1 Report title Agenda item Project, Programme and Portfolio Management Delivery Plan 6 Meeting Performance Management and Community Safety Panel 27 April 2009 Date Report by Document number Head of Strategy and Performance PMC 58 Public Summary This paper explains the progress in delivering effective project, programme and portfolio management within the Brigade and sets out the need for a delivery plan to guide the next steps. The delivery plan covers the people, process and governance aspects that the Brigade needs to continuously enhance to ensure that it has the capabilities necessary to deliver the changes that are planned for the coming years. Recommendation The Panel note the project, programme and portfolio delivery plan. 1 of 11

2 Introduction 1. The Brigade is faced with constant demands to deliver significant amounts of change. These demands come both from within, to deliver strategic aims and department plans, and from without, as parts of national and local government strategies. To ensure that we have the ability to meet these demands, we need to continuously improve our capability to deliver projects and programmes. 2. The Brigade has made significant improvements in achieving prioritisation, visibility and consistency for projects in the last two years. This Project, Programme and Portfolio Management (P3M) delivery plan is a formalisation of the direction of travel we have been pursuing to date and wish to continue into the future. Project, Programme and Portfolio Management (P3M) 3. For the purposes of this delivery plan, project management is a discipline for the management of projects which encompasses the planning, monitoring and control of all aspects of the project and the motivation of all those involved in it to achieve the project objective on time and to the specified cost, quality, and performance. 4. Programme management provides the governance and delivery of a grouping of projects and activities coordinated and managed as a unit such that they collectively achieve outcomes and realise benefits. 5. Projects and programmes are different - programmes are generally embarked upon when only a strategic outcome is defined, whereas projects require the end status and major deliverables to be defined before approval. As a result, even though they are linked, their management requires a different skill set, different tools and different governance arrangements. 6. Portfolio management is a process for co-ordinating successful delivery of a set of projects and programmes whilst continuing to deliver the service. It is about maximising the throughput of projects to ensure the optimum delivery of value from overall investment in change and balancing the commitment of resources between change (projects and programmes) and ensuring the continuation of day to day activities (business as usual). The Programme Support Office (PSO) as a Centre of Excellence 7. The Office of Government Commerce (OGC) recommends that an organisation should have a coordinating function providing strategic oversight, scrutiny and challenge across the organisation s portfolio of programmes and projects. They define this function as a Centre of Excellence (COE) for Project and Programme Management. This COE should be a focal point for supporting individual programmes and projects, and for driving the implementation of improvements to increase the organisation s capability and capacity in programme and project delivery. 8. The delivery plan in the Appendix has been written to reflect the OGC s guidance for organisational development through a COE function and takes into account the unique nature of the Brigade and lessons learnt from other organisations. 9. Further guidance on the OGC s recommendations for improving capability to deliver change projects and programmes can be found at: The Delivery Plan 10. This plan will move the Brigade closer to compliance with OGC project, programme and portfolio guidance (PRINCE2, MSP and Portfolio) while moving us up their Project, Programme, Portfolio Management 2 of 11

3 Maturity Model (P3M3) scale. This scale measures an organisation s maturity in the areas of: management control; benefits management; financial management; stakeholder management; risk management; organisational governance and resource management. More information on the P3M3 self assessment can be found at: 11. The main aim of the plan is to build on the significant improvements that have been made recently in project management. The details are in the Appendix but the primary objectives are to: a. support and develop the capabilities of the individuals who have been assigned the role of project manager; b. embed current project management processes and develop these further towards industry best practice; c. embed and enhance the governance of projects; d. assure the achievement of programme outcomes through establishing and refining the Brigade s programme management processes; e. embed and refine corporate portfolio management to maximise the return on investment and balance the load between change and service delivery; f. develop our capability to the point where we can actively seek recognition for our achievements in project, programme and portfolio management. 12. In particular, the plan suggests that we investigate the benefits of establishing a pool of professional project managers. One of the ways in which this could be done is to build on the existing approach of developing our own in-house expertise among staff who are required to manage projects as part of their work. This could become an optional part of the development process for uniformed staff, allowing them to acquire and apply a key set of transferable skills, developing their financial management and strategic awareness skills for example. 13. This plan reflects the intended direction of travel for the Brigade as a whole. The Programme Support Office can lead most of the activities required to deliver it and the budgets/headcount authorised by Authority in March reflected the necessary headcount, skills and costs. However continued senior management support in the form of effective project and programme sponsorship and performance management scrutiny will be required to enable success. All projects and programmes will need to be subjected to a level of scrutiny and management appropriate to their size and complexity. Authority s Strategic Objectives 14. Delivering the targets set out in all six of the Strategic Aims will require the delivery of existing and new projects and programmes to change the Brigade s infrastructure, processes, working patterns and behaviours. Corporate Risk number 6 is defined as: business processes to support delivery of our improvement programme are ineffective which impacts on the business benefits delivered. Implementation of this P3M plan is one of the control measures for this risk in that it aims to provide the Brigade with continuously improving capability to shape, control and deliver these changes which are essential to achieving the strategic aims. Head of Legal and Democratic Services comments 15. The Head of Legal and Democratic Services has reviewed this report and has no comments. 3 of 11

4 Head of Finance Comments 16. The Head of Service has reviewed this report and has no comments. Environmental Implications 17. Understanding (and subsequent management) of the environmental implications of projects will be enhanced as the process for project management includes ensuring that a Sustainable Development Impact Assessment is carried out for all projects. Equalities Implications 18. Understanding (and subsequent management) of the equalities implications of projects will be enhanced as the process for project management includes ensuring that an Equalities Impact Assessment is carried out for all projects. List of Appendices to this report: 1. The Project, programme and portfolio Management Delivery Plan Local Government (access to information) Act 1985 List of background documents 1. London Safety Plan 2. Centres of Excellence for Programme & Project Management, produced by the OGC 3. Portfolio, Programme and Project Management Maturity Model, produced by the OGC 4. Managing Successful Projects with PRINCE2, produced by the OGC 5. Managing Successful Programmes, produced by the OGC 6. Portfolio, Programme and Project Offices (P3O), produced by the OGC Proper officer Contact officer Telephone Nick Collins, Head of Strategy & Performance Matt Cocker x of 11

5 Project, programme and portfolio management delivery plan Increasing London Fire Brigade s capability to deliver change 5 of 11

6 Summary The project, programme and portfolio management delivery plan will support the delivery of strategic aims while controlling corporate risk 6: Business processes to support delivery of our improvement programme are ineffective which impacts on the business benefits delivered by increasing the Brigade s capability to deliver change. The focus will be on supporting those who are delivering (or are supporting) those delivering public facing services and introducing process without bureaucracy. Capability will be improved in people, process and governance themes for project, programme and portfolio delivery. Those involved in the delivery of projects will be supported, guided and developed to a level of professionalism in project management disciplines. The Programme Support Office will be consolidated and developed along the lines of an Office of Government Commerce Centre of Excellence for Project and Programme Management. Strategic context This document sets out the strategic framework for project, programme and portfolio management (P3M) and is part of a suite of performance management documents which show how the London Fire Brigade intends to shape the work we do and join our activities together to achieve our aims and objectives within the London Safety Plan. Its purpose is to clearly show how we will increase the London Fire Brigade s capability to deliver change. The Brigade s six main strategic aims are set out in the London Safety Plan. These are: 1. Prevention : Engaging with London s communities to inform and educate people in how to reduce the risk of fires and other emergencies 2. Protection : Influencing and regulating the built environment to protect people, property and the environment from harm 3. Response : Planning and preparing for emergencies that may happen, and making a high quality, effective and resilient response to them 4. Resources : Managing risk by using our resources flexibly, efficiently and effectively, continuously improving the way we use public money 5. People : Working together to deliver the highest quality services within a safe and positive environment for everyone in the organisation 6. Principles : Operating in accordance with our values, and ensuring that safety, sustainability, partnership and diversity run through all our activities Delivering the targets set out for these aims will require the delivery of existing and new projects and programmes to change the Brigade s infrastructure, processes, working patterns and behaviours. This P3M plan aims to provide the Brigade with continuously improving capability to shape, control and deliver these essential changes. Customer focus A core principle running through the P3M plans and actions is that P3M is there to support those delivering public facing services aimed at making London safer. The implementation of P3M will enhance the shaping and control of change without unnecessarily delaying its delivery or increasing the burden of bureaucracy on those delivering (or supporting) front line services. Project management The area where the greatest improvements can be achieved is in project management. The Brigade s capability in project management has improved significantly over the last few years. This has been achieved 6 of 11

7 through the efforts of the Programme Support Office in defining and embedding basic processes and providing support and training to project managers. Continuous improvement will continue in the following ways: During 2009/10 People: ensure that all project managers, project support officers, workstream leaders and newly appointed Group Managers will complete the Brigade specific, two day (Level 1) training in general project management ensure that all project managers will complete the four one day events that form the more advanced, in-depth (Level 2) training provide coaching support to project managers and sponsors seek to create a Special Award category which recognises and rewards excellence in project management continue to engage the project managers in their own development through focus groups and an active Community of Interest investigate the feasibility of establishing a dedicated pool of professional project managers and project support officers (from within existing headcount and budget) to lead the Brigade s highest priority projects. provide specific training to develop project support staff introduce an induction process for new project managers embed basic processes (including change control, workpackage definition, requirements management, change control, risk management) through coaching, training and 121 support Processes make tools and processes more readily accessible through Hotwire and SharePoint develop and embed a corporate projects SharePoint site continue to encourage the consistent use of lessons learned in defining and controlling new projects investigate the benefits of a project management tool (such as Microsoft Project Server) that could give consistent reporting and risk management and be compatible with corporate planning processes ensure regular benefit realisation reviews are undertaken and reported to CMB Governance embed prioritisation and governance categories review the information made available to CMB to enable them to govern the corporate portfolio of change reduce risks to project delivery through the provision of assurance activities such as initiation workshops, planning workshops and healthchecks ensure that all new projects are initiated appropriately, in accordance with agreed procedures embed project closedown activities to ensure appropriate hand-over to operations and provision for benefit realisation work with colleagues in Finance to embed the in-year project approval process support and enable, where relevant, the integration of corporate, financial, department and project planning 7 of 11

8 During 2010/12 People work towards project managers on the highest priority projects having professional qualifications (Association for Project Managers or Project Management Institute) through the existing training budget review existing competencies frameworks for those staff delivering projects to ensure that they reflect our requirements seek external recognition of the performance of individuals (e.g. entries to the Association for Project Managers Project Manager of the Year) sustain continuous development through focus groups and an active Community of Interest Processes investigate the benefits and feasibility of each project having a specific, cross functional budget allocated which is managed and reported on by the Project Manager consider the introduction of sophisticated project management processes (such as Earned Value Management) in those projects that would benefit from them Governance ensure all projects will have agreed levels of delegation and tolerance seek to open high priority projects to external scrutiny (e.g. Office of Government Commerce Gateway (OGC) reviews) ensure that every project has its business case regularly updated and scrutinised to confirm ongoing viability ensure that consistent metrics are used so that the effectiveness of projects can be easily compared ensure that resource management processes allow the commitment of cross-functional resources according to mature plans built on realistic estimates Programme management Programme management can be described as the grouping of projects and activities that are co-ordinated and managed as a unit so that they achieve outcomes and realise benefits. It requires the subordination of individual projects to the requirements of delivering business outcomes rather than the delivery of project outputs. As this form of programme management is relatively new to the Brigade, the intention is to start with one programme and integrate management using programme management techniques. During 2009/10 establish a programme structure focus on the business outcomes and benefits of programmes carry out ongoing assessment of the benefits of programme management in operation During 2010/12 pursue wider adoption of programme management techniques where appropriate develop the knowledge and skills of staff in programme management roles (including programme director, programme manager, business change manager and programme design manager) 8 of 11

9 integrate programme, portfolio and project management processes, reports and governance structures integrate programme planning with the London Safety, budgetary and risk planning processes Portfolio management Portfolio management is a process for co-ordinating the successful delivery of a set of projects and programmes whilst maintaining existing service levels. It is about maximising the throughput of projects to ensure the organisation optimises its return from its investment in change. Effective portfolio management both informs the organisation s awareness of its capacity for change and identifies opportunities to further improve capacity management. A form of portfolio management has been tried by Brigade under the banner of programme management in 2007 aligned to the three Directorates that were in place then. Lessons have been learnt from this activity and the grouping of projects into related portfolios allocated to directors has been laid out in the Director Business Outlines (Ref 1). During 2009/010 continue improvement in the consistent use of project management processes embed top management support for the portfolios as laid out in the Director Business Outline (Ref 1) encourage and support ownership of the portfolios within the directorates enforce rigorous assessment of project business cases to ensure that highest value projects are given priority support project teams in establishing escalation routes appropriate to the size, complexity and priority of each project reinforce the Programme Support Office as the primary source for collection, analysis and presentation of portfolio data raise the capability and performance of the Programme Support Office to support portfolio managers and CMB implement feedback loops to ensure top management decisions are communicated and acted upon by project teams During 2010/12 raise the performance of the PSO to influence the corporate portfolio of projects and programmes consider opening the portfolio to scrutiny both by the Authority and external bodies such as the OGC further integrate portfolio planning processes with the London Safety, Corporate, Budgetary and Strategic Risk planning processes review functions providing portfolio information across the Brigade to identify where consolidation can bring efficiency savings Programme Support Office The programme support office (PSO) exists to: 1. Give coherent upward reporting on the portfolio of projects in such a way as to enable effective decision making 2. Provide practical process support, guidance and advice to project managers in delivering their projects 3. Provide project assurance 4. Develop and set the Brigade s toolkit, guidance and performance standards for P3M 9 of 11

10 5. Provide advice and guidance on development and opportunities for project managers and sponsors through training and coaching programmes 6. Ensure that lessons learned are gathered and applied to projects 7. Network with external bodies to ensure best practice is applied within the Brigade and that the Brigade s P3M is represented in the best light amongst peers The plan for the PSO is to continue development towards a Centre of Excellence model as defined by the OGC (Ref 3). During 2009/10 In continuing to develop the service offered by the PSO, we will: recruit to fill the roles currently covered by contract staff. The new organisation will consist of: o a lead administrator who will also support the Planning and Risk teams o a Group Manager on secondment who will lead on the development of the people aspects of this plan and deliver support to project managers o an FRS F level project management specialist who will lead the process elements of this plan o an FRS G level manager who will lead the governance aspects of this plan, manage the team and also manage the planning team o to support these permanent roles a specialist project, programme and portfolio consultant will be engaged to provide in depth support and guidance to the team and senior managers where appropriate lead on all of the aims for P3M outlined above deliver assurance to all the high priority (governance levels A and B) projects continue building confidence and credibility through customer focussed, pragmatic support to project managers and sponsors continue to support senior management decision making through the gathering, analysis and presentation of project information increase the perceived value of the information reported upward exploit the information currently gathered by the PSO but not presented (such as the project interdependency network and combined portfolio performance indicators) develop and implement advanced project management training programmes offer coaching to sponsors as well as project managers integrate the project assurance activities with the Audit and Assurance Group develop the commitment and engagement of project managers in the Community of Interest During 2010/12 drive the scrutiny and challenge of the Brigade s portfolio lead on all of the aims for P3M outlined above develop and implement professional project management training programmes present to peer networking events (such as the Public Sector Project Management Conference) review the feasibility of project management staff rotating through the PSO to enhance the PSO and provide development opportunities to the individuals 10 of 11

11 ensure PSO staff will become professionally qualified in P3M and PSO functions if deemed appropriate, take ownership of the pool of project managers and project support officers Measurement and monitoring There is a comprehensive, task based, plan to delivery this plan. This plan includes measures to indicate successful implementation. Examples of some of the measures are: Area Measure Project assurance Number and results of healthchecks Percentage of time the PSO staff dedicated to Customer focus carrying out project specific support activities Numbers of project managers who complete training courses and hold qualifications Delivering training Project manager engagement Training effectiveness evaluation Attendance records for Community of Interest events References 1. Director Business Outline document 2. London Safety Plan 3. The Centre of Excellence a Pocket guide published by the OGC (http://www.ogc.gov.uk/documents/centre_of_excellence_ pack_v3.1.pdf) 4. P3M3 self assessment documentation can be found at: (http://www.p3m3- officialsite.com/nmsruntime/saveasdialog.asp?lid=382&sid=90) 11 of 11

Change Management Office Benefits and Structure

Change Management Office Benefits and Structure Change Management Office Benefits and Structure Author Melanie Franklin Director Agile Change Management Limited Contents Introduction 3 The Purpose of a Change Management Office 3 The Authority of a Change

More information

Middlesbrough Manager Competency Framework. Behaviours Business Skills Middlesbrough Manager

Middlesbrough Manager Competency Framework. Behaviours Business Skills Middlesbrough Manager Middlesbrough Manager Competency Framework + = Behaviours Business Skills Middlesbrough Manager Middlesbrough Manager Competency Framework Background Middlesbrough Council is going through significant

More information

Maturity Model. March 2006. Version 1.0. P2MM Version 1.0 The OGC logo is a Registered Trade Mark of the Office of Government Commerce

Maturity Model. March 2006. Version 1.0. P2MM Version 1.0 The OGC logo is a Registered Trade Mark of the Office of Government Commerce Maturity Model March 2006 Version 1.0 P2MM Version 1.0 The OGC logo is a Registered Trade Mark of the Office of Government Commerce This is a Value Added product which is outside the scope of the HMSO

More information

PORTFOLIO, PROGRAMME & PROJECT MANAGEMENT MATURITY MODEL (P3M3)

PORTFOLIO, PROGRAMME & PROJECT MANAGEMENT MATURITY MODEL (P3M3) PORTFOLIO, PROGRAMME & PROJECT MANAGEMENT MATURITY MODEL (P3M3) 1st February 2006 Version 1.0 1 P3M3 Version 1.0 The OGC logo is a Registered Trade Mark of the Office of Government Commerce This is a Value

More information

Confident in our Future, Risk Management Policy Statement and Strategy

Confident in our Future, Risk Management Policy Statement and Strategy Confident in our Future, Risk Management Policy Statement and Strategy Risk Management Policy Statement Introduction Risk management aims to maximise opportunities and minimise exposure to ensure the residents

More information

White Paper. PPP Governance

White Paper. PPP Governance PPP Governance The Governance of Projects, Programs and Portfolios (PPP) (sometimes called project governance for convenience) is the sub-set of corporate and organisational governance 1 focused on assisting

More information

Providing standards, methodologies and a set of PM tools. Promoting project management within the organisation

Providing standards, methodologies and a set of PM tools. Promoting project management within the organisation Strategic and governance services Consultancy and advisory services Advanced specialist Services SServuces Services Services Basic support services PMO: Project management office An organisational body

More information

Network Rail Infrastructure Projects Joint Relationship Management Plan

Network Rail Infrastructure Projects Joint Relationship Management Plan Network Rail Infrastructure Projects Joint Relationship Management Plan Project Title Project Number [ ] [ ] Revision: Date: Description: Author [ ] Approved on behalf of Network Rail Approved on behalf

More information

JOB DESCRIPTION. To provide Portfolio, Programme and Project support services as assigned.

JOB DESCRIPTION. To provide Portfolio, Programme and Project support services as assigned. Job Title: Department: Reports to: Direct Reports: Indirect Reports: Relates to: Portfolio, Programme & Project Support Officer (PSO) Projects Department Head of Projects None Those assigned to your projects

More information

UoD IT Job Description

UoD IT Job Description UoD IT Job Description Role: Projects Portfolio Manager HERA Grade: 8 Responsible to: Director of IT Accountable for: Day to day leadership of team members and assigned workload Key Relationships: Management

More information

NES/11/111. Dorothy Wright Director HR & OD Christine McCole, Depute Director HR Tom Power, OD Business Partner (Leadership & Performance Management)

NES/11/111. Dorothy Wright Director HR & OD Christine McCole, Depute Director HR Tom Power, OD Business Partner (Leadership & Performance Management) NES Item 8d December 2011 NES/11/111 (Enclosure) NHS Education for Scotland Board Paper Summary 1. Title of Paper People & Organisational Development Strategy 2. Author(s) of Paper Dorothy Wright Director

More information

Managing ICT contracts in central government. An update

Managing ICT contracts in central government. An update Managing ICT contracts in central government An update Prepared by Audit Scotland June 2015 Auditor General for Scotland The Auditor General s role is to: appoint auditors to Scotland s central government

More information

PRINCE2 and governance

PRINCE2 and governance PRINCE2 and governance Andy Murray, lead author of PRINCE2 (2009) and Director of Outperform UK Ltd White Paper November 2011 2 PRINCE2 and governance Contents 1 Purpose of this white paper 3 2 What is

More information

People & Organisational Development Strategy

People & Organisational Development Strategy 2013-2018 People & Organisational Development Strategy Delivering excellent research Delivering an excellent student experience Enhancing global reach and reputation 1. Introduction Glasgow 2020: A global

More information

ROLE PROFILE. Performance Consultant (Fixed Term) Assistant Director for Human Resources

ROLE PROFILE. Performance Consultant (Fixed Term) Assistant Director for Human Resources ROLE PROFILE Job Title Reports to Service area No. of staff responsible for Budget responsibility ( ) Performance Consultant (Fixed Term) Assistant Director for Human Resources HR 0 None Purpose of Job

More information

JOB PROFILE (GREEN BOOK)

JOB PROFILE (GREEN BOOK) JOB PROFLE (GREEN BOOK) Job Title: Corporate Programme Officer Post Reference Permanent/ Temporary Fixed-term 1 year Grade/Role: 5 Hours: 37 Reports to: Head of Corporate Services Directorate/ department:

More information

MoP Glossary of Terms - English

MoP Glossary of Terms - English English Term aggregated risk English Definition The overall level of risk to the portfolio when all the risks are viewed as a totality rather than individually. This could include the outputs of particular

More information

ESKITP7145.01 Manage IT service delivery performance metrics

ESKITP7145.01 Manage IT service delivery performance metrics Overview This sub-discipline covers the competencies required to manage the monitoring, analysis and communication of IT service delivery performance metrics. Monitoring service level performance is a

More information

Intelligent Customer Function (ICF)

Intelligent Customer Function (ICF) CAPABILITY AUDIT FOR HEIs Higher Education Institutions (HEIs) should organically develop their own to successfully manage the process of strategic sourcing. The capability audit provides an assessment

More information

1.1. To be the lead senior officer responsible for ICT strategy and delivery across the three boroughs.

1.1. To be the lead senior officer responsible for ICT strategy and delivery across the three boroughs. Job description Designation: Tri-borough Chief Information Officer Post Number: Department: Finance and Corporate Services Responsible to: H&F SRO, Exec director of Finance and Corporate Governance Employees

More information

JOB AND PERSON SPECIFICATION. It has an annual budget of approximately 50 million and currently a staff of approximately 300.

JOB AND PERSON SPECIFICATION. It has an annual budget of approximately 50 million and currently a staff of approximately 300. JOB AND PERSON SPECIFICATION Job Title: Division Grade: HR Adviser - HR Operations Section G Reports To: Head of HR Operations General Information The Commonwealth Secretariat is the principal intergovernmental

More information

JUNE 2010. Assurance for high risk projects

JUNE 2010. Assurance for high risk projects JUNE 2010 Assurance for high risk projects Our vision is to help the nation spend wisely. We apply our unique perspective of public audit to help Parliament and government drive lasting improvement in

More information

APPENDIX C. Internal Audit Report South Holland District Council Project Management

APPENDIX C. Internal Audit Report South Holland District Council Project Management APPENDIX C Internal Audit Report South Holland District Council Project Management Date: 20th December 2012 Contents Introduction and Scope 1 Executive Summary Assurance Opinion Key Messages 2 3 Management

More information

Transport for London. Projects and Planning Panel

Transport for London. Projects and Planning Panel Agenda Item 4 Transport for London Projects and Planning Panel Subject: TfL Pathway Date: 8 May 2013 1 Purpose 1.1 At its meeting of 8 January 2013 the Panel asked for further information about Pathway,

More information

Lessons learned from creating a change management framework

Lessons learned from creating a change management framework Lessons learned from creating a change management framework Author Melanie Franklin Director Agile Change Management Limited Contents Introduction 3 What is a Change Management Framework? 3 Why is it called

More information

CPS SECURITY & INFORMATION RISK MANAGEMENT POLICY CPS SECURITY & INFORMATION RISK MANAGEMENT POLICY 2013-2014

CPS SECURITY & INFORMATION RISK MANAGEMENT POLICY CPS SECURITY & INFORMATION RISK MANAGEMENT POLICY 2013-2014 CPS SECURITY & INFORMATION RISK MANAGEMENT POLICY 2013-2014 1 Version 1.0 CONTENTS Security Risks 3 Information Assurance Risk 3 Spreading Best Practice 3 Reporting Risks Upwards 4 Typical Risk Escalation

More information

Job description - Business Improvement Manager

Job description - Business Improvement Manager Job description - Business Improvement Manager Main Purpose of job The post has lead responsibility for optimising operational performance within the Operations directorate, and across the Society for

More information

Programme Governance and Management Plan Version 2

Programme Governance and Management Plan Version 2 PROCESS FOR CHANGE - Detailed Design Programme Governance and Management Plan Version 2 1 INTRODUCTION In October 2008, the Council approved the selection of seven opportunity themes to take forward from

More information

Benefits. MIRACLE Benefits. I have no idea! What is going on in here? Konferencja "Bezpieczny Projekt" WARSZAWA 11 maja 2010 r.

Benefits. MIRACLE Benefits. I have no idea! What is going on in here? Konferencja Bezpieczny Projekt WARSZAWA 11 maja 2010 r. Programme Plan MIRACLE Benefits Benefits What is going on in here? I have no idea! 1 W A R S Z A W A R Z E S Z Ó W W R O C Ł A W 1 Fitting the pieces together How the APMG Product Set helps you manage

More information

Director: Improvement and Corporate Services. Improvement & Corporate Services

Director: Improvement and Corporate Services. Improvement & Corporate Services HAY Job description JOB TITLE: DIRECTORATE: GRADE: Director: Improvement and Corporate Services Improvement & Corporate Services Director DATE PREPARED: March 2013 REPORTS TO: Chief Executive JOB PURPOSE:

More information

MARCH 2012. Strategic Risk Policy Update March 2012 v1.10.doc

MARCH 2012. Strategic Risk Policy Update March 2012 v1.10.doc MARCH 2012 Version 1.10 Strategic Risk Policy Update March 2012 v1.10.doc Document History Current Version Document Name Risk Management Policy Statement and Strategic Framework Last Updated By Alan Till

More information

Delivering e-procurement Local e-gov National e-procurement Project Overarching Guide to e-procurement for LEAs

Delivering e-procurement Local e-gov National e-procurement Project Overarching Guide to e-procurement for LEAs 1. Introduction Background The National e-procurement Project (NePP) and Centre for Procurement Performance (CPP) are working to support and enable schools to meet their e- Government targets and to gain

More information

Information Sharing Lessons Learned from Gateway Reviews: Gate 5 Benefits Realisation Review

Information Sharing Lessons Learned from Gateway Reviews: Gate 5 Benefits Realisation Review Information Sharing Lessons Learned from Gateway Reviews: Gate 5 Benefits Realisation Review October 2013 The purpose of this document is to share lessons learned to support agencies to better identify

More information

Business Solutions Manager Self and contribution to Team. Information Services

Business Solutions Manager Self and contribution to Team. Information Services POSITION DESCRIPTION Position Title: Responsible To: Responsible For Agile Test Analyst Business Solutions Manager Self and contribution to Team Position Purpose: The Agile Test Analyst is responsible

More information

Knowledge Management Strategy 2011-2014. Version 0.8

Knowledge Management Strategy 2011-2014. Version 0.8 Knowledge Management Strategy 2011-2014 Version 0.8 25 October 2011 1 1. Introduction 1.1 What is knowledge management? Knowledge management is creating, capturing, sharing and using the skills and experience

More information

POSITION DESCRIPTION. Role Purpose. Key Challenges. Key Result Areas

POSITION DESCRIPTION. Role Purpose. Key Challenges. Key Result Areas POSITION DESCRIPTION Position Title Manager, Technical Services Support Position Number Reports to Manager Technology Services Functional Auth HRM Auth Region IT Services Centre Head Office Date Feb 2011

More information

NSW Government ICT Benefits Realisation and Project Management Guidance

NSW Government ICT Benefits Realisation and Project Management Guidance NSW Government ICT Benefits Realisation and Project Management Guidance November 2014 CONTENTS 1. Introduction 1 2. Document purpose 1 3. Benefits realisation 1 4. Project management 4 5. Document control

More information

Selecting a project management methodology

Selecting a project management methodology VICTORIAN GOVERNMENT CIO COUNCIL Project Management Selecting a project management methodology Guideline This guideline provides advice for selecting and tailoring a project management methodology. Keywords:

More information

City and County of Swansea. Human Resources & Workforce Strategy 2013-2017. Ambition is Critical 1

City and County of Swansea. Human Resources & Workforce Strategy 2013-2017. Ambition is Critical 1 City and County of Swansea Human Resources & Workforce Strategy 2013-2017 Ambition is Critical 1 Delivering quality services for a safer, greener, smarter, fairer, healthier, richer Swansea Executive Summary

More information

P3M3 Portfolio Management Self-Assessment

P3M3 Portfolio Management Self-Assessment Procurement Programmes & Projects P3M3 v2.1 Self-Assessment Instructions and Questionnaire P3M3 Portfolio Management Self-Assessment P3M3 is a registered trade mark of AXELOS Limited Contents Introduction

More information

Gateway review guidebook. for project owners and review teams

Gateway review guidebook. for project owners and review teams Gateway review guidebook for project owners and review teams The State of Queensland (Queensland Treasury and Trade) 2013. First published by the Queensland Government, Department of Infrastructure and

More information

Andrew Bratt, Assistant Director Human Resources, Resources and Quality Assurance abratt@gmc-uk.org, 0161 923 6215

Andrew Bratt, Assistant Director Human Resources, Resources and Quality Assurance abratt@gmc-uk.org, 0161 923 6215 Agenda item: 21 Report title: Report by: Action: People Strategy- Leadership and Management Andrew Bratt, Assistant Director Human Resources, Resources and Quality Assurance abratt@gmc-uk.org, 0161 923

More information

Purpose: Content: Definition: Benefits: outputs outcomes benefits Business Case dis-benefit Key Responsibilities: Approach: Executive Developed

Purpose: Content: Definition: Benefits: outputs outcomes benefits Business Case dis-benefit Key Responsibilities: Approach: Executive Developed Key Learning Points The Swirl Logo is a trade mark of the AXELOS Limited. Is used by the Project Board throughout the project to verify its continued viability:- Is the investment in this project still

More information

Management and Leadership. Level 5 NVQ Diploma in Management and Leadership (QCF)

Management and Leadership. Level 5 NVQ Diploma in Management and Leadership (QCF) Management and Leadership Level 5 NVQ Diploma in Management and Leadership (QCF) 2014 Skills CFA Level 5 NVQ Diploma in Management and Leadership (QCF) Page 1 Level 5 NVQ Diploma in Management and Leadership

More information

THE KEY BENEFITS OF PRINCE2

THE KEY BENEFITS OF PRINCE2 THE OF PRINCE2 For the organization and the professional AXELOS.com The world s most practiced project management methodology THE ITEMS BELOW ARE ALIGNED TO ALL 6 PRINCE2, WITH THE MOST DIRECT CONNECTIONS

More information

Programme Manager Relationship Management System

Programme Manager Relationship Management System Programme Manager Relationship Management System Russam Ref 4573 Job Profile This document is a generic description for the role. Any specific requirements in the published advert should also be taken

More information

Using PRINCE2 and MSP Together

Using PRINCE2 and MSP Together Using PRINCE2 and MSP Together Andy Murray, Director, Outperform White Paper October 2010 2 Using PRINCE2 and MSP Together Contents 1 Purpose of this White Paper 3 2 Project and programme management context

More information

Impact and Knowledge Exchange Strategy 2013-2016 Delivering Impact from Research Excellence

Impact and Knowledge Exchange Strategy 2013-2016 Delivering Impact from Research Excellence 1. Background Impact and Knowledge Exchange Strategy 2013-2016 Delivering Impact from Research Excellence Impact is the demonstrable contribution that excellent research (basic, user-inspired and applied)

More information

DIRECTOR OF PEOPLE & ORGINAISATIONAL DEVELOPMENT NICK MERNOCK EMPLOYEE SUCCESSION PLANNING STRATEGY

DIRECTOR OF PEOPLE & ORGINAISATIONAL DEVELOPMENT NICK MERNOCK EMPLOYEE SUCCESSION PLANNING STRATEGY AGENDA ITEM: REPORT TO: POLICY & FINANCE COMMITTEE DATE: 19 TH OCTOBER, 2006 REPORT NO. REPORTING OFFICER: CONTACT OFFICER: OFFICERS CONSULTED: SUBJECT: CFO/193/06 CHIEF FIRE OFFICER DIRECTOR OF PEOPLE

More information

CHANGE MANAGEMENT PLAN

CHANGE MANAGEMENT PLAN Appendix 10 Blaby District Council Housing Stock Transfer CHANGE MANAGEMENT PLAN 1 Change Management Plan Introduction As part of the decision making process to pursue transfer, the Blaby District Council

More information

General Notes Time allowed 1 hour. Answer all 60 multiple choice questions Use the proforma answer sheet provided.

General Notes Time allowed 1 hour. Answer all 60 multiple choice questions Use the proforma answer sheet provided. Introductory Certificate The APM Project Fundamentals Qualification. Examination paper Candidate Number Date Location Examination Paper Sample Paper v1.4 General Notes Time allowed 1 hour. Answer all 60

More information

PROJECT MANAGEMENT FRAMEWORK

PROJECT MANAGEMENT FRAMEWORK PROJECT MANAGEMENT FRAMEWORK DOCUMENT INFORMATION DOCUMENT TYPE: DOCUMENT STATUS: POLICY OWNER POSITION: INTERNAL COMMITTEE ENDORSEMENT: APPROVED BY: Strategic document Approved Executive Assistant to

More information

Introduction. Chris Harrop, Chief Executive

Introduction. Chris Harrop, Chief Executive Page 1 of 10 Introduction I am proud to be the Chief Executive of the Walton Centre NHS Foundation Trust with its reputation for excellent patient care, quality services and sustainability. Over the last

More information

Time to Professionalise Project Governance? Rankins G J BSc MApplSci MBA CPPD Goal Professional Services Pty Ltd

Time to Professionalise Project Governance? Rankins G J BSc MApplSci MBA CPPD Goal Professional Services Pty Ltd Time to Professionalise Project Governance? Rankins G J BSc MApplSci MBA CPPD Goal Professional Services Pty Ltd This paper was presented at the 7th Annual Project Management Australia Conference (PMOZ

More information

Procurement Programmes & Projects P3M3 v2.1 Self-Assessment Instructions and Questionnaire. P3M3 Project Management Self-Assessment

Procurement Programmes & Projects P3M3 v2.1 Self-Assessment Instructions and Questionnaire. P3M3 Project Management Self-Assessment Procurement Programmes & Projects P3M3 v2.1 Self-Assessment Instructions and Questionnaire P3M3 Project Management Self-Assessment Contents Introduction 3 User Guidance 4 P3M3 Self-Assessment Questionnaire

More information

Performance Detailed Report. May 2008. Review of Performance Management. Norwich City Council. Audit 2007/08

Performance Detailed Report. May 2008. Review of Performance Management. Norwich City Council. Audit 2007/08 Performance Detailed Report May 2008 Review of Performance Management Audit 2007/08 External audit is an essential element in the process of accountability for public money and makes an important contribution

More information

Housing Association Regulatory Assessment

Housing Association Regulatory Assessment Welsh Government Housing Directorate - Regulation Housing Association Regulatory Assessment Melin Homes Limited Registration number: L110 Date of publication: 20 December 2013 Welsh Government Housing

More information

Informatics: The future. An organisational summary

Informatics: The future. An organisational summary Informatics: The future An organisational summary DH INFORMATION READER BOX Policy HR/Workforce Management Planning/Performance Clinical Document Purpose Commissioner Development Provider Development Improvement

More information

National Approach to Information Assurance 2014-2017

National Approach to Information Assurance 2014-2017 Document Name File Name National Approach to Information Assurance 2014-2017 National Approach to Information Assurance v1.doc Author David Critchley, Dave Jamieson Authorisation PIAB and IMBA Signed version

More information

MAKING YOUR ORGANISATION S INFORMATION ACCESSIBLE FOR ALL IMPLEMENTING THE GUIDELINES FOR ACCESSIBLE INFORMATION

MAKING YOUR ORGANISATION S INFORMATION ACCESSIBLE FOR ALL IMPLEMENTING THE GUIDELINES FOR ACCESSIBLE INFORMATION MAKING YOUR ORGANISATION S INFORMATION ACCESSIBLE FOR ALL IMPLEMENTING THE GUIDELINES FOR ACCESSIBLE INFORMATION project has been funded with support from the European Union. publication reflects the views

More information

Fundamental Performance Review Partnership Working 4

Fundamental Performance Review Partnership Working 4 Report title Agenda item Fundamental Performance Review Partnership Working 4 Meeting Performance Management & Community Safety Panel 19 May 2008 Date Report by Document Number Director of Corporate Services

More information

Customer Service Cluster Manager

Customer Service Cluster Manager London Borough of Camden JOB PROFILE Cluster POSITION TITLE: cluster manager DIRECTORATE: Culture and Environment DIVISION: Culture and customer service JOB FAMILY: SERVICE: service GRADE: PO6 REPORTS

More information

Efficiency & Effectiveness Program Five Year Program Plan Appendices June 2014 Version 2.0

Efficiency & Effectiveness Program Five Year Program Plan Appendices June 2014 Version 2.0 Efficiency & Effectiveness Program Five Year Program Plan 2014-2019 Appendices June 2014 Version 2.0 1 Contents APPENDIX 1 Efficiency and Effectiveness Program Delivery Model... 3 APPENDIX 2 Program Resourcing...

More information

Human Resources and Organisational Development. Job No. (Office Use)

Human Resources and Organisational Development. Job No. (Office Use) ROLE PROFILE Human Resources and Organisational Development Role Profile Job Title Head of Business and Technical Architecture Job No. (Office Use) F27 Grade (Office Use) Directorate Transformation and

More information

The Transport Business Cases

The Transport Business Cases Do not remove this if sending to pagerunnerr Page Title The Transport Business Cases January 2013 1 Contents Introduction... 3 1. The Transport Business Case... 4 Phase One preparing the Strategic Business

More information

Change and project management

Change and project management Change and project management www.first.com What gets measured, gets d! -Change leader Change and Project Management Change and project management Prince 2, PMI and PCI When projects fail in an organisation,

More information

Having a Project Support Office

Having a Project Support Office www.ronrosenhead.co.uk Having a Project Support Office The case for a (or programme) support office Produced by Ron Rosenhead Telephone: 020 8446 7766 www.ronrosenhead.co.uk www.agency.co.uk The case for

More information

Risk Management Plan 2012-2015

Risk Management Plan 2012-2015 Risk Management Plan 2012-2015 This controlled document shall not be copied in part or whole without the express permission of the author or the author s representative. Revision Date Previous Revision

More information

Position Description (PD)

Position Description (PD) HRPF: PositionDescription-JOB:REW Learning Resources Information Technology Services Project Management Office Position Description (PD) Manager, Project Management Office Continuing Position Number: 16664

More information

POSITION INFORMATION DOCUMENT

POSITION INFORMATION DOCUMENT POSITION INFORMATION DOCUMENT Position Title: Scheduling Officer, ICT Programs Classification Code: ASO6 Division: ICT Services Directorate: ICT Program Services Type of Appointment: Branch: ICT Program

More information

Project and Programme Management Capability Improvement Study

Project and Programme Management Capability Improvement Study irresistible creativity to inspire and change the world Project and Programme Management Capability Improvement Study Independent Reporter (Part C) Mandate CN/025 Office of Rail Regulation and Network

More information

JOB DESCRIPTION Facilities Manager Soft Services. RESPONSIBLE FOR: Team Leaders and Contract Support staff

JOB DESCRIPTION Facilities Manager Soft Services. RESPONSIBLE FOR: Team Leaders and Contract Support staff JOB DESCRIPTION Facilities Manager Soft Services DIRECTORATE: Merlin Works DEPARTMENT: Facilities Management SALARY: 44,880 RESPONSIBLE TO: Head of Facilities Management RESPONSIBLE FOR: Team Leaders and

More information

University of Edinburgh Knowledge Strategy Committee. 8 June 2012. Use of the Project Governance Toolkit for Shared Academic Timetabling

University of Edinburgh Knowledge Strategy Committee. 8 June 2012. Use of the Project Governance Toolkit for Shared Academic Timetabling University of Edinburgh Knowledge Strategy Committee 8 June 2012 Use of the Project Governance Toolkit for Shared Academic Timetabling Brief description of the paper Shared Academic Timetabling has been

More information

AGENDA ITEM 5 AYRSHIRE SHARED SERVICE JOINT COMMITTEE 1 MAY 2015 AYRSHIRE ROADS ALLIANCE CUSTOMER SERVICE STRATEGY

AGENDA ITEM 5 AYRSHIRE SHARED SERVICE JOINT COMMITTEE 1 MAY 2015 AYRSHIRE ROADS ALLIANCE CUSTOMER SERVICE STRATEGY AYRSHIRE SHARED SERVICE JOINT COMMITTEE 1 MAY 2015 AYRSHIRE ROADS ALLIANCE CUSTOMER SERVICE STRATEGY Report by the Head of Roads Ayrshire Roads Alliance PURPOSE OF REPORT 1. The purpose of this report

More information

Derbyshire County Council Performance and Improvement Framework. January 2012

Derbyshire County Council Performance and Improvement Framework. January 2012 Derbyshire County Council Performance and Improvement Framework January 2012 Contents 1. Introduction 3 2. About the framework 4 3. Planning 7 5. Monitoring Performance 8 6. Challenge and Review 11 7.

More information

MANAGING DIGITAL CONTINUITY

MANAGING DIGITAL CONTINUITY MANAGING DIGITAL CONTINUITY Project Name Digital Continuity Project DRAFT FOR CONSULTATION Date: November 2009 Page 1 of 56 Contents Introduction... 4 What is this Guidance about?... 4 Who is this guidance

More information

Information Sharing Lessons Learned from Gateway Reviews: Gate 3 Investment Decision Review

Information Sharing Lessons Learned from Gateway Reviews: Gate 3 Investment Decision Review Information Sharing Lessons Learned from Gateway Reviews: Gate 3 Investment Decision Review October 2013 The purpose of this document is to share lessons learned to support agencies to better identify

More information

HOME OFFICE CONTINUOUS IMPROVEMENT STRATEGY

HOME OFFICE CONTINUOUS IMPROVEMENT STRATEGY HOME OFFICE CONTINUOUS IMPROVEMENT STRATEGY OBJECTIVES 1. The overall purpose of the Department s Continuous Improvement Strategy is to ensure the Home Office delivers better for less, securing maximum

More information

Role Context & Purpose

Role Context & Purpose Group Manager Children s Social Care Services Role Profile: Grade: Accountable to: Accountable for: Senior Manager Hay B Service Leader 3-6 direct line reports, plus circa 48 staff that these direct reports

More information

January 2016. Communications Manager: Information for Candidates

January 2016. Communications Manager: Information for Candidates January 2016 Communications Manager: Information for Candidates Thank you for expressing interest in the role of Communications Manager. We have compiled this information pack to tell you more about The

More information

Senior Project Manager (Web Content Management)

Senior Project Manager (Web Content Management) Senior Project Manager (Web Content Management) IT Services Portfolio & Project Management Office Salary Grade 8-40,046 to 45,053 per annum Fixed term contract for 2 years (** see below for contract information)

More information

Benefits of conducting a Project Management Maturity Assessment with PM Academy:

Benefits of conducting a Project Management Maturity Assessment with PM Academy: PROJECT MANAGEMENT MATURITY ASSESSMENT At PM Academy we believe that assessing the maturity of your project is the first step in improving the infrastructure surrounding project management in your organisation.

More information

Customers and Corporate Services Directorate (Corporate Support) Plan 2015-16

Customers and Corporate Services Directorate (Corporate Support) Plan 2015-16 Appendix 2 Action Plan Due Date Status Customers and Corporate Services Directorate (Corporate Support) Plan 2015-16 CS1027 ICT Improvement Programme 31 January 2016 Objectives: CORPORATE SERVICES: ICT

More information

1 Context. 2 Background. CiCS Development Portfolio Definition 2015 Background

1 Context. 2 Background. CiCS Development Portfolio Definition 2015 Background CiCS Development Portfolio Definition 2015 Background 1 Context CiCS Vision We will be an innovative and influential department, respected by the University and recognised as a leader in the sector, delivering

More information

INVESTORS IN PEOPLE REVIEW REPORT

INVESTORS IN PEOPLE REVIEW REPORT INVESTORS IN PEOPLE REVIEW REPORT Lower Farm Primary School Page: 1 of 13 CONTENTS Key Information 3 Assessor Decision 3 Milestone Dates 3 Introduction 4 Assessment Objectives 4 Feedback Against the Assessment

More information

The Risk Management strategy sets out the framework that the Council has established.

The Risk Management strategy sets out the framework that the Council has established. Derbyshire County Council Management Policy Statement The Authority adopts a proactive approach to Management to achieve Best Value and continuous improvement and is committed to the effective management

More information

Appendix A: ICT and Information Management Strategy

Appendix A: ICT and Information Management Strategy Appendix A: ICT and Information Management 2014 2019 Head of Information and Business Change Sarah Caulkin October 2014 1 Version Control: Date Version Author Comments 04/08/14 0.1 Jo Harley First draft

More information

(Financial Accounting Team)

(Financial Accounting Team) Job Title: Accounting Technician (Financial Accounting Team) Job Grade: Band 3 Band 4 Directorate: Finance Job Reference Number: P02279 The Role As part of the Financial Compliance Team, you will report

More information

REPORT 4 FOR DECISION. This report will be considered in public

REPORT 4 FOR DECISION. This report will be considered in public REPORT 4 Subject: Safety Readiness for the Summer 2013 Events Programme Agenda item: Public Item 7 Report No: 4 Meeting date: 28 May 2013 Report to: Board Report of: Mark Camley, Interim Executive Director

More information

Human Resources, Health & Safety and Equalities Panel 13 November 2008

Human Resources, Health & Safety and Equalities Panel 13 November 2008 Report title e-hr Strategy Agenda item 10 Meeting Human Resources, Health & Safety and Equalities Panel 13 November 2008 Date Report by Document Number Head of Human Resources HRE 296 Summary This paper

More information

Audit Scotland Annual Report on Disability Equality A progress report for Dec 2007 to Nov 2008

Audit Scotland Annual Report on Disability Equality A progress report for Dec 2007 to Nov 2008 Audit Scotland Annual Report on Disability Equality A progress report for Dec 2007 to Nov 2008 Page 1 of 13 Introduction Background 1. Audit Scotland provides services to the Auditor General and the Accounts

More information

Directing Change A guide to governance of project management

Directing Change A guide to governance of project management Contents Foreword 1 1. Purpose 2 2. Introduction 3 3. Principles 5 4. Core components 7 5. Postscript 13 Appendix 1 14 Appendix 2 16 Directing Change A guide to governance of project management Foreword

More information

Project Management Toolkit Version: 1.0 Last Updated: 23rd November- Formally agreed by the Transformation Programme Sub- Committee

Project Management Toolkit Version: 1.0 Last Updated: 23rd November- Formally agreed by the Transformation Programme Sub- Committee Management Toolkit Version: 1.0 Last Updated: 23rd November- Formally agreed by the Transformation Programme Sub- Committee Page 1 2 Contents 1. Introduction... 3 1.1 Definition of a... 3 1.2 Why have

More information

Job No. (Office Use) Directorate Corporate Services Department Programme Management Office Reports to (Job Title) If No state reason

Job No. (Office Use) Directorate Corporate Services Department Programme Management Office Reports to (Job Title) If No state reason ROLE PROFILE Transformation Programmes Manager Role Profile Job Title Transformation Programme Manager Job No. (Office Use) C6074 Grade (Office Use) Directorate Corporate Services Department Programme

More information

As a result, HR is a key player in delivering City s new Vision under the leadership of the Vice-Chancellor, Professor Paul Curran.

As a result, HR is a key player in delivering City s new Vision under the leadership of the Vice-Chancellor, Professor Paul Curran. For UHR website An HR Metamorphosis at City University London Summary Since 2009, a challenging, rolling programme of parallel and integrated HR initiatives has transformed the efficiency and effectiveness

More information

Project Assessment Framework Establish service capability

Project Assessment Framework Establish service capability Project Assessment Framework Establish service capability July 2015 Component of the Project Assessment Framework (PAF) This document forms part of the Project Assessment Framework, as outlined below.

More information

BPU Head of Service Position Statement

BPU Head of Service Position Statement BPU Head of Service Position Statement The aim of this paper is to provide a position statement regarding the identified BPU functions within the Annual Council Reporting Framework. Workforce It is considered

More information

Shropshire Highways Draft Asset Management and Communications Strategy and Implications of Department for Transport Incentivised funding

Shropshire Highways Draft Asset Management and Communications Strategy and Implications of Department for Transport Incentivised funding Committee and Date Cabinet 14 th October 2015 Shropshire Highways Draft Asset Management and Communications Strategy and Implications of Department for Transport Incentivised funding Responsible Officer

More information

Benefits realisation. Gate

Benefits realisation. Gate Benefits realisation Gate 5 The State of Queensland (Queensland Treasury and Trade) 2013. First published by the Queensland Government, Department of Infrastructure and Planning, January 2010. The Queensland

More information