1 Lessons Learned for Contract Management A Presentation for PMI-AGC by Kurt Robertson PMP, MBA, Lean Sensei 6 Sigma Master Black Belt CFPIM, C.P.M. Copyright 2010, Saudi Aramco. All Rights Reserved. April 30, 2010
2 DISCLAIMER Private person May reference broad contracting experience beyond Saudi Aramco. Nothing in this presentation is specifically represents Saudi Aramco policy or specific contracting problems or events within Aramco. 2
3 Purpose, Objective, Applicability Purpose: To provide a high-level checklist of activities and considerations for proper contract administration. Objective: To leave the meeting with tips on improving your professionalism and on improving your life as a contract administrator. Applicability: Universal Projects Contract Management or Contract Administration 3
4 4
5 LEAN CONSIDERATION 8 WASTES 1. Over production 2. Over Processing 3. Excess Inventory 4. Transportation 5. Motion 6. Defects (Six Sigma) 7. Waiting 8. Human Resources REMEMBER: 1. Quality 2. Cost 3. Delivery 4. Safety 5. Morale QCDSM 5
6 Two Points of View 1. Contractor: (submits proposal, performs work) 2. Customer: (develops SOW, sends IFP/RFP/IFB, awards contract) Two Areas of Responsibility 1. Administrative Being on time Documentation Communication 2. Technical Cost Quality Delivery 6
7 Contract Management A Core Competency Open and fair Contract Management is the starting point for building positive customer/supply relationships. Contract Management has transformed from an administrative, tactical function to a strategic process integral to corporate strategy and directly contributing to the organization s competitive advantage. It is now a core process. Good contract writing and negotiation must be accompanied by effective contract management. If you re not effectively managing your contracts, you re not effectively managing your business. To award and successfully manage effective contracts, organizations must have a disciplined, capable and mature contract management process in place. Contract Management Defined The management of issues that arise during the performance of a contract, including the process of managing contract deliverables, deadlines, contract terms and conditions (T&Cs), while ensuring customer satisfaction. - National Contract Management Association, 2 nd ed. Life Cycle Contract Management: The proactive and methodical management of a contract from initiation through award to compliance and renewal. 7
8 Increased Interest in Contract Management Internal Focus Life Cycle Contract Management Internal process improvement External Focus Outsourcing Supplier Relationships Strategic Sourcing Cost control and transparency Globalization Complexity: Regulatory compliance Tracking of T&C and compliance 8
9 Contract Management Goal QCDSM Supplier Performance Manage business risks Cut expenses Increase revenues by reducing: Pricing errors Mistaken payments Operating and processing costs Personnel Sub-optimal supplier performance 9
10 Costs of Sub-optimal Contract Management 1. Sub-optimizing revenue: No enforcement of negotiated terms on your suppliers Unenforced rights may be waived Timely delivery Quality product Errors of double-handling Time wasted looking for contracts, schedules, file notes and data. Poor communications disparate and ad hoc 2. Being reactive instead of proactive 3. Litigation 4. Termination, Suspension or Disbarment 5. No new awards due to past performance 10
11 Contract Management-Primary Responsibilities 1. Know the Contract (#1 complaint about contract managers) 2. Work Control Work ordering Work completion Work inspection and acceptance Invoicing and payment 3. Contract Compliance Day-to-day monitoring: enforce contract milestone schedule Plan of action if supplier underperforms or if contract requirements change Criteria for measuring success: QCD + supplier responsiveness RFP/IFB amendment, contract modification or change order 4. Contractor Payment (#1 complaint from contractors) Prompt and accurate Quality work, delivered on time, at the cost agreed to Contractor administratively compliant 11
12 Contract Management-Primary Responsibilities 5. Administrative Rules of purchasing Contract law Transportation Health and safety regulations Social responsibilities 6. Documentation Requirements Document all actions, verify all requirements Invoicing, work plans, performance measures, insurance, supplier crew and material payments 7. Subcontract Plans Subcontractor clause 8. Contract Closeout 12
13 Checklist for PRE-AWARD Contract Management SOW (or technical specifications): Write it. Live with it Incomplete Gold plated Link pay provisions to specific stratified deliverables to make contract enforcement easier Make deliverables clear, specific, measurable Schedule C to the contract can be an excellent tool to drive behavior Contract Format and Ts & Cs non-standard (industry standards) Prequalification: Screen out weak contractors. The Team: Team Leader. Team Resumes: Everybody looks good on paper. JOB EX: What kinds of questions do they ask? How do their questions reflect their background and understanding of the work? 13
14 Checklist for PRE-AWARD Contract Management Improve the process (Lean) Automate the process Repository Lessons Learned/Best Practices Standardization (SIMULATION if time allows) Vocabulary Terms, Conditions and Format Standards of performance (expectations) Contract Work Plan List of tasks and schedule for completing those tasks. 14
15 Checklist for POST-AWARD Contract Management Monitor Contract Compliance Know and shepherd the deliverables Contract Key Performance Indicators (KPIs) Cost Quality Delivery (time, location, quantity) Evaluate Contractor Performance Provide timely corrective feedback to the contractor Administrative Technical 15
16 Checklist for POST-AWARD Contract Management Avoid Conflict of Interest For you The Customer (remember who you work for: Stockholm Syndrome) For the Contractor Ask yourself if activities are: Illegal Immoral Unsafe Unethical Anticipate, eliminate or mitigate risk. Inform appropriate parties (project manager, quality manager) of potential problems. Represent your organization in meetings be there. Keep your finger on the pulse of the project. Cultural interface and sensitivity. 16
17 Checklist for POST-AWARD Contract Management Only one contract administrator per contract (conflicting direction) Contract Modifications: Dated and sequentially numbered Specifically what has changed Specifically what has NOT changed Properly approved and executed Conduct Organizational Assessments and self-audits. Contract Management Maturity Model (CMMP) Maturity Levels: Ad hoc, Basic, Structured, Integrated, Optimized Ref: Contract Management Organization Assessment Tools By Gregory A. Garret, Rene G. Rendon Conduct periodic research on your contractor (or customer) for financial or legal problems - lien searches. 17
18 Checklist for POST-AWARD Contract Management Lessons Learned/Best Practices: Begin documenting early and share as appropriate to improve the process and deliverables Repository: common accessible storage area Kickoffs, Phase Wrap Ups, Status Meetings: Communicate Early Communicate Clearly Communicate Often Expectations: Establish them early. Manage them often. We receive the product quality and contractor performance we are willing to tolerate and accept. 18
19 Checklist for POST-AWARD Contract Management Unauthorized Commitments Only one spokesperson per contract Communication Ladder: Problems Authorization to perform work Site Visits Be Present: Difficult to manage a contract from behind a desk Let the contractor and the proponent know by your frequent presence you are the company s contract representative Insist on being kept informed Make random quality checks and other evaluative functions When in charge, take charge! 19
20 The Contractor s Point of View Everything above still applies. If your authorized customer representative asks for additional level of effort and it isn t: Illegal Immoral Unethical Unsafe Get a signed change order THEN proceed. Following verbal direction, even from an authorized person, often results in filing a claim for payment. Even a letter confirming verbal direction is better than nothing. 20
21 RESOURCES National Contract Management Association (NCMA) Contract Management Body of Knowledge (CMBOK). Next Level Purchasing Institute for Supplier Management (ISM) Purchasing Magazine 21
22 Thank you 22
Course Objectives: COR 206 - Contracting Officer's Representatives in a Contingency Environment
Course Objectives: COR 206 - Contracting Officer's Representatives in a Contingency Environment (course Learning/Performance Objectives followed by enabling learning objectives) 1. Recognize the duties,
More informationPMP Examination Tasks Puzzle game
PMP Examination Tasks Puzzle game Here is a great game to play to test your knowledge of the tasks you will be tested on in the actual examination. What we have done is take each of the domain tasks in
More informationProject Implementation: Procurement & Contract Management. April 2012
& Contract Management April 2012 & Contract Management We would like to acknowledge the contribution of the Programme Management Department in the preparation of this presentation that will introduce some
More informationCamber Quality Assurance (QA) Approach
Camber Quality Assurance (QA) Approach Camber s QA approach brings a tested, systematic methodology, ensuring that our customers receive the highest quality products and services, delivered via efficient
More informationContract Management: Moving from Monitoring to Managing
Contract Management: Moving from Monitoring to Managing Presented by Norma J. Hall, FNIGP, CPPO, CPPB, CPM UPPCC Chair and Program Manager for SC Budget & Control Board Division of Procurement Contract
More informationCrosswalk Between Current and New PMP Task Classifications
Crosswalk Between Current and New PMP Task Classifications Domain 01 Initiating the Project Conduct project selection methods (e.g., cost benefit analysis, selection criteria) through meetings with the
More informationCHAPTER 23. Contract Management and Administration
Date Issued: June 12, 2009 Date Last Revised: September 28, 2015 CHAPTER 23. Contract Management and Administration Table of Contents CHAPTER 23. Contract Management and Administration... 23-1 23.1 Policy...
More informationOne of the most common challenges facing U.S. government agencies, prime contractors, and subcontractors is managing contract changes.
48 Contract Management March 2010 Contract Management March 2010 49 One of the most common challenges facing U.S. government agencies, prime contractors, and subcontractors is managing contract changes.
More informationOne Government Contract Management Framework. September 2014
One Government Contract Framework September 2014 One Government Contract Framework Table of contents 1 Introduction... 4 2 Purpose... 4 3 Scope... 5 3.1 Contract management planning starts before a contract
More informationContract and Vendor Management Guide
Contents 1. Guidelines for managing contracts and vendors... 2 1.1. Purpose and scope... 2 1.2. Introduction... 2 2. Contract and Vendor Management 2.1. Levels of management/segmentation... 3 2.2. Supplier
More informationCONTRACT ADMINISTRATION AND MANAGEMENT GUIDE
CONTRACT ADMINISTRATION AND MANAGEMENT GUIDE STATE OF IDAHO DEPARTMENT OF ADMINISTRATION DIVISION OF PURCHASING REVISED 01 01 14 Table of Contents I. Purpose... 1 II. Overview of Contract Management and
More informationRisk Mitigation and Subcontract Management
Risk Mitigation and Subcontract Management Breakout Session # C13 Danielle Carr, MSM Program Acquisitions, HMS Technologies Stacey B. Dey-Foy Director Suspension & Debarment, EPA July 28, 2014 @ 4:00pm
More informationSupplier Performance Management Program. CEA Edmonton Buildings Committee November 13, 2012
Supplier Performance Management Program CEA Edmonton Buildings Committee November 13, 2012 Supplier Performance Management Program - Background Consulting Services Review (Dec 14, 2009): The Office of
More informationContract management's effect on in house counsel
IBM Software Industry Solutions Industry/Product Identifier Contract management's effect on in house counsel Impacting contract visibility, analysis and compliance Emptoris Contract Management Solutions
More informationPosition Classification Standard for Procurement Clerical and Technician Series, GS-1106. Table of Contents
Position Classification Standard for Procurement Clerical and Technician Series, GS-1106 Table of Contents SERIES DEFINITION... 2 EXCLUSIONS... 2 DEFINITIONS... 3 OCCUPATIONAL INFORMATION... 3 TITLES...
More informationRAPID RESPONSE PROGRAM
RAPID RESPONSE PROGRAM The Best Acquisition Solution Available To All Federal Agencies Presented by: Dwayne Terry Business Development dwayne.k.terry@us.army.mil LIFEL Page 1 of CONTENTS Organizational
More informationOBLIGATION MANAGEMENT
OBLIGATION MANAGEMENT TRACK & TRACE: CONTRACTUAL OBLIGATIONS Better Visibility. Better Outcomes RAMESH SOMASUNDARAM DIRECTOR, IT VENDOR MANAGEMENT SERVICES MARCH 2012 E N E R G I C A Governance Matter
More informationMNLARS Project Audit Checklist
Audit Checklist The following provides a detailed checklist to assist the audit team in reviewing the health of a project. Relevance (at this time) How relevant is this attribute to this project or audit?
More informationPurchasing Success for the Service Sector: Using Lean & Six Sigma.
Purchasing Success for the Service Sector: Using Lean & Six Sigma. Gurpreet Singh Khurana, MBA, C.P.M., Lean Six Sigma Green Belt Process Improvement Director, AmeriHealth Mercy Family of Companies gurpreet.khurana@amerihealthmercy.com
More informationNEOXEN MODUS METHODOLOGY
NEOXEN MODUS METHODOLOGY RELEASE 5.0.0.1 INTRODUCTION TO QA & SOFTWARE TESTING GUIDE D O C U M E N T A T I O N L I C E N S E This documentation, as well as the software described in it, is furnished under
More informationMeasuring Contract Management Process Maturity: A Tool for Enhancing the Value Chain
Measuring Contract Management Process Maturity: A Tool for Enhancing the Value Chain Dr. Rene G. Rendon, CPCM, C.P.M., PMP U.S. Naval Postgraduate School (831) 656-3464; rgrendon@nps.edu 91 st Annual International
More informationImproving sales effectiveness in the quote-to-cash process
IBM Software Industry Solutions Management Improving sales effectiveness in the quote-to-cash process Improving sales effectiveness in the quote-to-cash process Contents 2 Executive summary 2 Effective
More informationPROJECT MANAGEMENT FRAMEWORK
PROJECT MANAGEMENT FRAMEWORK DOCUMENT INFORMATION DOCUMENT TYPE: DOCUMENT STATUS: POLICY OWNER POSITION: INTERNAL COMMITTEE ENDORSEMENT: APPROVED BY: Strategic document Approved Executive Assistant to
More informationStandard conditions of purchase
Standard conditions of purchase 1 OFFER AND ACCEPTANCE 2 PROPERTY, RISK & DELIVERY 3 PRICES & RATES The Supplier shall provide all Goods and Services in accordance with the terms and conditions set out
More informationNEOXEN MODUS METHODOLOGY
NEOXEN MODUS METHODOLOGY RELEASE 5.0.0.1 INTRODUCTION TO PROJECT MANAGEMENT GUIDE D O C U M E N T A T I O N L I C E N S E This documentation, as well as the software described in it, is furnished under
More informationOffice of Research Facilities Development and Operations Contractor Safety Policy
Office of Research Facilities Development and Operations Contractor Safety Policy The National Institutes of Health (NIH) is committed to providing a safe environment for everyone who enters the NIH campus.
More informationCONTRACT MANAGEMENT COURSES
CONTRACT MANAGEMENT COURSES Principles and Practices Administration of Commercial Contracts Commercial Applications Risk Management in the Sourcing Environment TM Principles and Practices Identify contract
More informationHEALTH SAFETY & ENVIRONMENT MANAGEMENT SYSTEM
HEALTH SAFETY & ENVIRONMENT MANAGEMENT SYSTEM September 2011 OUR HEALTH, SAFETY AND ENVIRONMENT POLICY OUR PRINCIPLE OF DUE CARE We care about the wellbeing of our people and our impact on the environment.
More informationCATSA Screening Contractor Management System Standard (2015)
Public Works and Government Services Canada Canadian General Standards Board Travaux publics et Services gouvernementaux Canada Office des normes générales du Canada CATSA Screening Contractor Management
More informationLayton Construction Co., Inc. Quality Management Manual
Layton Construction Co., Inc QUALITY MANAGEMENT PLAN 1 Layton Construction Co., Inc. Quality Management Manual [ 2015 ] PHOENIX PHOENIX BOISE BOISE IRVINE IRVINE SALT LAKE CITY SALT ORLANDO LAKE CITY HAWAII
More informationProduct Lifecycle Management in the Medical Device Industry. An Oracle White Paper Updated January 2008
Product Lifecycle Management in the Medical Device Industry An Oracle White Paper Updated January 2008 Product Lifecycle Management in the Medical Device Industry PLM technology ensures FDA compliance
More informationChapter 1 Introduction to Contract Management and Administration
Chapter 1 Introduction to Contract Management and Administration Definitions What is Contract Management? Contract management is the process that ensures both parties to a contract fully understand their
More informationNZQA registered unit standard 25872 version 2 Page 1 of 5. Develop and implement a project plan to deliver on an Infrastructure works contract
Page 1 of 5 Title Develop and implement a project plan to deliver on an Infrastructure works contract Level 5 Credits 15 Purpose People credited with this unit standard are able to: explain relationship
More informationProcurement guidance Managing and monitoring suppliers performance
Procurement guidance Managing and monitoring suppliers performance Procurement guidance: Managing and monitoring suppliers performance Page 2 of 16 Table of contents Table of contents... 2 Purpose of the
More informationPlan to Pay (P2P) Optimize your process to Manage your Contractors with Oracle Primavera July, 2012
Plan to Pay (P2P) Optimize your process to Manage your Contractors with Oracle Primavera July, 2012 Agenda Oracle View of Plan to Pay (P2P) Composite Process Component Review Project Planning & Portfolio
More informationQuality Manual ISO9001:2008
Quality Manual ISO9001:2008 Connor Winfield Corp. Date: 4/26/10 Revision: 3 Quality Manual Quality Manual Connor Winfield GENERAL Section 0.1 Section Rev.: 2 Rev. Date: 4/26/10 Section Page 1 Index and
More informationVendor Performance Evaluation Requirements
Vendor Performance Evaluation Requirements The awarded vendor should note that the Contract Administrator will document the contractor s performance by completing a Vendor Performance Evaluation based
More informationFMC Technologies Measurement Solutions Inc.
Table of Contents 1 Revision History... 4 2 Company... 5 2.1 Introduction... 5 2.2 Quality Policy... 6 2.3 Quality Organization... 6 2.4 Company Processes... 7 3 Scope and Exclusions... 8 3.1 Scope...
More informationDr. Gad J. Selig, PMP, COP
The Critical Role of the Project Manager in Executing Successful Strategic Sourcing and Outsourcing Initiatives: Major Trends, Critical Success Factors and Lessons Learned Abstract: Dr. Gad J. Selig, PMP,
More informationADMINISTRATIVE SUPPORT AND CLERICAL OCCUPATIONS SIN 736 1
Following are the Contractor Site and Government Site Labor Categories for SIN 736-1, SIN 736-1, and SIN 736-5. Please do not hesitate to contact us at gsataps@amdexcorp.com if you have any questions ADMINISTRATIVE
More informationProcess Improvement Program Project Process
Process Improvement Program Project Process 1 P a g e 12/3/2014 The Process Improvement Program is part of the City of Fort Lauderdale s FL 2 STAT Approach to Exponential Improvement. Its objective is
More informationContract Management Process Maturity: Analysis of Organizational Assessments. Rene G. Rendon Naval Postgraduate School
Contract Management Process Maturity: Analysis of Organizational Assessments Rene G. Rendon Naval Postgraduate School 1 Overview Background Relevant Literature Assessment Tool Analysis of Assessments Summary
More informationISO 9001 Quality Management System
ISO 9001 Quality Management System DETAILED GUIDE ISO 9001 Background ISO 9001:2008 is the world s foremost quality management standard, used by hundreds of thousands of organizations in over 170 countries
More informationI S O I E C 2 7 0 0 2 2 0 1 3 I N F O R M A T I O N S E C U R I T Y A U D I T T O O L
15.1 ESTABLISH SECURITY AGREEMENTS WITH SUPPLIERS 15.1.1 EXPECT SUPPLIERS TO COMPLY WITH RISK MITIGATION AGREEMENTS Do you clarify the information security risks that exist whenever your suppliers have
More informationIntegrating Project Management and Service Management
Integrating Project and Integrating Project and By Reg Lo with contributions from Michael Robinson. 1 Introduction Project has become a well recognized management discipline within IT. is also becoming
More informationBusiness Process Optimization w/ Innovative Results
Business Process Optimization w/ Innovative Results Sam DiSalvatore Introduction The principle of continuous process improvement is based on the belief that even excellent products and services can be
More informationPROJECT MANAGEMENT PLAN TEMPLATE < PROJECT NAME >
PROJECT MANAGEMENT PLAN TEMPLATE < PROJECT NAME > Date of Issue: < date > Document Revision #: < version # > Project Manager: < name > Project Management Plan < Insert Project Name > Revision History Name
More information15 Principles of Project Management Success
15 Principles of Project Management Success Project management knowledge, tools and processes are not enough to make your project succeed. You need to get away from your desk and get your hands dirty.
More informationWHITE PAPER December, 2008
INTRODUCTION Key to most IT organization s ongoing success is the leadership team s ability to anticipate, plan for, and adapt to change. With ever changing business/mission requirements, customer/user
More informationHow to best position your construction company to a surety in 2013
How to best position your construction company to a surety in 2013 Table of Contents Surety 2013 market forecast... 3 Criteria used by construction surety underwriters... 3 Five key areas for best construction
More informationISO/IEC 17025 QUALITY MANUAL
1800 NW 169 th Pl, Beaverton, OR 97006 Revision F Date: 9/18/06 PAGE 1 OF 18 TABLE OF CONTENTS Quality Manual Section Applicable ISO/IEC 17025:2005 clause(s) Page Quality Policy 4.2.2 3 Introduction 4
More informationBIM Best Practice to Cut Capital and Operational Expenditure: Maximizing Business Value. Professor Mustafa Alshawi
BIM Best Practice to Cut Capital and Operational Expenditure: Maximizing Business Value Professor Mustafa Alshawi Improving Project Performance Current Project Portfolio 1.83 B UAED ($500M) Award Winning
More informationLenovo Service Parts Sales Terms and Conditions New Zealand
Lenovo Service Parts Sales Terms and Conditions New Zealand Please read these Terms and Conditions carefully as they apply to the purchase of Products and/or Services from Lenovo (Australia and New Zealand)
More informationEnhancing IT Governance, Risk and Compliance Management (IT GRC)
Enhancing IT Governance, Risk and Compliance Management (IT GRC) Enabling Reliable eservices Tawfiq F. Alrushaid Saudi Aramco Agenda GRC Overview IT GRC Introduction IT Governance IT Risk Management IT
More informationWhy do Project Fail? 42% 37% 27% 26% 24% 24% 0% 10% 20% 30% 40% 50% IBM Software Group Rational software. Source: AberdeenGroup, August 2006
Why do Project Fail? Unclear or continually changing product definitions Product does not meet customer or market requirements 37% 42% Unrealistic schedule expectations Projects not adequately staffed
More informationComponents of an Effective Contract Monitoring System
BEST PRACTICES IN GOVERNMENT Components of an Effective Contract Monitoring System July 2003 Russell W. Hinton State Auditor Department of Audits and Accounts Performance Audit Operations Division 254
More informationOperations. Group Standard. Business Operations process forms the core of all our business activities
Standard Operations Business Operations process forms the core of all our business activities SMS-GS-O1 Operations December 2014 v1.1 Serco Public Document Details Document Details erence SMS GS-O1: Operations
More information451 s Procurement and Vendor Management Capability Development Program
The case for improved Procurement and Vendor Management The current market environment is calling for increased operational efficiency and effectiveness, where value for money and market contestability
More informationDEPARTMENT OF DEFENSE HANDBOOK PARTS MANAGEMENT. This handbook is for guidance only. Do not cite this document as a requirement.
NOT MEASUREMENT SENSITIVE MIL-HDBK-512 04 October 2000 DEPARTMENT OF DEFENSE HANDBOOK PARTS MANAGEMENT This handbook is for guidance only. Do not cite this document as a requirement. AMSC N/A DISTRIBUTION
More informationReaching CMM Levels 2 and 3 with the Rational Unified Process
Reaching CMM Levels 2 and 3 with the Rational Unified Process Rational Software White Paper TP174 Table of Contents INTRODUCTION... 1 LEVEL-2, REPEATABLE... 3 Requirements Management... 3 Software Project
More informationConstruction Company Capacity Assessment
Business/Firm Name: Vendor NCDOT Number: Contact Address: Construction Company Capacity Assessment Name/Title of Person Taking Assessment: Phone Contact Information: Email Contact Information: List Current
More informationA GUIDE TO BEST PRACTICES FOR CONTRACT ADMINISTRATION
Page 1 of 18 A GUIDE TO BEST PRACTICES FOR CONTRACT ADMINISTRATION OFFICE OF FEDERAL PROCUREMENT POLICY (OFPP) OCTOBER 1994 TABLE OF CONTENTS FOREWORD CONTRACT ADMINISTRATION OVERVIEW OF THE CONTRACT ADMINISTRATION
More informationS24 - Governance, Risk, and Compliance (GRC) Automation Siamak Razmazma
S24 - Governance, Risk, and Compliance (GRC) Automation Siamak Razmazma Governance, Risk, Compliance (GRC) Automation Siamak Razmazma Siamak.razmazma@protiviti.com September 2009 Agenda Introduction to
More informationContract Management The Mavericks Won t Like This!
Contract Management The Mavericks Won t Like This! Keith Wallis How Much Did That Project Cost? Real Life Example Original contract amount $500K Variations scope changes not visible Total variations =
More informationProcurement Capability Standards
IPAA PROFESSIONAL CAPABILITIES PROJECT Procurement Capability Standards Definition Professional Role Procurement is the process of acquiring goods and/or services. It can include: identifying a procurement
More informationGSA Schedule Contract Compliance
GSA Schedule Contract Compliance Steve Charles Christopher Yukins Craig Holman June 11, 2008 GSA Schedule Contract 5-year Agreement Competitive Prices Over 100 federal activities and organizations Specific
More informationContract Management Framework
Contract Management Framework Contents Purpose and Scope... 2 The Contract... 2 The importance of the Contract... 2 Contract Management... 3 The Toolkits... 4 Outline of establishing a Contract Management
More informationAppendix E Program Management Plan Template
Appendix E Program Management Plan Template Version 2 March 7, 2005 This page is intentionally left blank. Version 2 March 7, 2005 Title Page Document Control Panel Table of Contents List of Acronyms Definitions
More informationISO 9001:2008 STANDARD OPERATING PROCEDURES MANUAL
8200 Brownleigh Drive Raleigh, NC 27617-7423 Phone: (919) 510-9696 Fax: (919) 510-9668 ISO 9001:2008 STANDARD OPERATING PROCEDURES MANUAL ALLIANCE OF PROFESSIONALS & CONSULTANTS, INC. - 1 - Table of Contents
More informationMaximize Telecom Savings with TEM Business Process Outsourcing
Maximize Telecom Savings with TEM Business Process Outsourcing As telecom expense management (TEM) continues to provide significant savings to the enterprise, organizations are considering business process
More informationThe Association of Change Management Professionals
The Association of Change Management Professionals Statement of Change Management Scope, Knowledge Areas, and Process Groups March 31, 2012 Introduction The Association of Change Management Professionals
More informationReplacement of Heat System Components
STATEMENT OF WORK FOR Replacement of Heat System Components At Warehouse Takoraudantie 4 08/17/2013 REV 8-24-13 Project 2013-021 Page 1 of 6 1.0 INTRODUCTION 1.1 Overview: The U.S. Embassy Helsinki has
More informationPurchase Order Terms and Conditions
Purchase Order Terms and Conditions "Avanade" means Avanade Asia Pte Ltd (Company Registration No.: 20005969E), a company incorporated in Singapore, having its offices at 238A Thomson Road, #25-01 Novena
More informationMKS Integrity & CMMI. July, 2007
& CMMI July, 2007 Why the drive for CMMI? Missed commitments Spiralling costs Late delivery to the market Last minute crunches Inadequate management visibility Too many surprises Quality problems Customer
More informationUsing Quality Assurance Standards. Don t assume quality, ensure quality
Using Quality Assurance Standards Don t assume quality, ensure quality Learning Objectives At the end of this module, you will be able to: Identify the difference between Quality Assurance (QA) and Quality
More informationCAP CONSULTING SERVICES AGREEMENT
CAP CONSULTING SERVICES AGREEMENT This Agreement is made on this day of, by and between the College of American Pathologists, a not-for-profit Illinois corporation with offices at 325 Waukegan Road, Northfield,
More informationWhy is Quality Important? Definition
QUALITY SYSTEMS By Daryle Niedermayer, I.S.P., PMP Why is Quality Important? Clients & users expect quality What if jetliners crashed as often as Microsoft Windows? Poor quality results in rework at additional
More informationConstruction Performance Mapping Model for Outsourcing Organizations
Construction Performance Mapping Model for Outsourcing Organizations Kristen C. Hurtado, M.S., John Savicky, M.S., and Kenneth T. Sullivan, Ph.D., MBA Arizona State University Tempe, Arizona Brian C. Lines,
More informationAPPLIED SCIENCE COOPERATIVE AGREEMENT STANDARD OPERATING PROCEDURES FOR PTRs, GRANTS & TECHNOLOGY TRANSFER STAFF
APPLIED SCIENCE COOPERATIVE AGREEMENT STANDARD OPERATING PROCEDURES FOR PTRs, GRANTS & TECHNOLOGY TRANSFER STAFF Purpose: This standard operating procedure assists the Applied Science personnel in performing
More informationMessage from the Co-Chairmen and Chief Executive Officers
Message from the Co-Chairmen and Chief Executive Officers As each of us works to meet individual and Company-wide business goals here at Torchmark, we must all ensure that the work we perform and the business
More informationBusiness Logistics Specialist Position Description
Specialist Position Description March 23, 2015 MIT Specialist Position Description March 23, 2015 Page i Table of Contents General Characteristics... 1 Career Path... 2 Explanation of Proficiency Level
More informationManaging Successful Software Development Projects Mike Thibado 12/28/05
Managing Successful Software Development Projects Mike Thibado 12/28/05 Copyright 2006, Ambient Consulting Table of Contents EXECUTIVE OVERVIEW...3 STATEMENT OF WORK DOCUMENT...4 REQUIREMENTS CHANGE PROCEDURE...5
More informationD. MCLAUGHLIN & SONS LTD QUALITY MANUAL
D. MCLAUGHLIN & SONS LTD QUALITY MANUAL Originated By: Anne Wall (Quality Consultant) Date: Approved By: Date: Issue AMENDMENT DATE Draft 1 Quality Manual QM1 CONTENTS 1 QUALITY ASSURANCE POLICY 1.1 Quality
More information1.1 Identification This is the Subcontractor Management Plan, document number XYZ035, for the SYSTEM Z project.
A Sample contractor Management Plan 1.0 INTRODUCTION 1.1 Identification This is the contractor Management Plan, document number YZ035, for the SYSTEM Z project. 1.2 Purpose The contractor Management Plan
More informationProcurement & Supply Chain Management
New Skills. New Thinking Procurement & Supply Chain Management Supply Chain Effectiveness Audit - Implementing lean processes in your supply chain 20 September 2012 Auckland 24 September 2012 Wellington
More informationVendor Relationship Management
Vendor Relationship Management Getting What You Paid For (and More) Stephen Guth VP, Vendor Management Thursday, February 26 th, 2015, 8:00 9:00 a.m. Topics Case Study Company Intro Begin with the End
More informationCONTRACTING FOR SERVICES
Tool QQ Early Childhood Iowa CONTRACTING FOR SERVICES This tool provides an overview of the components of a contract. If your ECI area board currently uses contracts to purchase services, use this tool
More informationCopyright 2014 Carnegie Mellon University The Cyber Resilience Review is based on the Cyber Resilience Evaluation Method and the CERT Resilience
Copyright 2014 Carnegie Mellon University The Cyber Resilience Review is based on the Cyber Resilience Evaluation Method and the CERT Resilience Management Model (CERT-RMM), both developed at Carnegie
More informationProject Management Plan Outline ITSC
Project Management Plan Outline ITSC Date: 02/28/2012 Introduction At start of each project vendors must create a project management plan for ITSC approval, including, at a minimum, the sections described
More informationBank Selection & Relationship Management From RFPs to Scorecards
Bank Selection & Relationship Management From RFPs to Scorecards Mark K. Webster, CPA, CCM, Partner Daniel L. Blumen, CTP, Partner Treasury Alliance Group LLC Agenda Overview Bank Selection The RFP Process
More informationTechnology Services Strategic Plan
Technology Services Strategic Plan 2014 Table of Contents A Changing Landscape... 3 Values... 4 Technology Services Goals... 5 Employee Engagement... 6 Operational Efficiency... 7 Agency Satisfaction...
More information--Administers assigned contracts. Establishes and maintains contract files. Tracks status of funds
H86911, page 1 Nothing in this job description restricts management's right to assign or reassign duties and responsibilities to this job at any time. DUTIES This is a non-career, term position with the
More informationS86810, page 1 Manager, Technology Operations Job Description
S86810, page 1 Manager, Technology Operations Job Description Nothing in this job description restricts management's right to assign or reassign duties and responsibilities to this job at any time. FUNCTIONAL
More informationSpecialties Manufacturing. Talladega Castings & Machine Co., Inc. ISO 9001:2008. Quality Manual
Specialties Manufacturing Talladega Castings & Machine Co., Inc. ISO 9001:2008 This document is the property of TMS and may not be reproduced, wholly, or in part, without the express consent of TMS. Rev.
More informationTable of Contents. Section G: Contract Administration Data Mod: AA20: (Verizon) 10/05/09-GS11T08BJD6001
Section Table of Contents Section G: Contract Administration Data Mod: AA20: (Verizon) 10/05/09- Page G.1 Contract Administration 1 G.1.1 Government Points of Contact 1 G.1.1.1 Procuring Contracting Officer
More informationMTAT.03.243 Software Engineering Management
MTAT.03.243 Software Engineering Management Lecture 17: Other SPI Frameworks and QM Systems Dietmar Pfahl Spring 2014 email: dietmar.pfahl@ut.ee Structure of Lecture 17 Other SPI Frameworks People CMM
More informationPOST AWARD CONTRACT MANAGEMENT
POST AWARD CONTRACT MANAGEMENT POST AWARD CONTRACT MANAGEMENT Overview of Types of Contracts and Award Methods Understanding the Contract Contents of the Contract Contract Performance Designating an agency
More informationManage Deliverables - Construction Step 6. July 12, 2012
Manage Deliverables - Construction Step 6 July 12, 2012 Project Management Concept Step 1: Needs Development Step 2: Scope Development Step 3: Procurement of Design Team Step 4: Design Step 5: Bid/Procurement
More informationQuality Management System Manual
Quality Management System Manual This manual has been reviewed and approved for use by: Jack Zazulak President, Aurora Machine Limited March 07, 2011 Date - Copyright Notice - This document is the exclusive
More informationWhy is Government Contract Data Management Different and Important?
Synopsis: Managing critical contract data is a part of the contract management function. However, it should be leveraged appropriately to allow a contractor s team to function optimally and efficiently.
More information