Public Works Capital Improvement Projects. March 29, 2010

Size: px
Start display at page:

Download "Public Works Capital Improvement Projects. March 29, 2010"

Transcription

1 Public Works Capital Improvement Projects March 29,

2 Focus Street Rehabilitation Projects Sanitary Sewer Program Transportation Projects 2

3 Street Projects PROGRAM GOALS Implement a systematic pavement rehabilitation and preventative maintenance program that can extend the life of streets and reduce future maintenance costs; and Maintain current Pavement Condition Index (PCI) through a comprehensive approach. 3

4 Street Project Funding Total funds for streets: FY 2012 FY 2013 General Fund $2,260,456 $2,266,615 Other Funds 1,640,858 1,643,837 $3,901,314 $3,910,452 Additional funding comes from many different sources to augment scarce local funds (General Fund) American Recovery/Reinvestment Act funds State Prop 1B Transportation Bonds ISTEA-STP State SB 300 Gas tax and sales tax 4

5 Street Projects Limited funding does not provide for frequent traditional large-scale treatments (overlays, reconstruction). We are exploring and implementing more cost effective techniques such as the following: 1. Improved coordination between Engineering and Operations 2. Improved inspection of utility cuts 3. Preserving existing pavements using chip and slurry seals 4. Use of new treatments to fill potholes 5. Improved contract monitoring and follow-up 6. Expansion of crack sealing program 5

6 Street Projects Completed in last two years: University Avenue from Overpass to Oxford Gilman Street Solano Avenue Martin Luther King Jr Way Planned for FY 2012 and 2013: Sacramento Street from University to Ashby Marin Avenue from The Alameda to The Circle Milvia Street from University to Blake 4 th Street from University to Gilman 6

7 Sanitary Sewer Program Projections for FY 2012 & FY 2013: FY 2012 FY 2013 Revenue $14,000,000 $14,000,000 Expenditures $17,500,000 $17,500,000 Annual Deficit ($ 3,500,000) ($3,500,000) Fund Balance $12,750,000 $ 9,250,000 7

8 Sanitary Sewer Program A comprehensive program is being implemented to balance and coordinate: Capital projects: replacing sewer lines to reduce or eliminate unhealthy overflows, and Operations & maintenance: cleaning and inspection program, flow monitoring, leak testing, grease source detection. 8

9 Sanitary Sewer Program Effective utilization of available resources is needed to: Ensure comprehensive and accurate data collection; Coordinate Engineering and Operations work; Implement cost effective capital improvements for improving water quality and flow reduction; and Respond to additional monitoring and reporting requirements of the EPA order. 9

10 Sanitary Sewer Program The comprehensive plan is paying off. One clear result: real improvement to Sanitary Sewer Overflows (SSOs)

11 Transportation Programs Alameda Countywide Transportation Plan (Future) Draft project list for the 2012 Alameda Countywide Transportation Plan: City to seek $226 million over the next 25 years Project delivery improvements 11

12 Transportation Grant Projects $15.8 Million FY th Street Bike Boulevard Extension $1,136,000 Berkeley Parking/Trans Action Plan $4,610,000 FY West Street Multi-Use Pathway $875,555 Safe Routes to Schools (Rosa Parks, 1000 Oaks, Malcolm X, Arts Magnet) $998,510 Bicycle Parking $46,887 Downtown BART Plaza Area Improvements Phase 1 $2,256,250 Bay Trail Extension to Marina, Segment 1 $2,428,000 12

13 Transportation Grant Projects $15.8 Million FY (cont d) Safe Routes to Transit $538,820 Caldecott 4th Bore/ Ashby Improvements $2,000,000 UC LRDP Transportation $1,061,000 Staff for Council/Community Requests (1.35 FTE for inquiry response) Current workload: 70 requests of varying sizes and duration 13

14 Update Refuse Fund Forecast 3-Year Forecast FY 2011 Projected FY 2012 Projected FY 2013 Projected Beginning Gross Fund Balance/Deficit $424,899 ($791,841) ($5,863,383) Total Revenue $32,971,777 $32,422,800 $32,762,528 Total Expenses $33,346,828 $35,036,718 $35,196,978 Personnel $15,274,884 $16,570,875 $16,653,693 Non- Personnel $18,071,944 $18,465,843 $18,543,285 Annual Operating Balance/Deficit ($375,051) ($2,613,198) ($2,434,450) Capital Improvement Costs (CIP) $841,689 $2,457,624 $500,000 Ending Annual Balance/Deficit (Including CIP) ($1,216,740) ($5,071,542) ($2,934,450) Ending Gross Fund Balance/Deficit ($791,841) ($5,863,383) ($8,797,833) Annual operating deficit $2.4M by 2013 before capital costs With capital costs deficit grows to $5M in 2012 & $2.9M in 2013 Without balancing measures fund deficit grows to $8.8M by FY

15 Options to Balance Fund FY 2012 Projected FY 2013 Projected Cost Savings Ecology Center Operational Changes ($68,000) ($254,000) CCC-Change container processing to outside MRF ($375,000) ($400,000) Commercial 1-Person Routes ($472,116) Residential 1-Person Routes ($708,174) Reduction of Pool Workers ($472,116) Elimination of Vacant positions ($383,194) ($387,842) New Landfill/C& D Disposal Contracts ($125,000) ($250,000) ($951,194) ($2,944,248) Revenue Rate Increase (assumes 4%rate increase in FY 2013) $956,485 Other Revenue $20,000 $450,000 $20,000 $1,406,485 New Costs Annual Payment- New Collection Trucks $213,000 $426,000 Loan Re-payment $92,828 $609,366 $305,828 $1,035,366 Net Benefit of Total Balancing Options $665,366 $3,315,367 15

16 Considerations for a New Rate Structure Benchmark new rates to other cities Minimum charge for collection services Charges associated with each service provided (garbage, recycling, green waste) EXAMPLE MONTHLY CHARGE Current Rate 4% 32 Gallon $27.56 $ % rate increase will generate $956,000 in new revenue 16

17 Refuse Fund Forecast with Balancing Measures FY 2011 Projected FY 2012 Projected FY 2013 Projected Beginning Fund Balance/Deficit $424,899 $0 $0 Annual Operating Deficit ($375,051) ($2,613,918) ($2,434,450) Balancing Measures/Savings $0 $971,194 $4,350,733 Annual Operating Balance/Deficit ($375,051) ($1,642,724) $1,916,284 Capital Expenditures $841,689 $2,457,624 $500,000 Annual Payment: New Collection Trucks $0 $213,000 $426,000 Loan Re-payment $92,828 $609,366 Ending Fund Balance/Deficit ($791,841) ($4,406,176) $380,918 Loan to Refuse Fund $791,841 $4,406,176 $0 Ending Fund Balance/Deficit $0 $0 $380,918 Annual payment- New collection trucks assume a 7 year payment term. Loan Re-payment assumes a 10 year repayment term. 17

Measure M Paving and Green Infrastructure Program Update

Measure M Paving and Green Infrastructure Program Update Office of the City Manager To: From: Honorable Mayor and Members of the City Council Dee Williams-Ridley, Interim City Manager Submitted by: Phillip Harrington, Acting Director, Public Works Subject: Measure

More information

CITY COUNCIL WORKSHOP MAY 24, 2016

CITY COUNCIL WORKSHOP MAY 24, 2016 1 CITY COUNCIL WORKSHOP MAY 24, 2016 Capital Budget FY 2016-2017 & 2017-2018 Robert Ovadia, PE, City Engineer 2 Overview FY 2015-16 Accomplishments Projects Completed during FY 2015-16 Projects Under Construction

More information

Jeff Haby, P.E. Director Sewer System Improvements. September 15, 2015. Agenda

Jeff Haby, P.E. Director Sewer System Improvements. September 15, 2015. Agenda SAWS Sanitary Sewer Overflow Reduction Program Jeff Haby, P.E. Director Sewer System Improvements SA Military Engineers Meeting Agenda SAWS Overview Consent Decree CD Compliance Programs Program Transition

More information

City of Dallas Wastewater Collection System: TCEQ Sanitary Sewer Outreach Agreement City Council Briefing January 17, 2007

City of Dallas Wastewater Collection System: TCEQ Sanitary Sewer Outreach Agreement City Council Briefing January 17, 2007 City of Dallas Wastewater Collection System: TCEQ Sanitary Sewer Outreach Agreement City Council Briefing January 17, 2007 1/12/2007 1 Briefing Purpose Provide update on Wastewater Collection Activities

More information

Sanitary Sewer Master Plan

Sanitary Sewer Master Plan , Illinois Sanitary Sewer Master Plan EXECUTIVE SUMMARY Prepared by September 9, 2010 1670 South Taylorville Road Decatur, Illinois 62521 www.bgmengineering.com Sanitary Sewer Master Plan A. SCOPE OF STUDY

More information

The Roads to Recovery. Facts About Transportation Funding and Spending

The Roads to Recovery. Facts About Transportation Funding and Spending The Roads to Recovery Facts About Transportation Funding and Spending How Pima County spends transportation money (F.Y. 2014-15 Transportation Budget) 1 Debt Service (1997 bonds): $19.1 million In 1997,

More information

Decision Matrix for Pavement Preservation. Mike Mamlouk Arizona State University

Decision Matrix for Pavement Preservation. Mike Mamlouk Arizona State University Decision Matrix for Pavement Preservation Mike Mamlouk Arizona State University Outline 1. Concept of preventive maintenance 2. Effectiveness of treatments 3. Treatment selection 2 Pavement Pavement Preservation

More information

2010-2011 Statement of Mandate. March 29, 2010

2010-2011 Statement of Mandate. March 29, 2010 2010-2011 Statement of Mandate March 29, 2010 Table of Contents 1. Message from Minister and Deputy Minister................................... 1 2. Department Mission...3 3. Department Mandate...3 4.

More information

Township of Enniskillen. Asset Management Plan

Township of Enniskillen. Asset Management Plan Township of Enniskillen Asset Management Plan 2014 1 TABLE OF CONTENTS Page A. Introduction 3 B. State of Local Infrastructure 4 C. Desired Levels of Service 7 D. Asset Management Strategy 8 E. Financing

More information

Pavement Management Program

Pavement Management Program Pavement Management Program 2013 Street Maintenance Program Executive Summary 1/15/2013 Presented by Mark Thiel Assistant Director Public Works Program Overview Start of current program 2005 812.5 Lane

More information

Proposed General Plan Update Goals, Policies, and Implementation Actions

Proposed General Plan Update Goals, Policies, and Implementation Actions Proposed General Plan Update Goals, Policies, and Implementation Actions The construction and maintenance of infrastructure is necessary to support existing and planned land uses and to achieve Environmental

More information

DRAFT Public Outreach Document for What s an SSMP?

DRAFT Public Outreach Document for What s an SSMP? DRAFT Public Outreach Document for What s an SSMP? This easy to read document is developed and provided to interested parties to assist in educating cities, agencies, their management, elected officials

More information

SEWER CLEANING, INSPECTION AND ASSESSMENT

SEWER CLEANING, INSPECTION AND ASSESSMENT 3.1 OVERVIEW Chapter 3 SEWER CLEANING, INSPECTION AND ASSESSMENT Preventive maintenance protects the investment of the sanitary sewer collection system infrastructure. Higher frequency cleaning of gravity

More information

POLLUTION PREVENTION FACT SHEET: AUTOMOBILE MAINTENANCE

POLLUTION PREVENTION FACT SHEET: AUTOMOBILE MAINTENANCE POLLUTION PREVENTION FACT SHEET: AUTOMOBILE MAINTENANCE Description This pollution prevention measure involves creating a program of targeted outreach and training for businesses involved in automobile

More information

Waste Management. Sunny Mistry. Rensselaer Polytechnic Institute. Solid and Hazardous Waste Prevention and Control Engineering. Spring 2014 MANE-6960

Waste Management. Sunny Mistry. Rensselaer Polytechnic Institute. Solid and Hazardous Waste Prevention and Control Engineering. Spring 2014 MANE-6960 Waste Management Sunny Mistry Rensselaer Polytechnic Institute Solid and Hazardous Waste Prevention and Control Engineering Spring 2014 MANE-6960 Introduction: Modern waste management strategies have been

More information

Pavement Management Implementation: Success Stories for Maryland Counties

Pavement Management Implementation: Success Stories for Maryland Counties Pavement Management Implementation: Success Stories for Maryland Counties September 25, 2015 Aaron D. Gerber, P.E. How Does Your Organization Manage Pavement Assets? By Experience/Past Practice? By Customer

More information

DATE: July 14, 2015. Mayor and City Council. Director of Finance. Financing Plan for Measure C-Funded Capital Projects RECOMMENDATION

DATE: July 14, 2015. Mayor and City Council. Director of Finance. Financing Plan for Measure C-Funded Capital Projects RECOMMENDATION 9 DATE: July 14, 2015 TO: FROM: SUBJECT: Mayor and City Council Director of Finance Financing Plan for Measure C-Funded Capital Projects RECOMMENDATION That Council reviews and comments on the proposed

More information

CHELTENHAM TOWNSHIP. SANITARY SEWER UPDATE Public Works Committee Meeting September 7, 2010 Curtis Hall

CHELTENHAM TOWNSHIP. SANITARY SEWER UPDATE Public Works Committee Meeting September 7, 2010 Curtis Hall CHELTENHAM TOWNSHIP SANITARY SEWER UPDATE Public Works Committee Meeting September 7, 2010 Curtis Hall 1 SANITARY SEWER UPDATE 1. Overview a. The Problem b. Pennsylvania Department of Environmental Protection

More information

Three Year Forecast Revenues and Expenditures Enterprise Fund Water & Sewer

Three Year Forecast Revenues and Expenditures Enterprise Fund Water & Sewer $120 $100 $80 $60 $40 $20 Three Year Forecast Revenues and Expenditures Enterprise Fund Water & Sewer 2007 2008 2009 2010 2011 2012 2013 Revenues Expenditures s 2010 through 2013 are estimated. ENTERPRISE

More information

MAIN STREET IMPROVEMENTS Water, Sewer, Stormwater and Streetscape Improvements

MAIN STREET IMPROVEMENTS Water, Sewer, Stormwater and Streetscape Improvements MAIN STREET IMPROVEMENTS Water, Sewer, Stormwater and Streetscape Improvements Presentation July 23, 2014 A. Morton Thomas and Associates, Inc. 800 King Farm Boulevard, 4 th Floor Rockville, Maryland 20850

More information

Kansas City s Overflow Control Program

Kansas City s Overflow Control Program Kansas City s Overflow Control Program Kansas City Water Services Water Wastewater Stormwater 2 Water Services Department 1000 Positions 835 Employees 3 Utilities FY 13/14 Budget = $307 million Water Wastewater

More information

REQUEST FOR PROPOSALS SANITARY SEWER MAINTENANCE SERVICES FOR THE TOWN CENTER SEWER ASSESSMENT DISTRICT WITHIN THE TOWN OF WOODSIDE

REQUEST FOR PROPOSALS SANITARY SEWER MAINTENANCE SERVICES FOR THE TOWN CENTER SEWER ASSESSMENT DISTRICT WITHIN THE TOWN OF WOODSIDE REQUEST FOR PROPOSALS SANITARY SEWER MAINTENANCE SERVICES FOR THE TOWN CENTER SEWER ASSESSMENT DISTRICT WITHIN THE TOWN OF WOODSIDE Submit Proposals to: Town of Woodside Public Works Department 2955 Woodside

More information

2013-2014 ANNUAL REPORT

2013-2014 ANNUAL REPORT 2013-2014 ANNUAL REPORT ALAMEDA COUNTY TRANSPORTATION SERVICES Welcome to Alameda County, Transportation Services second annual sustainability report. This report continues our commitment to environmental

More information

PUBLIC WORKS COMMISSION: PAVING WORK GROUP

PUBLIC WORKS COMMISSION: PAVING WORK GROUP Permeable Interlocking Concrete Pavers (PICP) PUBLIC WORKS COMMISSION: PAVING WORK GROUP IT S NOT ABOUT FILLING POTHOLES ANY MORE ENVIRONMENTALLY SUSTAINABLE INTEGRATED PAVING STRATEGIES FOR THE 21 ST

More information

Pavement Management Program

Pavement Management Program Pavement Management Program 2014 Street Maintenance Program Executive Summary 01/21/2014 Presented by Mark Thiel Assistant Director of Public Works Program Overview Start of current program 2005 825.1

More information

Summary Community Workshop #2 Fruitvale San Antonio Senior Center. Wednesday, April 22, 2009 7:00-9:00 p.m.

Summary Community Workshop #2 Fruitvale San Antonio Senior Center. Wednesday, April 22, 2009 7:00-9:00 p.m. Summary Community Workshop #2 Wednesday, April 22, 2009 7:00-9:00 p.m. Workshop Format and Process The City of Oakland is preparing a Specific Plan that will help define and determine a common vision for

More information

DRAFT MAINTAINING HOUSTON S STREETS REPAIR, REHABILITATION, RECONSTRUCTION. Using the Full Range of Tools for a Challenging Job

DRAFT MAINTAINING HOUSTON S STREETS REPAIR, REHABILITATION, RECONSTRUCTION. Using the Full Range of Tools for a Challenging Job MAINTAINING HOUSTON S STREETS REPAIR, REHABILITATION, RECONSTRUCTION Using the Full Range of Tools for a Challenging Job Report To: TTI Committee May 13, 2014 1 Pavement Management - Suggested Treatments

More information

CITY OF COTTAGE GROVE CAPITAL PROJECTS FUNDS BUDGET SUMMARY FY2008-09 ACTUAL FY2010-11 BUDGET FY2009-10 ACTUAL FY2007-08 ACTUAL FY2011-12 ADOPTED

CITY OF COTTAGE GROVE CAPITAL PROJECTS FUNDS BUDGET SUMMARY FY2008-09 ACTUAL FY2010-11 BUDGET FY2009-10 ACTUAL FY2007-08 ACTUAL FY2011-12 ADOPTED CITY OF COTTAGE GROVE CAPITAL PROJECTS FUNDS BUDGET SUMMARY FUND/DEPARTMENT FY2007-08 FY2008-09 FY2009-10 FY2010-11 BUDGET FY2011-12 ADOPTED Water SDC Fund 412,539 105,533 34,677 27,045 42,160 Street SDC

More information

How Your Business Can Prevent Stormwater Pollution

How Your Business Can Prevent Stormwater Pollution Tips for a Cleaner Bay How Your Business Can Prevent Stormwater Pollution alameda county You Can Prevent Water Pollution! Storm drains flow directly into creeks and the Bay without any treatment. Because

More information

RESOLUTION NO. WHEREAS, the 2016-2017 City Budget Forecast estimates that housing

RESOLUTION NO. WHEREAS, the 2016-2017 City Budget Forecast estimates that housing RESOLUTION NO. WHEREAS, the 2016-2017 City Budget Forecast estimates that housing (21.6 percent) and transportation (14.9 percent) are the two largest expense categories for the typical Austin family;

More information

Examples of Eligible Projects. Project Category Description Examples

Examples of Eligible Projects. Project Category Description Examples Examples of Eligible Projects Public Transit Local Roads, Bridges, and Active Transportation Regional and Local Airports which supports a shared passenger transport system which is available for public

More information

2012 2016 Capital Improvement Plan City of Houston WASTEWATER TREATMENT FACILITIES

2012 2016 Capital Improvement Plan City of Houston WASTEWATER TREATMENT FACILITIES 2012 2016 Capital Improvement Plan City of Houston WASTEWATER TREATMENT FACILITIES 2012 2016 Capital Improvement Plan City of Houston WASTEWATER TREATMENT FACILITIES The Wastewater Treatment System (System)

More information

2015 Utility Rates. Electric Garbage Recycling Sanitary Sewer Storm Sewer Water and Yard Waste

2015 Utility Rates. Electric Garbage Recycling Sanitary Sewer Storm Sewer Water and Yard Waste 2015 Utility Rates Electric Garbage Recycling Sanitary Sewer Storm Sewer Water and Yard Waste This document contains only utility rates as adopted by Council Ordinance No. 730 on December 14, 2014. These

More information

REQUEST FOR PROPOSALS (RFP) FOR FINANCIAL AUDIT SERVICES

REQUEST FOR PROPOSALS (RFP) FOR FINANCIAL AUDIT SERVICES REQUEST FOR PROPOSALS (RFP) FOR FINANCIAL AUDIT SERVICES Issued by: City of Clewiston 115 W. Ventura Avenue Clewiston, Florida 33440 September 30, 2015 1 REQUEST FOR PROPOSALS FOR FINANCIAL AUDIT SERVICES

More information

Monterey Regional Water Pollution Control Agency. Sewer System Management Plan

Monterey Regional Water Pollution Control Agency. Sewer System Management Plan Monterey Regional Water Pollution Control Agency Sewer System Management Plan March 31, 2013 Sewer System Management Plan Introduction I. Goals II. Organization III. Legal Authority IV. Operation and Maintenance

More information

EAST BAY REGIONAL SEWER PROGRAM

EAST BAY REGIONAL SEWER PROGRAM EAST BAY REGIONAL PRIVATE SEWER LATERAL PROGRAM The East Bay Regional Private Sewer Lateral Program is a joint effort to protect San Francisco Bay. This guidebook explains the program and provides guidelines

More information

BEFORE THE PHILADELPHIA WATER, SEWER AND STORMWATER RATE BOARD DIRECT TESTIMONY OF STEPHEN J. FURTEK

BEFORE THE PHILADELPHIA WATER, SEWER AND STORMWATER RATE BOARD DIRECT TESTIMONY OF STEPHEN J. FURTEK BEFORE THE PHILADELPHIA WATER, SEWER AND STORMWATER RATE BOARD Re Application of the Philadelphia Water Department for Increased Rates and Related Charges Fiscal Years 2017-2018 DIRECT TESTIMONY OF STEPHEN

More information

CITY OF PACIFIC GROVE 300 Forest Avenue, Pacific Grove, California 93950 AGENDA REPORT

CITY OF PACIFIC GROVE 300 Forest Avenue, Pacific Grove, California 93950 AGENDA REPORT Agenda No. 13A Page 1 of 2 CITY OF PACIFIC GROVE 300 Forest Avenue, Pacific Grove, California 93950 AGENDA REPORT TO: FROM: Honorable Mayor and Members of City Council Robert Huitt, Councilmember and Thomas

More information

Office of the City Manager INFORMATION CALENDAR December 15, 2015

Office of the City Manager INFORMATION CALENDAR December 15, 2015 Office of the City Manager To: From: Honorable Mayor and Members of the City Council Dee Williams-Ridley, Interim City Manager Submitted by: Savita Chaudhary, Director, Information Technology Subject:

More information

TOWN OF HILLSBOROUGH Compliance with Regulatory Mandates. Private Sewer Lateral Inspection and Repair Program

TOWN OF HILLSBOROUGH Compliance with Regulatory Mandates. Private Sewer Lateral Inspection and Repair Program TOWN OF HILLSBOROUGH Compliance with Regulatory Mandates Private Sewer Lateral Inspection and Repair Program SEWER SYSTEM- BACKGROUND 116 miles of gravity sanitary sewer pipelines 1 mile of force main

More information

Sanitary Sewer Overflows Response to EPA Rule Making

Sanitary Sewer Overflows Response to EPA Rule Making Massachusetts Water Resources Authority Sanitary Sewer Overflows Response to EPA Rule Making October 15, 2010 MASSACHUSETTS WATER RESOURCES AUTHORITY SUMMARY OF EPA RULE MAKING SUMMARY OF MWRA, ADVISORY

More information

Financial Planning and Community Investment

Financial Planning and Community Investment Financial Planning and Community Investment Background Materials Provided for Discussion City Council Study Session Feb 2, 2016 Study Session The City s Roles and Responsibilities In 1965, the City was

More information

Billy Cobb, Jr. Columbus Water Works October 23, 2015

Billy Cobb, Jr. Columbus Water Works October 23, 2015 Billy Cobb, Jr. Columbus Water Works October 23, 2015 Agenda 1. A Little About CWW 2. Sustainability 3. The Importance of Planning 4. CWW Planning 5. CWW Planning Implementation Columbus Water Works Provides

More information

Presentation of DISTRICT OF HOUSTON. 2010 TO 2014 Financial Plan

Presentation of DISTRICT OF HOUSTON. 2010 TO 2014 Financial Plan Presentation of DISTRICT OF HOUSTON 2010 TO 2014 Financial Plan What is a Financial Plan? Why? 1) Prudent Planning! 2) Legal Requirement, Community Charter (s165 & s166) First year of the plan is the budget

More information

The Council of the City of New York. Economic Development Corporation

The Council of the City of New York. Economic Development Corporation Hon. Melissa Mark-Viverito Speaker of the Council Hon. Julissa Ferreras Chair, Committee on Finance Hon. Daniel R. Garodnick Chair, Committee on Economic Development The Council of the City of New York

More information

BOLINAS COMMUNITY PUBLIC UTILITY DISTRICT

BOLINAS COMMUNITY PUBLIC UTILITY DISTRICT BOLINAS COMMUNITY PUBLIC UTILITY DISTRICT SEWER SYSTEM MANAGEMENT PLAN DEVELOPMENT PLAN AND SCHEDULE GOALS AND ORGANIZATION INTERIM DOCUMENT April 2008 TABLE OF CONTENTS List of Tables... 4 List of Figures...

More information

{ { { Meeting Date 08/03/10. City of Largo Agenda Item 24. Leland Dicus, P.E., City Engineer

{ { { Meeting Date 08/03/10. City of Largo Agenda Item 24. Leland Dicus, P.E., City Engineer City of Largo Agenda Item 24 Form Revision Date: 10/19/09: Meeting Date 08/03/10 Presenter: Leland Dicus, P.E., City Engineer Department: CD Community Development TITLE: GIS PROGRAM UPDATE The implementation

More information

Request for Proposals July 13, 2015

Request for Proposals July 13, 2015 Maintenance and Skilled Trades Division Request for Proposals July 13, 2015 District Wide Pavement Assessment The East Bay Regional Park District ( District ) is soliciting proposals from consultants to

More information

Financial Business Plan SWAC Meeting 3 April 23, 2009

Financial Business Plan SWAC Meeting 3 April 23, 2009 Financial Business Plan SWAC Meeting 3 April 23, 2009 5 Year Business Plan Highlights Recommendation: 5 year rate plan. Why: Rates increase each year. Minimize costs in early years. Gradually build funding

More information

PUBLIC FACILITIES ELEMENT SANITARY SEWER SUBELEMENT. Provide an Environmentally Sound Sanitary Sewer System

PUBLIC FACILITIES ELEMENT SANITARY SEWER SUBELEMENT. Provide an Environmentally Sound Sanitary Sewer System PUBLIC FACILITIES ELEMENT SANITARY SEWER SUBELEMENT GOAL 1: Ensure that the City's sanitary sewer system will provide an effective, efficient and environmentally sound method of wastewater collection,

More information

M E M O R A N D U M. Among the standard conditions contained in the NPDES permit is also a Duty to

M E M O R A N D U M. Among the standard conditions contained in the NPDES permit is also a Duty to M E M O R A N D U M DATE: August 7, 2015 TO: FROM: SUBJECT: Metropolitan Wastewater Management Commission (MWMC) Matt Stouder, MWMC General Manager Capacity Management, Operations, and Maintenance (CMOM)

More information

City of Santa Ana. FY 2014/2015 Capital Improvement Program. Broadway/Anahurst to 1 st Improvements. First Street Bridge Replacement

City of Santa Ana. FY 2014/2015 Capital Improvement Program. Broadway/Anahurst to 1 st Improvements. First Street Bridge Replacement Broadway/Anahurst to 1 st Improvements First Street Bridge Replacement MacArthur Rehabilitation/Bristol to Flower Fisher Park Butterfly Garden Improvements 1 Finance, PRCSA, CDA and PWA Data Gathering

More information

Description of Fund Types and Funds

Description of Fund Types and Funds Financial activities for local government fall into three broad categories, governmental, proprietary, and fiduciary fund categories. Governmental funds are used to account for activities primarily supported

More information

Unauthorized Discharges and Sanitary Sewer Overflows

Unauthorized Discharges and Sanitary Sewer Overflows TCEQ REGULATORY GUIDANCE Field Operations Support Division RG-395 Revised April 2011 Unauthorized Discharges and Sanitary Sewer Overflows What does this document cover? The Texas Commission on Environmental

More information

GAS TAX FUND CATEGORIES WITH EXAMPLES

GAS TAX FUND CATEGORIES WITH EXAMPLES GAS TAX FUND CATEGORIES WITH EXAMPLES PROJECT CATEGORY DESCRIPTION OUTCOME EXAMPLES Local Roads, Bridges Roads, bridges and New roads and rehabilitation of existing roads and Active active transportation

More information

City of Friendswood FY 2010 Capital Improvements Program - Water & Sewer Projects 5-Year CIP

City of Friendswood FY 2010 Capital Improvements Program - Water & Sewer Projects 5-Year CIP City of Friendswood FY 2010 Capital Improvements Program - Water & Sewer Projects 5-Year CIP PROJECT ESTIMATED COST ESTIMATED COUNCIL IDENTIFIED FUNDING SOURCES STRATEGIC COMPLETION INITIATIVES FM 2351/Beamer

More information

Wastewater Treatment - How to Reduce FOG in Dallas, Texas

Wastewater Treatment - How to Reduce FOG in Dallas, Texas Cease the Grease Background Implementation in 2005 To reduce FOG entering the wastewater system Enforcement Education Public Outreach Goals Reduce Environmental Impact Pollution Prevention Cost Savings

More information

Executive Summary Consent Decree

Executive Summary Consent Decree OVERFLOW ABATEMENT PROGRAM Executive Summary Consent Decree The sewer system in Nashville dates back to the late 1800s and originally consisted of a combined sewer system, later transitioning to separate

More information

The Southwest Florida Water Management District (District) does not discriminate on the basis of disability. This nondiscrimination policy involves

The Southwest Florida Water Management District (District) does not discriminate on the basis of disability. This nondiscrimination policy involves Southwest Florida Water Management District Fiscal Year 2011 2012 through Fiscal Year 2015 2016 Five-Year Capital Improvements Plan (As required by Section 373.536(6)(a)3, Florida Statutes) n e td m e

More information

How Your Vehicle Service Facility Can Prevent Stormwater Pollution

How Your Vehicle Service Facility Can Prevent Stormwater Pollution TIPS FOR A CLEANER BAY How Your Vehicle Service Facility Can Prevent Stormwater Pollution alameda county YOU CAN PREVENT WATER POLLUTION! Storm drains flow directly into creeks and the Bay without any

More information

PUBLIC WORKS DEPARTMENT STRATEGIC PLAN 2015 2020

PUBLIC WORKS DEPARTMENT STRATEGIC PLAN 2015 2020 PUBLIC WORKS DEPARTMENT STRATEGIC PLAN 2015 2020 1 Purpose of Strategic Plan This document serves as the road map for the Public Works Department. It identifies where we are going and how we are going

More information

City of Chula Vista. Fiscal Year 2016 2017. Proposed Budget Overview. May 9 and 18, 2016

City of Chula Vista. Fiscal Year 2016 2017. Proposed Budget Overview. May 9 and 18, 2016 City of Chula Vista Fiscal Year 2016 2017 Proposed Budget Overview May 9 and 18, 2016 Agenda Fiscal Year 2016 17 Proposed Budget All Funds Summary General Fund Summary Long Term Financial Plan Fiscal Year

More information

M I N U T E S 2015 BUDGET AND TAX LEVY PUBLIC HEARING DECEMBER 2, 2014 6:00 P.M. COUNCIL CHAMBERS

M I N U T E S 2015 BUDGET AND TAX LEVY PUBLIC HEARING DECEMBER 2, 2014 6:00 P.M. COUNCIL CHAMBERS M I N U T E S 2015 BUDGET AND TAX LEVY PUBLIC HEARING DECEMBER 2, 2014 6:00 P.M. COUNCIL CHAMBERS MEMBERS PRESENT: MEMBERS ABSENT: OTHERS PRESENT: Mayor Stiehm, Council Members Boughton, Enright, Carolan,

More information

INTRODUCTION. WASTEWATER MANAGEMENT PLAN MAY 2009 Metropolitan North Georgia Water Planning District 7-1

INTRODUCTION. WASTEWATER MANAGEMENT PLAN MAY 2009 Metropolitan North Georgia Water Planning District 7-1 INTRODUCTION There are approximately 16,000 miles of sewers and more than 450,000 manholes within the Metro Water District. Sewers and manholes within the Metro Water District range in age from new to

More information

5-Year CIP Period: Projects by Function

5-Year CIP Period: Projects by Function s by Function Does not include specific non-county managed programs such as Northern Virginia Regional Park Authority and the Water Authority Community Development - Action Plan Review Team (APRT) - Amenity

More information

The InSinkErator City of Philadelphia. How Food Waste Disposers Can Benefit Municipalities

The InSinkErator City of Philadelphia. How Food Waste Disposers Can Benefit Municipalities The InSinkErator City of Philadelphia P R O J E C T How Food Waste Disposers Can Benefit Municipalities BACKGROUND The InSinkErator City of Philadelphia P R O J E C T How Food Waste Disposers Can Benefit

More information

LA: THE DREAM STARTS HERE BUILDING LOS ANGELES INTO A GLOBAL CAPITAL OF CLEAN TECHNOLOGY

LA: THE DREAM STARTS HERE BUILDING LOS ANGELES INTO A GLOBAL CAPITAL OF CLEAN TECHNOLOGY LA: THE DREAM STARTS HERE BUILDING LOS ANGELES INTO A GLOBAL CAPITAL OF CLEAN TECHNOLOGY Mayor s Office of Economic Development Mayor s Office of Energy & Environment Office of Mayor Antonio R. Villaraigosa

More information

ACTION CALENDAR May 17, 2011

ACTION CALENDAR May 17, 2011 Office of the City Manager ACTION CALENDAR May 17, 2011 To: Honorable Mayor and Members of the City Council From: Phil Kamlarz, City Manager Submitted by: William Rogers, Director, Parks Recreation & Waterfront

More information

M I D W E S T S O C I E T Y F O R T R E N C H L E S S T E C H N O L O G Y. Kansas City, Missouri s Trenchless Program

M I D W E S T S O C I E T Y F O R T R E N C H L E S S T E C H N O L O G Y. Kansas City, Missouri s Trenchless Program M I D W E S T S O C I E T Y F O R T R E N C H L E S S T E C H N O L O G Y Kansas City, Missouri s Trenchless Program Outline of Presentation Intro to Kansas City Water Services information Trenchless Program

More information

METROPOLITAN REDEVELOPMENT PLAN II OLD ALBUQUERQUE HIGH SCHOOL

METROPOLITAN REDEVELOPMENT PLAN II OLD ALBUQUERQUE HIGH SCHOOL METROPOLITAN REDEVELOPMENT PLAN II OLD ALBUQUERQUE HIGH SCHOOL Preface This revised plan for redevelopment of the Old Albuquerque High School Metropolitan Redevelopment Area has been prepared pursuant

More information

Sewer System Management Plan University of California Kearney Agricultural Research & Extension Center 9240 S. Riverbend Ave.

Sewer System Management Plan University of California Kearney Agricultural Research & Extension Center 9240 S. Riverbend Ave. Sewer System Management Plan University of California Kearney Agricultural Research & Extension Center 9240 S. Riverbend Ave. Parlier, CA 93648 Wastewater ID # 5SSO11453 1 Goals 1.1 Regulatory Requirements

More information

Mayors Welcome Strong Surrey Votes Yes Coalition Support. Yes Vote Would Vastly Improve Transit and Transportation in Fast Growing City

Mayors Welcome Strong Surrey Votes Yes Coalition Support. Yes Vote Would Vastly Improve Transit and Transportation in Fast Growing City Mayors Welcome Strong Surrey Votes Yes Coalition Support Yes Vote Would Vastly Improve Transit and Transportation in Fast Growing City February 11, 2015 Vancouver, BC The Mayors Council on Regional Transportation

More information

A Systematic Approach to Reduce Infiltration and Inflow (I&I) and Sanitary Sewer Overflows (SSO) PETE GORHAM, P.E. MIKE LYNN FEBRUARY 19, 2015

A Systematic Approach to Reduce Infiltration and Inflow (I&I) and Sanitary Sewer Overflows (SSO) PETE GORHAM, P.E. MIKE LYNN FEBRUARY 19, 2015 A Systematic Approach to Reduce Infiltration and Inflow (I&I) and Sanitary Sewer Overflows (SSO) PETE GORHAM, P.E. MIKE LYNN FEBRUARY 19, 2015 Infiltration/Inflow (I/I) I & I Reduction: Three-Prong Attack

More information

FY 2012 & FY 2013 Proposed Balancing Measures. March 22, 2010

FY 2012 & FY 2013 Proposed Balancing Measures. March 22, 2010 FY 2012 & FY 2013 Proposed Balancing Measures March 22, 2010 1 Introduction National Economic Recovery - Slow General Fund - FY 12 ($3M) FY 13 ($4M) Special Funds ($9.5M) Federal Budget proposed cuts to

More information

TRANSPORTATION Carson Howell, Analyst

TRANSPORTATION Carson Howell, Analyst State of Utah FY 2008 Budget Recommendations Carson Howell, Analyst AGENCY BUDGET OVERVIEW Mission: Build and maintain the State s transportation system, plan and implement new highway projects, improve

More information

Transportation Infrastructure Asset Management

Transportation Infrastructure Asset Management 2015 NW Region TTAP& BIA Symposium Transportation Infrastructure Asset Management March, 2015 Happy Longfellow, PE hlongfellow@parametrix.com (206) 394-3649 ASSET MANAGEMENT OVERVIEW What? Why? How? Inventory

More information

CID STREET INFRASTRUCTURE ASSESSMENT

CID STREET INFRASTRUCTURE ASSESSMENT ABSTRACT An evaluation of the street infrastructure in Foxberry Estates Phase 1, including pavement condition, verification of construction techniques, and subgrade quality. Recommendations and costs for

More information

Division of Water Resource Management Report: A-1112DEP-058

Division of Water Resource Management Report: A-1112DEP-058 Review of Revenues and Expenditures for the City of Apalachicola Clean Water State Revolving Fund Debt Purchase Agreement Division of Water Resource Management Report: A-1112DEP-058 Office of Inspector

More information

Asset Management for MAP-21. Gary Lasham, P.E. Jonathan Pollack

Asset Management for MAP-21. Gary Lasham, P.E. Jonathan Pollack Asset Management for MAP-21 Gary Lasham, P.E. Jonathan Pollack Replaced Intermodal Surface Transportation Efficiency Act (ISTEA) MAP-21 is transforming the policy and programmatic framework for investments

More information

Village of St. Louis Sewer Back-up Policy

Village of St. Louis Sewer Back-up Policy Village of St. Louis Sewer Back-up Policy The Village of St. Louis is responsible for maintaining sewer mains and manholes, which are located in public rights-of-way (Village and Provincial maintained

More information

HIGHWAYS AND PUBLIC IMPROVEMENTS DEPARTMENT

HIGHWAYS AND PUBLIC IMPROVEMENTS DEPARTMENT HIGHWAYS AND PUBLIC IMPROVEMENTS DEPARTMENT 181 182 PUBLIC WORKS 183 PUBLIC WORKS PLANNING PERIOD: FY2010-11 THROUGH FY2014-15 FISCAL BUDGET PLANNING YEAR: FY2012-13 FUND: General Fund COST CENTER NUMBER

More information

The Corporation of the City of Nelson

The Corporation of the City of Nelson The Corporation of the City of Nelson Agenda 1. Introduction 2. Council Priorities & Strategic Direction 3. 2012 2016 Financial Plan Process 4. Proposed 2012 2016 Financial Plan Presentation 5. City Assets/Reserves/Debt

More information

Office of Environment, Health and Safety (EH&S) - Sanitary Sewer Overflow Incident Form (rev. 12/2014)

Office of Environment, Health and Safety (EH&S) - Sanitary Sewer Overflow Incident Form (rev. 12/2014) STEP 1 Immediately call EH&S at (510) 642-3073 with the following details of the incident: Name of First Responder Phone Number of First Responder Location of Spill Is the spill potentially greater than

More information

Sales and Use Tax Exclusion for CA Manufacturers and other financing programs

Sales and Use Tax Exclusion for CA Manufacturers and other financing programs Sales and Use Tax Exclusion for CA Manufacturers and other financing programs California Alternative Energy & Advanced Transportation Financing Authority CAEATFA State Treasurer s Office 915 Capitol Mall,

More information

CITY OF SAN JOSE 2015-2016 PROPOSED OPERATING BUDGET FUND DESCRIPTIONS

CITY OF SAN JOSE 2015-2016 PROPOSED OPERATING BUDGET FUND DESCRIPTIONS Airport Capital s CITY OF SAN JOSE These Enterprise s account for the Airport s capital expenditures and revenues and consist of the following: Airport Capital Improvement ; Airport Revenue Bond Improvement

More information

FISCAL YEAR 2014-2018 CAPITAL IMPROVEMENT PLAN WASTEWATER TREATMENT FACILITIES

FISCAL YEAR 2014-2018 CAPITAL IMPROVEMENT PLAN WASTEWATER TREATMENT FACILITIES FISCAL YEAR 2014-2018 CAPITAL IMPROVEMENT PLAN WASTEWATER TREATMENT FACILITIES 1 FISCAL YEAR 2014-2018 CAPITAL IMPROVEMENT PLAN Wastewater Treatment Facilities The Wastewater Treatment System (System)

More information

City of Sacramento, California Department of Utilities. March 2011

City of Sacramento, California Department of Utilities. March 2011 Department of Utilities Utility Rate Study March 2011 March, 2011 page i TABLE OF CONTENTS EXECUTIVE SUMMARY... 3 SECTION I: INTRODUCTION... 13 SECTION II: FINANCIAL POLICIES... 15 A. Defining Revenue

More information

Center for Sustainable Business Growth

Center for Sustainable Business Growth Center for Sustainable Business Growth Progress Report; December 2014 Bridgeport Eco-Technology Park The south and west ends of Bridgeport, where the Eco-Technology Park resides, have been the home of

More information

TOWN OF SURFSIDE UTILITY UPGRADE PROJECT Project Completion

TOWN OF SURFSIDE UTILITY UPGRADE PROJECT Project Completion TOWN OF SURFSIDE UTILITY UPGRADE PROJECT Project Completion Project Overview Sanitary Sewer System 2 Town of Surfside Project Overview Potable Water System 3 Town of Surfside Project Overview Storm Water

More information

The City of Owen Sound Asset Management Plan

The City of Owen Sound Asset Management Plan The City of Owen Sound Asset Management Plan December 013 Adopted by Council March 4, 014 TABLE OF CONTENTS 1 EXECUTIVE SUMMARY... 1 INTRODUCTION....1 Vision.... What is Asset Management?....3 Link to

More information

Work Practice: Wastewater Collection System Maintenance Plan Potential Safety Hazards

Work Practice: Wastewater Collection System Maintenance Plan Potential Safety Hazards Potential Safety Hazards Required items Potential PPE None Additional References - Collection System Related Work Practices & Forms Jet Truck Cleaning Work Practice (Do not drive on peoples driveway) CDL

More information

Pavement Management Office

Pavement Management Office Department of Transportation and Public Works Puerto Rico Pavement Management Office PAVEMENT PRESERVATION SEPPP 1 GOALS AND OBJECTIVES PRHTA has been collecting data for more than twenty (20) years with

More information

TOWN OF ALTONA 2016 FINANCIAL PLAN

TOWN OF ALTONA 2016 FINANCIAL PLAN TOWN OF ALTONA 2016 FINANCIAL PLAN Town of Altona 2016 Financial Plan Page 1 of 21 April 11, 2016 TOWN OF ALTONA 2016 FINANCIAL PLAN Executive Summary Municipal Taxes The enclosed budget documentation

More information

LETTER OF INTENT Measure A is the ten-year half-cent general sales tax approved by the voters in November 2012. Measure A funds projects that:

LETTER OF INTENT Measure A is the ten-year half-cent general sales tax approved by the voters in November 2012. Measure A funds projects that: LETTER OF INTENT Measure A is the ten-year half-cent general sales tax approved by the voters in November 2012. Measure A funds projects that: Are consistent with the needs identified in the text for Measure

More information

STORM DRAIN PIPE MAINTENANCE. a. Develop standard operating procedures for maintaining storm drain pipes.

STORM DRAIN PIPE MAINTENANCE. a. Develop standard operating procedures for maintaining storm drain pipes. STORM DRAIN PIPE MAINTENANCE a. Develop standard operating procedures for maintaining storm drain pipes. 2. PROCESS Storm drain pipes are to be maintained per the Storm Water System Maintenance Plan schedule.

More information

Solid Waste Management

Solid Waste Management LOB #357: TRANSFER STATION OPERATIONS Purpose Approximately 70 percent of the municipal solid waste collected in the County for disposal is delivered to the I-66 Transfer Station. The Transfer Station

More information

in Marina Del Rey Prepared by: County of Los Angeles Department of Public Works

in Marina Del Rey Prepared by: County of Los Angeles Department of Public Works Planned Public Works Projects in Marina Del Rey Prepared by: County of Los Angeles Department of Public Works Planned Projects in Marina Del Rey Waterline Projects Phase II Phase III Roadway Projects Admiralty

More information

FY 2011 OHIO SMALL CITIES COMMUNITY DEVELOPMENT BLOCK GRANT COMPREHENSIVE DOWNTOWN REVITALIZATION PROGRAM

FY 2011 OHIO SMALL CITIES COMMUNITY DEVELOPMENT BLOCK GRANT COMPREHENSIVE DOWNTOWN REVITALIZATION PROGRAM CITYOFOBERLIN OHIO CITY OF OBERLIN, OHIO FY 2011 OHIO SMALL CITIES COMMUNITY DEVELOPMENT BLOCK GRANT COMPREHENSIVE DOWNTOWN REVITALIZATION PROGRAM Background In October, 2011, the City of Oberlin Planning

More information

Holiday Island Suburban Improvement District 2011-2015 Capital Improvements Program Comprehensive Detail Schedule

Holiday Island Suburban Improvement District 2011-2015 Capital Improvements Program Comprehensive Detail Schedule 2011-2015 Capital Improvements Program Comprehensive Detail Schedule Final Approved Revenue Fund Projects Administration Fire-Proof Records Storage $ $ 10,000 $ $ $ $ 10,000 D.O. Roof Shingle Replacement

More information

Waste Handling & Disposal

Waste Handling & Disposal Objectives Cover Contain Educate Reduce/Minimize Product Substitution Description Improper storage and handling of solid wastes can allow toxic compounds, oils and greases, heavy metals, nutrients, suspended

More information