Options Assessment for Structuring and Financing new Hydropower in PNG

Size: px
Start display at page:

Download "Options Assessment for Structuring and Financing new Hydropower in PNG"

Transcription

1 Options Assessment for Structuring and Financing new Hydropower in PNG Issues and Options Report - Revised Judith Plummer November 2011

2 CONTENTS Summary Introduction...4 Purpose of this Paper...4 Background...4 Public versus Private Lessons from international experience...5 General...5 Single off-taker with some domestic use and a negotiated concession...6 Merchant Project without a long term power purchase agreement...7 Project with a split ownership...7 Projects let by competitive bidding Risks...10 Types of Risk...10 Structuring the project...12 Legal framework and regulatory regime...12 Environmental and social permitting...13 Issues of land ownership...13 Credit worthiness...13 Public versus private development Financing...15 Sources of finance...15 Financing plan...16 Illustration of Impact of Debt Tenor on Tariff Structure of transaction and impacts for Government...18 Economic and financial benefits accruing to Government...18 Format of concession...19 Forming a transaction Next Steps...23

3 Summary Hydropower provides a clean renewable source of energy when developed and managed responsibly. However, such projects are inherently risky because of their location, size, and nature. It is possible for Governments to off-load some of this risk to the private sector, but only at a cost (risk premium). Thus the question of financing and development of hydropower is always a matter of balancing both risk and cost. Hydropower projects can last for many decades and, after the initial debt financing has been repaid, can provide a source of electricity which is cheaper than most other options. The long term nature of the projects, together with the public nature of the resources involved has often caused Governments to feel that such projects should be developed in the public sector. However, hydropower projects have, in the past, had a reputation internationally for delays, cost overruns and poor management; particularly those developed in the public sector. One response to the difficulties encountered by public sector hydro has been to allow private sector development. While this can lead to improved efficiency, majority privately financed and developed hydro projects may have high tariffs in the early years after commissioning given the requirement to service the full cost of the debt incurred in construction over a short tenor. These tariffs are likely to be higher than the equivalent public sector project which may be eligible for lower cost, longer tenor debt finance or guarantees. Depending on the incentives in the off-take agreement, private sector projects may not necessarily be operated in such a way as to ensure maximisation of the economic gain for the country. To gain the benefits of all the options it may be possible to create a public private partnership to develop a project. The challenge is to structure the project to obtain the financing required to meet the tariff profile objective. In all cases the model needs to be commercially viable and sustainable, but precisely which model is appropriate depends on the intent of the project, broadly projects may fall into one or a combination of the following categories: - Where the project is built mainly to serve a single commercial, export or industrial off-taker it may be appropriate to develop it in the private sector with an emphasis on safe and sustainable development with maximization of the financial and economic gains for the country. Where the project is developed mainly for domestic use, it may be largely publicly developed using a form of public private partnership which is likely to maximise the benefit of available (development) finance options and minimise any adverse tariff impacts in the early years particularly for poorer consumers. Where the project is for mixed domestic and industrial use then a private public partnership may again be appropriate, but may be more complex to structure with emphasis both on maximizing financial and economic gains to the government from the project while providing quality commercial power supplies and also minimising any adverse domestic tariff impacts in the early years. Any combination of these models may be appropriate depending on the specific circumstances of the project concerned. Development of a hydropower project requires strong and experienced leadership. These skills can be hired in on a contract basis, but are likely to be more effective if they are exercised through a private investor. The likelihood of attracting such a private investor depends on the risk profile of the project. Careful attention to the management, mitigation and allocation of responsibility for various risks can do much to improve the attractiveness of a project for finance. Government needs to consider its preferred options in terms of project structure and risk allocation, based on extensive financial and economic modelling. It should be noted however, that the economic gains can be lost or reduced through delay in such decision making, so once information is available early decision making will be imperative.

4 1 Introduction Purpose of this Paper The objective of this issues summary paper, as specified in the terms of reference, is to set out a range of options for ownership, financing and arrangements for sharing the financial benefits for discussion with stakeholders in Papua New Guinea (PNG). The options analysis will explore private sector and public-private partnership models and compare these to a more public sector dominated approach. The paper begins by considering international examples of hydropower development with specific reference to finance considering the key issues of risk, financing and benefit sharing between Government and the developer. Finally the paper will suggest further steps, for discussion, that could be considered when setting out to pursue increased hydropower development. Background It is estimated that 12 % of PNG s population has access to electricity (According to the World Bank draft project appraisal document). The Government of PNG has set a target of achieving 70% access by To date, it has not been practical to establish a national power grid in PNG, due to the country s very rugged, mountainous terrain and capital constraints so the country has four separate main power grids, but large parts of the country remain un-electrified. Papua New Guinea s technically and economically feasible hydropower potential is estimated in excess of 4200 MW ( GWh/year) of which less than 5% has been developed to date ( The most significant growth in demand in the next few years is expected to be in Port Moresby, which is also an area where some plant is reaching the end of its life. As a result PNG Power Ltd. (PPL) is interested in pursuing the 80MW Naoro Brown Hydropower Project due to its proximity to Port Moresby. However, in addition, other projects which could serve demand in other parts of the country (both domestic and industrial) or serve new industries are also under consideration by both PPL and private developers. Public versus Private It is may be useful at this point to discuss the issue of public versus private. It is a popular misconception that there exists a hydropower project which is either totally private or totally public. Almost every project in the world requires the participation of both public and private sectors in some form. For example a privately funded and executed project must liaise with both central and local government on a range of issues of concern and legal necessities. It is very difficult for a private operator to implement a project without the support and cooperation of the public sector. Similarly a publicly funded and executed project will generally involve procurement and contracting or subcontracting to the private sector. Thus all projects are a combination of public and private aspects. However for the purposes of this report we will use the term Public for the project that is largely publicly developed and funded; the term private for a project which is largely privately developed and funded; and Public Private Partnership (PPP) for projects which involve both public and private finance. It should also be noted that projects may be publicly led (even though largely privately funded) or privately led (even though largely publicly funded). The leadership defines the control of the development rather than the funding. As will be shown in the sections which follow the level of private and public interest - as well as the lead role- can affect the financing and structure of the project.

5 2 Lessons from international experience General The concept of an independent power producer (IPP) became prevalent in the 1990s. Thermal power projects are routinely financed in this way, but using such a private development approach proved difficult for hydropower because of their particular characteristics of: - Capital intensive hydropower projects have high initial capital costs: higher than the equivalent thermal power station. As with any highly capital intensive infrastructure projects this can provide opportunities for corruption. Unrecognised (unremunerated) benefits hydropower projects may have additional benefits such as grid stabilisation, water storage, flood control, provision of access roads, and establishment of fish habitats or centres of tourism. While these may be significant benefits to the country the value of these benefits may not accrue to a private developer. Social and environmental safeguard issues - hydropower projects have historically become identified with poor standards of social and environmental implementation. While improvements have been made in these areas, contractors still have concerns over the risk of delays caused by protest by non-governmental or other interest groups. High front-end risk profile - hydropower projects are considered high risk (see further details in subsequent sections), but the risks are also frontloaded in a project, such that developers need a long period of operation (which tends to be low risk) to counter the high levels of risk encountered during construction. As a result private hydropower is still relatively rare, but in recent years private financing has shown interest in new generation projects in a range of countries, particularly where the power is to be used for industry or for export. The recent trend is for more forms of Public-Private Partnership where both sectors participate in the financing and ownership, as well as sharing the risks and rewards. Such arrangements are often the only solution when public funds are scarce and the private sector is unwilling to assume all of the cost and the risks. The reasons some governments choose to involve private sector is that they may bring good commercial practice to reduce construction and operation costs and, possibly, to ensure timely project delivery. The private sector may also have access to specific finance which may not be available to a public sector entity (see section on Financing) and which may be critical for financing the project if public resources are insufficient. The long concession periods noted above are possible given the long productive life of a hydropower project (often more than fifty years). However, it is difficult to find private finance which is of longer than about 12 year tenor (without use of guarantees or other credit enhancements). As a result the project struggles to cover its costs and repay its debts in the early years, but continues to yield revenues for many years. This profile of revenues is difficult for private operators to accommodate and most will require high tariffs in the early years to cover the cost of debt repayments. For this reason the Government returns from a project are sometimes built on a stepped basis to keep the Government returns low during the initial debt servicing phase and increase them later.

6 The additional benefits noted above, together with the traditional economic benefits of a large construction project and increased availability of productive power, can lead to significant economic benefits to a hydropower project well in excess of the financial benefits. However, even for a government agency these benefits are difficult to monetise and for a private operator they are impossible. Thus although the decision to develop a project should be based on the economic gain to the country; the decision as to whether finance will be available and whether the private sector will be willing to develop it, depend on the financial returns and the risk profile. This referred to as the gap between economic and financial viability and possibly the most significant problem in hydropower development, particularly if the project has more than one purpose (e.g. electricity and flood control). The economic costs and benefits particularly the secondary or less obvious costs and benefits are rarely well assessed. Most analysis is carried out on a project basis or from the developer s point of view and thus does not include such issues as the secondary benefits to the local economy or environmental losses which are key to Government decision making. Such is the comparative rarity and complexity of private or public/private hydropower developments; it is not possible to outline a typical project. Some recent projects have been financed on the basis of a single or majority industrial off-taker who guarantees to use most of the power produced. These projects may be similar whether the power is used for domestic industry, industrial production for export, or export of power. In Iceland, for example, they have imported consumers such as an international aluminium plant as it is difficult for the country to afford the cost of a dedicated cable to export their surplus power Europe. Most arrangements are still bespoke to the project concerned. However the following projects give an indication of a range of possibilities such as single off-taker projects, merchant projects and split ownership projects; together with some examples of the use of competitive bidding for private sponsor/developers: - Single off-taker with some domestic use and a negotiated concession Theun Hinboun Hydropower Lao PDR 120 MW Theun Hinboun was Lao PDR s first IPP concession. The project was let on a negotiated basis for an initial concession period of 30 years with an option for a ten year extension with the majority of electricity being evacuated to Thailand. Royalties are paid to the Ministry of Finance in the amount of 5% of all revenues for the duration of the project concession plus income tax at 15% subject to a five year tax holiday. Dividends (of some US$ 20 million) are also paid to the Lao PDR Government s state owned power company, in line with its 60% equity share (financed though and ADB loan). In addition the project was made responsible for US$ 2.6 million of costs associated with environmental mitigation. On termination of the concession the plant reverts to Lao Government ownership. Thus this is a private export project, but one which has benefited from a high level of public support from the outset. The originally planned 65/35 debt to equity ratio became 55/45 after the Asian currency crisis seriously disrupted financing during construction: further refinancing after several years of operation released the capital necessary for expansion as well as releasing capital for the shareholders. Nam Theun 2 Hydropower Lao PDR 1,070 MW Recently completed, Nam Theun 2, it is one of the largest private financing arrangements of any hydro project. The total cost of $1.45 billion was financed through a complex mix of commercial loans backed by guarantees, private equity, and aid. The project was financed on a 72/28 debt to equity ratio. The Lao Government holds 25 percent of the equity, for which funding was obtained from Multilateral Development Banks. Some US$500 million of debt was raised from international banks on the basis of guarantees from the World Bank and other multilateral development banks, and another US$500 million from Thai Banks based on the creditworthiness

7 of the Thai utility power as PPA off-taker. As with Theun Hinboun, the plant reverts to Government at the expiry of the concession. Nam Theun 2 was let through individual negotiation after an approach directly from prospective developers. US$30 million was paid as a concession payment to the government as consideration for the project land and the opportunity cost for loss of biodiversity. Royalties for the project are set on an increasing scale. From 5.2% for the first 15 years, increasing to 15% and then 30%; averaging 12% per annum for the life of the project. Income tax is also on an increasing scale from 5% to 30% following an initial 5 year tax holiday. Cumulative revenues to the government from are estimated to total US$ 2 billion over the concession period; more than 15 times the level necessary to service the debt used to finance the Lao government s shareholding. In addition Lao PDR will obtain an effective discount of 16.67% on the standard rate charged to Thailand for power off-take. Merchant Project without a long term power purchase agreement Allain-Duhangan Hydropower India 120 MW Allain Duhangan is a medium-sized private project (US$191million) developed by local and foreign sponsors on a merchant plant basis without a long-term power purchase agreement or any other form of public support, which is very unusual. However, the project sponsors did have industrial links which would allow them to sell some power direct to off-takers if they failed to find any other purchasers. The project was financed on a nominal debt/equity ratio of 65/35, with US$40 million of debt being provided by an IFC A Loan (denominated in Rupees) which allowed a further US$75 million to be raised from local banks. The project structure was made possible by the particular strength and features of the Indian power market and the pervading power shortages. Project with a split ownership San Roque Multipurpose Philippines 345 MW This US$1.19 billion multipurpose project failed to be financed in the public sector, and was then successfully implemented as Pubic-Private Partnership. It is one of the few examples of a Split ownership, where the project is geographically divided into public and private parts although both were implemented under a single contract by the private partner, which made construction coordination easier. The dam (US$610 million) was financed in the public sector using a bilateral soft loan (65 percent) and domestic funds. The power complex (US$580 million) was financed on a 75/25 debt to equity ratio, with 52 percent of the total cost derived from Export Credits. The rest of the debt came from Japanese Government loans and commercial banks. The utility payment obligations were backed by Sovereign Guarantees. Splitting the project also allowed the Government to operate the dam in line with the requirements of irrigation as well as power. Projects let by competitive bidding Nepal large hydropower development The Government of Nepal let three large projects as concessions though competitive bidding, which would partly provide power for export to India and partly provide domestic power. The project bids were variously judged on the percentage of power given free for domestic use and the percentage of royalties. All were BOOT projects, with the assets reverting to Government at the end of the concession period:- Royalties to Government Free domestic power Government Equity Upper Karnali 12% 27%

8 West Seti 2% first 15 years 10% thereafter 10% 15% Arun III 7.5% 21.9% In addition the bid for Arun III included an amount to compensate Government for the earlier work on the project that had been carried out in the public sector. The Government stood to benefit from, dividends, royalties, export tax, value added tax, corporation tax, free power and a range of economic benefits associated with employment and construction; in addition to receiving the assets at the end of the 30 year concession. Financial models were used to estimate the relative value of different levels of free equity or free power. In the case of West Seti these financial benefits were estimated at US$ 2 billion over the life of the project and economic benefits were estimated at an additional US$ 1.1 billion. However, despite being agreed in 2008, none of these projects have yet started construction owing to the difficult conditions in Nepal and perceived security issues. The concession for West Seti has been cancelled and the Government is now seeking concessional finance from China to develop this project. Uganda Bujagali hydropower project Uganda has an estimated power requirement of 380 MW at peak load (290MW base load) and its current power potential is only some 270 MW, as a result of which the country suffers regular power cuts. Facing this power deficit, the Government decided in 1994 to pursue an additional power project the Bujagali Hydropower Project. This was proposed as a privately developed project as Uganda had neither the financial capacity nor the latitude within its internationally financed development programmes to fund the power station as a public project. Following the failure, in 2002, of a negotiated concession with AES Inc, a major American power company which spent seven years endeavouring to develop the project, Government of Uganda decided to hold a competitive process to select a new developer. The World Bank/International Finance Corporation project appraisal document for the Bujagali project (April 2007) describes the following process for selection of the project sponsor (developer). In 2004, the Government established the Bujagali Project Steering Group to oversee and manage the project, in general, including the sponsor selection process. In addition to providing oversight, this multi-institutional Project Steering Group enhanced the accountability and transparency of the sponsor selection process. The following process for selection was to follow several phases in which sponsors were pre-qualified and then their comments were sought on the project documents. The RFP also stipulated that the Government would require the selected sponsor to undertake a transparent and competitive process for awarding the engineering, procurement and construction (EPC) contract for the project. The final RFP was issued to pre-qualified sponsors and the bid selected on the basis of price given: - The internal rate of return on the equity to be invested by the sponsor in the project, stated as a percentage and carried out to three decimal places; A cap on the Development Costs that the sponsor would be allowed to include in the tariff under the PPA; Sponsor acceptance of responsibility for the UETCL transmission line construction management; and The monthly operation and maintenance fee that the project company (to be formed by the selected sponsor) will earn under the PPA to the extent the plant s target availability is achieved.

9 Industrial Promotion Services (Kenya) (IPS(K)) (part of the Aga Khan Fund for Economic Development) was selected and invited for further negotiations and awarded the concession. They (with their partners Sithe Global Power LLC) formed a company, Bujagali Energy Limited (BEL), and signed the Power Purchase Agreement and Implementation Agreement on December 13, The process of selecting the sponsor took almost two years. Brazil - hydropower development The power sector in Brazil moved to a free market model in the 1990s including a move towards concessions awarded on a highest rent basis. Changes were made to this model in 2004 to encourage improved security of supply and facilitate more private investment. Hydro concessions were from then on to be auctioned on the basis of the lowest tariff offered. This auction system has now been used even for some very large (>3000MW) sites. This system is made possible in Brazil by the ability substantially to limit risk by: - pre-specifying projects in great detail; providing surety of payment and providing finance from the local development bank (BNES). While this has been successful for Brazil, there remain issues such as the question as to: - Whether the tariff should be capacity based and whether competition is ensured, particularly when one firm has the advantage of having carried out earlier studies. For other countries attempting a similar exercise; the large amount of equity required, the possibility of limited competition; the lack of finance and payment surety; and the possible sovereign risk makes this model very difficult to replicate. India hydropower concessions In India three models for the allocation of concessions are currently in practice:- Competitive bidding under which bids are assessed considering the extent of free power offered; the level of tariff; and the terminal value of the project (the value at transfer). This is somewhat similar to the method used in Nepal noted above Up front premium, under which bids are assessed considering the extent of free power offered and the level of up front payment offered for the award of the concession. Memorandum of understanding representing the terms of a bilateral agreement between the Government (state or central) and the developer. Originally the most frequently used model, but less common since the requirement for competitive bidding was introduced in the 2005 tariff policy (although hydropower projects were provided with an exemption from this policy).

10 3 Risks Types of Risk In the general parlance of hydropower projects, a risk is anything that can have a negative effect on the project outcome 1. Risks may be real or perceived; in other words, some risks depend on an individual s point of view, while others appear the same to all. An example of a real risk may be of an earthquake if the project lies in an earthquake prone zone. A perceived risk is more subjective; e.g., for an international financier, the political risk (risk of a project being affected by changes imposed by government) of a particular country may appear high, but for that country s government or that of its neighbour, the political risk may be acceptable. Risks are normally categorised as being Political risks (which may be mitigated by guarantee): Financial risks (which may be mitigated by insurance) or Project-related risks (technological, social or environmental, which are not generally insurable). A list of representative types of risk and the possible mitigation and management techniques for each is listed in Annex 1. This section highlights the key risks perceived by private investors: - Political risk - Adequacy of government and public sector agencies to respond in a timely manner in terms of issuance of licenses and approvals or other coordination with the project can be a matter of concern to private investors and cause project delays. Assigning responsibility for liaison with Government to a specific agency which is formally responsibly for coordinating with all the other agencies of Government on behalf of the project can minimise this risk. Hydrological risk is often left with the project company, but may be more effectively managed by the off-takers (who have alternative energy supplies with which to ameliorate the risk). Thus a tariff which is biased towards a capacity element and with only a small energy element, i.e. where the project company is effectively remunerated for the capacity available at the station rather than the actual energy generated. Payment Default. The payment obligations of the utility companies would need to be covered by a requirement to establish an Escrow account with a minimum holding. This could also be back-stopped by a government guarantee. Local Currency Devaluation. There may not be a sufficient financial market to provide for formal hedging so the risk may need to be born by the Project Company. Affordability of local domestic tariffs may be a problem in the initial period after commissioning when debt service is highest. The best option is to optimize the financing such that the grace period and tenor are maximised so that the early repayments are minimised. Alternatively, Government may wish to defer its dividends, royalties or taxes to keep the initial tariff lower. Other risks listed in annex 1 such as delay, cost over run, social and environmental objection and associated infrastructure risks can also cause very significant difficulties to a project. 1 Although in theory risks are issues for which it is possible to predict the probability of occurrence and uncertainties are issues for which the probability of occurrence is not known for the purposes of this report the general parlance of risk for all risks and uncertainties will be adopted

11 Whether a risk is real or perceived, they can all affect the likelihood of a project being financed or attracting private developers. The more risk a developer or financier feels that it is accepting, the higher the charge will be for accepting that risk. At the limit, when the risk profile is too high to be costed, the project may not attract any offers of finance. As noted above, hydropower projects are considered risky because they are capital intensive, environmentally and socially sensitive, and often built in challenging geographical conditions with limited infrastructure access (sometimes in countries without a strong track record of project implementation). As with other power projects, many hydro projects also suffer from weak financial viability due to low national electricity tariffs, poor collection efficiency and lack of a reliable regulatory framework. The attitude to risk of the various partners in a project will depend on their position and their perception of risk. Those providing debt are only interested in the security of their repayment and tend to be risk averse, whereas equity partners take a share in the profits and thus may be prepared to accept a little more risk in return for the prospect of higher returns. Equity Investors may also include the sponsors who actively manage the project and thus feel that they can manage and mitigate some of the risk. In some cases the view of risk is increased by the range of risks so where a developer might accept the political risk alone (e.g. for a thermal power plant) they may not accept the political risk when combined with the high perception of project risk (e.g. for a hydropower project). Although some of these risks are insurable, many others are not. Even the cost of insurance may vary according to which entity is taking the risk. When it comes to Public-Private Partnerships, careful thought has to be given to the allocation of risk between the public and private sectors to ensure that risk is handled in the most effective way possible and at least cost. It is usually recommended that risk is allocated to the parties most able to control the risk parameters. But if control (or mitigation) is not possible, then the risk must be born by one of the parties. There is often a tendency for the public sector to expect the private sector to take a larger share of the risk of the project than is feasible. The private sector will always seek a cost compensation for risk, so the more risk it has to bear, the higher its price. At a limit, if the risk is too high, the private sector will not participate. The cost of trying to off-load risk should be carefully considered; the public sector is often better off bearing a risk if it makes the project financeable. A well prepared analysis of financing options will include a risk analysis, which gives consideration of each risk; the degree to which it is capable of being mitigated, insured, or guaranteed; the likely effect on the financial viability and the financing of the project; and which party should bear the risk. Risks can be aggregated by a country s own portfolio of projects e.g., a country with a range of fuel options for power generation has effectively limited the effect of hydrological risk on its overall generation profile. Beyond aggregation, various types of risk mitigation instruments exist. These are variously referred to as guarantees or insurance, and often with a confusing mixture of definition of the terms. Broadly, a guarantee covers specific, mainly financial events, such as timely payment of debt service and has clear terms of default under which it is invoked. Insurance covers a wider range of events and has a time-limited process for claim against that event, which is subject to various exclusions. Credit Guarantees cover losses in the event of a debt service default regardless of whether the cause is a political or commercial risk. o Partial credit guarantee covers part of the debt service and are largely offered by international finance institutions such as a multilateral development bank. The purpose of such guarantees is to improve the terms (reduced interest and extended maturity) and increase the availability of debt finance to the borrower by sharing the risk between the guarantor and the lenders. o Full credit guarantee sometimes referred to as a wrap guarantee; covers the entire debt service in the event of default. This can be used, for example, to improve the credit risk rating of a bond issue. This type of guarantee is largely provided by private companies and is only available where the country s underlying risk rating is

12 substantially better than the project for which finance is being raised. The recent developments in the international financial markets have largely excluded this as an option to projects. o Export credit guarantee i.e., insurance; covers losses for lenders or exporters where the aspect of the project concerned is tied to export of goods or services. This is offered by export credit agencies (ECA) and supported by the country interested in promoting its exports. (ECAs may also effectively provide finance for exportrelated transactions) Political Risk Guarantees (or Partial Risk Guarantees) cover losses to commercial lenders caused by specific political events. Political Risk Insurance covers losses to equity investors for political events such as war, expropriation of assets, or lack of convertibility of currency. Structuring the project Before commencing on developing a project structure it is necessary to consider some framework issues related to the risk elements identified above, particularly: the legal and regulatory framework, the environmental and social issues and permits and the overall creditworthiness potential of the project. The following section will consider each of these issues in tern and then consider the alternative project structures. Legal framework and regulatory regime Key to the perception and management of risk are certain structural issues such as the legal framework, regulatory regimes, including the fiscal and other incentives (e.g. tax concessions) and access to arbitration. Regulatory risk or the risk of losses caused by adverse regulatory actions on such issues as tariffs, tax payments, or expatriating profits is often cited by the private sector as one of its most significant investment concerns. This perception of risk is heightened by the company s belief that this is an area in which they have no control over the outcome. In order to encourage private participation, governments need to put in place a sound and predictable regulatory framework. However, while this framework is being tried and tested, it may be necessary to define some aspects, such as the method of tariff calculation and fixation in the contract for an infrastructure project, and protect these aspects from future regulatory changes. To reduce the perception of regulatory risk, governments need to ensure that there is a clear and enforceable procedure for the regulatory process. This should include: A legal framework: o published policies and laws as well as procedures for their revision; o an independent regulator; and o a quick and effective dispute resolution system, such as an independent tribunal. A clear strategy: o an articulated government strategy for promotion of infrastructure development, including private participation; o in situations where incentives (e.g., tax holidays) are provided, these need to be transparent, easily accessible, and consistently applied; and o where possible, the administrative burden on the private sector (and opportunities for corruption) should be reduced by implementing initiatives such as single window clearance procedures. Transparent approach: o Public planning and procurement procedures need to be fair, transparent, and accountable.

13 While the reputation and consistency of the regulatory framework is being built, it may be possible to employ a partial risk guarantee, from a multilateral development bank (MDB), to reduce the regulatory risk. Environmental and social permitting As with all large infrastructure projects, environmental and social impacts need to be carefully handled or they can potentially be a source of substantial project delay and increased cost. The private sector will want to see that such issues have been clearly identified and plans put in place to agree them to the satisfaction of all parties, before committing themselves to a project. Environmental permitting and resettlement will remain essentially a sovereign issue and early actions may involve the Government in upfront cost. (These issues are not covered further here as they are not the focus of this paper but issues surrounding sustainable hydropower development are vital to successful and equitable project development.) Issues of land ownership In all hydropower projects, issues of land ownership and sharing of natural resources cause concern and often controversy. Countries such as Canada have spent years developing appropriate benefit sharing mechanisms for the traditional land owners. Packages of benefit sharing involve:- Financial compensation Land compensation Shares in the project company (giving an on-going share of profits) Payments for environmental services such as catchment protection Long term revenue sharing agreements Income generating schemes, The appropriate combination of such options can only be determined in a case by case basis but it is advantageous if there is an agreed Government policy on compensation. Schemes which give and ongoing small share in revenues for the expected project life (such as shares in the project, or catchment protection payments) are growing in popularity as they provide an interest in the project for subsequent generations of affected families. Credit worthiness An assessment of all the above issues (i.e., economic and financial analysis, assessment of environmental and social effects, risk and regulatory issues) will combine to give a picture of the creditworthiness of the project. Ultimately, it is this creditworthiness that will determine which players are interested in participating in the project and, in particular, whether the project proponent will be able to raise international or local private equity or debt or even parastatal equity or debt. Creditworthiness may be expressed as a credit rating, although this really only takes into account certain types of risk and financial returns. If the project is not deemed credit worthy, it may be necessary for the government to take action to support the project through a sovereign guarantee to underwrite the payment obligation of the power off-taker. If the sovereign guarantee is not considered acceptable, then a guarantee from a multilateral development bank (or other institution) may be required to enhance credibility. Public versus private development Once a project has been assessed as to its creditworthiness and risk, it is possible to begin to design a structure for it and assess the extent to which it is either a mainly private or mainly public project or a

14 public/private partnership. The degree to which the various risks can be mitigated will have a strong influence on the choice of project structure. If the risk is substantial and cannot be mitigated to any significant degree, then the project will be unlikely to attract private participation and will need to be developed in the public sector. However, even in a public sector project there may be opportunities for private participation in carefully structured areas where the risk is not transferred to the private player. The following diagram illustrates an overview of the decision-making process for assessing the appropriate project structure. Figure 1 Public or Private? (Head 2006)

15 4 Financing Sources of finance The range of financing options is wide and complex. There is a variety of sources and typical terms and conditions for potential sources of financing including for example developer equity, government equity, commercial lending, multilateral development banks, bilateral and export credit, off-taker financing, but these can broadly be summarised into the following key types:- Table 1 Types and source of finance Type of finance Source Interest Tenor notes Concessionary finance Grants or soft loans Usually from bilateral or multilateral development agencies; carbon credits Very Low Interest or administration fee Long term Public equity Public investment with the support of the government, sometimes indirectly funded from bilateral and multilateral development sources. Dividends Variable can start low and build Indefinite Could be structured such that it is marketable later if appropriate Public debt Project-specific loans from the government or from bilateral and multilateral development banks. Funds may be raised though public bonds. Interest rate set by Government Variable medium to long term - can include a grace period Could be structured such that it is marketable later if appropriate Export Credit Finance direct from the Export Credit Agencies. In proportion to equipment contracts., Medium to high interest Variable but generally short to medium term May depend on source of equipment/ contracting Private commercial debt Loans from private banks, and from the commercial arms of the multilateral development banks. (Possibly with surety from a Guarantee from a multilateral development banks.) High interest (Although may be moderated in presence of a guarantee) Short to medium term (although can be extended with guarantees) Possibly marketable (may include private bonds) Private equity Direct investments made by private Sponsors and other private investors, and the by the private arm of multilateral development banks. May also be subject to a guarantee. Dividends (high return expected for accepting risk) Depending on the length of the concession Possibly marketable Private and public equity and debt can come from either domestic or international markets.

16 Financing plan These financing options need to combined into a financing plan for the project which is put together well in advance of the planned construction scheduling. The instruments can be matched to different project structures from the private project (IPP), through various forms of public private partnership to the public project as shown in the diagram below:- Figure 2 Main financing instruments for different project structures (Head 2006) Illustration of Impact of Debt Tenor on Tariff As noted above, the tenor of finance can have a significant impact on the ultimate project tariff profile. Hydropower projects have a long operational life often in excess of 40 years and yet debt repayment periods may be as short as 12 years where no credit enhancement is available. Thus the cost profile (including debt repayment) may be significantly front-loaded. Unless the developer has any way to smooth this profile the tariff required of the project may be high in the initial years. Many of the public, concessionary or IFI backed forms of finance have longer tenors which can extend the average tenor of the overall financing package. The graphs shown overleaf give an indication of the cash flow and levelised tariff profile of otherwise identical projects financed using 10 or 20 year debt. As can be seen from the illustrative graphs, the actual tariff profile necessary to meet the projects cash flow requirements may differ significantly from the levelised tariff (discounted average), which is often used to compare projects. There may not be available local debt finance to provide cash flow finance with which to smooth this profile, or such debt may add significantly to the overall project cost.

17 Comparison of long run tariff profiles Project financed with debt on 10 year tenor C/kWh Project levelised tariff Current tariff level Tariff required to meet project cash flow Year Comparison of long run tariff profiles Project financed with debt on 20 year tenor C/kWh Project levelised tariff Current tariff level Tariff required to meet project cash flow Year Superimposing the two graphs demonstrates the difference between the two profiles and highlights the critical importance of debt tenor to hydropower project finance. The longer the debt tenor the closer the project cash flow will approach the levelised tariff levels. Given the political and social sensitivity of raising tariffs, the early years of the project may cause great difficulty for both Government and private developers. Above all, decisions should not be taken on the basis of levelised tariff unless this also reflects the actual tariff required with careful attention to the early years of project operation. Comparison of long run tariff profiles 10 vs. 20 year tenor debt in otherwise identical projects year tenor year tenor Project levelised tariff C/kWh Current tariff level Tariff required to meet project cash flow Year

18 5 Structure of transaction and impacts for Government As has been seen in the previous sections, in considering the implications of risk allocation, financing structures and financial benefits-sharing arrangements for the different project and ownership structures it is necessary to look at the implications for (a) the cost of producing electricity; (b) end user tariff and thus (c) the overall finance-ability of the various options. The cost and tariff implications are project specific, but generally private finance tends to be more expensive and of shorter tenor than public finance leading to higher tariffs particularly in the early years after commissioning. In considering the financial issues of specific projects it is also necessary to consider the economic benefits, and the structure of the transaction which are discussed in the following paragraphs. Economic and financial benefits accruing to Government The sources of financial and economic gain to Government from a hydropower project come in a variety of forms. The extent to which each is relevant will depend on whether the project is for domestic, industrial or export use: - Upfront concession fee favoured by Governments as it gives immediate short term cash advantage and are retained in the event that the project fails to materialise. However developers can be discouraged by them as they require upfront cash and can be seen as Government lack of faith in the continuity of the project or the long term commitment of the developer. These amounts are recovered by the developer from later project revenues, thus decreasing the amounts available to Government later in the project. Royalties usually based on water usage or availability, such that the revenues to government are not affected by the vagaries of variations in production or operating cost. Dividends from the Government s equity stake in the project usually at the same rate of calculation as dividends paid on private equity, unless Government decides to waive its dividend in return for lower public sector off-take prices (e.g. for development or rural electrification). The use of such funds may depend on how the equity contribution was financed (e.g. dividends may be used to service a loan used to fund the equity) Taxation in line with corporate taxation guidelines. This can include sales tax as well as corporation and other employment taxes. Low cost electricity supplies the Government may trade some of its other benefits for a discount on the cost of electricity from the plant to promote development and rural electrification. However, the project will have a certain level of financial robustness such that in whatever form the financial benefits accrue to Government they will cumulate to the level that the project can bear and no higher. It is therefore not feasible to maximise each of these payments at the expense of the developer. In the end, the developer may lose interest if the Government demands higher payments than the project can pay and still leave the developer a profit appropriate to the level of risk accepted. Thus to increase its financial returns the Government may have to insulate the project from some of the attendant risks leading the Government back to the familiar balance between risk and return. As custodian of the natural resources of a country, Government experiences a wider range of environmental, social and economic costs and benefits from a project than a developer. As noted

19 above the Government can expect wider economic costs and benefits from such issues as the employment generated by the project. Such employment will provide salaries to boost the local economy and also taxes paid on individual income. There may also be development benefits from the increased supply of electricity which may support development and also encourage investment. However, the development of the project may reduce income from tourism or fishing. These wider economic costs and benefits can have a significant impact on the host country, but are difficult to quantify and hard for developers to assess. As a result the project may be economically beneficial to the Government, but appear less financially attractive to a developer. This is referred to as the gap between economic and financial viability and it is one of the principal reasons for the difficulty in attracting developers and finance to hydropower projects. In the case of a lack of financial viability of a project which Government is keen to support for development reasons, the Government can improve its financial attractiveness of the project by providing subsidies or other forms of fiscal support to the project if is considers it an economic priority. Format of concession Concessions for private development can span a wide range of structures depending on the ownership of the assets and the sources of funding. Models may include management contracts and leases, but these are uncommon in hydropower. More commonly used models include BOOT (Build, own, operate, transfer) where the assets are owned in the private sector but later transferred to the public sector; BOT (Build, operate, transfer) where the assets are owned in the public sector but managed in the private sector; or ROM (Rehabilitate, operate, maintain) to rehabilitate and operate old state owned assets. If none of these structures are possible or attractive then the project may only be developed in the public sector. In this case the structure can either be a public company or special purpose vehicle which can attract some private finance (often referred to as a parastatal company). Alternatively, if sufficient public finance is available then the project can be developed entirely in the public sector. In some circumstances it is possible to divide the project into two and develop aspect (such as the dam) in the public sector and one aspect (such as the power station) in the private sector. The choice of model is summarised in figure 3. Figure 3 Choice of structure (Head 2006)

20 Forming a transaction Most forms of private development or public private partnership start with the development of a concession or other agreement which defines the obligations in the project. There are various ways of awarding a concession or otherwise setting a project in motion. In some cases this can be done through a preferred supplier (directly negotiated concession), but effort must be made to ensure that the deal is structured fairly and this can be done by asking an independent agencies to consider the costs and complexity involved in the projects. More often (in recent years) the concession is let by a competitive process, which is structured and arranged by Government with expert advice. In this case the process commences with public notification of the Government s intent to award a concession followed by a bidding process. The issue to be optimized through the bidding process may be the price of local off-take power or the level of Government royalties or a combination thereof. The Government of PNG should consider the options available to them and the pros and cons of each and take expert advice on financing specific transactions, allocation of risk and legal advice before taking a final decision on how to structure the project. This should then be explained in an outline document setting out the shareholdings, water rights; reservoir operation; tariffs principles; power sales; and method of procurement of the private partner. The document should also identify the length of concession, fiscal incentives, tax regime, royalties due, and environmental and social obligations. Having outlined the preferred structure it would be appropriate to consult potential investors to gauge the appetite for such a transaction: If the response is positive then a bidding process can be set in motion to attract private players as determined by the proposed structure. Depending on the extent of public involvement in the financing of the projects, the same document can be used to elicit interest from the multilateral investment banks and financial support from the private sector with the aim of assembling an outline financing plan and detailed financial model of the project. In some circumstances, projects may even be subject of a competition for finance. This method has particularly been used where some element of multilateral finance is available and the risks are considered moderate so several international banks may be interested. The competition may be based on the least cost, longest tenor, or a combination thereof.

Public-Private Partnerships

Public-Private Partnerships Public-Private Partnerships Closing Critical Issues Washington, Background In limited recourse finance, the primary source of debt service is the cash flow generated by the Project will evaluate all factors

More information

Risk Management. Risk Identification

Risk Management. Risk Identification Management This part provides guidance on the treatment of risks on a PPP project, and; Identifies the major risks common to many PPP projects across all sectors; Allocates the identified risks between

More information

REPUBLIC OF KENYA COUNTY GOVERNMENT OF LAIKIPIA MEDIUM TERM DEBT MANAGEMENT STRATEGY 2013/14-2017/18

REPUBLIC OF KENYA COUNTY GOVERNMENT OF LAIKIPIA MEDIUM TERM DEBT MANAGEMENT STRATEGY 2013/14-2017/18 REPUBLIC OF KENYA COUNTY GOVERNMENT OF LAIKIPIA MEDIUM TERM DEBT MANAGEMENT STRATEGY 2013/14-2017/18 COUNTY EXECUTIVE MEMBER, FINANCE, PLANNING AND COUNTY DEVELOPMENT LAIKIPIA COUNTY February 2014 i EXECUTIVE

More information

Australian Constructors Association. Bonding Issues Faced by Construction Companies in Australia

Australian Constructors Association. Bonding Issues Faced by Construction Companies in Australia Bonding Issues Faced by Construction Companies in Australia October 2009 This report contains 17 pages 6277500_6 Contents 1 Introduction and Summary 1 2 Purpose of Performance Guarantees and Bonds 3 3

More information

UK Guarantees scheme for infrastructure

UK Guarantees scheme for infrastructure Report by the Comptroller and Auditor General HM Treasury UK Guarantees scheme for infrastructure HC 909 SESSION 2014-15 28 JANUARY 2015 4 Key facts UK Guarantees scheme for infrastructure Key facts 40bn

More information

World Bank Guarantee Program

World Bank Guarantee Program World Bank Guarantee Program for the Consultation of Modernizing the World Bank s Operational Policy on Guarantees January 2012 Why World Bank Guarantees? Guarantees are viewed as a key financial instrument

More information

Community and Renewable Energy Scheme Project Development Toolkit

Community and Renewable Energy Scheme Project Development Toolkit Community and Renewable Energy Scheme Project Development Toolkit Balance Sheet Equity Investment Community Bond Issues Community Vehicle Crowd Funding Debentures a form of bond Debt Debt Service Cover

More information

Agreements, bonds and guarantees

Agreements, bonds and guarantees Agreements, bonds and guarantees SPV Formation The Special Project Vehicle (SPV) may take a variety of forms, including a corporation, limited liability company, general partnership, limited partnership,

More information

PPP Basics and Principles of a PPP Framework

PPP Basics and Principles of a PPP Framework Note 1 May 2012 PPP Basics and Principles of a PPP Framework This note is the first in a series of notes on developing a comprehensive policy, legal, and institution framework for public-private partnership

More information

NMRC AND THE NIGERIAN MORTGAGE MARKET:

NMRC AND THE NIGERIAN MORTGAGE MARKET: NMRC AND THE NIGERIAN MORTGAGE MARKET: An Intermediate Step to a full Secondary Mortgage Market 2014 CAPITAL MARKET COMMITTEE (CMC) RETREAT & CONFERENCE Sonnie Ayere Interim CEO, NMRC Chairman, Dunn Loren

More information

A new electricity market for Northern Ireland and Ireland from 2016 - Integrated Single Electricity Market (I-SEM)

A new electricity market for Northern Ireland and Ireland from 2016 - Integrated Single Electricity Market (I-SEM) A new electricity market for Northern Ireland and Ireland from 2016 - Integrated Single Electricity Market (I-SEM) Non-technical summary High level design Draft Decision Paper SEM -14-047 June 2014 1 INTRODUCTION

More information

Infrastructure and Project Financing Asia Pacific Scenario. Ajay Sagar

Infrastructure and Project Financing Asia Pacific Scenario. Ajay Sagar Infrastructure and Project Financing Asia Pacific Scenario by Ajay Sagar This article was originally published in the June 2006 Global Infrastructure Report of Project Finance International Magazine The

More information

Financing Energy Efficiency and Renewable Energy through the India Renewable Energy Development Agency

Financing Energy Efficiency and Renewable Energy through the India Renewable Energy Development Agency RENEWABLE ENERGY INDUSTRIAL ENERGY EFFICIENCY BUILDING ENERGY EFFICIENCY Financing Energy Efficiency and Renewable Energy through the India Renewable Energy Development Agency A RANGE OF FINANCIAL SUPPORT

More information

Cost of capital in the financial turmoil: how should utilities deal with it?

Cost of capital in the financial turmoil: how should utilities deal with it? Cost of capital in the financial turmoil: how should utilities deal with it? Virat Patel Partner Marco Venneri Manager As a direct result of the current credit crisis, the Weighted Average Cost of Capital

More information

SUPPLEMENTARY GREEN BOOK GUIDANCE

SUPPLEMENTARY GREEN BOOK GUIDANCE SUPPLEMENTARY GREEN BOOK GUIDANCE ADJUSTING FOR TAXATION IN PFI vs PSC COMPARISONS 1 INTRODUCTION 1.1 This guidance looks at the differential tax receipts that arise from the use of the Private Finance

More information

RULES AND REGULATIONS FOR FINANCING PROJECTS AND COMMERCIAL ACTIVITIES

RULES AND REGULATIONS FOR FINANCING PROJECTS AND COMMERCIAL ACTIVITIES Page 1 of 8 Section 1. Purpose These Rules and Regulations are adopted by the Board of Governors pursuant to Article 13.3. of the Agreement Establishing the Black Sea Trade and Development Bank (Establishing

More information

DRAFT KERALA STATE ELECTRICITY REGULATORY COMMISSION, NOTICE. No. 442/CT/2014/KSERC Dated, Thiruvananthapuram 31 st March, 2015

DRAFT KERALA STATE ELECTRICITY REGULATORY COMMISSION, NOTICE. No. 442/CT/2014/KSERC Dated, Thiruvananthapuram 31 st March, 2015 DRAFT 31.3.2015 KERALA STATE ELECTRICITY REGULATORY COMMISSION, NOTICE 442/CT/2014/KSERC Dated, Thiruvananthapuram 31 st March, 2015 The Kerala State Electricity Regulatory Commission hereby publishes

More information

OUT-OF-COURT RESTRUCTURING GUIDELINES FOR MAURITIUS

OUT-OF-COURT RESTRUCTURING GUIDELINES FOR MAURITIUS These Guidelines have been issued by the Insolvency Service and endorsed by the Bank of Mauritius. OUT-OF-COURT RESTRUCTURING GUIDELINES FOR MAURITIUS 1. INTRODUCTION It is a generally accepted global

More information

Renewable Electricity and Liberalised Markets REALM. JOULE-III Project JOR3-CT98-0290 GREECE ACTION PLAN. By ICCS / NTUA K. Delkis

Renewable Electricity and Liberalised Markets REALM. JOULE-III Project JOR3-CT98-0290 GREECE ACTION PLAN. By ICCS / NTUA K. Delkis Renewable Electricity and Liberalised Markets REALM JOULE-III Project JOR3-CT98-0290 GREECE ACTION PLAN By ICCS / NTUA K. Delkis October 1999 INTRODUCTION AND BACKGROUND Background to Renewable Energy

More information

Electricity Business in the Asia-Pacific Region

Electricity Business in the Asia-Pacific Region Electricity Business in the Asia-Pacific Region Business Environment and Challenges (Regional) The opportunities in coming years for CLP to increase its presence in the power industry in the Asia-Pacific

More information

Accounting for Infrastructure Projects within Enterprise Zones (EZ) and Tax Increment Financing (TIF) Funded Programmes.

Accounting for Infrastructure Projects within Enterprise Zones (EZ) and Tax Increment Financing (TIF) Funded Programmes. Accounting for Infrastructure Projects within Enterprise Zones (EZ) and Tax Increment Financing (TIF) Funded Programmes. Background 1 A number of initiatives are under way that involve local authorities

More information

Public Financial Disclosure A Guide to Reporting Selected Financial Instruments

Public Financial Disclosure A Guide to Reporting Selected Financial Instruments Public Financial Disclosure A Guide to Reporting Selected Financial Instruments TABLE OF CONTENTS AMERICAN DEPOSITARY RECEIPT 1 CASH BALANCE PENSION PLAN 2 COMMON TRUST FUND OF A BANK 4 EMPLOYEE STOCK

More information

UNECE PPP Healthcare Standard

UNECE PPP Healthcare Standard INTERNATIONAL SPECIALIST CENTRE OF EXCELLENCE ON PPPs IN HEALTH MANILA, PHILIPPINES UNECE PPP Healthcare Standard Questions on lessons learned in the development of Public-Private Partnership ( PPP ) programmes

More information

I N F O R M A T I O N A B O U T T R A D I N G I N S E C U R I T I E S Applicable from March 2012

I N F O R M A T I O N A B O U T T R A D I N G I N S E C U R I T I E S Applicable from March 2012 I N F O R M A T I O N A B O U T T R A D I N G I N S E C U R I T I E S Applicable from March 2012 This is a translation of the document Oplysninger om handel med værdipapirer in the Danish language. In

More information

T o o l k i t f o r P u b l i c - P r i v a t e P a r t n e r s h i p s i n r o a d s & H i g h w a y s. PPP Modalities

T o o l k i t f o r P u b l i c - P r i v a t e P a r t n e r s h i p s i n r o a d s & H i g h w a y s. PPP Modalities PPP Modalities Types and characteristics of PPP are presented in several sections of the Toolkit: refer Types of PPP in Key Issues. This section provides some consideration of which modality, or which

More information

[ 2 ] Basic Securitization Structure. [ 1 ] Securitization and Monetization. Ⅰ Basic Structure of Real Estate Securitization. Structured finance

[ 2 ] Basic Securitization Structure. [ 1 ] Securitization and Monetization. Ⅰ Basic Structure of Real Estate Securitization. Structured finance Ⅰ Basic Structure of Real Estate Securitization [ 1 ] Securitization and Monetization Asset securitization is where a financial institution or other business that owns assets places those assets in a structure

More information

IREDA-NCEF REFINANCE SCHEME

IREDA-NCEF REFINANCE SCHEME IREDA-NCEF REFINANCE SCHEME REVIVAL OF THE OPERATIONS OF EXISTING BIOMASS POWER & SMALL HYDRO POWER PROJECTS AFFECTED DUE TO UNFORSEEN CIRCUMSTANCES SUPPORTED BY THE NATIONAL CLEAN ENERGY FUND IREDA NCEF

More information

KEY CONSIDERATIONS IN POWER PURCHASE AGREEMENT (PPA) RISK ALLOCATION AND COMMON CLAUSES WHICH FORM PART OF A PPA

KEY CONSIDERATIONS IN POWER PURCHASE AGREEMENT (PPA) RISK ALLOCATION AND COMMON CLAUSES WHICH FORM PART OF A PPA KEY CONSIDERATIONS IN POWER PURCHASE AGREEMENT (PPA) RISK ALLOCATION AND COMMON CLAUSES WHICH FORM PART OF A PPA AFRICA UTILITY WEEK CONFERENCE Yesufu Longe Alonge Head, Power Procurement & Power Contracts

More information

6.0 Procurement procedure 1 Infrastructure

6.0 Procurement procedure 1 Infrastructure Page 6-1 6.0 Procurement procedure 1 Infrastructure 6.1 Overview Introduction Procurement procedure 1 Infrastructure consists of four parts: guidelines for understanding the strategic context for the procurement

More information

Financing of Renewable Energy in India: Implications for Policy. Gireesh Shrimali Climate Policy Initiative gireesh.shrimali@cpihyd.

Financing of Renewable Energy in India: Implications for Policy. Gireesh Shrimali Climate Policy Initiative gireesh.shrimali@cpihyd. Financing of Renewable Energy in India: Implications for Policy Gireesh Shrimali Climate Policy Initiative gireesh.shrimali@cpihyd.org CPI analyzes the effectiveness of policies relevant to climate change

More information

EXPLANATORY NOTES. 1. Summary of accounting policies

EXPLANATORY NOTES. 1. Summary of accounting policies 1. Summary of accounting policies Reporting Entity Taranaki Regional Council is a regional local authority governed by the Local Government Act 2002. The Taranaki Regional Council group (TRC) consists

More information

PAPER IIA UNITED KINGDOM OPTION

PAPER IIA UNITED KINGDOM OPTION THE ADVANCED DIPLOMA IN INTERNATIONAL TAXATION June 2008 PAPER IIA UNITED KINGDOM OPTION ADVANCED INTERNATIONAL TAXATION TIME ALLOWED 3¼ HOURS You should answer FOUR out of the seven questions. Each question

More information

Fund guide. Prudence Bond Prudence Managed Investment Bond

Fund guide. Prudence Bond Prudence Managed Investment Bond Fund guide Prudence Bond Prudence Managed Investment Bond Introduction to this guide We know that choosing which fund may be best for you isn t easy there are many options and everyone is different so

More information

Financing DESCOs A framework

Financing DESCOs A framework Financing DESCOs A framework A framework discussion about financing working capital for distributed energy services companies Chris Aidun and Dirk Muench March 2015 This paper looks at the growing need

More information

Loan financing for service providers

Loan financing for service providers Loan financing for service providers May 2014 Disclaimer The materials presented in this document are for general information only and should not be taken as constituting professional advice. Users should

More information

United States of America. Presentation of financial resources available to US investors in Afghanistan; Financial Tools

United States of America. Presentation of financial resources available to US investors in Afghanistan; Financial Tools United States of America Presentation of financial resources available to US investors in Afghanistan; Financial Tools Kabul, February 2007 Research categories for all countries Finance Categories 1. Equity

More information

Regulation for Renewable Energy Development: Lessons from Sri Lanka Experience

Regulation for Renewable Energy Development: Lessons from Sri Lanka Experience Regulation for Renewable Energy Development: Lessons from Sri Lanka Experience Priyantha D C Wijayatunga Asian Development Bank, Manila, Philippines * Corresponding author. Tel: +6326326131, Fax: +6326362338,

More information

Please send your responses via email, to: PFIevidence@hmtreasury.gsi.gov.uk. Respondent details. Mark Redhead. Head of Policy

Please send your responses via email, to: PFIevidence@hmtreasury.gsi.gov.uk. Respondent details. Mark Redhead. Head of Policy REFORM OF THE PRIVATE FINANCE INITIATIVE RESPONSE Please send your responses via email, to: PFIevidence@hmtreasury.gsi.gov.uk The deadline for responses is Friday 10 February 2012. Respondent details Your

More information

WEST BASIN MUNICIPAL WATER DISTRICT Debt Management Policy Administrative Code Exhibit G January 2015

WEST BASIN MUNICIPAL WATER DISTRICT Debt Management Policy Administrative Code Exhibit G January 2015 1.0 Purpose The purpose of this Debt Management Policy ( Policy ) is to establish parameters and provide guidance as to the issuance, management, continuing evaluation of and reporting on all debt obligations.

More information

Debt Policy. I. Purpose of the Debt Policy

Debt Policy. I. Purpose of the Debt Policy Debt Policy I. Purpose of the Debt Policy In support of its mission, (University) maintains a long term strategic plan. The strategic plan establishes University wide priorities as well as divisional programmatic

More information

OAKTREE HIGH YIELD BOND FUND

OAKTREE HIGH YIELD BOND FUND OAKTREE HIGH YIELD BOND FUND Institutional Class OHYIX Advisor Class OHYDX Before you invest, you may want to review the Fund s prospectus, which contains more information about the Fund and its risks.

More information

Contribution 787 1,368 1,813 983. Taxable cash flow 682 1,253 1,688 858 Tax liabilities (205) (376) (506) (257)

Contribution 787 1,368 1,813 983. Taxable cash flow 682 1,253 1,688 858 Tax liabilities (205) (376) (506) (257) Answers Fundamentals Level Skills Module, Paper F9 Financial Management June 2012 Answers 1 (a) Calculation of net present value (NPV) As nominal after-tax cash flows are to be discounted, the nominal

More information

IREDA-NCEF REFINANCE SCHEME REFINANCE SCHEME FOR PROMOTION OF RENEWABLE ENERGY SUPPORTED BY THE NATIONAL CLEAN ENERGY FUND

IREDA-NCEF REFINANCE SCHEME REFINANCE SCHEME FOR PROMOTION OF RENEWABLE ENERGY SUPPORTED BY THE NATIONAL CLEAN ENERGY FUND IREDA-NCEF REFINANCE SCHEME REFINANCE SCHEME FOR PROMOTION OF RENEWABLE ENERGY SUPPORTED BY THE NATIONAL CLEAN ENERGY FUND IREDA NCEF REFINANCE SCHEME REFINANCE SCHEME FOR PROMOTION OF RENEWABLE ENERGY

More information

Infrastructure Development Funding and Financing

Infrastructure Development Funding and Financing Infrastructure Development Funding and Financing 09 December 2013 2 Presentation outline 1. Role of infrastructure development 2. Public sector infrastructure investment 3. Funding options i. Recent airport

More information

foreign risk and its relevant to acca qualification paper F9

foreign risk and its relevant to acca qualification paper F9 01 technical foreign risk and its relevant to acca qualification paper F9 Increasingly, many businesses have dealings in foreign currencies and, unless exchange rates are fixed with respect to one another,

More information

DEBT SUSTAINABILITY ASSESSMENT

DEBT SUSTAINABILITY ASSESSMENT Second Green Power Development Project (RRP BHU 44444) DEBT SUSTAINABILITY ASSESSMENT A. Background 1. Objective. The government of Bhutan has followed an investment driven approach for inclusive economic

More information

SECTION 7 DEBT MANAGEMENT POLICY LAS VEGAS VALLEY WATER DISTRICT FISCAL YEAR 2015-16 OPERATING AND CAPITAL BUDGET

SECTION 7 DEBT MANAGEMENT POLICY LAS VEGAS VALLEY WATER DISTRICT FISCAL YEAR 2015-16 OPERATING AND CAPITAL BUDGET SECTION 7 DEBT MANAGEMENT POLICY LAS VEGAS VALLEY WATER DISTRICT FISCAL YEAR 2015-16 OPERATING AND CAPITAL BUDGET In Accordance With NRS 350.013 June 30, 2015 7-1 Table of Contents Introduction... 7-3

More information

Capital Structure and Project Finance Mark Williamson and Peter Barlow

Capital Structure and Project Finance Mark Williamson and Peter Barlow Capital Structure and Project Finance Mark Williamson and Peter Barlow Capital structure overview Very secure capital structure strong liquidity at parent cash of 357m at 30 June 2008 low debt at parent

More information

Solar Power Policy Uttar Pradesh 2012 Suggestions to be sent to : dirupneda@rediffmail.com ho_nmk@rediffmail.com

Solar Power Policy Uttar Pradesh 2012 Suggestions to be sent to : dirupneda@rediffmail.com ho_nmk@rediffmail.com Draft ver2 Solar Power Policy Uttar Pradesh 2012 Suggestions to be sent to : dirupneda@rediffmail.com ho_nmk@rediffmail.com 1 TABLE OF CONTENTS S.No Contents Page No 1. PREAMBLE 3 2. OBJECTIVES 3 3. OPERATIVE

More information

DEBT MANAGEMENT POLICY ANNUAL UPDATE HUMBOLDT COUNTY, NEVADA

DEBT MANAGEMENT POLICY ANNUAL UPDATE HUMBOLDT COUNTY, NEVADA DEBT MANAGEMENT POLICY ANNUAL UPDATE HUMBOLDT COUNTY, NEVADA July, 2015 TABLE OF CONTENTS I. INTRODUCTION 1 II. ABILITY TO AFFORD EXISTING GENERAL OBLIGATION DEBT, AUTHORIZED FUTURE GENERAL OBLIGATION

More information

How KASIKORNBANK Plans to Support Green Projects

How KASIKORNBANK Plans to Support Green Projects How KASIKORNBANK Plans to Support Green Projects Clean Power Asia 29-30 April 2013, Bangkok Thongchai Kangvanchai KASIKORNBANK Pcl. 1 Content Government s Policy of Promoting Green Energy KBank s Green

More information

SURVEY ON HOW COMMERCIAL BANKS DETERMINE LENDING INTEREST RATES IN ZAMBIA

SURVEY ON HOW COMMERCIAL BANKS DETERMINE LENDING INTEREST RATES IN ZAMBIA BANK Of ZAMBIA SURVEY ON HOW COMMERCIAL BANKS DETERMINE LENDING INTEREST RATES IN ZAMBIA September 10 1 1.0 Introduction 1.1 As Government has indicated its intention to shift monetary policy away from

More information

Monetary and Financial Aspects of Issuing Public Debt Instruments in Kuwait (1)

Monetary and Financial Aspects of Issuing Public Debt Instruments in Kuwait (1) Monetary and Financial Aspects of Issuing Public Debt Instruments in Kuwait (1) I would like to thank the Faculty of Commerce for arranging this meeting, which I hope will lead to the clarification of

More information

CITY OF LONDON LAW SOCIETY, LAND LAW COMMITTEE S INSURANCE PROVISIONS FOR A RACK RENT LEASE OF COMMERCIAL PROPERTY MARCH 2014

CITY OF LONDON LAW SOCIETY, LAND LAW COMMITTEE S INSURANCE PROVISIONS FOR A RACK RENT LEASE OF COMMERCIAL PROPERTY MARCH 2014 CITY OF LONDON LAW SOCIETY, LAND LAW COMMITTEE S INSURANCE PROVISIONS FOR A RACK RENT LEASE OF COMMERCIAL PROPERTY MARCH 2014 Schedule 1 Insurance provisions 1 1 INSURED RISKS AND OTHER DEFINITIONS 1.1

More information

Fund Guide. Prudential International Investment Bond International Prudence Bond

Fund Guide. Prudential International Investment Bond International Prudence Bond Fund Guide Prudential International Investment Bond International Prudence Bond Introduction to this guide We know that choosing which fund may be best for you isn t easy there are many options and everyone

More information

Overcoming financing challenges for Hydro Power Projects Francois Viljoen, Director, Cresco Project Finance, South Africa

Overcoming financing challenges for Hydro Power Projects Francois Viljoen, Director, Cresco Project Finance, South Africa Overcoming financing challenges for Hydro Power Projects Francois Viljoen, Director, Cresco Project Finance, South Africa Contents Features of Project Finance Challenges posed by Project Finance Risk assessment

More information

PPI 1 in IDA Countries, 2009 to 2014

PPI 1 in IDA Countries, 2009 to 2014 PPI 1 in IDA Countries, 2009 to 2014 This note is a product of the Public-Private Partnership Group of the World Bank, and the Private Participation in Infrastructure Database (PPI Database), written by

More information

AN INTRODUCTION TO MUNICIPAL LEASE FINANCING: ANSWERS TO FREQUENTLY ASKED QUESTIONS

AN INTRODUCTION TO MUNICIPAL LEASE FINANCING: ANSWERS TO FREQUENTLY ASKED QUESTIONS AN INTRODUCTION TO MUNICIPAL LEASE FINANCING: ANSWERS TO FREQUENTLY ASKED QUESTIONS Dated July 1, 2000 Copyright 2000. Association for Governmental Leasing & Finance, Washington, DC. All rights reserved.

More information

PUBLIC-PRIVATE PARTNERSHIP (PPP)

PUBLIC-PRIVATE PARTNERSHIP (PPP) PUBLIC-PRIVATE PARTNERSHIP (PPP) Virginia Tan, Allen & Overy Type: Published: Last Updated: Keywords: Legal guide June 2012 June 2012 PPP, infrastructure assets, public and private sectors This document

More information

Annex 1 Tool for the demonstration and assessment of additionality

Annex 1 Tool for the demonstration and assessment of additionality page 1 Tool for the demonstration and assessment of additionality 1. This document provides for a step-wise approach to demonstrate and assess additionality. These steps include: Identification of alternatives

More information

https://www.ofgem.gov.uk/publications-and-updates/ofto-build-providing-additional-flexibility-through-extendedframework

https://www.ofgem.gov.uk/publications-and-updates/ofto-build-providing-additional-flexibility-through-extendedframework All interested parties Direct Dial: 020 7901 1849 Email: transmissioncompetition@ofgem.gov.uk Date: 17 November 2015 Dear Colleague EPC Contract Principles for OFTO Build Tenders This letter provides guidance

More information

Advanced Financial Management

Advanced Financial Management Progress Test 2 Advanced Financial Management P4AFM-PT2-Z14-A Answers & Marking Scheme 2014 DeVry/Becker Educational Development Corp. Tutorial note: the answers below are more comprehensive than would

More information

PUBLIC PRIVATE PARTNERSHIP HANDBOOK

PUBLIC PRIVATE PARTNERSHIP HANDBOOK PUBLIC PRIVATE PARTNERSHIP HANDBOOK VERSION 2 March 2012 1 CONTENTS Section 1: Introduction to Public Private Partnerships... 3 1.1 What is Public Private Partnership?... 4 1.2 Typical PPP Delivery Models...

More information

Principles and Trade-Offs when Making Issuance Choices in the UK

Principles and Trade-Offs when Making Issuance Choices in the UK Please cite this paper as: OECD (2011), Principles and Trade-Offs when Making Issuance Choices in the UK, OECD Working Papers on Sovereign Borrowing and Public Debt Management, No. 2, OECD Publishing.

More information

Customer financing in Brazil Guide for a Finnish SME exporter

Customer financing in Brazil Guide for a Finnish SME exporter Customer financing in Brazil Guide for a Finnish SME exporter Contents Financial markets 2 Know your customer 3 Prepayments received from the buyer 4 Granting payment terms with invoice 5 Bills of exchange

More information

Presentation to the KZN Exporter Week

Presentation to the KZN Exporter Week Presentation to the KZN Exporter Week Chris Thirion Stakeholder Management & Marketing 17 November 2014 ECIC Environment Self-sustained state-owned public entity registered as a Schedule 3 (b) business

More information

FREE MARKET U.S. EQUITY FUND FREE MARKET INTERNATIONAL EQUITY FUND FREE MARKET FIXED INCOME FUND of THE RBB FUND, INC. PROSPECTUS.

FREE MARKET U.S. EQUITY FUND FREE MARKET INTERNATIONAL EQUITY FUND FREE MARKET FIXED INCOME FUND of THE RBB FUND, INC. PROSPECTUS. FREE MARKET U.S. EQUITY FUND FREE MARKET INTERNATIONAL EQUITY FUND FREE MARKET FIXED INCOME FUND of THE RBB FUND, INC. PROSPECTUS December 31, 2014 Investment Adviser: MATSON MONEY, INC. 5955 Deerfield

More information

What You Should Know About Home Equity Lines of Credit and Important Terms of FlexEquity SM

What You Should Know About Home Equity Lines of Credit and Important Terms of FlexEquity SM What You Should Know About Home Equity Lines of Credit and Important Terms of FlexEquity SM Effective March 1, 2008 The Housing Financial Discrimination Act of 1977 Fair Lending Notice It is illegal to

More information

Series of Shares B, B-6, E, F, F-6, O B, E, F, O O A, B

Series of Shares B, B-6, E, F, F-6, O B, E, F, O O A, B No securities regulatory authority has expressed an opinion about these securities and it is an offence to claim otherwise. The Funds and their securities offered under this Annual Information Form are

More information

Investing in infrastructure?

Investing in infrastructure? Investing in infrastructure? Independent guide for investors about infrastructure investments This guide is for you, whether you re an experienced investor or just starting out. Key tips from ASIC about

More information

SAMPLE TERMS OF REFERENCE FOR ELECTRICITY SECTOR PRIVATIZATION TRANSACTION ADVISORY SERVICES

SAMPLE TERMS OF REFERENCE FOR ELECTRICITY SECTOR PRIVATIZATION TRANSACTION ADVISORY SERVICES SAMPLE TERMS OF REFERENCE FOR ELECTRICITY SECTOR PRIVATIZATION TRANSACTION ADVISORY SERVICES Table of Contents 1st. INTRODUCTION... 3 2nd. ELECTRICITY SECTOR BACKGROUND. 4 3rd. SCOPE OF WORK. 6 PHASE :

More information

Understanding a Firm s Different Financing Options. A Closer Look at Equity vs. Debt

Understanding a Firm s Different Financing Options. A Closer Look at Equity vs. Debt Understanding a Firm s Different Financing Options A Closer Look at Equity vs. Debt Financing Options: A Closer Look at Equity vs. Debt Business owners who seek financing face a fundamental choice: should

More information

Project Finance Structuring: Case Study - Nam Theun 2

Project Finance Structuring: Case Study - Nam Theun 2 Project Finance Structuring: Case Study - Nam Theun 2 Session on Finance Sidharth Sinha Indian Institute of Management, Ahmedabad Project History 1970s - Mekong secretariat identified the hydropower potential

More information

SPDR Wells Fargo Preferred Stock ETF

SPDR Wells Fargo Preferred Stock ETF SPDR Wells Fargo Preferred Stock ETF Summary Prospectus-October 31, 2015 PSK (NYSE Ticker) Before you invest in the SPDR Wells Fargo Preferred Stock ETF (the Fund ), you may want to review the Fund's prospectus

More information

Outline feasibility study for ORET application in the health care sector

Outline feasibility study for ORET application in the health care sector Outline feasibility study for ORET application in the health care sector In this section we outline the information needed for a proper assessment of your application for financing under the ORET program.

More information

STANDARD LIFE INVESTMENTS PROPERTY INCOME TRUST LIMITED

STANDARD LIFE INVESTMENTS PROPERTY INCOME TRUST LIMITED This document is issued by Standard Life Investments Property Income Trust Limited (the "Company") and is made available by Standard Life Investments (Corporate Funds) Limited (the AIFM ) solely in order

More information

SIGNIFICANT GROUP ACCOUNTING POLICIES

SIGNIFICANT GROUP ACCOUNTING POLICIES SIGNIFICANT GROUP ACCOUNTING POLICIES Basis of consolidation Subsidiaries Subsidiaries are all entities over which the Group has the sole right to exercise control over the operations and govern the financial

More information

Virginia State University Policies Manual. Title: Debt Management Guidelines and Procedures Policy: 1500

Virginia State University Policies Manual. Title: Debt Management Guidelines and Procedures Policy: 1500 Purpose a. To provide guidance to Virginia State University in undertaking long-term debt obligations benefiting the University. b. To provide a structured framework for the issuance of long-term debt

More information

Risk Warning Notice. Introduction

Risk Warning Notice. Introduction First Equity Limited Salisbury House London Wall London EC2M 5QQ Tel 020 7374 2212 Fax 020 7374 2336 www.firstequity.ltd.uk Risk Warning Notice Introduction You should not invest in any investment product

More information

SSAP 24 STATEMENT OF STANDARD ACCOUNTING PRACTICE 24 ACCOUNTING FOR INVESTMENTS IN SECURITIES

SSAP 24 STATEMENT OF STANDARD ACCOUNTING PRACTICE 24 ACCOUNTING FOR INVESTMENTS IN SECURITIES SSAP 24 STATEMENT OF STANDARD ACCOUNTING PRACTICE 24 ACCOUNTING FOR INVESTMENTS IN SECURITIES (Issued April 1999) The standards, which have been set in bold italic type, should be read in the context of

More information

Note 24 Financial Risk Management

Note 24 Financial Risk Management Note Financial Risk Management Risk management principles and process Stora Enso is exposed to several financial market risks that the Group is responsible for managing under policies approved by the Board

More information

Importance of Credit Rating

Importance of Credit Rating Importance of Credit Rating A credit rating estimates ability to repay debt. A credit rating is a formal assessment of a corporation, autonomous governments, individuals, conglomerates or even a country.

More information

SECTOR ASSESSMENT (SUMMARY): FINANCE 1. 1. Sector Performance, Problems, and Opportunities

SECTOR ASSESSMENT (SUMMARY): FINANCE 1. 1. Sector Performance, Problems, and Opportunities Country Partnership Strategy: Bangladesh, 2011 2015 SECTOR ASSESSMENT (SUMMARY): FINANCE 1 Sector Road Map 1. Sector Performance, Problems, and Opportunities 1. The finance sector in Bangladesh is diverse,

More information

Section A Introduction This section asks for information that aims to identify the independence and ownership situation of your business.

Section A Introduction This section asks for information that aims to identify the independence and ownership situation of your business. Access to Finance Purpose of this survey Access to finance is crucial to business success and an important factor for economic growth in Europe following the economic crisis in 2007. The purpose of this

More information

1.040 Project Management

1.040 Project Management MIT OpenCourseWare http://ocw.mit.edu 1.040 Project Management Spring 2009 For information about citing these materials or our Terms of Use, visit: http://ocw.mit.edu/terms. 1.040/1.401 Project Management

More information

Export Import Bank Financing Programs

Export Import Bank Financing Programs Export Import Bank Financing Programs The Export Import Bank of the United States (Ex Im Bank) is the official export credit agency of the United States. Ex Im Bank assists in financing the export of U.S.

More information

Zurich Investment Bonds. Funds guide

Zurich Investment Bonds. Funds guide Zurich Investment Bonds Funds guide Contents Introduction 3 List of current investment funds by sector 4 Investment choice and flexibility 6 Fund risks 7 Managed funds 8 Multimanaged funds 10 UK equity

More information

Bonding P3 Projects. Frequently Asked Questions about P3s and Bonding

Bonding P3 Projects. Frequently Asked Questions about P3s and Bonding Bonding P3 Projects Government entities in the United States have understood the importance of surety bonds and have required bonds for over a century to provide performance and payment assurance for the

More information

ENERGY INDUSTRY INSURANCE SOLUTIONS

ENERGY INDUSTRY INSURANCE SOLUTIONS Summer 11 ENERGY INDUSTRY INSURANCE SOLUTIONS ELECTRICITY PRICE & FORCED POWER OUTAGE COVERAGE WEATHER DERIVATIVES SYSTEM PERFORMANCE INSURANCE TRADE CREDIT INSURANCE ACCOUNTS RECEIVABLE PUTS NON CANCELLABLE

More information

FINANCIAL MANAGEMENT AND PERFORMANCE ASSESSMENT

FINANCIAL MANAGEMENT AND PERFORMANCE ASSESSMENT Power Transmission Rehabilitation Project (RRP ARM 46416-002) A. Introduction FINANCIAL MANAGEMENT AND PERFORMANCE ASSESSMENT 1. An assessment on the financial management capacity and financial performance

More information

Current Funding Issues for Defined Benefit Pension Schemes

Current Funding Issues for Defined Benefit Pension Schemes Current Funding Issues for Defined Benefit Pension Schemes Introduction 1. According to the latest figures published by the Pensions Board, approximately 232,000 employees, or 33% of the total membership

More information

Business Financing. An Article by Michael L. Messer and Thomas L. Hofstetter SCHENCK, PRICE, SMITH & KING, LLP

Business Financing. An Article by Michael L. Messer and Thomas L. Hofstetter SCHENCK, PRICE, SMITH & KING, LLP Business Financing An Article by Michael L. Messer and Thomas L. Hofstetter SCHENCK, PRICE, SMITH & KING, LLP Even in these challenging economic times, businesses still have a need to grow and to obtain

More information

CHALLENGES AND PROSPECTS FOR NEPALESE CONSULTING BUSINESS: NEED OF CAPACITY BUILDING FOR SUSTAINABLE DEVELOPMENT

CHALLENGES AND PROSPECTS FOR NEPALESE CONSULTING BUSINESS: NEED OF CAPACITY BUILDING FOR SUSTAINABLE DEVELOPMENT CHALLENGES AND PROSPECTS FOR NEPALESE CONSULTING BUSINESS: NEED OF CAPACITY BUILDING FOR SUSTAINABLE DEVELOPMENT Mr. Hare Ram Shrestha Society of Consulting Architectural and Engineering Firms, Nepal Background

More information

Options for Business Activities in the UAE

Options for Business Activities in the UAE October 2013 Options for Business Activities in the UAE The matrix below provides an overview of the options available for a foreign company to conduct business activities within the United Arab Emirates

More information

FINANCING FROM NON-DONOR RESOURCES

FINANCING FROM NON-DONOR RESOURCES Distribution: Limited GC 24/L.10 29 December 2000 Original: English Agenda Item 12 English IFAD Governing Council Twenty-Fourth Session Rome, 20-21 February 2001 FINANCING FROM NON-DONOR RESOURCES I. INTRODUCTION

More information

Accounting and Reporting Policy FRS 102. Staff Education Note 14 Credit unions - Illustrative financial statements

Accounting and Reporting Policy FRS 102. Staff Education Note 14 Credit unions - Illustrative financial statements Accounting and Reporting Policy FRS 102 Staff Education Note 14 Credit unions - Illustrative financial statements Disclaimer This Education Note has been prepared by FRC staff for the convenience of users

More information

STELLENBOSCH MUNICIPALITY

STELLENBOSCH MUNICIPALITY STELLENBOSCH MUNICIPALITY APPENDIX 9 BORROWING POLICY 203/204 TABLE OF CONTENTS. PURPOSE... 3 2. OBJECTIVES... 3 3. DEFINITIONS... 3 4. SCOPE OF THE POLICY... 4 5. LEGISLATIVE FRAMEWORK AND DELEGATION

More information

Roche Capital Market Ltd Financial Statements 2009

Roche Capital Market Ltd Financial Statements 2009 R Roche Capital Market Ltd Financial Statements 2009 1 Roche Capital Market Ltd, Financial Statements Reference numbers indicate corresponding Notes to the Financial Statements. Roche Capital Market Ltd,

More information

Corporate Governance Guidelines

Corporate Governance Guidelines Corporate Governance Guidelines 1. Introduction Entra ASA ( Entra ), and together with its subsidiaries, ( the group ) will be subject to the reporting requirements on corporate governance set out in 3

More information

Financial Management

Financial Management Different forms business organization Financial Management Sole proprietorship Partnership Cooperative society Company Private limited Vs Public limited company Private co min- two and max fifty, Pub Ltd

More information