1 CAT-MIS Project Management Communicat Accounting Transition to Management Information System Project Management Communicat utilises our proven CAT-MIS Project Management method for the implementation of major accounting software solutions. CAT-MIS can be tailored to suit your exact requirements and is documented and agreed to at the outset of the project. This ensures that all areas of the implementation process are discussed and addressed and realistic expectations are set. An implementation framework reflecting respectively Communicat s and the Client s roles and responsibilities can then be agreed to in an informed manner through a thorough understanding of the project scope, objectives, activities and resource requirements. This structured and proven approach will allow you to control the process and understand the direction of the project and requirements of all the parties at the earliest opportunity. Communicat s approach to software implementation will enable you to achieve the most efficient, effective and economic utilisation of your resources. This will be achieved in the minimum time possible and at least cost to you. The CAT-MIS methodology includes three major components which are detailed in the following sections: Project Approach, Project Management, and Quality Assurance. NOTE: Communicat s CAT-MIS methodology and project approach information is provided as Commercialin-Confidence. This information may not be discussed or disclosed to any person without the written approval of Communicat. Project Approach The approach Communicat will be utilising for implementation into your organisation is based upon the following ten Phase approach which is outlined in detail in this section: Phase 1 Project Scoping Phase 2 Project Team Training Phase 3 Software Installation Phase 4 System Design Phase 5 System Build Phase 6 User Training Phase 7 Data Migration Phase 8 Acceptance Testing & Dress Rehearsals Phase 9 Live Operation Phase 10 Post Implementation Review Page 1

2 PHASE PROJECT INITIATION The aim of the project initiation phase is to confirm the project requirements in terms of scope, time-scales and participants and agree an implementation framework reflecting the respective Communicat and Client s roles and responsibilities. This will involve setting realistic expectations to ensure the success of the project and will lay the foundation for everything that follows. This critical phase of the project includes: Identification and agreement of project scope and objectives, Assessing and Communicating project risks to the client, Clearly defining scope of Communicat and the client s efforts and responsibilities, Identification and agreement of project management and quality control procedures including project reporting mechanisms and frequency, Approval of project approach, plan, deliverables and budget, and Approval of these Terms of Reference reflecting all of the above. The method will be one of review of the ten Phases of the CAT-MIS as detailed in this document. An initial order will have been issued to Communicat prior to the Project Initiation Phase. PHASE SOFTWARE INSTALLATION This phase will involve the software installation on the client s hardware platform by a Communicat Technical Consultant. Involvement of the Client s system administrator is of value at this stage to assist with system access and software installation. Software Modules:- Refer to quotation Page 2

3 PHASE PROJECT TEAM TRAINING It is common practice to first train a nucleus of client personnel on all of the functionality of the software. This training is concerned with the mechanics and features of the software, exploring the scope of the systems. It is not exhaustive and not an appropriate end user forum. Once a broad understanding of the product capabilities has been established the Client can then focus on their specific application of the software. This will ensure that the system specifiers can contribute in full to the decision making process in the next phase (System Design). Overview training on agreed software modules. Relevant Client personnel involved in the Design Phase will attend all training sessions. A maximum of four of your key people will attend each project team training session. A suitable training environment will be provided at Communicat. The Client will determine the apportionment of training time on each module by consultation and agreement with the Communicat consultant. PHASE SYSTEM DESIGN System design will follow on immediately from the Project Team Training. This process involves making decisions as to how each of the application areas are best configured to meet your stated requirements. This phase will take the form of a hands on' workshop activity. A System Design document will also be produced reflecting key set-up decisions and basis of build for circulation and sign off by the Client before actual system build activities commence. It is important that the scope and purpose of this document is agreed and clearly understood including the level of design detail to be reflected. Communicat design workshop. System Design document reflecting principal set-up decisions & initial reporting requirements. Revised Terms of Reference (where appropriate). All required design decisions are made in a timely manner to enable completion of the System Design document in the required time-scales. A definitive list of report requirements is provided. The initial project plan may need to be updated after this phase if necessary. A suitable development environment is provided. Page 3

4 PHASE SYSTEM BUILD This phase will involve the three following areas: 1. System Configuration The key objective is to configure the software and deliver in accordance with the signed off System Design document. Interfaces should also be developed at this Phase, concurrently with software configuration (as defined and agreed in the System Design document). Each application will be set-up and parameterised according to the criteria defined in the design specifications. This entails configuration of working directories and databases, establishing database definitions, defining transactions and associated journals and implementing basic security. At the end of this process a skeleton system will be available for user acceptance testing (UAT) and end user training. Whilst the full data set will not be loaded, the system will include a limited amount of reference data, sufficient to undertake system test activities. It is envisaged that three copies of the final system will be provided as part of this activity for training and test purposes. 2. Generation of Management Reports (Optional) As part of the implementation, a set of the Client s standard reports will need to be developed. (As defined and agreed in the System Design phase). 3. System Documentation (Optional) This will involve the development of the following: End User Procedures (optional), Customised training material (optional), and User Acceptance Test Plan (optional). Production of system in accordance with System Design document. Two further copies of configured database i.e., training and test. Management Reports (optional) End User Procedures (optional) End User Training material (optional). User Acceptance Test Plan (optional). Sign off of the System Design document is achieved prior to build activities OTHERWISE client sign off of Project Status Report to continue services, and system build activities in particular, regardless. The Client will provide appropriate test data as agreed to complete and test build deliverables. The above testing does not constitute user acceptance testing. Page 4

5 PHASE END USER TRAINING The purpose of this phase is to introduce and train users on the new system, its scope and functionality. The training agenda and required training materials will have been identified as part of the detailed planning and scoping as agreed during Phase 1 - Project Initiation. Typically a two-stage approach is adopted to such training. Stage one is high level and particularly geared towards managers. However, often all users attend this session to achieve a broad understanding of the overall system and the inter-dependency of the departments involved in the system. Stage two, standard user profiles are developed and mapped to each of the application areas of the system and detailed modular training sessions delivered. Here we will be training the day to day users of the system in job specific tasks that involve the new systems. Generic training courses may also be delivered instead of a more tailored approach. Identified modular training sessions: A detailed training plan has been undertaken and agreed agenda in place. The necessary training materials have been previously agreed and are in place. A suitable training environment and facilities are provided. A maximum of 8 users will attend each session. Page 5

6 PHASE DATA MIGRATION Overview An initial planning activity should have been undertaken as part of the business mapping and design phase and the scope and method of data transfer determined. This early planning will have identified any interfaces to be developed for the purpose of data transfer, any clean up tasks necessary and with regard to manual data entry, what needs to be entered and by whom. Interfaces will have been developed as part of the system build phase. The data conversion cycle should include the transfer of year to date balances across from the current general ledger system to the new system. In addition, all creditors and debtors master file and outstanding balance details should be transferred into the new system. Manual data entry is often usefully assigned to users on completion of their end user training as a further system familiarisation exercise and may be appropriate for some areas of data transfer. Assistance in execution of cut-over activities. Detailed planning has previously been undertaken and detailed task plan agreed & in place. Communicat is able to assist in the process. Page 6

7 PHASE USER ACCEPTANCE TESTING The purpose of this activity is to ensure the delivered system is fully tested and signed off to the Client s satisfaction. It is important to ensure that the completed system is capable of performing in the Client s environment. User acceptance testing should be a verification process to ensure the delivered system correctly addresses the Client s business and operational procedures. Acceptance test plans will have been built and agreed during system build. The Client s project team will own and drive this activity and may elect to involve other users to ensure the new systems work for them in an environment that imitates real life. Under the guidance of Communicat, the Client will operate the system on a pre-agreed set of data making sure that the system responds in a way that enables he Client to complete their normal functions. There will be testing for completeness and suitability as well as accuracy of results. During this Phase, change control should be rigorously applied to ensure that the system does not grow outside its original scope or that changes are applied which could have an unpredicted knock on effect in other areas of the application. If a pilot or parallel run activity is to take place it is still important that a limited amount of testing is undertaken by the project team beforehand. Having completed the system building, a test pack of appropriate data and business scenarios should be generated and processed through the system in a series of acceptance tests. Satisfactory completion of these tests will allow the system to be signed off for pilot/parallel running. Communicat would recommend our presence during the tests to ensure a timely resolution to issues raised. Advice, guidance and issue resolution during test execution. Test Review (the Client s Responsibility). Test Results (the Client s Responsibility). The Client s will undertake test execution and recording of test results. Communicat will participate in the Test Review. The Client will document Test Review findings/actions. Page 7

8 PHASE LIVE OPERATION Typically a full parallel run is not required. The system will be using tried and tested products and user acceptance will have proven their ability to address the user requirements and operational procedures. Provided that controls and checks have been built into the data migration exercise then we will know that the new systems will have commenced from a stable and accurate base. The most likely area for data errors to occur will be from incorrect operation of the system in the early days. A pre-defined live running phase should therefore be agreed where careful monitoring of the system and its operation is undertaken and resulting feedback and suggestions noted. These documented notes will provide the basis of the Post Implementation Review. It is important that responsibility is assigned within The Client s project team for the monitoring, collation and documenting of all live running issues. Communicat assistance in live running as agreed. A pre-defined formal live running period has been agreed. PHASE POST IMPLEMENTATION REVIEW Approximately eight weeks after the live date, Communicat will return to the Client s office to evaluate the success of the implementation in meeting the Client s specified objectives. This post implementation review will provide a forum for assessing and addressing all resulting feedback from the live running phase. This may include a revisiting of certain set-up or operational decisions and also additional requirements previously unidentified or outside of the original scope of the project. It is also an ideal forum for conducting a further training needs analysis. The post implementation review then becomes the opportunity to totally appraise the new system in light of everything that has been learned to date. The findings of the post implementation review should be presented to the Project Steering Committee and recommendations for any further work and sign-off for the completed application. Assistance in Post Implementation Review. Post Implementation Review Report. Page 8

9 PROJECT MANAGEMENT AND CONTROLS Project Management Communicat will have overall responsibility for the management of this implementation including production and maintenance of a definitive project plan; Communicat will advise as required on the content of such a plan; Communicat will monitor the progress of agreed Communicat activities and report on any deviance to the agreed Terms of Reference or planned time-scales for deliverables. Project Control Procedures Change Request Form (CRF): Change control procedures should be agreed at the outset of the project and detailed within the Terms of Reference. Unless otherwise agreed and stated, it is assumed that Communicat s standard Change Request Form (CRF) will be adopted where required. Communicat will use one form to record all requests by either party for any changes to the agreed software implementation. All the parties should be familiar with the CRF and sign off process. Communicat's standard change control procedure is assumed unless an alternative is explicitly stated. (Refer to Attachment - Change Request Form). There are three general categories of change control, change in scope, delay, change in estimates. Each of these is discussed below. Change in Scope: This type of change control documents a modification in the definition of tasks to be carried out. This is usually caused by adding or deleting activities, (for example, the requirement to interview more of the Client s personnel). Changes in scope almost always affect project costs and target dates. Delay: This type of change control documents situations that cause the project team to be delayed in performing its work due to circumstances or events beyond its control. Delays can be caused by: User delays in responding to requests for information or approvals. Change in Estimates: This type of change control documents variances that are recognised in advance as affecting a group of tasks. A change request should be generated and all affected project costs and target dates should be re-estimated. PROJECT QUALITY ASSURANCE: The purpose of this quality plan is to clearly define the control procedures to be adopted to ensure all Communicat deliverables adhere to Communicat s standard quality procedures and are achieved in accordance with the Terms of Reference. Ownership and management of the project must be established. The approach to quality assurance should be detailed and procedures for completion and approval of deliverables clearly stated. QA Role The Project Manager from Communicat assigned to the implementation will have overall responsibility for this project will review and sign off the following agreed documents: Page 9

10 Terms of Reference This document is only considered approved when both The Client s and a Communicat signatory, other than the author of the document is evidenced. System Design Document This document must be signed off by the Client before commencing with the next phase in the project - System Build. Project Status Reports (To be agreed) These reports will be produced as agreed for review and sign off by both the Client and Communicat. Project Plans Where Communicat have responsibility for production and maintenance of the project plan, such a plan will be reviewed and signed off internally prior to issue to the project team. COMPLETION AND APPROVAL OF DELIVERABLES: These mechanisms are used to report & secure agreement on completion of deliverables: Service Report A Service Report will be completed by the assigned Communicat consultant(s) on a weekly basis and issued for sign off by the Client s Project Manager. These reports will reflect all activities undertaken and deliverables completed within that time period. Once the Client s sign-off has been achieved, the report will then be submitted to Communicat for review. Deliverables Sign Off All Communicat deliverables will be approved and signed-off by a Client s representative. Resource Estimate Please refer to separate spreadsheet document. TERMS AND CONDITIONS: Consultancy will be charged at the currently scheduled hourly rates (min. 4 session): Expenses incurred for travel, e.g. airfares are not included in the daily rates quoted. All expenses will be re-charged at cost. Where attendance on site at the client s office is required and duration of attendance required is less than a full day, a call-out fee will apply. A standard day is considered to be 8 hours, normally between 9.00am and 6pm. The minimum charge unit is half a day. Cancellation of this consultancy service must be notified to Communicat in writing. Cancellation within one complete working day of commencement will incur the full consultancy service charge. Cancellation within three working days of commencement will incur half the consultancy service charge. Prices remain firm for 60 days from date of the client agreeing these Terms of Reference. Page 10

To provide a procedure and associated guidelines to facilitate the management of project dependencies.

To provide a procedure and associated guidelines to facilitate the management of project dependencies. Management DEPENDENCY MANAGEMENT Purpose To provide a procedure and associated guidelines to facilitate the management of project dependencies. Overview Dependencies in this Phase are defined as actions,

More information

PROJECT MANAGEMENT FRAMEWORK

PROJECT MANAGEMENT FRAMEWORK PROJECT MANAGEMENT FRAMEWORK DOCUMENT INFORMATION DOCUMENT TYPE: DOCUMENT STATUS: POLICY OWNER POSITION: INTERNAL COMMITTEE ENDORSEMENT: APPROVED BY: Strategic document Approved Executive Assistant to

More information

White Paper On Pilot Method Of ERP Implementation

White Paper On Pilot Method Of ERP Implementation White Paper On Pilot Method Of ERP Implementation Rod Clarke Rod Clarke provides guidance, advice and support to businesses in successfully applying IS/IT in support of their business goals. He brings

More information

NSW Government ICT Benefits Realisation and Project Management Guidance

NSW Government ICT Benefits Realisation and Project Management Guidance NSW Government ICT Benefits Realisation and Project Management Guidance November 2014 CONTENTS 1. Introduction 1 2. Document purpose 1 3. Benefits realisation 1 4. Project management 4 5. Document control

More information

Lead Business Analyst

Lead Business Analyst Senior Business Analyst Date produced: July 2014 Produced by: Rob Norman Date last reviewed: November 2014 Reviewed by: Adrian Morris Date evaluated: November 2014 Evaluated by: Jenny Buck / Louise Dibble

More information

Project Management Process

Project Management Process Project Management Process Description... 1 STAGE/STEP/TASK SUMMARY LIST... 2 Project Initiation 2 Project Control 4 Project Closure 5 Project Initiation... 7 Step 01: Project Kick Off 10 Step 02: Project

More information

<Project Name> ACCEPTANCE TEST PLAN <SCOPE OF TEST E.G. SYSTEM TESTING> <BUSINESS UNIT/DIVISION> DEPARTMENT of INFRASTRUCTURE, ENERGY and RESOURCES

<Project Name> ACCEPTANCE TEST PLAN <SCOPE OF TEST E.G. SYSTEM TESTING> <BUSINESS UNIT/DIVISION> DEPARTMENT of INFRASTRUCTURE, ENERGY and RESOURCES DEPARTMENT of INFRASTRUCTURE, ENERGY and RESOURCES ACCEPTANCE TEST PLAN Version - DOCUMENT ACCEPTANCE and RELEASE

More information

Derbyshire Trading Standards Service Quality Manual

Derbyshire Trading Standards Service Quality Manual Derbyshire Trading Standards Service Quality Manual This Quality Manual has been developed to give a broad outline of how the Trading Standards Division s range of services comply with the requirements

More information

PORTFOLIO, PROGRAMME & PROJECT MANAGEMENT MATURITY MODEL (P3M3)

PORTFOLIO, PROGRAMME & PROJECT MANAGEMENT MATURITY MODEL (P3M3) PORTFOLIO, PROGRAMME & PROJECT MANAGEMENT MATURITY MODEL (P3M3) 1st February 2006 Version 1.0 1 P3M3 Version 1.0 The OGC logo is a Registered Trade Mark of the Office of Government Commerce This is a Value

More information

A GUIDE TO IMPLEMENTING SAP BUSINESS ONE

A GUIDE TO IMPLEMENTING SAP BUSINESS ONE A GUIDE TO IMPLEMENTING SAP BUSINESS ONE THE ULTIMATE GUIDE If you are considering SAP Business One as your business management solution or have already selected SAP Business One and you are about to embark

More information

Transition and Transformation. Transitioning services with minimal risk

Transition and Transformation. Transitioning services with minimal risk IBM Global TECHNOLOGY Servicess and Transformation ing services with minimal risk Summary To transition services is a complex process involving many issues. When outsourcing to IBM, you gain the benefit

More information

Single Electricity Market

Single Electricity Market Single Electricity Market SEM R2.0.0 INTRA-DAY TRADING MARKET TRIAL APPROACH COPYRIGHT NOTICE All rights reserved. This entire publication is subject to the laws of copyright. This publication may not

More information

Overview Of The. For The. Management Of IT Business

Overview Of The. For The. Management Of IT Business Overview Of The ALERT System Specifically Developed For The Management Of IT Business Contents CONTENTS THE OBJECTIVE 3 APPLICATION SCOPE 4 KEY SYSTEM FEATURES 5 THE COMPANY BEHIND ALERT 6 ALERT FUNCTION

More information

Maturity Model. March 2006. Version 1.0. P2MM Version 1.0 The OGC logo is a Registered Trade Mark of the Office of Government Commerce

Maturity Model. March 2006. Version 1.0. P2MM Version 1.0 The OGC logo is a Registered Trade Mark of the Office of Government Commerce Maturity Model March 2006 Version 1.0 P2MM Version 1.0 The OGC logo is a Registered Trade Mark of the Office of Government Commerce This is a Value Added product which is outside the scope of the HMSO

More information

People at Work Project An Assessment of Psychosocial Hazards in the Workplace Project Management Plan

People at Work Project An Assessment of Psychosocial Hazards in the Workplace Project Management Plan People at Work Project An Assessment of Psychosocial Hazards in the Workplace Project Management Plan This Project Management Plan details the key elements critical to the successful implementation of

More information

JOB DESCRIPTION. Assistant Director of Technology and Telecommunications

JOB DESCRIPTION. Assistant Director of Technology and Telecommunications JOB DESCRIPTION Title of Post: ICT Service Desk Officer Grade of Post: Band 3 Reports to: Accountable to: Location ICT Service Desk Manager Assistant Director of Technology and Telecommunications The South

More information

Recruitment and Selection Procedure

Recruitment and Selection Procedure Recruitment and Selection Procedure INTRODUCTION The College aims to attract, select and retain the best candidate to any given vacancy within the college. The College is committed to safeguarding and

More information

Audit of NSERC Award Management Information System

Audit of NSERC Award Management Information System Internal Audit Audit Report Audit of NSERC Award Management Information System TABLE OF CONTENTS 1. EXECUTIVE SUMMARY... 2 2. INTRODUCTION... 3 3. AUDIT FINDINGS- BUSINESS PROCESS CONTROLS... 5 4. AUDIT

More information

DIRECTIVE NUMBER: 141.03.04.001 v2.0. SUBJECT: Correctional Integration Systems Change Management Plan

DIRECTIVE NUMBER: 141.03.04.001 v2.0. SUBJECT: Correctional Integration Systems Change Management Plan DEPARTMENT OF CORRECTION SUPPORT Management Services DIRECTIVE NUMBER: SUBJECT: Correctional Integration Systems Change PAGE NUMBER: 1 of 10 Adopted: 12-15-03 01.00.00. POLICY OF THE DEPARTMENT It is the

More information

Dallas IIA Chapter / ISACA N. Texas Chapter. January 7, 2010

Dallas IIA Chapter / ISACA N. Texas Chapter. January 7, 2010 Dallas IIA Chapter / ISACA N. Texas Chapter Auditing Tuesday, October Project 20, 2009 Management Controls January 7, 2010 Table of Contents Contents Page # Project Management Office Overview 3 Aligning

More information

KPMG Advisory. Microsoft Dynamics CRM. Advisory, Design & Delivery Services. A KPMG Service for G-Cloud V. April 2014

KPMG Advisory. Microsoft Dynamics CRM. Advisory, Design & Delivery Services. A KPMG Service for G-Cloud V. April 2014 KPMG Advisory Microsoft Dynamics CRM Advisory, Design & Delivery Services A KPMG Service for G-Cloud V April 2014 Table of Contents Service Definition Summary (What s the challenge?)... 3 Service Definition

More information

Implementation and Customer Services ( ICS") Installation Services Standard Terms and Conditions of Supply. (Effective September 2013)

Implementation and Customer Services ( ICS) Installation Services Standard Terms and Conditions of Supply. (Effective September 2013) Implementation and Customer Services ( ICS") Installation Services Standard Terms and Conditions of Supply 1. General (Effective September 2013) This web page content defines the standard terms and conditions

More information

1. To ensure the College desktop virtual environment is appropriately configured to maintain security and optimal performance.

1. To ensure the College desktop virtual environment is appropriately configured to maintain security and optimal performance. JOB DESCRIPTION Job Title: Grade: Hours: Location: Department: Accountable to: Virtual Desktop Engineer Support Grade F 37 hours per week (pro-rata) Framwellgate Moor Campus ICT Job Purpose The holder

More information

CRM Phase 3 Development, support and maintenance - Questions and Answers

CRM Phase 3 Development, support and maintenance - Questions and Answers No. Question Answer 1. 2. 3. 4. 5. 6. 7. Are we able to discuss the requirements of this tender with the UKCES prior to submitting our proposal? Can we be placed on a list to be notified of future opportunities

More information

Clinical Risk Management: Agile Development Implementation Guidance

Clinical Risk Management: Agile Development Implementation Guidance Document filename: Directorate / Programme Document Reference NPFIT-FNT-TO-TOCLNSA-1306.02 CRM Agile Development Implementation Guidance v1.0 Solution Design Standards and Assurance Project Clinical Risk

More information

Step by Step Project Planning

Step by Step Project Planning Step by Step Project Planning Contents Introduction The Planning Process 1 Create a Project Plan...1 Create a Resource Plan...1 Create a Financial Plan...1 Create a Quality Plan...2 Create a Risk Plan...2

More information

Setting SMART Objectives

Setting SMART Objectives Setting SMART Objectives Whilst line managers are responsible for ensuring that objectives are set it is important that, wherever possible, objectives are jointly agreed, between staff and line manager,

More information

The Benefits of Management Information Systems to the Professional Practice

The Benefits of Management Information Systems to the Professional Practice The Benefits of Management Information Systems to the Professional Practice SAICE 15th Annual Conference on Computers in Civil Engineering By Dr James A Robertson PrEng & Reg M Barry, Financial Director,

More information

SEVEN STEPS TO ERP HEAVEN

SEVEN STEPS TO ERP HEAVEN SEVEN STEPS TO ERP HEAVEN In this special report Columbus ERP consultant Steven Weaver shares his secrets to ERP project success. Purchasing and successfully implementing an ERP system is one of the costliest,

More information

Industrial Rapid Implementation Methodology (InRIM)

Industrial Rapid Implementation Methodology (InRIM) Industrial Rapid Implementation Methodology (InRIM) Introduction The path to improving asset effectiveness and productivity must be based on a firm foundation created from the interaction of three essential

More information

Centrify Server Suite Health Check

Centrify Server Suite Health Check CENTRIFY OPERATIONS HEALTH CHECK OVERVIEW Centrify Server Suite Health Check Summary Have you ever wondered if your organization is using Centrify s solution to the fullest potential? At Centrify, we take

More information

Pricing Schedule for Fasset Event Management 2016 to 2018

Pricing Schedule for Fasset Event Management 2016 to 2018 Pricing Schedule for Fasset Management 2016 to 2018 Cost per Pricing based Cost per based Name of the event Budget & Tax Update Annual General Meeting 1 1 s 42 1 Suppliers 2 7 Speakers 4 0 Hosts 6 0 Number

More information

Document Management System Request for Proposals April 22, 2013

Document Management System Request for Proposals April 22, 2013 FINANCE DEPARTMENT Office (402) 562-4231 Fax (402) 563-1380 Document Management System Request for Proposals April 22, 2013 Overview: The City of Columbus, Nebraska (hereafter referred to as City ) is

More information

A director s guide How to prepare an RFI for an HR & payroll software system

A director s guide How to prepare an RFI for an HR & payroll software system A director s guide How to prepare an RFI for an HR & payroll software system consulting software solutions www.access-select.co.uk Selecting a new HR & payroll system is a big decision, one requiring significant

More information

The Association offers a factoring service to homeowners whose properties

The Association offers a factoring service to homeowners whose properties PARAGON HOUSING ASSOCIATION LIMITED POLICY: POLICY AREA: FACTORING POLICY FINANCE AND INVESTMENT DATE APPROVED: 21 ST AUGUST 2013 DATE NEXT REVIEW: AUGUST 2018 Contents 1. Introduction 2. Aims 3. Objectives

More information

Entity Information Management Strategic Review Service Definition. Overview of the service

Entity Information Management Strategic Review Service Definition. Overview of the service Entity Information Management Strategic Review Service Definition Overview of the service The purpose of this service is to review all elements of an organisation s information management strategy and

More information

MICROSOFT DYNAMICS CRM

MICROSOFT DYNAMICS CRM MICROSOFT DYNAMICS CRM SERVICE DEFINITION G-CLOUD Commercial-in-Confidence civil.lockheedmartin.co.uk SECTION 1 LOCKHEED MARTIN S MICROSOFT DYNAMICS CRM CAPABILITY INTRODUCTION Lockheed Martin offers a

More information

Adlib Hosting - Service Level Agreement

Adlib Hosting - Service Level Agreement Adlib Hosting - Service Level Agreement June 2014 This service level agreement (SLA) applies to the Adlib Hosting services provided by Axiell ALM Netherlands BV, and includes the activities and facilities

More information

LGS Project Management Methodology

LGS Project Management Methodology Page: 32 LGS Project Management Methodoy The LGS project management methodoy is integral to our overall delivery methodoy. Based on inpro, one of the LGS inspiration series documents, our methodoy is compliant

More information

Infrastructure Change Management. The process and procedures for all changes to the live environment

Infrastructure Change Management. The process and procedures for all changes to the live environment Infrastructure Change Management The process and procedures for all changes to the live environment Version 4.1 October 2012 1.0 Introduction... 3 2.0 The Change Process... 4 2.1 Why raise a change?...

More information

Contract Management. Brief 22. Public Procurement. September 2011

Contract Management. Brief 22. Public Procurement. September 2011 Brief 22 September 2011 Public Procurement Contract Management C O N T E N T S The process of contract management Contract management in practice Post contract performance review www.sigmaweb.org This

More information

Amendments History No Date Amendment 1 July 2015 Policy re approved with Job titles and roles updated 2 3 4 5 6 7

Amendments History No Date Amendment 1 July 2015 Policy re approved with Job titles and roles updated 2 3 4 5 6 7 Document Details Title Claims Management Policy Trust Ref No 1534-27272 Local Ref (optional) N/A Main points the document covers This policy and procedure details the arrangements for the notification

More information

ARGYLL AND BUTE COUNCIL SUPPORT SERVICES REVIEW 15 DECEMBER 2011 SUMMARY REPORT

ARGYLL AND BUTE COUNCIL SUPPORT SERVICES REVIEW 15 DECEMBER 2011 SUMMARY REPORT ARGYLL AND BUTE COUNCIL EXECUTIVE SUPPORT SERVICES REVIEW 15 DECEMBER 2011 SUMMARY REPORT 1.0 SUMMARY 1.1 The service reviews for Customer and Support Services, Improvement and HR and Strategic Finance

More information

Centrify OS X Basic Jump Start

Centrify OS X Basic Jump Start CENTRIFY DATASHEET Centrify OS X Basic Jump Start The Centrify OS X Jump Start gives organizations the training and hands-on experience to rapidly deploy Centrify's solution for Identity, Policy and Device

More information

developing an action plan Implementing change: Implementing change: developing an action plan

developing an action plan Implementing change: Implementing change: developing an action plan Implementing change: developing an action plan Implementing change: developing an action plan Implementing change: developing an action plan Implementing change overview The change process through which

More information

Managed WAN Installation Service Definition

Managed WAN Installation Service Definition Version 2.0 2 nd March 2015 Contents CONFIDENTIALITY STATEMENT......... 4 1 DOCUMENT CONTROL......... 5 1.1 Version control... 5 1.2 Distribution Intended... 5 2 INTRODUCTION......... 6 3 INSTALLATION

More information

PERFORMANCE MANAGEMENT STRATEGY

PERFORMANCE MANAGEMENT STRATEGY PERFORMANCE MANAGEMENT STRATEGY Date published: May 2013 South Essex Homes Keeping you informed www.southessexhomes.co.uk 0800 833 160 1 of 12 SOUTH ESSEX HOMES: PERFORMANCE MANAGEMENT STRATEGY This strategy

More information

Performance Management Development System (PMDS) for all Staff at NUI Galway

Performance Management Development System (PMDS) for all Staff at NUI Galway Performance Management Development System (PMDS) for all Staff at NUI Galway PMDS.doc 1 1. Introduction The Performance and Development Review System (PMDS) for NUI Galway has its foundation in Sustaining

More information

EDMS Project Outcome Realisation Plan

EDMS Project Outcome Realisation Plan Outcome Realisation Plan Version 1.A (14 August 2008) Copy: Uncontrolled Corporate Support Department of Treasury and Finance DOCUMENT ACCEPTANCE and RELEASE NOTICE This is version 1.A of the Outcome Realisation

More information

First National Data Quality Review: Executive Summary Quality Information Committee

First National Data Quality Review: Executive Summary Quality Information Committee First National Data Quality Review: Executive Summary Quality Information Committee Executive Summary Introduction to the report This report has been produced by the Quality Information Committee (QIC)

More information

Merrycon s Approach to Business Continuity Management

Merrycon s Approach to Business Continuity Management Merrycon s Approach to Business Continuity Management Business Continuity is a management discipline that provides a framework for an organisation to build resilience, providing the capability for an effective

More information

T2S PROGRAMME OFFICE. Connecting to T2S. Technical Session. June 25 th, 2014. 2010 Colt Telecom Group Limited. All rights reserved.

T2S PROGRAMME OFFICE. Connecting to T2S. Technical Session. June 25 th, 2014. 2010 Colt Telecom Group Limited. All rights reserved. T2S PROGRAMME OFFICE Connecting to T2S Technical Session June 25 th, 2014 2010 Colt Telecom Group Limited. All rights reserved. Agenda Connecting to T2S Overview Onboarding Phase NSP Support User Testing

More information

SCHEDULE 16. Exit Plan. sets out the strategy to be followed on the termination (including Partial Termination) or expiry of this Agreement; and

SCHEDULE 16. Exit Plan. sets out the strategy to be followed on the termination (including Partial Termination) or expiry of this Agreement; and SCHEDULE 16 Exit Plan 1. Scope 1.1 This schedule: (A) sets out the strategy to be followed on the termination (including Partial Termination) or expiry of this Agreement; and requires the Service Provider

More information

National Occupational Standards for the Financial Services Sector. Administration for Mortgage and/or Financial Planning Intermediaries

National Occupational Standards for the Financial Services Sector. Administration for Mortgage and/or Financial Planning Intermediaries The Sector Skills Council for financial services, accountancy and finance National Occupational Standards for the Financial Services Sector Administration for Mortgage and/or Financial Planning Intermediaries

More information

The Art of CRM. A white paper by cloudfortyseven Limited. Author: Michael Fleming DipM ACIM

The Art of CRM. A white paper by cloudfortyseven Limited. Author: Michael Fleming DipM ACIM The Art of CRM A white paper by cloudfortyseven Limited Author: Michael Fleming DipM ACIM Copyright 2010 by cloudfortyseven Limited all the text, graphics, design, and other works are the copyrighted works

More information

OPERATIONAL SERVICE LEVEL AGREEMENT BETWEEN THE CLIENT AND FOR THE PROVISION OF PRO-ACTIVE MONITORING & SUPPORT SERVICES

OPERATIONAL SERVICE LEVEL AGREEMENT BETWEEN THE CLIENT AND FOR THE PROVISION OF PRO-ACTIVE MONITORING & SUPPORT SERVICES OPERATIONAL SERVICE LEVEL AGREEMENT BETWEEN THE CLIENT AND FOR THE PROVISION OF PRO-ACTIVE MONITORING & SUPPORT SERVICES IN CONFIDENCE TABLE OF CONTENTS 1 CONTACT DETAILS 1 1.1 The Client Contract Management

More information

Level 5 Diploma in Managing the Supply Chain (QCF) Qualification Specification

Level 5 Diploma in Managing the Supply Chain (QCF) Qualification Specification Level 5 Diploma in Managing the Supply Chain (QCF) Qualification Specification Created: May 2012 Version: 1.0 Accreditation Number: 600/5605/8 Qualification Start Date: 1 st June 2012 Qualification Last

More information

STANDARD TERMS AND CONDITIONS FOR DIGITAL PROJECTS. - part of the Supply Agreement for digital projects

STANDARD TERMS AND CONDITIONS FOR DIGITAL PROJECTS. - part of the Supply Agreement for digital projects STANDARD TERMS AND CONDITIONS FOR DIGITAL PROJECTS - part of the Supply Agreement for digital projects Version 2.0, Juni 2014 CONTENTS Contents... 2 1. Preamble... 5 2. The Agreement... 5 2.1 The delivery...

More information

DRAFT 8 th January 2015 Senior Chef Apprenticeship in Culinary Arts Standard Assessment Plan. Introduction

DRAFT 8 th January 2015 Senior Chef Apprenticeship in Culinary Arts Standard Assessment Plan. Introduction DRAFT 8 th January 2015 Senior Chef Apprenticeship in Culinary Arts Standard Assessment Plan Introduction Hospitality employers, recognised by the Department for Business Innovation and Skills (BIS) as

More information

Colorado Department of Health Care Policy and Financing

Colorado Department of Health Care Policy and Financing Colorado Department of Health Care Policy and Financing Solicitation #: HCPFRFPCW14BIDM Business Intelligence and Data Management Services (BIDM) Appendix B BIDM Project Phases Tables The guidelines for

More information

IRIS Managed Payroll Service

IRIS Managed Payroll Service IRIS Managed Payroll Service Friendly, reliable, efficient For further information please call the IRIS team on 0844 815 5677 or email earniesales@iris.co.uk About IRIS Managed Payroll Service IRIS have

More information

Assessment Services Panel Contract

Assessment Services Panel Contract User Guidelines December 2014 Assessment Services Panel Contract Version 5.0 Assessment Services Panel Contract Assessment Services Panel Contract Status Document number File number Application Category

More information

School Council Financial Audits Guidelines to Schools Division

School Council Financial Audits Guidelines to Schools Division School Council Financial Audits Guidelines to Schools Division Contents Introduction... 3 Why do we audit?... 4 Who do we audit?... 5 What do we audit?... 6 When will schools be audited? (SCFA Calender)...

More information

7 Golden Rules for Participation a short film commission SPECIFICATION. Invitation to submit a quotation

7 Golden Rules for Participation a short film commission SPECIFICATION. Invitation to submit a quotation 7 Golden Rules for Participation a short film commission SPECIFICATION Invitation to submit a quotation January 2015 Part One Details of Specification 1. Introduction Scotland s Commissioner for Children

More information

INTERNAL AUDIT SERVICES Glenorchy City Council Internal audit report of Derwent Entertainment Centre financial business and operating systems

INTERNAL AUDIT SERVICES Glenorchy City Council Internal audit report of Derwent Entertainment Centre financial business and operating systems INTERNAL AUDIT SERVICES Internal audit report of Derwent Entertainment Centre financial business and operating systems ADVISORY Contents Executive summary...2 Internal audit findings...4 Summary of other

More information

INTRODUCTION. 1.1 The Need for Guidance on ERP System Validation

INTRODUCTION. 1.1 The Need for Guidance on ERP System Validation Chapter1 13/3/06 8:38 pm Page 1 1 INTRODUCTION 1.1 The Need for Guidance on ERP System Validation There are numerous books that address the topic of computer systems validation in the regulated life sciences

More information

A Retailer Guide to Bank Accreditation

A Retailer Guide to Bank Accreditation A Retailer Guide to Bank Accreditation An Overview of the Bank Accreditation / Acquirer Acceptance Testing Process for Chip and PIN Produced by the Chip and PIN Programme Management Organisation Version

More information

Honours Degree (top-up) Computing Abbreviated Programme Specification Containing Both Core + Supplementary Information

Honours Degree (top-up) Computing Abbreviated Programme Specification Containing Both Core + Supplementary Information Honours Degree (top-up) Computing Abbreviated Programme Specification Containing Both Core + Supplementary Information 1 Awarding Institution / body: Lancaster University 2a Teaching institution: University

More information

UoD IT Job Description

UoD IT Job Description UoD IT Job Description Role: Projects Portfolio Manager HERA Grade: 8 Responsible to: Director of IT Accountable for: Day to day leadership of team members and assigned workload Key Relationships: Management

More information

Guidelines for the Employment of Assistant Psychologists in Ireland

Guidelines for the Employment of Assistant Psychologists in Ireland The Psychological Society of Ireland Policy Document: Guidelines for the Employment of Assistant Psychologists in Ireland 2014 Contents 1. Introduction...3 2. The Role of an Assistant Psychologist...4

More information

Appendix D Programme Stream 6 CRM Procurement. Programme Stream 6 Remodelling of Customer Services Programme CRM Procurement

Appendix D Programme Stream 6 CRM Procurement. Programme Stream 6 Remodelling of Customer Services Programme CRM Procurement Programme Stream 6 Remodelling of Customer Services Programme CRM Procurement Recommendations That the Executive note CRM procurement will be put out to tender in 2010/11 and note the proposed phasing

More information

Procurement guidance Managing and monitoring suppliers performance

Procurement guidance Managing and monitoring suppliers performance Procurement guidance Managing and monitoring suppliers performance Procurement guidance: Managing and monitoring suppliers performance Page 2 of 16 Table of contents Table of contents... 2 Purpose of the

More information

Contract and Vendor Management Guide

Contract and Vendor Management Guide Contents 1. Guidelines for managing contracts and vendors... 2 1.1. Purpose and scope... 2 1.2. Introduction... 2 2. Contract and Vendor Management 2.1. Levels of management/segmentation... 3 2.2. Supplier

More information

FNSICACC307A Reconcile and monitor accounts receivable

FNSICACC307A Reconcile and monitor accounts receivable FNSICACC307A Reconcile and monitor accounts receivable Release: 1 Modification History Not Available Approved Page 2 of 11 INTRODUCTION Unit Descriptor Application of the Unit This unit describes the functions

More information

Managing Sickness Absence Procedure. Management Guidance

Managing Sickness Absence Procedure. Management Guidance Managing Sickness Absence Procedure. Management Guidance Related Documents: Absence Policy 1. Purpose 1.1. The aim of this procedure is to ensure Tees Valley YMCA adopts a fair and effective approach to

More information

Your launch pad for excellence UNIVERSITY. 6 cm filling height. Ferranti Computer Systems MECOMS University Training Overview

Your launch pad for excellence UNIVERSITY. 6 cm filling height. Ferranti Computer Systems MECOMS University Training Overview Your launch pad for excellence UNIVERSITY 6 cm filling height Ferranti Computer Systems MECOMS University Training Overview CLASSROOM: ADVANCED FUNCTIONAL METER DATA MANAGEMENT UNIVERSITY Introduction

More information

Resource Management. Determining and managing the people resources on projects can be complex as:

Resource Management. Determining and managing the people resources on projects can be complex as: Baseline Resource Management RESOURCE MANAGEMENT Purpose To provide a procedure and associated guidelines to facilitate the management of project people resources. Overview This Phase is used to establish

More information

PRCA Communications Management Standard (CMS) for In-House Teams

PRCA Communications Management Standard (CMS) for In-House Teams PRCA Communications Management Standard (CMS) for In-House Teams PRCA Communications Management Standard (CMS) for In-House Teams Contents Introduction 4 The Communications Management Standard for In-House

More information

COMHAIRLE NAN EILEAN SIAR S CUSTOMER SERVICE STRATEGY

COMHAIRLE NAN EILEAN SIAR S CUSTOMER SERVICE STRATEGY S September 2008 CONTENTS INTRODUCTION...3 CUSTOMER RELATIONSHIP MANAGEMENT (CRM)...7 ACCESS CHANNELS...9 CUSTOMER CARE STANDARDS...13 PERFORMANCE & CONTINUOUS IMPROVEMENT...15 2 INTRODUCTION Background

More information

Introduction: Synopsis: right right Detail: Page

Introduction: Synopsis: right right Detail: Page Introduction: Here s a question that often gets asked: What are the benefits of Business Analysis? The depressing but true answer is that the benefits are usually invisible: good Business Analysis ensures

More information

SAP ERP Upgrade Checklist Project Preparation

SAP ERP Upgrade Checklist Project Preparation A SAP ERP Upgrade Checklist Project Preparation Upgrade Project Phase Project Preparation Definition From the project perspective the project preparation phase includes: Learning about the new functionality

More information

The power to transform your business

The power to transform your business The power to transform your business Optimus 2020 continues to be the number one choice for litho and packaging printers worldwide. What is the secret of our longevity? Constant research and forward thinking

More information

Physical Security Information Management Software - Concepts - Solutions

Physical Security Information Management Software - Concepts - Solutions Physical Security Information Management Software - Concepts - Solutions A system is only as secure as its weakest link Technical Management Security Information Management ViPRO.solutions Communications

More information

AGILE ANALYSIS AVOIDING PARALYSIS: AN INTEGRATED FRAMEWORK FOR RESPONSIVE PROJECT ANALYSIS 1

AGILE ANALYSIS AVOIDING PARALYSIS: AN INTEGRATED FRAMEWORK FOR RESPONSIVE PROJECT ANALYSIS 1 AGILE ANALYSIS AVOIDING PARALYSIS: AN INTEGRATED FRAMEWORK FOR RESPONSIVE PROJECT ANALYSIS 1 The Business Case formally documents and baselines the change project. It provides the framework within which

More information

Policy on Student Module and Programme Feedback

Policy on Student Module and Programme Feedback Policy on Student Module and Programme Feedback Introduction The University constantly reviews the structure of its degrees, the content of its modules and the application of its rules and regulations.

More information

Request for Proposal for implementation of SAP HANA ERP System at MCL, ZAMBIA

Request for Proposal for implementation of SAP HANA ERP System at MCL, ZAMBIA Request for Proposal for implementation of SAP HANA ERP System at MCL, ZAMBIA RFP No. MCL/ZM/IT/001 Date of Issue: 10 th September, 2015 Last date of submission: 17 th October, 2015 Place of Submission:

More information

APPENDIX A (CFO/263/09) Merseyside Fire & Rescue Service ICT Outsourcing Procurement Support. Final Report

APPENDIX A (CFO/263/09) Merseyside Fire & Rescue Service ICT Outsourcing Procurement Support. Final Report Merseyside Fire & Rescue Service ICT Outsourcing Procurement Support Final Report Version 1.1 Oct 2009 Contents 1. Executive Summary...3 2. Context and Background...3 3. Deliverables and Value Added...

More information

For the Design, Installation, Commissioning & Maintenance of Fixed Gaseous Fire Suppression Systems

For the Design, Installation, Commissioning & Maintenance of Fixed Gaseous Fire Suppression Systems BAFE Scheme: SP203-3 Version 1: July 2008 Amendment No: 1 Fire Protection Industry Scheme, Reference SP203 Part 3 For the Design, Installation, Commissioning & Maintenance of Fixed Gaseous Fire Suppression

More information

Support Service Level Agreements

Support Service Level Agreements Support Service Level Agreements Our commitment to you This Service Level Agreement (SLA) identifies what Newedge customers can typically expect from us with regard to day-to-day online application and

More information

External Audit Reviews. Report by Director of Finance

External Audit Reviews. Report by Director of Finance THE HIGHLAND COUNCIL AUDIT AND STANDARDS COMMITTEE 4 DECEMBER 2003 Agenda Item Report No External Audit Reviews Report by Director of Finance SUMMARY The pages that follow contain a report from the Council's

More information

WHITE PAPER. Ready, Set, Go Upgrade to ERP Cloud Release 10

WHITE PAPER. Ready, Set, Go Upgrade to ERP Cloud Release 10 WHITE PAPER Ready, Set, Go Upgrade to ERP Cloud Release 10 INTRODUCTION It s time to upgrade our ERP. For many, those words often trigger thoughts of projects past where countless hours are spent bringing

More information

ACDM GUIDELINES TO FACILITATE PRODUCTION OF A DATA HANDLING PROTOCOL

ACDM GUIDELINES TO FACILITATE PRODUCTION OF A DATA HANDLING PROTOCOL ACDM GUIDELINES TO FACILITATE PRODUCTION OF A DATA HANDLING PROTOCOL BACKGROUND The need was identified by the Electronic Data Transfer Special Interest Group (SIG) for each company or organisation to

More information

MAGENTA KEYLINE IS A CUTTER GUIDE, DO NOT PRINT. PLEASE SET TRAPPING THROUGHOUT

MAGENTA KEYLINE IS A CUTTER GUIDE, DO NOT PRINT. PLEASE SET TRAPPING THROUGHOUT Risk & Assurance Integrated software solution Managing risks and providing assurance that the process is working is a key requirement for any organisation, as is having an effective and efficient software

More information

Securing best practice, quality methods and fit-for-purpose resourcing and facilities www.thelpi.org

Securing best practice, quality methods and fit-for-purpose resourcing and facilities www.thelpi.org Technical Support Centre Accreditation Securing best practice, quality methods and fit-for-purpose resourcing and facilities www.thelpi.org Learning & Performance Institute Introduction With the increasing

More information

Business Continuity Planning and Disaster Recovery Planning

Business Continuity Planning and Disaster Recovery Planning 4 Business Continuity Planning and Disaster Recovery Planning Basic Concepts 1. Business Continuity Management: Business Continuity means maintaining the uninterrupted availability of all key business

More information

Healthwatch Oxfordshire Board of Directors

Healthwatch Oxfordshire Board of Directors Healthwatch Oxfordshire Board of Directors Date of Meeting: October 14 th 2014 Paper No: 9 Title of Presentation: Amendments to contract with OCC This paper is for Discussion Decision x Information Purpose

More information

Hertsmere Borough Council. Data Quality Strategy. December 2009 1

Hertsmere Borough Council. Data Quality Strategy. December 2009 1 Hertsmere Borough Council Data Quality Strategy December 2009 1 INTRODUCTION Public services need reliable, accurate and timely information with which to manage services, inform users and account for performance.

More information

Recovery College Co-ordinator. Job Description

Recovery College Co-ordinator. Job Description Recovery College Co-ordinator Job Description Job Title: Recovery College Co-ordinator Band: 7 Location: Recovery College, Ulster Hospital In order to meet the needs of the Trust s services you may be

More information

Letter of Agreement. Audience. Deliverables and Specifications. Date. Usually, I put this document on my business letterhead.

Letter of Agreement. Audience. Deliverables and Specifications. Date. Usually, I put this document on my business letterhead. Date Mr. Jim Customer Address Address Usually, I put this document on my business letterhead Letter of Agreement Thank you for selecting me as the independent contractor to design and develop XYZ, an intermediate

More information

CRM Budgeting & Planning

CRM Budgeting & Planning This document has been put together to support clients with their budgeting and planning for implementing CRM for a Phase 1. No matter what your budget, Cloud9 Insight have designed three different first

More information