1 Performance and progress at Sellafield

2 The Sellafield Site In 2008 the Nuclear Decommissioning Authority (NDA) appointed Nuclear Management Partners (NMP) as the Parent Body Organisation for Sellafield Ltd. The consortium of three world class organisations, URS, Amec Foster Wheeler and Areva, was tasked with bringing resources and processes from across the globe to improve the performance of the world s most challenging nuclear site Sellafield. 02

3 The increasing demand for accelerated decommissioning by HM Government resulted in the development of the Nuclear Decommissioning Authority (NDA) in The NDA s main priority was to clean-up and reduce the hazards at Sellafield. It was accepted that, making improvements on a site suffering from ageing infrastructure, a poor record of the historic waste inventory generated through the days of the Cold War and a weakened planning and project management capability, was an enormously difficult task and would not to be achieved over night. However, since 2008, under the leadership of NMP, the Sellafield workforce has delivered a succession of site records and first time achievements, with a particularly notable improvement in overall performance in the last 18 months. Some of the highlights include the removal of radioactive waste from ponds and silos for the first time in decades, the first returns of high level waste to the countries of origin, completion of the overseas fuel reprocessing programme and generation of over 700m of efficiency savings. For the last two years, the Sellafield workforce has consecutively achieved its best ever overall safety levels also saw the largest ever entry of apprentices at 170 and the planned 2015 intake of 200 young people will more than treble the figure in 2008 when NMP first arrived at Sellafield. NMP has continued to invest in the local community, with almost 25m now donated from its fee to charitable organisations and major socioeconomic projects. It has however, not been an easy journey. There are areas where better and faster progress was expected and hoped for, particularly in the major projects area, where inherent uncertainty over historic waste inventories has resulted in engineering complexities and associated cost increases. While NMP has made good progress in understanding the technical challenges faced by these major projects, cost and timescale of delivery has inevitably been an issue of concern. Over the six years of the contract, however, NMP has created an environment in which Sellafield Ltd has had the resources, processes and support in place to build capability and make significant progress. This capability has enabled the site to deliver tangible improvements across almost all areas, as detailed later in this document. Stakeholders understandably have a strong desire for demonstrable progress at Sellafield, given the level of public investment that the site demands. This year s record performances and best ever safety levels are testament to the strides that have been made at Sellafield. As the site transitions to the NDA s new management arrangement, NMP is proud to have built the foundations for sustained success. We recognise the achievements of the site in the last six years and thank NMP for their support in stewarding Sellafield through a crucial phase of delivery and planning. January 2015 Rt Hon Edward Davey MP Secretary of State for Energy and Climate Change 03

4 Sellafield The world s most challenging nuclear site The UK s nuclear industry began at Sellafield and the site is home to the nation s first full-scale nuclear reactors, the Windscale Piles, built for national defence purposes. It is also home to the world s first commercial-scale nuclear power station, Calder Hall, and houses two nuclear fuel storage ponds from the 1940/50s and two nuclear waste silos also built years ago. The scale of the challenge 04

5 Today Sellafield is the world s most complex and challenging nuclear site. 1,200 buildings, over 200 of which hold nuclear inventory, are contained on two square kilometres of land, making Sellafield one of the UK s largest industrial sites. One hundred of these facilities are individually categorised as being at least equivalent (in some cases significantly higher) to a nuclear reactor in terms of potential hazard and security status. Sellafield is now also one of the UK s largest construction sites, with multi-billion pound facilities being built to help deliver the clean-up mission. There are more than 450 ongoing engineering and construction projects with 17 valued at over 100m. Windscale Piles The main challenges facing the site today originate from the very early days of the UK s nuclear weapons programme. Radioactive materials were accumulated throughout the 1940s, 50s and 60s and left in inadequate long term storage conditions in the site s legacy ponds and silos. Poor historical record-keeping during the early days of weapons production for the Cold War, meant little was known about the nuclear waste housed in some of the original facilities at Sellafield. These historic facilities were not built to meet modern design standards and now stand within a congested footprint of a site that has grown in mission and complexity over the decades, resulting in an interlinked array of old and new processing plants and infrastructure. Initiatives such as security enhancement and the need to comprehensively address the resilience issues raised by events at Fukushima provided additional challenge to an already intensive programme of change being driven by NMP. 05

6 Since 2008 NMP has brought in senior leaders and specialists from its three parent organisations to lead and support Sellafield Ltd in tackling its multiple challenges. Through its reach to almost two hundred thousand people in its combined workforce, NMP has been able to bring in resources at speed to deal with immediate issues, while more strategic deployment of NMP employees (or enhancers) to train and coach Sellafield incumbent staff has delivered enhanced capability on the site, resulting in a turnaround in the site s performance. Driving improvement and change Resources In accordance with the enormity of the challenge at Sellafield, NMP has been able to provide some of its best people to lead the Sellafield Ltd organisation. This strength of leadership has driven the site to adapt and respond successfully to its new priority of decommissioning. The value brought by NMP enhancers can be found across the site. Examples include: technical support to the Waste Vitrification Plant (where highly active liquor is converted into a solid stable form), which is now achieving world record levels of performance; benchmarking for post operational clean out of radioactive materials at the end of a facility s operational lifetime; improved cost estimating; benchmarking the design of new facilities; rolling out a disciplined operations culture across operating plants; support in the production of the site s long term performance plan. Enhancers have also driven improvements in commercial operations, supply chain management and in contracting strategies for capital projects. They have delivered coaching activities to support project and engineering managers in robust decision making and leadership skills. Bringing in global expertise and experience to respond to Sellafield Ltd s targeted requests for support has inevitably carried a cost. In the early stages of the contract, NMP appointed over 120 enhancers on the site. Today, as efforts have been focused on more specific areas of the site and skill transfer to incumbent staff has been affected, the complement of enhancers has been reduced to less than 30. At the very start of the contract, NMP committed to the development of incumbent Sellafield Ltd staff such that they could replace NMP secondees over a period of time. NMP has delivered on this commitment, with almost half of the senior team now being Sellafield Ltd employees. NMP has also enabled Sellafield staff to attend a number of its parent companies corporate training programmes, such as the Leadership Development Programme based in South Carolina and the Major Projects Forum in Denver. 06

7 NMP Global Experience and Expertise Savannah River URS Birchwood, UK Amec Foster Wheeler La Hague AREVA 07

8 Driving improvement and change continued Setting out a vision for the future Sharing Processes and Benchmarking Capability NMP has introduced global best practice and proven processes to improve performance and meet safety requirements the first priority at Sellafield. NMP s parent companies have introduced processes developed over many years across their world-wide operations to share international best practice. Safety processes, including MoveSMART and a revitalised employee led Peer to Peer behavioural safety campaign, have helped to deliver improved worker safety to the current record levels. Safety and operational performance has also benefited from the introduction of NMP processes such as Line of Sight, ACEMAN, Plant Operational Control Centres, Fleet Calls, PAIS and URS s project management programme, Execution with Certainty. All of these are designed to improve effectiveness, efficiency and safety through a strict code of operational conduct and project management discipline. NMP s Journey to Excellence programme has provided staff with a clear vision of the future at Sellafield and the steps needed to make this a reality. Efficiency based programmes have also been introduced by NMP. Roll Back for example, has seen over 930,000 square feet of plant areas removed from radiological access restrictions, allowing more efficient operational conditions for workers. Sellafield staff have been involved in benchmarking exercises with NMP parent companies facilities such as the Savannah River and Hanford sites in the US and at La Hague and Marcoule in France. Since NMP took over at Sellafield, the relationship with the World Association of Nuclear Operators (WANO) has flourished, with a demanding programme of benchmarking and sharing of international best practice that has delivered significant benefits to the site. 08

9 Resourcing for the future Our greatest challenge Legacy Pond and Silos Strengthening the Long Term Capability on the Site Accordingly, NMP implemented a full restructuring of the organisation which focused on providing clear links to the long term mission of the site. The Sellafield workforce is one of the most competent and well trained in the world. It was clear though, that there was a need to develop the skills and talent to address the new site decommissioning priorities. Since 2008, NMP and the NDA have re-aligned and broadened the focus of Sellafield from a history of prioritisation on commercial operations to the safe clean-up and decommissioning mission on the site. This is reflected in the enhanced role of the Decommissioning Directorate. In specific response to the challenges posed by the site s legacy ponds and silos, NMP implemented organisational changes to raise the profile and capability of this priority decommissioning area. A Major Projects Group was also established to implement NMP s commitment to improved project delivery. As a consequence, Sellafield Ltd is better equipped and structured to respond to the challenges of the decommissioning mission now and in the future. During NMP s tenure as the PBO, record numbers of apprentices and graduates have been introduced to the site. Sellafield Ltd was recognised in the prestigious Top 100 Apprenticeship Employers list by the National Apprenticeship Service and the Deputy Prime Minister, Nick Clegg, said; I would like to take this chance to congratulate Sellafield Ltd on your success at this year s National Apprenticeship Awards. In 2015, Sellafield was named as one of the best graduate employers in the UK. Ranking eighth in the Job Crowd Top 100 Graduate Employers list Sellafield Ltd came ahead of many major companies like Jaguar Land Rover, Sky, Virgin Media, Nestlé and Sainsbury s. The list covers all industries and sectors, with the only qualifying criteria being that a firm must take on more than 30 graduates each year to be eligible for consideration. The supply chain resource has also been strengthened through the introduction of long term supplier framework contracts which have introduced a broader base of companies to the site, providing the opportunity to build long term capability in the supply chain. Sellafield Ltd has also increased the spend to SMEs to meet and then exceed the NDA estate target of 20 per cent. 09

10 In 2009, NMP launched the Integrated Change Programme to make sure the early changes being made at Sellafield were being coordinated in an effective way. In 2014, we launched the Excellence Plan for the site as a successor to the ICP. This is the formal programme to achieve the performance improvements that will enable the Sellafield Ltd strategy. Making change the right way The Excellence Plan, which will guide the site over the coming years, beyond NMP s tenure, has clear prioritisation and a strong focus on measurable business benefits. It is underpinned, sanctioned and assured. The Excellence Plan has been built to deliver what is most needed where it is needed most. It is aligned directly with the priorities and strategies of the delivery divisions, and has provided a proactive framework for embedding improvements and best practices from our parent companies. 10

11 While the Excellence Plan sets out the things that we need to improve in order to deliver the Sellafield Ltd Strategy, it does not set out the full scope of what we need to deliver at Sellafield and when we will do it. This is detailed in the separate, but interdependent Sellafield Plan (commonly known as the Performance Plan). Planning for success Whilst an inherited plan was in place when NMP took ownership of Sellafield Ltd in November 2008, it was collectively agreed that the plan was not realistic and could not be delivered. In 2011, NMP delivered the site s first underpinned Performance Plan. It set out how NMP would apply its global experience to improve operations, generate efficiencies and deliver detailed programmes of work. An updated plan for the site was launched in It incorporates the extensive knowledge that has been acquired on the site over the last six years. This Plan will lead the site into a pivotal phase in its history full scale high hazard retrieval. 11

12 Addressing the priorities Sellafield s new clean-up mission meant it faced more extensive and complex projects than ever before. NMP set out to rebuild project management capability in the organisation by putting the right people in the right roles and bringing in proven processes from its three organisations. Execution with Certainty was a proven way of improving the execution of projects on URS s other sites across the world. It ensured that project safety became the key consideration for projects and introduced streamlined approaches to reduce time, expense and risk and ensure quality performance. It also ensured integrated project phases to eliminate gaps in scope and integrated project teams to eliminate gaps in responsibilities. NMP also introduced a new gated process, leading to a more independent and structured approach and increased the focus on risk management. Under NMP s guidance, Sellafield was the first NDA site to be accredited by the Association of Project Managers for its training programme. 12

13 Legacy Ponds and Silos Legacy Ponds and Silos NMP and NDA have together brought about a new focus on clean-up of the legacy ponds and silos; the historic facilities that represent some of the highest risks on the site. NMP created, for the first time, a fully integrated plan for the retrieval and treatment of the waste from these ponds and silos, thus forming the basis of the spending review and better engagement with Government on the priorities for the site. The building blocks are now in place for legacy ponds and silos and the site is seeing tangible results in removing these key hazards. Driving Reliable Operations The Operations workstream is a fundamental one at Sellafield. It is all about operating the plants in a professional, consistent and safe way, whilst ensuring that nuclear safety is the overriding priority. Rebuilding the plan for Sellafield operations enabled a clear link between the NDA strategy and key decisions about the future of the site and its missions. NMP s focus on Conduct of Operations and Line of Sight to the overall strategy was embedded throughout Sellafield to improve the reliability and safety of operational plants. Operations moved from a reactive process to one that looked at delivering consistent and safe operations getting the right people, resources and instructions in place for each piece of work. NMP s Line of Sight initiative demands that the performance of all plants is reviewed on a daily basis, involving the process workers physically doing the work through to Director level. This enables early identification of issues and corrective action, improvements in maintenance and availability of plants and addressing of any safety issues and human factors affecting performance. Line of Sight also incorporates preparing for and execution of outage management. It has brought about more reliable operational outcomes, increased availability of plant, reduced contamination incidents, improved nuclear safety and improved maintenance regimes. Root cause analysis of failure modes in production have been utilised to focus the programmes that will lead to a medium to long term improvement in operational performance. Ultimately, Line of Sight provides confidence in the site s ability to deliver the NDA targets of finishing reprocessing by 2018 (Thorp) and Magnox (2019), reducing volumes of high level waste and carrying out future retrievals in the high hazard legacy plants. Ensuring the Full Lifetime of Thorp The Thermal Oxide Reprocessing Plant (Thorp), which supports more than 2,000 jobs, is fundamentally dependent on the downstream high level waste evaporators and vitrification plant. When NMP arrived at Sellafield, the Thorp programme was at a high risk of being cut short as a result of uncertainty over residual evaporator lifetimes. This risk not only had commercial implications for Sellafield Ltd, NDA and Government, but also a severe socioeconomic impact in West Cumbria. Through the expertise brought by NMP, and in particular parent company Areva, detailed inspections and assessments of the residual evaporator lifetime has resulted in comprehensive safety cases being made to restart, continue and extend operations until such times as the new Evaporator D project comes on line. This has secured the ongoing operation of Thorp with the associated commercial and socio-economic risks now being mitigated. 13

14 Making safety the priority Sellafield is a highly hazardous nuclear site. Regardless of the site s mission, NMP has put safety as its highest priority. Early in its tenure, NMP drove an enhanced focus on employee safety and the safe management of nuclear materials. NMP initiated a drill down on safety performance to identify gaps and address shortfalls. A continuous programme of benchmarking and assessment was introduced. NMP enhanced nuclear safety awareness through a nuclear safety training course and the establishment of standard nuclear safety dashboards across the site. Under NMP, Sellafield Ltd increased its assurance inspection team in size and strength and embedded it within each operating unit. To enhance the safety of employees, NMP introduced a number of programmes under an umbrella style of industrial safety including ACEMAN The human performance tool helped teams to identify, recognise and address the barriers they faced in their work. MoveSMART The occupational injury prevention programme was introduced to raise safety awareness and ease strain and stresses on the body to help prevent injuries. Peer to Peer Observations This safety approach, built upon the existing Behavioural Safety programme, focuses on encouraging employees to think about each other s safety and converse to reinforce safe behaviours or prevent an unsafe act. Charities also benefit from the programme as they receive money for each observation made. The safety initiatives introduced by NMP at Sellafield are now firmly embedded in the site and executed by the Sellafield Ltd workforce as part of their everyday practices. This step change in safety culture has resulted in Sellafield s best ever overall safety records in both 2013/14 and 2014/15. 14

15 In 2013 NMP led the creation of the Sellafield Ltd Strategy, the Key to Britain s Energy Future. This provided a strategic framework for Sellafield, driving future success. Strategies for success Sellafield Ltd Strategy Underpinned for the first time by specific strategic objectives, the Strategy set out to ensure: Safe, secure stewardship of the site, making demonstrable progress in the completion of commercial operations and the safe acceleration of risk and hazard reduction and delivering a return on investment. This strategy successfully drove the creation of the Sellafield Plan and the Excellence Plan setting the site in the right strategic direction for success. Sellafield Performance Plan Performance Plan 2011 provided the site with an underpinned performance plan for the first time. It gave the site a fully integrated lifetime plan that was aligned to Government budget provision for the first time in many years. The 2014 updated version of the Plan incorporated the much greater knowledge of the site and how to clean it up. Sellafield Excellence Plan The Excellence Plan 2014/15 builds on the achievements of previous improvement programmes. The Excellence Plan focuses on safer performance; best value from the supply chain; better financial and schedule performance; fewer unplanned outages and getting the right people with the right skills at the right time. The Plan will drive forward ongoing improvements at the site. 15

16 Performance and progress Since 2008, much has been achieved through the people, resources and processes that NMP has brought to the site. Decommissioning progress NMP has led the site in changing its focus to nuclear clean-up and decommissioning on behalf of the NDA. Since 2008, some significant milestones have been achieved by Sellafield Ltd under NMP leadership. Pile Fuel Storage Pond (PFSP) The PFSP, a sub-divided open air storage pond built in the late 1940s, was used to store, cool and prepare fuel from the original Windscale site reactor for reprocessing. It has not received any waste for decades and has, until recent times sat dormant, containing more than 650 tonnes of waste material and fuel, under a care and maintenance regime. This material needs to be removed and immobilised through modern waste treatment processes. This is made extremely difficult through uncertainty over exact inventory, the fact that the pond has remained open to the elements for over 60 years and the radioactive sludges that have built up over the period. Under the leadership of NMP, the first spent fuel to be removed from the pond in over 50 years was retrieved in Since then, more than a hundred tonnes of material has been removed, the equivalent weight to a blue whale or a Boeing 757 aircraft. Magnox Swarf Storage Silos (MSSS) MSSS is a series of wet silos into which fuel cladding from the early Magnox programme was tipped. It represents one of the highest hazards on the site. The objective is to retrieve and package the material into a safe form. Originating from the 1950s, the building was not designed to support retrieval of material which again is uncertain in composition and is in a difficult chemical form. The structure of the building has been strengthened and active liquor has been removed and safely treated. This represents about three per cent of the overall activity in MSSS, but also equates to a tenth of activity released at Chernobyl. Another major step forward in risk reduction at the facility has been achieved by introducing passive ventilation to all 22 compartments. 16

17 Safety and Security The Site has achieved its best ever overall safety records consecutively in the past two years. The current Lost Time Accident (LTA) rate is now at a record low level. For the first time in the site s history, there has been a full year without a nuclear reportable event, an environmental reportable event or any internal dose cases. This has all been achieved despite having to make 30,000 man entries to decontaminate a plant area the size of seven football pitches over an 11 month period. In 2014, Sellafield Ltd broke nuclear records, winning nine ROSPAs (Royal Society for Prevention of Accidents) for safety performance the best performance by a nuclear operator. The site has also been able to respond to the demand for enhanced resilience measures following the events of Fukushima and has delivered significant site security improvements through the Security, Emergency Management and Resilience Programme valued at over 1bn. The safety and security of Sellafield is the overriding priority Windscale Pile Chimney Demolition The 530 tonne filter gallery that sat on top of the 110 metre high chimney contaminated during the Windscale fire of 1957, has recently been demolished changing the Sellafield skyline forever. The filter gallery was built of concrete, brick and steel and has been removed using conventional equipment in a very unconventional environment. First Generation Magnox Storage Pond (FGMSP) Constructed in the 1950s to store, cool and prepare Magnox fuel for reprocessing, FGMSP currently holds legacy skips of used nuclear fuel, which need to be removed and repacked prior to removal. This facility represents a significant challenge due to fuel fragments, debris and a significant build-up of radioactive sludge, resulting from fuel corrosion over the decades. The first progress in decades has been made into retrieving the material from this open air pond. As with the PFSP, the biggest challenge is uncertainty over the historic inventory of FGMSP. To aid characterisation and assessment of the material, Sellafield staff have deployed technology usually used in hazardous deep sea conditions, in the form of remotely operated mini submarines. The machines are mounted with underwater cameras to provide real time images of the pond s contents and can now be equipped with eductors (vacuum cleaners) and equipment to sling previously unmanageable skips. Having gained images of the material that has been previously inaccessible for decades, and following completion of the Sludge Packaging Plant in 2014, sludge retrievals will soon commence, representing a major milestone in reducing the radiological hazard at Sellafield s legacy plants. Other Decommissioning Achievements under NMP Leadership The sixth highest hazard on the site has recently been eliminated by completing the repacking of the legacy Plutonium Contaminated Material Filter Stillage, moving them to newer engineered stores, four years ahead of schedule. Other achievements include the first completion of decommissioning of a power producing nuclear reactor and safe completion of Europe s largest asbestos removal projects. 17

18 Operations, Major Projects and life time estimates Thorp Reprocessing Plant Waste Vitrification Plant Reprocessing Plants In 2014/15, Sellafield Ltd achieved some of its best plant performances in many years including Thorp, Magnox and Vitrification Plant throughputs. There has also been the best ever performance of Advanced Gas-cooled Reactor receipts, enabling EDF to improve the resilience of their spent fuel management to keep stations producing electricity for the whole of the UK. A key factor in these operational throughput improvements has been a significantly improved outage management system implemented over the last six years. Reliability and safety of operational plants across Sellafield has also been secured through the introduction of new approaches from NMP s extensive experience around the world including the commercial nuclear industry and the Department of Energy in the USA. Vitrification Plant and High Level Waste Under NMP and, specifically the expertise provided by Areva through its work at the company s La Hague facility, the Sellafield Waste Vitrification Plant (WVP) has achieved world record performance. Early in the contract period, NMP oversaw the first return of High Level Waste to its countries of origin, an achievement that many anti-nuclear commentators and industry experts alike thought would never happen. Today numerous shipments have safely repatriated High Level Waste to its originating nations. NMP intervention and expertise enabled Evaporator B to be brought back into service and has lengthened the lifetime of Evaporator C. This has ensured the ongoing operation of Thorp and, combined with design modifications to the new fourth Evaporator, has removed the previously planned need for a fifth. Strengthening the Infrastructure Historically, Sellafield operations have frequently been restricted by the fragility of an ageing utilities. The site s electrical distribution system is of the equivalent scale to the 100,000 populated city of Carlisle, and has suffered from a lack of attention over many years. Under NMP, two 40-year-old electrical transformers were replaced ahead of schedule, removing the highest risk to the site s electrical distribution system. The site has now enjoyed a period of over a year without a power induced operational outage. Major Projects Perhaps the most challenging aspect of the site that NMP has faced is the design and construction of major projects associated with the clean-up mission. The inherent uncertainties associated with historic waste inventories and consequential engineering complexities continually serve to frustrate predicted delivery timescales and cost estimates. The nature of the nuclear industry means that worst case scenarios must be fully addressed in the design of a processing facility. Uncertainty over the chemical composition and physical condition of legacy waste streams inevitably lead to increasing costs and timescales as more is learned about the true nature of the challenge. NMP and Sellafield Ltd have made significant inroads to the understanding of historical waste issues, but as a consequence, have been obliged to increase cost estimates and projected timescales. While this has attracted public criticism, the work carried out in recent years has been essential to ensure safe delivery of the clean-up mission in future years. 18

19 Sellafield legacy pond a clean-up priority Gaining Control Over Major Projects Estimates and Actual Costs The scale of the challenge in managing the vast array of major construction projects on the site cannot be overstated. Today, we have 89 major projects being delivered on the site, 49 of which have a forecast value of over 20m, 28 over 50m and 19 over 100m. When NMP took over the management and operation of Sellafield in 2008, it inherited a similar number of major projects, 14 of which were scrutinised throughout the contract by the National Audit Office (NAO) and Public Accounts Committee. Performance in delivery of these projects has been mixed and further improvement is still needed in Sellafield s capability to accurately estimate project costs and to deliver to time and budget. However, in the latter stages of NMP s contract at Sellafield, the increase in estimate for projects in the design and planning phase reduced significantly as did, with the notable exception of the Silo Direct Encapsulation Plant (SDP), the forecast outturn costs for the projects in the construction phase. In its report of March 2015, the NAO noted that for major projects in the design and planning phase, Estimated lifetime cost of the SDP doubled in December 2014, while other projects estimated costs have not increased significantly [since September 2013] and Following earlier increases in the estimated costs for major projects in the construction phase, their costs have now stabilised [since September 2013]. Lifetime Estimates Earlier in this document, we have explained the process of development of Performance Plan 2011 (PP11) and Performance Plan 2014 (PP14). In each of these documents lifetime estimates of cost are provided to NDA and Government to ensure that provisions are made to cover the long term liabilities associated with decommissioning at Sellafield. It is of course important to note that the figures are only estimates, based on projections covering more than a hundred years into the future. Consequently, while there is understandable expectation that the short term estimates are reasonably accurate, the uncertainty associated with future work (particularly considering that much of the waste has still to be characterised), means that such a long term plan will undoubtedly change as technology advances into the future. Comparing PP11 to PP14 The total estimated liability for Sellafield as calculated from PP14 was 88.4bn in 2014 money values. This compares to 70.1bn calculated in PP11 (2011 money values). Adjusting for indexation ( 5.9bn) and work carried out between 2011 and 2014 ( 4.9bn), the anticipated increase in lifetime estimates is bn. It should be noted however that only 3% of the increase is actual cost related to the period 2011 to 2014 (ie under NMP control/performance). The remaining 97% is based on estimates, not cost, of which 45% of the increase refers to plans for work that will be done beyond For the period of 2014 to 2025: 25% is additional mitigating scope (eg newly identified work to address legacy problems) 17% is improved estimating maturity 10% is new scope (eg post Fukushima requirements, security enhancements) 8% is due to improved estimating maturity 19

20 Achieving savings NMP has delivered over 715m of efficiency savings for the NDA and the tax payer since It has enabled monies that have been saved through the Integrated Change Plan to be redirected to higher priority programmes such as Legacy Ponds and Silos. Cost savings have also been achieved through the reduction of downtime and incident recovery brought about by significant improvements to the safety and health of workers. So, while there has been much public commentary associated with the fees paid to NMP over the duration of its contract ( 238m from 2008 to 2015, which equates to approximately 2% of turnover), for every pound spent on fee, NMP has returned three pounds in efficiency savings against the original baseline plan. Additionally, as a result of risk mitigation and removal of previously planned work on the site, resulting from NMP led initiatives, Sellafield Ltd has logged more than 850m in capital savings throughout the contract and in future years, relative to the original plan. Today, Sellafield is delivering four times more risk reduction per pound spent in infrastructure projects than it was in Reducing Our Own Costs to the Taxpayer Since NMP took responsibility for Sellafield in In 2014/15, the annual cost of our reachback resources had been cut by more than half while the cost of our nominated staff had been cut by 40% relative to peak annual costs. Income Since 2008, under NMP, Sellafield Ltd has delivered more than 550m of income to the NDA with a further 9b of revenue projected over the next 12 years. 715m 550m 9bn of efficiency savings delivered for the NDA and the tax payer since 2008 of income to the NDA of revenue projected over the next 12 years 20

21 Investing in the community Albion Square, Whitehaven The NMP socio-economic programme has delivered impact in a challenging macro-economic environment. It has leveraged significant external funding and projects that it has supported are making a real and visible difference. 25m invested in economic and community programmes Under the ownership of NMP, the number of apprentices joining Sellafield has more than trebled to 200 this year, reflecting NMP s commitment to developing West Cumbria s next generation of nuclear workers. NMP committed early to work with the NDA on the development of the Britain s Energy Coast (BEC) Master Plan by signing a Partners Charter and joining with Sellafield Ltd and the NDA to fund the BEC. NMP has actively participated in the BEC Board and development of the Local Enterprise Partnership. Since 2008 NMP has invested more than 25m in economic and community programmes, levering over 30m of match funding. That support has funded activity that underpins the potential for West Cumbria to be a Centre of Nuclear Excellence including: Britain s Energy Coast Construction Skills Centre ( 4m); Summergrove accommodation; Albion Square ( 5.34m); Pillar House ( 2.25m); Port of Workington ( 4m) and the funding of a Project Manager for CONE. As well as supporting major economic and infrastructure projects NMP has also invested in making a difference for people living in West Cumbria. The NMP Community Fund, delivered through the Cumbria Community Foundation, has seen over 55,000 local people benefit directly through community, advice, crisis support, education, sport and culture projects. NMP is also the long term sponsor of the Whitehaven Festivals, bringing around 4m extra into the local economy and attracting over 330,000 visitors. The impact of NMP s socio-economic activity has been supplemented by that of the individual parents URS, Amec Foster Wheeler and AREVA. Their commitment to West Cumbria is evident for example through the relocation of NMP and URS to the newly refurbished Old Town Hall. Amec Foster Wheeler s significant employment of local people and AREVA s new office in West Lakes Science and Technology Park. NMP Investing in West Cumbria since 2008 Supporting Regeneration and Infrastructure Supporting Communities Supporting Learning and Skills 21

22 Summary of performance First Contract Period ( ) Generated substantial efficiency savings of over 715m Increased annual expenditure in the local supply chain by approximately 50% 100m Provided the NDA and Government with a much greater understanding of the true extent of the challenges and risks associated with the site, as detailed in the Sellafield Plan Completed the first decommissioning of a power producing nuclear reactor Completed the first returns of High Active Waste to the countries of origin Safely completed Europe s largest asbestos removal project 25m invested in socio-economic projects and charitable organisations in West Cumbria Achieved the site s best ever industrial safety performance Made the first retrieval in 50 years of spent fuel from a legacy storage pond Implemented a passive safety system in one of the highest risk legacy facilities 22

23 We recognise the achievements of the site in the last six years and thank NMP for their support in stewarding Sellafield through a crucial phase of delivery and planning. Rt Hon Edward Davey MP Secretary of State for Energy and Climate Change Acknowledgement of NMP performance from the Secretary of State in his statement of 13 January Achievements in Second Contract Term Below are some of the highlights of performance over the last 18 months. Safety Performance Best overall safety performance on record for two consecutive years. No internal radiation dose events recorded to date this year first time ever in 2014/15. Legacy Clean-up Sludge Retrieval from the First Generation Magnox Storage Pond Following a successful new construction project to deal with radioactive sludges (one of the main legacy issues on the site), Sellafield Ltd started to retrieve sludge from this legacy facility in early Emptying the Legacy Pile Fuel Storage Pond Over 100 tonnes of waste material now retrieved from this ageing pond. In total, there are 650 tonnes of metal equipment to be retrieved as part of the decommissioning programme. Cleaning Up After the Windscale Fire The Windscale pile chimneys have been a major part of the Sellafield skyline since the 1940s and the filter gallery at the top of the last remaining chimney has just been removed. Safe decommissioning of Calder Hall (world s first commercial scale Reactor) 10 years without a lost time accident while carrying out work on an ageing facility where there are many heavy tasks, including defuelling of reactors, stripping down steel and removing top ducts with one of the largest cranes in Europe. Technology and Innovation Introduction of New Technology A number of innovations have been introduced at Sellafield in recent months: the first nuclear site to use ice-pigging technology to clean and repair pipes quickly and efficiently; and the UK s first nuclear site to print components via a 3D printer, with some of these now being deployed on plant. Operations Plutonium Contaminated Material Repacking Successfully repacked the Plutonium Contaminated Material filters four years ahead of schedule with significant cost savings. This removed the site s sixth highest risk. Vitrification Line 3 Back in Operation Following a ventilation problem in late 2013, Vitrification Line 3 has been successfully decontaminated and is back in operation a programme of work that took just under 12 months despite presenting the site with many challenges. Encapsulated Product Store 3 Handover Completion of, the latest generation of Intermediate Level Waste stores to be built on the Sellafield site. Reprocessing of Overseas Fuel Completed The THORP facility has now completed reprocessing of the final overseas owned fuel. This completes over two decades of work and is a major milestone for the site and the UK nuclear industry. 23

24 Nuclear Management Partners T: +44(0) NMP Office, Old Town Hall, Duke Street, Whitehaven, Cumbria CA28 7NU

Safely delivering excellence in decommissioning, waste management and reprocessing

Safely delivering excellence in decommissioning, waste management and reprocessing Sellafield site overview Safely delivering excellence in decommissioning, waste management and reprocessing www.nda.gov.uk www.sellafieldsites.com www.nuclearmanagementpartners.com People, partnerin Under

More information

Delivering world class performance in safety, health, quality and environmental protection

Delivering world class performance in safety, health, quality and environmental protection Safety and the environment overview Delivering world class performance in safety, health, quality and environmental protection www.nda.gov.uk www.sellafieldsites.com www.nuclearmanagementpartners.com Safety

More information

Progress on the Sellafield site: an update

Progress on the Sellafield site: an update Report by the Comptroller and Auditor General Nuclear Decommissioning Authority Progress on the Sellafield site: an update MARCH 2015 Our vision is to help the nation spend wisely. Our public audit perspective

More information

ACCREDITATION. APM Corporate CASE STUDY

ACCREDITATION. APM Corporate CASE STUDY Introduction Sellafield Ltd is responsible for safely delivering decommissioning, reprocessing, nuclear waste management and fuel manufacturing activities on behalf of the Nuclear Decommissioning Authority.

More information

Asset Management. Approve Strategy (Gate C) March 2011. Critical Enabler Doc Ref: SMS/TS/F12-AM-001

Asset Management. Approve Strategy (Gate C) March 2011. Critical Enabler Doc Ref: SMS/TS/F12-AM-001 Critical Enabler Doc Ref: SMS/TS/F12-AM-001 Contents Executive Summary 3 1 Background 5 2 Current Situation 5 3 The Case for Change 5 4 Key Options 6 5 Issues 7 6 Recommendations 8 7 References 9 Appendix

More information

Section A: Introduction, Definitions and Principles of Infrastructure Resilience

Section A: Introduction, Definitions and Principles of Infrastructure Resilience Section A: Introduction, Definitions and Principles of Infrastructure Resilience A1. This section introduces infrastructure resilience, sets out the background and provides definitions. Introduction Purpose

More information

Asset Management. Enabling effective estates strategies >

Asset Management. Enabling effective estates strategies > Asset Management Enabling effective estates strategies Enabling effective estates strategies In these challenging times, we help our clients deliver strategies that contribute to the overall performance

More information

Nuclear Decommissioning Authority Business Plan

Nuclear Decommissioning Authority Business Plan Nuclear Decommissioning Authority Business Plan Financial year beginning April 2015 to fi nancial year ending March 2018 March 2015 23117210 2 Nuclear Decommissioning Authority Business Plan Financial

More information

Guide to nuclear decommissioning

Guide to nuclear decommissioning Guide to nuclear decommissioning Contents: What is decommissioning? Stages of decommissioning Site restoration Waste management The UK decommissioning industry The international picture What is decommissioning?

More information

Draft Business Plan. Financial year beginning April 2016 to fi nancial year ending March 2019

Draft Business Plan. Financial year beginning April 2016 to fi nancial year ending March 2019 Draft Business Plan Financial year beginning April 2016 to fi nancial year ending March 2019 January 2016 . Nuclear Decommissioning Authority Draft Business Plan Financial year beginning April 2016 to

More information

ACCREDITATION. APM Corporate CASE STUDY

ACCREDITATION. APM Corporate CASE STUDY Introduction Nuclear Engineering Services (NES) is a project-led organisation with over 60 years experience in the nuclear industry. The company specialises in the design, manufacture, assembly, test,

More information

Improving the National Nuclear Laboratory Project Management Capability - 11017

Improving the National Nuclear Laboratory Project Management Capability - 11017 ABSTRACT Improving the National Nuclear Laboratory Project Management Capability - 11017 T.P. Tinsley, N.P. Hanigan National Nuclear Laboratory Central Lab, Sellafield, Seascale, Cumbria, United Kingdom

More information

Waste Transfer Pricing Methodology for the disposal of higher activity waste from new nuclear power stations

Waste Transfer Pricing Methodology for the disposal of higher activity waste from new nuclear power stations Waste Transfer Pricing Methodology for the disposal of higher activity waste from new nuclear power stations December 2011 Contents Contents... i Introduction... 1 Executive Summary... 1 Background...

More information

Management of Radioactive Waste & Materials Inventory Data

Management of Radioactive Waste & Materials Inventory Data Management of Radioactive Waste & Materials Inventory Data Critical Enabler Contents Executive Summary... 3 1. Introduction... 4 2. Inventory Data Users... 5 3. Current Situation... 7 3.1 Management of

More information

INVESTORS IN PEOPLE REVIEW REPORT

INVESTORS IN PEOPLE REVIEW REPORT INVESTORS IN PEOPLE REVIEW REPORT Lower Farm Primary School Page: 1 of 13 CONTENTS Key Information 3 Assessor Decision 3 Milestone Dates 3 Introduction 4 Assessment Objectives 4 Feedback Against the Assessment

More information

Sustainable Development Strategy

Sustainable Development Strategy Sustainable Development Strategy Our vision and strategy: A railway fit for the future 2013 2024 Document Ref: SBPT204 Version 0.71 Executive summary Network Rail exists to generate outstanding value for

More information

Programmes Commercial Strategy

Programmes Commercial Strategy Programmes Commercial Strategy 2 Programmes Commercial Strategy 01 Introduction Magnox Limited (Magnox), a company owned by Energy Solutions, manages and operates ten nuclear licensed sites across the

More information

Long term operation integrated processes for delivering extended asset performance

Long term operation integrated processes for delivering extended asset performance Long term operation integrated processes for delivering extended asset performance 15 04 2015 Agenda 1. Introduction 2. Long term operation process for delivery 3. Business planning and key assumptions

More information

knowledgeable. responsive.

knowledgeable. responsive. experienced. knowledgeable. responsive. PProviding management, operations and technical services to the government and industry demands experience, knowledge and responsiveness. Not many companies are

More information

Your asset is your business. The more challenging the economy, the more valuable the asset becomes. Decisions are magnified. Risk is amplified.

Your asset is your business. The more challenging the economy, the more valuable the asset becomes. Decisions are magnified. Risk is amplified. Asset management Your asset is your business. The more challenging the economy, the more valuable the asset becomes. Decisions are magnified. Risk is amplified. Data is about more than numbers. It tells

More information

Charities & Not for Profit Protecting your organisation, supporting its success. Risk Management Insurance Employee Benefits Investment Management

Charities & Not for Profit Protecting your organisation, supporting its success. Risk Management Insurance Employee Benefits Investment Management Charities & Not for Profit Protecting your organisation, supporting its success Risk Management Insurance Employee Benefits Investment Management Charities are there to help those in need. But who helps

More information

The UK Nuclear Power Industry

The UK Nuclear Power Industry 7.10 The UK Nuclear Power Industry An overview - A bright future for nuclear power The UK has a rich legacy of skills related to the nuclear power industry which have been built up over half a century,

More information

Sustainability and Environmental Review. Introduction

Sustainability and Environmental Review. Introduction Sustainability and Environmental Review Introduction Edmundson Electrical Ltd is a long established privately owned company with an unrivalled reputation in the marketplace and with a unique culture that

More information

The Asset Management Landscape

The Asset Management Landscape The Asset Management Landscape ISBN 978-0-9871799-1-3 Issued November 2011 www.gfmam.org The Asset Management Landscape www.gfmam.org ISBN 978-0-9871799-1-3 Published November 2011 This version replaces

More information

The anglo american Safety way. Safety Management System Standards

The anglo american Safety way. Safety Management System Standards The anglo american Safety way Safety Management System Standards 2 The Anglo American Safety Way CONTENTS Introduction 04 Anglo American Safety Framework 05 Safety in anglo american 06 Monitoring and review

More information

Managing contractors involved in high impact activities

Managing contractors involved in high impact activities www.pwc.co.uk November 2011 Managing contractors involved in high impact activities A study of practices adopted by major organisations across six different sectors Contents 1. Introduction 2 2. Executive

More information

Nuclear Consultancy & Engineering Services

Nuclear Consultancy & Engineering Services Insert a caption to go with the photograph in here ITER, France Wednesday, 14 December 2011 Nuclear Consultancy & Engineering Services T H E N U C L E A R A T K I N S A S S Y S T E M A L L I A N C E CONSTRUCTION

More information

Magnox lifetime plan 2013

Magnox lifetime plan 2013 Magnox plan summary Magnox lifetime plan 2013 Magnox plan summary Magnox lifetime plan 2013 Magnox, owned by EnergySolutions, is the management and operations contractor responsible for ten nuclear sites

More information

4 Adoption of Asset Management Policy and Strategy

4 Adoption of Asset Management Policy and Strategy 4 Adoption of Asset Management Policy and Strategy Abstract The report recommends the adoption of an updated Asset Management Policy 2014 and an Asset Management Strategy 2014-2019. Both documents are

More information

RC-17. Alejandro V. Nader National Regulatory Authority Montevideo - Uruguay

RC-17. Alejandro V. Nader National Regulatory Authority Montevideo - Uruguay RC-17 Radiation Protection in Waste Management and Disposal Implementing the Joint Convention on the Safety of Spent Fuel Management and on the Safety of Radioactive Waste Management Alejandro V. Nader

More information

Optimised Management of Orphan Wastes in the UK

Optimised Management of Orphan Wastes in the UK Optimised Management of Orphan Wastes in the UK ICEM13, Brussels, Belgium 9 th September 2013 Slimane Doudou, Jennifer McTeer, Stephen Wickham (Galson Sciences Ltd) Rob Thied, Richard Woodcock (Nuclear

More information

PROGRAMME MANAGEMENT AND BUSINESS PLANNING

PROGRAMME MANAGEMENT AND BUSINESS PLANNING PROGRAMME MANAGEMENT AND BUSINESS PLANNING This paper describes what lessons were learned from the programme management and business planning which was done to support the operation of the Help Scheme

More information

INTEGRATED RISK MANAGEMENT SOLUTIONS

INTEGRATED RISK MANAGEMENT SOLUTIONS INTEGRATED RISK MANAGEMENT SOLUTIONS OUR SERVICES RPS Integrated Risk Management Solutions provides specialist HSE & Risk Management consultancy services to the energy industry and other major hazard industries.

More information

NSS 2014 UK NATIONAL PROGRESS REPORT. March 2014

NSS 2014 UK NATIONAL PROGRESS REPORT. March 2014 NSS 2014 UK NATIONAL PROGRESS REPORT March 2014 1. Support for the Convention on the Physical Protection of Nuclear Material and the International Convention for the Suppression of Acts of Nuclear Terrorism

More information

GROWTH DEAL HERALDS NEW ERA FOR COAST TO CAPITAL LEP

GROWTH DEAL HERALDS NEW ERA FOR COAST TO CAPITAL LEP GROWTH DEAL HERALDS NEW ERA FOR COAST TO CAPITAL LEP The Coast to Capital Local Enterprise Partnership today agreed an historic Growth Deal with the Government which will see at least 202.4million invested

More information

Integrated Risk Management Solutions

Integrated Risk Management Solutions Integrated Risk Management Solutions Our services 2 RPS Integrated Risk Management Solutions provides specialist HSE & Risk Management consultancy services to the energy industry and other major hazard

More information

RENCEE SAFETY MARIES

RENCEE SAFETY MARIES IAEA MINISTE ERIAL CONFE RENCEE ON NUCLEAR SAFETY Vienna,, 20 24 June 2011 CHAIRPERSONS SUMM MARIES 1 The attached texts are the Chairpersons summaries of the main proposals that emerged from the Working

More information

MATCH FUNDING TO GET YOUR BUSINESS FIT FOR NUCLEAR (F4N)

MATCH FUNDING TO GET YOUR BUSINESS FIT FOR NUCLEAR (F4N) MATCH FUNDING TO GET YOUR BUSINESS FIT FOR NUCLEAR (F4N) F4N FUNDING CALL Grants averaging 10k per project (for Business Excellence and R&D projects) to help manufacturers in England measure and improve

More information

Liquid Effluent Treatment Plant (LETP) Land Clean-Up

Liquid Effluent Treatment Plant (LETP) Land Clean-Up Liquid Effluent Treatment Plant (LETP) Land Clean-Up Frequently Asked Questions What is proposed? Magnox Ltd is proposing to remove the redundant Liquid Effluent Treatment Plant (LETP) at Harwell and to

More information

Environment Agency 2014 All rights reserved. This document may be reproduced with prior permission of the Environment Agency.

Environment Agency 2014 All rights reserved. This document may be reproduced with prior permission of the Environment Agency. Flood and coastal erosion risk management Long-term investment scenarios (LTIS) 2014 We are the Environment Agency. We protect and improve the environment and make it a better place for people and wildlife.

More information

Department for Work and Pensions Communication Capability Review. February 2013

Department for Work and Pensions Communication Capability Review. February 2013 Department for Work and Pensions Communication Capability Review February 2013 Management summary 2.1 The Communication Capability Review of the Department for Work and Pensions (DWP) is one of a series

More information

How are companies currently changing their facilities management delivery model...?

How are companies currently changing their facilities management delivery model...? Interserve and Sheffield Hallam University market research 2012 Page 2 www.commercial.interserve.com How are companies currently changing their facilities management delivery model...? we have a strategy

More information

Fleet Services CORPORATE SERVICES. Branch Manager: Steve Rapanos 57 FLEET SERVICES 2016 2018 BUSINESS PLAN

Fleet Services CORPORATE SERVICES. Branch Manager: Steve Rapanos 57 FLEET SERVICES 2016 2018 BUSINESS PLAN Fleet Services CORPORATE SERVICES Branch Manager: Steve Rapanos 57 FLEET SERVICES 2016 2018 BUSINESS PLAN Table of Contents INTRODUCTION Our Branch 60 CONTRIBUTION TO THE CITY S VISION The Way Ahead 62

More information

Environmental Policy 2014-2016

Environmental Policy 2014-2016 Environmental Policy 2014-2016 Our responsibility to the environment is a sustainable commitment inscribed in AREVA's Value Charter. The deep involvement of AREVA sites in improving environmental risk

More information

Maximising supply chain throughput with existing infrastructure

Maximising supply chain throughput with existing infrastructure Maximising supply chain throughput with existing infrastructure Improve customer service without capital outlay 1 the CHALLENGE SUPPLY CHAIN AND LOGISTICS Increasing global complexity and uncertainty is

More information

2.0 Land Quality Programme

2.0 Land Quality Programme 2.0 Land Quality Programme The Sellafield site has a legacy of ground contamination from its historical use as a Royal Ordnance factory and its subsequent development as a nuclear facility. The ground

More information

Nuclear Decommissioning Authority. Business Plan 2012-2015

Nuclear Decommissioning Authority. Business Plan 2012-2015 Business Plan 2012-2015 Business Plan 2012-2015 Business Plan presented to Parliament pursuant to Schedule 3 of the Energy Act 2004. Business Plan laid before Scottish Parliament by the Scottish Ministers

More information

Driving Transformational Change. Innovative Solutions for Optimising Performance in Quarrying & Mining Fleets

Driving Transformational Change. Innovative Solutions for Optimising Performance in Quarrying & Mining Fleets Driving Transformational Change Innovative Solutions for Optimising Performance in Quarrying & Mining Fleets Babcock International Group: In Brief The UK s leading engineering support services organisation

More information

Technical Journal. Paper 142

Technical Journal. Paper 142 Technical Journal 09 Paper 142 142 Kevin Balaam Programme Manager Highways & Transportation Atkins The Area 6 MAC approach to planning and programme management Introduction Steve Dickinson Schemes Manager

More information

Tapping the benefits of business analytics and optimization

Tapping the benefits of business analytics and optimization IBM Sales and Distribution Chemicals and Petroleum White Paper Tapping the benefits of business analytics and optimization A rich source of intelligence for the chemicals and petroleum industries 2 Tapping

More information

A housing stock fit for the future: Making home energy efficiency a national infrastructure priority

A housing stock fit for the future: Making home energy efficiency a national infrastructure priority A housing stock fit for the future: Making home energy efficiency a national infrastructure priority The benefits of home energy efficiency Reduce carbon emissions Energy efficiency can reduce carbon emissions

More information

Report. by the Comptroller and Auditor General. Ministry of Defence. Army 2020

Report. by the Comptroller and Auditor General. Ministry of Defence. Army 2020 Report by the Comptroller and Auditor General Ministry of Defence Army 2020 HC 263 SESSION 2014-15 11 JUNE 2014 4 Key facts Army 2020 Key facts 82,500 trained regular Army personnel planned in December

More information

Nuclear Safety. Policy 2013-2016

Nuclear Safety. Policy 2013-2016 Nuclear Safety Policy 2013-2016 Nuclear Safety Policy 2013-2016 T he organisational principles and actions defined in the Nuclear Safety Charter and applied within the group have achieved significant improvements

More information

Engineering & Support Services

Engineering & Support Services Engineering & Support Services Expert Project, Engineering & Customer Support Services Providing a range of Engineering and Support Services for:- Mission Critical Environments Data Centres & Server Room

More information

IT Project Management and Consultancy Solutions Find out more about Waldeck s expertise and experience

IT Project Management and Consultancy Solutions Find out more about Waldeck s expertise and experience IT Project Management and Consultancy Solutions Find out more about Waldeck s expertise and experience Contents Please find enclosed within this document useful information about Waldeck s IT solutions

More information

Qlik UKI Consulting Services Catalogue

Qlik UKI Consulting Services Catalogue Qlik UKI Consulting Services Catalogue The key to a successful Qlik project lies in the right people, the right skills, and the right activities in the right order www.qlik.co.uk Table of Contents Introduction

More information

Mining & Construction Transforming your fleet performance

Mining & Construction Transforming your fleet performance Mining & Construction Transforming your fleet performance Giving you greater focus on your business Today s difficult economy challenges organisations within the mining and construction sector to deliver

More information

Government Degree on the Safety of Nuclear Power Plants 717/2013

Government Degree on the Safety of Nuclear Power Plants 717/2013 Translation from Finnish. Legally binding only in Finnish and Swedish. Ministry of Employment and the Economy, Finland Government Degree on the Safety of Nuclear Power Plants 717/2013 Chapter 1 Scope and

More information

SUPPORTING THE RAIL INDUSTRY UNIQUE SOLUTIONS FOR UNIQUE SITUATIONS WWW.SGS.COM/RAIL

SUPPORTING THE RAIL INDUSTRY UNIQUE SOLUTIONS FOR UNIQUE SITUATIONS WWW.SGS.COM/RAIL SUPPORTING THE RAIL INDUSTRY UNIQUE SOLUTIONS FOR UNIQUE SITUATIONS WWW.SGS.COM/RAIL OUR UNIQUE SOLUTION TO YOUR UNIQUE SITUATION SGS is recognised as the global benchmark for quality and integrity. We

More information

ENTERPRISE RISK MANAGEMENT FRAMEWORK

ENTERPRISE RISK MANAGEMENT FRAMEWORK ROCKHAMPTON REGIONAL COUNCIL ENTERPRISE RISK MANAGEMENT FRAMEWORK 2013 Adopted 25 June 2013 Reviewed: October 2015 TABLE OF CONTENTS 1. Introduction... 3 1.1 Council s Mission... 3 1.2 Council s Values...

More information

ISRS. For the health of your business SAFER, SMARTER, GREENER

ISRS. For the health of your business SAFER, SMARTER, GREENER ISRS TM For the health of your business SAFER, SMARTER, GREENER 1 BEST PRACTICE ISRS Best practice safety and sustainability management ISRS is a world leading system to assess, improve and demonstrate

More information

Dr Jon Billowes Deputy Director

Dr Jon Billowes Deputy Director Dr Jon Billowes Deputy Director 1. Background to the 2. Dalton s research strategy 3. Dalton s education & training strategy The University of Manchester (Established 1 st October 2004) A New University

More information

Strategic Plan. New Zealand Fire Service Commission to 2005 2010

Strategic Plan. New Zealand Fire Service Commission to 2005 2010 Strategic Plan New Zealand Fire Service Commission to 2005 2010 Table of contents Forward from the Chairperson...3 Summarises the purpose, content and logic behind the Commission s strategic direction.

More information

INTRODUCTION. Three Mile Island Unit 2

INTRODUCTION. Three Mile Island Unit 2 INTRODUCTION here was an accident at Three Mile Island Unit 2 on March 28,1979. It caused extensive damage to the plant's nuclear fuel core. Most of the plant's major systems were relatively undamaged.

More information

Constraints to Implementing Decommissioning and Environmental Remediation in IAEA Member States MAIN OUTCOMES

Constraints to Implementing Decommissioning and Environmental Remediation in IAEA Member States MAIN OUTCOMES 55 th IAEA General Conference Side Event organised by the Waste Technology Section Division of Nuclear Fuel Cycle and Waste Technology IAEA Department of Nuclear Energy Constraints to Implementing Decommissioning

More information

Asset Management Policy March 2014

Asset Management Policy March 2014 Asset Management Policy March 2014 In February 2011, we published our current Asset Management Policy. This is the first update incorporating further developments in our thinking on capacity planning and

More information

UK Strategy for the Management of Solid Low Level Radioactive Waste from the Nuclear Industry

UK Strategy for the Management of Solid Low Level Radioactive Waste from the Nuclear Industry UK Strategy for the Management of Solid Low Level Radioactive Waste from the Nuclear Industry August 2010 Executive Summary The UK strategy for the management of solid low level radioactive waste from

More information

Oil Spill Emergency Response. Oil Spill Emergency

Oil Spill Emergency Response. Oil Spill Emergency Oil Spill Emergency Response 1 Oil Spill Emergency Response We work to prevent incidents that may result in spills of hazardous substances. This means making sure our facilities are well designed, safely

More information

HSMS. Group Health AND Safety Management System

HSMS. Group Health AND Safety Management System 3 2 CONSULTATION AND EMPOWERMENT 4 RISK MANAGEMENT 1 AMBITION, POLICY AND RULES LEADERSHIP, ACCOUNTABILITY AND ORGANISATION PLAN AND COMMIT 5 EMERGENCY PREPAREDNESS 10 AUDIT AND MATURITY PATH 9 LEARN AND

More information

BEST PRACTICES IN CYBER SUPPLY CHAIN RISK MANAGEMENT

BEST PRACTICES IN CYBER SUPPLY CHAIN RISK MANAGEMENT BEST PRACTICES IN CYBER SUPPLY CHAIN RISK MANAGEMENT DuPont Crop Protection Operating Disciplines for Supply Chain Sustainability, Risk Management and Resilience INTERVIEWS George Poe Integrated Operations

More information

2013-18 Business Plan. Executive Summary UK Shared Business Services Ltd

2013-18 Business Plan. Executive Summary UK Shared Business Services Ltd 2013-18 Business Plan Executive Summary UK Shared Business Services Ltd Published June 2013 Contents I Introduction 3 II Executive Summary 6 Introduction: Geared for Growth in the Service of our Customers

More information

13 ENVIRONMENTAL AND SOCIAL MANAGEMENT SYSTEM

13 ENVIRONMENTAL AND SOCIAL MANAGEMENT SYSTEM 13 ENVIRONMENTAL AND SOCIAL MANAGEMENT SYSTEM This ESIA has identified impacts (both positive and negative) to the physical, natural and socio-economic environments, as well as to community and worker

More information

Audit Report. Implementation of the Recovery Act at the Savannah River Site

Audit Report. Implementation of the Recovery Act at the Savannah River Site U.S. Department of Energy Office of Inspector General Office of Audits and Inspections Audit Report Implementation of the Recovery Act at the Savannah River Site OAS-RA-L-11-12 September 2011 Department

More information

Over the last twelve months, we've completed two significant changes which are important in providing a solid base for Spectrum to move forward.

Over the last twelve months, we've completed two significant changes which are important in providing a solid base for Spectrum to move forward. Spectrum Housing Group Moving Forward www.spectrumhousing.co.uk Introduction We are proud of what we do at Spectrum. We continue to deliver high quality services to our residents while growing and developing

More information

The world s leading sustainability consultancy. Sustainable Solutions for the Oil and Gas Industry

The world s leading sustainability consultancy. Sustainable Solutions for the Oil and Gas Industry The world s leading sustainability consultancy Sustainable Solutions for the Oil and Gas Industry The oil and gas industry currently faces the greatest environmental, health and safety challenges in its

More information

Care Providers Protecting your organisation, supporting its success. Risk Management Insurance Employee Benefits Investment Management

Care Providers Protecting your organisation, supporting its success. Risk Management Insurance Employee Benefits Investment Management Care Providers Protecting your organisation, supporting its success Risk Management Insurance Employee Benefits Investment Management Care providers are there to help those in need. But who helps the care

More information

Five steps to Enterprise Risk Management

Five steps to Enterprise Risk Management risk decisions 2011 Five steps to Enterprise Risk Management by Val Jonas CEO Risk Decisions Group www.riskdecisions.com management solutions Val Jonas: Five steps to Enterprise Risk Management Five steps

More information

The F Word - Why Facilities Matter

The F Word - Why Facilities Matter The F Word - Why Facilities Matter By Martin Pickard Leaders of businesses and organisations don't want to talk about Facilities. It's a dirty word associated with cleaning, maintenance and other non-core

More information

FM & SECURITY SOLUTIONS. SSS Managed Services. Impartial, innovative, involved

FM & SECURITY SOLUTIONS. SSS Managed Services. Impartial, innovative, involved FM & SECURITY SOLUTIONS SSS Managed Services Impartial, innovative, involved SSS MANAGED SERVICES INTRODUCTION SSS Managed Services provides a range of flexible, scalable and service-led solutions for

More information

Housing Association Regulatory Assessment

Housing Association Regulatory Assessment Welsh Government Housing Directorate - Regulation Housing Association Regulatory Assessment Melin Homes Limited Registration number: L110 Date of publication: 20 December 2013 Welsh Government Housing

More information

Significant incidents in nuclear fuel cycle

Significant incidents in nuclear fuel cycle IAEA-TECDOC-867 Significant incidents in nuclear fuel cycle INTERNATIONAL ATOMIC ENERGY AGENCY The IAEA does not normally maintain stocks of reports in this series. However, microfiche copies The originating

More information

Enhanced resilience for major emergencies Proven capability solutions to deliver the resilience you need

Enhanced resilience for major emergencies Proven capability solutions to deliver the resilience you need Enhanced resilience for major emergencies Proven capability solutions to deliver the resilience you need 1 The Alliance Value Proposition Alliance Value Proposition The threat posed today Terrorist threats

More information

Code of Practice EST 01 Decommissioning arrangements prior to site hand over Oct 2004

Code of Practice EST 01 Decommissioning arrangements prior to site hand over Oct 2004 Estates Division Imperial College London Room 503 Sherfield Building South Kensington Campus London SW7 2AZ, UK Tel: +44 (0)20 7594 9832 Fax: +44 (0)20 7594 9050 r.mayne@imperial.ac.uk www.imperial.ac.uk

More information

BS 11000 Collaborative Business Relationships Product Guide

BS 11000 Collaborative Business Relationships Product Guide BS 11000 Collaborative Business Relationships Product Guide BS 11000 Collaborative Business Relationships What is BS 11000? In business, as in other walks of life, teamwork can pay real dividends. Companies

More information

The PMO as a Project Management Integrator, Innovator and Interventionist

The PMO as a Project Management Integrator, Innovator and Interventionist Article by Peter Mihailidis, Rad Miletich and Adel Khreich: Peter Mihailidis is an Associate Director with bluevisions, a project and program management consultancy based in Milsons Point in Sydney. Peter

More information

INDUSTRIAL SITE SERVICES. sharing responsibility

INDUSTRIAL SITE SERVICES. sharing responsibility INDUSTRIAL SITE SERVICES sharing responsibility safe, professional industrial site services Veolia Environmental Services is an international, market-leading waste management company providing a comprehensive

More information

Environment Committee 11 January 2016

Environment Committee 11 January 2016 Environment Committee 11 January 2016 Title Whole Life Costing of Footway Maintenance Treatments and Scheme Prioritisation Report of Wards Status Urgent Key Enclosures Commissioning Director, Environment

More information

Ubertas Cloud Services: Service Definition

Ubertas Cloud Services: Service Definition Ubertas Cloud Services: Service Definition February 2013 Innovation. Power. Trust. Contents 1. About Ubertas... 2 Our Company... 2 Our Approach to Service Delivery... 2 Our Partner Network & the UK Cloud

More information

Fleet Complete. Insight. Innovation. Intervention.

Fleet Complete. Insight. Innovation. Intervention. Fleet Complete Insight. Innovation. Intervention. Risk. Reinsurance. Human Resources. Empower Results Aon UK Limited is authorised and regulated by the Financial Conduct Authority 1 Aon is market leader

More information

2015 EDUCATION PAYROLL LIMITED STATEMENT OF INTENT

2015 EDUCATION PAYROLL LIMITED STATEMENT OF INTENT 2015 EDUCATION PAYROLL LIMITED STATEMENT OF INTENT Published in August 2015 Education Payroll Limited 2015 EDUCATION PAYROLL LIMITED STATEMENT OF INTENT CONTENTS Foreword 3 Who We Are 4 What We Do 5 How

More information

Cash for Growth Working Capital in the Nordics

Cash for Growth Working Capital in the Nordics 2014 Cash for Growth Working Capital in the Nordics Contents Executive summary 3 Working capital performance across the Nordics 4 Understanding the drivers 5 A comparison with Europe 6 Performance within

More information

Technical & Engineering: OIL & GAS

Technical & Engineering: OIL & GAS Providing Qualified Professionals Be Exceptional About us Recruitment Process Compliance Client Support Payroll Control Our Clients Oil & Gas Industry Contact About us Cordant Technical & Engineering Recruitment

More information

WHITE PAPER. From Building Information Management to Facilities Management

WHITE PAPER. From Building Information Management to Facilities Management October 2011 WHITE PAPER. Management to Facilities Management A look at the benefits to be found by fostering the links between Building Information Modelling (used by the construction industry) and Computer

More information

Health, safety and environment policy and management arrangements

Health, safety and environment policy and management arrangements Health, safety and environment policy and management arrangements An overview of how Rolls-Royce Group plc delivers its policy commitments on health, safety and environment Issue 6 October 2006 Contents

More information

Road Safety ROAD SAFETY

Road Safety ROAD SAFETY Road Safety 1 ROAD SAFETY Our staff and contractors drive around 1.1 billion kilometres each year: to deliver products to our customers or keep our operations running. That s equivalent to driving about

More information

Information Services Strategy 2011-2013

Information Services Strategy 2011-2013 Information Services Strategy Issue 1 1 Introduction The States of Jersey public sector is facing significant pressure for efficiencies and savings. This has created the context to take a fresh look at

More information

Telford College of Arts and Technology

Telford College of Arts and Technology FURTHER EDUCATION COMMISSIONER ASSESSMENT SUMMARY Telford College of Arts and Technology JANUARY 2016 Assessment Background Telford College of Arts and Technology (TCAT) is a medium sized general FE College

More information

Community Investment Strategy

Community Investment Strategy Community Investment Strategy Introduction Sanctuary Group is one of the largest providers of housing and care services in the UK. We are a not-for-profit organisation and reinvest our surplus income into

More information

Management System Manual International Nuclear Services Ltd and Pacific Nuclear Transport Ltd

Management System Manual International Nuclear Services Ltd and Pacific Nuclear Transport Ltd PROM 000 M01 Issue 4 August 2015 Management System Manual International Nuclear Services Ltd and Pacific Nuclear Transport Ltd Delivering Specialist Nuclear Services with Pride 2 Management System Manual

More information

WORKFORCE PLAN Page 1

WORKFORCE PLAN Page 1 2015 2019 WORKFORCE PLAN Page 1 Contents 1. Introduction... 3 2. Developing the Plan... 6 3. Organisational Structure... 9 4. Workforce Profile... 10 5. Workforce Requirements... 11 6. Workforce Strategies...

More information