1 VA Office of Inspector General OFFICE OF AUDITS AND EVALUATIONS Department of Veterans Affairs Audit of the Pharmacy Reengineering Software Development Project December 23,

2 ACRONYMS AND ABBREVIATIONS CIO iehr IOC IT MOCHA OIG OIT OMB PECS PMAS PRE VA Chief Information Officer Integrated Electronic Health Record Initial Operating Capability Information Technology Medication Order Checking Health Care Application Office of Inspector General Office of Information and Technology Office of Management and Budget Pharmacy Enterprise Customization System Project Management Accountability System Pharmacy Reengineering Veterans Affairs To Report Suspected Wrongdoing in VA Programs and Operations: Telephone: (Hotline Information:

3 Report Highlights: Audit of VA s Pharmacy Reengineering Software Development Project Why We Did This Audit In October 2009, the Office of Information and Technology (OIT) restarted the Pharmacy Reengineering (PRE) project under the Project Management Accountability System (PMAS). PRE is critically needed to help address patient safety issues associated with adverse drug events. Accordingly, we evaluated the effectiveness of OIT s management of the PRE project. What We Found Although some progress has been made, OIT has not been effective in keeping the PRE project on target in terms of schedule and cost, as well as the functionality delivered. Deployed PRE functionality has improved patient safety. However, project managers have struggled to deploy PRE increments in a timely manner. Project managers were also unable to provide reliable costs at the increment level. OIT restarted PRE at a time when PMAS had not evolved to provide the oversight needed to ensure project success. As such, PRE management was challenged in keeping the project on track. Consequently, OIT is at an increased risk of not completing PRE on time and within budget. Moreover, the future of Pharmacy Reengineering is uncertain due to potential plans to transfer funding and remaining development to the Integrated Electronic Health Record (iehr) project in FY Stronger accountability over cost, schedule, and scope for the remaining development is needed prior to such a transfer so that iehr is not compromised by the same challenges. What We Recommended We recommended the Executive in Charge and Chief Information Officer (CIO) ensure all of the time used, including the time on the initial operating capability phase, to complete each remaining PRE increment is reported and monitored; ensure adequate oversight and controls, including the planning guidance, staffing, and cost and schedule tracking needed to deliver functionality on time and within budget; and establish a plan for future funding of PRE until iehr is decided. Agency Comments The CIO agreed with our recommendations and provided an acceptable corrective action plan. We will assess OIT s corrective actions in the future. LINDA A. HALLIDAY Assistant Inspector General for Audits and Evaluations i

4 TABLE OF CONTENTS Introduction...1 Results and Recommendations...2 Finding Progress Made, But Challenges Remain in Pharmacy Reengineering Management...2 Recommendations...12 Appendix A Background...16 Appendix B Scope and Methodology...18 Appendix C Status of PRE Increments...19 Appendix D Executive in Charge and Chief Information Officer Comments...23 Appendix E Office of Inspector General Contact and Staff Acknowledgments...28 Appendix F Report Distribution...29 ii

5 INTRODUCTION Objective History of PRE We conducted this audit to determine whether the Office of Information and Technology (OIT) has effectively managed the Pharmacy Reengineering (PRE) software development project to provide pharmacy stakeholders with agreed-upon functionality while meeting cost and schedule goals. VA initially launched PRE in March 2003 with scheduled completion by September 2008 at an estimated cost of approximately $144 million. PRE would replace VA s suite of obsolete pharmacy applications with an improved system designed to meet VA s current and future business needs. Initial PRE increments would address patient safety issues by providing clinical decision support tools to reduce medication errors and adverse drug events. In subsequent increments, PRE would address items such as pharmaceutical inventory management, dispensing, and clinical monitoring. In FY 2009, VA found a significant number of its information technology (IT) development projects were behind schedule or over budget. VA temporarily halted 45 IT development projects, including PRE, for not meeting cost and schedule goals. In June 2009, the Secretary of Veterans Affairs announced that VA would implement the Project Management Accountability System (PMAS) to improve management of its IT development projects and stop the succession of project failures. PRE could not resume development until managers created a project restart plan that met PMAS requirements. In October 2009, the then Assistant Secretary for Information and Technology approved the restart of PRE. The project completion date was scheduled for According to VA s Exhibit 300 submitted to the Office of Management and Budget in September 2009, the total cost of PRE had risen to approximately $164 million. An Exhibit 300 describes the justification, planning, and implementation of an individual IT capital asset included in an agency s IT investment portfolio. It also provides information on resources, timelines, activities, risks, and performance of the investment or IT development project. Other Information The following appendixes provide additional information. Appendix A provides pertinent background information. Appendix B provides details on our scope and methodology. Appendix C provides a status of the increments included in PRE. Appendix D provides VA management comments on a draft of this report. VA Office of Inspector General 1

6 RESULTS AND RECOMMENDATIONS Finding Progress Made, But Challenges Remain in Pharmacy Reengineering Management OIT has not been effective in managing the restarted PRE project to meet mission needs. OIT has deployed limited PRE functionality to date, including automated alerts for clinicians to verify prescriptions before ordering them to help improve patient safety. However, project managers have struggled to deploy PRE functionality to VA s medical facilities in a timely manner. For example, three of the initial PRE increments took from approximately 19 months to 46 months to achieve national deployment and one increment deployment remains incomplete. In addition, project managers have been unable to provide reliable cost information at an increment level for the PRE increments delivered to date. OIT restarted PRE at a time when PMAS had not evolved to a point where it could provide the oversight needed to ensure project success. PRE project management was challenged by a lack of guidance, planning, staffing, schedule tracking, and project status reviews. Because of these project management challenges, OIT is at an increased risk of not completing PRE and providing the agreed-upon patient safety functionality on time and within budget by 2019 as planned. Moreover, the future of overall Pharmacy Reengineering remains uncertain due to potential plans to transfer funding and development of all remaining functionality to the Integrated Electronic Health Record (iehr ) project in FY The PMAS Concept Some PRE Functionality Delivered PRE development and deployment was restarted under PMAS, which was created in June 2009 to stop VA s succession of IT development failures. PMAS represented a major shift from the way VA historically planned and managed IT development projects. The focus under PMAS for IT development projects shifted to incremental development. Under PMAS, the PRE management team made progress developing and implementing some of the planned PRE functionality. For example, the team has deployed the following functionality throughout VA s medical facilities: Non-dosing medication order checks Drug monographs Customized medication order checks In spite of this progress, a great deal of functionality remains to be deployed. VA Office of Inspector General 2

7 Non-Dosing Medication Order Checks VA s clinicians and pharmacists have been receiving PRE alerts on potential harmful drug interactions and duplicate therapies since the first increment of the Medication Order Checking Health Care Application (MOCHA) was deployed in March Medication order checks are system-generated alerts intended to safeguard patients by providing relevant drug-related information for medical personnel to consider before they place orders for patients. Drug interaction alerts help medical personnel identify and prevent harmful interactions between the medications they are ordering and other medications their patients are using. Similarly, duplicate therapy alerts help medical personnel prevent unintentional drug duplication. These alerts warn medical personnel when a patient is already receiving the same exact medication or a different drug in the same therapeutic category. Drug Monographs Customized Medication Order Checks VA clinicians and pharmacists have had access to PRE drug monographs since the first increment of MOCHA was deployed in March The monographs provide drug information pertaining to drug interactions, including descriptions of the interactions, severity levels, potential clinical effects, and recommendations for monitoring and managing the interactions. The monographs serve as additional tools to aid medical personnel in protecting patient safety as they place medication orders for patients. Since May 2011 when the first increment of the Pharmacy Enterprise Customization System (PECS) was deployed, personnel from the Pharmacy Benefits Management Services have been able to customize the drug information maintained by First Databank, a commercial off the shelf database to improve medication order checks. First Databank maintains clinical information on drugs approved by the Food and Drug Administration. PECS allows VA pharmacists to tailor the information to better fit the profiles of veterans receiving healthcare at VA medical facilities. For example, the commercial database currently generates a level 2 alert for the concurrent use of capecitabine and warfarin. The alert states that patients older than 60 are predisposed to this drug interaction, which could cause internal bleeding. Because VA treats a significant number of older patients, Pharmacy Benefits Management Services personnel are in the process of changing this alert from a level 2 to a more severe level 1 alert. Improved Patient Safety With this functionality, PRE has helped VA improve patient safety, which has been a primary focus of the software development project. The total number of adverse drug events reported by VA declined from FY 2010 to FY VA Office of Inspector General 3

8 The table below compares statistics for FY 2010 and FY Table 1 Summary Statistics of VA s Adverse Drug Events Adverse Drug Events FY 2010 FY 2012 Requiring Hospitalizations Requiring Interventions To Prevent Impairments or Disabilities Threatening Lives Resulting in Disabilities 3 0 Resulting in Death 4 3 Total Source: VA OIG based on data from the VA Adverse Drug Event Reporting System In addition, project plans call for additional medication order checks, such as maximum single dosage checks and daily dosage range checks, to be deployed in future incremental deliveries of PRE functionality. Pharmacy Benefits Management Services personnel expect these dosing medication order checks to further improve patient safety. Deployment Delays Pose Schedule Challenges Project managers have not deployed incremental PRE functionality to all VA s medical facilities in a timely manner. According to the PMAS Guide published by OIT in March 2010, IT projects were required to deliver complete and deployable new functionality in cycles of 6 months or less. However, this version of the PMAS Guide was silent concerning how long IT projects could take to actually fully deploy new functionality to all planned sites. Consequently, PRE project managers were only required to deliver deployable functionality to one site within 6 months. Although PRE project managers were able to deliver incremental functionality at one site within 6 months, they have struggled to deploy the incremental functionality to all VA medical facilities. For example: The project team started working on the first increment of PECS in October The team completed deployment of this increment in May 2011 (approximately 19 months later). The project team started working on the first increment of MOCHA in October The team completed deployment of this increment in March 2012 (approximately 29 months later). The project team started working on the second increment of MOCHA in December The team anticipates completing deployment of this VA Office of Inspector General 4

9 increment in February 2014 (more than 4 years after the increment was started). In November 2012, OIT published a new PMAS Guide. The revised guidance now requires all active IT projects to include two increment types: development and implementation. The development increment covers the time needed to produce the software solution. The implementation increment encompasses the time to fully deploy the new capability nationwide. Each of the two increments has a duration of 6 months or less, which essentially allows one year to develop and deploy new incremental functionality. Because three PRE increments took far more than a year to be deployed, they would not have met the new requirements even if they had been in place at the time the increments were underway. Although PRE has delivered functionality resulting in improved patient safety, a great deal of functionality remains to be delivered. As of May 31, 2013, the project team had completed only 20 (30 percent) of 66 total PRE increments. Five other increments were in progress. Given the slow deployment progress to date, PRE faces the risk of not being able to deliver all agreed-upon functionality by the planned project completion date in Unreliable Expenditure Tracking Risks Cost Overruns PRE project managers could not provide accurate information at the increment level on PRE expenditures to date. According to the PMAS Guide, project managers are required to manage their financial resources by increment. However, the PRE Program Manager told us that it is not currently possible to accurately budget and track costs by increment. The Program Manager can only estimate incremental costs because the PRE contracts awarded several years ago were not increment-based; rather, they were written at a program level. The Program Manager further explained that actual costs are not entered into the PMAS Dashboard until they are reconciled to invoices, which could take up to 2 years because the invoices are not associated with specific increments. According to the Program Manager, PRE officials are working to convert the PRE contracts to make them increment-based contracts. However, the conversions are not expected to be complete until February By not capturing accurate budget and expenditure data, the PRE project management team could not accurately report planned versus actual incremental expenditures to allow VA and OIT leaders to assess PRE s progress. The PRE Program Manager estimated that as of May 31, 2013, OIT had spent approximately $47 of the total $53 million budgeted for PRE through Although the limited PRE functionality deployed to date has helped improve patient safety, the project will have spent 100 percent of the funding available for development by the end of calendar year Resources to VA Office of Inspector General 5

10 accomplish development and deployment of the remaining 46 of the total 66 PRE increments remain in question. Inadequate Project Oversight Structure Guidance Lacking PRE development and deployment was restarted at a time when PMAS was still too immature to ensure the oversight and accountability needed for project success. Due to inadequate guidance, planning, staffing, schedule tracking, and independent reviews, OIT management has been ineffective in keeping the PRE project on target in terms of schedule and cost, as well as the functionality delivered. The project management team was required to manage PRE under PMAS before OIT had developed any detailed guidance on PMAS processes, deliverables, management controls, and roles and responsibilities. * When the Secretary of Veterans Affairs announced the implementation of PMAS on June 19, 2009, it was in the preliminary stages of development. At that time, PMAS was primarily the Assistant Secretary for Information and Technology s vision rather than a fully developed methodology for managing IT development projects. As such, OIT launched PMAS before it was well defined, and before it had developed the processes and management controls needed to institute the new methodology. On July 9, 2009, OIT published PMAS Instructions for Project Managers. The intent of this document was to inform project managers of the steps they needed to take to manage paused projects, along with the actions needed to gain approval to restart their projects under PMAS. However, the document fell short in several areas. For example, it did not provide a description of PMAS and did not include information on PMAS processes because OIT had not developed them. It also did not explain how to manage a project under PMAS, how OIT would monitor projects, or the roles and responsibilities of personnel responsible for managing and monitoring projects. The Assistant Secretary for Information and Technology approved the restart of the PRE program in October However, OIT did not publish the PMAS Guide until March 2010 after the project was already well underway. The PMAS Guide provided an overview of PMAS, described the PMAS processes, and defined critical terms such as incremental deliverables. It identified management controls for monitoring performance and ensuring that PMAS procedures were followed. It also explained project management and oversight roles and responsibilities. Inadequate Planning Contributed to Delays Partly due to the lack of guidance, the project management team did not adequately re-plan PRE to fit PMAS prior to the restart of the project. According to the Program Manager, PRE had been in development for several years prior to the inception of PMAS. PRE project managers * Audit of VA s Project Management Accountability System Implementation, Report No , August 29, VA Office of Inspector General 6

11 subsequently tried to deliver the capability that had been in development for several years in the first few PRE increments. Consequently, the increments were too big to deliver in a timely manner. This resulted in the project team spending a substantial amount of time on testing and resolving defects, which led to significant delays in initial operating capability (IOC) testing, and ultimately delayed the start of national deployment. For example, the Test Evaluation Summary for the first increment of MOCHA indicated that Software Quality Assurance personnel tested 465 (98 percent) of 474 functional requirements from February 2009 (testing started before the restart) to March PRE personnel and users submitted a total of 503 remedy tickets for defects during testing of the MOCHA application. A defect is a flaw in a component or a system that can cause a failure to perform a required function. Test analysts categorized the defects according to severity. The analysts categorized 45 of the 503 tickets as critical defects and 150 as major defects. Resolution of 289 (57 percent) of the 503 tickets required modifications, such as revised software code, database, or system configuration. In addition, project managers did not provide enough details to OIT leaders in their restart plan to provide reasonable assurance that the incremental delivery dates could be met. The plan stated that one of the re-planning objectives was to support delivery of initial operating capability of PRE components in manageable increments not to exceed 6 months. It also provided the planned start and initial operating capability dates for the six increments in the restart plan. However, it did not include important details such as how many functional requirements needed to be tested in each increment or dates when each increment would be nationally deployed. Without such details, OIT leaders could not adequately assess whether the plan was reasonable and achievable. Insufficient Staffing Affected Progress Project management staffing was insufficient for considerable periods of time throughout the life of the PRE project. The PMAS Guide states that delivery success depends on resources being available before a project starts each increment. It also states that increments will not start or maintain execution unless they have the required resources. Nevertheless, PRE s component projects went through significant periods of time without having a project manager to lead the projects. For example, the PECS Project Manager position was vacant for 20 months between October 2009 and May Similarly, the MOCHA Project Manager position was vacant for 14 months during that same period. These two projects also experienced significant project manager turnover. PECS has had four different project managers since PRE was restarted while MOCHA has had three. The PRE Program Manager stated that the vacancies and lack of leadership continuity negatively affected the PRE project. For example, vacancies such as these make it more difficult to accomplish tasks such as VA Office of Inspector General 7

12 delivering expected outcomes on time and within budget, resolving risks and issues that could affect project success, and reporting project status data for the PMAS Dashboard. The vacancies and turnover increased the likelihood that the projects would not achieve incremental delivery success. In addition, the Program Manager stated that he relied on contractor personnel to help him manage the projects when the project manager positions were vacant. This type of reliance places the Government at risk of using contractor personnel to perform inherently governmental functions. Inadequate Schedule Tracking PRE project managers reported incomplete schedule information on the PMAS Dashboard. According to OIT officials, at this point in time, project managers were only required to report how long it took to develop the new functionality and enter into the initial operating capability phase for each increment. Thus, project managers were meeting PMAS Dashboard reporting requirements by reporting incomplete information because initially OIT was not concerned with tracking how long it took to move from initial operating capability to national deployment. The PMAS Dashboard was designed to provide VA and OIT senior leaders with real-time visibility of current project status information needed for making timely and informed decisions on IT development projects. Each month, project managers are required to enter updated information on the status of their projects into the PMAS Dashboard. Further, Office of Management and Budget (OMB) Circular A-11, Part 7, Section 300, Planning, Budgeting, Acquisition, and Management of Capital Assets, provides guidance and reporting requirements for major IT development projects. It requires Federal agencies to institute performance measures and management processes for monitoring and comparing planned results against actual performance. OMB expects agencies to achieve, on average, 90 percent of cost, schedule, and performance goals. An agency must review all projects not achieving 90 percent of its goals to determine whether it still needs the projects and what corrective actions, including possible termination, should be taken. In addition, OMB s Information Technology Investment Baseline Management Policy (M-10-27), issued June 28, 2010, requires agencies to measure performance against both the current approved baseline and the original baseline. Despite these requirements, the schedule information maintained on the PMAS Dashboard did not accurately reflect program status because project managers only reported partial schedule information. For example: The PRE Program Manager reported that PRE started the first increment of PECS in October 2009 and successfully completed delivery of the required functionality at one site in March The project team VA Office of Inspector General 8

13 completed national deployment of this version of PECS in May However, the Program Manager did not report the approximately 14 months that it took to complete testing, address defects, and fully deploy this application. As a result, although the Dashboard omitted a major portion of the PECS software development project, it consistently indicated that PRE successfully delivered the first increment of PECS even though it had not yet been deployed. Similarly, the PRE Program Manager reported that PRE started the first increment of MOCHA in October 2009 and successfully completed delivery of the required functionality at one site in June The project team completed national deployment of this version of MOCHA in March Once again, the Program Manager did not report the approximately 21 months that it took to complete testing, address defects, and fully deploy this application. Thus, the PMAS Dashboard also did not capture a significant portion of the MOCHA software development project, but continuously reported that PRE successfully delivered the first increment of MOCHA even though it had not been deployed. When the project management team realized that PRE would not be able to deliver incremental functionality in a timely manner, the team convinced OIT leadership to allow them to divide the PRE increments into sub-increments that would be included in the PMAS Dashboard. OIT approved this change in November Accordingly, the team divided PRE increments into user functional test increments and operational readiness increments. In addition, the PRE Program Manager started reporting the status of these increments on the PMAS Dashboard. As a result, PRE evolved to being composed of 48 increments. This change, however, still did not capture a significant amount of time for each increment that is, the time to progress from testing to full deployment. User functional testing captures the time it takes to complete development and testing with the customer in a test environment. Operational readiness captures the time needed to complete testing at six test sites using test accounts. After these tests are completed, PRE officials test the functionality at the same six test sites using production data in production accounts to complete and exit IOC. After an increment exits IOC, PRE officials deploy the software application to all 128 VA medical facilities. Consequently, the PRE project management team did not account on the PMAS Dashboard for the time needed to move from the end of operational readiness to IOC and then to full deployment. In November 2012, OIT published a new PMAS Guide in part to address this issue. The guide states that projects in the active state include two increment types: development and implementation. Each increment has a duration of 6 months or less. Development includes both software development and achievement of IOC. Implementation includes full delivery of the new VA Office of Inspector General 9

14 capability in a national deployment. To comply with the new guidance, the PRE Program Manager added national deployment increments to the PMAS Dashboard, which brought the total number of PRE increments accounted for on the PMAS Dashboard to 66. The PRE Program Manager was still not reporting the time it took to move PRE increments from IOC to full deployment on the PMAS Dashboard because policies and procedures at the time of our audit did not require reporting for the IOC period. Project Status Reviews Not Performed PRE did not undergo periodic independent oversight reviews that could have helped the project stay on track. Although required by the PMAS Guide, OIT did not perform a PMAS compliance review of the PRE project until May It performed two additional compliance reviews in To determine whether PRE complied with PMAS, the reviews mainly focused on the completeness of required documentation, such as the project charter and the project management plan. The reviews also noted, among other things, that PRE did not have adequate resources for project management and contracts associated with PRE were not negotiated to complement the Agile development methodology. However, the compliance reviews did not address whether the project was on track regarding cost, schedule, and performance. OIT also has not performed independent reviews of the data reported by the PRE Program Manager on the PMAS Dashboard to ensure the data are reliable and complete. In our August 2011 audit report on PMAS, we indicated that the data maintained in the PMAS Dashboard were not reliable. We concluded that OIT would not be able to realize the intended benefits of the PMAS Dashboard until it establishes the procedures and controls needed to ensure the data that project managers report in the PMAS Dashboard are reliable and provide a complete picture of each project s status. We recommended OIT designate personnel and provide them with detailed written procedures for performing periodic independent reviews of the PMAS Dashboard to ensure data reliability and completeness. The then Assistant Secretary for Information and Technology periodically required project managers to provide status briefings to support his review of selected IT development projects. In addition, the Assistant Secretary held red and yellow flag meetings to resolve risks and issues negatively impacting the PRE project. Nonetheless, these types of reviews do not diminish the necessity of performing the periodic independent oversight reviews required by the PMAS Guide. In May 2013, OIT reported that it had taken the following corrective actions to address this issue. The PMAS Business Office has started conducting reviews of the PMAS Dashboard, primarily looking for inaccuracies in PMAS schedule-related data. In addition, OIT has revised the standard operating procedures for conducting PMAS compliance reviews. Specifically, it added procedures for compliance reviews to evaluate project VA Office of Inspector General 10

15 budget and expenditure information compared with percentage of project completion, beginning with the third quarter of FY Conclusion OIT s second attempt to develop and deploy PRE has not been effective. Deployed PRE functionality has helped improve patient safety, which is a step forward. However, project managers have not deployed planned functionality to VA s medical facilities in a timely manner. As of May 31, 2013, the project team had completed only 20 (30 percent) of 66 total PRE increments. Further, project managers have been unable to provide reliable cost information at the increment level for the PRE increments completed to date. The PRE Program Manager estimated that as of May 31, 2013, OIT had spent approximately $47 of the total $53 million budgeted for PRE through At this spending rate, the project will expend 100 percent of the funding available for development by the end of calendar year PRE was restarted under PMAS, a project management discipline created in June 2009 to stop VA s succession of IT development failures. However, OIT restarted PRE at a time when PMAS had not evolved to a point where it could provide the oversight needed to ensure project success. As such, PRE project management was challenged by a lack of guidance, planning, staffing, schedule tracking, and project status reviews. Because of these challenges, OIT is at an increased risk of not completing PRE and providing the agreed-upon functionality on schedule and within budget by 2019 as planned. Thus, future advances in patient safety are susceptible to being behind schedule, which could adversely affect veterans who are prescribed medications. PRE Future Uncertain Due to iehr Plans Going forward, plans for a shared VA and Department of Defense system could eliminate entirely a future need for the PRE project. VA s Exhibit 300 submission for FY 2014 has proposed decreasing total project costs to approximately $53 million by transferring the development of all future pharmacy management functionality to the Integrated Electronic Health Record (iehr) project starting in FY The decision to transfer funding and development of all remaining Pharmacy Reengineering functionality to iehr raises concerns, especially in light of the uncertainty surrounding the interagency project. A lack of commitment to developing the joint iehr system has delayed progress. In March 2011, the Secretaries of VA and Defense first announced they would work together to develop the integrated system, with a goal of implementing it throughout both departments by Pharmacy operations would be included as one major component of iehr. However, in February 2013, the Secretaries announced their Departments were moving away from developing a single integrated electronic health record and would focus instead on modernizing their existing systems. The revised strategy VA Office of Inspector General 11

16 was to achieve interoperability between their separate systems as a means of achieving cost savings and meeting needs more quickly. Ultimately, in April 2013, the Defense Secretary announced that his Department was well behind VA in progress. As such, the Defense Secretary halted all Defense efforts toward an iehr to allow time to gain a better understanding of where his Department was with regard to the initiative. As Defense deliberates, VA continues with efforts to modernize the Veterans Health Information Systems and Technology Architecture its core system for the iehr initiative. Until a final decision is made and a path forward is established for interagency cooperation on iehr, successful completion of the PRE initiative will continue to hang in the balance. Moreover, stronger accountability, particularly over the PRE cost, schedule, and scope for providing the remaining functionality, is needed prior to such a transfer so that iehr is not compromised from the outset by the same challenges as PRE. Recommendations 1. We recommended the Executive in Charge and Chief Information Officer, Office of Information and Technology, ensure all of the time needed to develop and deploy each remaining Pharmacy Reengineering increment, to include the initial operating capability phase, is reported and monitored on the Project Management Accountability System Dashboard. 2. We recommended the Executive in Charge and Chief Information Officer, Office of Information and Technology, develop guidance and a reliable methodology for capturing and reporting planned and actual project costs at the increment level on the Project Management Accountability System Dashboard for the remaining increments of Pharmacy Reengineering software development. 3. We recommended the Executive in Charge and Chief Information Officer, Office of Information and Technology, establish guidance on replanning software development projects that have been paused in sufficient detail to demonstrate that increments of the projects are well thought out and achievable. 4. We recommended the Executive in Charge and Chief Information Officer, Office of Information and Technology, establish controls to ensure information technology projects have sufficient leadership and staff assigned throughout the project life cycle. 5. We recommended the Executive in Charge and Chief Information Officer, Office of Information and Technology, establish plans on how future Pharmacy Reengineering development will be funded until a VA Office of Inspector General 12

17 decision is made regarding transferring this effort to the Integrated Electronic Health Record project. Management Comments and OIG Response The CIO concurred with our recommendations and provided a corrective action plan. We consider OIT s corrective actions acceptable and will assess their effectiveness during our PMAS follow-up audit. The CIO provided technical comments for our consideration. Following is a summary of our response to areas where we disagreed with the positions taken by the CIO. Management Comment: The CIO asserted that many of our findings do not recognize the difference between the time period covered by a PMAS increment and the time period covered by a full software development cycle. He also asserted that some of our measurements and analyses incorrectly attribute time to increments that, in fact, belong to time periods between increments, such as the time from IOC Entry to IOC Exit. Further, the CIO s position is that PRE has been very effective at completing deployment of increments in less than 6 months. The challenges are occurring in the period of IOC, which is before the deployment increment starts. Because current policies and procedures do not include reporting for the IOC period, this time period is not tracked on the PMAS Dashboard. OIG Response: The OIG s analysis in the report reflects the difference between a PMAS increment and a full software development cycle. Regardless, this initiative began in 2003 and was restarted in In spite of development over the past 4 years, planned functionality has not been fully deployed and cost information by increment is unreliable. We state that OIT took approximately 19 and 29 months to deploy 2 of the initial PRE increments. Moreover, OIT will take more than 4 years to deploy another increment that it started in December 2009, assuming it meets a February 2014 deployment deadline. Current PMAS guidance requires development and deployment to be completed in 1 year, with each increment having a duration of 6 months or less. Given that it took OIT more than a year to achieve IOC, the CIO presents an inaccurate project status in asserting that PRE was effective in completing deployment increments within 6 months. IT projects should account for all of the time required to develop and deploy an increment of functionality. The time period to accomplish IOC was not recorded on the PMAS Dashboard. According to the CIO, OIT policies and procedures in existence at the time of our audit did not require reporting the IOC period on the PMAS Dashboard. In our view, it is misleading for OIT and senior VA leadership to review a PMAS Dashboard that omits the IOC phase and indicates a project increment is on track because it delivered functionality to one site, although the increment ultimately took several years to complete national deployment. This was the case for two of the PRE increments we reviewed during our VA Office of Inspector General 13

18 audit. The issue is not whether OIT was in compliance with the policies and procedures current at the time of our audit. Rather, the issue is whether OIT s practices in managing PRE increments were sound. In our view, those project management practices were not effective. Management Comment: The CIO maintains that our findings do not take into account deployment variances caused by the highly customized business processes within the Veterans Health Administration. He also stated that the PMAS definition of success is functionality delivered into the production environment. The CIO said that project increments intentionally do not account for IOC time, as this time varies significantly among increments, depending on the given clinical environment. OIG Response: We recognize and appreciate the complexities associated with deploying incremental functionality within the Veterans Health Administration s varying clinical environments. However, we also believe that if healthcare IT project increments are suitably scoped, OIT should be able to complete development and deployment within the time frames required by PMAS. The PMAS Guide does not make exceptions for Veterans Health Administration initiatives based on their complexity. The CIO stated in the response to our first recommendation that OIT has modified PMAS Dashboard requirements, making it mandatory to track all periods of time within a project including deployment, testing, and IOC. The functionality for the PMAS Dashboard to track all periods of time within a project will be available after implementation in February We believe these corrective actions are steps in the right direction. Management Comment: The CIO asserted that our findings did not take into account that PMAS is an evolving set of policies, practices, and methodologies, which have progressed through lessons learned and best practices over the last 4 years. He stated that many of the OIG findings reflect lapses in data collection and reporting, which were present in previous iterations of PMAS. OIG Response: We agree with the CIO s position that PMAS has evolved considerably over the last 4 years. Our goal was to present a fair and unbiased assessment of PRE at the time of the audit. We objectively took into account changes in PMAS policies, practices, and methodologies over time. In our report we identified problems, but we also pointed out how OIT has taken positive steps to improve PMAS from its inception to its state at the time we completed our audit. There is still room for PMAS improvement and a need for VA to ensure PMAS controls are adequate to oversee VA s development of IT investments, budgeted at $570 million for FY 2012 and $519 million for FY VA Office of Inspector General 14

19 Management Comment: Regarding PRE funding, the CIO asserted that our report does not take into account factors in place to prioritize IT development projects based on governance processes established across VA. OIG Response: We do not believe that the funding prioritization process is relevant to our report findings regarding PRE. At the time of our audit, VA had made a decision to transfer funding and all remaining Pharmacy Reengineering development to the iehr project starting in FY Our concern was that this was not a prudent decision in light of the uncertainty surrounding the iehr project at that time. The CIO s response to our last recommendation, outlining plans to move PRE forward as an independent project instead of as part of iehr, seems to be in line with our concern and may resolve the issue. VA Office of Inspector General 15

20 Appendix A Overview of PMAS Background PMAS was designed as a project management discipline that provided incremental delivery of IT system functionality tested and accepted by customers within established schedule and cost criteria. The PMAS concept requires projects to deliver functional business capability in increments of 6 months or less. Customers certify incremental delivery of functionality on a customer acceptance form. The Assistant Secretary for Information and Technology can pause a project when it fails to deliver functionality as scheduled three times. Once a project has been paused, no further development can occur until it has been evaluated, re-planned, and approved to restart by the Assistant Secretary for Information and Technology. In an effort to make project managers and projects more successful, PMAS relies on a number of organizations and tools such as the PMAS Business Office, integrated project teams, risk management reporting, and the PMAS Dashboard. The PMAS Business Office develops and maintains policy and guidance, monitors the progress of all VA IT projects in PMAS, and oversees PMAS Dashboard reporting. Integrated project teams are a group of multi-disciplinary representatives working collaboratively to plan, manage, and execute all activities required to deliver a project to the field. Members of the team include representatives from organizations, disciplines, and functions that have a stake or responsibility for the success of the project. To help manage risks, anyone associated with a project can raise a yellow flag to identify project environment changes that have the potential to affect project cost, schedule, quality, or scope significantly. Similarly, personnel can raise a red flag to resolve issues or risks that will prevent projects from moving forward and to require senior leadership intervention for resolution to prevent a missed increment deliverable. The PMAS Dashboard was intended for project managers to give senior leaders the visibility they need into project status. Overview of PRE VA planned for PRE to replace all legacy pharmacy applications with a system designed to meet VA s current and future business needs. VA s suite of pharmacy applications created in the 1980s using dated technology had become obsolete and expensive to maintain and enhance. VA expected PRE to provide improved pharmacy operations, efficiencies in workflow and processes for clinicians, and an increased ability to respond to patient safety issues. When VA launched PRE in March 2003, its plans called for initial PRE increments to address critical patient safety issues by providing clinical decision support tools to reduce medication errors and adverse drug events. VA Office of Inspector General 16

21 VA expected the use of these tools to result in lower health care costs and improved care for veterans. Subsequent PRE increments would address items such as pharmaceutical inventory management, order dispensing, and clinical monitoring. In June 2009, the Secretary of Veterans Affairs announced that VA would implement PMAS to improve management of VA s IT development projects and to stop the succession of project failures. VA also temporarily halted PRE because it was not meeting cost and schedule goals. The Assistant Secretary for Information and Technology approved the restart of PRE in October 2009 after the PRE project management team created a new project plan to meet PMAS requirements. VA expected to complete PRE in 2019 at a total cost of approximately $164 million. In FY 2013, VA proposed transferring the development of all remaining pharmacy functionality to iehr beginning in FY 2014, which could decrease total project costs by $111 million to approximately $53 million. Under this proposal, starting in FY 2014, the development of all remaining Pharmacy Reengineering functionality, such as inventory management as well as any remaining patient safety functionality, would be funded and developed under iehr. Key Components PRE is composed of the following components: Pharmacy Enterprise Customization System a system that allows VA pharmacists to improve order checks as a result of customizing drug information maintained by First Databank, a commercial off the shelf database. Medication Order Checking Healthcare Application an application that cross-checks drugs and dosing against the drug database for industry updates. Among other things, it improves drug interaction, duplicate therapy, maximum single dosage, and daily dosage order checks. Pharmacy Product System National and Local drug database management components that replace VA s legacy National Drug File Management System, which used a cumbersome, manual 30- to 60-day process to find and add new drug information. The new system uses automation to find, capture, and store drug information in a national repository. These components of PRE work together to provide VA s clinicians and pharmacists access to accurate and up-to-date medication order checks with the ultimate goal of reducing adverse drug events and improving patient safety. VA Office of Inspector General 17

22 Appendix B Scope and Methodology Scope and Methodology We conducted our audit work from October 2012 through December We focused our efforts on evaluating the actions OIT has taken to plan and manage the active PRE increments PECS, MOCHA, and Pharmacy Product System National from October 2009 when PRE was restarted through April We reviewed Federal laws and regulations related to effective management and oversight of IT development projects. We also reviewed OIT s guidance on IT project management to provide additional criteria for our audit. We interviewed senior OIT officials, program and project managers, and stakeholders to discuss planning, execution, accomplishments, obstacles encountered, and concerns. We evaluated whether OIT was providing incremental deliveries of functionality while staying within cost and schedule goals by analyzing project documentation and the information reported on the PMAS Dashboard. To determine whether PRE was improving patient safety related to drug prescriptions, we obtained and analyzed historical data on adverse drug event incidents and outcomes. Finally, we analyzed OIT s actions to provide effective oversight of the PRE software development effort. Data Reliability Government Standards To test the reliability of computer-processed data, we compared the information provided on the PMAS Dashboard with information included in supporting project documentation. We reviewed the data on the Dashboard to determine whether they provided a valid and reliable representation of project status. We concluded the data were not sufficiently reliable to determine the actual performance of the PRE software development project. As a result, we developed recommendations for improving the reliability of data included in the PMAS Dashboard. Our assessment of internal controls focused on those controls relating to our audit objectives. We conducted this performance audit in accordance with generally accepted government auditing standards. These standards require that we plan and perform the audit to obtain sufficient, appropriate evidence to provide a reasonable basis for our findings and conclusions based on our audit objective. We believe that the evidence obtained provides a reasonable basis for our findings and conclusions based on our audit objective. VA Office of Inspector General 18

VA Office of Inspector General

VA Office of Inspector General xe VA Office of Inspector General OFFICE OF AUDITS AND EVALUATIONS Department of Veterans Affairs Follow-Up Audit of the Information Technology Project Management Accountability System January 22, 2015

More information

VA Office of Inspector General

VA Office of Inspector General VA Office of Inspector General OFFICE OF AUDITS AND EVALUATIONS Department of Veterans Affairs Audit of Office of Information Technology s Strategic Human Capital Management October 29, 2012 11-00324-20

More information

VA Office of Inspector General

VA Office of Inspector General VA Office of Inspector General OFFICE OF AUDITS AND EVALUATIONS Department of Veterans Affairs Review of Alleged System Duplication in the Virtual Office of Acquisition Software Development Project September

More information

Audit of Veterans Health Administration Blood Bank Modernization Project

Audit of Veterans Health Administration Blood Bank Modernization Project Department of Veterans Affairs Office of Inspector General Audit of Veterans Health Administration Blood Bank Modernization Project Report No. 06-03424-70 February 8, 2008 VA Office of Inspector General

More information

VA Office of Inspector General

VA Office of Inspector General VA Office of Inspector General OFFICE OF AUDITS AND EVALUATIONS Department of Veterans Affairs Review of Alleged Lack of Access Controls for the Project Management Accountability System Dashboard May 9,

More information

VA Office of Inspector General

VA Office of Inspector General VA Office of Inspector General OFFICE OF AUDITS AND EVALUATIONS Department of Veterans Affairs Review of Alleged Incomplete Installation of Encryption Software Licenses October 11, 2012 12-01903-04 ACRONYMS

More information

1 Published on September 14, 2015, and January 6, 2016, respectively.

1 Published on September 14, 2015, and January 6, 2016, respectively. STATEMENT OF BRENT ARRONTE DEPUTY ASSISTANT INSPECTOR GENERAL FOR AUDITS AND EVALUATIONS OFFICE OF INSPECTOR GENERAL DEPARTMENT OF VETERANS AFFAIRS BEFORE THE COMMITTEE ON VETERANS AFFAIRS UNITED STATES

More information

Department of Veterans Affairs

Department of Veterans Affairs OFFICE OF AUDITS & EVALUATIONS Department of Veterans Affairs Audit of the FLITE Strategic Asset Management Pilot Project September 14, 2010 09-03861-238 ACRONYMS AND ABBREVIATIONS CoreFLS COTR FLITE IT

More information

Department of Veterans Affairs VA DIRECTIVE 6071

Department of Veterans Affairs VA DIRECTIVE 6071 Department of Veterans Affairs VA DIRECTIVE 6071 Washington, DC 20420 Transmittal Sheet PROJECT MANAGEMENT ACCOUNTABILITY SYSTEM (PMAS) 1. REASON FOR ISSUE. To set forth policies and responsibilities for

More information

THE DEPARTMENT OF JUSTICE S LITIGATION CASE MANAGEMENT SYSTEM. U.S. Department of Justice Office of the Inspector General Audit Division

THE DEPARTMENT OF JUSTICE S LITIGATION CASE MANAGEMENT SYSTEM. U.S. Department of Justice Office of the Inspector General Audit Division THE DEPARTMENT OF JUSTICE S LITIGATION CASE MANAGEMENT SYSTEM U.S. Department of Justice Office of the Inspector General Audit Division Audit Report 09-22 March 2009 TABLE OF CONTENTS Page THE DEPARTMENT

More information

Project Monitoring and Control

Project Monitoring and Control Project Monitoring and Control ProPath Office of Information and Technology Table of Contents Project Monitoring and Control Process Maps... 1 Process: Project Monitoring and Control... 10 Project Monitoring

More information

VA Office of Inspector General

VA Office of Inspector General VA Office of Inspector General OFFICE OF AUDITS AND EVALUATIONS Veterans Health Administration Review of the Management of Travel, Duty Stations, Salaries and Funds in the Procurement and Logistics Office

More information

AUDIT REPORT. The Department of Energy's Management of Cloud Computing Activities

AUDIT REPORT. The Department of Energy's Management of Cloud Computing Activities U.S. Department of Energy Office of Inspector General Office of Audits and Inspections AUDIT REPORT The Department of Energy's Management of Cloud Computing Activities DOE/IG-0918 September 2014 Department

More information

Approval for the Project Management Accountability System (PMAS) Guide

Approval for the Project Management Accountability System (PMAS) Guide Approval for the Project Management Accountability System (PMAS) Guide The PMAS Guide provides guidance for planning, management control, processes, roles, and responsibilities for VA Information Technology

More information

STATEMENT OF BELINDA J

STATEMENT OF BELINDA J STATEMENT OF BELINDA J. FINN ASSISTANT INSPECTOR GENERAL FOR AUDITS AND EVALUATIONS OFFICE OF INSPECTOR GENERAL DEPARTMENT OF VETERANS AFFAIRS BEFORE THE SUBCOMMITTEE ON HEALTH COMMITTEE ON VETERANS AFFAIRS

More information

UNITED STATES DEPARTMENT OF EDUCATION OFFICE OF INSPECTOR GENERAL 400 MARYLAND AVENUE, S.W. WASHINGTON, DC 20202-1500.

UNITED STATES DEPARTMENT OF EDUCATION OFFICE OF INSPECTOR GENERAL 400 MARYLAND AVENUE, S.W. WASHINGTON, DC 20202-1500. UNITED STATES DEPARTMENT OF EDUCATION OFFICE OF INSPECTOR GENERAL 400 MARYLAND AVENUE, S.W. WASHINGTON, DC 20202-1500 February 1, 2006 Michell Clark, Designee Assistant Secretary for Management and Acting

More information

UNITED STATES DEPARTMENT OF EDUCATION OFFICE OF INSPECTOR GENERAL

UNITED STATES DEPARTMENT OF EDUCATION OFFICE OF INSPECTOR GENERAL UNITED STATES DEPARTMENT OF EDUCATION OFFICE OF INSPECTOR GENERAL AUDIT SERVICES June 30, 2016 Control Number ED-OIG/A04O0014 James W. Runcie Chief Operating Officer Federal Student Aid U.S. Department

More information

VA Office of Inspector General

VA Office of Inspector General T VA Office of Inspector General OFFICE OF AUDITS AND EVALUATIONS Veterans Health Administration Review of Alleged Mismanagement of the Service-Oriented Architecture Research and Development (SOARD) Pilot

More information

VA Office of Inspector General

VA Office of Inspector General . VA Office of Inspector General OFFICE OF AUDITS & EVALUATIONS Department of Veterans Affairs Review of Alleged Improper Program Management within the FLITE Strategic Asset Management Pilot Project September

More information

VA Office of Inspector General

VA Office of Inspector General VA Office of Inspector General OFFICE OF AUDITS AND EVALUATIONS Veterans Benefits Administration Audit of Fiduciary Program s Management of Field Examinations June 1, 2015 14-01883-371 ACRONYMS BFFS CY

More information

VA Office of Inspector General

VA Office of Inspector General VA Office of Inspector General OFFICE OF AUDITS AND EVALUATIONS Veterans Benefits Administration Review of Transition to a Paperless Claims Processing Environment February 4, 2013 11-04376-81 ACRONYMS

More information

VA Office of Inspector General

VA Office of Inspector General VA Office of Inspector General OFFICE OF AUDITS & EVALUATIONS Department of Veterans Affairs Federal Information Security Management Act Audit for Fiscal Year 2013 May 29, 2014 13-01391-72 ACRONYMS AND

More information

September 2005 Report No. 06-009

September 2005 Report No. 06-009 An Audit Report on The Health and Human Services Commission s Consolidation of Administrative Support Functions Report No. 06-009 John Keel, CPA State Auditor An Audit Report on The Health and Human Services

More information

Office of Audits and Evaluations Report No. AUD-13-007. The FDIC s Controls over Business Unit- Led Application Development Activities

Office of Audits and Evaluations Report No. AUD-13-007. The FDIC s Controls over Business Unit- Led Application Development Activities Office of Audits and Evaluations Report No. AUD-13-007 The FDIC s Controls over Business Unit- Led Application Development Activities September 2013 Executive Summary The FDIC s Controls over Business

More information

AUDIT REPORT. The Energy Information Administration s Information Technology Program

AUDIT REPORT. The Energy Information Administration s Information Technology Program U.S. Department of Energy Office of Inspector General Office of Audits and Inspections AUDIT REPORT The Energy Information Administration s Information Technology Program DOE-OIG-16-04 November 2015 Department

More information

Status of Enterprise Resource Planning Systems Cost, Schedule, and Management Actions Taken to Address Prior Recommendations

Status of Enterprise Resource Planning Systems Cost, Schedule, and Management Actions Taken to Address Prior Recommendations Report No. DODIG-2013-111 I nspec tor Ge ne ral Department of Defense AUGUST 1, 2013 Status of Enterprise Resource Planning Systems Cost, Schedule, and Management Actions Taken to Address Prior s I N T

More information

GAO INFORMATION TECHNOLOGY DASHBOARD. Opportunities Exist to Improve Transparency and Oversight of Investment Risk at Select Agencies

GAO INFORMATION TECHNOLOGY DASHBOARD. Opportunities Exist to Improve Transparency and Oversight of Investment Risk at Select Agencies GAO United States Government Accountability Office Report to Congressional Requesters October 2012 INFORMATION TECHNOLOGY DASHBOARD Opportunities Exist to Improve Transparency and Oversight of Investment

More information

UNITED STATES DEPARTMENT OF EDUCATION OFFICE OF INSPECTOR GENERAL

UNITED STATES DEPARTMENT OF EDUCATION OFFICE OF INSPECTOR GENERAL UNITED STATES DEPARTMENT OF EDUCATION OFFICE OF INSPECTOR GENERAL AUDIT SERVICES August 24, 2015 Control Number ED-OIG/A04N0004 James W. Runcie Chief Operating Officer U.S. Department of Education Federal

More information

VA Office of Inspector General

VA Office of Inspector General Nrt56 VA Office of Inspector General OFFICE OF AUDITS AND EVALUATIONS Department of Veterans Affairs Follow-up Review of the Veterans Benefits Management System September 14, 2015 13-00690-455 ACRONYMS

More information

Implementation of the DoD Management Control Program for Navy Acquisition Category II and III Programs (D-2004-109)

Implementation of the DoD Management Control Program for Navy Acquisition Category II and III Programs (D-2004-109) August 17, 2004 Acquisition Implementation of the DoD Management Control Program for Navy Acquisition Category II and III Programs (D-2004-109) Department of Defense Office of the Inspector General Quality

More information

INFORMATION TECHNOLOGY: Reservation System Infrastructure Updated, but Future System Sustainability Remains an Issue

INFORMATION TECHNOLOGY: Reservation System Infrastructure Updated, but Future System Sustainability Remains an Issue INFORMATION TECHNOLOGY: Reservation System Infrastructure Updated, but Future System Audit Report OIG-A-2015-010 May 19, 2015 This page intentionally left blank. NATIONAL RAILROAD PASSENGER CORPORATION

More information

VA Office of Inspector General

VA Office of Inspector General VA Office of Inspector General OFFICE OF AUDITS AND EVALUATIONS Veterans Health Administration Audit of the Community Nursing Home Program March 29, 2013 11-00331-160 ACRONYMS AND ABBREVIATIONS CMS GEC

More information

Software Development Processes

Software Development Processes Software Development Processes Audit Report Report Number IT-AR-15-006 July 13, 2015 Highlights The Postal Service does not consistently manage software development risk. Background Organizations spend

More information

SENTINEL AUDIT V: STATUS OF

SENTINEL AUDIT V: STATUS OF SENTINEL AUDIT V: STATUS OF THE FEDERAL BUREAU OF INVESTIGATION S CASE MANAGEMENT SYSTEM U.S. Department of Justice Office of the Inspector General Audit Division Audit Report 10-03 November 2009 Redacted

More information

DoD Methodologies to Identify Improper Payments in the Military Health Benefits and Commercial Pay Programs Need Improvement

DoD Methodologies to Identify Improper Payments in the Military Health Benefits and Commercial Pay Programs Need Improvement Report No. DODIG-2015-068 I nspec tor Ge ne ral U.S. Department of Defense JA N UA RY 1 4, 2 0 1 5 DoD Methodologies to Identify Improper Payments in the Military Health Benefits and Commercial Pay Programs

More information

Navy Enterprise Resource Planning System Does Not Comply With the Standard Financial Information Structure and U.S. Government Standard General Ledger

Navy Enterprise Resource Planning System Does Not Comply With the Standard Financial Information Structure and U.S. Government Standard General Ledger DODIG-2012-051 February 13, 2012 Navy Enterprise Resource Planning System Does Not Comply With the Standard Financial Information Structure and U.S. Government Standard General Ledger Additional Copies

More information

Department of Labor U.S. Office of Inspector General Office of Audit AUDIT OF WORKFORCE INVESTMENT ACT DATA VALIDATION FOR THE ADULT

Department of Labor U.S. Office of Inspector General Office of Audit AUDIT OF WORKFORCE INVESTMENT ACT DATA VALIDATION FOR THE ADULT Department of Labor U.S. Office of Inspector General Office of Audit EMPLOYMENT AND TRAINING ADMINISTRATION AUDIT OF WORKFORCE INVESTMENT ACT DATA VALIDATION FOR THE ADULT AND DISLOCATED WORKER PROGRAMS

More information

VA Office of Inspector General

VA Office of Inspector General VA Office of Inspector General OFFICE OF AUDITS AND EVALUATIONS Veterans Health Administration Audit of The National Call Center for Homeless Veterans December 3, 2014 13-01859-42 ACRONYMS FY HOMES OIG

More information

Information Technology

Information Technology May 7, 2002 Information Technology Defense Hotline Allegations on the Procurement of a Facilities Maintenance Management System (D-2002-086) Department of Defense Office of the Inspector General Quality

More information

ELECTRONIC HEALTH RECORDS. Outcome-Oriented Metrics and Goals Needed to Gauge DOD s and VA s Progress in Achieving Interoperability

ELECTRONIC HEALTH RECORDS. Outcome-Oriented Metrics and Goals Needed to Gauge DOD s and VA s Progress in Achieving Interoperability United States Government Accountability Office Report to Congressional Committees August 2015 ELECTRONIC HEALTH RECORDS Outcome-Oriented Metrics and Goals Needed to Gauge DOD s and VA s Progress in Achieving

More information

Independent Evaluation of NRC s Implementation of the Federal Information Security Modernization Act of 2014 for Fiscal Year 2015

Independent Evaluation of NRC s Implementation of the Federal Information Security Modernization Act of 2014 for Fiscal Year 2015 Independent Evaluation of NRC s Implementation of the Federal Information Security Modernization Act of 2014 for Fiscal Year 2015 OIG-16-A-03 November 12, 2015 All publicly available OIG reports (including

More information

THE ASSISTANT SECRETARY OF DEFENSE

THE ASSISTANT SECRETARY OF DEFENSE THE ASSISTANT SECRETARY OF DEFENSE 1200 DEFENSE PENTAGON WASHINGTON, DC 20301-1200 HEALTH AFFAIRS 30 July 12 MEMORANDUM FOR ASSISTANT SECRETARY OF THE ARMY (MANPOWER AND RESERVE AFFAIRS) ASSISTANT SECRETARY

More information

Audit of the Office of Emergency Management and Homeland Security: FEMA Urban Area Security Initiative Grant Management 2012 through 2014

Audit of the Office of Emergency Management and Homeland Security: FEMA Urban Area Security Initiative Grant Management 2012 through 2014 Audit of the Office of Emergency Management and Homeland Security: FEMA Urban Area Security Initiative Grant Management 2012 through 2014 MARTIN MATSON City Comptroller STACEY MAZMANIAN Audit Manager City

More information

VA Office of Inspector General

VA Office of Inspector General VA Office of Inspector General OFFICE OF AUDITS AND EVALUATIONS Veterans Health Administration Review of Alleged Mismanagement at the Health Eligibility Center September 2, 2015 14-01792-510 ACRONYMS CBO

More information

HHS OCIO Policy for Information Technology (IT) Enterprise Performance Life Cycle (EPLC)

HHS OCIO Policy for Information Technology (IT) Enterprise Performance Life Cycle (EPLC) Office of the Chief Information Officer Office of the Assistant Secretary for Resources and Technology Department of Health and Human Services HHS OCIO Policy for Information Technology (IT) Enterprise

More information

TREASURY INSPECTOR GENERAL FOR TAX ADMINISTRATION

TREASURY INSPECTOR GENERAL FOR TAX ADMINISTRATION TREASURY INSPECTOR GENERAL FOR TAX ADMINISTRATION The Customer Account Data Engine 2 Systems Development Guidelines; However, Process Improvements Are Needed to Address Inconsistencies September 30, Year

More information

EPA Could Improve Processes for Managing Contractor Systems and Reporting Incidents

EPA Could Improve Processes for Managing Contractor Systems and Reporting Incidents OFFICE OF INSPECTOR GENERAL Audit Report Catalyst for Improving the Environment EPA Could Improve Processes for Managing Contractor Systems and Reporting Incidents Report No. 2007-P-00007 January 11, 2007

More information

Navy s Contract/Vendor Pay Process Was Not Auditable

Navy s Contract/Vendor Pay Process Was Not Auditable Inspector General U.S. Department of Defense Report No. DODIG-2015-142 JULY 1, 2015 Navy s Contract/Vendor Pay Process Was Not Auditable INTEGRITY EFFICIENCY ACCOUNTABILITY EXCELLENCE INTEGRITY EFFICIENCY

More information

U.S. DEPARTMENT OF THE INTERIOR OFFICE OF INSPECTOR GENERAL Verification of Previous Office of Inspector General Recommendations September 2009

U.S. DEPARTMENT OF THE INTERIOR OFFICE OF INSPECTOR GENERAL Verification of Previous Office of Inspector General Recommendations September 2009 U.S. DEPARTMENT OF THE INTERIOR OFFICE OF INSPECTOR GENERAL Verification of Previous Office of Inspector General Recommendations September 2009 ISD-EV-MOA-0002-2009 Contents Acronyms and Other Reference

More information

Department of Homeland Security Office of Inspector General. Review of U.S. Coast Guard Enterprise Architecture Implementation Process

Department of Homeland Security Office of Inspector General. Review of U.S. Coast Guard Enterprise Architecture Implementation Process Department of Homeland Security Office of Inspector General Review of U.S. Coast Guard Enterprise Architecture Implementation Process OIG-09-93 July 2009 Contents/Abbreviations Executive Summary...1 Background...2

More information

EPA Needs to Improve Its. Information Technology. Audit Follow-Up Processes

EPA Needs to Improve Its. Information Technology. Audit Follow-Up Processes U.S. ENVIRONMENTAL PROTECTION AGENCY OFFICE OF INSPECTOR GENERAL Information Technology EPA Needs to Improve Its Information Technology Audit Follow-Up Processes Report No. 16-P-0100 March 10, 2016 Report

More information

Report of Audit OFFICE OF INSPECTOR GENERAL. Information Technology Infrastructure Project Management A-07-02. Tammy Rapp Auditor-in-Charge

Report of Audit OFFICE OF INSPECTOR GENERAL. Information Technology Infrastructure Project Management A-07-02. Tammy Rapp Auditor-in-Charge OFFICE OF INSPECTOR GENERAL Report of Audit Information Technology Infrastructure Project Management A-07-02 Tammy Rapp Auditor-in-Charge FARM CREDIT ADMINISTRATION Memorandum Office of Inspector General

More information

June 2008 Report No. 08-038. An Audit Report on The Department of Information Resources and the Consolidation of the State s Data Centers

June 2008 Report No. 08-038. An Audit Report on The Department of Information Resources and the Consolidation of the State s Data Centers John Keel, CPA State Auditor An Audit Report on The Department of Information Resources and the Consolidation of the State s Data Centers Report No. 08-038 An Audit Report on The Department of Information

More information

VA Office of Inspector General

VA Office of Inspector General w VA Office of Inspector General OFFICE OF AUDITS AND EVALUATIONS Veterans Health Administration Audit of Support Service Contracts November 19, 2014 12-02576-30 ACRONYMS AND ABBREVIATIONS A&A COR ecms

More information

July 2012 Report No. 12-045. An Audit Report on The ReHabWorks System at the Department of Assistive and Rehabilitative Services

July 2012 Report No. 12-045. An Audit Report on The ReHabWorks System at the Department of Assistive and Rehabilitative Services John Keel, CPA State Auditor The ReHabWorks System at the Department of Assistive and Rehabilitative Services Report No. 12-045 The ReHabWorks System at the Department of Assistive and Rehabilitative Services

More information

Veterans Benefits Administration

Veterans Benefits Administration OFFICE OF AUDITS & EVALUATIONS Veterans Benefits Administration Audit of the Veterans Service Network February 18, 2011 09-03850-99 ACRONYMS AND ABBREVIATIONS ATT BDN GAO IMS IT PMAS SEI VETSNET Application

More information

Office of Inspector General Evaluation of the Consumer Financial Protection Bureau s Consumer Response Unit

Office of Inspector General Evaluation of the Consumer Financial Protection Bureau s Consumer Response Unit Office of Inspector General Evaluation of the Consumer Financial Protection Bureau s Consumer Response Unit Consumer Financial Protection Bureau September 2012 September 28, 2012 MEMORANDUM TO: FROM: SUBJECT:

More information

ELECTRONIC HEALTH RECORDS. Fiscal Year 2013 Expenditure Plan Lacks Key Information Needed to Inform Future Funding Decisions

ELECTRONIC HEALTH RECORDS. Fiscal Year 2013 Expenditure Plan Lacks Key Information Needed to Inform Future Funding Decisions United States Government Accountability Office Report to Congressional July 2014 ELECTRONIC HEALTH RECORDS Fiscal Year 2013 Expenditure Plan Lacks Key Information Needed to Inform Future Funding Decisions

More information

STATEMENT OF CHARLES EDWARDS DEPUTY INSPECTOR GENERAL U.S. DEPARTMENT OF HOMELAND SECURITY BEFORE THE

STATEMENT OF CHARLES EDWARDS DEPUTY INSPECTOR GENERAL U.S. DEPARTMENT OF HOMELAND SECURITY BEFORE THE STATEMENT OF CHARLES EDWARDS DEPUTY INSPECTOR GENERAL U.S. DEPARTMENT OF HOMELAND SECURITY BEFORE THE COMMITTEE ON HOMELAND SECURITY SUBCOMMITTEE ON OVERSIGHT AND MANAGEMENT EFFICIENCY U.S. HOUSE OF REPRESENTATIVES

More information

Report No. D-2009-097 July 30, 2009. Data Migration Strategy and Information Assurance for the Business Enterprise Information Services

Report No. D-2009-097 July 30, 2009. Data Migration Strategy and Information Assurance for the Business Enterprise Information Services Report No. D-2009-097 July 30, 2009 Data Migration Strategy and Information Assurance for the Business Enterprise Information Services Additional Information and Copies To obtain additional copies of this

More information

PUBLIC RELEASE PATENT AND TRADEMARK OFFICE. Inadequate Contractor Transition Risks Increased System Cost and Delays

PUBLIC RELEASE PATENT AND TRADEMARK OFFICE. Inadequate Contractor Transition Risks Increased System Cost and Delays PUBLIC RELEASE PATENT AND TRADEMARK OFFICE Inadequate Contractor Transition Risks Increased System Cost and Delays Inspection Report No. OSE-10084-8-0001 / December 1997 Office of Systems Evaluation PTO

More information

Office of Audits and Evaluations Report No. EVAL-14-001. The FDIC s Information Technology Project Management Process

Office of Audits and Evaluations Report No. EVAL-14-001. The FDIC s Information Technology Project Management Process Office of Audits and Evaluations Report No. EVAL-14-001 The FDIC s Information Technology Project Management Process July 2014 Executive Summary The FDIC s Information Technology Project Management Process

More information

OAIG-APO Department of Defense Inspector General 400 Army Navy Drive (Room 1015) Arlington, VA 22202-4704

OAIG-APO Department of Defense Inspector General 400 Army Navy Drive (Room 1015) Arlington, VA 22202-4704 Additional Copies To obtain additional copies of the final report, visit the website of the Department of Defense Inspector General at www.dodig.mil/audit/reports or contact the Office of Assistant Inspector

More information

REVIEW OF NASA S MANAGEMENT AND OVERSIGHT

REVIEW OF NASA S MANAGEMENT AND OVERSIGHT SEPTEMBER 16, 2010 AUDIT REPORT OFFICE OF AUDITS REVIEW OF NASA S MANAGEMENT AND OVERSIGHT OF ITS INFORMATION TECHNOLOGY SECURITY PROGRAM OFFICE OF INSPECTOR GENERAL National Aeronautics and Space Administration

More information

The Department of the Treasury s HR Connect Human Resources System Was Not Effectively Implemented. February 2005. Reference Number: 2005-10-037

The Department of the Treasury s HR Connect Human Resources System Was Not Effectively Implemented. February 2005. Reference Number: 2005-10-037 The Department of the Treasury s HR Connect Human Resources System Was Not Effectively Implemented February 2005 Reference Number: 2005-10-037 This report has cleared the Treasury Inspector General for

More information

Status Report of the Auditor General of Canada to the House of Commons

Status Report of the Auditor General of Canada to the House of Commons 2011 Status Report of the Auditor General of Canada to the House of Commons Chapter 1 Financial Management and Control and Risk Management Office of the Auditor General of Canada The 2011 Status Report

More information

DoD Needs an Effective Process to Identify Cloud Computing Service Contracts

DoD Needs an Effective Process to Identify Cloud Computing Service Contracts Inspector General U.S. Department of Defense Report No. DODIG-2016-038 DECEMBER 28, 2015 DoD Needs an Effective Process to Identify Cloud Computing Service Contracts INTEGRITY EFFICIENCY ACCOUNTABILITY

More information

Sound Transit Internal Audit Report - No. 2014-3

Sound Transit Internal Audit Report - No. 2014-3 Sound Transit Internal Audit Report - No. 2014-3 IT Project Management Report Date: Dec. 26, 2014 Table of Contents Page Background 2 Audit Approach and Methodology 2 Summary of Results 4 Findings & Management

More information

Solution for Enterprise Asset. Management. System Vehicle Maintenance Facility Data. Management. Advisory Report. Report Number DR-MA-15-004

Solution for Enterprise Asset. Management. System Vehicle Maintenance Facility Data. Management. Advisory Report. Report Number DR-MA-15-004 Solution for Enterprise Asset Management System Vehicle Maintenance Facility Data Management Advisory Report Report Number DR-MA-15-004 September 18, 2015 Highlights This management advisory discusses

More information

Veterans Health Administration

Veterans Health Administration OFFICE OF AUDITS AND EVALUATIONS Veterans Health Administration Audit of Veterans Integrated Service Network Contracts December 1, 2011 10-01767-27 ACRONYMS AND ABBREVIATIONS CO COTR ecms EPLS FAR IGCE

More information

Controls Over EPA s Compass Financial System Need to Be Improved

Controls Over EPA s Compass Financial System Need to Be Improved U.S. ENVIRONMENTAL PROTECTION AGENCY OFFICE OF INSPECTOR GENERAL Controls Over EPA s Compass Financial System Need to Be Improved Report No. 13-P-0359 August 23, 2013 Scan this mobile code to learn more

More information

STATE OF NORTH CAROLINA

STATE OF NORTH CAROLINA STATE OF NORTH CAROLINA PERFORMANCE AUDIT DEPARTMENT OF HEALTH AND HUMAN SERVICES DIVISION OF MEDICAL ASSISTANCE MEDICAID PROVIDER ELIGIBILITY AUGUST 2014 OFFICE OF THE STATE AUDITOR BETH A. WOOD, CPA

More information

GAO VA HEALTH CARE. Reliability of Reported Outpatient Medical Appointment Wait Times and Scheduling Oversight Need Improvement

GAO VA HEALTH CARE. Reliability of Reported Outpatient Medical Appointment Wait Times and Scheduling Oversight Need Improvement GAO United States Government Accountability Office Report to Congressional Requesters December 2012 VA HEALTH CARE Reliability of Reported Outpatient Medical Appointment Wait Times and Scheduling Oversight

More information

NASA S PROCESS FOR ACQUIRING INFORMATION TECHNOLOGY SECURITY ASSESSMENT AND MONITORING TOOLS

NASA S PROCESS FOR ACQUIRING INFORMATION TECHNOLOGY SECURITY ASSESSMENT AND MONITORING TOOLS MARCH 18, 2013 AUDIT REPORT OFFICE OF AUDITS NASA S PROCESS FOR ACQUIRING INFORMATION TECHNOLOGY SECURITY ASSESSMENT AND MONITORING TOOLS OFFICE OF INSPECTOR GENERAL National Aeronautics and Space Administration

More information

Office of Inspector General

Office of Inspector General DEPARTMENT OF HOMELAND SECURITY Office of Inspector General Security Weaknesses Increase Risks to Critical United States Secret Service Database (Redacted) Notice: The Department of Homeland Security,

More information

AUDIT OF NASA S EFFORTS TO CONTINUOUSLY MONITOR CRITICAL INFORMATION TECHNOLOGY SECURITY CONTROLS

AUDIT OF NASA S EFFORTS TO CONTINUOUSLY MONITOR CRITICAL INFORMATION TECHNOLOGY SECURITY CONTROLS SEPTEMBER 14, 2010 AUDIT REPORT OFFICE OF AUDITS AUDIT OF NASA S EFFORTS TO CONTINUOUSLY MONITOR CRITICAL INFORMATION TECHNOLOGY SECURITY CONTROLS OFFICE OF INSPECTOR GENERAL National Aeronautics and Space

More information

THOMAS G. DAY SENIOR VICE PRESIDENT, INTELLIGENT MAIL AND ADDRESS QUALITY PRITHA N. MEHRA VICE PRESIDENT, BUSINESS MAIL ENTRY AND PAYMENT TECHNOLOGIES

THOMAS G. DAY SENIOR VICE PRESIDENT, INTELLIGENT MAIL AND ADDRESS QUALITY PRITHA N. MEHRA VICE PRESIDENT, BUSINESS MAIL ENTRY AND PAYMENT TECHNOLOGIES March 31, 2009 THOMAS G. DAY SENIOR VICE PRESIDENT, INTELLIGENT MAIL AND ADDRESS QUALITY PRITHA N. MEHRA VICE PRESIDENT, BUSINESS MAIL ENTRY AND PAYMENT TECHNOLOGIES GEORGE W. WRIGHT VICE PRESIDENT, INFORMATION

More information

Department of Veterans Affairs

Department of Veterans Affairs Audit Report Department of Veterans Affairs December 2013 OFFICE OF LEGISLATIVE AUDITS DEPARTMENT OF LEGISLATIVE SERVICES MARYLAND GENERAL ASSEMBLY This report and any related follow-up correspondence

More information

Review of the SEC s Systems Certification and Accreditation Process

Review of the SEC s Systems Certification and Accreditation Process Review of the SEC s Systems Certification and Accreditation Process March 27, 2013 Page i Should you have any questions regarding this report, please do not hesitate to contact me. We appreciate the courtesy

More information

VA Office of Inspector General

VA Office of Inspector General i VA Office of Inspector General OFFICE OF AUDITS AND EVALUATIONS Veterans Benefits Administration Audit of Liquidation Appraisal Oversight Cleveland and Phoenix Regional Loan Centers October 4, 2012 10-04045-124

More information

Office of the Auditor General Performance Audit Report. Statewide UNIX Security Controls Department of Technology, Management, and Budget

Office of the Auditor General Performance Audit Report. Statewide UNIX Security Controls Department of Technology, Management, and Budget Office of the Auditor General Performance Audit Report Statewide UNIX Security Controls Department of Technology, Management, and Budget December 2015 State of Michigan Auditor General Doug A. Ringler,

More information

Audit Report. Management of Naval Reactors' Cyber Security Program

Audit Report. Management of Naval Reactors' Cyber Security Program U.S. Department of Energy Office of Inspector General Office of Audits and Inspections Audit Report Management of Naval Reactors' Cyber Security Program DOE/IG-0884 April 2013 Department of Energy Washington,

More information

NATIONAL CREDIT UNION ADMINISTRATION OFFICE OF INSPECTOR GENERAL

NATIONAL CREDIT UNION ADMINISTRATION OFFICE OF INSPECTOR GENERAL NATIONAL CREDIT UNION ADMINISTRATION OFFICE OF INSPECTOR GENERAL INDEPENDENT EVALUATION OF THE NATIONAL CREDIT UNION ADMINISTRATION S COMPLIANCE WITH THE FEDERAL INFORMATION SECURITY MANAGEMENT ACT (FISMA)

More information

VistA Evolution Presentation to World Vista

VistA Evolution Presentation to World Vista VistA Evolution Presentation to World Vista Theresa A. Cullen, MD, MS Chief Medical Information Officer Director, Health Informatics Office of Informatics and Analytics Veterans Health Administration Department

More information

GAO VA HEALTH CARE. Reliability of Reported Outpatient Medical Appointment Wait Times and Scheduling Oversight Need Improvement

GAO VA HEALTH CARE. Reliability of Reported Outpatient Medical Appointment Wait Times and Scheduling Oversight Need Improvement GAO United States Government Accountability Office Report to Congressional Requesters December 2012 VA HEALTH CARE Reliability of Reported Outpatient Medical Appointment Wait Times and Scheduling Oversight

More information

Followup Audit: Enterprise Blood Management System Not Ready for Full Deployment

Followup Audit: Enterprise Blood Management System Not Ready for Full Deployment Inspector General U.S. Department of Defense Report No. DODIG 2015 008 OCTOBER 23, 2014 Followup Audit: Enterprise Blood Management System Not Ready for Full Deployment INTEGRITY EFFICIENCY ACCOUNTABILITY

More information

Release Management. ProPath. Office of Information and Technology

Release Management. ProPath. Office of Information and Technology Release Management ProPath Office of Information and Technology Table of Contents Release Management Process Maps... 1 Process: Release Management... 7 Release Management and Goals... 9... 9 Goals... 9

More information

STATE OF NORTH CAROLINA

STATE OF NORTH CAROLINA STATE OF NORTH CAROLINA INFORMATION SYSTEMS AUDIT OFFICE OF INFORMATION TECHNOLOGY SERVICES INFORMATION TECHNOLOGY GENERAL CONTROLS OCTOBER 2014 OFFICE OF THE STATE AUDITOR BETH A. WOOD, CPA STATE AUDITOR

More information

U.S. ELECTION ASSISTANCE COMMISSION OFFICE OF INSPECTOR GENERAL

U.S. ELECTION ASSISTANCE COMMISSION OFFICE OF INSPECTOR GENERAL U.S. ELECTION ASSISTANCE COMMISSION OFFICE OF INSPECTOR GENERAL FINAL REPORT: U.S. Election Assistance Commission Compliance with the Requirements of the Federal Information Security Management Act Fiscal

More information

Information Technology Processes FinCEN is an agency whose mission is dependent on the effective collection,

Information Technology Processes FinCEN is an agency whose mission is dependent on the effective collection, Appendix L Project Management and Information Technology Processes FinCEN is an agency whose mission is dependent on the effective collection, dissemination, and meaningful analysis of large quantities

More information

UNITED STATES DEPARTMENT OF THE INTERIOR BUREAU OF LAND MANAGEMENT MANUAL TRANSMITTAL SHEET

UNITED STATES DEPARTMENT OF THE INTERIOR BUREAU OF LAND MANAGEMENT MANUAL TRANSMITTAL SHEET Form 1221-2 (June 1969) UNITED STATES DEPARTMENT OF THE INTERIOR BUREAU OF LAND MANAGEMENT Release: 1-1718 Date: MANUAL TRANSMITTAL SHEET Subject 1265 Information Technology Investment Management (ITIM)

More information

GAO INFORMATION TECHNOLOGY. Management Improvements Are Essential to VA s Second Effort to Replace Its Outpatient Scheduling System

GAO INFORMATION TECHNOLOGY. Management Improvements Are Essential to VA s Second Effort to Replace Its Outpatient Scheduling System GAO May 2010 United States Government Accountability Office Report to the Ranking Member, Committee on Veterans Affairs, U.S. Senate INFORMATION TECHNOLOGY Management Improvements Are Essential to VA s

More information

Audit of the Data Center Consolidation Initiative at NARA. OIG Draft Audit Report No. 12-09. May 10, 2012

Audit of the Data Center Consolidation Initiative at NARA. OIG Draft Audit Report No. 12-09. May 10, 2012 Audit of the Data Center Consolidation Initiative at NARA OIG Draft Audit Report No. 12-09 May 10, 2012 Table of Contents Executive Summary... 3 Background... 4 Objectives, Scope, Methodology... 7 Audit

More information

U.S. Department of Energy Office of Inspector General Office of Audits & Inspections

U.S. Department of Energy Office of Inspector General Office of Audits & Inspections U.S. Department of Energy Office of Inspector General Office of Audits & Inspections Audit Report Follow-up Audit of the Department's Cyber Security Incident Management Program DOE/IG-0878 December 2012

More information

Department of Homeland Security

Department of Homeland Security Implementation Status of EINSTEIN 3 Accelerated OIG-14-52 March 2014 Washington, DC 20528 / www.oig.dhs.gov March 24, 2014 MEMORANDUM FOR: FROM: SUBJECT: Bobbie Stempfley Acting Assistant Secretary Office

More information

VA Office of Inspector General

VA Office of Inspector General VA Office of Inspector General OFFICE OF AUDITS AND EVALUATIONS Veterans Health Administration Review of Patient-Centered Community Care (PC3) Provider Network Adequacy September 29, 2015 15-00718-507

More information

Report No. DODIG U.S. Department of Defense SEPTEMBER 17, 2014

Report No. DODIG U.S. Department of Defense SEPTEMBER 17, 2014 Inspector General U.S. Department of Defense Report No. DODIG-2014-114 SEPTEMBER 17, 2014 Independent Auditor s Report on Agreed-Upon Procedures for DoD Compliance With Service Contract Inventory Compilation

More information

Program Management Office Provided Adequate Oversight of Two Contracts Supporting the Defense Enterprise Accounting and Management System

Program Management Office Provided Adequate Oversight of Two Contracts Supporting the Defense Enterprise Accounting and Management System Report No. DODIG-2014-006 I nspec tor Ge ne ral U.S. Department of Defense OCTOBER 25, 2013 Program Management Office Provided Adequate Oversight of Two Contracts Supporting the Defense Enterprise Accounting

More information

UNITED STATES DEPARTMENT OF EDUCATION OFFICE OF INSPECTOR GENERAL

UNITED STATES DEPARTMENT OF EDUCATION OFFICE OF INSPECTOR GENERAL UNITED STATES DEPARTMENT OF EDUCATION OFFICE OF INSPECTOR GENERAL Evaluation and Inspection Services Memorandum May 5, 2009 TO: FROM: SUBJECT: James Manning Acting Chief Operating Officer Federal Student

More information

DoD Cloud Computing Strategy Needs Implementation Plan and Detailed Waiver Process

DoD Cloud Computing Strategy Needs Implementation Plan and Detailed Waiver Process Inspector General U.S. Department of Defense Report No. DODIG-2015-045 DECEMBER 4, 2014 DoD Cloud Computing Strategy Needs Implementation Plan and Detailed Waiver Process INTEGRITY EFFICIENCY ACCOUNTABILITY

More information