam Rehab

Moving Small Mountains Vesuvius Dam Rehab Moving Small Mountains Vesuvius Dam Rehab Susan L. Peterson, P.E., regional dams engineer, Eastern Region, Bedford, IN Note: The following article, Moving Small Mountains Vesuvius Dam Rehab, by Sue Peterson,

More information

UNDER DRAINAGE AND FILTER DESIGN

UNDER DRAINAGE AND FILTER DESIGN UNDER DRAINAGE AND FILTER DESIGN Tailings and HLP Workshop 28 April to 1 May 2010 INTRODUCTION The internal drainage is of crucial importance to the reliability and safety of a tailings dam throughout

More information

Design of Bridges. Introduction. 3 rd to 4 th July 2012. Lecture for SPIN Training at the University of Dar es Salaam

Design of Bridges. Introduction. 3 rd to 4 th July 2012. Lecture for SPIN Training at the University of Dar es Salaam Design of Bridges Introduction 3 rd to 4 th July 2012 1 FUNCTION OF A BRIDGE To connect two communities which are separated by streams, river, valley, or gorge, etc. 2 EVOLUTION OF BRIDGES 1. Log Bridge

More information

Numerical Analysis of the Moving Formwork Bracket Stress during Construction of a Curved Continuous Box Girder Bridge with Variable Width

Numerical Analysis of the Moving Formwork Bracket Stress during Construction of a Curved Continuous Box Girder Bridge with Variable Width Modern Applied Science; Vol. 9, No. 6; 2015 ISSN 1913-1844 E-ISSN 1913-1852 Published by Canadian Center of Science and Education Numerical Analysis of the Moving Formwork Bracket Stress during Construction

More information

Engineering Geological Asset Management for Large Dams. Yasuhito SASAKI (1)

Engineering Geological Asset Management for Large Dams. Yasuhito SASAKI (1) Engineering Geological Asset Management for Large Dams Yasuhito SASAKI (1) (1) Geology Research Team, Public Works Research Institute, Japan E-mail:ya-sasa@pwri.go.jp Abstract Comprehensive inspection

More information

Land Disturbance, Erosion Control and Stormwater Management Checklist. Walworth County Land Conservation Department

Land Disturbance, Erosion Control and Stormwater Management Checklist. Walworth County Land Conservation Department Land Disturbance, Erosion Control and Stormwater Management Checklist Walworth County Land Conservation Department The following checklist is designed to assist the applicant in complying with the Walworth

More information

2.0 BASIC CONCEPTS OF OPEN CHANNEL FLOW MEASUREMENT

2.0 BASIC CONCEPTS OF OPEN CHANNEL FLOW MEASUREMENT 2.0 BASIC CONCEPTS OF OPEN CHANNEL FLOW MEASUREMENT Open channel flow is defined as flow in any channel where the liquid flows with a free surface. Open channel flow is not under pressure; gravity is the

More information

DESIGN GUIDELINES FOR EARTH RETENTION

DESIGN GUIDELINES FOR EARTH RETENTION DESIGN GUIDELINES FOR EARTH RETENTION Strata Systems, Inc. 380 Dahlonega Rd., Suite 200 Cumming, GA 30040 USA www.geogrid.com TABLE OF CONTENTS MECHANICS OF RETAINING WALLS... 3 THE STRATAWEB SOLUTION...4

More information

MIKE 21 FLOW MODEL HINTS AND RECOMMENDATIONS IN APPLICATIONS WITH SIGNIFICANT FLOODING AND DRYING

MIKE 21 FLOW MODEL HINTS AND RECOMMENDATIONS IN APPLICATIONS WITH SIGNIFICANT FLOODING AND DRYING 1 MIKE 21 FLOW MODEL HINTS AND RECOMMENDATIONS IN APPLICATIONS WITH SIGNIFICANT FLOODING AND DRYING This note is intended as a general guideline to setting up a standard MIKE 21 model for applications

More information

How To Retaining Wall Guide

How To Retaining Wall Guide How To Retaining Wall Guide Before you start: Consents and Engineering Building Consent Retaining walls over 1.5m high will require a building consent from the Local Body Council. Walls that carry extra

More information

BMP-7. A sediment filter or an excavated impounding area around a storm drain drop inlet or curb inlet.

BMP-7. A sediment filter or an excavated impounding area around a storm drain drop inlet or curb inlet. BMP-7 BMP: STORM DRAIN INLET PROTECTION Definition A sediment filter or an excavated impounding area around a storm drain drop inlet or curb inlet. To prevent sediment from entering storm drainage systems

More information

5.0 OVERVIEW OF FLOOD DAMAGE REDUCTION MEASURES

5.0 OVERVIEW OF FLOOD DAMAGE REDUCTION MEASURES 5.0 OVERVIEW OF FLOOD DAMAGE REDUCTION MEASURES Flood damage reduction consists of two basic techniques structural and non-structural. Structural methods modify the flood and take the flood away from people

More information

Minimizes sediment and debris from entering storm drains that lead to waterways and watercourses.

Minimizes sediment and debris from entering storm drains that lead to waterways and watercourses. 4.5-p DRAIN INLET PROTECTION Alternative Names: DI protection, Drop Inlet Protection DESCRIPTION Storm drain inlet (DI) protection slows and ponds stormwater, and filters sediment and debris before it

More information

EMERGENCY HOME PROTECTION. Homeowner's Guide for Emergency Flood Control. Contents INTRODUCTION

EMERGENCY HOME PROTECTION. Homeowner's Guide for Emergency Flood Control. Contents INTRODUCTION EMERGENCY HOME PROTECTION Homeowner's Guide for Emergency Flood Control Contents Discussion or Section Page Number Introduction 3 Potential Flooding Periods 4 General Rules and Control Aids 5,6 Sandbags

More information

Open channel flow Basic principle

Open channel flow Basic principle Open channel flow Basic principle INTRODUCTION Flow in rivers, irrigation canals, drainage ditches and aqueducts are some examples for open channel flow. These flows occur with a free surface and the pressure

More information

NUMERICAL ANALYSIS OF SEEPAGE THROUGH EMBANKMENT DAMS (CASE STUDY: KOCHARY DAM, GOLPAYEGAN)

NUMERICAL ANALYSIS OF SEEPAGE THROUGH EMBANKMENT DAMS (CASE STUDY: KOCHARY DAM, GOLPAYEGAN) NUMERICAL ANALYSIS OF SEEPAGE THROUGH EMBANKMENT DAMS (CASE STUDY: KOCHARY DAM, GOLPAYEGAN) *Reza Naghmehkhan Dahande 1 and Ahmad Taheri 2 1 Department of Civil Engineering-Water Management, Islamic Azad

More information

Small Dam Hazard Assessment Inventory

Small Dam Hazard Assessment Inventory Small Dam Hazard Assessment Inventory What would happen if your dam were to fail? This is a question that most dam owners hope they will never have to answer. However it is a question you, as a responsible

More information

PROJECT COST ESTIMATE ASSUMPTIONS AND EXCLUSIONS

PROJECT COST ESTIMATE ASSUMPTIONS AND EXCLUSIONS C PROJECT ESTIMATE ASSUMPTIONS AND EXCLUSIONS In support of the alternatives development process, preliminary cost estimates were prepared for each of the three Candidate Build Alternatives. The cost estimates

More information

APPLICATION PROCEDURES FOR PLACEMENT OF UNDERGROUND TELECOMMUNICATION CABLES IN THE VICINITY OF TRANSPORTATION FACILITIES

APPLICATION PROCEDURES FOR PLACEMENT OF UNDERGROUND TELECOMMUNICATION CABLES IN THE VICINITY OF TRANSPORTATION FACILITIES APPLICATION PROCEDURES FOR PLACEMENT OF UNDERGROUND TELECOMMUNICATION CABLES IN THE VICINITY OF TRANSPORTATION FACILITIES UNDER THE JURISDICTION OF ALBERTA TRANSPORTATION 1.0 Application Procedures 2.0

More information

Department of Civil Engineering Senior Design Project Fall 2013. Final Report The University of Toledo Ottawa River Restoration

Department of Civil Engineering Senior Design Project Fall 2013. Final Report The University of Toledo Ottawa River Restoration Department of Civil Engineering Senior Design Project Fall 2013 Final Report The University of Toledo Ottawa River Restoration Submitted To: Patrick Lawrence, Ph.D, Professor and Chair, Department of Geography

More information

Aging sewer pipes buried in the Bow River bed, from the foot of Muskrat Street to Glen Avenue must be replaced A raised crossing pipes crossing over

Aging sewer pipes buried in the Bow River bed, from the foot of Muskrat Street to Glen Avenue must be replaced A raised crossing pipes crossing over ewer utility crossing pedestrian bridge Aging sewer pipes buried in the Bow River bed, from the foot of Muskrat Street to Glen Avenue must be replaced A raised crossing pipes crossing over the river at

More information

CHAPTER 2 HYDRAULICS OF SEWERS

CHAPTER 2 HYDRAULICS OF SEWERS CHAPTER 2 HYDRAULICS OF SEWERS SANITARY SEWERS The hydraulic design procedure for sewers requires: 1. Determination of Sewer System Type 2. Determination of Design Flow 3. Selection of Pipe Size 4. Determination

More information

Elevating Your House. Introduction CHAPTER 5

Elevating Your House. Introduction CHAPTER 5 CHAPTER 5 Elevating Your House Introduction One of the most common retrofitting methods is elevating a house to a required or desired Flood Protection Elevation (FPE). When a house is properly elevated,

More information

Table 4.9 Storm Drain Inlet Protetion Applicable for

Table 4.9 Storm Drain Inlet Protetion Applicable for BMP C220: Storm Drain Inlet Protection Purpose To prevent coarse sediment from entering drainage systems prior to permanent stabilization of the disturbed area. Conditions of Use Type of Inlet Protection

More information

APPENDIX C INLETS. The application and types of storm drainage inlets are presented in detail in this Appendix.

APPENDIX C INLETS. The application and types of storm drainage inlets are presented in detail in this Appendix. Storm Drainage 13-C-1 APPENDIX C INLETS 1.0 Introduction The application and types of storm drainage inlets are presented in detail in this Appendix. 2.0 Inlet Locations Inlets are required at locations

More information

How to build raised beds page

How to build raised beds page This leaflet has information to help you if you want to build a raised bed yourself or if you need information to give to a professional contractor. This information should be read in conjunction with

More information

Architectural Processing and Inspections for Home Mortgage Insurance

Architectural Processing and Inspections for Home Mortgage Insurance Page 1 of 5 [Text Only] Architectural Processing and Inspections for Home Mortgage Insurance Directive Number: 4145.1 SITE GRADING AND DRAINAGE GUIDELINES Construction complaints and structural defect

More information

The Manitoba Water Services Board SECTION 022180 Standard Construction Specifications PIPE EXCAVATION, BEDDING AND BACKFILL Page 1 of 11

The Manitoba Water Services Board SECTION 022180 Standard Construction Specifications PIPE EXCAVATION, BEDDING AND BACKFILL Page 1 of 11 Page 1 of 11 Part 1 General 1.1 DESCRIPTION OF WORK.1 The work described herein shall consist of the excavation of trenches (or excavation of tunnels); the supply and placing of bedding and backfill materials;

More information

SECTION 5: SANITARY SEWER SYSTEM DESIGN

SECTION 5: SANITARY SEWER SYSTEM DESIGN SECTION 5: SANITARY SEWER SYSTEM DESIGN 5.01 GENERAL Sanitary sewer improvements shall be designed to serve the ultimate level of City development as defined in the General Plan and the Wastewater Facilities

More information

SUSTAINABLE URBAN DRAINAGE SYSTEMS

SUSTAINABLE URBAN DRAINAGE SYSTEMS overflow can lead into a permeable conveyance system to increase further the benefit and reduce the need for pipe systems. Pollutant removal rates have been shown to be high, with some pollutants being

More information

Geotechnical Building Works (GBW) Submission Requirements

Geotechnical Building Works (GBW) Submission Requirements Building Control (Amendment) Act 2012 and Regulations 2012: Geotechnical Building Works (GBW) Submission Requirements Building Engineering Group Building and Construction Authority May 2015 Content : 1.

More information

Report on. Wind Resistance of Signs supported by. Glass Fiber Reinforced Concrete (GFRC) Pillars

Report on. Wind Resistance of Signs supported by. Glass Fiber Reinforced Concrete (GFRC) Pillars Report on Wind Resistance of Signs supported by Glass Fiber Reinforced Concrete (GFRC) Pillars Prepared for US Sign and Fabrication Corporation January, 2006 SUMMARY This study found the attachment of

More information