Slab Track on the Dutch High Speed Line: Decision making criteria
|
|
- Clement Hensley
- 8 years ago
- Views:
Transcription
1 Slab Track on the Dutch High Speed Line: Decision making criteria Theo Winter (BAM Rail) Project Director Rheda 2000 vof Bilbao, January
2 Contents of the presentation 1. HSL Zuid Project Description 2. Tendering Phase Strategic Decisions 3. Design, Build, Finance & Maintain (DBFM) Contract 4. Scope of the HSL Zuid (Slabtrack) Project 5. Design & Engineering Specifics of the Dutch Slabtrack 6. Planning, Construction & Logistics Strategies 7. Testing & Commissioning 8. Achieved Results 2
3 3
4 Political choices in the Netherlands in Construction of a new HSL Zuid, as part of the TEN, along a separate line 2. Agreement with Belgium: first operation in 2005! 3. The objective to replace short distance air travel by high speed trains 4. The belief that PPP will bring added value: private enterprises are more able to deliver a train system of exceptional quality in time 4
5 Project description Hoofddorp RAS Rotterdam West RAS Rotterdam Lombardijen Noordelijk Holland Shield-driven Tunnel Groene Hart Zuid Holland Midden Barendrecht Zuid Holland Zuid Breda RAS Brabant Noord Brabant Zuid 5
6 HSL Zuid: The general set-up of the project ProRail Traffic Control Client Belgium ProRail Inframgt. Dutch State NMBS Inspectie Verkeer en Waterstaat D&C 4000 mio DBFM (30 yrs) 105 mio/yr Concession (15 yrs) Municipalities 148 mio/yr Substructure 6 CONSORTIA Superstructure INFRASPEED Traffic HSA:NS/KLM (Air France) Interfaces Interfaces 6
7 Essential features Noordelijk Holland Largest PPP contract ever awarded by Dutch Government to a Private Party Hoofddorp RAS Shield-driven Tunnel Groene Hart Rotterdam West RAS Rotterdam Lombardijen Zuid Holland Midden Barendrecht Zuid Holland Zuid Breda RAS Brabant Noord Brabant Zuid 7
8 Essential features Hoofddorp RAS Rotterdam West RAS Rotterdam Lombardijen Noordelijk Holland Shield-driven Tunnel Groene Hart Zuid Holland Midden Barendrecht Zuid Holland Zuid Largest PPP contract ever awarded by Dutch Government to a Private Party Design, Build, Finance and Maintain the superstructure of the new 90 km high speed link between Amsterdam and Belgium border, concession term from 2001 to 2031 with a 5 year construction period and a 25 year availability period Breda RAS Brabant Noord Brabant Zuid 8
9 Essential features Hoofddorp RAS Rotterdam West RAS Rotterdam Lombardijen Breda RAS Noordelijk Holland Shield-driven Tunnel Groene Hart Zuid Holland Midden Barendrecht Zuid Holland Zuid Brabant Noord Brabant Zuid Largest PPP contract ever awarded by Dutch Government to a Private Party Design, Build, Finance and Maintain the superstructure of the new 90 km high speed link between Amsterdam and Belgium border, concession term from 2001 to 2031 with a 5 year construction period and a 25 year availability period 3.0 billion performance based revenue, covers investment cost, maintenance cost, cost of amortisation, taxes, insurances, cost of capital, profit and overhead. Initial Funding Requirement of 1.2 billion. Payments based on availability with a minimum of 99%. 9
10 Essential features Hoofddorp RAS Rotterdam West RAS Rotterdam Lombardijen Breda RAS Noordelijk Holland Shield-driven Tunnel Groene Hart Zuid Holland Midden Barendrecht Zuid Holland Zuid Brabant Noord Brabant Zuid Largest PPP contract ever awarded by Dutch Government to a Private Party Design, Build, Finance and Maintain the superstructure of the new 90 km high speed link between Amsterdam and Belgium border, concession term from 2001 to 2031 with a 5 year construction period and a 25 year availability period 3.0 billion performance based revenue, covers investment cost, maintenance cost, cost of amortisation, taxes, insurances, cost of capital, profit and overhead. Initial Funding Requirement of 1.2 billion. Payments based on availability with a minimum of 99%. Contract signed 1 st June 2001 Financial Close 30 th October
11 11
12 The Infraprovider tender process Prequalification procedure in Spring 1999 resulted in 4 consortia: 1. Fastrail : Alstom-Strukton- Volker Wessels Stevin 2. Infraspeed : Royal BAM-Siemens-Fluor- Innisfree-HSBC 3. Zuidrailgroep : Bechtel-Amey-Øve Arup- DuraVermeer-Hyder 4. Speedrail : Balfour Beatty-Adtranz-Ballast Nedam a.o. (withdrew Dec. 1999) 12
13 Early strategic choices; Slabtrack & Rheda In 1999 several options were investigated by Infraspeed with respect to the choice of the track system: Ballasted system (note limited height available) Embedded systems a.o. Balfour Beatty Direct fastening systems a.o. Edilon Slabtrack Systems a.o. Bögl (prefab), Balfour Beatty LVT (Channel Tunnel system), Zublin and Rheda 2000 Conclusion: Rheda 2000 is the most reliable (RAMS), flexible (technically & construction) and bankable (LCC) track system! 13
14 Acceleration of the tender process Final offer combined with a signed up banking financing: FINAL TECHNOLOGY FINAL PRICE TECHNICAL DUE DILIGENCE FINANCIAL DUE DILIGENCE FINAL STRUCTURE FINAL BANKING CONSORTIUM LEGAL DUE DILIGENCE CONTRACTUAL DUE DILIGENCE BAFO OFFER 14
15 15
16 Cashflow during development period Shareholders Fluor Siemens BAM Innisfree HSBC Equity Client the State RIA INFRASPEED bv Loans Banks ING Rabobank KBC KfW Dexia Hypovereinsbank Lump sum EIB EPC Consortium Fluor Siemens BAM CoA Mid 2006 IMC bv Integrated Maintenance Company Development period : to mid
17 Cashflow during availibilty period Shareholders Fluor Siemens BAM Innisfree HSBC 105/yr Dividend Client the State INFRASPEED bv Interest & repayment Banks ING Rabobank KBC KfW Dexia Hypovereinsbank EIB EPC Consortium Fluor Siemens BAM CoA Mid 2006 Maintenance fee IMC bv Integrated Maintenance Company During the Availibility period :
18 DBFM: specific for Infraspeed EPC Consortium Multiple Clients to take into account Design responsibility solely with EPC Compliant with Requirements (as per RIA) System Engineering CENELEC En50126 Verification & Validation (V&V) method Technical Specification of Interoperability (TSI) RAMS issues effecting Life Cycle Costing (LCC) New Technology versus Proven Systems 18
19 IFS Maintenance acceptance Lenders acceptance via ext. assessment IFS internal RAMS Demonstration Requirements Compliance (Matrix) external various apportioned req ments Certificate of Availability (by HABO) HS 7: Safety Case for construction & operation phase via ext. Assessment FS 7: conform EU guideline 96/48 Interoperable via Notified Body 19
20 Development Period: Clients & Influential Parties 2) HABO NOBO ISA INFRASPEED BV 1) TA & Banks EPC Consortium CoA End ) IMBV 20
21 System Engineering Approach Infraspeed HSL Assets Systems Assets Civil Assets Track & Noise BAM (43%) Systems Siemens (46%) Program Management Fluor (11%) Track Traction & Power Distribution Noise & Fencing Signalling Buildings & Miscellaneous Communications System breakdown structure Ancillary Equipment 21
22 V model EN Concept System Definition Risk Analysis System Requirements HSL-Zuid responsibility Substructure TOC Infraspeed Maintenance System Validation Operation & Maintenance System acceptance Renewal Performance Monitoring Apportionment of Requirements INFRASPEED EPC Subsystem Validation Design Construction Static tests System integration Dynamic testing Production Development Period 22
23 Requirements & Validation Client Requirements System Requirements Maintenance Requirements Laws and Standards (including TSI) XRCT External Certification SACE Study Analysis Calculations & Engineering PRST Pre Site Test (= FAT) OSIN On Site Inspection OSTC On Site Testing & Commissioning 23
24 Life Cycle Costs HABO ProRail EPC Consortium Fluor Siemens BAM ISA NOBO TA IMC bv Integrated Maintenance Company 24
25 Many new technologies introduced! ERTMS; balises in the track 25 kv OCS Substation GSM-R mast Man Machine Interface Rheda 2000 NL 25
26 DBFM is the driving factor to innovations! ERTMS-communication Perfect track geometry All systems work together 26
27 27
28 Alignment of HSL-Zuid Sub Structure as taken from Civil Assets Provider 28
29 Alignment of HSL-Zuid Sub Structure as taken from Civil Assets Provider Slab- and Ballasted Track 29
30 Alignment of HSL-Zuid Sub Structure as taken from Civil Assets Provider Slab- and Ballasted Track Noise Attenuation Systems 30
31 Alignment of HSL-Zuid Sub Structure as taken from Civil Assets Provider Slab- and Ballasted Track Noise Attenuation Systems Traction Power Distribution Signalling systems Communication systems Ancillary Equipment 31
32 EPC Consortium Infraspeed BV EPC Consortium Maintenance company Track & Noise (TRK) BAM (43%) Systems (SYS) Siemens (46%) Program Management (PMG) Fluor (11%) Track (TRA) Noise & Fencing (NFE) Buildings & Miscellaneous (BMI) Rheda Track Cat. A Rheda Track Cat. B Joint Venture BAM Civiel & BAM Rail & Pfleiderer Rheda Track Cat. C Rheda Switches Responsible for Engineering, Procurement and Construction of the slab track system for the HSL ZUID Ballast 300 Ballast 160 Ballast 40 Work Breakdown Structure 32
33 Facts Hoofddorp Legend Km E Normal direction of travel Enter / Exit point Mandatory special trackwork B40 A B K Special Trackwork descriptor B40 Ballast 40 Maintenance yard Ballast 160 Track B300 Ballast 300 Track (..,..) Alignment revision and source Breda H Rotterdam D F K B300 Belgium B40 S J L G 33
34 Rheda 2000 vof Subcontractor of BAM HSL Infraprovider vof (BHI) Back to Back contract with BHI 162 km single track (300 km/h) 4 switch complexes (15 switches 1:34,7) 1 high speed turnout (1:39,17) 2 turnouts 1:12 to maintenance yards Laying, welding and grinding long rails Engineering started 03/2002 Trial Track period 05/ /2004 Construction period 09/ /
35 35
36 Survey of existing ballastless track systems Basic type Monolithic/slab construction Direct support Support layer Concrete Asphalt Construction type In-situ concrete with fixed sleepers In-situ concrete with elastically supported sleepers In-situ concrete without sleepers Precast slab segments Continuously embedded rail With sleepers Existing Systems RHEDA 2000 Stedef Shinkansen slab track (J-slab) Edilon ATD RHEDA-BERLIN Sonneville Bögl Embedded Rail Structure GETRAC RHEDA classic SBB IPA Balfour Beatty Züblin Porr 36
37 Evolution of Rheda technology Rheda 2000 TW Rheda 2000 NL Rheda 2000 ESP Rheda 2000 India Rheda 2000 CN 37
38 Modified Bi-Block Sleeper B W60M 38
39 Rail Fastening System Vossloh
40 Rheda 2000 Turnout Sleeper 40
41 Elastic turnout rail fastening ERL 41
42 RHEDA 2000 on embankment (Standard) 42
43 RHEDA 2000 on bridges (Standard) The cams are positioned in joints between the track segments 43
44 RHEDA 2000 in tunnels (Standard) 44
45 45
46 Encountered substructures on the HSL Zuid embankment settlement free plate bridge tunnel 46
47 Encountered substructures on the HSL Zuid embankment settlement free plate bridge tunnel 47
48 System Adaptation for the HSL Zuid (I) More than 70% of the substructure is as a viaduct Variable length of substructures Variable stiffness characteristics of the viaducts Low overall construction height available No in between concrete layer possible Limited room for camplates Limited possibility of connecting to substructure Limited availibility of transferring forces to substructure Smaller width available 48
49 System Adaptation for the HSL Zuid (II) Substructure Design Substructure on piles Substr. Category Cat I Settlement Free Deformation Properties Δh total = 30mm Δh diff. = 2mm Δh/Δl = 1:2000 Special Substructure Cat III Settlement Sensitive Δh total = 50mm Δh diff. = 2mm Δh/Δl = 1:350 Embankment Substructure Cat II Settlement Poor Δh total = 30mm Δh diff. = n.a. Δh/Δl = 1:500 49
50 System Adaptation for the HSL Zuid (III) Flexible Interface 0.5 m 0.3 m Longitudinal Reinforcement 0.13 m 2 x m Free Drilling Zones 50
51 var 3.6m (6 sleepers) 6.5m (10 sleepers) var outer dowel 51
52 System Adaptation for the HSL Zuid (IV) Flexible for any substructure length 52
53 System Adaptation Flexible for any cant Cross Section C = 0-40 mm Cross Section C = mm Cross Section C = mm 53
54 Rheda switches 54
55 Basic Design results Switches WBN / BWG: 1:12 Rheda, movable frog 1:34,7 Rheda movable frog 1:39,17 Rheda, movable frog Transition in stiffness track - switch Stiffness: 52,5 -> 22,5 kn/mm In 8 steps FAKOP Variable track gauge 55
56 Interface with substructure Construction height Separated slabs Connection to substructure Substructure Construction height 56
57 Separated slabs construction height 480 mm construction height 580 mm construction height 480 mm 1:34.7 Sensitive Areas (tongue & frog) 57
58 Connection to substructure 58
59 59
60 Planning, Construction & Logistics strategies DBFM leads to the following clear Mission Statement: 1. Safety 2. Quality 3. Production Rates Excellent Qa/Qc system supports the above 1. Development of the Paperless Quality System 2. True independence of Qc officers (in the field) 3. Relentless testing off and on site Mechanization also supports the above 1. Better working conditions (HSE) 2. Continous higher quality of workmanship 3. Continous higher production rates 60
61 Integrated process Risk Management System Safety Management System Quality Management System Design Procurement Construction Testing & Commissioning Completion & Delivery Maintenance Phases of Project Design Specifications Requirements Verification & Validation Proces RAMS Proces 61
62 Mechanization leads to an industrial process of a continous improving construction with a constant high quality on-site Manual Fully-mechanized I N D U S T R I A L P R O C E S S P R O D U C T I O N up to m1 / shift N O P A P E R W O R K, real time control 62
63 Mechanization pre-requisites Clear Work Breakdown Structure Every sub proces optimised Mechanize using as guidelines 1. Safety 2. Quality 3. Production Rates Use Test Tracks to get beyond the starting points of the learning curves Monitor on a very frequent basis Plan Do Check Act 63
64 Building method Fixing construction method incl. construction speed and man hours Track 1 Work direction Track 2 Number Activity Performance per day 07:00-16:00 14:00-23:00 Concrete worker Rail worker Subcontractor Positioning sleepers Positioning longitudinal rebars Drilling of dowel holes Install fixation of lateral formwork Lay down & fix Intermediate layer Distribute rebars Track 1+2 Distribute sleepers Track m/d 300m/d 300m/d 600m/d 600m/d 900m/d 600m/d Track 1 Work direction Track 2 Number a Activity Disassembly Disassembly Curing and Concreting Final positioning Assembly Assembly Glue construction rails formwork hardening (fine alignment) formwork rebars dowels Performance per day 07:00-16:00 14:00-23:00 Concrete worker Rail worker Subcontractor Assembly lateral formwork (joints) Preliminary positioning (rough alignment) Assembly construction rails 300m/d 300m/d 300m/d 300m/d 300m/d 300m/d 300m/d 300m/d 300m/d 300m/d 300m/d
65 Learning curve test tracks Production Rate (m/shift) 300 Target reached! Time Start Construction HSL Wigan Schiedam Construction Trial 65
66 Impressions of the project HSL Zuid Drilling of dowel holes Sleeper positioning 66
67 Impressions of the project HSL Zuid Track rough adjustment Track precise adjustment 67
68 Impressions of the project HSL Zuid Track concreting Rail installation 68
69 69
70 100% 90% 80% 70% 60% 50% 40% 30% 20% 10% 0% 29 maart 2005 Quality reached (QC-Quotient) ZVP (team 1+2) and Tunnels Sep- 15- Sep- 25- Sep- 5- Okt- 15- Okt- 25- Okt- 4- Nov- 14- Nov- 24- Nov- 4- Dez- 14- Dez- 24- Dez- 3- Jan- 13- Jan- 23- Jan- 2- Feb- 12- Feb- 22- Feb- 4- Mrz- 14- Mrz- 24- Mrz- 3- Apr- 13- Apr- 23- Apr- 3- Mai- 13- Mai- 23- Mai- 2- Jun- 12- Jun- 22- Jun- 2- Jul- 12- Jul- 22- Jul- 1- Aug- 11- Aug- 21- Aug- 31- Aug- 10- Sep- 20- Sep- 30- Sep- 10- Okt- 20- Okt- 30- Oktdate QC Quotient trendlijn Number of findings per Slab (Quality Tendency) 3,00 2,50 2,00 1,50 1,00 0,50 5- Sep- 15- Sep- 25- Sep- 5- Okt- 15- Okt- 25- Okt- 4- Nov- 14- Nov- 24- Nov- 4- Dez- 14- Dez- 24- Dez- 3- Jan- 13- Jan- 23- Jan- 2- Feb- 12- Feb- 22- Feb- 4- Mrz- 14- Mrz- 24- Mrz- 3- Apr- 13- Apr- 23- Apr- 3- Mai- 13- Mai- 23- Mai- 2- Jun- 12- Jun- 22- Jun- 2- Jul- 12- Jul- 22- Jul- 1- Aug- 11- Aug- 21- Aug- 31- Aug- 10- Sep- 20- Sep- 30- Sep- 10- Okt- 20- Okt- 30- Okt- Quality figures Fps 0,00 date QC Tendency trendlijn
71 Manhour comparison Manhour comparison inclusive night hours - BAFO, Pre-construction stage & As built Manhours acc. - BAFO Manhours acc. - Pre-construction stage Manhours acc. - As built Proportionate night hours - BAFO Proportionate night hours -Pre-constr. Proportionate night hours - As built wk wk wk wk wk wk wk wk wk wk wk wk wk wk wk wk wk wk wk wk wk wk wk wk wk wk wk wk wk wk wk wk wk Amount of worker per week No night hours - As built Calendar weeks
72 4,6 4,5 4,5 29 maart ,3 2,9 2,8 3,7 4,0 3,6 3,4 3,9 3,6 3,3 2,9 2,8 3,2 3,7 3,4 3,5 3,1 2,9 3,5 3,2 5,5 5,5 4,8 4,8 6,1 7,0 7,7 8,4 8,6 8,6 10,1 11,6 3,2 3,4 2,9 3,2 3,4 2,0 3,0 3,6 4,6 4,7 4,8 4, ,6 8,0 6,7 6,6 6,8 6,2 5,9 8,6 5,9 6,3 6,5 6,9 6,7 6,5 6,3 6,2 6,1 6,1 6,1 6,1 6,1 6,0 5,9 5,8 5,7 5,6 5,5 5,4 5,3 5,2 5,2 5,1 5,0 5,0 5,0 5,0 4,9 4,9 4, wk wk wk wk wk wk wk wk wk wk wk wk wk wk wk wk wk wk wk wk wk wk wk wk wk wk wk Manhour learning curve in tunnels Weekly manhour rates in Tunnels Tunnel [manhour/m1] Average Tunnel Manhour per concreted track meter Calendar week
73 73
74 Drop test TNO settlement free piled slabs NOH 700 kg at height of cm 74
75 Intermediate Layer (4 mm Polypropylene Geotextile) tested at Fraunhofer Institute Darmstadt Purpose: 1. Separation superstructure - substructure 2. Minimizing Stress concentrations as required by Anforderungs Katalog Feste Fahrbahn Tests were needed for: - Friction behaviour - Stiffness parameters 75
76 HILTI Dowel Tests (I) 76
77 HILTI Dowel Tests (II) 77
78 Gap Tests at Stevin II Lab TU Delft 78
79 Lateral displacement Bridge Hollandsch Diep Southern Ramp: Vossloh DFF 300 test 79
80 80
81 81
82 82
83 83
84 84
85 First high speed test train on 14 Feb
86 86
87 87
88 88
89 89
PPP in Practice High Speed Line Netherlands. Infraspeed Maintenance. Ruud Schellekens. Goal
PPP in Practice High Speed Line Netherlands Infraspeed Maintenance Ruud Schellekens Goal HSL-line Facts & Figures The Parties Two examples (problem/change) 1 Track Description Hoofddorp RAS Rotterdam West
More informationFast track to Sustainable Mobility. ETCS Implementation on HSL Zuid: Challenges and Technical Solutions Jörn Schlichting, Infraspeed, Siemens AG
Fast track to Sustainable Mobility ETCS Implementation on HSL Zuid: Challenges and Technical Solutions Jörn Schlichting, Infraspeed, Siemens AG 1 Signalling Overview Ca. 100 km high-speed line, ETCS level
More informationRecent developments in slab track
finalesveld_slabtrack.qxd 23/5/03 10:08 am Page 1 SLAB TRACK Recent developments in slab track Coenraad Esveld, Professor of Railway Engineering, Delft University of Technology Delft With the design of
More informationSlab Track Austria. System ÖBB-PORR elastically supported slab
Slab Track Austria System ÖBB-PORR elastically supported slab 5. 2. 3. 4. 7. 6. Five holes for spindles 2. ÖBB-PORR slab 3. elastomeric layer 4. concrete joint sealing compound 5. rail support seat 6.
More informationRHEDA MRT The ballastless track for underground and surface commuter transit
RHEDA MRT The ballastless track for underground and surface commuter transit 2 3 Cities on the move Living and working today confront people with increasing demands for mobility. Planners and engineers
More informationThe Dutch Railway System. Logistics & Railway Infrastructure Forum NL Indonesia April 30 th 2015
The Dutch Railway System Logistics & Railway Infrastructure Forum NL Indonesia April 30 th 2015 1 Welkom Eigenaar: ProRail 27 november 2014 Welkom Eigenaar: ProRail 27 november 2014 Exchange of knowledge
More informationAT&T Global Network Client for Windows Product Support Matrix January 29, 2015
AT&T Global Network Client for Windows Product Support Matrix January 29, 2015 Product Support Matrix Following is the Product Support Matrix for the AT&T Global Network Client. See the AT&T Global Network
More informationAirport Rail Link is gathering speed. Wolfgang Rueprich, Project Manager Airport Rail Link, October 21, 2009
Airport Rail Link is gathering speed Wolfgang Rueprich, Project Manager Airport Rail Link, October 21, 2009 Integrated Public Transit System for Metropolitan Regions Regional / Long Distance Rail Service
More informationCOMPARISON OF FIXED & VARIABLE RATES (25 YEARS) CHARTERED BANK ADMINISTERED INTEREST RATES - PRIME BUSINESS*
COMPARISON OF FIXED & VARIABLE RATES (25 YEARS) 2 Fixed Rates Variable Rates FIXED RATES OF THE PAST 25 YEARS AVERAGE RESIDENTIAL MORTGAGE LENDING RATE - 5 YEAR* (Per cent) Year Jan Feb Mar Apr May Jun
More informationCOMPARISON OF FIXED & VARIABLE RATES (25 YEARS) CHARTERED BANK ADMINISTERED INTEREST RATES - PRIME BUSINESS*
COMPARISON OF FIXED & VARIABLE RATES (25 YEARS) 2 Fixed Rates Variable Rates FIXED RATES OF THE PAST 25 YEARS AVERAGE RESIDENTIAL MORTGAGE LENDING RATE - 5 YEAR* (Per cent) Year Jan Feb Mar Apr May Jun
More informationLIGHT RAIL ON RING 3 NOVEMBER 19 TH 2014. Supplier Workshop. Islevbro station (Rødov
LIGHT RAIL ON RING 3 NOVEMBER 19 TH 2014 Supplier Workshop Islevbro station (Rødov 1 Agenda In the Auditorium: 1. Welcome and programme; purpose of the day 2. Ring 3 in Brief 3. Vision of Light Rail on
More informationSettlement of Precast Culverts Under High Fills; The Influence of Construction Sequence and Structural Effects of Longitudinal Strains
Settlement of Precast Culverts Under High Fills; The Influence of Construction Sequence and Structural Effects of Longitudinal Strains Doug Jenkins 1, Chris Lawson 2 1 Interactive Design Services, 2 Reinforced
More informationMacetti Ing. Alessandro Via Marconi 12H 24050 Palosco (BG) Tel: 035-846843 E-mail: amacetti@gmail.com
Macetti Ing. Alessandro Via Marconi 12H 24050 Palosco (BG) Tel: 035-846843 E-mail: amacetti@gmail.com INTRODUCTION Studio Macetti Macetti engineering firm provides engineering services in the field of
More informationLVT System for. AlpTransit Gotthard AG
LVT System for the longest railway tunnel in the world AlpTransit Gotthard AG The Low Vibration Track (LVT) system for Gotthard Base Tunnel In December 2016, the world s longest railway tunnel will start
More informationAsset Management Policy for Major PFI Projects
Asset Management Policy for Major PFI Projects Agenda Asset Management Drivers Typical AM positioning in Motorway PFI Asset management Strategy Works Planning and Scheduling Innovation & Risk Mitigation
More informationDulles Corridor Metrorail Project
Dulles Corridor Metrorail Project MONTHLY COST AND SCHEDULE UPDATE FOR PHASE 2 AS OF JULY 31, 2015 SEPTEMBER 2015 Phase 2 Cost Summary July Expenditures $ 19.2 Million Total Expenditures $ 508.7 Million
More informationSelectie van uitgevoerde tenders. TTF Marketing & Communicatie b.v. Utrechtseweg 148, 3818 ER Amersfoort, +31 (0)33-461 58 52, www.ttfmc.
Selectie van uitgevoerde tenders Rijkswaterstaat Paths (roads) to the future N.a. 2004 BAM Infraconsult / BAM Wegen Won Innovation programme Consultancy Rijkswaterstaat Sea locks IJmuiden N.a. 2006 BAM
More informationOffshore Windfarm Egmond aan Zee 4 years of Operation
Offshore Windfarm Egmond aan Zee 4 years of Operation CUEN Offshore Wind Energy Conference 28 June 2011, Cambridge Elke Delnooz Operations Support Manager www.noordzeewind.nl 1 Contents Project description
More informationSECOND PENANG BRIDGE PROJECT
INTRODUCTION PROJECT PARTICULARS Jambatan Kedua (JKSB), a wholly-owned company of the Minister of Finance, Incorporated (MoF Inc.) was appointed as the concessionaire for the Second Penang Bridge Project
More informationUtrechtseweg 148 3818 ER Amersfoort +31 (0)33-461 58 52 info@ttfmc.nl www.ttfmc.nl
Rijkswaterstaat Paths (roads) to the future N.a. 2004 BAM Infraconsult / BAM Wegen Won Innovation programme Consultancy Rijkswaterstaat Sea locks IJmuiden N.a. 2006 BAM Civiel Won Innovation programme
More informationOverview of Program Management Services and Proposed CIP FY2012-17
Finance & Administration Committee Item III-A January 13, 2010 Overview of Program Management Services and Proposed CIP FY2012-17 Page 3 of 64 Washington Metropolitan Area Transit Authority Board Action/Information
More informationHSL Zuid. Phase II Implementation Concept. Final Report. Study for alternative transport system on HSL Zuid
HSL Zuid Phase II Implementation Concept Final Report Study for alternative transport system on HSL Zuid DB International GmbH Central Germany and Western Europe Oskar-Sommer-Straße 15 D-60596 Frankfurt
More informationHS line TSI Conformity Certification and Safety Assessment
Roma-Napoli HS line TSI Conformity Certification and Safety Assessment Roma, 16 December 2004 Carlo Carganico Rome Naples Certification: contents EU and Italian railway legislation RFI: role and responsibility
More informationCondition monitoring and condition-based railway Asset Management for High Speed lines
Fast track to Sustainable Mobility Condition monitoring and condition-based railway Asset Management for High Speed lines Stasha Jovanovic & Giuseppe Aurisicchio MER MEC S.p.A. Italy 1 Activities Object
More informationINTERACTION BETWEEN MOVING VEHICLES AND RAILWAY TRACK AT HIGH SPEED
INTERACTION BETWEEN MOVING VEHICLES AND RAILWAY TRACK AT HIGH SPEED Prof.Dr.Ir. C. Esveld Professor of Railway Engineering TU Delft, The Netherlands Dr.Ir. A.W.M. Kok Associate Professor of Railway Engineering
More informationSafe & Sound Bridge Terminology
Safe & Sound Bridge Terminology Abutment A retaining wall supporting the ends of a bridge, and, in general, retaining or supporting the approach embankment. Approach The part of the bridge that carries
More informationEmbedded Rail Slab Track
Embedded Rail Slab Track 01 Commissioned section of the BBEST system on the West Coast Main Line at Crewe in September 2003 Balfour Beatty Rail has developed, for supply to railway clients, main contractors
More informationchain, a Rotterdam experience
Integration of rail in the supply chain, a Rotterdam experience Guus de Mol, Manager Development & Logistic Solutions Kivi Niria, May 27 th 2011 Overview Keyrail and the Betuweroute Developments volume
More informationOperating Concept and System Design of a Transrapid Maglev Line and a High-Speed Railway in the pan-european Corridor IV
Operating Concept and System Design of a Transrapid Maglev Line and a High-Speed Railway in the pan-european Corridor IV A. Stephan & E. Fritz IFB Institut für Bahntechnik GmbH, Niederlassung, Germany
More informationCertification Case: Locomotives for Corridor A (and more)
Certification Case: Locomotives for Corridor A (and more) Dr.ir. L. (Lieuwe) Zigterman MIRSE Inhoud Lieuwe Zigterman DoorZigt B.V. Casus: certificering ES64F4: Gebaseerd op ervaringen opgedaan bij KEMA
More informationSTATUS REPORT FOR THE SUBMERGED REEF BALL TM ARTIFICIAL REEF SUBMERGED BREAKWATER BEACH STABILIZATION PROJECT FOR THE GRAND CAYMAN MARRIOTT HOTEL
STATUS REPORT FOR THE SUBMERGED REEF BALL TM ARTIFICIAL REEF SUBMERGED BREAKWATER BEACH STABILIZATION PROJECT FOR THE GRAND CAYMAN MARRIOTT HOTEL performed by Lee E. Harris, Ph.D., P.E. Consulting Coastal
More informationINNOVATIONS IN RAILWAY TRACK
INNOVATIONS IN RAILWAY TRACK Coenraad Esveld Professor of Railway Engineering, TU Delft This paper describes innovations in railway track structures. Special attention is devoted to alternatives for ballasted
More informationOrdinance on Railway Infrastructure. General provisions. Article 1
Based on article 15, par. 4 of the Railway Law (Narodne Novine no. 123/03 and 30/04), the Minister of the Sea, Tourism, Transport and Development has issued Ordinance on Railway Infrastructure General
More informationCase 2:08-cv-02463-ABC-E Document 1-4 Filed 04/15/2008 Page 1 of 138. Exhibit 8
Case 2:08-cv-02463-ABC-E Document 1-4 Filed 04/15/2008 Page 1 of 138 Exhibit 8 Case 2:08-cv-02463-ABC-E Document 1-4 Filed 04/15/2008 Page 2 of 138 Domain Name: CELLULARVERISON.COM Updated Date: 12-dec-2007
More informationearned value management
earned value management in control of big productions an eyeon white paper october 2013 1 contents 4 ly escalation 5 linking and cost control 6 cost forecasting 6 implementation towards effective project
More informationProject Rijksweg 15, Maasvlakte-Vaanplein
Project Rijksweg 15, Maasvlakte-Vaanplein challenges of a DBFM-contract Adrie Franken, Contractmanager A15 MaVa Rijkswaterstaat Topics Project scope Procurement strategy characteristics of the DBFM-contract
More informationThe way to go. rheda 2000 ballastless track system
The way to go. RHEda 2000 BALLASTLESS TRACK SYSTEM RHEDA 2000 2 3 On ballastless track toward railways of Our contribution to high-speed technology: the RHEDA 2000 ballastless track system is the direct
More informationBuildings Construction Procurement Strategy
Buildings Construction Procurement Strategy Graham Strickleton Site, Buildings and Power supplies Procurement Manager JOURNEE DEDIEE AUX INDUSTRIELS ET AUX MEMBRES DU RESEAU A.P.I Disclaimer: these slides
More informationMETHOD OF STATEMENT FOR STATIC LOADING TEST
Compression Test, METHOD OF STATEMENT FOR STATIC LOADING TEST Tension Test and Lateral Test According to the American Standards ASTM D1143 07, ASTM D3689 07, ASTM D3966 07 and Euro Codes EC7 Table of Contents
More informationEmbedded Parts Introduction - Anchors
In the plant construction or process plants such as chemical, petrochemical, gas or power plants various disciplines are brought into contact and built on each other. Civil, mechanical, electro technical
More informationThe complete provider for. Gauging Products and Measurement Systems
The complete provider for Gauging Products and Measurement Systems The Gauging Requirement Effective clearance assessment is something that concerns all railways and demands for significantly increased
More informationEnhanced Vessel Traffic Management System Booking Slots Available and Vessels Booked per Day From 12-JAN-2016 To 30-JUN-2017
From -JAN- To -JUN- -JAN- VIRP Page Period Period Period -JAN- 8 -JAN- 8 9 -JAN- 8 8 -JAN- -JAN- -JAN- 8-JAN- 9-JAN- -JAN- -JAN- -JAN- -JAN- -JAN- -JAN- -JAN- -JAN- 8-JAN- 9-JAN- -JAN- -JAN- -FEB- : days
More informationProject Cost & Schedule Monitoring Process Using MS Excel & MS Project
Project Cost & Schedule Monitoring Process Using MS Excel & MS Project Presented by: Rajesh Jujare About Us Solutions is founded with objectives a. To share its expertise and experiences to overcome the
More informationPlanning and Scheduling. Railway Maintenance Work. with TILOS
Planning and Scheduling of Railway Maintenance Work with TILOS Linear Scheduling Software High Output System Traditional Technique The best practise to plan and manage Railway Repair and Maintenance works
More informationAlpha Fund S.I.F. Specialized Investment Fund LIFE SETTLEMENT FUND OF FUNDS
Alpha Fund S.I.F. Specialized Investment Fund LIFE SETTLEMENT FUND OF FUNDS Pag 1 di 29 Life Settlements Alternative asset class, investing in life insurance contracts of aged U.S. citizen. Return widely
More informationNumerical Analysis of the Moving Formwork Bracket Stress during Construction of a Curved Continuous Box Girder Bridge with Variable Width
Modern Applied Science; Vol. 9, No. 6; 2015 ISSN 1913-1844 E-ISSN 1913-1852 Published by Canadian Center of Science and Education Numerical Analysis of the Moving Formwork Bracket Stress during Construction
More informationRail Roughness Monitoring in the Netherlands
Rail Roughness Monitoring in the Netherlands A.H.W.M. Kuijpers M+P consulting engineers, P.O. Box 2094, 5260 CB, Vught, The Netherlands Tel.: +31 73 6589050; Fax: +31 73 6589051 ArdKuijpers@mp.nl Summary
More informationCrack formation in structural slabs on underwater concrete
Graduation Thesis Faculty of Civil Engineering Delft University of Technology Crack formation in structural slabs on underwater concrete W.H. van der Woerdt 1158325 Graduation Committee: Prof. dr. ir.
More informationRijkswaterstaat. Basic Principles of PPP
Basic Principles of PPP Auditing Public Private Partnerships; the work continues Seminar for Supreme Audit Institutions 26 and 27 November 2012 The Hague, The Netherlands The Directorate-General for Public
More informationPreliminary Presentation
Preliminary Results Presentation Year ended 31 December 2012 February 2013 1 Executive Summary Very good progress during 2012 despite no improvement in market transaction levels - Underlying Group Operating
More informationSelection of a Railway Track System by Best Value Analysis
!!! Integrated Project (IP) Thematic Priority 6: Project No. TIP5-CT-2006-031415 Sustainable Development, Global Change and Ecosystems Selection of a Railway Track System by Best Value Analysis! INNOTRACK
More informationSBB Infrastructure, Measurement and Diagnostic Technology.
SBB Infrastructure, Measurement and Diagnostic Technology. Your partner for testing railway technology. Contents. Measurement and Diagnostic Technology 4 3 Infrastructure diagnostics 6 Running gear technology
More informationProposal For a Trivia Bid and Interview
HILLSBOROUGH COUNTY AVIATION AUTHORITY Planned Procurement Opportunities Report May 2015 Prepared by the Procurement Department Planned Procurement Opportunities Report - May 2015 Overview The Planned
More informationPlanned Procurement Opportunities Report. April 2015
HILLSBOROUGH COUNTY AVIATION AUTHORITY Planned Procurement Opportunities Report April 2015 Prepared by the Procurement Department Planned Procurement Opportunities Report - April 2015 Overview The Planned
More informationAnalysis One Code Desc. Transaction Amount. Fiscal Period
Analysis One Code Desc Transaction Amount Fiscal Period 57.63 Oct-12 12.13 Oct-12-38.90 Oct-12-773.00 Oct-12-800.00 Oct-12-187.00 Oct-12-82.00 Oct-12-82.00 Oct-12-110.00 Oct-12-1115.25 Oct-12-71.00 Oct-12-41.00
More informationState Materials Laboratory 2013 Performance Measures. Quality Assurance Section
The State Materials Laboratory provides specialized materials testing and engineering expertise in construction materials, and materials quality acceptance programs in support of the state highway system
More informationeuropass + 2 meeting Paris
europass + 2 meeting Paris Statistical information about access to original and new web site and tool Wednesday, 2011 June - 16 Claus-Jürgen Prenzel bfzonline / f-bb page 1 of 19 Table of contents Webhits:
More informationAsphalt in Railway Tracks
Airfield uses of asphalt Asphalt in Railway Tracks Ref: (3)2-03-00.015 European Asphalt Pavement Association P.O. Box 175 3620 AD Breukelen, The Netherlands www.eapa.org info@eapa.org October 2003 2 Contents
More informationXING #1 Professional Social Network In German Speaking Europe
XING #1 Professional Social Network In German Speaking Europe Preliminary FY Results 2011 Presentation March 1, 2012 ADVERTISING EVENTS E-RECRUITING... Successful execution of 2011 strategy PAID MEMBERSHIP
More informationINCREASE OF DURABILITY AND LIFETIME OF EXISTING BRIDGES. PIARC TC 4.4 EXPERIENCE.
INCREASE OF DURABILITY AND LIFETIME OF EXISTING BRIDGES. PIARC TC 4.4 EXPERIENCE. M.Sc. Gediminas Viršilas Head of Bridge Division, Lithuanian Road Administration Working group 2 of PIARC Technical Committee
More informationSPECIFICATION NET LINE 1 - Wilkinson Street Diamond Crossing (WSDC) re-ballast
General Requirements: The existing fixed diamond crossing at the Armstrong Way / Wilkinson Street junction (NG7 7NW) has become contaminated with material from roadway run-off and requires re-ballasting
More informationLife after 30! Innovative investigation and repair of the Overvaal railway tunnel. r a i l w a y s a n d h a r b o u r s PROJECT TEAM
Text Hannes Gräbe Spoornet (Technology Management) hannesg@spoornet.co.za r a i l w a y s a n d h a r b o u r s Life after 30! Innovative investigation and repair of the Overvaal railway tunnel 1 PROJECT
More informationExamining rails in detail. Rail inspection: Rail testing Rail measurement Welding monitoring and vehicle testing Consulting
Examining rails in detail Rail inspection: Rail testing Rail measurement Welding monitoring and vehicle testing Rail inspection Value retention and safety for your rails Our tests Geometrical testing of
More informationOPERATING FUND. PRELIMINARY & UNAUDITED FINANCIAL HIGHLIGHTS September 30, 2015 RENDELL L. JONES CHIEF FINANCIAL OFFICER
PRELIMINARY & UNAUDITED FINANCIAL HIGHLIGHTS September 30, 2015 RENDELL L. JONES CHIEF FINANCIAL OFFICER MANAGEMENT OVERVIEW September 30, 2015 Balance Sheet Cash and cash equivalents had a month-end balance
More informationERTMS deployment challenges in a deregulated market. Björn Westerberg April 25, 2012
ERTMS deployment challenges in a deregulated market Björn Westerberg April 25, 2012 Agenda SJ AB Overview ERTMS Challenges 1 Service to Customer 2 OneCommonSystem 3 Finding a Business Case 2 SJ AB Operates
More informationNoise Abatement Political Background
Noise Abatement Political Background Advanced Noise Reduction Rob Hofman Dienst Verkeer en Scheepvaart (DVS) 2 Netherlands 34.000 km 2 land Capital Amsterdam Population density 3 16 million inhabitants,
More informationStructures Construction Pre-Work Checklist PRE-WORK SHEET FOR PROJECT MANAGERS
Structures Construction Pre-Work Checklist PRE-WORK SHEET FOR PROJECT MANAGERS 1 Proposal & Plans Received? 2 Review Proposal, highlight important facts. Know proposal well to be able to find answers quickly.
More informationVirginia Approach Spans
Virginia Concrete Conference 2009 Woodrow Virginia Approach Spans David Tackoor, HNTB Formerly of URS Corp for Potomac Crossing Consultants Woodrow 1 Second Severn Crossing 2 Medway Crossing (Channel Tunnel
More informationBNAM 2008 BERGEN BYBANE NOISE REDUCTION BY TRACK DESIGN. Reykjavik, august 2008. Arild Brekke, Brekke & Strand akustikk as, Norway
BNAM 08 BERGEN BYBANE NOISE REDUCTION BY TRACK DESIGN Dr.ing Arild Brekke Brekke & Strand akustikk as Box 1024 Skøyen 0218 Oslo Email: arild.brekke@bs-akustikk.no Introduction BNAM 08 A city line now is
More informationPRELIMINARY ACCOUNTS FOR 2010
INTERIM REPORT FOR Q4 2010 AND INTERIM REPORT FOR Q4 2010 AND PRELIMINARY ACCOUNTS FOR 2010 HIGHLIGHTS Profit for Hurtigruten in 2010 Pre-tax profit of NOK 22 million (loss of NOK 28 million in 2009) EBITDA
More informationSubsidence due to peat decomposition in the Netherlands kinematic observations from radar interferometry
Subsidence due to peat decomposition in the Netherlands kinematic observations from radar interferometry Miguel Caro Cuenca, Ramon Hanssen, Freek van Leijen. Fringe 2007, Frascati, Italy Netherlands, Area
More informationEXHIBIT 2-2-C PROGRESS SCHEDULES
EXHIBIT 2-2-C PROGRESS SCHEDULES PART 1 GENERAL 1.01 SUMMARY A. The work specified in this section consists of furnishing transportation, labor, materials, equipment and incidentals necessary for preparation,
More informationFINAL PRODUCT TO BE DELIVERED TO ISR RAILWAY LINES AKKO CARMIEL, HAIFA BET SHEAN AND HERZELYA KEFAR SABE LINES
FINAL PRODUCT TO BE DELIVERED TO ISR RAILWAY LINES AKKO CARMIEL, HAIFA BET SHEAN AND HERZELYA KEFAR SABE LINES IN_110860_230512_FINAL_PRODUCT_TO_ISR_08 TABLE OF CONTENTS 1 FOREWORD... 1 2 RAILWAY LINE
More informationPresented by: Ray Crawford ASQ Design and Construction Division
Certification for Construction Quality Managers Presented by: Ray Crawford ASQ Design and Construction Division TODAYS PRESENTATION Who We Are Quality issues in the industry Targeted uses of BOK Framework
More informationWORK SCOPE. Domains in which we work:
WORK SCOPE Engineering consulting, technical office, assistance and supervision in industrial works. We specialize in structures, civil works and industrial equipment. Domains in which we work: Industrial
More informationTrends in the advertising market
Trends in the advertising market Report 2015/12 Monthly report on developments in the Swiss advertising market Highlights in December 2 Short summary of the advertising year 2015 3 Advertising impact within
More informationMETHOD STATEMENT HIGH STRIAN DYNAMIC TESTING OF PILE. Prepared by
METHOD STATEMENT HIGH STRIAN DYNAMIC TESTING OF PILE Prepared by Infratech ASTM CO., LTD. Contents Chapter Description Page Contents...... 1 List of Appendix. 1 1. Introduction.. 2 2. Test Method..2 3.
More informationALIGNMENT ASSUMPTIONS
JUNE 2013 LETBANESEKRETARIATET ALIGNMENT ASSUMPTIONS REPORT ADDRESS COWI A/S Visionsvej 53 9000 Aalborg Denmark TEL +45 56 40 00 00 FAX +45 56 40 99 99 WWW cowi.com JUNE 2013 LETBANESEKRETARIATET ALIGNMENT
More informationInstallation guide for the SafeLine type anchorage device. Tested in compliance with EN 795: 1996. No.: SE-...
Installation guide for the SafeLine type anchorage device Tested in compliance with EN 795: 1996 No.: SE-... Version: 09.10.2008 SE 67 Subject to technical alterations! Contents 1. General information
More informationGUIDANCE NOTES FOR DEVELOPMENTS OR ENGINEERING WORKS IN THE VICINITY OF SPT SUBWAY INFRASTRUCTURE JULY 2005
GUIDANCE NOTES FOR DEVELOPMENTS OR ENGINEERING WORKS IN THE VICINITY OF SPT SUBWAY INFRASTRUCTURE JULY 2005 CONTENTS 1.0 INTRODUCTION 2.0 OVERVIEW OF SPT APPROACH TO DEVEOPMENTS/WORKS IN THE VICINITY OF
More informationENTRY FORM. DVASE 2015 Excellence in Structural Engineering Awards Program
ENTRY FORM DVASE 2015 Excellence in Structural Engineering Awards Program PROJECT CATEGORY (check one): Buildings under $2M Buildings Over $100M Buildings $2M-$10M X Other Structures Under $5M Buildings
More information2 CONTACT INFORMATION 4 3 ROUTE DESCRIPTION 5
1 INTRODUCTION 3 2 CONTACT INFORMATION 4 3 ROUTE DESCRIPTION 5 1998-2003 Wireless Services B.V., all rights reserved Page 2 1 Introduction About Wireless Services Wireless Services B.V. is specialized
More informationAndrew Pylyp. Capital Market Day. Managing Director Wer liefert was? Stockholm 27. November 2006
Capital Market Day Andrew Pylyp Managing Director Wer liefert was? Stockholm 27. November 2006 Wer liefert was? GmbH Capital Market Day, November 27, 2006 134 Company History Media 1932 Business-to-Business
More informationPlanned Procurement Opportunities Report. March 2015
HILLSBOROUGH COUNTY AVIATION AUTHORITY Planned Procurement Opportunities Report March 2015 Prepared by the Procurement Department Overview The Planned Procurement Opportunities Report is updated and posted
More informationPriority decision. High-Frequency Rail Transport Programme
Priority decision High-Frequency Rail Transport Programme Priority decision High-Frequency Rail Transport Programme Additional rail capacity There will be 6 intercity and 6 Sprinters (all-station regional
More informationIntroduction. Evaluating Value for Money. Hans de Kievit Senior PPP Consultant. Projects: Auditing Public Private Partnerships; the work continues
Evaluating Value for Money Auditing Public Private Partnerships; the work continues Seminar for Supreme Audit Institutions 26 and 27 November 2012 The Hague, The Netherlands Introduction Hans de Kievit
More informationTechnical Application Document. Hilti HIT-RE 500-SD
Technical Application Document Technical Evaluation Report 3/10-649 Injection system for rebar connections Hilti HIT-RE 500-SD Subject to European Technical Approval ATE-09/0295 Holder of approval: HILTI
More informationStrain Measurement in Pavements with a Fibre Optics Sensor Enabled Geotextile
Strain Measurement in Pavements with a Fibre Optics Sensor Enabled Geotextile Olivier Artières 1, Matteo Bacchi 2, Paolo Bianchini 1, Pierre Hornych 3 and Gerrit Dortland 1 1 TenCate Geosynthetics France,
More informationPRELIMINARY STEEL IMPORTS INCREASE 17% IN JANUARY Import Market Share 32% in January
News Release FOR IMMEDIATE RELEASE February 25, 2015 CONTACT: Lisa Harrison 202.452.7115/ lharrison@steel.org PRELIMINARY STEEL IMPORTS INCREASE 17% IN JANUARY Import Market Share 32% in January Washington,
More informationMANAGEMENT INFORMATION REPORT Department for Business Innovations & Skills (BIS)
MANAGEMENT INFORMATION REPORT Department for Business Innovations & Skills (BIS) Version 3.2 9/1/215 Clyde & Co 4 th Floor, Collingwood House, 3 Collingwood Street, Newcastle, NE1 1JW T: 191 229 223 F:
More informationImportant Dates Calendar 2014-2015 FALL
Important Dates Calendar 204-205 FALL Rev. 6-8-4 st 8 H st 0 2nd 0 st 5 2nd 5 3rd 5 LSC Advanced Registration Begins May 27 May 27 May 27 May 27 May 27 May 27 May 27 May 27 May 27 Returning Students Advanced
More informationLETBANE PÅ RING 3. Information about the public procurement process
Information about the public procurement process Document ID: L3-X-LB-PRE-0001 Version: 2.0 Issue date: 2015-11-10 Issued by: Ring 3 Letbane I/S Approved by: AGF Anne-Grethe Foss Checked by: PAMA Patrik
More informationAfrican Bank Investments Limited Strategies to grow in the mass market
African Bank Investments Limited Strategies to grow in the mass market June 2007 Presentation agenda Who we are Our target market A transforming business Is this a good time to be in this market? Outlook
More informationPreventing road crash injuries involving children
Preventing road crash injuries involving children Experience of Slovenia Robert Štaba, AMZS Road Safety Comission Secretary SOL Road Safety Conference - Budapest 2011 SLOVENIA 2 million people Capital
More informationHEAVY DUTY CROSSINGS TRANSIT CROSSINGS DRIP TRACK TANK CAR SPILL CONTAINMENT VEHICLE INSPECTION PITS CONVEYOR/UNLOADING PITS
HEAVY DUTY CROSSINGS TRANSIT CROSSINGS DRIP TRACK TANK CAR SPILL CONTAINMENT VEHICLE INSPECTION PITS CONVEYOR/UNLOADING PITS RAIL SCALE APPROACHES & FOUNDATIONS SLAB TRACK TUNNEL TRACK SUPPORT WASH BAY
More information1,045 m length of the Deh Cho Bridge
Innovative Design Features: Lightweight truss: The principles of lightweight design led to a saving of 25% in the use of structural steel. State of the art deck system: Designed as a four-way slab, it
More informationHealth & Safety Monthly Report. Waterfront Auckland. February - March 2013
Health & Safety Monthly Report FOR Waterfront Auckland February - March 2013 1 Contents Executive Summary... 3 Services Update... 4 Project Quality Plan (PQP)... 4 Policy... 4 Programme... 4 Management
More informationL_All_Vocatinal_Ed_Construction. Sector: Construction. Sr. No Specialisation Page No 1 Construction and Building Technology 02.
L_All_Vocatinal_Ed_Construction Sector: Construction Sr. No Specialisation Page No 1 Construction and Building Technology 02 1 P a g e 2 P a g e VOCATIONAL EDUCATIONAL QUALIFICATION FRAMEWORK (Sector -
More informationCONFERENCE CALL. FY2013 Preliminary Results 21.03.2014
CONFERENCE CALL FY2013 Preliminary Results 21.03.2014 FY 2013 COMPANY Highlights 2013 May Increase of the shareholdings to 100% in Altmarkt-Galerie Dresden as of 1 May 2013 67% were already owned by DES
More informationHOUSE BUILDING DIGEST
HOUSE BUILDING DIGEST (Construction Specifications-Foundations) Creating Enabling Environment for Affordable Housing for All This is an attempt by BMTPC to provide useful but often ignored information
More information