GUIDE FOR WATER MAIN EXTENSIONS

Size: px
Start display at page:

Download "GUIDE FOR WATER MAIN EXTENSIONS"

Transcription

1 This guide will provide you with a summary of the water main extension process for Indiana American Water. While it is our goal to make this guide as complete and easy to follow as possible, it is recommended that you meet with your local Indiana American Water Developer Services Contact who can fully review the process with you in detail. This guide is for all areas served by Indiana American Water. It is organized into the topics shown below. Preliminary Approval/Engineering Review IDEM Notice of Intent Application Fire Service Application Contractor Pre-Qualification Agreement Construction Acceptance Refund

2 PAGE 2 OF 9 Preliminary Project Discussion/Meeting Contact your local Developer Services Contact (DSC) or Indiana American Water (INAW) Developer Services. A meeting or discussion will take place to: Determine if your development can be served by Indiana American Water Discuss details and requirements of the development Determine if Off-Site main is needed to get to the development Discuss installation in easement vs. right-of-way Discuss required Utility Fee involved with project Discuss Subsequent Connection Fee, if required Utility Fee: The Utility Fee covers engineering, administrative costs, legal costs, direct labor cost, direct labor overhead and transportation costs incurred by the Utility. The amount of this fee may change each year, based on the previous year s actual costs. Indiana-American Water notifies the Indiana Utility Regulatory Commission (IURC) of the amount of the utility fee on an annual basis, as well as the method of calculation. Subsequent Connection Fee: If your new development has frontage along an existing water main installed within the last ten years, you may owe a subsequent connector fee. Approval/Engineering Review The following items are required from the developer prior to review by an INAW engineer: Proposed Plans. The Developer will provide proposed plans for water main installation. The plans must meet Indiana American Water s Minimum Requirements for Preliminary Review, Approved and As-Built Drawings and the Indiana-American Water Company Specifications. Off-Site vs. On-Site Main. An off-site Main is defined as the main installed to a development site where the developer is not developing the land on one or both sides of the main. The developer s land may front the main, but the services may not necessarily be connected directly to the off-site main. An on-site Main is defined as the main installed within a development where the developer is developing the land fronting both sides of the main. Off-Site and on-site mains must be submitted as separate projects.

3 PAGE 3 OF 9 Overall Project Drawing. If your project is a part of a larger development, an overall project drawing must be submitted. Preliminary Plat. Preliminary plat must be submitted along with the plans. The recorded plat will be required prior to project acceptance. Engineer. Provide name and contact information for your engineer. The engineer must be a registered Professional Engineer (P.E.) in the State of Indiana. Plan Review. Your plans will be reviewed by an INAW Engineer. If changes to the plans are necessary, a marked-up plan indicating the changes will be returned to the developer for revisions. The proposed plan must be approved by the INAW Engineer before construction of the water main may begin. The approved plan will also become an exhibit to your agreement. Main Upsizing. There may be situations where INAW will desire a main larger than required for your development, for future growth or other needs. INAW will pay the developer the actual cost difference between the smaller and larger mains. If upsizing is involved in your project, this will be documented on your project agreement. IDEM Notice of Intent Application The Indiana Department of Environmental Management (IDEM) requires that a Notice of Intent to Construct a Water Main Extension (NOI) letter be submitted for all water main extension projects, regardless of main size or length. Depending upon the length of the project, fees may be required. The developer must utilize a registered professional engineer to prepare the NOI Letter. The following items should be completed: Boxes 1 through 16 Box 8 please verify this number with your local DSC. The number is different for each Indiana American Water district. Box 17 preference checked Box 18 marked appropriately and fee included when appropriate Box 19 Responsible Person Signature Engineer Signature Developer Signature

4 PAGE 4 OF 9 The NOI letter and fee should be submitted to INAW along with the project plans. INAW will complete the Water Utility Information. When the project plans are approved, the INAW Engineer will mail the application and fee to IDEM, by certified mail. The required 30-day waiting period begins upon IDEM s receipt of the application. Construction may begin after the 30-day waiting period is complete. The Developer will be copied on the correspondence with IDEM, which will include the certified mail number. Construction must commence within 12 months of the submittal date of the NOI. If construction does not commence within that 12 month period, a new NOI submittal will be required. (Ref. IAC ). Please note that if water main extension plans deviate from Indiana American Water s Minimum Standards for Preliminary Review, Approved and As-Built Drawings for Developer Installed Water Mains, a full IDEM Construction Permit may be required. Fire Service Application If private fire lines or hydrants are anticipated, contact the Local Developer Services Contact for assistance. The developer will work with the local contact to get the application package and actual flow test data from the nearest location. The fire service is then designed based upon the flow test data and specific project needs. The following should be submitted to the local contact: Application for Private Fire Service (two original signed and witnessed copies) Data Sheet for Proposed Fire Service Installation Sheets from the Water Main Extension plans showing: Area map showing streets adjacent to proposed site/development, including at least one intersection. General Site Layout with: Utilities (existing and proposed) Fire Services Vault Point of connection between the proposed fire service and the existing water main Fire Service Vault Detail with project specific information added to the INAW standard (not a copy of ours). Include a note stating the make, model and size of the DCDA device (double check with detector backflow preventer) or specification/submittal sheets for it. Note that the State of Indiana requires USC approved backflow prevention devices.

5 PAGE 5 OF 9 Fire Pump and associated piping and suction pressure control valve. Include specification/submittal sheet(s) for the suction pressure control valve. Note: The INAW engineer does not require hydraulic calculations or drawings of the sprinkler layout inside the building. However, most fire departments require these. Some districts may forward them to the fire department with the application. Check with your local DSC for details. Note: The process in our Indiana Northwest district varies slightly from what is outlined here. The Northwest DSC will provide details. Contractor Pre-Qualification All contractors who install water mains and/or who perform taps on existing mains must be on our Approved Contractor List. If your contractor is not on the Approved Contractor List, they must complete the Contractor Work Experience Questionnaire and Qualification Statement and submit it to INAW. Please allow plenty of time for processing this paperwork prior to the start of construction. Agreement The developer submits the following items to the local DSC prior to preparation of project agreements: Estimated Cost Form. This form is required and will become part of your water main extension agreement. It gives an estimate of your costs for labor and materials. Please note that the materials shown on the Estimated Cost Form must match what is shown on the approved plans. Water Main Installation Contractor. Provide the name and contact information for your water main installation contractor. All contractors must be on our Approved Contractor List. If your contractor is not approved, please see the Contractor Pre- Qualification section of this guide. Approval must be granted prior to start of construction. Fire Hydrant Authorization. Some Indiana districts require authorization letters from the local fire department on location of hydrants. Your local district contact can tell you if this is a requirement for your development.

6 PAGE 6 OF 9 Approved Waterline Construction Plans (3 copies). Three full sets of approved plans are required. The Agreement for Water Main Extension will be prepared and sent to developer upon approval of the water main extension plans. The agreement will include the approved plans as Exhibit A and the Estimated Cost Form as Exhibit B. Subsequent Connector Fees will be established for Off-Site main projects and will be documented on the agreement. The fee is calculated by taking the total estimated cost of the main (including utility fees) and dividing it by the amount of serviceable frontage along the new main. Serviceable frontage includes all main that can be tapped for service, on both sides of the street. This fee is paid by any property owner, not a part of the development, who desires to connect to this main to receive water service. The fee is paid per foot of frontage that the property owner has on the main. This fee is collected by INAW and immediately refunded to the developer. The Utility has the right at any time to construct other new main extensions and appurtenant facilities connecting to the main extension installed by the developer. Neither the connection of any such new main extension nor any service connection furnished from it shall be subject to subsequent connector fees. The developer will not be entitled to any refund based on the new main extension or service connection from it. When the signed agreement is returned to INAW, the developer will be notified by letter that a pre-construction meeting may be scheduled. To schedule this meeting, call your Local Developer Services Contact. Construction The IDEM 30-Day waiting period for the NOI must be complete. The pre-construction meeting will be held with INAW, the developer, the contractor and the developer s engineer. The following items must be complete prior to the start of construction: Construction of road subgrade must be complete. Please note that some districts require curbs to be in place before main installation begins. This ensures that the main is located in the proper place and at the proper depth. Your local DSC can provide details on this requirement. Centerline or off-set stakes must be maintained until construction of the water main is complete

7 PAGE 7 OF 9 Developer must provide verification that all required permits have been obtained, prior to the start of construction. Obtaining the required permits and approvals is a critical element for the successful completion of your project. The Developer is responsible for all required permits and approvals, including all permit fees for the water mains and appurtenant facilities for the project. The contractor will install the water main as per the approved plans and according to the Indiana American Water Company Specifications. Developer s engineer shall provide written progress reports and periodic inspections of the main installation as required by INAW at the preconstruction meeting. Developer will have the new main flushed, disinfected and pressure tested. A representative from INAW must be present during this process. This representative will collect bacteriological samples and will send them to a State Certified Lab. The developer s representative must complete the Pressure and Leakage Tests for Main Extensions form and have it signed by the INAW representative. Acceptance After construction and testing is complete, the following items are required from the developer prior to acceptance of the water main by INAW: As-Built Drawings. The Developer will provide three sets of certified As-Built drawings. The drawings must meet Minimum Requirements for Preliminary Review, Approved and As-Built Drawings. All mains must be shown in right-of-way or easement, as documented on the final recorded plat or recorded easement documents. Note: Some districts may require additional smaller size as-built drawings for use in determining meter pit placement. Your DSC will discuss this with you. Certification by Engineer. This form is to be completed by the developer s engineer and must be stamped by a registered Professional Engineer. This document certifies the accuracy of the As-Built Drawings. Plat Map. Recorded final plat must be submitted. Final Actual Cost Form. This form documents the developers final actual costs for the project and it must be signed by the developer. If the cost varies substantially from the Estimated Cost Form provided at the beginning of the project, an explanation of

8 PAGE 8 OF 9 the difference may be requested. All materials listed on this form must match exactly to what is shown on the As-Built Drawings. Transfer of Ownership. This document transfers ownership of the new water main and appurtenances from the developer to INAW. The dollar amount at the top of the form must match the dollar amount on the Final Actual Cost Form. The Transfer of Ownership document must be signed by the developer. Utility Fee Check. Check for utility fee is required. The fee is a percentage of the final cost reported on the Final Actual Cost Form. The percentage is documented in the project agreement. Easements. Provide original recorded easement documents if required for your project. The easements must be on the INAW standard easement document and must be granted to INAW. The legal description of the easement and an easement drawing are required as exhibits. Final Inspection. Contact your local DSC to set up a final inspection of the main and its appurtenances. The inspection will include making sure that the valves and hydrants are to finished grade, the hydrants are painted properly, the valves are operational and the valve boxes are straight. The inspection will also include verification that the As-Built drawings match what was installed. Acceptance Letter. When all the above requirements have been met, an acceptance letter is mailed to the developer. This letter includes the amount of the Refundable Advance Account, described below. Refundable Advance Account. The developer has the opportunity to recover an amount up to, but not exceeding, their original investment in the main extension. The Refundable Advance Account is established in the amount of the actual cost of the main, as reported on the Final Actual Cost Form, plus the utility fee paid. Subsequent Connector Fees. For Off-Site main projects, the subsequent connector fee documented on the agreement will be revised based on the final actual costs of the project. A copy of the revised agreement page will be sent to the developer along with the Acceptance Letter. Main Upsizing. If a main upsizing refund is involved in your project, and documented on your agreement, the refund check will be issued at the time of project acceptance. Water Service Connections. New service connections may be requested from the local district after the acceptance letter has been issued.

9 PAGE 9 OF 9 Revenue Refunds A one-time revenue refund is issued for each new service connected to the main installed for your project. As described below, revenue refunds are based on connections to the main and the developer may or may not receive the entire Refundable Advance amount back in refunds. The refund period expires ten years from the in-service date of the project, as documented on the acceptance letter, or when the balance in the Refundable Advance Account is depleted. Residential refunds are calculated by using the estimated annual revenue for a residential customer. This one-year revenue amount is multiplied by three to establish a three-year revenue amount. The estimated cost of a service connection for a residential customer is then deducted from the three-year revenue to establish the refund amount. Commercial, Industrial, and Multifamily Refunds are calculated by using the actual first 12 months of revenue for the service. The first 12 months of revenue is multiplied by three to establish a three-year revenue. The cost for the service connection is then deducted from the three-year revenue to establish the refund amount. For the Indiana Northwest district (Gary), refunds are done throughout the year. Contact the local developer services contact for details. For all other Indiana districts, refunds are issued once a year, based on the following schedule: January Greenwood, Winchester February Kokomo, West Lafayette March Jeffersonville April New Albany, Newburgh May Richmond, Warsaw June Noblesville July Shelbyville August Wabash Valley/Sullivan, Mooresville September Wabash, Muncie, Somerset, Summitville October Crawfordsville, Franklin November - Seymour

CONTRACTOR WORK EXPERIENCE QUESTIONNAIRE AND QUALIFICATION STATEMENT. Designated Contact: Date: (Name of person to whom bid packages would be sent)

CONTRACTOR WORK EXPERIENCE QUESTIONNAIRE AND QUALIFICATION STATEMENT. Designated Contact: Date: (Name of person to whom bid packages would be sent) CONTRACTOR WORK EXPERIENCE QUESTIONNAIRE AND QUALIFICATION STATEMENT A-7 Submitted to: Shannyn Walker, P.E., Manager Engineering Planning Indiana American Water 555 East County Line Road, Suite 201 Greenwood,

More information

The checklist utilized by the Authority will be similar to that which is shown below. Project Name: Location: Consulting Engineering Firm:

The checklist utilized by the Authority will be similar to that which is shown below. Project Name: Location: Consulting Engineering Firm: Page 1 of 6 Section 1. PURPOSE This policy is an Engineering checklist of the Local Review Program for sanitary sewer improvement projects by the Bedford Regional Water Authority ( Authority ). Section

More information

FIRE SUPPRESSION INSTALLATION CITY OF HARRISONBURG, VIRGINIA

FIRE SUPPRESSION INSTALLATION CITY OF HARRISONBURG, VIRGINIA FIRE SUPPRESSION INSTALLATION CITY OF HARRISONBURG, VIRGINIA I. PURPOSE The purpose of this document is to provide planners and designers with information necessary in the design and construction of sprinkler

More information

Close-Out Documents... 9

Close-Out Documents... 9 Water and Sanitary Sewer Service Connection Requirements Service Connection Requirements... 1 Application for Services... 2 Water Meter Application... 2 Wet Tap/Tie-in Connection Requirements... 3 Meter

More information

CITY OF YORBA LINDA P.O. BOX 87014 CALIFORNIA 92885-8714

CITY OF YORBA LINDA P.O. BOX 87014 CALIFORNIA 92885-8714 CITY OF YORBA LINDA P.O. BOX 87014 CALIFORNIA 92885-8714 BUILDING DIVISION (714) 961-7120 Single Family Residential New Construction, Additions & Alterations Submittal Requirements Required agency approvals

More information

EXHIBIT A SCOPE OF SERVICES WATER SERVICE REPLACEMENT PROJECT. BROWARD OPERATIONS CENTER 5548 NW 9 th AVENUE FORT LAUDERDALE, FLORIDA 33309

EXHIBIT A SCOPE OF SERVICES WATER SERVICE REPLACEMENT PROJECT. BROWARD OPERATIONS CENTER 5548 NW 9 th AVENUE FORT LAUDERDALE, FLORIDA 33309 EXHIBIT A SCOPE OF SERVICES WATER SERVICE REPLACEMENT PROJECT BROWARD OPERATIONS CENTER 5548 NW 9 th AVENUE FORT LAUDERDALE, FLORIDA 33309 FLORIDA DEPARTMENT OF TRANSPORTATION DISTRICT FOUR 1.0 SCOPE OF

More information

RESIDENTIAL ON-SITE WASTEWATER TREATMENT SYSTEM (OWTS) INSTALLATION PERMIT (New or Repair) Instructions and Application Form

RESIDENTIAL ON-SITE WASTEWATER TREATMENT SYSTEM (OWTS) INSTALLATION PERMIT (New or Repair) Instructions and Application Form DEPARTMENT OF PUBLIC HEALTH AND ENVIRONMENT 1555 North 17 th Avenue Greeley, CO 80631 Web: www.weldhealth.org Health Administration Vital Records Tele: 970.304.6410 Fax: 970.304.6412 Public Health & Clinical

More information

Reference Guide for Obtaining Permits and Utility Services For New Construction

Reference Guide for Obtaining Permits and Utility Services For New Construction Reference Guide for Obtaining Permits and Utility Services For New Construction (Revised 04-2012) Table of Contents City Offices Telephone Numbers...1 Application for Utilities...2 Building Permits New

More information

SECTION 7 - CHARGES, FEES AND DEPOSITS

SECTION 7 - CHARGES, FEES AND DEPOSITS SECTION 7 - CHARGES, FEES AND DEPOSITS 7.1 Charges, fees, and deposits for areas managed or served by the District may be established and approved by the Board of Directors based on actual costs to serve

More information

ATTENTION BUILDERS, CONTRACTORS AND DEVELOPERS

ATTENTION BUILDERS, CONTRACTORS AND DEVELOPERS ATTENTION BUILDERS, CONTRACTORS AND DEVELOPERS Wellington Fire Protection District Development and Construction Plan Review Fee Policy. For any questions, contact the Fire Marshal at (970) 568-3232, ext

More information

SPECIFICATIONS FOR THE INSTALLATION OF FIRE ALARM SYSTEMS, SPRINKLER SYSTEMS, AND MASTER BOXES IN THE POQUONNOCK BRIDGE FIRE DISTRICT

SPECIFICATIONS FOR THE INSTALLATION OF FIRE ALARM SYSTEMS, SPRINKLER SYSTEMS, AND MASTER BOXES IN THE POQUONNOCK BRIDGE FIRE DISTRICT SPECIFICATIONS FOR THE INSTALLATION OF FIRE ALARM SYSTEMS, SPRINKLER SYSTEMS, AND MASTER BOXES IN THE POQUONNOCK BRIDGE FIRE DISTRICT The purpose of these specifications is to insure that there are minimum

More information

SECTION 5 DRAFTING STANDARDS

SECTION 5 DRAFTING STANDARDS SECTION 5 DRAFTING STANDARDS 1 SECTION FIVE TABLE OF CONTENTS Description Page TABLE OF CONTENTS... 5-2 GENERAL... 5-3 DRAFTING STANDARDS... 5-5 DRAFTING MINIMUM REQUIREMENTS HANDOUT... 5-8 2 GENERAL 1.

More information

How To Install An Overhead Sewer

How To Install An Overhead Sewer Village of Broadview Flood Control Assistance Program Village of Broadview 2350 S. 25 th Avenue, Broadview, IL 60155 INTRODUCTION The Village of Broadview is served by combined sewers which carry sewage

More information

LAKEHAVEN UTILITY DISTRICT. Developer Extension Agreement Application

LAKEHAVEN UTILITY DISTRICT. Developer Extension Agreement Application Applicant shall indicate that the required information has been provided or is not applicable to the project by placing the appropriate mark in the first column of this checklist. Missing or incomplete

More information

MERCER ISLAND FIRE DEPARTMENT FIRE COMMERCIAL SPRINKLER STANDARDS

MERCER ISLAND FIRE DEPARTMENT FIRE COMMERCIAL SPRINKLER STANDARDS MERCER ISLAND FIRE DEPARTMENT FIRE COMMERCIAL SPRINKLER STANDARDS COMMERCIAL FIRE SPRINKLER SYSTEMS Page 1-5 SCOPE: Fire sprinkler systems in the City of Mercer Island shall meet the criteria as set forth

More information

FORT WAYNE WATER UTILITY Fort Wayne, Indiana GENERAL RULES & REGULATIONS

FORT WAYNE WATER UTILITY Fort Wayne, Indiana GENERAL RULES & REGULATIONS FORT WAYNE WATER UTILITY Fort Wayne, Indiana GENERAL RULES & REGULATIONS Adopted and Approved by The Board of Public Works and effective as of February 12, 2003 TABLE OF CONTENTS GENERAL RULES AND REGULATIONS

More information

1.3.2 Method of construction and restoration of existing water service connections. This shall include:

1.3.2 Method of construction and restoration of existing water service connections. This shall include: 1.0 GENERAL 1.1 DESCRIPTION: This specification shall cover the rehabilitation of existing water lines using the GRUNDOCRACK PIPE BURSTING SYSTEM. Pipe bursting is a system by which the pneumatic bursting

More information

STANDARD SPECIFICATIONS AND STANDARD DRAWINGS FOR THE CONSTRUCTION OF

STANDARD SPECIFICATIONS AND STANDARD DRAWINGS FOR THE CONSTRUCTION OF STANDARD SPECIFICATIONS AND STANDARD DRAWINGS FOR THE CONSTRUCTION OF WATER FACILITIES Phil Lauri, P.E. District Engineer August 2014 1965 Placentia Avenue Costa Mesa, CA 92627 (949) 631-1291 AUGUST 2014

More information

CITY OF FARMERSVILLE, TEXAS

CITY OF FARMERSVILLE, TEXAS CITY OF FARMERSVILLE, TEXAS MANUAL FOR THE DESIGN OF WATER AND SANITARY SEWER LINES Subdivision Ordinance #2007-08 Exhibit B February 13, 2007 TABLE OF CONTENTS Description Page No. General... 1 Water

More information

The Borough Council hereby ordains:

The Borough Council hereby ordains: AN ORDINANCE OF THE BOROUGH DEFINING AND ESTABLISHING RATES AND REGULATIONS FOR WATER AND SEWER SERVICE TO PROPERTIES AND ESTABLISHMENTS THEREIN; REQUIRING AND REGULATING CONNECTIONS TO THE WATER AND SEWER

More information

City of Morro Bay Building Division 955 Shasta Ave., Morro Bay, CA 93442-1900, 805-772-6261

City of Morro Bay Building Division 955 Shasta Ave., Morro Bay, CA 93442-1900, 805-772-6261 City of Morro Bay Building Division 955 Shasta Ave., Morro Bay, CA 93442-1900, 805-772-6261 BUILDING PERMIT APPLICATION Permit No. Type Date Project Address Parcel No. Lot Block Tract Project Description:

More information

PWC SCHEDULE OF DEPOSITS, FEES AND CHARGES. Table of Contents

PWC SCHEDULE OF DEPOSITS, FEES AND CHARGES. Table of Contents PWC SCHEDULE OF DEPOSITS, FEES AND CHARGES Table of Contents I. DEFINITIONS... 2 II. DEPOSITS... 3 A. Establishment of Credit:... 3 B. Deposit Refunds:... 4 III. CUSTOMER SERVICE FEES AND CHARGES... 4

More information

Workflow Information Packet Land Development Projects

Workflow Information Packet Land Development Projects Workflow Information Packet Land Development Projects Typical Construction Flow Diagram for Land Development Projects Construction Plans Approved and Construction Permit Issued by Loudoun Water Pre-Construction

More information

City of El Paso City Plan Commission Staff Report

City of El Paso City Plan Commission Staff Report City of El Paso City Plan Commission Staff Report Revised Case No: SUSU14-00124 Fresno Place Replat A Application Type: Resubdivision Combination CPC Hearing Date: February 12, 2015 Staff Planner: Joaquin

More information

Items Required to Submit for Specialized Certificate of Occupancy for Operating a Sexually-Oriented Business City of Fort Worth, Texas

Items Required to Submit for Specialized Certificate of Occupancy for Operating a Sexually-Oriented Business City of Fort Worth, Texas Items Required to Submit for Specialized Certificate of Occupancy for Operating a Sexually-Oriented Business City of Fort Worth, Texas Applicant should review Chapter 5, Article 2, Comprehensive Zoning

More information

City of Grand Rapids. Rules and Regulations

City of Grand Rapids. Rules and Regulations City of Grand Rapids Rules and Regulations Table of Contents Section 1: Service Applications... 1 1.1 Application for Water/Sewer Services... 1 1.2 Application for New Construction... 2 Section 2: Owner

More information

Town of North Hero, Vermont Water Department. Private Water Line Transfer and Acceptance Policy

Town of North Hero, Vermont Water Department. Private Water Line Transfer and Acceptance Policy Town of North Hero, Vermont Water Department Private Water Line Transfer and Acceptance Policy Criteria for acceptance of existing private waterlines: 1. Main distribution water line must be a minimum

More information

CITY OF VAUGHAN SCHEDULE O LOT GRADING DESIGN FOR RESIDENTIAL DEVELOPMENT

CITY OF VAUGHAN SCHEDULE O LOT GRADING DESIGN FOR RESIDENTIAL DEVELOPMENT Page 1 CITY OF VAUGHAN SCHEDULE O LOT GRADING DESIGN FOR RESIDENTIAL DEVELOPMENT CIVIC CENTRE 2141 MAJOR MACKENZIE DRIVE MAPLE ONTARIO L6A 1T1 905-832-2281 Page 2 SECTION 1 - GENERAL OBJECTIVES To provide

More information

New Commercial Service Application

New Commercial Service Application Please submit with this form an application fee of $500.00 and an Electronic CAD file of your preliminary plat. CAD file can be emailed to craign@inlandpower.com. Member Information Work Order Number:

More information

SECTION 01 78 29 AS-BUILT DOCUMENTATION

SECTION 01 78 29 AS-BUILT DOCUMENTATION SECTION 01 78 29 AS-BUILT DOCUMENTATION PART 1: GENERAL 1.01 AS-BUILTS Where identified as a product of the Work, provide as-built drawings adhering to the criteria provided here and in the special conditions.

More information

REQUIREMENTS FOR OBTAINING A THORNBURY TOWNSHIP, DELAWARE COUNTY PERMIT

REQUIREMENTS FOR OBTAINING A THORNBURY TOWNSHIP, DELAWARE COUNTY PERMIT REQUIREMENTS FOR OBTAINING A THORNBURY TOWNSHIP, DELAWARE COUNTY PERMIT ATTACHED ARE THE REQUIREMENTS FOR OBTAINING A BUILDING PERMIT INCOMPLETE SUBMISSIONS WILL BE RETURNED IN THEIR ENTIRETY -- NO EXCEPTIONS!!

More information

SECTION 7 UNDERDRAIN SERVICE

SECTION 7 UNDERDRAIN SERVICE SECTION 7 UNDERDRAIN SERVICE ARTICLE I USE OF THE PUBLIC UNDERDRAIN SYSTEM 7.100 The purpose of the District s underdrain system is to provide a method for conveying ground water from around building foundations

More information

Business Entire Plumbing Contractions And Reviews

Business Entire Plumbing Contractions And Reviews MODIFICATIONS TO TUCSON WATER STANDARD WATERWORKS SPECIFICATION NO. 1445, PRIVATE PLUMBING REMOVE THE ENTIRE SECTION AND REPLACE WITH THE FOLLOWING: 1445.0100 1445.0101 GENERAL Description of Work The

More information

SECTION 02100 SITE PREPARATION

SECTION 02100 SITE PREPARATION SECTION 02100 SITE PREPARATION PART 1 - GENERAL 1.01 RELATED DOCUMENTS A. Drawings and General Provisions of Contract, including General Conditions and Supplementary Conditions and Division 1 through Division

More information

Note: All terms which are defined and which are used throughout this document appear in italicized text beginning with a CAPITAL letter.

Note: All terms which are defined and which are used throughout this document appear in italicized text beginning with a CAPITAL letter. SCHEDULE OF CONSULTANT S SERVICES Note: All terms which are defined and which are used throughout this document appear in italicized text beginning with a CAPITAL letter. Project (Insert name and description

More information

POLICIES, PROCEDURES & GENERAL DESIGN REQUIREMENTS

POLICIES, PROCEDURES & GENERAL DESIGN REQUIREMENTS POLICIES, PROCEDURES & GENERAL DESIGN REQUIREMENTS Approved by City Council September 17, 2009 Approved by City Council September 17, 2009 2 General Design Requirements TABLE OF CONTENTS SECTION 1 GENERAL

More information

How To Get A Fire Alarm Permit In Vail

How To Get A Fire Alarm Permit In Vail Fire and Emergency Services 2399 N. Frontage Road W. Vail, Colorado 81657 Tel: 970-479-2252 www.vailgov.com Fire Marshal FIRE ALARM PERMIT Commercial and Residential Fire Alarm shop drawings are required

More information

Tucson Electric Power Company Rules and Regulations

Tucson Electric Power Company Rules and Regulations Original Sheet No.: 907 Introduction The Company will construct, own, operate and maintain lines along public streets, roads and highways which the Company has the legal right to occupy, and on public

More information

SEWER BACKUP PREVENTION PROGRAM

SEWER BACKUP PREVENTION PROGRAM SEWER BACKUP PREVENTION PROGRAM PROGRAM DESCRIPTION The Village will provide partial funding for a Village approved overhead sewer, backflow prevention device and/or related equipment to single-family

More information

NTUA GUIDELINES FOR DESIGNING AN ELECTRICAL POWER DISTRIBUTION SYSTEM FOR NEW DEVELOPMENTS

NTUA GUIDELINES FOR DESIGNING AN ELECTRICAL POWER DISTRIBUTION SYSTEM FOR NEW DEVELOPMENTS NTUA GUIDELINES FOR DESIGNING AN ELECTRICAL POWER DISTRIBUTION SYSTEM FOR NEW DEVELOPMENTS These guidelines are intended to familiarize Developers regarding some issues that are important to get electric

More information

City of La Vernia 102 E. Chihuahua Street, La Vernia, Texas 78121 Phone: (830)779-4541 Fax: (830) 253-1198 cityoflavernia@lavernia-tx.

City of La Vernia 102 E. Chihuahua Street, La Vernia, Texas 78121 Phone: (830)779-4541 Fax: (830) 253-1198 cityoflavernia@lavernia-tx. cityoflavernia@lavernia-tx.gov Commercial New/Remodel Building Requirements This document is not meant to modify any Federal or State laws or City Ordinances. It is intended to be informative and to be

More information

505.3.6 For a building with a crawl space, see Figure 10. 505-1

505.3.6 For a building with a crawl space, see Figure 10. 505-1 505 WATER SERVICE INSTALLATION 505.1 DEFINITION A service line is comprised of the piping and related appurtenances including the connection installed from the Des Moines Water Works water main to the

More information

CHAPTER 12 Revised January 1, 2013 SIGNING AND SEALIN OF PROFESSIONAL SURVEY DELIVERABLES

CHAPTER 12 Revised January 1, 2013 SIGNING AND SEALIN OF PROFESSIONAL SURVEY DELIVERABLES CHAPTER 12 Revised January 1, 2013 SIGNING AND SEALIN OF PROFESSIONAL SURVEY DELIVERABLES Chapter Contents Sec. 12.01 Sec. 12.02 Sec. 12.03 Sec. 12.04 Sec. 12.05 Sec. 12.06 Introduction Business & Legal

More information

ENGINEERING DESIGN GUIDELINES. for SUBDIVISIONS OR COMMERCIAL DEVELOPMENTS

ENGINEERING DESIGN GUIDELINES. for SUBDIVISIONS OR COMMERCIAL DEVELOPMENTS ENGINEERING DESIGN GUIDELINES for SUBDIVISIONS OR COMMERCIAL DEVELOPMENTS City of Birmingham Department of Planning, Engineering and Permits Engineering Division Office of the City Engineer 2008 TABLE

More information

EWEB is also in need of updating its meter installation and service installation fees which have not changed since June 2006.

EWEB is also in need of updating its meter installation and service installation fees which have not changed since June 2006. M E M O R A N D U M EUGENE WATER & ELECTRIC BOARD TO: Commissioners Simpson, Brown, Helgeson, Manning and Mital FROM: Mel Damewood, Engineering Manager Brad Taylor, Water Operations Manager DATE: October

More information

Contractor s License & Endorsements

Contractor s License & Endorsements Planning, Development & Transportation Engineering Department 281 North College Avenue P.O. Box 580 Fort Collins, CO 80522.0580 970.221.6605 970.221.6378 - fax fcgov.com/engineering Contractor s License

More information

SERVICE RULES AND REGULATIONS LOUISVILLE WATER COMPANY

SERVICE RULES AND REGULATIONS LOUISVILLE WATER COMPANY 2015 SERVICE RULES AND REGULATIONS LOUISVILLE WATER COMPANY TABLE OF CONTENTS 1.0 Water Service and Meters 1.01 General Policies 1.01.1 Application of Rules... page 1 1.01.2 Violation of Rules... page

More information

Memorandum Potentially Affected AIA Contract Documents AIA Document A105 2007 AIA Document B105 2007 Important Information

Memorandum Potentially Affected AIA Contract Documents AIA Document A105 2007 AIA Document B105 2007 Important Information Memorandum Important information related to requirements of state or local laws to include additional provisions in residential construction contracts Potentially Affected AIA Contract Documents AIA Document

More information

City of Grand Rapids. Rules and Regulations

City of Grand Rapids. Rules and Regulations City of Grand Rapids Rules and Regulations 1 Table of Contents Section 1: Service Applications... 6 1.1 Application for Water/Sewer Services... 6 1.2 Application for New Construction... 6 Section 2: Owner

More information

FIVE YEAR CERTIFICATION REPORT

FIVE YEAR CERTIFICATION REPORT GARDEN GROVE FIRE DEPARTMENT FIRE PREVENTION DIVISION FIVE YEAR CERTIFICATION REPORT Service and maintenance report of automatic fire extinguishing systems, including fire sprinklers, dry, deluge, and

More information

Right-of-Way Permit Application Process (Plans that affect District owned or maintained right-of-way)

Right-of-Way Permit Application Process (Plans that affect District owned or maintained right-of-way) Flood Control District of Maricopa County (District) 2801 W. Durango Street Phoenix, AZ 85009 Telephone: 602-506-4583 or 602-506-5476 Fax: 602-506-1663 Right-of-Way Permit Application Process (Plans that

More information

A Century of Progress with Pride

A Century of Progress with Pride The City of Berwyn Engineering Department A Century of Progress with Pride November 12, 2014 Re: Waiting List Application I am interested in the following programs and would like to be added to the waiting

More information

2015 Calendar Year. Residential Accounts. Residential Accounts. Department of Water Resources (DWR) Rates & Fees

2015 Calendar Year. Residential Accounts. Residential Accounts. Department of Water Resources (DWR) Rates & Fees Rates & Fees Residential Accounts Residential Accounts 2015 Calendar Year Initial Charges New Construction or Irrigation 3 Base Meter 2 Account Activation Fee System Development Charge 1 Size Meter Fee

More information

SECTION 8 WATER SUPPLY SYSTEMS

SECTION 8 WATER SUPPLY SYSTEMS SECTION 8 WATER SUPPLY SYSTEMS Contents Page 8-1 INTRODUCTION... 1 8-2 INTENT OF WATER SYSTEM IMPROVEMENT STANDARDS... 1 8-3 DEFINITIONS... 1 8-4 APPLICABLE STANDARDS... 1 8-5 IMPROVEMENT AND LANDSCAPE

More information

Construction Management Program

Construction Management Program Use and Limitation: The Sponsor may use this document as a guide in preparing a construction management program for their specific project. Sponsors and Consultants are cautioned that the provision of

More information

Utility Service Application

Utility Service Application Utility Service Application for Multi-family/Non-residential Developments Thank you for contacting the City of Tampa for your water and wastewater utility service needs. We have assembled this package

More information

Utility Customer Service

Utility Customer Service Utility Customer Service NEW CHANGES TO CHAPTER 47 WATER & WASTEWATER ORDINANCE PROVISIONS Chapter 47 of the City Code of Ordinances regarding Water and Sewer services has received its first major overhaul

More information

MOBILE HOME SERVICE REQUIREMENTS GAS

MOBILE HOME SERVICE REQUIREMENTS GAS ELECTRIC AND GAS 1.0 INDEX 1.0 INDEX 2.0 PURPOSE 3.0 GENERAL 4.0 REFERENCE MATERIAL 5.0 TYPICAL UNDERGROUND UTILITY LAYOUT 6.0 METER PAD DETAILS 7.0 GENERAL INSTALLATION PROCEDURES 8.0 PEDESTAL SPECIFICATIONS

More information

Water Services and Utilities - General Regulations in Ohio

Water Services and Utilities - General Regulations in Ohio WATER AND SEWER RULES AND REGULATIONS March 2015 TABLE OF CONTENTS SECTION 1 - GENERAL RULES...1 1.1 GENERAL REGULATION...1 1.2 DEFINITIONS...1 1.3 FIXED PRESSURE NOT GUARANTEED...1 1.4 WATER QUALITY NOT

More information

Appendix F Subdivision Street Construction Applications and Forms

Appendix F Subdivision Street Construction Applications and Forms Appendix F Subdivision Street Construction Applications and Forms Subdivison Street Construction Process: Applicant submits the following: o Copy of the recorded record plan o Approved construction drawings

More information

How To Get Water From A Water Meter

How To Get Water From A Water Meter TITLE 150 LEGISLATIVE RULE PUBLIC SERVICE COMMISSION SERIES 7 RULES FOR THE GOVERNMENT OF WATER UTILITIES 150-7-1. General. 1.1. Scope -- These rules govern the operation and service of water utilities

More information

ACEDP LOW- AND MODERATE-INCOME HOOKUPS PROCESS

ACEDP LOW- AND MODERATE-INCOME HOOKUPS PROCESS ACEDP LOW- AND MODERATE-INCOME HOOKUPS PROCESS I. INTRODUCTION Use of Arkansas Community and Economic Development Program (ACEDP) funds to connect low and moderate-income residents to utility systems is

More information

Sample Company SECTION 019113 GENERAL COMMISSIONING REQUIREMENTS PART 1 GENERAL 1.1 SUMMARY AND CONTRACT RESPONSIBILITIES

Sample Company SECTION 019113 GENERAL COMMISSIONING REQUIREMENTS PART 1 GENERAL 1.1 SUMMARY AND CONTRACT RESPONSIBILITIES SECTION 019113 GENERAL COMMISSIONING REQUIREMENTS PART 1 GENERAL 1.1 SUMMARY AND CONTRACT RESPONSIBILITIES A. The Owner will contract separately and directly for the majority of the commissioning work

More information

Your Guide To. Development. Services

Your Guide To. Development. Services Your Guide To Development Services Table of Contents Section introduction...1 Project Development Process...2 critical Dates for Services...3 Demolition Procedures...4 obtaining Potable Water Service...5

More information

Attachment 5 Electrical Engineering

Attachment 5 Electrical Engineering A. Phase 1, Preliminary Design: The CONSULTANT shall: Attachment 5 Electrical Engineering 1. Ascertain the requirements for each project through a meeting with the Capital Projects Division Manager or

More information

Application Package for License for Sidewalk Dining Adjacent to Eating Establishment

Application Package for License for Sidewalk Dining Adjacent to Eating Establishment Application Package for License for Sidewalk Dining Adjacent to Eating Establishment Community & Economic Development Department Planning Division T :: 831.648.3190 F :: 831.648.3184 www.ci.pg.ca.us/cedd

More information

Fire Alarm System Submissions

Fire Alarm System Submissions Gypsum Fire Protection District Fire Alarm System Submissions As of July 1 st, 2007 all Fire Alarm Submissions will be required to be signed by a NICET Level 3 or higher. Fire Alarm System Submissions

More information

Town of Beaumont. Lot Grading Guidelines

Town of Beaumont. Lot Grading Guidelines Town of Beaumont Lot Grading Guidelines LOT GRADING APPROVAL PROCESS Lot Grading Guidelines... 3 Introduction... 3 Purpose... 3 Definitions... 3 Lot Grading... 3 Lot Grading Plan... 3 Lot Grading Certificate...

More information

SEWER LINE EXTENSION DESIGN CHECKLIST

SEWER LINE EXTENSION DESIGN CHECKLIST SEWER LINE EXTENSION DESIGN CHECKLIST SWLE# Utilities Staff Date DISCLAIMER - This checklist is provided to Consulting Engineers for the express purpose of assisting them in compiling design plans for

More information

CHECKLIST TO DESIGNATE AREAS OF EVALUATION FOR REQUESTS FOR PROPOSAL (RFP)

CHECKLIST TO DESIGNATE AREAS OF EVALUATION FOR REQUESTS FOR PROPOSAL (RFP) Michigan Department Of Transportation 5100B (05/13) CHECKLIST TO DESIGNATE AREAS OF EVALUATION FOR REQUESTS FOR PROPOSAL (RFP) Page 1 of 2 REQUISITION NUMBER DUE DATE TIME DUE MDOT PROJECT MANAGER JOB

More information

City of Lubbock Public Works Engineering Design Standards and Specifications

City of Lubbock Public Works Engineering Design Standards and Specifications City of Lubbock Public Works Engineering Design Standards and Specifications Department of Public Works Engineering City of Lubbock, Texas January 1, 2012 These Standards and Specifications are general

More information

Transformer Deluge Systems

Transformer Deluge Systems Transformer Deluge Systems How Do Transformer Fires Ignite? Common causes of transformer failure: Weather-related events such as lightning Short circuits in electrical equipment The most common cause is

More information

1. It would create hazardous effects of storm water run-off. 3. It would increase hazardous driving conditions on the public road.

1. It would create hazardous effects of storm water run-off. 3. It would increase hazardous driving conditions on the public road. SECTION 6: REQUIREMENTS FOR A DRIVEWAY CONNECTION A. Required information. The application shall be accompanied by a sketch of the proposed driveway which at a minimum shall indicate: 1. Geometric information

More information

DESIGN and CONSTRUCTION STANDARDS

DESIGN and CONSTRUCTION STANDARDS Design and Construction Standards DESIGN and CONSTRUCTION STANDARDS TABLE OF CONTENTS GENERAL REQUIREMENTS 1 INTRODUCTION and POLICIES 2 ENGINEERING PROCEDURES 3 FEES AND BONDS WATER STANDARDS 1 WATER

More information

Special Specification 7021 Water Main and Sewer Line Replacements

Special Specification 7021 Water Main and Sewer Line Replacements Special Specification 7021 Water Main and Sewer Line Replacements 1. DESCRIPTION Furnish, install, or replace water pipe, water valves, water meters and boxes, water service connections, fire hydrant assemblies,

More information

RESIDENTIAL BUILDING PERMIT REQUIREMENTS

RESIDENTIAL BUILDING PERMIT REQUIREMENTS RESIDENTIAL BUILDING PERMIT REQUIREMENTS The Building Inspection Division has compiled this packet to help our customers obtain a Building Permit. Enclosed we have listed all departments and inspection

More information

SERVICE RULES AND REGULATIONS LOUISVILLE WATER COMPANY

SERVICE RULES AND REGULATIONS LOUISVILLE WATER COMPANY 2014 SERVICE RULES AND REGULATIONS LOUISVILLE WATER COMPANY TABLE OF CONTENTS 1.0 Water Service and Meters 1.01 General Policies 1.01.1 Application of Rules... page 1 1.01.2 Violation of Rules... page

More information

SIERRA LAKES COUNTY WATER DISTRICT P.O. Box 1039, Soda Springs, CA 95728-1039 (7300 Short Road, Serene Lakes)

SIERRA LAKES COUNTY WATER DISTRICT P.O. Box 1039, Soda Springs, CA 95728-1039 (7300 Short Road, Serene Lakes) SIERRA LAKES COUNTY WATER DISTRICT P.O. Box 1039, Soda Springs, CA 95728-1039 (7300 Short Road, Serene Lakes) Maintenance Office Administrative Office Billing Office 530-426-7802 530-426-7800 916-332-4872

More information

Application for the Construction or Installation of Aboveground Storage Tank (AST) Systems or Associated Underground or Over-water Piping Systems

Application for the Construction or Installation of Aboveground Storage Tank (AST) Systems or Associated Underground or Over-water Piping Systems Page 1 of 5 Application for the Construction or Installation of Aboveground Storage Tank (AST) Systems or Associated Underground or Over-water Piping Systems New Hampshire Department of Environmental Services

More information

PROCEDURE MANUAL FOR ENGINEERING CONSULTANTS

PROCEDURE MANUAL FOR ENGINEERING CONSULTANTS PROCEDURE MANUAL FOR ENGINEERING CONSULTANTS CITY OF GREATER SUDBURY ENGINEERING SERVICES DIVISION JUNE 2005 TABLE OF CONTENTS Chapter 1 - Reference Procedure Manuals and Specifications - CAD Drawing Requirements

More information

SECTION IV - TESTS AND INSPECTIONS PART 1 - GENERAL. 1.01 Testing - General

SECTION IV - TESTS AND INSPECTIONS PART 1 - GENERAL. 1.01 Testing - General SECTION IV - TESTS AND INSPECTIONS PART 1 - GENERAL 1.01 Testing - General Testing shall be of the type and frequency described in each section and summarized in Item 1 of this section. In addition to

More information

CITY OF SURREY BY-LAW NO. 6569

CITY OF SURREY BY-LAW NO. 6569 CITY OF SURREY BY-LAW NO. 6569 As amended by By-laws No. 7026, 02/01/82; 9960, 03/13/90; 10368, 01/22/90; 10797, 01/28/91; 12268, 04/25/94; 12384, 07/02/94; 12828, 05/13/96; 13171, 07/29/97; 13220, 09/22/97;

More information

in the Real Estate Transaction

in the Real Estate Transaction The Critical Role of the REALTOR in the Real Estate Transaction Listed here are nearly 200 typical actions, research steps, procedures, processes, and review stages in a successful residential real estate

More information

Prescriptive, Custom, New Construction and Data Center

Prescriptive, Custom, New Construction and Data Center Construction and Data Center Application Terms & Conditions and Final Payment Agreement Version: November 2014 TERMS AND CONDITIONS Program Effective Dates AEP Ohio Business Incentives Program offers incentives

More information

Independent School District No. 1 Strive Achieve Succeed Go Beyond Lewiston, Idaho

Independent School District No. 1 Strive Achieve Succeed Go Beyond Lewiston, Idaho Independent School District No. 1 Strive Achieve Succeed Go Beyond Lewiston, Idaho REQUEST FOR QUALIFICATIONS Independent School District No. 1, Lewiston, Idaho ( District ) is seeking responses from individuals

More information

REQUEST FOR PROPOSALS

REQUEST FOR PROPOSALS REQUEST FOR PROPOSALS Solicitation Number: R-14-007-MR Transfer and Implementation of Data Records to GIS Ready Files ADDENDUM #2 05:00 PM Central June 5, 2014 This addendum answers questions submitted

More information

WINDOW AND DOOR REPLACEMENT REQUIREMENTS

WINDOW AND DOOR REPLACEMENT REQUIREMENTS WINDOW AND DOOR REPLACEMENT REQUIREMENTS Should you have any questions after reading the following information, please call the Building Inspection Department at 651-439-4439 to discuss the topics of concern.

More information

LAKES REGION SANITARY DISTRICT COST REIMBURSEMENT PROGRAM FOR THE INSTALLATION OF OVERHEAD SEWERS OR BACKFLOW PREVENT DEVICES

LAKES REGION SANITARY DISTRICT COST REIMBURSEMENT PROGRAM FOR THE INSTALLATION OF OVERHEAD SEWERS OR BACKFLOW PREVENT DEVICES PROGRAM REQUIREMENTS The District will provide funds to building owners who have or may experience sanitary sewer backups during periods of heavy rainfall for the installation of overhead sewers or backflow

More information

d. Building permits may only be approved if consistent with the approved development plan and land division for all units with common walls.

d. Building permits may only be approved if consistent with the approved development plan and land division for all units with common walls. Section 20.920.060 Tier 2 Infill Standards. In addition to the Tier 1 standards and incentives, Tier 2 infill parcels and land divisions and the subsequent development on those Tier 2 infill parcels shall

More information

SERVICE AGREEMENT. Page 1

SERVICE AGREEMENT. Page 1 1 26 A l to n A d a m s D ri ve, W a xa h a c hi e, T e xa s 7 51 65 P. O.B o x 40, R e d O a k, T e xa s 7 51 54 9 72-61 7-3 52 4 O ffi c e 97 2-6 17-00 30 F a x w w w. ro ck e t tw a te r. co m SERVICE

More information

Applicants are required to file an original and five (5) paper copies.

Applicants are required to file an original and five (5) paper copies. APPLICATION FOR A CERTIFICATE OF TERRITORIAL AUTHORITY FOR COMMUNICATIONS SERVICE PROVIDERS State Form 52648 (R5 / 8-11) INDIANA UTILITY REGULATORY COMMISSION Applicants are required to file an original

More information

TOWNSHIP OF BRIGHTON REQUEST FOR PROPOSALS SANITARY SEWER REPAIRS AND/OR GRINDER PUMP INSTALLATION

TOWNSHIP OF BRIGHTON REQUEST FOR PROPOSALS SANITARY SEWER REPAIRS AND/OR GRINDER PUMP INSTALLATION TOWNSHIP OF BRIGHTON REQUEST FOR PROPOSALS SANITARY SEWER REPAIRS AND/OR GRINDER PUMP INSTALLATION April 25, 2014 DUE DATE/LOCATION: Friday, May 9, 2014 Bid forms and references are due by 9:30 A.M. at:

More information

DESIGN STANDARDS MANUAL

DESIGN STANDARDS MANUAL DEPARTMENT OF PUBLIC UTILITIES CITY OF VIRGINIA BEACH, VA DESIGN STANDARDS MANUAL Revised Table of Contents Table of Contents 1 Introduction... 1-1 1.1 Authority... 1-1 1.2 Revisions... 1-1 1.3 Organization

More information

Request for Proposal # 2016-054

Request for Proposal # 2016-054 Request for Proposal # 2016-054 GIS Editing & Updating Services Due Date: July 7, 2016 Time: 2:00PM Receipt Location: Government Center, 500 N. Main Street, 7 th Floor, Room #709, Monroe, NC 28112 Procurement

More information

3. Contractor shall ensure that all permits are obtained prior to any construction. Contractor shall be responsible for all utility fees.

3. Contractor shall ensure that all permits are obtained prior to any construction. Contractor shall be responsible for all utility fees. The following shall serve as the minimum requirements for contractors performing work in relation to the Authority s potable water and sanitary sewer system(s), appurtenances and service connections. General:

More information

Bylaw No. 8880. Private Sewer and Water Service Connection Bylaw, 2010

Bylaw No. 8880. Private Sewer and Water Service Connection Bylaw, 2010 Bylaw No. 8880 Private Sewer and Water Service Connection Bylaw, 2010 Codified to Bylaw No. 9202 June 23, 2014 BYLAW NO. 8880 The Private Sewer and Water Service Connection Bylaw, 2010 Whereas pursuant

More information

WATER & SEWER SERVICES

WATER & SEWER SERVICES WATER/SEWER ENGINEERING SECTION PHONE (703) 228-3677 WATER & SEWER SERVICES INFORMATION & APPLICATION PACKAGE REVISED MAY 2014 1 MAY 2014 Dear Customer: Thank you for taking the time to read this information

More information

Land development manual Section 73 Compliance Certificate application process

Land development manual Section 73 Compliance Certificate application process Land development manual Section 73 Compliance Certificate application process Published by Sydney Water PO Box 399 Parramatta NSW 2124 sydneywater.com.au Copyright 2013 Sydney Water Corporation Sydney

More information

SOLD. Lot 1. 1 Mile: Population: 10,200 Median HH Income: $33,100. 3 Mile: Population: 80,200 Median HH Income: $34,900

SOLD. Lot 1. 1 Mile: Population: 10,200 Median HH Income: $33,100. 3 Mile: Population: 80,200 Median HH Income: $34,900 Walmart Outparcels For Sale College Station, TX Store # 1150 1815 Brothers Blvd FM 2818 W SOLD Texas Ave S/ Hwy 6 Longmire Dr Brothers Blvd Lot 1 For more information about this site, contact: Lot 1: ±2.41

More information

AGREEMENT FOR CONSTRUCTION MANAGEMENT SERVICES. Responsibilities of Construction Manager Scope of Construction Manager s Basic Services

AGREEMENT FOR CONSTRUCTION MANAGEMENT SERVICES. Responsibilities of Construction Manager Scope of Construction Manager s Basic Services AGREEMENT FOR CONSTRUCTION MANAGEMENT SERVICES Article I Article II Article III Article IV Article V Article VI Article VII Article VIII Article IX Responsibilities of Construction Manager Scope of Construction

More information