Specifications for Asbestos Abatement

Size: px
Start display at page:

Download "Specifications for Asbestos Abatement"

Transcription

1 Specifications for Asbestos Abatement Virginia Department of Health Henry/Martinsville Health Department 295 Commonwealth Boulevard Martinsville, Virginia Prepared for City of Martinsville, Virginia 300 Fishel Street Martinsville, Virginia Prepared by: Diversified Environmental Services, Inc. PO Box 1365 (24402) 1219 B Stoneburner Street Staunton, Virginia Patrick A. DiFlorio, President DES Project # May 2014 DIVERSIFIED ENVIRONMENTAL SERVICES, INC. Patrick A. DiFlorio, Virginia Asbestos Project Designer #

2 ASBESTOS ABATEMENT 1.General 1.1 This section describes detailed requirements and procedures in order to successfully comply with all federal, state, and local laws, regulations, ordinances and rules, as they pertain to the abatement, storage, and disposal of asbestos containing materials within the Commonwealth of Virginia. 2.Contractor Qualification 2.1 Only contractor s who maintain current licensure from the Virginia Department of Professional and Occupational Regulation as a Commonwealth of Virginia Asbestos Abatement Contractor, and can document at least a minimum of three (3) years experience in performing similar projects in size and scope, are to be considered as qualified to perform the work described in this section. 3. Scope of Work- 3.1 The subject property and description is: Virginia Department of Health Henry/Martinsville Health Department 295 Commonwealth Boulevard Martinsville, Virginia The work includes the removal and disposal of non-friable asbestos containing materials. The Contractor shall furnish all labor, materials, equipment, and insurance required for the removal and disposal of asbestos containing materials in accordance with the regulations of the responsible agency, the EPA, and OSHA. 3.2 The work includes, but is not necessarily limited to the following: Removal and disposal of asbestos containing floor tile and mastic, and adjacent cove base moldings from the original portion of the building. Approximately 4000 square feet The contractor is advised to field verify these quantities. DES and the City of Martinsville is not responsible for verifying quantities. The health department must remain open for clients on a daily basis during normal working hours. Monday thru Friday 8:00am 5:00pm. All work must be performed during off hours and on weekends. It is anticipated that the abatement will be performed on weekends and replacement materials will be installed in the evenings after hours. The abatement areas are: CLASS II ABATEMENT (PER OSHA ) 9 x 9 floor tile and associated mastic in the following areas of the Health Department building: Area #1- The small corridor and rooms including the Storage Room, Old Dental Offices, waiting room, Approximately 500 SF

3 Area #2- The Reception Area and the Restroom at the Main Entrance Approximately 1700 SF Area #3- The main Clerical Area, Fiscal Office, Eligibility Office, and the Supplies Room Approximately 1100 SF Area #4- The Administration area corridors, Nurse Supervisor Office, Break Room, Nurse Manager Office Approximately 640 SF The Contractor is responsible for determining all locations and quantities of ACM s. 3.3 All work will be performed in strict accordance with, but not limited to, EPA 40 CFR 61 Subpart A & B - National Emission Standards for Hazardous Air Pollutants (NESHAP), Title 29 Code of Federal Regulations, Section Occupational Safety and Health Administration, US Department of Labor, the Virginia Occupational Safety and Health Standards for Industry, Department of Labor and Industry-Construction. 4. Work Schedule All work should be performed by June 30, Completion of work could be a considering factor in the selection of this firm. Give details as to when you can start this project and complete it. 5. Definitions- Amended water means water to which a surfactant (wetting agent) has been added to increase the ability of the liquid to penetrate ACM. Asbestos includes chrysotile, amosite, crocidolite, tremolite asbestos, anthrophyllite asbestos, actinolite asbestos, and any of these minerals that has been chemically treated and/or altered. Asbestos-containing material (ACM) means any material containing more than one percent (1%) asbestos. Class I asbestos work means the activities involving the removal of TSI and surfacing ACM and PACM. Class II asbestos work means activities involving the removal of ACM which is not thermal system insulation or surfacing material. This includes, but is not limited to, the removal of asbestos-containing wallboard, floor tile and sheeting, roofing and siding shingles, and construction mastics. Class III asbestos work means repair and maintenance operations, where ACM, including TSI and surfacing ACM and PACM, is likely to be disturbed. Clean room means an uncontaminated room having facilities for the storage of employees street clothes and uncontaminated material and equipment. Competent person means, in addition to the definition in 29 CFR (F), one who is capable of identifying existing asbestos hazards in the workplace and selecting the appropriate control strategy for asbestos exposure, who has the authority to take prompt corrective measures to eliminate them, as specified in 29 CFR (F): in addition for class I and class II work who is specially trained in a training course which meets the criteria of EPA s Model Accreditation Plan (40 CFR 763) for supervisor, or its equivalent and, for class III and Class IV work, who is trained in a manner consistent with EPA requirements for training of local education agency maintenance and custodial staff as set forth at 40 CFR (a)(2).

4 Critical barrier means one or more layers of plastic sealed over all openings into a work area or any other similarly placed physical barrier sufficient to prevent airborne asbestos in a work area from migrating to an adjacent area. Decontamination area means an enclosed area adjacent and connected to the regulated area and consisting of an equipment room, shower area, and clean room, which is used for the decontamination of workers, materials, and equipment that are contaminated with asbestos. Demolition means the wrecking or taking out of any load-supporting structural member and any related razing, removing, or stripping of asbestos products. Disturbance means activities that disrupt the matrix of ACM or PACM, crumble or pulverize ACM or PACM, or generate visible debris from ACM or PACM. Disturbance includes cutting away small amounts of ACM or PACM, no greater than the amount which can be contained in one standard sized glovebag or waste bag In order to access a building component. In no event shall the amount of ACM or PACM so disturbed exceed that which can be contained in one glovebag of waste bag which shall not exceed 60 inches in length and width. Employee exposure means that exposure to airborne asbestos that would occur if the employee were not using respiratory protective equipment. Equipment room (change room) means a contaminated room located within a decontamination area that is supplied with impermeable bags or containers for the disposal of contaminated protective clothing and equipment. Fiber means a particulate form of asbestos, 5 micrometers or longer, with a length-to-diameter ratio of at least 3 to 1. Glovebag means not more than a 60 x 60 inch impervious plastic bag-like enclosure affixed around an asbestos-containing material, with glove-like appendages through which material and tools may be handled. High-efficiency particulate air (HEPA) filter means a filter capable of trapping and retaining at least percent of all mono-dispersed particles of 0.3 micrometers in diameter. Homogeneous area means an area of surfacing material or thermal system insulation that is uniform in color and texture. Industrial hygienist means a professional qualified by education, training, and experience to anticipate, recognize, evaluate, and develop controls for occupational health hazards. Intact means that the ACM has not crumbled, been pulverized, or otherwise deteriorated so that the asbestos is no longer likely to be bound with its matrix. Negative Initial Exposure Assessment means a demonstration by the employer, that employee exposure during an operation is expected to be consistently below the Permissible Exposure Limit (PEL). PACM means presumed asbestos containing material. Presumed Asbestos Containing Material means thermal system insulation and surfacing material found in buildings constructed no later than The designation of a material as PACM may be rebutted by the building owner or employer by having the material tested pursuant to the requirements of AHERA (40 CFR Part 763), which the results of these test will demonstrate that the material does not contain asbestos. Project Designer means a person who has successfully completed the training requirements for an abatement project designer established by 40 U.S.C. Sec (g). Regulated area means: an are established by the employer to demarcate areas where Class I,II,III asbestos work is conducted, and any adjoining area where debris and waste from such asbestos work

5 accumulate; and a work area within which airborne concentrations of asbestos, exceed or there is a reasonable possibility they may exceed the permissible exposure limit. Removal means all operations where ACM and/or PACM is taken out or stripped from structures or substrates, and includes demolition operations. Surfacing ACM means ACM that is sprayed, troweled-on or otherwise applied to surfaces (such as acoustical plaster on ceilings and fireproofing materials on structural members, or other materials on surfaces for acoustical, fireproofing, and other purposes). Thermal system insulation (TSI/ACM) means ACM applied to pipes, fitting, boilers, breeching, tanks, ducts or other structural components to prevent heat loss or gain. 6. Contractor Submittals- 6.1 The Contractor shall submit to the Owners Representative, the following documentation: 6.2 Contractor license issued by the Virginia Department of Professional and Occupational Regulation (VDPOR). 6.3 Project Supervisor- -Name and current address of project Supervisor. -Current training certificate from an AHERA accredited training facility. -Supervisor license issued by VDPOR. -Current medical clearance issued by a physician certifying that the individual has been cleared to use respiratory protective devices. -Current CPR/First Aid certification -Current fit test documentation per 29 CFR Worker documentation- -Current training certificate from an AHERA accredited training facility. -Asbestos worker licenses issued by VDPOR. -Current medical clearance issued by a physician certifying that the individual has been cleared to use respiratory protective devices. -Current fit test documentation per 29 CFR Copy of Contractor s written Hazard Communication Program (29 CFR ) 6.6 Certification that all employees have been trained per 29 CFR Material Safety Data Sheets 6.8 Copy of Contractor s written Respiratory Protection Program per 29 CFR Site specific respirator selection procedures for Class I and Class II work Copy of Contractor s Safety and Health Program Site specific asbestos abatement plan to include: -Personal protective equipment to be used -The location and description of regulated areas including clean and dirty areas, access tunnels, threestage decontamination unit (clean room, shower room, equipment room, staging areas for load-out of ACM. -Negative Initial Exposure Assessment in accordance with 29 CFR Method of notification of other contractors/employers at the worksite. -Abatement methods to include critical barriers, containment, and other control procedures.

6 -Location of local exhaust equipment (HEPA). -Sequencing of asbestos related work. -Storage and disposal procedures. -Air monitoring procedures (personal, environmental). -Fire and medical emergency response procedures. -Security procedures to be used for all regulated areas. -Lock out / Tag-out procedures for electrical connections Permits and Notifications -Copies of all permits and notifications, if required, shall be obtained by the Contractor and submitted to the owner at least 20 days prior to the commencement of asbestos activities. These will include notification to the Regional Office of the USEPA, the Virginia Department of Labor and Industry / Division of Occupational Safety and Health. -Local building permits issued by the Building Inspector of the locality, for demolition activities, if applicable. -Posting locations for all permits and notifications. -Copies of State and Federal permits for the selected disposal Landfill designating the site as an approved Landfill that accepts asbestos waste Commencement of abatement activities shall not be authorized until the contractor submits all required documentation described in Section Regulated Areas All asbestos work shall be conducted within regulated areas. The regulated areas shall be demarcated to minimize the number of persons within the area and to protect persons outside the area from exposure to airborne asbestos. Access to the regulated area shall be limited to authorized persons. The Contractor shall control access to regulated areas. A log book shall be kept documenting all authorized entry into and out of the regulated area. Personnel authorized to enter the regulated area shall be trained, be cleared by a physician, and don personal protective equipment before entering a regulated area. 7.1 Warning signs and tape Warning signs and barricade tape shall be provided at the boundaries and entrances to the regulated areas. Signs shall be so located as to allow personnel to read and take necessary protective steps required before entering the regulated area. Warning signs shall be conform to 29 CFR 1910 and 29 CFR , displaying the following legend in the lower panel: DANGER ASBESTOS CANCER AND LUNG DISEASE HAZARD AUTHORIZED PERSONNELL ONLY RESPIRATORS AND PROTECTION CLOTHING ARE REQUIRED IN THIS AREA Warning tape shall be red in color, and display an asbestos danger legend. 8. Electrical Requirements 8.1 Provide temporary power sources and equipment per applicable electrical code requirements. All electrical devices shall be protected via ground fault circuit interrupters (GFCI).

7 9. Specific Engineering Controls for Class II asbestos abatement Work 9.1 Negative Pressure Enclosure- Critical Barriers of 6 mil polyethylene film (poly) one layer thick shall be installed on all cracks, voids, fixture devices, mechanical penetrations, etc. Critical barriers shall have double layered polyethylene film on all HVAC devices. A polyethylene splash guard will be installed at a height sufficient to allow for the protection of existing walls and associated remaining base moldings. 9.2 Local exhaust ventilators shall be installed to allow for a minimum of at least Four (4) air changes per hour. Local exhaust units shall be sufficient to maintain a minimum pressure differential of 0.02 inches of water column relative to the adjacent, unsealed areas. Pressure differential shall be continuously monitored 24 hours per day with a manometric recording device. The recording device shall be capable of printing recorded pressure differentials on a paper chart or other media, so as to provide a permanent record. Exhaust flow from the local ventilators shall be vented outside the building. At no time shall the exhaust air be allowed to flow within the building, or be directed through the building ventilation system, unless prior approval has been granted by the owner or the owner s representative. The owner or owner s representative shall be notified immediately if pressure differentials fall below the prescribed minimum. Upon discovery of a pressure differential below the prescribed minimum, all work activities within the containment shall cease until the situation can be corrected. 9.3 Decontamination Unit A Three (3) stage decontamination unit shall be installed directly adjacent, and attached to the negative pressure enclosure. The unit shall have a clean room where workers can don personal protective equipment; a metal shower room capable of supplying both hot and cold potable water equipped with a sanitary drain to allow discharge effluent to collect below the floor level of the shower; and an equipment room to store contaminated equipment and collected containerized ACM. The individual rooms shall be separated by airlocks constructed of opposing polyethylene flaps installed to prevent the migration of airborne asbestos fibers from the negative pressure enclosure through the decontamination unit. 9.4 Where feasible, the contractor shall install a viewing window with an opaque flap on the outside, for work observations by the Industrial Hygienist / Project Monitor. 10. Work Practices for Class II work The ACM shall be thoroughly saturated with amended water. Materials shall be immediately containerized into a woven bag, and then two (2) 6 mil impermeable polyethylene bags, and staged at the equipment room. The bags shall not be overloaded. Woven mesh type bags will not be counted as a layer Each bag of a double-bagged container shall be sealed with duct tape using a goose-neck closure system No gross ACM shall be allowed to remain on the floor between work shifts At the end of the work shift, bags shall pass through the decontamination unit; and then be properly labeled and transported to the disposal container Upon completion of gross removal, fine cleaning procedures shall be implemented using HEPA equipped vacuums and wet wiping techniques Mastic removal procedures must be performed using hand methods. No mastic remover with a flash point lower than 140 F will be allowed at the work site.

8 11. Respiratory Protection 11.1 Respirator selection shall be, at a minimum, in strict accordance with 29 CFR Class II work If submittal data of the negative exposure assessment (NEA) confirms exposure levels during a similar operation remained consistently below the PEL, the contractor shall provide Half-faced negative pressure respirators equipped with high efficiency filters. 12. Protective Clothing 12.1 Provide workers with sufficient sets of protective full-body clothing, including overalls, headgear, gloves, and foot coverings. All protective clothing shall remain in the work area until the abatement activities have ended, at which time they shall be disposed of as asbestos waste The contractor shall provide authorized visitors complete sets of disposable protective clothing. 13. Air Monitoring 13.1 Air monitoring shall be conducted both in and outside the work area throughout the duration of abatement activities. Outside monitoring of ambient air will be performed by the Owners Industrial Hygienist / Project Monitor. Work area environmental samples, if applicable, shall be taken on a daily basis by a testing laboratory employed by the Contractor, or by the Contractor s personnel OSHA Required Personal Monitoring Contractor s Personal Monitoring shall in strict accordance with OSHA Standard Samples shall be collected by pumps that maintain NIST calibration that certifies flow rates within an accuracy of plus or minus 5%. Pumps shall be calibrated with an inline representative filter, before and after sample collection Air samples shall be analyzed in accordance with the OSHA Standard , by a competent trained person or laboratory. The results of samples shall be posted outside of the work enclosure as soon as they are made available from the analytical laboratory, but no more than 72 hours after the sample analysis has been received from the lab. Data should include Contractor required 8 hour TWA determinations with a description of work activities representing the collected sample, and results of work area Short Term Excursion Limit (STEL) environmental samples. Sample analysis reports shall show the duration of the collection as well as the flow rate of the sampling pump All costs associated with the Contractor s personal and environmental air monitoring shall be borne by the Contractor Ambient Environmental Air Monitoring The Owner has contracted the services of a Virginia Licensed Project Monitor to perform ambient environmental air sampling outside the work area; and final Clearance sampling for re-occupancy. The Project Monitor shall notify both the Contractor and the Owner immediately if any samples outside the work enclosure exceed 0.01 fibers/cc. Abatement activities shall cease until the situation is corrected. 14. Cleanup and Lockdown 14.1 All bags and equipment shall be removed from the work area via the decontamination unit.

9 14.2 Remove visible accumulations of asbestos material and debris. Wet wipe all surfaces within the work area All critical barriers, HEPA equipped ventilation units, air filtration, and the decontamination unit shall remain in place until final clearance is achieved The Project Monitor will perform a visual inspection of the work area to confirm that the area is free of visible asbestos debris Certification that the area is clean will be issued in writing by the Project Monitor. Once certification has been issued, the Contractor shall apply a fine mist of an approved encapsulation/lockdown agent to all surfaces within the work area. The encapsulation / lockdown agent shall not be allowed to puddle. Sufficient time shall be allowed for the encapsulant to dry prior to Final Clearance Sampling. 15. Final Clearance 15.1 Final air samples will be taken by the Project Monitor. After allowing the encapsulant to dry for at least 24 hours, the Project Monitor shall begin the final air clearance procedure. A Sufficient number of PCM cassettes will be loaded onto calibrated vacuum pumps, and operated for a period of 120 minutes. The cassettes will be collected and placed under Chain Of Custody, mounted for laboratory analysis, and then analyzed. If the final air samples do not meet clearance standards per the NIOSH 7400, PCM protocol (< 0.01 Fibers/ Cubic Centimeter), the Contractor will be responsible for all associated costs of re-cleaning the work area, as well as subsequent sampling and analysis. 16. Disposal 16.1 The storage / transport vehicle shall be lined with two (2) layers of 6 mil poly film. Proper asbestos signage and barrier tape shall demarcate the storage area while the container is onsite. During off hours the container shall be secured via a locking device Storage / Transport containers shall be maintained to allow for maximum storage capacity at the work site The Contractor shall comply with the 40 CFR 61 (Subpart B), the Virginia Department of Waste Management Regulations, local, and regional standards for the transport and disposal of all generated asbestos waste The waste manifest shall be authorized by the Owner or the Owners representative. Copies of the landfill s accepted waste manifest must be sent to the Owner within 30 days of transport to the landfill facility. END OF SECTION

ASBESTOS MANAGEMENT PROGRAM

ASBESTOS MANAGEMENT PROGRAM ASBESTOS MANAGEMENT PROGRAM Prepared By: Triumvirate Environmental Program Approval Developed: August 2011 Updated: June 2015 Associate Vice President of Public Safety & Administrative Services Date Associate

More information

TAMPA ELECTRIC COMPANY ENERGY SUPPLY ASBESTOS AWARENESS PROGRAM

TAMPA ELECTRIC COMPANY ENERGY SUPPLY ASBESTOS AWARENESS PROGRAM ASBESTOS AWARENESS PROGRAM TABLE OF CONTENTS TITLE PAGE # PURPOSE / INTRODUCTION 1 RESPONSIBILITY 2 EMPLOYEE TRAINING AND DOCUMENTATION 2-4 MEDICAL SURVEILLANCE 4 UNPLANNED DISTRUBANCE OF ASBESTOS CONTAINING

More information

Miami University s Asbestos Operations & Maintenance Program Administered by

Miami University s Asbestos Operations & Maintenance Program Administered by Miami University s Asbestos Operations & Maintenance Program Administered by ENVIRONMENTAL SAFETY & RISK MANAGEMENT 529-2829 Table of Contents Purpose 2 Personnel Covered Under the Asbestos Mangement Plan

More information

ASBESTOS MANAGEMENT PROGRAM

ASBESTOS MANAGEMENT PROGRAM ASBESTOS MANAGEMENT PROGRAM September 2015 Asbestos Management Program Table of Contents I. Purpose II. III. IV. Definitions Identification of Asbestos Asbestos Sampling V. Notification and Labeling VI.

More information

ASBESTOS IN ROOFING SYSTEMS WORK PRACTICES AND DISPOSAL IN ASSOCIATION WITH ROOFING PROJECTS

ASBESTOS IN ROOFING SYSTEMS WORK PRACTICES AND DISPOSAL IN ASSOCIATION WITH ROOFING PROJECTS ASBESTOS IN ROOFING SYSTEMS WORK PRACTICES AND DISPOSAL IN ASSOCIATION WITH ROOFING PROJECTS 1.0 GENERAL 1.1 SUMMARY A. The following procedures apply to the project manual and drawings for asbestos in

More information

NDSU TABLE OF CONTENTS

NDSU TABLE OF CONTENTS NDSU TABLE OF CONTENTS 1.0 INTRODUCTION 2.0 DEFINITIONS AND DESCRIPTIONS 3.0 OPERATIONS AND MAINTENANCE PROCEDURES FOR ACM 4.0 FIBER RELEASE EPISODES 5.0 DEMOLITION INFORMATION 6.0 REMARKS 1.0 INTRODUCTION

More information

ASBESTOS MANAGEMENT INTRODUCTION

ASBESTOS MANAGEMENT INTRODUCTION SECTION: II. General Hygiene/ Safety Chapter: 7. Asbestos Management Revision Date: 12/05/2013 Review Date: ASBESTOS MANAGEMENT INTRODUCTION PURPOSE This policy has been developed to ensure that hazardous

More information

Asbestos in the Workplace: A Guide to Removal of Friable Asbestos Containing Material

Asbestos in the Workplace: A Guide to Removal of Friable Asbestos Containing Material Asbestos in the Workplace: A Guide to Removal of Friable Asbestos Containing Material Revised November 21, 2013 Application Code of Practice Where asbestos is present or believed to be present in a workplace

More information

Asbestos Abatement Work Plan for the Carter Carburetor Superfund Site

Asbestos Abatement Work Plan for the Carter Carburetor Superfund Site for the Prepared for: ACF Industries LLC 101 Clark Street St. Charles, Missouri 63301 Prepared by: AMEC Environment & Infrastructure, Inc. 15933 Clayton Road, Suite 215 Ballwin, Missouri 63011 Project

More information

Characteristics/Applications

Characteristics/Applications Facilities Operations and Development Environmental Health & Safety 1314 Kinnear Rd. Columbus, Ohio 43212 Phone (614) 292-1284 Fax (614) 292-6404 http://fod.osu.edu The Ohio State University Asbestos Management

More information

Asbestos Operations and Maintenance Program. San José State University

Asbestos Operations and Maintenance Program. San José State University San José State University One Washington Square San José, California Facilities Development and Operations Department July 25, 2012 1) Purpose and Scope The purpose of the Asbestos Operations and Maintenance

More information

North Carolina State University. Asbestos Management Plan

North Carolina State University. Asbestos Management Plan North Carolina State University 1.0 Introduction Purpose The purpose of this plan is to establish the polices and procedures to be used at North Carolina State University (NCSU) in the management of building

More information

The Richard Stockton University ASBESTOS MANAGEMENT PLAN

The Richard Stockton University ASBESTOS MANAGEMENT PLAN The Richard Stockton University ASBESTOS MANAGEMENT PLAN January 2015 Asbestos Management Plan Table of Contents I. Introduction II. III. IV. Definitions Identification of Asbestos Notification and Labeling

More information

Standards for Asbestos Abatement

Standards for Asbestos Abatement 19a-332a-1. Definitions Standards for Asbestos Abatement 19a-332a-1. Definitions The following definitions shall apply for the purpose of Section 19a-332a-1 to Section 19a-332a- 16 inclusive. (a) "Adequately

More information

LEGAL REVIEW & UPDATE

LEGAL REVIEW & UPDATE LEGAL REVIEW & UPDATE There are lots of laws and regulations designed to protect workers, the general public, and the environment. However, not everyone follows the laws. Many people deliberately break

More information

UNOFFICIAL. 1. Owner: Delaware Department of Transportation (DelDOT) WEBSITE

UNOFFICIAL. 1. Owner: Delaware Department of Transportation (DelDOT) WEBSITE SECTION 01013 - SUMMARY OF THE WORK - ASBESTOS ABATEMENT PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other

More information

ALBERT EINSTEIN COLLEGE of MEDICINE of YESHIVA UNIVERSITY. MANAGING ASBESTOS at EINSTEIN. Prepared by: Department of Environmental Health and Safety

ALBERT EINSTEIN COLLEGE of MEDICINE of YESHIVA UNIVERSITY. MANAGING ASBESTOS at EINSTEIN. Prepared by: Department of Environmental Health and Safety ALBERT EINSTEIN COLLEGE of MEDICINE of YESHIVA UNIVERSITY Prepared by: Department of Environmental Health and Safety Revised: August, 2013 ALBERT EINSTEIN COLLEGE of MEDICINE of YESHIVA UNIVERSITY DEPARTMETN

More information

CONTROL METHODS. There are five ways to control the release of asbestos fibers:

CONTROL METHODS. There are five ways to control the release of asbestos fibers: Control Methods CONTROL METHODS When asbestos containing materials are found in a building, the owner must decide which method or methods will be used to deal with the asbestos. The decision will be based

More information

Asbestos Inspection Project Procedure

Asbestos Inspection Project Procedure EOSMS 402 Date: 01/13/2014 Page 1 of 6 1) Purpose This document is intended to specify the scope of services required of Asbestos Contractor in asbestos inspection projects at Kennesaw State University

More information

ASBESTOS CONTAINING MATERIALS OPERATIONS & MAINTENANCE PLAN 2015

ASBESTOS CONTAINING MATERIALS OPERATIONS & MAINTENANCE PLAN 2015 ASBESTOS CONTAINING MATERIALS OPERATIONS & MAINTENANCE PLAN 2015 Prepared For: (School Name) PREPARED BY: DIOCESE OF JOLIET ENVIRONMENTAL OFFICE FOR ANY ENVIRONMENTAL RELATED EMERGENCY CONTACT: RICHARD

More information

SECTION 02 8213 ASBESTOS ABATEMENT

SECTION 02 8213 ASBESTOS ABATEMENT PART 1 GENERAL 1.01 RELATED DOCUMENTS A. Drawings and general provisions of Contract, including General and Supplementary Conditions and Division 1 specification sections shall apply to work of this section.

More information

Building Owners Responsibilities for Asbestos

Building Owners Responsibilities for Asbestos Building Owners Responsibilities for Asbestos August 2012 Minnesota Department of Labor and Industry Occupational Safety and Health Division This material can be provided to you in a different format (Braille,

More information

Asbestos Abatement Management Program. Facilities Operations and Development Environmental Health & Safety

Asbestos Abatement Management Program. Facilities Operations and Development Environmental Health & Safety Asbestos Abatement Management Program Facilities Operations and Development Environmental Health & Safety November 7, 2012 INTRODUCTIONS David Kos (EHS) Director of Environmental Affairs David Kehl (EHS)

More information

UI Procedures for Asbestos Management

UI Procedures for Asbestos Management UI Procedures for Asbestos Management The University of Iowa Rev.12/12/2012 These procedures apply to employees and contractors involving the identification, work on, removal, or repair of asbestos-containing

More information

ASBESTOS MANAGEMENT PLAN

ASBESTOS MANAGEMENT PLAN ASBESTOS MANAGEMENT PLAN SAN JOSE STATE UNIVERSITY Environmental Health & Occupational Safety Asbestos Management Plan 1.0 Introduction 2.0 Policy 3.0 Responsibilities 4.0 Contract Administration 5.0 In-House

More information

British Columbia Institute of Technology. BCIT Safety Manual ASBESTOS MANAGEMENT

British Columbia Institute of Technology. BCIT Safety Manual ASBESTOS MANAGEMENT BCIT Safety Manual Contents 1. Purpose... 3 2. Definitions... 3 2.1 Asbestos... 3 2.2 Asbestos Containing Material (ACM)... 3 2.3 Friable Material... 3 2.4 Low Risk Work Activity... 3 2.5 Moderate Risk

More information

ASBESTOS OPERATIONS AND MAINTENANCE PLAN

ASBESTOS OPERATIONS AND MAINTENANCE PLAN UNIVERSITY OF FLORIDA ASBESTOS OPERATIONS AND MAINTENANCE PLAN Administered by: Environmental Health and Safety Building 179 PO Box 112190 Gainesville, Florida 32611 Introduction The following document

More information

Questions & Answers (Q & A) Regarding Asbestos Treatment with the Fire Suppression and Renovation Project

Questions & Answers (Q & A) Regarding Asbestos Treatment with the Fire Suppression and Renovation Project Questions & Answers (Q & A) Regarding Asbestos Treatment with the Fire Suppression and Renovation Project The Watergate Community is currently in the process with the fire suppression and interior renovations

More information

Wellesley College Asbestos Management Program

Wellesley College Asbestos Management Program Wellesley College Asbestos Management Program Table of Contents Page Policy 2 Impacts of Asbestos Containing Materials (ACM)... 3 Compliance... 3 Objectives... 4 Operational Controls Standard Operating

More information

ADVANCED ENVIRONMENTAL ANALYSIS, INC. 25694 NELSON ROAD HEMPSTEAD, TEXAS 77445

ADVANCED ENVIRONMENTAL ANALYSIS, INC. 25694 NELSON ROAD HEMPSTEAD, TEXAS 77445 ADVANCED ENVIRONMENTAL ANALYSIS, INC. 25694 NELSON ROAD HEMPSTEAD, TEXAS 77445 August 3, 2010 PROJECT SPECIFICATIONS In accordance with the Texas Department of State Health Services Regulation 295.34,

More information

University of Pittsburgh Safety Manual. EH&S Guideline Number: 01-007 ASBESTOS

University of Pittsburgh Safety Manual. EH&S Guideline Number: 01-007 ASBESTOS Page 1 of 5 The inhalation of asbestos fibers in excess amounts can lead to chronic lung disease. Our knowledge of these health effects comes from studies of workers exposed routinely to high concentrations

More information

Asbestos Management Program and Procedures. Northern Illinois University

Asbestos Management Program and Procedures. Northern Illinois University Asbestos Management Program and Procedures Northern Illinois University Department of Environmental Health and Safety 8/12/2013 INTRODUCTION Contents INTRODUCTION... 2 PURPOSE... 6 DEFINITIONS... 8 GENERAL

More information

Asbestos Management POLICY

Asbestos Management POLICY Asbestos Management POLICY All Asbestos Containment Material (ACM) removal activities shall comply with applicable federal, state, and local regulations. Areas of responsibility of Facilities Management

More information

DIVISION 248 ASBESTOS REQUIREMENTS. Asbestos Emission Standards and Procedural Requirements 340-248-0250. Asbestos Abatement Project Exemptions

DIVISION 248 ASBESTOS REQUIREMENTS. Asbestos Emission Standards and Procedural Requirements 340-248-0250. Asbestos Abatement Project Exemptions DIVISION 248 ASBESTOS REQUIREMENTS Asbestos Emission Standards and Procedural Requirements 340-248-0250 Asbestos Abatement Project Exemptions (1) Any person who conducts or provides for the conduct of

More information

PROCEDURE 31 - Asbestos Safety. Table of Contents

PROCEDURE 31 - Asbestos Safety. Table of Contents PROCEDURE 31 - Asbestos Safety Table of Contents Page Synopsis... 31-ii Asbestos Safety Checklist... 31-iii 31 ASBESTOS SAFETY... 31-1 31.1 Purpose and Scope... 31-1 31.2 Definitions... 31-1 31.3 Procedure...

More information

ASBESTOS and LEAD-BASED PAINT INVESTIGATION TOWN OF ST. PAUL WILLIS BUILDING ST. PAUL, VIRGINIA

ASBESTOS and LEAD-BASED PAINT INVESTIGATION TOWN OF ST. PAUL WILLIS BUILDING ST. PAUL, VIRGINIA ASBESTOS and LEAD-BASED PAINT INVESTIGATION TOWN OF ST. PAUL WILLIS BUILDING ST. PAUL, VIRGINIA May 22, 2013 Robert R. Jones, Ph.D., REM, AHERA Asbestos Inspector, 5/22/13 Signature Date Asbestos Virginia

More information

ASBESTOS MANAGEMENT PROGRAM RISK MANAGEMENT AND SAFETY 2014 Page 1

ASBESTOS MANAGEMENT PROGRAM RISK MANAGEMENT AND SAFETY 2014 Page 1 ASBESTOSS MANAGEMENT PROGRAM RISK MANAGEMENT AND SAFETY 2014 1 TABLE OF CONTENTS 1.0 INTRODUCTION 4 1.1 Policy 4 1.2 Purpose 4 1.3 Scope and Application 4 2.0 EMERGENCY CONTACT INFORMATION 4 2.1 Asbestos

More information

CITY OF BOSTON DEPARTMENT OF HEALTH AND HOSPITALS ASBESTOS REGULATIONS

CITY OF BOSTON DEPARTMENT OF HEALTH AND HOSPITALS ASBESTOS REGULATIONS Section 1.01 Authority, Purpose and Scope 1.02 Definitions 1.03 General Requirements 1.04 Reserved 1.06 Reserved 1.07 Reserved 1.08 Reserved 1.09 Reserved 1.10 Reserved 1.11 Record Keeping 1.12 Permit

More information

Asbestos Management Plan

Asbestos Management Plan Asbestos Management Plan Contents Contact Information...3 Purpose...3 Introduction...3 Sample List of Asbestos Containing Materials...3 Definitions...4 Applicable Regulations...7 Responsibilities...8 University

More information

ASBESTOS AWARENESS IN THE WORKPLACE. This easy-to-use Leader s Guide is provided to assist in conducting a successful presentation.

ASBESTOS AWARENESS IN THE WORKPLACE. This easy-to-use Leader s Guide is provided to assist in conducting a successful presentation. ASBESTOS AWARENESS IN THE WORKPLACE This easy-to-use Leader s Guide is provided to assist in conducting a successful presentation. Featured are: INTRODUCTION: A brief description of the program and the

More information

ASBESTOS CONTROL PLAN

ASBESTOS CONTROL PLAN ASBESTOS CONTROL PLAN POLICY It is the long term plan of Emily Carr University to have an asbestos free workplace. In the interim, The University plans to manage asbestos hazards based on prioritization

More information

ASBESTOS. CSEA / Local 1000 AFSCME / AFL-CIO. 143 Washington Avenue, Albany, New York 12210. Danny Donohue, President

ASBESTOS. CSEA / Local 1000 AFSCME / AFL-CIO. 143 Washington Avenue, Albany, New York 12210. Danny Donohue, President S A F E T Y & H E A L T H ASBESTOS QUESTIONS AND ANSWERS FOR BUILDING OCCUPANTS CSEA / Local 1000 AFSCME / AFL-CIO 143 Washington Avenue, Albany, New York 12210 Danny Donohue, President : CSEA OCCUPATIONAL

More information

TECHNICAL ABATEMENT SPECIFICATIONS FOR THE REMOVAL OF ASBESTOS-CONTAINING MATERIALS FROM THE POWER HOUSE BUILDING

TECHNICAL ABATEMENT SPECIFICATIONS FOR THE REMOVAL OF ASBESTOS-CONTAINING MATERIALS FROM THE POWER HOUSE BUILDING PN 0241.006 August 2007 TECHNICAL ABATEMENT SPECIFICATIONS FOR THE REMOVAL OF ASBESTOS-CONTAINING MATERIALS FROM THE POWER HOUSE BUILDING Prepared for: City of Cincinnati Metropolitan Sewer District 1600

More information

Vermont Regulations for Asbestos Control

Vermont Regulations for Asbestos Control Vermont Regulations for Asbestos Control V.S.A. Title 18, Chapter 26 Effective February 1987; Amended November 1995 Vermont Department of Health 1 08 Cherry Street, Box 70 Burlington, VT 05402 Agency of

More information

Washington University Asbestos Operations and Maintenance Plan

Washington University Asbestos Operations and Maintenance Plan 1. Purpose Washington University Asbestos Operations and Maintenance Plan 1.1. The purpose of this Asbestos Operations and Maintenance (O&M) Plan is to minimize the potential for exposure to airborne asbestos

More information

EVERYONE'S RESPONSIBILITY

EVERYONE'S RESPONSIBILITY EVERYONE'S RESPONSIBILITY Guidelines for an Asbestos Operations and Maintenance Program February 2007 Guidelines for an Asbestos Operations and Maintenance Program Workplace Safety & Health Division 200

More information

Asbestos Standard for the Construction Industry. OSHA 3096 2002 (Revised)

Asbestos Standard for the Construction Industry. OSHA 3096 2002 (Revised) Asbestos Standard for the Construction Industry OSHA 3096 2002 (Revised) This informational booklet provides a generic, non-exhaustive overview of a particular topic related to OSHA standards. It does

More information

DESERT RESEARCH INSTITUTE MOLD ASSESSMENT AND REMEDIATEION PROCEDURE

DESERT RESEARCH INSTITUTE MOLD ASSESSMENT AND REMEDIATEION PROCEDURE 1.0 Introduction DESERT RESEARCH INSTITUTE This Desert Research Institute (DRI) Mold Assessment and Remediation Procedure was established to assure that consistent and uniform information is provided to

More information

asbestos management SECTION 21 SECTION CONTENTS ADDITIONAL READING Asbestos Management / Page1 / SECTION 21 TULANE UNIVERSITY

asbestos management SECTION 21 SECTION CONTENTS ADDITIONAL READING Asbestos Management / Page1 / SECTION 21 TULANE UNIVERSITY SECTION 21 asbestos management TULANE UNIVERSITY ENVIRONMENTAL HEALTH AND SAFETY POLICIES AND PROCEDURES MANUAL REVISION DATE: 9/1/03 Return to Table of Contents, EH&S Policies & Procedures Manual SECTION

More information

ASBESTOS OPERATIONS & MAINTENANCE PROGRAM

ASBESTOS OPERATIONS & MAINTENANCE PROGRAM ASBESTOS OPERATIONS & MAINTENANCE PROGRAM Pursuant to Asbestos standards OSHA: 29CFR1926.1101 Construction; & 1910.1001 General Industry; EPA: 40CFR763.92 Training; & 763.120 Asbestos worker protection

More information

Syracuse University s Guidelines for Work Involving Materials Containing Trace Asbestos (Asbestos at a Concentration Less than 1%)

Syracuse University s Guidelines for Work Involving Materials Containing Trace Asbestos (Asbestos at a Concentration Less than 1%) Syracuse University s Guidelines for Work Involving Materials Containing Trace Asbestos (Asbestos at a Concentration Less than 1%) I. Asbestos Survey Requirements Prior to performing any construction,

More information

THE RICHARD STOCKTON UNIVERSITY OF NEW JERSEY ASBESTOS ABATEMENT CONTINGENCY PLAN. February 2015

THE RICHARD STOCKTON UNIVERSITY OF NEW JERSEY ASBESTOS ABATEMENT CONTINGENCY PLAN. February 2015 THE RICHARD STOCKTON UNIVERSITY OF NEW JERSEY ASBESTOS ABATEMENT CONTINGENCY PLAN February 2015 Risk Management and Environmental Health and Safety Office RMEHS ASBESTOS ABATEMENT CONTINGENCY PLAN Table

More information

Click to edit Master title style Maricopa County Asbestos NESHAP Overview. Valerie Brodeur Asbestos NESHAP Inspector

Click to edit Master title style Maricopa County Asbestos NESHAP Overview. Valerie Brodeur Asbestos NESHAP Inspector Click to edit Master title style Maricopa County Asbestos NESHAP Overview Valerie Brodeur Asbestos NESHAP Inspector Click to edit Master title style Some Asbestos Facts Asbestos is a proven human carcinogen

More information

Procedures and Guidelines for Texas A&M University-Kingsville Employees

Procedures and Guidelines for Texas A&M University-Kingsville Employees Procedures and Guidelines for Texas A&M University-Kingsville Employees ENVIRONMENTAL HEALTH & SAFETY OFFICE 1010 RETAMA DRIVE SUPPORT SERVICES BUILDING KINGSVILLE, TX 78363 MARCH 2004 TABLE OF CONTENTS

More information

SUBPART 6 - ASBESTOS SOURCES 2105.60 ASBESTOS ABATEMENT CONTRACTOR LICENSES

SUBPART 6 - ASBESTOS SOURCES 2105.60 ASBESTOS ABATEMENT CONTRACTOR LICENSES SUBPART 6 - ASBESTOS SOURCES 2105.60 ASBESTOS ABATEMENT CONTRACTOR LICENSES a. General. In addition to the accreditation and permit requirements under 2105.61 and 2105.62, respectively, of this Article,

More information

Asbestos Management Program (EHS Program Manager 7.5)

Asbestos Management Program (EHS Program Manager 7.5) Asbestos Management Program (EHS Program Manager 7.5) 1.0 Introduction The Weill Cornell Medicine (WCM) Asbestos Management Program protects the WCM community from the health hazards related to asbestos

More information

ASBESTOS AWARENESS TRAINING

ASBESTOS AWARENESS TRAINING ALBERT EINSTEIN COLLEGE of MEDICINE of YESHIVA UNIVRESITY Substance: Asbestos CAS Registry Number: 1332-21-4 ASBESTOS AWARENESS TRAINING Synonyms: chrysotile, amosite (cummingtonite-grunerite), actinolite,

More information

IWU PHYSICAL PLANT SAFETY PROGRAM. Toxic and Hazardous Substances, Title 29 Code of Federal Regulations (CFR) Part 1910.1001, Subpart Z Asbestos

IWU PHYSICAL PLANT SAFETY PROGRAM. Toxic and Hazardous Substances, Title 29 Code of Federal Regulations (CFR) Part 1910.1001, Subpart Z Asbestos STANDARDS Toxic and Hazardous Substances, Title 29 Code of Federal Regulations (CFR) Part 1910.1001, Subpart Z Asbestos 1. INTRODUCTION IWU has a responsibility to provide a safe environment for students,

More information

CITY OF PHILADELPHIA DEPARTMENT OF PUBLIC HEALTH BOARD OF HEALTH ASBESTOS CONTROL REGULATION

CITY OF PHILADELPHIA DEPARTMENT OF PUBLIC HEALTH BOARD OF HEALTH ASBESTOS CONTROL REGULATION CITY OF PHILADELPHIA DEPARTMENT OF PUBLIC HEALTH BOARD OF HEALTH ASBESTOS CONTROL REGULATION Philadelphia Department of Public Health Air Management Services 321 University Avenue Philadelphia, PA 19104

More information

Addendum 1 Clarifications

Addendum 1 Clarifications Addendum 1 Clarifications Asbestos 1. Clarifications CONTRACTOR is instructed to incorporate standard abatement procedures as mandated by the Federal OSHA Construction Industry Standard; 29 CFR 1926.1101,

More information

Preparing the Work Area

Preparing the Work Area Preparing the Work Area Work Area Preparation Objectives of Work Area Prep Sequence and Methods for Prep Engineering Controls: Negative Pressure Requirements, Equipment and Set-up Purpose of Area Prep

More information

ASBESTOS MANAGEMENT PLAN. Tufts University Medford, Massachusetts

ASBESTOS MANAGEMENT PLAN. Tufts University Medford, Massachusetts ASBESTOS MANAGEMENT PLAN Tufts University Medford, Massachusetts October 2008 Revised 35 New England Business Center Andover, MA 01810 (978) 557-8150 www.woodardcurran.com TABLE OF CONTENTS SECTION PAGE

More information

Final Amendments of 310 CMR 7.15: Asbestos

Final Amendments of 310 CMR 7.15: Asbestos Final Amendments of 310 CMR 7.15: Asbestos Published in the Massachusetts Register on June 20, 2014, Typographical Corrections Published on November 21, 2014 7.00 AIR POLLUTION CONTROL Definitions Revised

More information

EXHIBIT A SCOPE OF SERVICES

EXHIBIT A SCOPE OF SERVICES EXHIBIT A SCOPE OF SERVICES 1.0 INTRODUCTION Asbestos consulting services are required for Item/Segment No. 227775-1, SR-7 (US 441) from Fillmore Street to South of Stirling Road, Hollywood, Broward County,

More information

UNIFIED FACILITIES GUIDE SPECIFICATIONS

UNIFIED FACILITIES GUIDE SPECIFICATIONS USACE / NAVFAC / AFCEC / NASA UFGS-02 82 16.00 20 (August 2011) ----------------------------------- Preparing Activity: NAVFAC Superseding UFGS-02 82 16.00 20 (February 2010) UNIFIED FACILITIES GUIDE SPECIFICATIONS

More information

DEPARTMENT OF LICENSING AND REGULATORY AFFAIRS DIRECTOR'S OFFICE OCCUPATIONAL HEALTH STANDARDS

DEPARTMENT OF LICENSING AND REGULATORY AFFAIRS DIRECTOR'S OFFICE OCCUPATIONAL HEALTH STANDARDS MIOSHA-STD-1407 (07/15) 74 Pages For further information Ph: 517-322-1845 www.michigan.gov/mioshastandards DEPARTMENT OF LICENSING AND REGULATORY AFFAIRS DIRECTOR'S OFFICE OCCUPATIONAL HEALTH STANDARDS

More information

Loss Control TIPS Technical Information Paper Series

Loss Control TIPS Technical Information Paper Series Loss Control TIPS Technical Information Paper Series Innovative Safety and Health Solutions SM Asbestos-Containing Material (ACM) In Buildings The presence of asbestos in buildings, particularly those

More information

Why was asbestos used?

Why was asbestos used? Asbestos Awareness What is Asbestos? Why was asbestos used? Asbestos appealed to manufacturers and builders for a variety of reasons. It is strong yet flexible, and it will not burn. It conducts electricity

More information

Lead Exposure Management Plan

Lead Exposure Management Plan Lead Exposure Management Plan 1.0. Policy CSUF has developed the Lead Exposure Management Plan to reduce occupational and environmental exposure to lead, a potent neurotoxin and carcinogen that causes

More information

ASBESTOS CONTROL PROGRAM

ASBESTOS CONTROL PROGRAM WESTERN UNIVERSITY OCCUPATIONAL HEALTH AND SAFETY ASBESTOS CONTROL PROGRAM Last Update: August 2012 TABLE OF CONTENTS 1.0 INTRODUCTION AND SCOPE... 3 2.0 DEFINITIONS... 4 3.0 HISTORICAL INFORMATION...

More information

Asbestos Management. 2. Introduction. Contents

Asbestos Management. 2. Introduction. Contents Asbestos Management Contents 1. Policy 2. Introduction 3. Scope 4. Definitions 5. Asbestos Inventory and Identification 6. Inspection 7. Access Control 8. Repair and Maintenance of Asbestos-Containing

More information

UNIVERSITY OF ROCHESTER ENVIRONMENTAL HEALTH & SAFETY

UNIVERSITY OF ROCHESTER ENVIRONMENTAL HEALTH & SAFETY Revision No.: 1 Page 1 of 6 I. PURPOSE This procedure establishes the process to conduct asbestos work as it applies to Operation and Maintenance activities, including emergencies. II. PERSONNEL AFFECTED

More information

SPECIFICATION DIVISION 2 NUMBER SECTION DESCRIPTION DIVISION 02 EXISTING CONDITIONS SECTION 028214 ASBESTOS REMEDIATION FLOOR TILE AND MASTIC

SPECIFICATION DIVISION 2 NUMBER SECTION DESCRIPTION DIVISION 02 EXISTING CONDITIONS SECTION 028214 ASBESTOS REMEDIATION FLOOR TILE AND MASTIC ARCHITECTURE, ENGINEERING AND CONSTRUCTION P00000000 0000 DOCUMENTS ARCHITECTURE & ENGINEERING 326 East Hoover, Mail Stop B Ann Arbor, MI 48109-1002 Phone: 734-764-3414 Fax: 734-936-3334 SPECIFICATION

More information

How To Deal With Asbestos

How To Deal With Asbestos SUMMARY OF OSHA ASBESTOS STANDARD 29CFR1926.1101 Contents (a) Scope and Application... 100 (b) Definitions... 100 (c) Permissible Exposure Limits... 100 (d) Multi-employer Worksites... 100 (e) Regulated

More information

34 ASBESTOS. Where is it?

34 ASBESTOS. Where is it? 34 ASBESTOS This chapter provides some brief information about asbestos in construction. If you encounter asbestos on the job, you will need more information. Here are the two main sources of further information

More information

ENVIRONMENTAL OPERATIONS & MAINTENANCE GUIDANCE MANUAL BACKGROUND INFORMATION ON ASBESTOS AND LEAD BASED PAINT

ENVIRONMENTAL OPERATIONS & MAINTENANCE GUIDANCE MANUAL BACKGROUND INFORMATION ON ASBESTOS AND LEAD BASED PAINT ENVIRONMENTAL OPERATIONS & MAINTENANCE GUIDANCE MANUAL I. INTRODUCTION BACKGROUND INFORMATION ON ASBESTOS AND LEAD BASED PAINT Asbestos Asbestos is a naturally occurring fibrous mineral that is mined from

More information

THE UNIVERSITY OF NORTH CAROLINA AT CHAPEL HILL ENVIRONMENT, HEALTH AND SAFETY 1120 Estes Drive Extension Chapel Hill, North Carolina 27599 CB#1650

THE UNIVERSITY OF NORTH CAROLINA AT CHAPEL HILL ENVIRONMENT, HEALTH AND SAFETY 1120 Estes Drive Extension Chapel Hill, North Carolina 27599 CB#1650 THE UNIVERSITY OF NORTH CAROLINA AT CHAPEL HILL ENVIRONMENT, HEALTH AND SAFETY 1120 Estes Drive Extension Chapel Hill, North Carolina 27599 CB#1650 REVISION TWO EFFECTIVE DATE: August 2008 UPDATED: April

More information

Asbestos: Guidelines for Managing Asbestos in Buildings

Asbestos: Guidelines for Managing Asbestos in Buildings Asbestos: Guidelines for Managing Asbestos in Buildings 2015 PLEASE NOTE This publication is not designed to replace the legislation. Please use the original legislation to find out exactly what requirements

More information

BOSTON COLLEGE OFFICE OF ENVIRONMENTAL HEALTH & SAFETY ASBESTOS MANAGEMENT PROGRAM

BOSTON COLLEGE OFFICE OF ENVIRONMENTAL HEALTH & SAFETY ASBESTOS MANAGEMENT PROGRAM BOSTON COLLEGE OFFICE OF ENVIRONMENTAL HEALTH & SAFETY ASBESTOS MANAGEMENT PROGRAM Prepared: May, 1999 Revised: February, 2004 Reviewed: September, 2004 Table of Contents Section Title Page # 1.0 Program

More information

Mark Costello Commissioner of Labor

Mark Costello Commissioner of Labor Oklahoma Department of Labor Oklahoma Asbestos Control Act 40 O.S. 450, et seq. Abatement of Friable Asbestos Materials Rules OAC 380:50 Current as of May 15, 2015 Mark Costello Commissioner of Labor This

More information

Asbestos Management Plan. Keesler AFB

Asbestos Management Plan. Keesler AFB Asbestos Management Plan Keesler AFB February 1995 Table of Contents Executive Summary ES - 1 Regulations R - 1 Definitions D - 1 Acronyms and Abbreviations AD - 1 Purpose Statement PS - 1 1.0 Introduction

More information

100 North Senate Avenue, Indianapolis, IN 46204 Phone: (317) 308-3103 Toll Free: (800) 451-6027

100 North Senate Avenue, Indianapolis, IN 46204 Phone: (317) 308-3103 Toll Free: (800) 451-6027 GUIDANCE OLQ GENERAL ID #003-02-SW INDIANA DEPARTMENT OF ENVIRONMENTAL MANAGEMENT OFFICE OF LAND QUALITY ASBESTOS HANDLING AND DISPOSAL REQUIREMENTS www.idem.in.gov Mitchell E. Daniels, Jr. Thomas W. Easterly

More information

Regulatory Requirements for Asbestos Inspections Prior to Renovation Projects

Regulatory Requirements for Asbestos Inspections Prior to Renovation Projects Regulatory Requirements for Asbestos Inspections Prior to Renovation Projects Subject: Abstract for the 2012 Healthcare Engineering Society of Northern Illinois Mr. Kohon, having attended last yearʼs event

More information

LRI Hidden Valley Acceptance Criteria for Asbestos and Asbestos Contaminate Waste Material

LRI Hidden Valley Acceptance Criteria for Asbestos and Asbestos Contaminate Waste Material LRI Hidden Valley Acceptance Criteria for Asbestos and Asbestos Contaminate Waste Material Asbestos Policy and Criteria Policy: Pierce County Recycling Composting and Disposal (LRI) has established an

More information

How To Care For Asbestos

How To Care For Asbestos Asbestos Awareness Training 1 Please watch video https://www.youtube.com/watch?v=pgzewa0 aafu 2 Asbestos is a Hazard that has No Visible Signs. Known as the silent killer, asbestos is an odorless, colorless

More information

University of Nevada, Reno

University of Nevada, Reno University of Nevada, Reno ASBESTOS PROGRAM Program Contact: John A. Braun, CSP Environmental Health and Safety University of Nevada, Reno Phone: 775-784-6478 ASBESTOS PROGRAM UNIVERSITY OF NEVADA, RENO

More information

Asbestos Building Inspection Report Oak Forest Gun Club 4001 W Fieldcrest Drive Markham, Illinois 60452 Project No.: 1403308

Asbestos Building Inspection Report Oak Forest Gun Club 4001 W Fieldcrest Drive Markham, Illinois 60452 Project No.: 1403308 Asbestos Building Inspection Report Oak Forest Gun Club 4001 W Fieldcrest Drive Markham, Illinois 60452 Project No.: 1403308 557 West Polk Street, Suite 201 Chicago, IL 60607 312.447.1200 p 312.447.0922

More information

Fact Sheet on Asbestos

Fact Sheet on Asbestos Fact Sheet on Asbestos WHAT IS ASBESTOS? Asbestos is a naturally occurring mineral found in certain rock formations, mined from open pit mines. Most of the asbestos used in the United States today comes

More information

ASBESTOS SCIENCE TECHNOLOGIES, INC.

ASBESTOS SCIENCE TECHNOLOGIES, INC. ASBESTOS SCIENCE TECHNOLOGIES, INC. P.O. Box 505 Bangor, CA 95914 Phone (530) 518-0934 Email - astinc17@yahoo.com Report for Lincoln Elementary School 1582 Lincoln Road Yuba City, Ca. 95993 Mold Report

More information

Administrative Procedure. Asbestos

Administrative Procedure. Asbestos Administrative Procedure FT107 Asbestos Board Received: January 30, 2012 Review Date: February 2015 Accountability: 1. Frequency of Reports As needed 2. Severity Threshold As needed (eg. Ministry of Labour

More information

Asbestos Frequently Asked Questions

Asbestos Frequently Asked Questions Asbestos Frequently Asked Questions What is asbestos? Asbestos is a mineral which is mined, processed, and used in many building materials. Since 1988, asbestos has been banned in most US building components;

More information

UBC Plant Operations Asbestos Work Procedures April 2004

UBC Plant Operations Asbestos Work Procedures April 2004 UBC Plant Operations Asbestos Work Procedures April 2004 These Procedures are for use by UBC Plant Operations, Utilities, Housing & Conferences, and IT Services only and are not intended for use by other

More information

(A) All asbestos-containing waste material shall be deposited as soon as is practical by the waste generator at:

(A) All asbestos-containing waste material shall be deposited as soon as is practical by the waste generator at: 3745-20-05 Standard for asbestos waste handling. [Comment: For dates of non-regulatory government publications, publications of recognized organizations and associations, federal rules, and federal statutory

More information

Asbestos Work Permit Procedures

Asbestos Work Permit Procedures These procedures are to be followed by all persons required to perform the following work: Handling, installation or removal of non-friable manufactured products known to contain asbestos provided no sanding,

More information

SECTION 16 ASBESTOS MANAGEMENT

SECTION 16 ASBESTOS MANAGEMENT SECTION 16 ASBESTOS MANAGEMENT 16.1 Asbestos Management Procedure 16.2 Asbestos O&M Procedure Reviewed: October 2008 Revised: February 2003 Date Accepted: April 2002 Draft Date: December 2001 16.1 ASBESTOS

More information

Asbestos Awareness at the University of Toronto

Asbestos Awareness at the University of Toronto Asbestos Awareness at the University of Toronto What is Asbestos? Asbestos is a general term given to a group of naturally occurring mineral silicates that are made up of long thin fibres. These fibrous

More information

CONNECTICUT STATUTES : (4)

CONNECTICUT STATUTES : (4) CONNECTICUT STATUTES : (4) TITLE 20 PROFESSIONAL AND OCCUPATIONAL LICENSING, CERTIFICATION, TITLE PROTECTION AND REGISTRATION. EXAMINING BOARDS CHAPTER 400K INDUSTRIAL HYGIENE AND SAFETY INSPECTOR TITLE

More information

BLR s Safety Training Presentations

BLR s Safety Training Presentations BLR s Safety Training Presentations Asbestos Safety 29 CFR 1910.1001 I. Background for the Trainer: The OSHA Asbestos Standard for general industry, found in 29 CFR 1910.1001, requires information and

More information

CONTAINS ASBESTOS FIBERS

CONTAINS ASBESTOS FIBERS ASBESTOS Rules and Regulations Controlling Exposure DANGER CONTAINS ASBESTOS FIBERS AVOID CREATING DUST CANCER AND LUNG DISEASE HAZARD This booklet was prepared and published by Division of Field and Legal

More information