Audit Report Rottnest Island 2015 Network Quality and Reliability of Supply Performance Audit - Operation of Compliance Monitoring Systems

Size: px
Start display at page:

Download "Audit Report Rottnest Island 2015 Network Quality and Reliability of Supply Performance Audit - Operation of Compliance Monitoring Systems"

Transcription

1 ABN Rottnest Island 2015 Network Quality and Reliability of Supply Performance Audit - Operation of Compliance Monitoring Systems Telephone: Fax: projects@qualeng.net Web: Postal Address: PO Box Z5261, St George s Terrace, PERTH WA 6831 Office: Level 2, 231 Adelaide Terrace, Perth, Western Australia, 6000

2 executive summary Under the Electricity Industry (Network Quality and Reliability of Supply) Code 2005 (the Code), Division 3, Section 26, Rottnest Island Authority (RIA) is required to arrange for an independent audit of the operation of the systems that are in place to monitor its compliance with Part 2 of the Code or an instrument made under Section 14(3). In July 2015 the RIA commissioned to carry out the audit in respect of the operation of the systems to cover the period 1 July 2014 to 30 June The RIA's distribution system consists of an 11 kv distribution network (defined as the 11 kv HV Transmission System), both underground and above ground, a number of substations and a 415V LV distribution network comprising five underground feeders. The RIA has contracted Programmed Facility Management (PFM) to manage, operate and maintain the electricity assets and to be responsible for compliance with the licence conditions and with the Code. The audit was conducted between August and September 2015 and included: review of the actions resulting from previous audit recommendations, review of supporting documentation, interviews of key personnel, review of evidence, data, reports and processes demonstrating the operation and performance of the systems. The audit found that the action arising from the previous audit finding had not been completed. The finding and recommendation are still open: No evaluation of the power quality monitoring results was noted. An assessment is required and outcome and actions documented. One opportunity for improvement arising from the previous audit is also pending: Verification of network reliability figures is carried out informally. Data entry, calculation results and report figures should be subject to verification.

3 The audit found that the RIA and PFM have maintained adequate systems to monitor compliance with the requirements of Part 2 of the Code. There are processes in place for: monitoring of power quality through measurement of voltage fluctuations (flicker) and voltage harmonic distortion; monitoring of interruption duration, frequency and causes of interruption by means of registers for planned and unplanned outages; managing planned and forced interruptions; documenting outage procedures, restoration priority, emergency response and disaster recovery plans to maintain supply to customers; providing alternative power supplies to reduce the effect of interruptions; providing notifications of planned outages to customers; calculation and reporting of reliability data. As well as the findings open from the previous audit two additional findings were recorded: There were no register or records to indicate that the 72 hour minimum outage notification had been monitored during the reporting period. There was no evidence in the current registers that interruptions over 12 hours or that frequency of interruptions in excess of 16 per year are monitored over the 10 year period. Based on the scope of the audit defined in section 26 of the Code, and except for the findings noted above, has found that Rottnest Island Authority has in place systems to monitor its compliance with the requirements of Part 2 of the Code, Quality and Reliability Standards.

4 This report is an accurate representation of the findings and opinions of the auditors following the assessment of the client's conformance to nominated Licence conditions. The report is reliant on evidence provided by other parties and is subject to limitations due to the nature of the evidence available to the auditor, the sampling process inherent in the audit process, the limitations of internal controls and the need to use judgement in the assessment of evidence. On this basis shall not be liable for loss or damage to other parties due to their reliance on the information contained in this report or in its supporting documentation. Approvals Representation Name Signature Position Date Auditor: M Zammit Lead Auditor / Engineering Manager, 23/09/2015 Audit Team M Zammit S Campbell Audit Team Description Project Director and Lead Auditor Reviewer Issue Status Issue No Date Description Approved A 22/09/2015 First Draft issue MZ 1 23/09/2015 First Issue MZ AUDITREPORT-4807-RIA QUAL&RELIAB Page 4 of

5 TABLE OF CONTENTS 1 OBJECTIVES AND SCOPE OF AUDIT Introduction Audit Objectives Audit Scope Audit Methodology Limitations and Qualifications Acronyms and Abbreviations LICENSEE'S RESPONSE TO PREVIOUS AUDIT RECOMMENDATIONS Background Progress of actions from 2014 Audit KEY FINDINGS System to manage compliance with Part 2, Division 1, Quality Standards (sec. 5 to 8) Quality of Supply: System/Process Duty to Disconnect if Quality of Supply may Lead to Damage (section 8) Summary of power quality issues and reports System to manage compliance with Part 2, Division 2, Standards for Interruption of Supply (Sec. 9-12) Duty to maintain the supply with a minimum number and duration of interruptions (Sec. 9) Duty to reduce the effects of interruptions and provision for alternative supplies for proposed interruptions (Sec. 10) Planned interruptions and Notifications (Sec. 11) Significant interruptions to small use customers (Sec.12) System to manage compliance with Part 2, Division 3, Standards for the duration of interruption of supply in particular areas (Sec. 13) Provisions may be excluded or modified by agreement with customers (Sec 15) AUDIT SUMMARY AND RECOMMENDATIONS...24 AUDITREPORT-4807-RIA QUAL&RELIAB Page 5 of

6 1 Objectives and Scope of Audit 1.1 INTRODUCTION Rottnest Island Authority (RIA) has an Electricity Integrated Regional Licence (EIRL3 Licence) (the Licence) issued by the Economic Regulation Authority (the Authority) under Sections 7 and 15(2) of the Electricity Industry Act 2004 (WA) (the Act). Under the scope of the Licence RIA generates and distributes electricity to commercial customers. Under the terms of the Act RIA is required to comply with the Electricity Industry (Network Quality and Reliability of Supply) Code 2005 (the Code). In accordance with Division 3 "Performance reporting", Section 26 "Annual report on monitoring systems" of the Code, RIA is required to arrange for an independent audit of the operation of the systems that are in place to monitor its compliance with Part 2 of the Code or an instrument under Section 14(3). In July 2015 RIA commissioned to carry out the Performance Audit to cover the period 1 July 2014 to 30 June The audit has been conducted and this report prepared in accordance with the Code. The RIA's distribution system consist of an 11 kv network (identified as the 11 kv HV Transmission System) comprising two feeders (number 2 and number 6), both underground and above ground, a number of substations and a 415V LV distribution network comprising five feeders (Feeders 1, 3, 4, 5 and 7). The RIA has placed the responsibility for managing the operation and maintenance of the licence assets on Programmed Facility Management (PFM) under a contractual agreement, the "Facilities, Operations and Utilities Management Agreement" (FOU) which was replaced by the Facilities Utilities and Support Services (FUSS) at the start of Under this agreement PFM is responsible for compliance with the licence conditions and with the Code. 1.2 AUDIT OBJECTIVES The purpose of the Performance Audit is to assess and report on the operation of the systems implemented by the licensee to monitor its compliance with Part 2 of the Code or an instrument under section 14(3). AUDITREPORT-4807-RIA QUAL&RELIAB Page 6 of

7 1.3 AUDIT SCOPE Part 2 of the Code includes 4 Divisions: 1. Division 1, "Quality Standards" for compliance with requirements for quality of supply at the point of connection to the customer, in regard to voltage fluctuations and harmonic distortion. 2. Division 2, "Standards for the interruption of supply to individual customers" provides for the maintenance of supply and management of interruptions to customers, both in terms of the duration and number of interruptions. It includes for: 2.1. Provision of supply with the minimum number and duration of interruptions Consideration of providing alternative supply if the interruption is expected to be significant, its effect substantial or if the customer has special health needs that require continuous supply Allowing planned interruptions if the customer is notified within a suitable time and where the duration does not exceed 6 hours, or 4 hours for temperatures over 30 C or north of the 26th parallel Provides for the distributor to remedy the causes of interruptions or enter into alternative arrangements if the supply has been interrupted more than 12 hours continuously or more than 16 times in the prescribed 12 months and it is considered that the prescribed standard is unlikely to be met for the customer. 3. Division 3, "Standards for the duration of interruptions of supply in particular areas" provides that the average length of interruptions should not exceed 290 minutes in any area of the State, other than the Perth CBD and urban areas and 160 minutes for urban areas other than the Perth CBD (calculated as average of the yearly averages over 4 years). 4. Division 4, "Variations of obligations under this Part" provides for: 4.1. review and approval by the Minister of alternative requirements and 4.2. agreement between the transmitter/distributor and the customer of extensions and modifications to the standards. The audit was carried out between August and September The following representatives participated in the audit on RIA's behalf and/or contributed to sourcing the documentation and providing evidence to the audit: Ms Janett Enke, Contracts & Project Officer, RIA Mr Orrin Neale, Island Engineer, PFM Mr Dino Ajid, Power Generation Supervisor, PFM Mr Roger Fletcher, Risk, Compliance & HSE Manager, PFM. The main auditor representative was Mr M Zammit, Lead Auditor and Mr S Campbell was the AUDITREPORT-4807-RIA QUAL&RELIAB Page 7 of

8 documentation reviewer. 1.4 AUDIT METHODOLOGY The audit followed in part the methodology defined in the Authority's Audit and Review Guidelines: Electricity and Gas Licences, April 2014, including: preparation of an audit plan and risk assessment for internal control, fieldwork, reporting. The audit proceeded through a documentation review, meetings, interviews and checks of processes. These were supported by additional queries to clarify aspects of policies and procedures. 1.5 LIMITATIONS AND QUALIFICATIONS An audit provides a reasonable level of assurance on the effectiveness of control procedures, however there are limitations due to the nature of the evidence available to the auditor, the sampling process inherent in checking the evidence, the limitations of internal controls and the need to use judgement in the assessment of evidence. 1.6 ACRONYMS AND ABBREVIATIONS Abbreviation Authority CAIDI CMMS Description Economic Regulation Authority Customer Average Interruption Duration Index Computerised Maintenance Management System Code Electricity Industry (Network Quality and Reliability of Supply) Code 2005 FUSS NA PFM Plt Pst RIA Facilities Utilities and Support Services Not Applicable Programmed Facility Management Long Term Flicker (as defined in the Code) Short Term Flicker (as defined in the Code) Rottnest Island Authority AUDITREPORT-4807-RIA QUAL&RELIAB Page 8 of

9 Abbreviation RMU SAIDI SAIFI THD Description Ring Main Unit System Average Interruption Duration Index System Average Frequency Duration Index Total Harmonic Distortion AUDITREPORT-4807-RIA QUAL&RELIAB Page 9 of

10 2 Licensee's Response to Previous Audit Recommendations 2.1 BACKGROUND The previous quality and reliability of supply audit was completed in September This section reviews RIA's progress on the recommendations of the 2014 audit as well as RIA's planned actions to address any outstanding issues. The recommendations arising from the previous report and the status of the actions determined in this audit have been summarised in the following table. AUDITREPORT-4807-RIA QUAL&RELIAB Page 10 of

11 SUPPLY PERFORMANCE AUDIT - OPERATION OF COMPLIANCE REF 48/7 2.2 PROGRESS OF ACTIONS FROM 2014 AUDIT The following table lists the recommendations made in the 2014 audit and records progress of any actions. Item No Code Ref 1 Part 2 Div 1, Sec Div 3, Sec. 13 Requirement Findings 2014 Recommendations and Opportunities for Improvement Quality and Reliability standards, voltage fluctuations, harmonics: A transmitter and a distributor must, so far as is reasonably practicable, ensure that electricity supplied by the transmitter or distributor to a customer s electrical installations, as measured at the point of connection of those installations to the network, at all times complies with the standards including voltage fluctuation (flicker) and harmonics. Standards for the duration of interruption of supply in particular areas System to monitor compliance with standards for the duration of interruption of supply in particular areas (30, 160, 290 min) Results for fluctuations (flicker) were mainly in accordance with the Code with some excursion in excess of the limit. No evaluation of the power quality monitoring results was noted. An evaluation is required leading to acceptance of the results or improvement action. At present there is no formal verification of reported information. 1/2014. Implement a process to ensure that results of power quality monitoring are reviewed and either accepted or appropriate action taken. 2/2014. (OFI) Data entered, calculation results and report figures should be subject to verification. Verification process should be documented; this could be achieved by Status Process has not been formalised, however action is in place to document the review of power quality monitoring. Open, finding carried over to the 2015 audit. Verification was carried out informally in Process was due to be documented in the calculation file however due to change in systems and personnel the process is still under review. AUDITREPORT-4807-RIA QUAL&RELIAB Page11 of

12 SUPPLY PERFORMANCE AUDIT - OPERATION OF COMPLIANCE REF 48/7 Item No Code Ref Requirement Findings 2014 Recommendations and Opportunities for Improvement Status describing it in the calculation sheets (action carry over from audit). It is noted that a corrective action was in progress at the end of the audit Open, finding carried over to the 2015 audit. Note: "Open"actions have been included in the recommendations for the new audit period. AUDITREPORT-4807-RIA QUAL&RELIAB Page12 of

13 3 Key Findings 3.1 SYSTEM TO MANAGE COMPLIANCE WITH PART 2, DIVISION 1, QUALITY STANDARDS (SEC. 5 TO 8) Requirement: The Licensee is required to have systems in place to monitor compliance with requirements for quality of supply at the point of connection to the customer, both in terms of voltage fluctuations and harmonic distortion and for disconnection of customer where there is a possibility of damage to the customer installation Quality of Supply: System/Process Systems are in place for monitoring compliance with the Code quality standards including: the "RIA Electrical Water Gas Licence Compliance Register" (April 2015) a spreadsheet listing compliance requirements, timing and appropriate actions required; PFM's procedure "PRO-ROT-ELEC Voltage and Harmonic Fluctuation Monitoring" (14/8/2013) setting out the requirements for power quality measurements; the "FUSS Compliance and Licence Bible" setting up the dates for compliance activities (where FUSS is Facilities Utilities and Support Services contract for operational services; annual independent testing of connections and analysis of data for power quality coinciding with the island peak demand period. It was noted that the operator (PFM) procedures are under review and scheduled for weekly discussions with the operational crews for further consolidation and updating. Quality of supply monitoring was carried out by the external consultant Nilsen WA Pty Ltd. The testing was carried out during the Summer peak demand period under work order "WA217212" generated by the work management system "Maximo" in accordance with the "Compliance and Utilities Spreadsheet". The Work Order prompt is in the process of been shifted to the FUSS CMMS (Computerised maintenance management system). Results and analysis were reported in Nielsen's "Rottnest Island Power Quality Report: Dec Jan. 2015". Measurements were taken at 6 locations: Abbott St substation Hotel Rottnest Shopping Precinct Tea Rooms Lodge Waste Water Treatment Plant. AUDITREPORT-4807-RIA QUAL&RELIAB Page 13 of

14 Not all of the above connections had been tested in It is noted that the Waste Water Treatment Plant is part of RIA's facilities, therefore it does not represent customers. Each location was monitored over a continuous period of 7 days. Total Harmonic Distortion (THD) was measured and was well within limits. Flicker was within limits at all sites except for Abbott St where there were flicker spikes over the limit. Flicker spikes appeared to be one-off occurrences. Table 1: Flicker and Harmonics Measurements Site Hotel Rottnest Flicker (Pst 1.0; Plt 0.8) Harmonics (THD 8%) Pst Plt (Max %) Customer's Complaints on Quality Shopping Precinct Tea Rooms Lodge peak < 0.83 peak < Abbott St peak peak avg 0.56 avg Nil Notes: 1. Five spikes over the limit. 2. One single occurrence over 7 day period, on 22:00, 9 January Overall the power quality measurements in the audit period indicated that the supply at the connections monitored are in general compliance with the requirement of the Code. There are occasional peaks in flicker that exceed the prescribed limit. The THD measurements were also in accordance with the Code. The audit noted that the test results had not been adequately reviewed: No evaluation of the power quality monitoring results was noted. This was also the case in the previous reporting period, however there have been both system and operator changes during the current reporting period and the previous action has been noted by PFM Duty to Disconnect if Quality of Supply may Lead to Damage (section 8) PFM has procedure "PRO-RNI-I Voltage and Harmonic Fluctuation Monitoring Procedure" in place to guide the disconnection of customers in the event that results of power quality monitoring AUDITREPORT-4807-RIA QUAL&RELIAB Page 14 of

15 exceed the Code limits and damage may result to a customer electrical installation. In addition there are procedures for responding to customers' power quality complaints: the "FUSS Complaint Handling Procedure; RIA's "Utilities Customer Complaints Procedure", (updated 15/4/2015). A register is in place to record customer complaints including power quality complaints: RIA's "Electrical Customer Complaints Reporting Register". No customer complaints related to power quality were registered during the audit period Summary of power quality issues and reports Review of the systems, processes and practices dealing with quality of supply has shown the following gap: 1. No evaluation of the power quality monitoring results was noted during the reporting period. An assessment is required and outcomes documented. No significant "quality" event were reported during the audit period and there were no customer complaints for either voltage fluctuations and harmonics. 3.2 SYSTEM TO MANAGE COMPLIANCE WITH PART 2, DIVISION 2, STANDARDS FOR INTERRUPTION OF SUPPLY (SEC. 9-12) The licensee has to have systems to monitor compliance with requirements for the minimisation of interruptions to customers, both in term of the duration and number of interruptions. The requirements are for the licensee to: Maintain the supply with the minimum number and duration of interruptions (Sec. 9); Reduce the effects of interruptions; consider providing alternative supply if the proposed interruption is expected to be significant, its effect substantial or if the customer has special health needs that require continuous supply (Sec. 10); Ensure that where interruptions are planned, where practicable the customer is notified within a suitable time and the duration does not exceed 6 hours, or 4 hours for temperatures over 30 C or north of the 26th parallel (Sec. 11); Remedy the causes of interruptions or enter into alternative arrangements if the supply has been interrupted more than 12 hours continuously or more than 16 times in the prescribed 12 months and it is considered that the prescribed standard is unlikely to be met for the customer (Sec. 12). AUDITREPORT-4807-RIA QUAL&RELIAB Page 15 of

16 3.2.1 Duty to maintain the supply with a minimum number and duration of interruptions (Sec. 9) Requirement: The licensee must establish systems to monitor compliance with the requirement to ensure, so far as is reasonably practicable, that the supply of electricity to a customer is maintained and the occurrence and duration of any interruptions is kept to a minimum. PFM has systems in place to monitor compliance with the requirements for a minimum number and duration of interruptions. PFM uses two outage registers to record details of planned and forced interruptions. Details include outage identification, date, disconnection and reconnection times, duration, location, area, customers and connections affected. The registers are: a register of "Operational Outages" which provides details of all forced outages including both transmission and distribution interruptions and identifies causes, including generation faults; a register of "Planned Outages" recording outages due to maintenance, asset improvement etc. In addition PFM has plans and procedures to react to interruptions and reduce their impact: "Electrical Disaster Recovery Plan" (DRP), 29/12/2011), including the provision of mobile generators in case of loss of feeders; "Power Reinstatement Procedure" (14/8/2014); "Restoration Priority Register" for allocating priority to customer reconnections; "PRO-RNI-I Powerhouse Outages Procedure" (14/8/2013); "PRO-RNI-I Planned Outage Notification Procedure" (14/8/2013). Every forced interruption is documented in the "Operational Incident Report Form" that records the nature of the incident, causes, details of damage and corrective actions. In total there were 5 Planned and 5 Operational outages for the period. One of the planned outages was over 6 hours however the outage did not affect any customers. One of the forced outages was over 6 hours and affected eight customers and nine connections. In regard to Planned Outages: one outage was for pole top washdown on pole W13 on the 11 kv line in December 2014; it lasted 10.5 hours but it did not affect any customers through the provision of mobile generators; a further outage was for 5.5 hours but did not affect any customers; a further two other were due to pole top washdown; one was for a repair to an inspection cover and affected three customers and 54 connections. In regard to Operational (Forced) outages: one outage was 8 hours and was due to an RMU trip at the Powerhouse switchyard. AUDITREPORT-4807-RIA QUAL&RELIAB Page 16 of

17 Summary: Table 2: Systems to monitor compliance with requirement to maintain supply and the occurrence and duration of interruptions to a minimum Site Procedures dealing with outages Systems and Procedures monitoring performance All Yes Yes Duty to reduce the effects of interruptions and provision for alternative supplies for proposed interruptions (Sec. 10) Requirement: The licensee must establish systems to monitor compliance with its duty to reduce, so far as is reasonably practicable, the effect of any interruptions and consider providing alternative supply for proposed interruptions if the interruption is greater than 6 hours, or there is a substantial effect on the business or there are special health needs customers. Reduce the effect of any interruptions The audit found that there are systems in place to monitor interruptions and provide alternative supplies to reduce the effect of interruptions. PFM has plans and procedures in place to monitor and deal with emergencies and crisis, these include: the outage registers noted in section the "Electrical Services Disaster Recovery Plan, Electrical Disaster Recovery Plan, Business Continuity Planning", (ESDRP), December 2011, which analyses the network and identifies the most likely disaster scenarios, the action and recovery plans together with an estimate of outage duration; the Disaster Recovery Plan for the Electrical Distribution Network (DRP), February 2013, which defines the steps necessary to provide alternative electrical supply to Rottnest Island electrical services with mobile gen-sets as well as the connection arrangements for temporary generation; the "PRO-RNI-I ", Restoration Priority Register Electrical Services, setting the restoration order of RIA's electrical services; the "PRO-RNI-I Powerhouse Outages Procedure" which provides for the power station restart in case of distribution circuit breaker trips, generator trips, power blackouts and includes black start procedures; emergency response tests are documented in the "Electricity Business Continuity Drill Form". AUDITREPORT-4807-RIA QUAL&RELIAB Page 17 of

18 Due to the compact size and topology of the network the extent of outages can be readily assessed. As noted in section 3.2.1, PFM monitors both planned and forced outages for duration, location, customers, connections and causes, as well as mitigating actions such as availability or provision of alternative supply. The data from the outage registers is entered in the "Network Reliability Parameters" spreadsheet which collects all yearly and historical data as well as customer and connection numbers. Calculations for duration and frequency of interruptions are performed in this file and used for further reports. The SCADA computerised management system provides for automatic restoration of power to the distribution system in the event of power failure. The powerhouse operator can manually override the SCADA system to restore power in accordance with the order of the Restoration Register. Desktop tests of emergency response have been carried out for scenarios selected from the DRP. the tests are scheduled in the operator calendar. Records of tests are documented in the "Electricity Business Continuity Drill Form" and were examined by the auditor. Provision of Alternative Supply The DRP documents the arrangement of plant and procedures for providing and restoring supply in response to a range of power outages at different network locations. The DRP provides the connection arrangement for each location, wiring diagram for the equipment installation and the equipment required for generation. Special Health Needs Customers and Commercially Sensitive Loads There were no special health needs (SN) customers on the island during the audit period. SN customers are managed by the RIA. SN customers have to apply for special support to the RIA, the process is informal and there have been no instances of applications in the last few years. The island has no facilities or resources for supporting SN customers. Some of the critical customers on the island, such as Telstra, have their own back up generator sets, whilst others, like the nursing post and the police rely on PFM for back up supplies. The audit confirmed evidence of consultation process with businesses in preparation to planned outages. AUDITREPORT-4807-RIA QUAL&RELIAB Page 18 of

19 Summary Table 3: Systems to monitor compliance with duty to reduce the effect of interruptions and provide alternative supply for planned interruptions Site Reduce the Effect of Interruptions Alternative Supply Special Needs Customers All Yes Yes NA (There were no special health needs customers on Rottnest Island in the audit period) Planned interruptions and Notifications (Sec. 11) Requirement: The licensee must establish systems to monitor compliance with the requirement to maintain planned outages which do not exceed 6 hours and providing notifications at least 72 hours before each outage for eligible persons (using no more than 50 MW per year). PFM has a system to manage and monitor planned outages and notifications. Planned Outages Not Exceeding 4 or 6 Hours As noted in sections 3.2.1, PFM maintains a register of planned outages with details of start and end dates, duration, location, causes and customers affected. While the duration of planned outages was recorded, there was no clear indication in the outage register that it is a breach of section 11 of the Code when an outage exceeds 6 hours duration nor clear provision in the register to document reasons for excessive duration. However all outages with a duration in excess of the limit did not impact on any customers due to adequate provision of alternative power supply. Planned Outage Notifications PFM's "PRO-RNI-I Planned Outage Notification Procedure" is in place addressing outage notification including the 72 hours advance warning. The notification process requires the operator, PFM, to advise both the RIA and customers of impending outages by letter, and/or phone. The audit examined evidence of notifications for four of the planned outages. The evidence viewed showed that customers had received advice at least 72 hours ahead of the outages. It is noted that while records are available to show compliance with the Code, there are no register AUDITREPORT-4807-RIA QUAL&RELIAB Page 19 of

20 or records to confirm that the 72 hour minimum notification warning has been monitored for each planned outage. Summary Table 4: Systems to monitor compliance with planned outages not exceeding 4 or 6 hours and providing notifications at least 72 hours before each planned outage Site Duration ( 6h) Systems to monitor notifications 72 hours prior All Yes Not fully implemented 2. There were no register or records to indicate that the 72 hour minimum notification warning had been monitored during the reporting period. There should be evidence to show that compliance with the notification requirement is being monitored Significant interruptions to small use customers (Sec.12) Requirement: The licensee must establish systems to monitor compliance with the requirement to remedy the causes of interruptions or make alternative arrangements where significant interruption (duration over 12 hours or more than 16 interruptions in the preceding year) occurred for small use customers and where the Licensee considers that the prescribed standard (9 years out of 10) is unlikely to be met. Outage durations are monitored through the Planned and Operational Outages registers noted at section There were no significant interruptions in the audit period. No customer supply was interrupted more than 16 times in the audit period. In regard to performance over 10 years, records are available up to 2007 and show that there was only one interruption over 12 hours, in and 16 interruptions within a single audit period occurred only once in the period, in As this performance is in compliance with the Code, there was no obligation under the Code for the licensee to take any actions under this section. While the duration and number of annual outages is recorded, there was no evidence in the current registers that interruptions over 12 hours or that frequency of interruptions in excess of 16 per year are monitored over the 10 year period. AUDITREPORT-4807-RIA QUAL&RELIAB Page 20 of

21 Summary Table 4: Systems for monitoring compliance with interruption duration not to exceed 12 hours Site 2015 # interruptions > 12 hours Compliance = 0 All 0 No small use customer affected 9 Years out of 10 ( 12 hours) Compliance Yes Complying between 2007 and 2015 (only one year interruption > 12 h ( )) Causes of Interruption Remedied / Alternative Arrangements No action necessary. Table 5: Systems for monitoring compliance with interruption frequency not to exceed 16 per customer per period Site 2015 # interruptions > 16 per period 9 Years out of 10 (# 16) 2014 # > 16 Compliance = 0 Compliance Compliance = 0 All 0 Yes Complying between 2007 and 2015 (only one year > 16 interruptions ( )) Causes of Interruption Remedied / Alternative Arrangements 0 No action necessary. Note: it is noted that the Code and criteria have changed over the 9 year period. 3. There was no evidence in the current registers that interruptions over 12 hours or that frequency of interruptions in excess of 16 per year are monitored over the 10 year period. AUDITREPORT-4807-RIA QUAL&RELIAB Page 21 of

22 3.3 SYSTEM TO MANAGE COMPLIANCE WITH PART 2, DIVISION 3, STANDARDS FOR THE DURATION OF INTERRUPTION OF SUPPLY IN PARTICULAR AREAS (SEC. 13) Requirement: The licensee must establish systems to monitor compliance with the Code requirement to ensure that the average length of interruptions to customer premises for the four years up to the current year for areas other than the Perth CBD do not exceed 160 minutes in urban areas and 290 minutes in any other area of the State. PFM monitors the duration of interruptions through the Planned and Forced Outage registers noted in section and through a spreadsheet, the "Network Reliability Parameters" which records the data and carries out the calculations that provide the required performance figures. The spreadsheet carries records of several years so that long term performance can be assessed. As noted in section above, operational development and plant upgrades have been implemented both over the audit period and over previous periods. This has led to an improvement in the performance of the system in regard to the length of interruptions to customers. The figure of total length of interruptions per customer premises over a year has dropped to minutes in from a high of in At present there is no formal verification of reported information. Summary Table 6: Systems to monitor compliance with requirement for interruption not to exceed 290 minutes average per customer over 4 years. Site 2015 ( < 290 m) All using distribution connections using customer served 4 Year Average (Avg over 4 years 290 min) using distribution connections using customer served Note: Definitions of customer numbers and connections were changed in Calculations are based on 527 connections (which includes accommodation units) whilst previously 191 connections were used. PFM are reviewing the number of customer premises being supplied. The review is currently taking place and may result in a change to the interruption duration figures for the next reporting period under section 13 of the Code. AUDITREPORT-4807-RIA QUAL&RELIAB Page 22 of

23 4. (OFI) At present there is no formal verification of reported information. Entry data, calculation results and report figures should be subject to verification and verification process documented. 3.4 PROVISIONS MAY BE EXCLUDED OR MODIFIED BY AGREEMENT WITH CUSTOMERS (SEC 15) Requirement: A customer and a transmitter or a distributor may agree in writing that a provision of this Part is excluded or modified in relation to the supply of electricity by the transmitter or distributor to the customer and the agreement must set out the matters that the parties consider are the advantages and disadvantages. There are no agreements in place to exclude or modify provisions of this Part of the code. AUDITREPORT-4807-RIA QUAL&RELIAB Page 23 of

24 4 Audit Summary and Recommendations Under Section 26 "Annual report on monitoring systems" of the Code, Rottnest Island Authority is required to arrange for an independent audit of the operation of the systems that are in place to monitor its compliance with Part 2 of the Code. or an instrument under Section 14(3). The audit has found that monitoring systems are in operation and are in compliance with the requirements of the Code except as noted in the following summary. There was one recommendation and one Opportunity for Improvement (OFI) arising from the audit, both findings and recommendations are still open: The recommendation was in regard to implementing a process to ensure that results of power quality monitoring are reviewed and acted upon. The action arising from the recommendations has not been completed and the recommendations has carried over to this audit period. The lack of evaluation of the power quality monitoring results was confirmed during the reporting period. An assessment is required and outcome and actions, if any, documented. The OFI was in regard to the need to verify the entry of data and calculation results including reliability and report figures. The audit found that the OFI action is still open and has been included in this year findings. Together with the recommendation and OFI still open from the previous audit, the audit made two findings: There were no register or records to indicate that the 72 hour minimum notification warning had been monitored during the reporting period. There should be evidence to show that compliance with the notification requirement of section 11 of the Code is being monitored. While the duration and number of annual outages is recorded, there was no evidence in the current registers that interruptions over 12 hours or that frequency of interruptions in excess of 16 per year are monitored over the 10 year period. The audit and recommendations summary is provided in the next table. The table summarises the findings and recommendations of the report in regard to the system operation and compliance. The table rates the various element as complying (), not in compliance ( ), or as actions in progress, observations or opportunities for improvement (OFI). Based on the scope of the audit defined in section 26 of the Code and except for the findings noted above, has found that the system and processes within RIA and PFM are in compliance with the requirements of Part 2 of the Code, "Quality and Reliability Standards". AUDITREPORT-4807-RIA QUAL&RELIAB Page 24 of

25 SUPPLY PERFORMANCE AUDIT - OPERATION OF COMPLIANCE REF 48/7 Table 7: Systems Compliance Summary Code Division, Section Div 1, Sec. 5-7 Code Requirement General System System to monitor compliance with requirements of the Code. System to monitor compliance with quality and Reliability standards: voltage fluctuations, harmonics. Evidence of System Evidence of Process Findings / Comments Recommended Corrective Actions / Operation of the systems which monitor Rottnest Island Authority's compliance with the Code, complies with the Code requirements except for the findings reported below. Measurements are systematic, initiated from compliance calendars and CMMS and occur annually at peak demand time. No complaints from customers on quality of supply. THD is measured and is in compliance. Opportunities for Improvement (OFI) All flicker readings were in compliance except for one-off peaks. Results for fluctuations (flicker) were mainly in accordance with the Code with some excursion in excess of the limit. No evaluation of the power quality monitoring results was noted. An assessment is required and outcome and actions, if any, documented. 1/2015. Implement a process to ensure that results of power quality monitoring are reviewed and outcomes and actions documented. AUDITREPORT-4807-RIA QUAL&RELIAB Page25 of

26 SUPPLY PERFORMANCE AUDIT - OPERATION OF COMPLIANCE REF 48/7 Code Division, Section Div 1, Sec. 8 Div 2, Sec. 9 Div 2, Sec. 10 Div 2, Sec. 11 Code Requirement System to monitor compliance with duty to disconnect if damage may result due to power quality. System to monitor compliance with maintaining the supply with a minimum number and duration of interruptions. System to monitor compliance with reduction of effects of interruptions or provision for alternative supplies for proposed interruptions. System to monitor compliance with length and (continued below) Evidence of System Evidence of Process Findings / Comments Recommended Corrective Actions / Disconnections are covered by procedures, can proceed in case of emergencies and are documented. PFM monitors the number of interruptions, their duration, customers affected and causes. Procedures and processes are in place to monitor and reduce the effects of interruptions and provide alternative supplies. PFM records the length of interruptions. There was no indication in the outage register or other control document that it is a breach of section 11 of the Code when an outage exceeds 6 hours duration. However no customers were affected by any planned outage exceeding the duration requirement of the Code. Opportunities for Improvement (OFI) AUDITREPORT-4807-RIA QUAL&RELIAB Page26 of

27 SUPPLY PERFORMANCE AUDIT - OPERATION OF COMPLIANCE REF 48/7 Code Division, Section Div 2, Sec. 12 Div 3, Sec. 13 Code Requirement notifications for planned interruptions. System to monitor compliance with limiting significant interruptions to small use customers ( 16 times or 12 Hours) and to provide remedial action where breaches occur. System to monitor compliance with standards for the duration of interruption of supply in particular areas (30, 160, 290 min) Evidence of System Evidence of Process Findings / Comments Recommended Corrective Actions / A system is in place to issue notifications of planned interruptions. There were no register or records to indicate that the 72 hour minimum notification had been monitored during the reporting period. Outage numbers are monitored. There is evidence of compliance in 8 years out of 9. There is evidence of improvement actions. There was no evidence in the current registers that interruptions over 12 hours or that frequency of interruptions in excess of 16 per year are monitored over the 10 year period Figures are monitored. Complies. At present there is no formal verification of reported information. Opportunities for Improvement (OFI) 2/2015. There should be evidence to show that compliance with the notification requirement of section 11 of the Code is being monitored. 3/2015. Establish a process for monitoring compliance of the number and frequency of significant interruptions over 10 years, in accordance with section 12 of the Code. 4/2015. (OFI) Entry data, calculation results and report figures should be subject to verification. Verification process should be documented; this could be achieved by describing it in the calculation sheets (action carry over from audit). It is noted that a corrective action was in progress at the end of the previous audit period. AUDITREPORT-4807-RIA QUAL&RELIAB Page27 of

Rio Tinto - Iron Ore - Distribution Network Service Provider Network Quality and Reliability of Supply Code 2005 COMPLIANCE AUDIT 2010-2011

Rio Tinto - Iron Ore - Distribution Network Service Provider Network Quality and Reliability of Supply Code 2005 COMPLIANCE AUDIT 2010-2011 Rio Tinto - Iron Ore - Distribution Network Service Provider Network Quality and Reliability of Supply Code 2005 COMPLIANCE AUDIT 2010-2011 WP04302 WP04302-EE-CE-001 Rev 1 11 October 2011 Rio Tinto - Iron

More information

ROTTNEST ISLAND AUTHORITY OPERATION OF ELECTRICAL SERVICES CUSTOMER SERVICE CHARTER 2009. Electrical Customer Service Charter 2009 Version 2 1

ROTTNEST ISLAND AUTHORITY OPERATION OF ELECTRICAL SERVICES CUSTOMER SERVICE CHARTER 2009. Electrical Customer Service Charter 2009 Version 2 1 ROTTNEST ISLAND AUTHORITY OPERATION OF ELECTRICAL SERVICES CUSTOMER SERVICE CHARTER 2009 Electrical Customer Service Charter 2009 Version 2 1 1. Introduction...5 1.1 Rottnest Island Mission Statement...5

More information

Electricity Network Performance Report New South Wales. Transmission Annual Report Outline

Electricity Network Performance Report New South Wales. Transmission Annual Report Outline Electricity Network Performance Report New South Wales Transmission Annual Report Outline Issued April 2012 New South Wales Electricity Network Performance Report Transmission Network Service Provider

More information

Size template. Grid Connection Masterclass Energex John Lansley Senior Network Solutions Engineer

Size template. Grid Connection Masterclass Energex John Lansley Senior Network Solutions Engineer Size template Grid Connection Masterclass Energex John Lansley Senior Network Solutions Engineer The average system size has doubled since 2010 Key Network Issues Reverse power on up to 12 off 11 kv feeders

More information

Contractor Connect Scheme Electrical Contractor and Worker Handbook

Contractor Connect Scheme Electrical Contractor and Worker Handbook Contractor Connect Scheme Electrical Contractor and Worker Handbook January 2016 Document release information Document number 13553681 Document title Revision status Contractor Connect Scheme handbook

More information

Electricity Service Standards

Electricity Service Standards CODE OF PRACTICE Electricity Service Standards Revised August 2015 Contents 1. Preface... 1 Format... 1 2. Application and Objectives... 2 3. Service Standards... 3 3.1 General... 3 3.2 Particular... 3

More information

No. 22 663 SUPPLEMENTARY GAZETTE THE SOUTH AUSTRALIAN GOVERNMENT GAZETTE. www.governmentgazette.sa.gov.au PUBLISHED BY AUTHORITY

No. 22 663 SUPPLEMENTARY GAZETTE THE SOUTH AUSTRALIAN GOVERNMENT GAZETTE. www.governmentgazette.sa.gov.au PUBLISHED BY AUTHORITY No. 22 663 SUPPLEMENTARY GAZETTE THE SOUTH AUSTRALIAN GOVERNMENT GAZETTE www.governmentgazette.sa.gov.au PUBLISHED BY AUTHORITY ALL PUBLIC ACTS appearing in this GAZETTE are to be considered official,

More information

Customer Installation Safety Plan. March 2015

Customer Installation Safety Plan. March 2015 Customer Installation Safety Plan March 2015 Document History Issue No. Date Approved By Summary of Changes 1 June 2014 Chief Engineer Updated and revised in line with requirement for biennial review under

More information

Electricity Networks Service Standards: An Overview

Electricity Networks Service Standards: An Overview Electricity Networks Service Standards: An Overview A Report for the NSW Department of Premier and Cabinet 2 September 2014 Final Report HoustonKemp.com Report Author/s Ann Whitfield Tom Graham Contact

More information

Electricity Industry Code. made under the Electricity Act 1994

Electricity Industry Code. made under the Electricity Act 1994 Electricity Industry Code made under the Electricity Act 1994 Seventeenth Edition: approved 16 July 2014 effective 25 July 2014 This Seventeenth Edition of the Electricity Industry Code pursuant to section

More information

Customer connection enquiry form (For the connection of loads and generators)

Customer connection enquiry form (For the connection of loads and generators) Customer connection enquiry form (For the connection of loads and generators) Please provide as much detail as possible to ensure TasNetworks can meet your requirements. When completed please attach and

More information

Customer Code of Practice & Security of Supply. Standard Distribution Licence Conditions 8, 9 and 10

Customer Code of Practice & Security of Supply. Standard Distribution Licence Conditions 8, 9 and 10 Customer Code of Practice & Security of Supply Standard Distribution Licence Conditions 8, 9 and 10 (Effective from 26th August 2004) This Code of Practice has been prepared in a form approved by Ofgem

More information

IESO Supply Deliverability Guidelines

IESO Supply Deliverability Guidelines PUBLIC IMO_GDL_0021 IESO Supply Deliverability Guidelines Issue 3.0 This document is to be used to evaluate long-term system adequacy and connection assessments Public Disclaimer The posting of documents

More information

Electricity Network Performance Report 2012/13

Electricity Network Performance Report 2012/13 Electricity Network Performance Report 2012/13 Electricity Network Performance Report Contents INTRODUCTION... 1 1 PROFILE... 2 1.1 Overview... 2 1.2 Capital works program... 4 2 NETWORK MANAGEMENT...

More information

Newmarket-Tay Power Distribution Ltd.

Newmarket-Tay Power Distribution Ltd. Newmarket-Tay Power Distribution Ltd. Electrical January 2008 590 Steven Court Newmarket Ontario L3Y 6Z2 Telephone: (905) 895-2309 Newmarket-Tay Power Distribution Ltd. No person may copy, reproduce, distribute

More information

Energex Customer Charter. For residential and small business customers

Energex Customer Charter. For residential and small business customers Energex Customer Charter For residential and small business customers Contents 1. The Energex Customer Charter 1 Energex is your electricity distributor 1 Where is the Energex network? 1 Access to information

More information

Security Policy Review: Credible Event Management. Scope and Methodology Draft for Industry 2014

Security Policy Review: Credible Event Management. Scope and Methodology Draft for Industry 2014 Security Policy Review: Credible Event Management Scope and Methodology Draft for Industry 2014 Version Date Change 1 26/03/2014 Draft for industry Position Date Prepared By: Reviewed By: Ina Ilieva, Senior

More information

The Narragansett Electric Company d/b/a National Grid, Filing to Amend Terms and Conditions for Distribution Service Docket No.

The Narragansett Electric Company d/b/a National Grid, Filing to Amend Terms and Conditions for Distribution Service Docket No. Jennifer Brooks Hutchinson Senior Counsel September 3, 2010 VIA HAND DELIVERY & ELECTRONIC MAIL Luly E. Massaro, Commission Clerk Rhode Island Public Utilities Commission 89 Jefferson Boulevard Warwick,

More information

COMPLIANCE REVIEW OF 2006/07 ASSET MANAGEMENT PLAN. Top Energy Limited

COMPLIANCE REVIEW OF 2006/07 ASSET MANAGEMENT PLAN. Top Energy Limited PB ASSOCIATES COMPLIANCE REVIEW OF 2006/07 ASSET MANAGEMENT PLAN Prepared for PB Associates Quality System: Document Identifier : 153162 Top Energy Final Report Revision : 2 Report Status : Final Date

More information

Scope of Restoration Plan

Scope of Restoration Plan RWG Area Restoration Review Worksheet (10/28/09) EOP-006-02 Directory 8 EOP-005 NYSRG Rule G Text Restoration Plan Requirement R1.Each Reliability Coordinator shall have a Reliability Coordinator Area

More information

Service Level Agreement (SLA)

Service Level Agreement (SLA) 1. Introduction This Service Level Agreement formalises Nextgen Networks commitment to our customers and outlines our operational policies and practices that define the customer experience. Nextgen is

More information

SYNERGY GAS CUSTOMER CHARTER. Small Use Business Customers

SYNERGY GAS CUSTOMER CHARTER. Small Use Business Customers SYNERGY GAS CUSTOMER CHARTER Small Use Business Customers If you don t speak English and need help with this guide, call the telephone interpreter service (TIS National) on 13 14 50 to arrange an interpreter.

More information

Guide. Minister s Guide to Auditing for Building Surveyors. April 2014

Guide. Minister s Guide to Auditing for Building Surveyors. April 2014 Guide Minister s Guide to Auditing for Building Surveyors April 2014 Guide Minister s Guide to Auditing for Building Surveyors April 2014 Department of Planning, Transport and Infrastructure 136 North

More information

FIXED CHARGE: This is a cost that goes towards making the service available, including

FIXED CHARGE: This is a cost that goes towards making the service available, including ELECTRICITY BILL COMPONENTS FIXED CHARGE: This is a cost that goes towards making the service available, including installation and maintenance of poles, power lines and equipment, and 24-hour customer

More information

Operational Audit and. Asset Management System Review. Shire of Coolgardie

Operational Audit and. Asset Management System Review. Shire of Coolgardie Shire of Coolgardie Operational Audit and Asset Management System Shire of Review Dowerin 2011 (Water Services Operating Licence) Water Services Operating Licence (Sewerage and Non-Potable Water) DRAFT

More information

Chapter 1. Network Structures

Chapter 1. Network Structures Chapter 1 Network Structures Definition Standard IEC 60038 defines voltage ratings as follows: Low voltage (): for a phase-to-phase voltage of between 100 V and 1,000 V, the standard ratings are: 400 V

More information

2010 No. 698 ELECTRICITY. The Electricity (Standards of Performance) Regulations 2010

2010 No. 698 ELECTRICITY. The Electricity (Standards of Performance) Regulations 2010 STATUTORY INSTRUMENTS 2010 No. 698 ELECTRICITY The Electricity (Standards of Performance) Regulations 2010 Made - - - - 8th March 2010 Coming into force - - 1st April 2010 CONTENTS PART I General 1. Citation,

More information

GETTING CONNECTED WITH

GETTING CONNECTED WITH GETTING CONNECTED WITH Table of Contents INTRODUCTION... 1 01 BEING A MEMBER... 1 Becoming a member... 1 Meters, reading your meter and meter testing... 2 Accessing your property... 2 Vegetation management...

More information

PROJECT NO. 40269 ORDER ADOPTING AMENDMENTS TO 25.52 AS APPROVED AT THE OCTOBER 12, 2012 OPEN MEETING

PROJECT NO. 40269 ORDER ADOPTING AMENDMENTS TO 25.52 AS APPROVED AT THE OCTOBER 12, 2012 OPEN MEETING PROJECT NO. 40269 PRIORITIES FOR POWER RESTORATION TO CERTAIN MEDICAL FACILITIES PUBLIC UTILITY COMMISSION OF TEXAS ORDER ADOPTING AMENDMENTS TO 25.52 AS APPROVED AT THE OCTOBER 12, 2012 OPEN MEETING The

More information

WESTERN AUSTRALIA HEAVY VEHICLE ACCREDITATION SCHEME (WAHVAS) BUSINESS RULES (DRAFT)

WESTERN AUSTRALIA HEAVY VEHICLE ACCREDITATION SCHEME (WAHVAS) BUSINESS RULES (DRAFT) WESTERN AUSTRALIA HEAVY VEHICLE ACCREDITATION SCHEME (WAHVAS) BUSINESS RULES (DRAFT) June 2015 DRAFT v1.3 Remove on final Contents 1. BUSINESS RULES OVERVIEW 3 1.1 Purpose 3 1.2 Legal Status of the Business

More information

Agenda do Mini-Curso. Sérgio Yoshio Fujii. Ethan Boardman. sergio.fujii@areva-td.com. ethan.boardman@areva-td.com

Agenda do Mini-Curso. Sérgio Yoshio Fujii. Ethan Boardman. sergio.fujii@areva-td.com. ethan.boardman@areva-td.com Agenda do Mini-Curso Sérgio Yoshio Fujii sergio.fujii@areva-td.com Ethan Boardman ethan.boardman@areva-td.com Agenda do Mini-Curso Sistemas de Distribuição (DMS) Characteristics of Distribution Network

More information

David Payne, P.E. Associate Director February 18, 2014

David Payne, P.E. Associate Director February 18, 2014 David Payne, P.E. Associate Director February 18, 2014 Overview of Texas A&M University State's first public institution of higher education, was opened on Oct. 4, 1876 as the Agricultural and Mechanical

More information

(2) Words and expressions used and not defined in these regulations but defined in the Act shall have the meaning assigned to them in the Act.

(2) Words and expressions used and not defined in these regulations but defined in the Act shall have the meaning assigned to them in the Act. (e) condition based maintenance means a set of maintenance actions based on continuous or frequent assessment of equipment condition, which is obtained from either of or a combination of embedded sensors,

More information

CUSTOMER CHARTER. Version 6

CUSTOMER CHARTER. Version 6 CUSTOMER CHARTER R ETA I L Version 6 Introducing Tas Gas Retail Inside the Charter Welcome to Tas Gas Retail 2 About Tas Gas Retail 3 Account Information 4 Sample Account 7 Service Charges 8 Disconnection

More information

Managing Contractor Health and Safety Risks Guidelines for Local Government

Managing Contractor Health and Safety Risks Guidelines for Local Government Managing Contractor Health and Safety Risks Guidelines for Local Government Acknowledgements This manual has been prepared by Noel Arnold & Associates Pty Ltd, occupational health and safety consultants

More information

Working for business. Workplace Safety Discount Application With employees

Working for business. Workplace Safety Discount Application With employees Working for business Workplace Safety Discount Application With employees What is the Workplace Safety Discount? Workplace Safety Discount provides a framework for building successful and sustainable workplace

More information

Document Details. 247Time Backup & Disaster Recovery Plan. Author: Document Tracking. Page 1 of 12

Document Details. 247Time Backup & Disaster Recovery Plan. Author: Document Tracking. Page 1 of 12 Document Details Title: Author: 247Time Backup & Disaster Recovery Plan Document Tracking Page 1 of 12 TABLE OF CONTENTS 1 INTRODUCTION... 3 1.1 OVERVIEW... 3 1.2 DEFINED REQUIREMENT... 3 2 DISASTER OVERVIEW...

More information

PUBLIC UTILITIES COMMISSIO~t~ Docket No. DE 15-

PUBLIC UTILITIES COMMISSIO~t~ Docket No. DE 15- Th~NALZZ~ Exhibit STATE OF NEW HAMPSHIRE t~~eeee BEFORE THE FROM FILE PUBLIC UTILITIES COMMISSIO~t~ Liberty Utilities (Granite State Electric) Corp. dibla Liberty Utilities Calendar Year 2014 Reliability

More information

GUIDELINE NO. 22 REGULATORY AUDITS OF ENERGY BUSINESSES

GUIDELINE NO. 22 REGULATORY AUDITS OF ENERGY BUSINESSES Level 37, 2 Lonsdale Street Melbourne 3000, Australia Telephone.+61 3 9302 1300 +61 1300 664 969 Facsimile +61 3 9302 1303 GUIDELINE NO. 22 REGULATORY AUDITS OF ENERGY BUSINESSES ENERGY INDUSTRIES JANUARY

More information

Residential Solar Service Agreement (RSSA) Customer Sited Solar Photovoltaic Systems

Residential Solar Service Agreement (RSSA) Customer Sited Solar Photovoltaic Systems Residential Solar Service Agreement (RSSA) Customer Sited Solar Photovoltaic Systems This Agreement is made and entered into this day of, 20, ( Effective Date ) by and between the Orlando Utilities Commission

More information

Operational Risk Publication Date: May 2015. 1. Operational Risk... 3

Operational Risk Publication Date: May 2015. 1. Operational Risk... 3 OPERATIONAL RISK Contents 1. Operational Risk... 3 1.1 Legislation... 3 1.2 Guidance... 3 1.3 Risk management process... 4 1.4 Risk register... 7 1.5 EBA Guidelines on the Security of Internet Payments...

More information

NORTHERN IRELAND ELECTRICITY Ltd STATEMENT OF CHARGES FOR USE OF. THE NORTHERN IRELAND ELECTRICITY Ltd ELECTRICITY DISTRIBUTION SYSTEM

NORTHERN IRELAND ELECTRICITY Ltd STATEMENT OF CHARGES FOR USE OF. THE NORTHERN IRELAND ELECTRICITY Ltd ELECTRICITY DISTRIBUTION SYSTEM NORTHERN IRELAND ELECTRICITY Ltd STATEMENT OF CHARGES FOR USE OF THE NORTHERN IRELAND ELECTRICITY Ltd ELECTRICITY DISTRIBUTION SYSTEM BY AUTHORISED PERSONS Effective from 1 October 2011 to 30 September

More information

PERFORMANCE AUDIT Licence Requirement / Rating Finding Recommendation Action By Whom Due Date

PERFORMANCE AUDIT Licence Requirement / Rating Finding Recommendation Action By Whom Due Date 2014 Performance Audit and Asset Management System Review, Electricity Generation Licence, POST AUDIT IMPLEMENTATION PLAN EIA = Electricity Industry Act 2004 EIMC = Electricity Industry (Metering) Code

More information

Electricity Contract. Standard Retail Contract between Aurora Energy and you. www.auroraenergy.com.au 1

Electricity Contract. Standard Retail Contract between Aurora Energy and you. www.auroraenergy.com.au 1 Electricity Contract Standard Retail Contract between Aurora Energy and you www.auroraenergy.com.au 1 Contents Introduction... 3 Your electricity contract with Aurora Energy... 3 Privacy Collection Statement...3

More information

Section / Nature of Change

Section / Nature of Change Terms of Service Document Change History The following Change History log contains a record of changes made to this document: Published / Revised Version # Author Section / Nature of Change 5 Nov 2011

More information

Management Systems Recognition Booklet

Management Systems Recognition Booklet Management Systems Recognition Booklet Page 1 of 15 Contents Revision History... 4 Related Documents... 4 1 Management Systems Recognition Booklet... 5 2 Accreditation Status... 5 3 The Recognition Process...

More information

Federal Wage System Job Grading Standards for Electric Power Controlling, 5407. Table of Contents

Federal Wage System Job Grading Standards for Electric Power Controlling, 5407. Table of Contents Federal Wage System Job Grading Standards for Electric Power Controlling, 5407 Table of Contents WORK COVERED... 2 WORK NOT COVERED...2 TITLES... 2 GRADE LEVELS... 2 SPECIAL ADDITIONAL RESPONSIBILITIES...

More information

Portland General Electric Company P.U.C. Oregon No. E-18 Original Sheet No. C-1 RULE C CONDITIONS GOVERNING CUSTOMER ATTACHMENT TO FACILITIES

Portland General Electric Company P.U.C. Oregon No. E-18 Original Sheet No. C-1 RULE C CONDITIONS GOVERNING CUSTOMER ATTACHMENT TO FACILITIES P.U.C. Oregon No. E-18 Original Sheet No. C-1 RULE C CONDITIONS GOVERNING CUSTOMER ATTACHMENT TO FACILITIES 1. Acceptance of Electricity Service By establishing or requesting a POD or by continuing an

More information

Pennsylvania Summer Reliability

Pennsylvania Summer Reliability A. Reliability Enhancement Programs In 2015, Pennsylvania Power Company s ( Penn Power or Company ) reliability plan incorporates projects and programs to enhance overall reliability. The plan is structured

More information

A Guide To Your Real Estate Purchase

A Guide To Your Real Estate Purchase A Guide To Your Real Estate Purchase Buying real estate is always an exciting experience but sometimes, it can also be daunting. This information is provided to help your purchase proceed quickly and efficiently.

More information

ABN: 92 089 531 984 Address: Level 1, 1 William Street, Perth WA 6000 Fax: [08] 9486 3346 or [08] 9486 3951 Email: customer.services@alinta.net.

ABN: 92 089 531 984 Address: Level 1, 1 William Street, Perth WA 6000 Fax: [08] 9486 3346 or [08] 9486 3951 Email: customer.services@alinta.net. Gas Supply Standard Form Contract Terms & Conditions Alinta Sales Pty Ltd ABN: 92 089 531 984 Address: Level 1, 1 William Street, Perth WA 6000 Fax: [08] 9486 3346 or [08] 9486 3951 Email: customer.services@alinta.net.au

More information

How the National Grid System Operates. Chris Gorman Lead Account Executive Syracuse

How the National Grid System Operates. Chris Gorman Lead Account Executive Syracuse How the National Grid System Operates Chris Gorman Lead Account Executive Syracuse 2 Parts of the Electric System Parts of the Electric System 1. Generating Station: Produces Electricity. 2. Transmission

More information

2. WHO IS ONLINE POWER AND GAS?

2. WHO IS ONLINE POWER AND GAS? Customer Charter ABOUT THIS CHARTER This Customer Charter provides you with a summary of your rights, entitlements and obligations under your agreement with Online Power and Gas ( us / we ) and under the

More information

Load Dispatcher (Class Code 5223) Task List

Load Dispatcher (Class Code 5223) Task List A. Load Dispatching, General Load Dispatcher (Class Code 5223) Task List 1. Prior to work shift speaks to Load Dispatcher(s), reviews hardcopy and computer logs, and looks at the dispatcher's diagram board

More information

NET METERING SUB-CODE. for Connecting Renewable Energy Generating Systems to the Distribution Network in Ghana

NET METERING SUB-CODE. for Connecting Renewable Energy Generating Systems to the Distribution Network in Ghana for Connecting Renewable Energy Generating Systems to the Distribution Network in Ghana JANUARY 2015 1 Table of Contents PART A: BACKGROUND... 1 1 Introduction... 1 1.1 Objective... 1 1.2 Status... 1 2

More information

Review of Electricity Distribution Network Minimum Service Standards and Guaranteed Service Levels to apply in Queensland from 1 July 2010

Review of Electricity Distribution Network Minimum Service Standards and Guaranteed Service Levels to apply in Queensland from 1 July 2010 Final Decision Review of Electricity Distribution Network Minimum Service Standards and Guaranteed Service Levels to apply in Queensland from 1 July 2010 April 2009 Level 19, 12 Creek Street Brisbane Queensland

More information

Our Customer Service Charter... 3

Our Customer Service Charter... 3 Document No.: COM CH00001 Page 1 of 5 TABLE OF CONTENTS Our Customer Service Charter... 3 Copies of our Charter and the Code... 3 Gas Distributor Gas Retailer... 3 Our Obligations to You... 3 Reliability

More information

Report in respect of. Service Disruption on 9 April 2012

Report in respect of. Service Disruption on 9 April 2012 Report in respect of Service Disruption on 9 April 2012 1. Introduction On 9 April 2012, a power outage occurred in the Shatin Switching Centre, one of three switching centres deployed by SmarTone Mobile

More information

IP AUSTRALIA B2B ONLINE TRANSACTION SYSTEM AGREEMENT

IP AUSTRALIA B2B ONLINE TRANSACTION SYSTEM AGREEMENT IP AUSTRALIA B2B ONLINE TRANSACTION SYSTEM AGREEMENT Name of Customer: (The Customer) A.C.N. A.B.N. IPA Customer Number Telephone Fax Email Physical Address Postcode Mail Address Postcode Name of the Customer

More information

Tel: +8 6382 4600 Fax: +8 6382 4601 www.bdo.com.au 38 Station Street Subiaco, WA 6008 PO Box 700 West Perth WA 6872 Australia DECLARATION OF INDEPENDENCE BY BRAD MCVEIGH TO THE DIRECTORS OF FOUNDATION

More information

Company Management System. Business Continuity in SIA

Company Management System. Business Continuity in SIA Company Management System Business Continuity in SIA Document code: Classification: Company Project/Service Year Document No. Version Public INDEX 1. INTRODUCTION... 3 2. SIA S BUSINESS CONTINUITY MANAGEMENT

More information

Operational Control of the UKPN Low Voltage Distribution Network for EPN and LPN Regions

Operational Control of the UKPN Low Voltage Distribution Network for EPN and LPN Regions Operational Control of the UKPN Low Voltage Distribution Network for EPN and LPN Regions Owner Name Title Signature Steve White Head of Network Control and Operations Date 16 February 2016 Authoriser Name

More information

Standard Gas. Terms and Conditions. synergy.net.au. June 2014. MKSYN0002C_P May 2014 ABN 58 673 830 106

Standard Gas. Terms and Conditions. synergy.net.au. June 2014. MKSYN0002C_P May 2014 ABN 58 673 830 106 Standard Gas Terms and Conditions June 2014 MKSYN0002C_P May 2014 synergy.net.au ABN 58 673 830 106 Contents 1. Supply of gas... 4 2. We will comply with certain codes, standards and policies... 4 3. When

More information

Asset Management Strategy

Asset Management Strategy Asset Management Strategy ElectraNet Corporate Headquarters 52-55 East Terrace, Adelaide, South Australia 5000 PO Box, 7096, Hutt Street Post Office, Adelaide, South Australia 5000 Tel: (08) 8404 7966

More information

Designation of Inspectors (Electricity) in Western Australia

Designation of Inspectors (Electricity) in Western Australia Government of Western Australia Department of Commerce Application and Renewal Designation of Inspectors (Electricity) in Western Australia DP0668_2015_01 Explanatory notes Purpose of this document This

More information

Operation and Control Microgrid and Distributed Generation. Mohammad Shahidehpour Illinois Institute of Technology

Operation and Control Microgrid and Distributed Generation. Mohammad Shahidehpour Illinois Institute of Technology Operation and Control Microgrid and Distributed Generation Mohammad Shahidehpour Illinois Institute of Technology Outline Introduction - Microgrids High Reliability Distribution Systems Perfect Power System

More information

Disaster Recovery Service Specific Terms and Conditions

Disaster Recovery Service Specific Terms and Conditions Disaster Recovery Service Specific Terms and Conditions The Sure Disaster Recovery Service supports Your business if You lose telecommunication services at one of Your sites due to an emergency such as

More information

NETWORK OUTPUT MEASURES CONSULTATION

NETWORK OUTPUT MEASURES CONSULTATION NETWORK OUTPUT MEASURES CONSULTATION Great Britain s electricity transmission network transmits high-voltage electricity from where it is produced to where it is needed throughout the country. It broadly

More information

Emergency Alert Contracts and Contract Management Under the New Zealand Electricity Industry

Emergency Alert Contracts and Contract Management Under the New Zealand Electricity Industry Victorian Governm n! ol ilor' Offict LBS Variation Variation of Intergovernmental Agreement in relation to the Management of the Contract for the National Emergency Warning System between The State of

More information

STATUTORY INSTRUMENTS 2012 No. _

STATUTORY INSTRUMENTS 2012 No. _ STATUTORY INSTRUMENTS 2012 No. _ THE ELECTRONIC SIGNATURES REGULATIONS 2012 ARRANGEMENT OF REGULATIONS Regulation PART I-PRELIMINARY 1. Title. 2. Interpretation PART II - LICENSING AND RECOGNITION OF CERTIFICATION

More information

Transmission Business Electrical Incident & Safety Performance Reporting Guide

Transmission Business Electrical Incident & Safety Performance Reporting Guide Transmission Business Electrical Incident & Safety Performance Reporting Guide December 2011 Version 1.0 Energy Safe Victoria PO Box 262 Collins Street West MELBOURNE VIC 8007 AUSTRALIA Telephone (03)

More information

Electrical Shore Connections / Cold Ironing

Electrical Shore Connections / Cold Ironing STANDARD FOR CERTIFICATION No. 2.25 Electrical Shore Connections / Cold Ironing JULY 2014 The electronic pdf version of this document found through http://www.dnv.com is the officially binding version

More information

Balancing and Settlement Code BSC PROCEDURE BSCP537. QUALIFICATION PROCESS FOR SVA PARTIES, SVA PARTY AGENTS AND CVA MOAs

Balancing and Settlement Code BSC PROCEDURE BSCP537. QUALIFICATION PROCESS FOR SVA PARTIES, SVA PARTY AGENTS AND CVA MOAs Balancing and Settlement Code BSC PROCEDURE BSCP537 QUALIFICATION PROCESS FOR SVA PARTIES, SVA PARTY AGENTS AND CVA MOAs APPENDIX 3 GUIDANCE NOTES ON COMPLETING THE SAD Version 2.0 Date: 10 September 2007

More information

Electric System Performance Review Trustees Briefing. April 2013

Electric System Performance Review Trustees Briefing. April 2013 Electric System Performance Review Trustees Briefing April 2013 Electric Reliability Indices All Metrics Continue to Perform Within Historical Range Reliability Index 2012 Trend to 5-Year Avg. LIPA MSA

More information

I n t e l l i g e n t N e t w o r k S o l u t i o n s

I n t e l l i g e n t N e t w o r k S o l u t i o n s This NetWolves Service Level Agreement ("SLA") provides detailed Descriptions of Metrics for NetWolves service performance and installation for Business Internet Access Services ( BIA Services ). This

More information

TERMS AND CONDITIONS

TERMS AND CONDITIONS Virginia Electric and Power Company TERMS AND CONDITIONS XXIV. GENERATOR INTERCONNECTION STANDARD Electric generator interconnection service includes only the ability to interconnect an electric generator

More information

injury management practices

injury management practices audit guidelines injury management practices guidelines to understanding the audit standards for the injury management section of the acc partnership programme ACC2465 Printed September 2006 These guidelines

More information

How To Calculate Service Credits

How To Calculate Service Credits Telnes, Inc. Service Level Agreement Service Metrics SLA for SDSL and T1 Telnes, Inc. is committed to providing the highest quality of service to our Customers. Our goal is to not only meet our Customer

More information

INCORPORATING RELIABILITY CALCULATIONS IN ROUTINE NETWORK PLANNING: THEORY AND PRACTICE

INCORPORATING RELIABILITY CALCULATIONS IN ROUTINE NETWORK PLANNING: THEORY AND PRACTICE ICORPORATIG RELIABILIT CALCULATIOS I ROUTIE ETWORK PLAIG: THEOR AD PRACTICE J.G. SLOOTWEG*, P.M. VA OIRSOUW** *Essent etwerk B.V., P.O. Box 856, 5201 AW, s-hertogenbosch **Phase to Phase B.V., P.O. Box

More information

NATIONAL FIRE ALARM AND SIGNALING CODE

NATIONAL FIRE ALARM AND SIGNALING CODE GAP.11.1.1.0 A Publication of Global Asset Protection Services LLC NATIONAL FIRE ALARM AND SIGNALING CODE INTRODUCTION National Fire Protection Association (NFPA) documents describe a level of fire protection

More information

Amcom Service Level Agreement

Amcom Service Level Agreement Amcom Service Level Agreement September 2015 Amcom Pty Ltd ACN 009 336 341 amcom.com.au Level 22, 44 St Georges Terrace, Perth WA 6000 GPO Box 2541, Perth WA 6001 Contents Definitions and Interpretation...

More information

Request to Increase Insurance Life Event

Request to Increase Insurance Life Event Request to Increase Insurance Life Event Accumulation Scheme (Division 5) members only Use this form to apply to increase your insurance cover when a specific life event has occurred. As an accumulation

More information

CONNECTING YOU TO SPECIALIST ELECTRICAL SUPPORT services

CONNECTING YOU TO SPECIALIST ELECTRICAL SUPPORT services CONNECTING YOU TO SPECIALIST ELECTRICAL SUPPORT services SpecialistS IN ELECTRICAL SUPPORT SERVICES TO MINING, UTILITIES & industry Ampcontrol is committed to supporting our customers to maintain efficient

More information

Title 20 PUBLIC SERVICE COMMISSION. Subtitle 50 SERVICE SUPPLIED BY ELECTRIC COMPANIES. Chapter 02 Engineering

Title 20 PUBLIC SERVICE COMMISSION. Subtitle 50 SERVICE SUPPLIED BY ELECTRIC COMPANIES. Chapter 02 Engineering Title 20 PUBLIC SERVICE COMMISSION Subtitle 50 SERVICE SUPPLIED BY ELECTRIC COMPANIES Chapter 02 Engineering Authority: Public Utility Companies Article, 2-121, 5-101 and 5-303, Annotated Code of Maryland.

More information

ESB Networks Response. ERGEG Consultation. Voltage Quality Regulation in Europe

ESB Networks Response. ERGEG Consultation. Voltage Quality Regulation in Europe NETWORKS ESB Networks Response to ERGEG Consultation on Voltage Quality Regulation in Europe Date: 22 February 2007 Distribution System Operator ESB Networks Page 1 of 12 Contents 1.0 INTRODUCTION...3

More information

City of Buffalo Municipal Electric Utility Energy Emergency Response

City of Buffalo Municipal Electric Utility Energy Emergency Response City of Buffalo Municipal Electric Utility Energy Emergency Response Table of Contents Page 1. Goals 2 2. Types of Energy Emergencies..3 3. Utility Emergency Operating Plans.4 4. Link to General Reliability/Outage

More information

CUSTOMER CHARTER. Small Customer Charter

CUSTOMER CHARTER. Small Customer Charter CUSTOMER CHARTER Small Customer Charter Version 2.0 6 November 2014 1. Our commitment to you The terms and conditions agreed between you and Pacific Hydro Retail Pty Ltd (ABN 43 155 908 839) (hereafter

More information

PA PUC AERS & Metropolitan Edison Company Site Visit

PA PUC AERS & Metropolitan Edison Company Site Visit PA PUC AERS & Metropolitan Edison Company Site Visit October 26, 2010 Scott Lowry Director-Operation Services, Met-Ed Andrew Zulkosky Manager-Engineering, Met-Ed Curt Christenson Manager-York Customer

More information

SOUTHERN MARYLAND ELECTRIC COOPERATIVE, INC. HUGHESVILLE, MD

SOUTHERN MARYLAND ELECTRIC COOPERATIVE, INC. HUGHESVILLE, MD SOUTHERN MARYLAND ELECTRIC COOPERATIVE, INC. HUGHESVILLE, MD HOLLAND CLIFF HEWITT ROAD 230 KV TRANSMISSION LINE PROJECT ELECTRIC ALTERNATIVE EVALUATION STUDY BLACK & VEATCH CORPORATION B&V Project 146026(G)

More information

The Electrical Safety Regulation (pre and post 1 January 2014)

The Electrical Safety Regulation (pre and post 1 January 2014) The Electrical Safety Regulation (pre and post 1 January 2014) The following table provides an overview comparison between the Electrical Safety Regulation 2002 (the ESR 2002) current as at 1 July 2013

More information

Networks. ESB Networks Ltd Basis of Charges for Connection to the Distribution System. Commercial and Customer Asset Management ESB Networks Ltd.

Networks. ESB Networks Ltd Basis of Charges for Connection to the Distribution System. Commercial and Customer Asset Management ESB Networks Ltd. Networks ESB Networks Ltd Basis of Charges for Connection to the Distribution System Revision Date: 14/01/20010 Revision No.: 1 Document No: DOC-10129-AXQ Issued by: ESB Networks Ltd Approved by : CER

More information

Monitoring Quality of Service in Serbia. Belgrade, 2. November 2007.

Monitoring Quality of Service in Serbia. Belgrade, 2. November 2007. Monitoring Quality of Service in Serbia Belgrade, 2. November 2007. Serbian Power Sector Number of customers: 3.33 mil. 1 TSO 5 DSO/Supply of captive customers 5 generation companies 23 Trading/Supply

More information

TECHNICAL INTERCONNECTION REQUIREMENTS FOR DISTRIBUTED GENERATION. Micro Generation & Small Generation, 3-phase, less than 30 kw

TECHNICAL INTERCONNECTION REQUIREMENTS FOR DISTRIBUTED GENERATION. Micro Generation & Small Generation, 3-phase, less than 30 kw TECHNICAL INTERCONNECTION REQUIREMENTS FOR DISTRIBUTED GENERATION Micro Generation & Small Generation, 3-phase, less than 30 kw i COPYRIGHT 2010 HYDRO ONE NETWORKS INC. ALL RIGHTS RESERVED ii LIMITATION

More information

NETWORK MANAGEMENT STRATEGY

NETWORK MANAGEMENT STRATEGY ABN 85 082 464 622 NETWORK MANAGEMENT STRATEGY DOCUMENT NUMBER: NW-#30065608-V6 DATE: 12 MAY 2011 NW-#30065608-v6-Network_Management_Strategy.DOC Page 1 of 20 This page is intentionally blank. NW-#30065608-v6-Network_Management_Strategy.DOC

More information

Electric Distribution System Owner (Wire Owner) Service Quality and Reliability Performance, Monitoring, and Reporting Rules

Electric Distribution System Owner (Wire Owner) Service Quality and Reliability Performance, Monitoring, and Reporting Rules Rule 002 (Formerly EUB Directive 002) Electric Distribution System Owner (Wire Owner) Service Quality and Reliability Performance, Monitoring, and Reporting Rules The Alberta Utilities Commission (AUC/Commission)

More information

PERSONAL ALERT SYSTEMS REBATE SCHEME PROVIDER PANER DEED

PERSONAL ALERT SYSTEMS REBATE SCHEME PROVIDER PANER DEED DATED DAY OF 2015 PERSONAL ALERT SYSTEMS REBATE SCHEME PROVIDER PANER DEED between MINISTER FOR COMMUNITIES AND SOCIAL INCLUSION - and - [INSERT PARTY NAME] ACN [INSERT] Page 1 of 1 TABLE OF CONTENTS BACKGROUND...

More information

2014 ELECTRIC SYSTEM RELIABILITY REPORT CITY OF ANAHEIM PUBLIC UTILITIES DEPARTMENT

2014 ELECTRIC SYSTEM RELIABILITY REPORT CITY OF ANAHEIM PUBLIC UTILITIES DEPARTMENT 2014 ELECTRIC SYSTEM RELIABILITY REPORT CITY OF ANAHEIM PUBLIC UTILITIES DEPARTMENT Contents Overview... 3 1.0 Electric System Reliability... 4 1.1 Annual Reliability Data with Utility Comparisons... 4

More information

CUSTOMER-FACING PERFORMANCE MEASURES

CUSTOMER-FACING PERFORMANCE MEASURES CUSTOMER-FACING PERFORMANCE MEASURES CUSTOMER FEEDBACK AND RESPONSE Transpower New Zealand Limited March 2013 Customer-facing performance measures Transpower New Zealand Limited 2007. All rights reserved.

More information

CUSTOMER CHARTER NEXT BUSINESS ENERGY PTY LIMITED ABN 91 167 937 555

CUSTOMER CHARTER NEXT BUSINESS ENERGY PTY LIMITED ABN 91 167 937 555 CUSTOMER CHARTER NEXT BUSINESS ENERGY PTY LIMITED ABN 91 167 937 555 NEXT BUSINESS ENERGY A summary of the rights, entitlements and obligations of small customers This document sets out some of the rights,

More information

ELECTRICITY SUPPLY/ TRADE LICENSE KORLEA INVEST A.S

ELECTRICITY SUPPLY/ TRADE LICENSE KORLEA INVEST A.S Hamdi Mramori Street, No 1 Prishtina 10000 Kosovo Tel: +381 (0) 38 247 615 ext. 103 Fax: +381 (0) 38 247 620 e-mail: info@ero-ks.org www.ero-ks.org ELECTRICITY SUPPLY/ TRADE LICENSE GRANTED TO: KORLEA

More information