1 US 95 Northwest Corridor 2014 Financial Plan Annual Update As of December 31, 2014 Submitted March 31, 2015 US 95 Northwest Corridor Clark County, Nevada

2

3 US 95 Northwest Corridor 2014 Financial Plan Annual Update Prepared for Nevada Department of Transportation As of December 31, 2014

4 This page is left intentionally blank

5 I-15 SOUTH CORRIDOR IMPROVEMENTS 2014 FINANCIAL PLAN ANNUAL UPDATE Table of Contents 1. Project Description... 1 Project Purpose... 2 Project Phases Project Schedule Project Cost Cost Estimating Methodology Escalation Project Funds Federal Funds State Funds Local Funds Financing Issues Cash Flow Phase 2A Phase 2B Phase 3A Phase 3B Phase 3C Phase 3D Phase 3E Phase Total Project P3 Assessment Risk and Response Strategies Annual Update Cycle Summary of Cost Changes since Last Year s Financial Plan Cost and Funding Trends since the Initial Financial Plan Summary of Schedule Changes since Last Year s Financial Plan Schedule Trends since the Initial Financial Plan Appendix A Letter of Certification iii

6 I-15 SOUTH CORRIDOR IMPROVEMENTS 2014 FINANCIAL PLAN ANNUAL UPDATE Appendix B Financial Plan Checklist Appendix C Funding Documents Appendix D NDOT Programming Papers (PSAMS) US 95 Northwest Corridor Environmental Phase Phase Phase 2A Phase Phase 3A Phase Appendix E Phase 3 Sub-Phase Graphics Appendix F 2014 Cost Risk Assessment Workshop Update Exhibits/Tables Exhibit 1 Project Location... 1 Table 1 Project Schedule... 6 Table 2 Project Schedule Comparison... 7 Table 3 Total Project Cost by Cost Element... 9 Table 4 Cost Comparison by Cost Element Table 5 Escalation Rates Exhibit 2 US 95 Northwest Corridor Funding Share by Source, Millions ($ s) Table 6 Programmed Funding in Millions ($ s) Exhibit 3 Phase 2A Interchange Annual and Cumulative Cash Flow (Millions $ s) Exhibit 4 Phase 2B Annual and Cumulative Cash Flow (Millions $ s) Exhibit 5 Phase 3A Annual and Cumulative Cash Flow (Millions $ s) Exhibit 6 Phase 3B Annual and Cumulative Cash Flow (Millions $ s) Exhibit 7 Phase 3C Annual and Cumulative Cash Flow (Millions $ s) Exhibit 8 Phase 5 Annual and Cumulative Cash Flow (Millions $ s) Exhibit 9 US 95 Northwest Corridor Cost and Funding History Exhibit 10a US 95 Northwest Corridor Construction Schedule History Exhibit 10b US 95 Northwest Corridor Construction Schedule History iv

7 I-15 SOUTH CORRIDOR IMPROVEMENTS 2014 FINANCIAL PLAN ANNUAL UPDATE Acronyms and Abbreviations: AASHTO American Association of State way and Transportation Officials AU Financial Plan Annual Update BLM Bureau of Land Management CRA Cost Risk Assessment CN Construction FEIS Final Environmental Statement FHWA Federal way Administration FONSI Finding of No Significant IFP Initial Financial Plan NDOT Nevada Department of Transportation NDOW Nevada Department of Wildlife NEPA National Environmental Policy Act of 1969 PE Preliminary Engineering PMP Project Management Plan PPDM Project Development and Design Manual PS&E Plans, Specifications, and Estimates Reclamation U.S. Bureau of Reclamation ROD Record of Decision ROW Right-of-Way RR Railroad RTC Regional Transportation Commission of Southern Nevada RTP Regional Transportation Plan US 95 US way 95 USFWS U.S. Fish and Wildlife Service VE Value Engineering YOE Year-of-Expenditure v

8 I-15 SOUTH CORRIDOR IMPROVEMENTS 2014 FINANCIAL PLAN ANNUAL UPDATE This page is left intentionally blank vi

9 US 95 NORTHWEST CORRIDOR 2014 FINANCIAL PLAN ANNUAL UPDATE 1. Project Description The US 95 Northwest Corridor from Washington Avenue to Kyle Canyon Road is one of the fastest growing areas in southern Nevada. The US 95 freeway facility links urbanized Las Vegas on the south to rural Clark County and the Paiute Indian Reservation to the north. It serves heavy regional commuter demands between predominately residential areas in northwest Las Vegas and large employment centers in downtown Las Vegas and the Las Vegas resort corridor. This highway also serves as the only major transportation link between Las Vegas and the Toiyabe National Forest, commonly referred to as Mount Charleston. Mount Charleston serves a dual role as a small community and as a getaway for southern Nevadans, attracting thousands of vehicles every weekend. The project area, located within Clark County, Nevada, extends on US 95 from Washington Avenue to Kyle Canyon Road, a distance of approximately 13 miles, as shown in Exhibit 1. DURANGO DRIVE Exhibit 1 Project Location 1

10 US 95 NORTHWEST CORRIDOR 2014 FINANCIAL PLAN ANNUAL UPDATE Project Purpose The purpose of the project is to relieve congestion and improve the operational characteristics of the US 95 Northwest Corridor in response to continued and proposed development and the resultant traffic growth in the Las Vegas Valley. The proposed improvements to US 95 will: Accommodate projected local traffic; Decrease congestion; Reduce travel times; Improve access to areas planned for development; Improve freeway operations; Improve safety; Meet stakeholder/public expectations; Reduce vehicle emissions; Reduce idling; Beautify the corridor; and Improve driver comfort. Project Phases The US 95 Northwest Corridor Project improvements have been subdivided into five phases for construction, consistent with the timing of the anticipated need for improvements. The project limits of these phases and the proposed improvements are as follows: Phase 1 Washington Avenue to Ann Road Construction was completed on Phase 1 in July This project phase: widened US 95 from 3 general purpose lanes in each direction to accommodate 1 HOV ( Occupancy Vehicle) and auxiliary lanes in each direction from Washington Avenue to Ann Road; widened the Gowan Road grade separation; constructed tieback walls at the grade separations; improved operations at Cheyenne Avenue interchange by constructing a loop ramp to accommodate the heavy westbound Cheyenne Avenue to southbound US 95 demand; improved operations at Durango Drive interchange by constructing a loop ramp to accommodate the heavy westbound Durango Drive to southbound US 95 demand; and constructed drainage, noise walls, lighting, signing, Intelligent Transportation Systems (ITS) facilities, landscape and aesthetic features. Phase 2 Ann Road to Kyle Canyon Road The Phase 2 improvements will be constructed within the existing US 95 right-of-way. Phase 2 has been divided into two separate contracts for construction: Phase 2A - Widen US 95 from Ann Road to Durango Drive Widening US 95 from 3 general purpose lanes in each direction to accommodate 1 HOV lane and auxiliary lanes in each direction from Ann Road to Centennial Parkway; 2

11 US 95 NORTHWEST CORRIDOR 2014 FINANCIAL PLAN ANNUAL UPDATE Widening US 95 from 2 general purpose lanes in each direction to accommodate 1 additional general purpose lane, 1 HOV lane and auxiliary lanes in each direction from Centennial Parkway to Durango Drive; Constructing sound walls in noise sensitive areas; Perpetuating drainage, lighting, signing and ITS improvements; Improving landscape and aesthetic features; and Relocating utilities as necessary. Phase 2B - Widen US 95 from Durango Drive to Kyle Canyon Road. Widening US 95 from 2 general purpose lanes in each direction to accommodate 1 additional general purpose lane and auxiliary lanes in each direction from Durango Drive to Kyle Canyon Road; Constructing sound walls in noise sensitive areas; Perpetuating drainage, lighting, signing and ITS improvements; Improving landscape and aesthetic features; and Relocating utilities as necessary. Constructing a new park-and-ride facility in the southwest quadrant of the US 95/Durango Drive interchange as needed Phase 3 US 95/CC-215 Northern Beltway Interchange Phase 3 improvements will be constructed within the existing right-of-way of US 95 and CC-215. In order to deliver the project over the next 2-15 years, the project team has developed a phasing plan. This new plan proposes 5 sub-phases or contracts with costs ranging from $13- $75 million dollars per phase. Below describes the scope of work and cost estimate for each proposed sub-phases. Each contract will improve the operations of the interchange incrementally and will have independent utility from the other contracts. See Appendix E for plan sheets showing the individual sub-phases. The contracts will occur in the following order: Phase 3A - This project consists of building three of the major traffic movements through the proposed system to system interchange. To provide operational benefit immediately, it was determined to construct the northbound US 95 to eastbound CC 215 ramp (NE), the westbound CC 215 to southbound US 95 ramp (WS), and improve the eastbound to southbound ramp (ES). This improves flows for high traffic movements and alleviates congestion during peak hours at the existing intersections of CC 215 and Oso Blanca Road and Sky Pointe Drive, just west and east of US 95. A temporary connection for the NE to CC 215 will be needed until the eastbound CC 215 mainline is constructed during Phase 3C. In order to complete the tie-in points of the WS and NE ramps on US 95, this project will include all outside widening of US 95 in both directions between the entrance/exits of the ramps and Ann Road. Additionally the proposed southbound collector distributor (CD) road, the tie back walls on Tropical Parkway/Azure Drive structure, and the widening of the eastbound CC 215 to southbound US 95 ramp at the entrance of US 95 will also be constructed as part of this project. This project will also include the Clark County Regional Flood Control Facility CNWE 0301 and CNWE 0304 along CC-215 from an existing concrete channel (East Tenaya Way) north to US 3

12 US 95 NORTHWEST CORRIDOR 2014 FINANCIAL PLAN ANNUAL UPDATE 95. This will construct approximately 5,500 linear feet of reinforced concrete box storm drain with all appurtenances Phase 3B - In order to complete last three contracts of the system to system interchange, the Kern River Gas Line must be relocated. The gas line is 36 inches in diameter and is pressured to 1,300 psi. It was constructed in 1992 and provides service to Southwest Gas in Las Vegas and many other clients. NDOT has prior rights where the line crosses. The City of Las Vegas and Clark County also have prior rights for short lengths of the pipeline. However, for the majority of the gas line within the project footprint, Kern River has prior rights. The current location of the gas line is impacted by 4 new structures and several feet of added fill that will be located directly above the existing line. Therefore it was determined that by relocating the line further to the north, all conflicts with the new roadway improvements would be eliminated. The total length of newly constructed gas line is approximately 5,100 ft. Phase 3C In this phase, the local access and eastbound CC 215 mainline improvements need to be constructed to minimize costs for temporary improvements for the remaining ramps and maintain local connectivity. Phase 3C will build the eastbound CC 215 mainline from the Grand Montecito structure to west of the Tenaya Way grade separation, the eastbound CC 215 to southbound US 95 (ES), the John Herbert Blvd. interchange, the eastbound frontage road to John Herbert Blvd. (EN), the new Oso Blanca Road alignment, and the connection of the local access on John Herbert Blvd. to Azure Parkway. This connection will require the City of Las Vegas to acquire a small parcel adjacent to the north leg of the Azure/Sky Point Drive intersection. All signing, lighting, and drainage improvements necessary for these improvements will be built as part of this phase. Temporary connections for the westbound on and off ramps to John Herbert will be provided until the completion of the westbound CC 215 in Phase 3E. Once these improvements are constructed, traffic on mainline CC 215 will be shifted to the eastbound mainline, until the construction of the westbound CC 215 mainline is completed in Phase 3E. Phase 3D This phase will construct the remainder of the ramps needed to complete the US 95/CC 215 system to system interchange. These ramps consist of the southbound US 95 to eastbound CC 215 (SE), the eastbound CC 215 to northbound US 95 (ENL), southbound US 95 to westbound CC 215 (SW), and westbound CC 215 to northbound US 95 (WN). Additionally, the westbound frontage road from John Herbert Blvd. interchange to Oso Blanca Road and the northbound US 95 to westbound CC 215 (NW) flyover ramp including the crossing at US 95, will be constructed within this phase. All signing, lighting, and drainage improvements necessary for these improvements will be built as part of this phase. 4

13 US 95 NORTHWEST CORRIDOR 2014 FINANCIAL PLAN ANNUAL UPDATE Phase 3E - All remaining features of the CC 215 will be completed in this phase. This work includes building the westbound CC 215 through the interchange. All signing, lighting, and drainage improvements necessary for these improvements will be built as part of this phase. This phase will also include landscaping and aesthetics for the entire system to system interchange. Phase 4 US 95 at Horse Drive Phase 4 was completed in May This phase: constructed a new service interchange; and constructed drainage, lighting, signing, landscape and aesthetic features and ITS improvements. Phase 5 US 95 at Kyle Canyon Road The Phase 5 improvements will be constructed within the existing US 95 right-of-way and consist of: Constructing a new service interchange; Perpetuating drainage, lighting, signing and ITS improvements; Improving landscape and aesthetic features; and Relocating utilities as necessary. A Re-Evaluation of the Environmental Assessment for US 95 Northwest Washington Avenue to Kyle Canyon project (FHWA-NV-EA 07.01) was completed in December The document was prepared to re-evaluate the changed conditions and determine if the original Environmental Assessment (EA), signed October 4, 2007 and FONSI signed May 7, It was determined that there were no changes in the project scope or general limits and purpose and need remain the same. The current design may eliminates the Park and Ride Facility identified in the EA south of the Durango Interchange. The RTC has built the new Centennial Hills Transit Center and Park and Ride south of the parcel outlined in the EA. The Centennial Hills Transit Center and Park & Ride includes approximately 900 surface parking spaces for cars, transit shelter and transit bays for future express transit service and local routes. The parcel identified by the EA, north of Oso Blanca Road, is no longer needed for the Park-N-Ride Facility.. 2. Project Schedule The overall project, as shown in Table 1, is scheduled to be substantially complete in March The individual element schedules are from the risk-adjusted project 70th percentile schedule after implementing risk response strategies. 5

14 US 95 NORTHWEST CORRIDOR 2014 FINANCIAL PLAN ANNUAL UPDATE Table 1 Project Schedule Task Name Start Finish US 95 Northwest Corridor 10/1/2007 3/31/2029 Environmental Clearance (Completed) 10/1/ /1/2007 Phase 1 - Washington Avenue to Ann Road 8/2/2008 6/30/2013 Design (Completed) 8/2/2008 6/8/2010 Construction (Completed) 6/8/2010 6/30/2013 Phase 2 - Ann Road to Kyle Canyon Road 6/1/2009 6/30/2020 Design - Phase 2A (Completed) 6/1/2009 3/1/2014 Construction - Phase 2A (Under Construction) 3/1/2014 8/31/2015 Design - Phase 2B 7/1/2014 6/30/2016 Construction - Phase 2B 1/1/2019 6/30/2020 Phase 3 - /CC-215 Northern Beltway Interchange 6/1/2009 3/31/2029 Preliminary Design - Phase 3/Final Design Phase 3A 6/1/ /30/2014 Construction - Phase 3A 5/1/2015 5/1/2017 Design - Phase 3B 9/30/ /1/2018 Construction - Phase 3B 10/1/2018 3/31/2020 Design - Phase 3C 9/30/ /1/2021 Construction - Phase 3C 10/1/ /1/2023 Design - Phase 3D 9/30/ /1/2024 Construction - Phase 3D 10/1/ /31/2026 Design - Phase 3E 9/30/ /1/2027 Construction - Phase 3E 10/1/2027 3/31/2029 Phase 4 - at Horse Drive 6/1/2008 5/27/2011 Design (Completed) 6/1/2008 5/31/2009 Construction (Completed) 6/1/2009 5/27/2011 Phase 5 - at Kyle Canyon Road 8/1/2014 5/1/2020 Design 8/1/2014 8/1/2017 Construction 11/1/2018 5/1/2020 6

15 US 95 NORTHWEST CORRIDOR 2014 FINANCIAL PLAN ANNUAL UPDATE A comparison of the project schedules from the 2009 Initial Financial Plan through the Annual Updates are shown in Table 2. Table 2 Project Schedule Comparison Activity Name 2009 Initial Financial Plan 2010 Annual Update 2011 Annual Update 2012 Annual Update 2013 Annual Update 2014 Annual Update Start Finish Start Finish Start Finish Start Finish Start Finish Start Finish Finding of No Significant (FONSI) 10/ / / / / / / / / / / /2007 Phase 1 - Washington Avenue to Ann Road Design 8/2008 8/2010 8/2008 8/2010 8/2008 6/2010 8/2008 6/2010 8/2008 6/2010 Construction FY 2011 FY /2010 9/2012 8/2010 9/2012 6/2010 7/2013 6/2010 7/2013 6/2010 7/2013 Phase 2 - Ann Road to Kyle Canyon Road Design 6/2009 6/2012 6/2009 6/2012 6/ /2013 6/2009 6/2016 Construction FY 2026 FY / /2030 6/ / /2013 6/2015 Design - Phase 2A 6/2009 3/2014 Construction - Phase 2A 3/2014 8/2015 3/2014 8/2015 Design - Phase 2B 7/2014 6/2016 Construction - Phase 2B 1/2019 6/2020 1/2019 6/2020 Phase 3 - /CC-215 Northern Beltway Interchange Design 6/2009 6/2012 6/2009 6/2012 6/2009 6/2012 6/2009 9/2015 Construction FY 2012 FY / /2013 Design - Phase 3A 6/ /2014 Construction - Phase 3A 2/2013 1/2015 2/2013 1/ /2015 9/2017 5/2015 5/2017 Design - Phase 3B 9/ /2018 Construction - Phase 3B 10/2018 3/ /2018 3/2020 Design - Phase 3C 9/ /2021 Construction - Phase 3C 1/2015 1/2017 1/2015 1/ /2021 4/ / /2023 Design - Phase 3D 9/ /2024 Construction - Phase 3D 1/2017 1/2019 1/2017 1/ / / / /2026 Design - Phase 3E 9/ /2027 Construction - Phase 3E 1/2019 7/2020 1/2019 7/ /2027 3/ /2027 3/2029 Phase 4 - at Horse Drive Design 6/2008 5/2009 6/2008 5/2009 6/2008 5/2009 6/2008 5/2009 6/2008 5/2009 Construction FY 2009 FY / /2010 6/2009 6/2011 6/2009 6/2011 6/2009 6/2011 6/2009 6/2011 Phase 5 - at Kyle Canyon Road Design 1/2013 1/2015 1/2013 1/2015 1/2013 1/2015 7/2023 6/2025 8/2014 8/2017 Construction FY 2016 FY /2018 9/2020 6/ /2027 6/ / /2035 9/ /2018 5/2020 US 95 Northwest Corridor FY 2008 FY / / / / / / /2007 9/ /2007 3/2029 The Initial Financial Plan schedule focused on the construction phases of the various projects contained within the US 95 Northwest Corridor program; therefore information was not available for the sub-phases for the initial plan and subsequent annual updates. The 2014 Annual Update includes breakout information for the design and construction phases of each project, where applicable for comparison purposes. 7

16 US 95 NORTHWEST CORRIDOR 2014 FINANCIAL PLAN ANNUAL UPDATE This page is left intentionally blank 8

17 US 95 NORTHWEST CORRIDOR 2014 FINANCIAL PLAN ANNUAL UPDATE 3. Project Cost All project costs shown in this document are presented as Year-of-Expenditure (YOE) dollars at the 70% risk-based confidence level for the overall project. YOE dollars are equal to current dollars escalated to the midpoint of expenditure for each element of the project. A Cost Risk Assessment (CRA) workshop was held July 1 & 2, 2014 for the US 95 Northwest Corridor program. The overall objective of the CRA workshop was to validate and quantify uncertainty and risk in the project cost and schedule for the three remaining projects within the program. Phase 2 - Ann Road to Kyle Canyon Road Phase 3 - /CC-215 Northern Beltway Interchange Phase 5 - at Kyle Canyon Road During the CRA workshop the project team, working collaboratively with independent subject matter experts, reviewed the base cost and schedule and identified, characterized, and analyzed risks. This workshop was accomplished in a structured setting and led by an independent Risk Lead. To determine the 70% risk-based confidence level a cost risk analysis or risk-based modeling tool was incorporated to model the overall risk of the project. Risk-based analysis provides a distribution of probabilities that a project will not exceed an estimated dollar figure. Typically, agencies report the project risk-based estimation using the 70 th percent confidence interval after the implementation of risk response strategies. As of December 31, 2014, the total cost estimate of the US 95 Northwest Corridor project is estimated to be $ million with $ million in costs left to complete at the 70% confidence level. Table 3 depicts the cost estimate breakdown for each of the major project elements including costs spent to date and costs left to complete the project. It should be noted that construction engineering and administration costs are included in the construction element total. For a more detailed breakdown of base costs see the US 95 Northwest Corridor Cost Risk Assessment report in Appendix F. Table 3 Total Project Cost by Cost Element Project Cost Element Costs to Date Costs in Millions ($ s) 70 th Percentile 2014 Estimate Cost to Complete Environmental Document $3.81 $3.81 Completed Phase 1 - Washington Avenue to Ann Road Design $3.54 $3.54 Completed 9

18 US 95 NORTHWEST CORRIDOR 2014 FINANCIAL PLAN ANNUAL UPDATE Project Cost Element Costs to Date Costs in Millions ($ s) 70 th Percentile 2014 Estimate Cost to Complete Right of Way $0.17 $0.17 Completed Construction $82.14 $82.14 Completed Phase 2 - Ann Road to Kyle Canyon Road Phase 2A Total $85.85 Completed Design $1.35 $1.35 Completed Right of Way $0.15 $0.15 Completed Construction $15.04 $37.52 $22.48 Phase 2B Design $2.22 $2.22 Right of Way $0.15 $0.15 Construction $37.52 $37.52 Total $16.54 $78.91 $62.37 Phase 3 - /CC-215 Northern Beltway Interchange Phase 3A Preliminary Engineering/Design Phase 3A $7.63 $7.63 Completed Right of Way $0.52 $0.52 Completed Construction $0.00 $57.47 $57.47 Phase 3B Design $0.00 $2.08 $2.08 Right of Way $0.00 $0.00 $0.00 Construction $0.00 $18.93 $18.93 Phase 3C Design $0.00 $6.96 $6.96 Right of Way $0.00 $0.00 $0.00 Construction $0.00 $88.53 $88.53 Phase 3D Design $0.00 $6.59 $6.59 Right of Way $0.00 $0.00 $0.00 Construction $0.00 $86.39 $

19 US 95 NORTHWEST CORRIDOR 2014 FINANCIAL PLAN ANNUAL UPDATE Phase 3E Project Cost Element Costs to Date Costs in Millions ($ s) 70 th Percentile 2014 Estimate Cost to Complete Design $0.00 $1.89 $1.89 Right of Way $0.00 $0.00 $0.00 Construction $0.00 $25.03 $25.03 Phase 4 - at Horse Drive Total $8.14 $ $ Design $2.70 $2.70 Completed Right of Way $11.30 $11.30 Completed Construction $42.00 $42.00 Completed Phase 5 - at Kyle Canyon Road Total $56.00 $56.00 Design $3.09 $3.09 Right of Way $0.00 $0.00 Construction $38.79 $38.79 Total $41.88 $41.88 US 95 Northwest Corridor Total $ $ $ All costs shown as costs to date were developed from NDOT programming papers contained in Appendix D. The costs depicted for the environmental assessment were considered all environmental costs spent to date through October 2007 when the FONSI was determined. The remaining environmental costs spent to date through December 31, 2014 were assumed to be classified as preliminary engineering costs and were used on the Phase 3. 11

20 US 95 NORTHWEST CORRIDOR 2014 FINANCIAL PLAN ANNUAL UPDATE A comparison of the project costs by element from the 2009 Initial Financial Plan and the Annual Updates from are shown in Table 4. Table 4 Cost Comparison by Cost Element Project Cost Element 2009 Initial Financial Plan Costs in Millions ($ s) 2010 Annual Update 2011 Annual Update 2012 Annual Update 2013 Annual Update 2014 Annual Update Net Change since Last Annual Update Net Change since Initial Financial Plan Environmental Document $3.81 N/A N/A Phase 1 - Washington Avenue to Ann Road Design $3.30 $3.60 $3.60 $3.50 $3.50 $3.54 $0.04 $0.24 Right of Way $0.00 $0.10 $0.10 $0.20 $0.20 $0.17 ($0.03) $0.17 Construction $ $76.00 $76.00 $82.00 $81.60 $82.14 $0.54 ($67.06) Phase 2 - Ann Road to Kyle Canyon Road TOTAL $ $79.70 $79.70 $85.70 $85.30 $85.85 $0.55 ($66.65) Design $6.00 $6.30 $1.70 $1.60 $2.70 $0.87 ($2.43) Right-of-Way $6.50 $13.60 $0.00 $0.20 $0.10 $0.20 ($6.20) Construction $ $ $58.00 $58.50 $71.90 $3.14 ($117.86) Phase 2A Design $1.35 Right of Way $0.15 Construction $37.52 Phase 2B Design $2.22 Right of Way $0.15 Construction $37.52 Phase 3 - at CC-215 TOTAL $ $ $59.70 $60.30 $74.70 $78.91 $4.21 ($126.49) Design $12.60 $14.10 $16.40 $15.90 $19.80 $5.35 $12.55 Right-of-Way $0.00 $0.30 $2.90 $2.50 $2.40 ($1.88) $0.52 Construction $ $ $ $ $ $26.15 $45.35 Phase 3A Preliminary Engineering/Design Phase 3A $7.63 Right of Way $0.52 Construction $57.47 Phase 3B Design $2.08 Right of Way $

21 US 95 NORTHWEST CORRIDOR 2014 FINANCIAL PLAN ANNUAL UPDATE Project Cost Element 2009 Initial Financial Plan Costs in Millions ($ s) 2010 Annual Update 2011 Annual Update 2012 Annual Update 2013 Annual Update 2014 Annual Update Construction $18.93 Phase 3C Design $6.96 Right of Way $0.00 Construction $88.53 Phase 3D Design $6.59 Right of Way $0.00 Construction $86.39 Phase 3E Design $1.89 Right of Way $0.00 Construction $25.03 Phase 4 - at Horse Drive Net Change since Last Annual Update Net Change since Initial Financial Plan TOTAL $ $ $ $ $ $ $29.62 $58.42 Design $3.00 $3.00 $2.70 $2.70 $2.70 $2.70 $0.00 ($0.30) Right of Way $13.00 $11.30 $11.30 $11.30 $11.30 $11.30 $0.00 ($1.70) Construction $53.10 $51.30 $42.00 $42.00 $42.00 $42.00 $0.00 ($11.10) Phase 5 - at Kyle Canyon Road TOTAL $69.10 $65.60 $56.00 $56.00 $56.00 $56.00 $0.00 ($13.10) Design $2.80 $2.90 $4.60 $4.70 $5.00 $3.09 ($1.69) $0.29 Right of Way $0.20 $1.40 $0.30 $0.30 $0.60 $0.00 ($0.60) ($0.20) Construction $35.70 $35.40 $58.10 $60.00 $55.50 $38.79 ($16.71) $3.09 TOTAL $38.70 $39.60 $63.00 $65.00 $61.10 $41.88 ($19.22) $3.18 US 95 Northwest Corridor TOTAL $ $ $ $ $ $ $$18.96 ($140.84) 13

22 US 95 NORTHWEST CORRIDOR 2014 FINANCIAL PLAN ANNUAL UPDATE 3.1 Cost Estimating Methodology Preliminary cost estimates for the US 95 Northwest Corridor project include estimates for construction items, design, construction engineering, right-of-way acquisition, utilities relocation, and contingencies. Quantities for the major items of construction were estimated from preliminary engineering plans and investigations. Estimated unit costs for these major items were developed from actual bid prices for similar work in the Las Vegas urban area. The primary source of current bid prices is the NDOT Reasonable Cost database which is updated as contracts are awarded. In addition to the cost of the major construction items, other elements of the preliminary cost estimates, such as mobilization and traffic control, have been accounted for as lump sum allowances or percentages of the cost of other elements. A Cost Risk Assessment (CRA) workshop was held July 1 & 2, 2014 for the remaining projects (Phases 2, 3 and 5) of the US 95 Northwest Corridor project. The overall objective of the workshop was to update the base costs, uncertainty, project schedule and risks for these projects. The Risk Lead, along with the Project Team and the various subject matter experts (SMEs), performed a baseline risk assessment. As part of the risk assessment the cost estimates were reviewed by an independent Cost Lead by verifying the accuracy and reasonableness of the total cost estimate and schedule. During the risk assessment workshop, threats and opportunities were identified, and the Risk Team quantified likelihoods and impact ranges that best modeled the threats and opportunities. Uncertainty ranges were developed for the cost estimate that represents each project s current state of development. More information is provided on project risks in Section 8. For more information see the US 95 Northwest Corridor Cost Risk Assessment report in Appendix F. 3.2 Escalation All cost estimates in this Financial Plan are in year-of-expenditure dollars. Year-of-expenditure costs are calculated by applying an estimated annual escalation rate to base year cost estimates. As part of the CRA modeling, escalation rate forecasts were developed. To account for price increases between the date the base cost estimate was created and when the actual work will be performed, the CRA modeling requires escalation rate forecasts for construction (CN), preliminary engineering (PE), and right-of-way (ROW) costs incurred by a project. Each project element s (PE, ROW, CN) escalation rate is utilized to develop YOE dollars by escalating to the midpoint of each element s completion. Escalation is the measurement of the change in project costs due to general price inflation and ordinary changes in commodity supply and demand. As the price of a construction component changes, the overall costs of a construction project typically varies with it. In this analysis, 14

23 US 95 NORTHWEST CORRIDOR 2014 FINANCIAL PLAN ANNUAL UPDATE escalation rates are applied for preliminary engineering, right-of-way, and construction component costs in order to estimate the future project costs under the baseline schedule and any extensions due to schedule delay. National data from the Bureau of Labor Statistics for several series; Concrete, Steel, Asphalt, Machinery & Equipment, Aggregate, Lumber & Wood Products, Electric Lighting Equipment, and other Minor Inputs (including Chemicals/Resins, Paint, etc.) were utilized along with State data from the BLS Occupational Employment and Wage Statistics for construction labor wages to develop forecasted construction escalation rates. An overall construction price escalation rate forecast was developed by combining escalation forecasts of each component, based on weights reflecting that component s share of the cost of a typical roadway project. Preliminary engineering escalation forecasts were developed using State wage data from the BLS Occupational Employment and Wage Statistics for civil engineer wages. Right of way acquisition cost escalation forecasts were developed via State data available from the Lincoln Institute of Land Policy (in partnership with the University of Wisconsin, School of Business). The escalation forecasts were developed utilizing a simulation model incorporating curve fitting of probability distributions that best match each series historical price change over multiple historical year groups. The final escalation forecasts by year for construction, preliminary engineering, and right-of-way reflect the median forecasted values produced within the simulation model. The escalation rates utilized in the risk assessment for are shown in Table 5. Table 5 Escalation Rates Year PE ROW CN % 4.02% 3.19% % 4.12% 3.33% % 4.35% 3.72% % 4.58% 3.94% % 4.75% 3.80% % 4.83% 4.01% % 5.28% 4.05% % 4.11% 4.28% 2022 and Beyond 2.74% 2.94% 4.51% 15

24 US 95 NORTHWEST CORRIDOR 2014 FINANCIAL PLAN ANNUAL UPDATE 4. Project Funds Revenues to support transportation investments within the US 95 Northwest Corridor project will come from a variety of public, tax-based sources, raised at either the local, state or federal level. All future funding depicted within this financial plan is itemized in the Regional Transportation Plan (RTP) contained within Appendix C and is considered dedicated to the corresponding listed element of the US 95 Northwest Corridor project. All past funding is covered in NDOT Project and Programming Details as shown in Appendix D. Exhibit 2 presents the total project funding amount that is available by source; federal, state, or local. Exhibit 2 US 95 Northwest Corridor Funding Share by Source, Millions ($ s) 16

25 US 95 NORTHWEST CORRIDOR 2014 FINANCIAL PLAN ANNUAL UPDATE Table 6 details the current programmed funds for the US 95 Northwest Corridor project. Table 6 Programmed Funding in Millions ($ s) Funding Source Environmental Clearance (Completed) Previous Funding To Date FY 2015 FY 2016 FY 2017 FY 2018 FY FY FY FY TOTALS State Funds 1 $3.81 $3.81 Phase 1 - Washington Avenue to Ann Road (Completed) Various Federal Funds 2 $51.47 $51.47 Various State Funds 2 $34.19 $34.19 Various Local Funds 2 $0.19 $0.19 Phase 1 Total $85.85 $85.85 Phase 2 - Ann Road to Kyle Canyon Road Phase 2A NHPP 3,4 $28.94 $28.94 SAFETEA-LU NHS 3,4 $2.46 $2.46 State Matching 3,4 $2.04 $2.04 City of Las Vegas 3,4 $1.47 $1.47 STP 3,4 $7.38 $7.38 Phase 2A Totals $42.29 $42.29 Phase 2B NHPP 5 $26.36 $26.36 STP 5 $8.79 $8.79 State Matching 5 $1.85 $1.85 Phase 2B Totals $37.00 $

26 US 95 NORTHWEST CORRIDOR 2014 FINANCIAL PLAN ANNUAL UPDATE Funding Source Previous Funding To Date Phase 3 - /CC-215 Northern Beltway Interchange Preliminary Design/Design Phase 3A FY 2015 FY 2016 FY 2017 FY 2018 FY FY FY FY TOTALS State Funds 1 $1.06 $1.06 HIGH PRIORITY, SAFTEA-LU 1,6 $13.99 $13.99 State Matching 6 $0.74 $0.74 Phase 3A State Matching 7 $1.42 $1.42 Clark County Regional Flood Control District 7 $17.67 $17.67 HIGH PRIORITY, SAFTEA-LU 7 $0.66 $0.66 NHPP 7 $20.91 $20.91 RTC of Southern Nevada (Gas Tax) 7 $6.40 $6.40 SAFETEA-LU HWY SAFETY PROG 7 $0.61 $0.61 STP 7 $4.75 $4.75 Phase 3/3A Totals $15.79 $52.51 $68.20 Phase 3B NHPP 8 $12.18 $12.18 State Matching 8 $0.86 $0.86 STP 8 $4.06 $4.06 Phase 3B Totals $17.10 $17.10 Phase 3C Clark County Beltway Program 5 $45.00 $45.00 STP Clark County 5 $10.00 $10.00 $20.00 Phase 3C Totals $10.00 $45.00 $10.00 $

27 US 95 NORTHWEST CORRIDOR 2014 FINANCIAL PLAN ANNUAL UPDATE Funding Source Phase 4 - at Horse Drive (Completed) Previous Funding To Date FY 2015 FY 2016 FY 2017 FY 2018 FY FY FY FY TOTALS HIGH PRIORITY, SAFTEA-LU 9 $4.53 $4.53 SAFETEA-LU STP LAS VEGAS 9 $19.42 $19.42 STEA STP LAS VEGAS 9 $1.58 $1.58 City of Las Vegas 9 $9.46 $9.46 RTC of Southern Nevada 9 $21.00 $21.00 Phase 4 Totals $56.00 $56.00 Phase 5 - at Kyle Canyon Road Fuel Revenue Indexing (FRI) 5,8 $2.00 $6.71 $8.71 Phase 5 Totals $2.00 $6.71 $8.71 US 95 Northwest Corridor Total $ $54.41 $0.00 $37.00 $17.10 $16.71 $45.00 $10.00 $0.00 $ Sources: See Appendix C and D 1 - Project and Programming Details Project ID Project and Programming Details Project ID Project and Programming Details Project ID Project and Programming Details Project ID Regional Transportation Plan : December 13, Project and Programming Details Project ID Project and Programming Details Project ID Transportation Improvement Program for FY : August 14, Rev October Project and Programming Details Project ID

28 US 95 NORTHWEST CORRIDOR 2014 FINANCIAL PLAN ANNUAL UPDATE The following are descriptions for the funding sources for the future projects within the US 95 Northwest Corridor program. 4.1 Federal Funds 4.10 Federal Transportation Funding The Federal way Trust Fund was established in Revenues include taxes on gasoline (18.4 cents per gallon), diesel (24.4 cents per gallon), tires over 40 pounds, truck and trailer sales, heavy vehicle use, and interest. Most of the funding Nevada utilizes is received via apportionments and is distributed to various programs such as the National way Performance Program and Surface Transportation, Program noted below. The Federal Aid way Program is reimbursable funding with matching funds (state, local and/or private) required for most of the programs. Nevada s match is typically 5% (95% Federal) due to the high percentage of federal lands in the state.. Normally, funding levels are authorized in a six-year surface transportation bill. In recent years, federal transportation legislation has been funded via a series of short-term continuing resolutions, with the exception of Moving Ahead for Progress in the 21st Century Act (MAP-21) which covered federal fiscal years 2013 and The most recent federal bill, the way and Transportation Funding Act of 2014 was signed into law by President Obama on August 8, This legislation provides federal transportation funding through May 2015 and provides additional funding for the Federal way Trust Fund which was experiencing a shortfall National way Performance Program (NHPP) The NHPP provides support for the condition and performance of the National way System (NHS), for the construction of new facilities on the NHS, and to ensure that investments of Federal-aid funds in highway construction are directed to support progress toward the achievement of performance targets established in a State's asset management plan for the NHS. This program is funded by contract authority from the way Account of the way Trust Fund. Funds are subject to the overall Federal-aid obligation limitation. MAP-21 has a new approach to core formula program funding, authorizing a lump sum total instead of individual authorizations for each program. Once Nevada s share of the total is calculated, it is divided up by program within the State. The federal share is typically 95 percent Surface Transportation Program (STP) This program is available for projects statewide and it is the normal practice of NDOT to use this funding source for major projects on the interstate highways and major state routes. The Surface Transportation Program (STP) provides flexible funding that may be used by States and localities for projects to preserve and improve the conditions and performance on 20

29 US 95 NORTHWEST CORRIDOR 2014 FINANCIAL PLAN ANNUAL UPDATE any Federal-aid highway, bridge and tunnel projects on any public road, pedestrian and bicycle infrastructure, and transit capital projects, including intercity bus terminals. MAP-21 has a new approach to core formula program funding, authorizing a lump sum total instead of individual authorizations for each program. Once Nevada s share of the total is calculated, it is divided up by program within the State. The federal share is typically 95 percent. This program also has a sub-allocation for urbanized areas, including a sub-allocation that can only be used in Clark County SAFETEA-LU ( Priority and HWY Safety Program) In SAFETEA-LU Section 1702, Congress earmarked federal funds for projects nationwide. Generally, these funds are not available for other projects; although the funding for some projects may be loaned to other projects within the list. The federal share is typically 95 percent. 4.2 State Funds 4.21 State way Fund (NDOT State Gas Tax & State Matching Per Nevada State Constitution Article 9, Section 5, the proceeds from the imposition of any license or registration fee and other charge with respect to the operation of any motor vehicle upon any public highway in Nevada and the proceeds from the imposition of any excise tax on gasoline or other motor vehicle fuel shall, except costs of administration, be used exclusively for the construction, maintenance, and repair of the public highways of this State. way Fund revenue sources include gas and special fuel tax, motor carrier fees, registration fees, and driver s license fees. Nevada Revised Statute ( NRS ) provides the statutory authority for these revenues and expenditures plus other pertinent revenue and expenditures to flow through the State way Fund and caps the cost of administration incurred by the Department of Motor Vehicles SB5 Funding Senate Bill 5, passed at the th Special Session of the legislature, provides funding via a transfer to the Nevada Department of Transportation from the Fund for Cleaning up Discharges of Petroleum. This money must be used for the construction, reconstruction, improvement and maintenance of public roads. Per SB5, 70% of this funding is allocated for use in Clark County, 20% is allocated for use in Washoe County, and 10% is available for use in other counties. 4.3 Local Funds 4.31 Local Funds The Clark County Regional Flood Control District has provided funding for the Clark County Regional Flood Control Facility CNWE 0301 and CNWE 0304 along CC-215 from an existing 21

30 US 95 NORTHWEST CORRIDOR 2014 FINANCIAL PLAN ANNUAL UPDATE concrete channel (East Tenaya Way) north to US 95. This project has been incorporated into the Phase 3A project. Additional funding for the Phase 3A project is also coming from the RTC of Southern Nevada (Gas Tax) Fuel Revenue Indexing The RTC partnered in 2013 with local leaders, our business community, state legislature, the Governor and the Clark County Commission to support Fuel Revenue Indexing to keep pace with material and labor costs, generate funds for critically needed transportation projects and create jobs. From January 2014 to December 2016, a portion of what drivers pay at the pump will help fund transportation projects throughout Clark County. For motorists, this averages about a dime a day over the three-year time period. This investment at the pump will generate approximately $700 million to fund 199 projects in Southern Nevada, ultimately creating more than 9,000 jobs. After 2016, in order for fuel revenue indexing to continue in Clark County, it will go to the vote of the people via a ballot initiative. 5. Financing Issues At this time no funding through bonds or other types of financing is shown for any of the future projects within the corridor. 6. Cash Flow Since funding sources for the US 95 Northwest Corridor project are designated for each project individually the cash flow for the overall program is presented separately for each project. Monies cannot necessarily be moved from project to project because of the many different funding sources. 22

31 US 95 NORTHWEST CORRIDOR 2014 FINANCIAL PLAN ANNUAL UPDATE 6.1 Phase 2A As Exhibit 3 illustrates, the Phase 2A funds will be sufficient to cover Phase 2A total costs leading to an approximate $10.8 million funding surplus. Exhibit 3 Phase 2A Interchange Annual and Cumulative Cash Flow (Millions $ s) 6.3 Phase 2B As Exhibit 4 illustrates, the Phase 2B funds are expected to be available in FY 2017 and are currently insufficient to cover Phase 2B total costs leading to an approximate $2.4 million funding gap. To close this funding gap, NDOT will take steps to acquire funding from state, local or federal sources. Exhibit 4 Phase 2B Annual and Cumulative Cash Flow (Millions $ s) 23

32 US 95 NORTHWEST CORRIDOR 2014 FINANCIAL PLAN ANNUAL UPDATE 6.4 Phase 3A Exhibit 5 shows that the anticipated funding will be sufficient to cover all of the Phase 3A costs leading to an overall surplus of approximately $2.7 million. Exhibit 5 Phase 3A Annual and Cumulative Cash Flow (Millions $ s) 6.5 Phase 3B Exhibit 6 illustrates the cash flow for Phase 3B. The anticipated funding will be insufficient to cover the expected costs leading to an overall deficit of approximately, $21 million in FY To close this funding gap, NDOT will take steps to acquire additional funding from state, local or federal sources. Exhibit 6 Phase 3B Annual and Cumulative Cash Flow (Millions $ s) 24

33 US 95 NORTHWEST CORRIDOR 2014 FINANCIAL PLAN ANNUAL UPDATE 6.6 Phase 3C Exhibit 7 shows the cash flow for the Phase 3C project. Exhibit 7 Phase 3C Annual and Cumulative Cash Flow (Millions $ s) 6.7 Phase 3D No funding has currently been identified for Phase 3D. The project is currently anticipated to begin construction in FY NDOT will take steps to acquire funding from state, local or federal sources within the next RTP. 6.7 Phase 3E No funding has currently been identified for Phase 3D. The project is currently anticipated to begin construction in FY NDOT will take steps to acquire funding from state, local or federal sources within the next RTP. 25

34 US 95 NORTHWEST CORRIDOR 2014 FINANCIAL PLAN ANNUAL UPDATE 6.7 Phase 5 Exhibit 8 reveals that the available funding for the Phase 5 funds will be insufficient to cover the total costs creating an approximate $3.6 million funding gap beginning in in FY 2016 and increasing to $20.8 million in FY NDOT and Clark County will take steps to acquire funding from state, local or federal sources. Exhibit 8 Phase 5 Annual and Cumulative Cash Flow (Millions $ s) 6.8 Total Project The 2009 Initial Financial Plan developed cash flow results for the overall US 95 Northwest Corridor project, but did not discuss individual project cash flows. Because the funding sources are dedicated to individual projects of the overall US 95 Northwest Corridor project, any comparison should be made at the individual projects level. Because individual project cash flow results are not contained within the 2009 Initial Financial Plan, no relevant comparison can be presented in this Annual Update. 7. P3 Assessment Nevada Revised Statutes through 168 provides legislative authority for transportation projects including methods of authorization. Specifically: NRS Alternative methods of authorization - A public body may authorize a person to develop, construct, improve, maintain or operate, or any combination thereof, a transportation facility pursuant to NRS or

35 US 95 NORTHWEST CORRIDOR 2014 FINANCIAL PLAN ANNUAL UPDATE A public private partnership is currently not being considered by NDOT for the remaining portions of US 95 Northwest Corridor project. NDOT cannot solicit for P3 proposals, but can react to an unsolicited offer. Additional information can also be found in NRS HIGHWAYS, ROADS AND TRANSPORTATION FACILITIES. 8. Risk and Response Strategies NDOT has committed to the implementation of comprehensive risk identification and risk management process for statewide mega-projects, defined by NDOT as any project over $100 million cost. US 95 Northwest Corridor project qualifies as such a project. A Cost Risk Assessment (CRA) workshop was held July 1 & 2, 2014 for the US 95 Northwest Corridor project. The overall objective of the workshop was to update base costs, uncertainty, project schedule and risks for the project. The Risk Lead, along with the Project Team and the various subject matter experts (SMEs), performed a baseline risk assessment of both phases. The potential risk events and elements facing the phases were discussed. During the discussion, the workshop participants identified high risk elements or potential events which may occur that would impact the project. For each risk element identified, it was determined whether the risk would affect cost, schedule, or simultaneously both cost and schedule. During the workshop risk response strategies were developed for key project risks. These response strategies will be added to the Project Risk Management Plan that the Project Manager will utilize to control risk on the project. Key Project Cost and Schedule Risks Phase 2A - Itemized in Table 7 are the top cost and schedule threats and/or opportunities identified in the risk assessment along with any mitigation strategies developed for key risks. For more information see the US 95 Northwest Corridor Cost Risk Assessment report located in Appendix F. Table 7 Phase 2A Risks Threat or Opportunity Pending Change Orders. Currently have one at $1.4M, reserve and additional $500K for over/under runs and additional change orders. Response Strategy Hold a reserve to pay for pending change orders 27

36 US 95 NORTHWEST CORRIDOR 2014 FINANCIAL PLAN ANNUAL UPDATE Phase 2B - Itemized in Table 8 are the top cost and schedule threats and/or opportunities identified in the risk assessment along with any mitigation strategies developed for key risks. For more information see the US 95 Northwest Corridor Cost Risk Assessment report located in Appendix F. Table 8 Phase 2B Risks Threat or Opportunity Intersection of Kyle Canyon and with Forest Service visitor center installation gets advanced to be construction with 2B. Currently do not have any agreements in place. Need agreements for manhole covers, service pedestals, etc. There is a low risk this could increase time in the base schedule. The cost is for rerouting if not all metered services are available. Different Site Conditions. This is highly likely in any excavation area. Response Strategy Continue to work with City to determine whether Phase 5 should be combined into Phase 2B. Currently ample time in schedule to get agreements in place. Hold risk reserve for potential change orders for differing site conditions Phase 3A - Itemized in Table 9 are the top cost and schedule threats and/or opportunities identified in the risk assessment along with any mitigation strategies developed for key risks. For more information see the US 95 Northwest Corridor Cost Risk Assessment report located in Appendix F. Table 9 Phase 3A Risks Threat or Opportunity Risks associated with shaft construction. Risk is obstructions, caliche, water table, dealing with shaft construction. Kern River gas line conflicts. Risk is to protect in place for package 1 end lightweight fill $0.5M bridge across $1.5M Added costs for constructability issues of an additional 0.5 across the board Response Strategy Consider transferring risk to contractor via specification or consider capping the risk. Include prequalification's requirements in specifications for shaft subcontractor. Protect in place measures for the WS Ramp. Update the base costs accordingly Phase 3B - Itemized in Table 10 are the top cost and schedule threats and/or opportunities identified in the risk assessment along with any mitigation strategies developed for key risks. For more information see the US 95 Northwest Corridor Cost Risk Assessment report located in Appendix F. 28

US-95 Northwest Corridor Initial Financial Plan

US-95 Northwest Corridor Initial Financial Plan T G YO N N HI O N N WA S NW CORRIDOR ROA D US-95 Northwest Corridor Initial Financial Plan C AV E ENU L E TO KY A April 2009 TABLE OF CONTENTS INTRODUCTION----------------------------------------------------------------------------------

More information

US-95 Northwest Corridor Project Management Plan

US-95 Northwest Corridor Project Management Plan T G YO N N HI O N N WA S NW CORRIDOR ROA D US-95 Northwest Corridor Project Management Plan C AV E ENU L E TO KY A April 2009 TABLE OF CONTENTS 1.0 Project Description and Scope of Work -----------------------------------------------------

More information

Chapter 5 Financial Plan

Chapter 5 Financial Plan The Safe, Accountable, Flexible, Efficient Transportation Equity Act: A Legacy for Users (SAFETEA_LU) requires that the MTP incorporate a financial plan for the planning period. The MTP is required to

More information

SURFACE TRANSPORTATION PROGRAM (STP) PROCEDURES FOR THE OKLAHOMA CITY URBANIZED AREA FUNDS

SURFACE TRANSPORTATION PROGRAM (STP) PROCEDURES FOR THE OKLAHOMA CITY URBANIZED AREA FUNDS SURFACE TRANSPORTATION PROGRAM (STP) PROCEDURES FOR THE OKLAHOMA CITY URBANIZED AREA FUNDS October 2015 Background The Surface Transportation Program (STP) was originally established as Section 133 of

More information

Federal Highway Administration 1200 New Jersey Avenue, SE Washington, DC 20590 202-366-4000

Federal Highway Administration 1200 New Jersey Avenue, SE Washington, DC 20590 202-366-4000 1 of 8 12/27/2013 8:21 AM U.S. Department of Transportation Federal Highway Administration 1200 New Jersey Avenue, SE Washington, DC 20590 202-366-4000 MAP-21 - Moving Ahead for Progress in the 21st Century

More information

3.1 Historical Considerations

3.1 Historical Considerations 3. Recommended Scope of Bridge improvements 3.1 Historical Considerations In the fall of 2000, an outside consultant, Fraser Design, suggested that the existing 4 th St. Bridge is potentially eligible

More information

The financial plan was prepared in conjunction with the Technical Working Group. Refer to Table 3-1: Funding and Implementation Plan.

The financial plan was prepared in conjunction with the Technical Working Group. Refer to Table 3-1: Funding and Implementation Plan. 3 Financial Plan The purpose of the financial plan is to identify funding options that would be likely sources of money to advance recommendations made by this study. The Capitol Region Transportation

More information

Technical Memorandum REVENUE FORECASTS. Prepared for: Prepared by:

Technical Memorandum REVENUE FORECASTS. Prepared for: Prepared by: Technical Memorandum REVENUE FORECASTS Prepared for: Prepared by: April 2014 TABLE OF CONTENTS 1 Introduction... 1 1.1 Inflation Indices... 2 1.2 Previous Studies... 3 2 Highway Revenue Baseline Forecast...

More information

Maryland Invests $845 Million in New Highway and Bridge Projects

Maryland Invests $845 Million in New Highway and Bridge Projects Maryland Invests $845 Million in New Highway and Bridge Projects Completing Widening of MD 404 Talbot And Caroline Counties Top Regional Priority Queen Anne s, Talbot, and Caroline Counties Widening MD

More information

FHWA Colorado Division Control of Access to the Interstate and its Right-of-Way February 2005

FHWA Colorado Division Control of Access to the Interstate and its Right-of-Way February 2005 FHWA Colorado Division Control of Access to the Interstate and its Right-of-Way February 2005 Background: It is in the national interest to maintain the Interstate System to provide the highest level of

More information

Primer Highway Trust Fund. Federal Highway Administration Office of Policy Development

Primer Highway Trust Fund. Federal Highway Administration Office of Policy Development Primer Highway Trust Fund Federal Highway Administration Office of Policy Development November 1998 Highway Trust Fund Primer Summary This Highway Trust Fund Primer is designed to provide basic information

More information

Implementation Strategy

Implementation Strategy Implementation Strategy 6 The following implementation strategy defines strategic points of intervention for complete streets programming, including visioning, goal-setting, local agency plans, coordination

More information

2035 FINANCIAL RESOURCES FORECAST

2035 FINANCIAL RESOURCES FORECAST 2035 FINANCIAL RESOURCES FORECAST AKRON METROPOLITAN AREA TRANSPORTATION STUDY 806 CITICENTER BUILDING 146 SOUTH HIGH STREET AKRON, OHIO 44308 December 2012 This report was prepared by the Akron Metropolitan

More information

GENERAL. This manual addresses five local programs that are funded under the current Highway Act:

GENERAL. This manual addresses five local programs that are funded under the current Highway Act: OVERVIEW The Local Public Agency Manual published by the Missouri Department of Transportation (MoDOT) is intended to be used as a guide for cities and counties that sponsor projects utilizing federal

More information

**The Winter 2010 edition of The Road Ahead newsletter is available online.

**The Winter 2010 edition of The Road Ahead newsletter is available online. RTC e-news Brief for January 29, 2010. This e-newsletter was created to keep you informed about key activities and issues pertaining to Your RTC. I encourage you to share this information with your board

More information

Summary of MAP-21 Matrix

Summary of MAP-21 Matrix Summary of MAP-21 Matrix Overview On July 6, 2012, President Obama signed into law P.L. 112-141, the Moving Ahead for Progress in the 21st Century Act (MAP-21). Funding surface transportation programs

More information

TRANSPORTATION Carson Howell, Analyst

TRANSPORTATION Carson Howell, Analyst State of Utah FY 2008 Budget Recommendations Carson Howell, Analyst AGENCY BUDGET OVERVIEW Mission: Build and maintain the State s transportation system, plan and implement new highway projects, improve

More information

LOUISVILLE - SOUTHERN INDIANA OHIO RIVER BRIDGES PROJECT Initial Financial Plan

LOUISVILLE - SOUTHERN INDIANA OHIO RIVER BRIDGES PROJECT Initial Financial Plan LOUISVILLE - SOUTHERN INDIANA OHIO RIVER BRIDGES PROJECT Initial Financial Plan Submitted to: Federal Highway Administration Submitted by: Kentucky Transportation Cabinet Indiana Department of Transportation

More information

9988 REDWOOD AVENUE PROJECT TRAFFIC IMPACT ANALYSIS. April 24, 2015

9988 REDWOOD AVENUE PROJECT TRAFFIC IMPACT ANALYSIS. April 24, 2015 9988 REDWOOD AVENUE PROJECT TRAFFIC IMPACT ANALYSIS April 24, 2015 Kunzman Associates, Inc. 9988 REDWOOD AVENUE PROJECT TRAFFIC IMPACT ANALYSIS April 24, 2015 Prepared by: Bryan Crawford Carl Ballard,

More information

12MAP-21, a funding and authorization bill to govern U.S. federal surface MONITORING IMPLEMENTATION AND PERFORMANCE

12MAP-21, a funding and authorization bill to govern U.S. federal surface MONITORING IMPLEMENTATION AND PERFORMANCE MONITORING IMPLEMENTATION AND PERFORMANCE 12MAP-21, a funding and authorization bill to govern U.S. federal surface transportation spending, creates a data-driven, performance-based multimodal program

More information

Program guidance that details the eligibility, criteria and application process. Ferry Boat Program. Ohio Department of Transportation

Program guidance that details the eligibility, criteria and application process. Ferry Boat Program. Ohio Department of Transportation Program guidance that details the eligibility, criteria and application process. Ferry Boat Program Ohio Department of Transportation TABLE OF CONTENTS Program Overview Program Administration.........2

More information

Section ALTERNATIVES. 3. Alternatives

Section ALTERNATIVES. 3. Alternatives Section 3 ALTERNATIVES 3. Alternatives 3.0 Alternatives The Springfield Rail Improvements Project Build Alternatives would utilize different routes. The No Build Alternative includes the continuation of

More information

Improving Access in Florida International University Biscayne Bay Campus Executive Summary

Improving Access in Florida International University Biscayne Bay Campus Executive Summary EXECUTIVE SUMMARY Improving Access in Florida International University Biscayne Bay Campus Executive Summary Prepared for: Miami-Dade County Metropolitan Planning Organization (Miami-Dade MPO) Prepared

More information

Draft Transportation Management Plan for Via Verdi Repair Project

Draft Transportation Management Plan for Via Verdi Repair Project for Via Verdi Repair Project prepared for City of Richmond This report was prepared by: This report was reviewed by: Ryan McClain, P.E. Fehr & Peers TABLE OF CONTENTS 1.0 INTRODUCTION & PROJECT DESCRIPTION...

More information

SEMINOLE PRATT WHITNEY ROAD & NORTHLAKE BLVD. FREQUENTLY ASKED QUESTIONS

SEMINOLE PRATT WHITNEY ROAD & NORTHLAKE BLVD. FREQUENTLY ASKED QUESTIONS UPDATED: 01/31/14 SEMINOLE PRATT WHITNEY ROAD & NORTHLAKE BLVD. FREQUENTLY ASKED QUESTIONS Q. 1. What are the County s plans for Seminole Pratt Whitney Road between SR 80 (Southern Blvd) and the Bee Line

More information

CHAPTER 4 SURFACE TRANSPORTATION PROGRAM (STP)

CHAPTER 4 SURFACE TRANSPORTATION PROGRAM (STP) Local Assistance Program Guidelines Chapter 4 CHAPTER 4 SURFACE TRANSPORTATION PROGRAM (STP) CONTENTS Section Subject Page Number 4.1 INTRODUCTION... 4-1 4.2 ELIGIBILITY CRITERIA... 4-1 General... 4-1

More information

The Need for Traffic Incident Management

The Need for Traffic Incident Management The Need for Traffic Incident Management With traffic incidents responsible for approximately 50-60% of the congestion delays motorists encounter on the nation s roadways every day, increased roadway capacity

More information

DISTRICT 3 TRAFFIC MANAGEMENT PLAN CHECKLIST

DISTRICT 3 TRAFFIC MANAGEMENT PLAN CHECKLIST State of California Business, Transportation and Housing Agency DISTRICT 3 TRAFFIC MANAGEMENT PLAN CHECKLIST District / EA: District 3/ EA 03-3E380 Date Prepared: 1/10/2013 Prepared By: Robert Himes Stage

More information

KEEPING NEVADA CONNECTED: Future Mobility in the Silver State

KEEPING NEVADA CONNECTED: Future Mobility in the Silver State KEEPING NEVADA CONNECTED: Future Mobility in the Silver State MARCH 2014 202-466-6706 www.tripnet.org Founded in 1971, TRIP, of Washington, DC is a nonprofit organization that researches, evaluates and

More information

FINANCIAL PLAN. Any future earmarks are assumed to carry their own limitation and not reduce the regular limitation identified in these calculations.

FINANCIAL PLAN. Any future earmarks are assumed to carry their own limitation and not reduce the regular limitation identified in these calculations. VII. FINANCIAL PLAN FHWA Funds The Federal Highway Administration (FHWA) funds are appropriated by Congress. FHWA funding levels are identified in the six-year Transportation Act. Each year, a federal

More information

3 Tappan Zee Bridge Rehabilitation Options

3 Tappan Zee Bridge Rehabilitation Options 3 Tappan Zee Bridge Rehabilitation Options 3.1 Introduction This chapter describes possible options that rehabilitate and enhance the existing Tappan Zee Bridge. Four Rehabilitation Options have been developed:

More information

Federal Guidelines for STP-U Funding

Federal Guidelines for STP-U Funding MPC 5.f Attachment 1 STP-U Eligibility Guidelines Page 1 of 5 Federal Guidelines for STP-U Funding SURFACE TRANSPORTATION PROGRAM (STP) ELIGIBLE EXPENDITURES PERIOD AVAILABLE: FY + 3 Years FUND: Highway

More information

Alternatives Design Report. Draft

Alternatives Design Report. Draft Draft 3/4/2014 TABLE OF CONTENTS I Introduction... 1 A. HISTORY... 1 B. PROJECT BACKGROUND... 1 II. ALTERNATIVES DEVELOPMENT... 8 A. ALTERNATE 1 NO BUILD... 8 B. ALTERNATE 2 IMPROVE ROADWAY ON EXISTING

More information

NEVADA TRANSPORTATION BY THE NUMBERS:

NEVADA TRANSPORTATION BY THE NUMBERS: NEVADA TRANSPORTATION BY THE NUMBERS: Meeting the State s Need for Safe and Efficient Mobility APRIL 2013 202-466-6706 www.tripnet.org Founded in 1971, TRIP of Washington, DC, is a nonprofit organization

More information

Fixing America s Surface Transportation (FAST)Act

Fixing America s Surface Transportation (FAST)Act Fixing America s Surface Transportation (FAST)Act Active Transportation Forum March 23 rd 2016 1 Replaces the Moving Ahead for Progress in the 21 st Century Act (MAP-21) of 2012 5-year bill (FY 2016-2020)

More information

Accident Analysis of Sheridan Road between Isabella Street and South Boulevard

Accident Analysis of Sheridan Road between Isabella Street and South Boulevard Accident Analysis of Sheridan Road between Isabella Street and South Boulevard Prepared for TranSystems Corporation for the City of Evanston Submitted by Regina Webster & Associates, Inc. Date: 08/15/2008

More information

IH-635 MANAGED LANES PROJECT, SEG. 3.2

IH-635 MANAGED LANES PROJECT, SEG. 3.2 IH-635 MANAGED LANES PROJECT, SEG. 3.2 Location: Dallas, Texas Owner: Texas Department of Transportation Client: Ferrovial Agroman Construction Cost: $1 Billion Construction Completion Date: December,

More information

SR-18 Corridor Improvements in Wood County

SR-18 Corridor Improvements in Wood County Public Meeting Information Package SR- Corridor Improvements in Wood County Thursday, May 19, 2011 10:00 a.m. to 1:00 p.m. Meeting Location: Hancock-Wood Electric Cooperative Building 1399 Business Park

More information

Are we being asked to pay enough to support our national highway and transit network?

Are we being asked to pay enough to support our national highway and transit network? Are we being asked to pay enough to support our national highway and transit network? Highlights: Last year, the average American driver traveled 11,400 miles in their car or light truck, bought 529 gallons

More information

AASHTO First Take at the New Surface Transportation Bill FIXING AMERICA S SURFACE TRANSPORTATION (FAST) ACT December 2, 2015

AASHTO First Take at the New Surface Transportation Bill FIXING AMERICA S SURFACE TRANSPORTATION (FAST) ACT December 2, 2015 AASHTO First Take at the New Surface Transportation Bill FIXING AMERICA S SURFACE TRANSPORTATION (FAST) ACT December 2, 2015 OVERVIEW On December 1, 2015, the House-Senate Conference Committee on H.R.

More information

RPA 14/ATURA Surface Transportation Program (STP) APPLICATION FOR FUNDS

RPA 14/ATURA Surface Transportation Program (STP) APPLICATION FOR FUNDS RPA 14/ATURA Surface Transportation Program (STP) APPLICATION FOR FUNDS Please provide the following information when applying to RPA 14/ATURA for Surface Transportation Program (STP) funding for projects

More information

Alternatives to the Circ Project Prioritization Methodology Prepared for Circ Task Force July 28, 2011

Alternatives to the Circ Project Prioritization Methodology Prepared for Circ Task Force July 28, 2011 Alternatives to the Circ Project Prioritization Methodology Prepared for Circ Task Force July 28, 2011 CCRPC staff has developed a draft methodology described below and detailed in the attached pages for

More information

Surface Transportation Program (STP) Projects

Surface Transportation Program (STP) Projects Toledo Metropolitan Area Council of Governments American Reinvestment and Recovery Act (Economic Stimulus Program) Application Packet for: Surface Transportation Program (STP) Projects APPLICATIONS DUE

More information

GUIDANCE FOR TRANSIT FINANCIAL PLANS

GUIDANCE FOR TRANSIT FINANCIAL PLANS U.S. Department of Transportation Federal Transit Administration GUIDANCE FOR TRANSIT FINANCIAL PLANS JUNE 2000 Prepared By: Federal Transit Administration Office of Planning Office of Program Management

More information

Finance Work Program Budget. FTC Workshop

Finance Work Program Budget. FTC Workshop Finance Work Program Budget FTC Workshop March 2010 Today s Presentation Basic Concepts Funding Sources Estimating Resources Finance Plan/Cash Forecast Cash Flow vs. Commitment Funding Priorities Work

More information

SAFETEA-LU TECHNICAL CORRECTIONS BILL SUMMARY

SAFETEA-LU TECHNICAL CORRECTIONS BILL SUMMARY SAFETEA-LU TECHNICAL CORRECTIONS BILL SUMMARY Draft 7/2/08 The SAFETEA-LU Technical Corrections Bill (HR 1195) was enacted on June 6, 2008 (P.L. 110-244). The Bill can be found at: http://frwebgate.access.gpo.gov/cgi-bin/getdoc.cgi?dbname=110_cong_bills&docid=f:h1195enr.txt.pdf

More information

FHWA Initial Financial Plan May 12, 2009

FHWA Initial Financial Plan May 12, 2009 South Access to the Golden Gate Bridge Doyle Drive Project FHWA Major Projects Financial Plan FHWA Initial Financial Plan May 12, 2009 Submitted in Partnership by: Federal Highway Administration San Francisco

More information

INDOT 2000-2025 Long Range Plan

INDOT 2000-2025 Long Range Plan Chapter 9 INDOT 2000-2025 Long Range Plan Highway Needs Analysis Overview The statewide transportation planning process provides for the identification of highway needs through a comprehensive process

More information

PART I TRAFFIC VIOLATIONS

PART I TRAFFIC VIOLATIONS PART I TRAFFIC VIOLATIONS A. MOTOR VEHICLE STATUTES N.J.S.A. 39:3-4 Driving or parking unregistered motor vehicle 39:3-9a Failure to notify change in name $22 39:3-9a Failure to endorse license $42 39:3-10

More information

8+ %!0"% 8+1!%"'$%,$"$

8+ %!0% 8+1!%'$%,$$ 8+ 8+ %!0"% The next step in developing recommendations for improvements to Grand Avenue was to identify, develop and evaluate alternatives to address the issues and needs identified in the previous chapter.

More information

Comment #1: Provide an interchange at Route 7 and Farm Market Road/White Gate Road. This was studied in the late 1990 s.

Comment #1: Provide an interchange at Route 7 and Farm Market Road/White Gate Road. This was studied in the late 1990 s. Proposed Truck Climbing Lane Route 7 Westbound Between West Market Street and Route 9 UPC# 58599, Project # 6007-053-133, P101 Date of Meeting: August 24, 2010 Time: 6:00PM to 8:00PM Location: Rust Library

More information

Examples of Transportation Plan Goals, Objectives and Performance Measures

Examples of Transportation Plan Goals, Objectives and Performance Measures Examples of Transportation Plan Goals, Objectives and Performance Measures The next step in the Long Range Transportation Plan (LRTP) process is to develop goals, objectives, and performance measures.

More information

CAPACITY AND LEVEL-OF-SERVICE CONCEPTS

CAPACITY AND LEVEL-OF-SERVICE CONCEPTS CHAPTER 2 CAPACITY AND LEVEL-OF-SERVICE CONCEPTS CONTENTS I. INTRODUCTION...2-1 II. CAPACITY...2-2 III. DEMAND...2-2 IV. QUALITY AND LEVELS OF SERVICE...2-2 Service Flow Rates...2-3 Performance Measures...2-3

More information

The Transportation Package

The Transportation Package The Transportation Package The transportation package raises $4.2 billion over 10 years, to invest in highway, rail, mobility, ferry, and transit projects throughout the state. These new revenues, combined

More information

EXHIBIT A Accessible Truck Routes Map

EXHIBIT A Accessible Truck Routes Map EXHIBIT A Accessible Truck Routes Map ASHEVILLE, NORTH CAROLINA ROUTE: A ROUTE: B ROUTE: C ROUTE: D ROUTE: E EXHIBIT A EXHIBIT B Craven Street Improvements Map ASHEVILLE, NORTH CAROLINA EXHIBIT B EXHIBIT

More information

Welcome! Purpose of Tonight s Meeting. Informational Open House to discuss two City projects: Goal is to LISTEN TO YOU

Welcome! Purpose of Tonight s Meeting. Informational Open House to discuss two City projects: Goal is to LISTEN TO YOU Purpose of Tonight s Meeting Informational Open House to discuss two City projects: Fairchild Street Subway Phase I Engineering: Immediate need to replace subway Bowman Avenue Feasibility Study Future

More information

Surface Transportation Program (STP)

Surface Transportation Program (STP) Project Name: Project Sponsor: FEDERAL FUNDS PROJECT APPLICATION TRANSPORTATION IMPROVEMENT PROGRAM 2008-2013 SALT LAKE and OGDEN/ LAYTON URBAN AREAS Surface Transportation Program (STP) Urban Surface

More information

PRIORITIZATION PROCESSES

PRIORITIZATION PROCESSES PROJECT SELECTION & PRIORITIZATION PROCESSES STIP Workshop Presented by: Bill Lawrence April 2011 Purpose and Review Overview of Project Selection Process Review Various Prioritization Processes Tk Take

More information

CHAPTER 27 New Public Road Connections. Table of Contents

CHAPTER 27 New Public Road Connections. Table of Contents Chapter 27 New Public Road Connections Table of Contents CHAPTER 27 New Public Road Connections Table of Contents CHAPTER 27 New Public Road Connections... 27-3 ARTICLE 1 - General... 27-3 Responsibility...

More information

Mid-Coast Corridor Transit Project San Diego, California New Starts Engineering (Rating Assigned November 2015)

Mid-Coast Corridor Transit Project San Diego, California New Starts Engineering (Rating Assigned November 2015) Mid-Coast Corridor Transit Project San Diego, California New Starts Engineering (Rating Assigned November 2015) Summary Description Proposed Project: Light Rail Transit 10.9 Miles, 9 Stations Total Capital

More information

Analysis of the 2015 Senate Surface Transportation Reauthorization Plan: The DRIVE Act

Analysis of the 2015 Senate Surface Transportation Reauthorization Plan: The DRIVE Act Analysis of the 2015 Senate Surface Transportation Reauthorization Plan: The DRIVE Act The Developing a Reliable and Innovative Vision for the Economy Act, or DRIVE Act, which was approved 65 to 34 July

More information

Ne w J e r s e y Tr a f f i c Co n g e s t i o n :

Ne w J e r s e y Tr a f f i c Co n g e s t i o n : Ne w J e r s e y Tr a f f i c Co n g e s t i o n : A Growing Crisis January 2008 Cover photo : Route 3, Passaic County introduction A rising tide of traffic congestion threatens to increase roadway gridlock,

More information

Informational Workshop Public Meeting Kanawha Falls Bridge Project

Informational Workshop Public Meeting Kanawha Falls Bridge Project Informational Workshop Public Meeting Kanawha Falls Project WV Department of Transportation Division of Highways in Cooperation with the Federal Highway Administration State Project S310-13-0.02 00 Federal

More information

Regional Surface Transportation Program Policy and Allocation

Regional Surface Transportation Program Policy and Allocation FY 2014-15 Regional Surface Transportation Program Policy and Allocation August 2015 Humboldt County Association of Governments 611 I Street, Suite B Eureka, CA 95501 Phone: 707.444.8208 www.hcaog.net

More information

Montana Legislative Fiscal Division. September 19, 2000. Prepared by Greg DeWitt, Senior Fiscal Analyst

Montana Legislative Fiscal Division. September 19, 2000. Prepared by Greg DeWitt, Senior Fiscal Analyst Montana Legislative Fiscal Division Highway State Special Revenue Account: Working Capital Update September 19, 2000 Prepared by Greg DeWitt, Senior Fiscal Analyst Highway State Special Revenue Account:

More information

Mid-Coast Corridor Transit Project San Diego, California New Starts Project Development (Rating Assigned November 2014)

Mid-Coast Corridor Transit Project San Diego, California New Starts Project Development (Rating Assigned November 2014) Mid-Coast Corridor Transit Project San Diego, California New Starts Project Development (Rating Assigned November 2014) Summary Description Proposed Project: Light Rail Transit 10.9 Miles, 9 Stations Total

More information

Principles for Authorization of the Surface Transportation Program

Principles for Authorization of the Surface Transportation Program Principles for Authorization of the Surface Transportation Program The United States requires a vast system of roads, highways, and bridges in order to move goods and people. The principle material used

More information

SUMMARY... iii INTRODUCTION... 1 PROJECT SPONSORS... 1 PROJECT DESCRIPTION... 1 PROJECT HISTORY... 3 PROJECT MANAGEMENT AND OVERSIGHT...

SUMMARY... iii INTRODUCTION... 1 PROJECT SPONSORS... 1 PROJECT DESCRIPTION... 1 PROJECT HISTORY... 3 PROJECT MANAGEMENT AND OVERSIGHT... BRENT SPENCE BRIDGE REPLACEMENT/REHABILITATION PROJECT INITIAL FINANCIAL PLAN PROJECT IDENTIFIER(S): HAM-71/75-0.00/0.22, PID 75119 HAM-71-0.00, PID 89077 HAM-75-0.22, PID 89068 Kentucky Project Item No.

More information

Transportation Management Plan Template

Transportation Management Plan Template DATE: TO: FROM: SUBJECT: Date Name Position Transportation Service Center Name Position Transportation Service Center Transportation Management Plan Job Number(s) Control Section(s) Route Details County

More information

CONNECTICUT S TOP TRANSPORTATION ISSUES:

CONNECTICUT S TOP TRANSPORTATION ISSUES: CONNECTICUT S TOP TRANSPORTATION ISSUES: Meeting the State s Need for Safe, Smooth and Efficient Mobility NOVEMBER 2015 202-466-6706 tripnet.org Founded in 1971, TRIP of Washington, DC, is a nonprofit

More information

CHAPTERTWO. Alternatives 2.1 ALTERNATIVES DEVELOPMENT PROCESS

CHAPTERTWO. Alternatives 2.1 ALTERNATIVES DEVELOPMENT PROCESS 2. Section 2 TWO CHAPTERTWO 2.1 ALTERNATIVES DEVELOPMENT PROCESS This EIS has been prepared in compliance with the Council on Environmental Quality (CEQ) regulations for implementing NEPA (40 CFR 1500-1508).

More information

Legislative Fiscal Bureau One East Main, Suite 301 Madison, WI 53703 (608) 266-3847 Fax: (608) 267-6873

Legislative Fiscal Bureau One East Main, Suite 301 Madison, WI 53703 (608) 266-3847 Fax: (608) 267-6873 Legislative Fiscal Bureau One East Main, Suite 301 Madison, WI 53703 (608) 266-3847 Fax: (608) 267-6873 February 16, 2010 TO: FROM: Members Joint Committee on Finance Bob Lang, Director SUBJECT: Governor's

More information

QUALITY ASSURANCE. and QUALITY CONTROL PROCESS GUIDE. for PROJECT MANAGERS

QUALITY ASSURANCE. and QUALITY CONTROL PROCESS GUIDE. for PROJECT MANAGERS QUALITY ASSURANCE and QUALITY CONTROL PROCESS GUIDE for PROJECT MANAGERS MDOT Trunkline Projects January 2005 TABLE OF CONTENTS Discussion.. 2 Scope Verification Meeting..... 3 Overview 3 Procedure...

More information

Light Rail Transit in Phoenix

Light Rail Transit in Phoenix 4. Presentation and Discussion: Phoenix Light Rail Implementation Wulf Grote Planning and Development Director, Phoenix Valley Metro Light Rail Transit in Phoenix Broadway Citizen s Task Force February

More information

The Urban Renewal Authority of Pueblo

The Urban Renewal Authority of Pueblo The Urban Renewal Authority of Pueblo The Urban Renewal Plan for the Saint Charles Industrial Park Urban Renewal Project Area Page 1 I. DEFINITIONS The terms used in this Urban Renewal Plan shall have

More information

2010 FINANCIAL PLAN ANNUAL UPDATE

2010 FINANCIAL PLAN ANNUAL UPDATE THE INTERCOUNTY CONNECTOR PROJECT 2010 FINANCIAL PLAN ANNUAL UPDATE AS OF FISCAL YEAR ENDING JUNE 30, 2010 DATE SUBMITTED: JANUARY 6, 2011 SUBMITTED IN PARTNERSHIP BY: MARYLAND STATE HIGHWAY ADMINISTRATION

More information

A Legislative Briefing prepared by Volume 7, Number 1 February 2001

A Legislative Briefing prepared by Volume 7, Number 1 February 2001 fiscal forum A Legislative Briefing prepared by Volume 7, Number 1 February 2001 Mitchell E. Bean, Director P. O. Box 30014, Lansing, MI 48909-7514 517-373-8080! FAX 517-373-5874! www.house.state.mi.us/hfa

More information

Executive Summary. Transportation Needs CHAPTER. Existing Conditions

Executive Summary. Transportation Needs CHAPTER. Existing Conditions CHAPTER 1 Executive Summary The City of Forest Grove Transportation System Plan (TSP) was updated to keep it consistent with recent growth trends in the city and other transportation planning efforts in

More information

Tier 1 Strategies. WV Route 14 Corridor Management Plan

Tier 1 Strategies. WV Route 14 Corridor Management Plan 1.1 1.2 1.3 1.4 Signal timing optimization system improvements. Improve geometry traffic control at high crash intersections. Construct intersection capacity improvement projects. Widen longer sections

More information

SYSTEMWIDE REQUIREMENTS

SYSTEMWIDE REQUIREMENTS SYSTEMWIDE REQUIREMENTS for the Peninsula Rail Program San Francisco to San Jose on the Caltrain Corridor Description of the Systemwide Context for the High Speed Train Project This document provides a

More information

Access Management South Dakota Department of Transportation

Access Management South Dakota Department of Transportation Public Meeting/ Open House October 21, 2014 Minnehaha County Environmental Assessment and Section 4(f) De Minimis Analysis Northern Segment of Hwy 100 I-90 to South of Madison Street Minnehaha County The

More information

Wilmington Urban Area Metropolitan Planning Organization Surface Transportation Program Direct Attributable Project Submittal Guide Fiscal Year 2016

Wilmington Urban Area Metropolitan Planning Organization Surface Transportation Program Direct Attributable Project Submittal Guide Fiscal Year 2016 Wilmington Urban Area Metropolitan Planning Organization Surface Transportation Program Direct Attributable Project Submittal Guide Fiscal Year 2016 Date of Release: September 14, 2015 Pre application

More information

MAP 21 themes. Strengthens America s highway and public transportation systems. Supports the Department s aggressive safety agenda

MAP 21 themes. Strengthens America s highway and public transportation systems. Supports the Department s aggressive safety agenda MAP 21 themes Strengthens America s highway and public transportation systems Creates jobs and supports economic growth Supports the Department s aggressive safety agenda Simplifies and focuses the Federal

More information

Chapter 5. Transportation. Decatur County Comprehensive Plan. Introduction. Goals and Objectives. Goal. Objectives. Goal.

Chapter 5. Transportation. Decatur County Comprehensive Plan. Introduction. Goals and Objectives. Goal. Objectives. Goal. Chapter 5 Transportation Chapter 5: Transportation Introduction The transportation system forms the backbone of a community. I-74 connects Decatur County with the large metropolitan areas of Cincinnati

More information

2014 Surface Transportation Program Island Sub-region RTPO Technical Advisory Committee Recommendations. Amount Requested

2014 Surface Transportation Program Island Sub-region RTPO Technical Advisory Committee Recommendations. Amount Requested 2014 Surface Transportation Program Island Sub-region RTPO Technical Advisory Committee Recommendations Name Overlay s Applicant Amount Requested Recommended Funding Amount Coupeville, Langley $411,661

More information

KENTUCKY TRANSPORTATION CABINET. Department of Rural and Municipal Aid. Office of Local Programs

KENTUCKY TRANSPORTATION CABINET. Department of Rural and Municipal Aid. Office of Local Programs KENTUCKY TRANSPORTATION CABINET Department of Rural and Municipal Aid Office of Local Programs Office of Local Programs Transportation Enhancements Safe Routes to School Congestion Mitigation and Air Quality

More information

The Roads to Recovery. Facts About Transportation Funding and Spending

The Roads to Recovery. Facts About Transportation Funding and Spending The Roads to Recovery Facts About Transportation Funding and Spending How Pima County spends transportation money (F.Y. 2014-15 Transportation Budget) 1 Debt Service (1997 bonds): $19.1 million In 1997,

More information

Multi Modal Roadway Transportation Impact Fees and Asset Value

Multi Modal Roadway Transportation Impact Fees and Asset Value January 2010 SB 360 Article Series: Factors to be Considered in Transitioning from a Road Impact Fee to a Mobility Fee Contributing Authors: Steven A. Tindale, P.E., AICP Robert P. Wallace, P.E., AICP

More information

Chapter 8 Funding Considerations

Chapter 8 Funding Considerations Chapter 8 Funding Considerations Expanding transit services into El Dorado Hills under any of the service alternatives has associated operating and capital costs. This chapter considers the funding sources

More information

NEW JERSEY TRANSPORTATION BY THE NUMBERS:

NEW JERSEY TRANSPORTATION BY THE NUMBERS: NEW JERSEY TRANSPORTATION BY THE NUMBERS: Meeting the State s Need for Safe and Efficient Mobility JANUARY 2015 202-466-6706 tripnet.org Founded in 1971, TRIP of Washington, DC, is a nonprofit organization

More information

Airport and Aviation Funding Programs

Airport and Aviation Funding Programs Chapter 7 Airport and Aviation Funding Programs Airports and aviation projects across the nation benefit from many funding sources including the federal, state, and local units of government. Some improvement

More information

I-25 / Rio Bravo Interchange

I-25 / Rio Bravo Interchange I-25 / Rio Bravo Interchange TONIGHT S MEETING SCHEDULE OPEN HOUSE 6:00 PM TO 6:30 PM PRESENTATION BEGINS AT 6:30 PM Q & A FOLLOWING PRESENTATION CN A300280 / PNA300280 I-25 / Rio Bravo Interchange SECOND

More information

CALIFORNIA TRANSPORTATION BY THE NUMBERS:

CALIFORNIA TRANSPORTATION BY THE NUMBERS: CALIFORNIA TRANSPORTATION BY THE NUMBERS: Meeting the State s Need for Safe and Efficient Mobility SEPTEMBER 2014 202-466-6706 tripnet.org Founded in 1971, TRIP of Washington, DC, is a nonprofit organization

More information

Cost Estimating Guideline December, 2015

Cost Estimating Guideline December, 2015 Cost Estimating Guideline December, 2015 Procedures are subject to change without notice. Check the Capital Project Delivery website to ensure this is the current version. Table of Contents Section 1 -

More information

14-97. 14-97.002 Definitions. For the purposes of this rule chapter the following definitions shall apply unless the context clearly shows otherwise:

14-97. 14-97.002 Definitions. For the purposes of this rule chapter the following definitions shall apply unless the context clearly shows otherwise: 14-97 14-97.001 Purpose. This rule chapter sets forth an access control classification system and access management standards to implement the State Highway System Access Management Act of 1988. The implementation

More information

Analysis of the Obama Administration s FY 2017 Budget Proposal for Transportation

Analysis of the Obama Administration s FY 2017 Budget Proposal for Transportation Analysis of the Obama Administration s FY 2017 Budget Proposal for Transportation FY 2017 Budget Summary The Obama s Administration s proposed budget for FY 2017, which was submitted to Congress February

More information

Chapter 22. Lump Sum Project Guidelines

Chapter 22. Lump Sum Project Guidelines Chapter 22 Lump Sum Project Guidelines 22.1 General...22-1 22.2 Project Selection...22-3 22.3 Plans Preparation...22-5 22.4 Preliminary Estimate...22-7 22.5 Specifications...22-9 22.6 Contracts Administration...22-11

More information

CHAN & PARTNERS ENGINEERING, LLC

CHAN & PARTNERS ENGINEERING, LLC July 2012 CHAN & PARTNERS ENGINEERING, LLC Consulting Civil Engineers Imagine Austin Comprehensive Plan Infrastructure, Operations, Maintenance & Service Cost Comparison Preferred Growth Scenario and Trend

More information

FHWA Emergency Relief (FHWA-ER) Training

FHWA Emergency Relief (FHWA-ER) Training FHWA Emergency Relief (FHWA-ER) Training Training Developed and Coordinated By Colorado Department of Transportation 2 Agenda FHWA Flowchart Policies, Purpose, Agency Roles Application Process Eligibility

More information

Appendix E Traffic Impact Analysis

Appendix E Traffic Impact Analysis Appendix E Traffic Impact Analysis 2010 Facility Master Plan Factoria Recycling and Transfer Station November 2010 2010 Facility Master Plan Factoria Recycling and Transfer Station November 2010 Department

More information