1 TUNNELING AND UNDERGROUND CIVIL ENGINEERING EUROPE CENGIZ INSAAT AND MAKYOL Turkey RECORD TURKISH HIGHWAY TUNNEL TO BEAT THE SNOWS Sandvik drill-rigs employed by the CMA contracting joint venture are driving under Mount Ovit in north-eastern Turkey to ensure all-year-round land access to this relatively remote part of the country in Anatolia. Currently the main transport to Trabzon, Rize and surrounding regions from the main centres of Ankara and Istanbul is restricted to air, water via the Black Sea coast, and a long coastal road. More direct road transport to the rest of the nation has been held back by narrow roads and blockage of mountain passes by winter snows. Now, however, there is full momentum to complete a link that has been planned since 1880 in the times of the Ottoman Empire. The current road was constructed in 1930 over Mount Ovit pass at 2,600m (8,500ft) above sea level, and needed employment of 1,500 workers. 196 Sandvik Year 2013 in Action
2 Construction projects around the world 197
3 TUNNELING AND UNDERGROUND CIVIL ENGINEERING The new improved D925 highway project, valued at EUR 150M, will link Ikizdere, in Rize Province, and Ispir, in Erzurum Province, for the first time providing an all-year, all-weather link and boosting the local economies. LONGEST TUNNEL IN TURKEY In addition to various road improvement projects along the route, the Ovit Tunnel is the key element in the new link. It comprises two tubes of and, at 14.7km (48,200ft) long, it will be the longest tunnel in Turkey and, on completion, is expected to be the World s fourth longest road tunnel. reach the optimum portal positions. The two bores are connected by crosscuts at intervals of 250m to enable escape routes and to provide services accommodation. In profile there will be a grade, chiefly to facilitate drainage, of 3.5% for the first 7km from the main northwest portal, and of 1.0% for 5.5km from the other portal. At the high point, 2,500m above sea level there will be a 1,700m long drive, 8m square, to facilitate emergency egress and ventilation. This replaces the original plan for an access shaft as it was decided this would be too deep and difficult to access high up in the mountainous terrain. The tunnel plan is mainly straight with slight curves at each end to CONTRACTORS The contractor CMA (Cengiz Insaat and Makyol), responsible for the whole tunnel and highway construction project, and the client and owner is TCK, the Turkish national General Directorate of Highways. The project management structure is substantially affected by the two construction sites, at each tunnel portal, being remote from each other, especially in winter. Thus the site at the southeast portal has its own tunnelling and mechanical chiefs Ferhat Şahinbaş and Murat Ozan respectively. 198 Sandvik Year 2013 in Action
4 From left: Oğuzhan Öztürk, Burak Özgür and Sedat Şeker The project is led on site by Alper Eryiğit as project manager, supported by chief engineer Kerim Tütüncü. In the management structure under Kerim Tütüncü there is Muharrem Tezcan as tunnelling chief engineer and Sedat Seker as chief mechanical service engineer. Of the joint venture participants, Makyol has 42 years of experience in many heavy construction projects, making it one of the oldest and most experienced contractors in Turkey with many completed highway projects. It has also international experience in Albania, Algeria, Azerbaijan, Iraq, Morocco, and Oman. Tunnelling and mining specialist Cengiz was founded in 1980 and has been involved in many tunnelling, highway, mining and infrastructure projects, including work in Azerbaijan, Bulgaria, Bosnia-Herzegovina and Iraq as well as throughout Turkey. After that, we tested the new Alpha330 rock tools at the site and, with these tools they have minimized the hole deviation problems and consequently minimized the rod and especially shank adapter failures. Oğuzhan Öztürk Sandvik Construction LAYOUT The two tunnels are actually being driven as four drives with two partial faces in each. The full excavation dimensions of each horseshoe-shape drive are 8.4m height x 11.78m width, plus trenches on each side to provide space for future drains. First a top heading is driven to a height of 5.9m followed by a bench of 2.5m height, a contractual distance of 250m behind. A ramp between the two facilitates access for the drill-rig and mucking out. Alper Eryiğit RIGS Most of the tunnelling is carried out by drill-and-blast using four Sandvik DT820 rigs with standard manual controls, one for each of the current main tunnel excavation drives. Construction projects around the world 199
5 TUNNELING AND UNDERGROUND CIVIL ENGINEERING However the rigs also carry out any necessary rock bolting and excavation of crosscuts between the two bores. The decision to go for Sandvik is attributed to both a strong relationship between Sandvik Construction Turkey and the Cengiz Group, but the delivery times for the ordered rigs were also very important. In addition to the four tunnelling and one surface drill-rig (see below) used on the Mount Ovit site, Sandvik has also sold another three tunnelling rigs and a surface rig to Cengiz for a tunnelling project in Bosnia-Herzegovina. The Sandvik Construction Turkey tunnelling team, consisting of Erdinç Çetin, Oğuz Arslan and Burak Özgür, most closely associated with the Mount Ovit project, mentioned that the 1700-m new access drive to the centre of the main tunnel drives will enable CMA to test the newer DT921i tunnelling drill-rig. This will be equipped with Sandvik s advanced isure control software for fully automatic operation requiring minimal human intervention. Then, CMA will transfer the DT921i rig to granite faces in the southeast end of the planned tunnel. In addition to the four DT820 tunnelling drill-rigs a Sandvik DX700 top-hammer surface-drilling rig has been employed to excavate rock from the portals and associated cuttings. There is a long tradition of drill-and-blast tunnelling in Turkey and for such an important project CMA needed the best. We were looking first for well qualified operators, said Alper Eryiğit, but sometime training is necessary for which Sandvik is supporting us. HARD GOING Most of the rock to be excavated is expected to be granitic, both standard granite and porphyritic, or basalt, generally making good ground for drill-and-blast tunnelling. However there are some fracture zones between the main rock masses (see section summary version being scanned). CMA employs Sandvik ballistic bits of 45mm diameter for blast holes, and 51mm in diameter for rock-bolt holes. Using 4.9m-long drill rods, each round is drilled to a depth of up to 4.5m. This achieves an advance of 7 8m per day on all four current faces. At the time of the reporting some 6.2km of advance had been achieved, in totalling all four faces. Blasting is scheduled twice a day, usually meaning that there is a blast every 12-h working shift. The joint venture s Mechanical Maintenance Chief, Sedat Şeker, reports that the hard and abrasive rock has taken some toll of drill consumables. Even so, on average each blast hole bit lasts m without grinding. Earlier there had been shank breakage problems while drilling in the very hard rock, but since the adoption of the new design (Sandvik Alpha330) of rock tools, there have been no more problems. Sandvik Construction Turkey s Rock Tools Sales Engineer, Oğuzhan Öztürk explains, While they were using R38-R32 standard rock tools they had really big shank adaptor and rod failure problems due to very hard rock conditions the very hard granite. Most of the rod failures were because of the bending of the rods in the deviated holes. That was also the reason of the shank adapter failures. After that, we tested the new Alpha330 rock tools at the site and, with these tools they have minimized the hole deviation problems and consequently minimized the rod and especially shank adapter failures. 200 Sandvik Year 2013 in Action
6 SANDVIK ISURE OFFERS MANY MORE POSSIBILITIES TO CHECK HOLE LENGTH AND DRILLING PERFORMANCE. IT GIVES FAR BETTER CONTROL OF THE WHOLE DRILLING AND BLASTING PROCESS AND THEREFORE GIVES GOOD OPPORTUNITIES FOR PROCESS PERFORMANCE IMPROVEMENT. Erdinç Çetin Sandvik Construction Construction projects around the world 201
7 TUNNELING AND UNDERGROUND CIVIL ENGINEERING Now, they are using only Alpha330 tools for their underground drill rigs. This system has decreased their consumption, especially for rods and shank adapters, accelerated the drilling process, increased the hole quality which, in turn, is increasing the blasting efficiency and at the end decreasing the whole tunnelling process costs. Alpha330 rock tools are designed especially for 45mmdiameter drilling with high-power (20kW+) drills. Sandvik s particular expertise in steel metallurgy together with stateof-the-art CAD/CAM procedures has resulted in optimized geometry resulting in higher stiffness and longer service life than the earlier R32 design, also a Sandvik innovation. Project Manager Alper Eryiğit of CMA confirmed that although the rock is generally massive and hard, it can be variable. There are about 70m of soft ground at the portals, requiring special support measures. The rock was very abrasive between 300 and 350m in from the northwest portal. It took about four hours to drill a round until 250m, but on hitting the granite from 250m it took 3.5h. I would prefer moderate rock conditions for optimum progress, with time taken of 2.5h to drill a round rather than the h in granite. But the rock is changing and we are quite ok now. Overall we expect 75% of the drives to be in granite and 25 45% in basalt. CMA Tunnelling Chief Muharrem Tezcan reported that the normal drill patterns included blast holes in the top-heading wedge cut, and parallel holes in the bench. He explained that the blasting itself employs micro gel-style explosive in 38mm-diameter capsules as these produce lower air pollution, allowing the face to be approached earlier for support work and mucking out. Around 200kg is used in each top-heading blast. Initiation uses one electronic detonator attached to a non-electric circuit. INSTABILITY At the southeast portal there is up to 350m of overburden superficial and a large fracture zone, making tunnelling more problematical. We have suffered from water penetration and collapses, reports Eryiğit. The ground has changed to basalt with an alteration and fracture zone, but we are still continuing with drill-and-blast. Basalt actually occurs at both ends. To a considerable extent, the CMA tunnelling team has to be ready to tackle whatever it encounters. Eryiğit explained, There has been limited site investigation due to the great overburden, of up to 900m, meaning that there would be long investigation hole lengths with difficult access. This is partially why we are keen to check the performance of intelligent jumbos in the emergency access drive. Çetin added, Sandvik isure offers many more possibilities to check hole length and drilling performance. It gives far better control of the whole drilling and blasting process and therefore gives good opportunities for process performance improvement. SEQUENCE A typical tunnelling cycle starts with drilling the top heading first followed by blasting and loading out. The newly blasted surfaces are scaled with an excavatormounted hydraulic breaker. Then a primary lining of sprayed concrete, reinforced with polypropylene fibres, is applied up to the face for safety. Next the bench face undergoes the same sequence. SUPPORT Meanwhile systematic rock bolting, using the Sandvik DT820 drill-rigs, is carried out up to 15m behind the face, together with welded steel-mesh sheet installation and fibrereinforced sprayed concrete according to the determined 202 Sandvik Year 2013 in Action
8 rock type. Split-set-type rock bolts are normally installed. Although the more difficult rock types necessitate increasing measures such as higher rock bolt density and thicker sprayed concrete, the most unstable zones require different approaches. In soft rock and zones with high overburden self-drilling anchors (SDAs) are used to avoid having the drill hole stand open before installing the bolt. Using SDAs the drill-bit employed is sacrificial and the rebar drill steel is grouted in place immediately to secure early support. In addition, within the overburden area umbrella support is installed with lengths of rebar over the next stretches to be excavated. In all cases the versatile Sandvik DT820 drill rigs carry out all drilling and bolt installation. SERVICE CMA has its own workshops and maintenance crew on site, but supported in the case of drilling equipment by Sandvik. Frequently used consumables and service parts such as drill requirements and machine filters are stocked in the sites at both ends of the tunnel route but larger or less frequently needed parts are supplied by Sandvik from its depot in Trabzon. CMA uses original parts for all drillrig requirements. Commented CMA Chief of Mechanical Maintenance, Sedat Şeker, We are quite happy with Sandvik s performance in service and that of the equipment. There is usually sameday service response from the Trabzon depot. Two spare drills are available on site to permit overhauls in the workshops every 500 hours of operation. If view of the remote location of the sites, all workers usually remain in site accommodation, working 13 days out of 14 on 12-h shifts. FINAL STRUCTURE The support elements described earlier provide the required support during construction and as a base for the final structure. CMA will install cast-in-place concrete to a depth of 460mm using travelling formwork made in Turkey. First, however, a plastic waterproofing membrane is installed over a smooth layer of sprayed concrete. This provides a drainage passage to the main drains to be installed at the foot of each tunnel wall alongside service ducts. SCHEDULE CMA mobilized on its two construction sites and camps in 2012 with a groundbreaking ceremony on 12 May attended by national and local dignitaries. The tunnel is scheduled to be open for traffic in November/December 2015, in time for the winter snows, necessitating tunnelling to be complete by the mid-summer of that year. Sandvik Construction would like to thank all Mount Ovit project site management for their great co-operation in arranging the site visits and with the compilation of this report. FACTS SANDVIK DT820 Coverage m 2 Hole diameter mm Hole length 3,440 6,180 mm/10 16 ft Boom 2 x TB 90 Feed Rock drill Control and operation system Length (with default) feed) Width (drilling) Weight Weight with Utility boom 2 x TF Cylinder feeds 2 x HLX5 14,900 mm 4,660 mm 3,000 mm 26,500 kg 28,900 kg Construction projects around the world 203
METHOD OF STATEMENT FOR STATIC LOADING TEST
Compression Test, METHOD OF STATEMENT FOR STATIC LOADING TEST Tension Test and Lateral Test According to the American Standards ASTM D1143 07, ASTM D3689 07, ASTM D3966 07 and Euro Codes EC7 Table of Contents
More informationCurrent opportunities of sprayed waterproofing membrane. Frank Clement Technical Manager Sprayable Membranes MEYCO Global Underground Construction
Current opportunities of sprayed waterproofing membrane Frank Clement Technical Manager Sprayable Membranes MEYCO Global Underground Construction 1 What would we like to achieve? 2 What is desired? 3 and
More informationSpecification Guidelines: Allan Block Modular Retaining Wall Systems
Specification Guidelines: Allan Block Modular Retaining Wall Systems The following specifications provide Allan Block Corporation's typical requirements and recommendations. At the engineer of record's
More informationDesign, Testing and Automated Monitoring of ACIP Piles in Residual Soils
Design, Testing and Automated Monitoring of ACIP Piles in Residual Soils Stephen W. Lacz 1, M. ASCE, P.E. and Richard C. Wells 2, F. ASCE, P.E. 1 Senior Professional, Trigon Kleinfelder, Inc., 313 Gallimore
More informationTreatment Practice for Controlling Water Damage in the Annular Space of Shaft Freezing Hole
An Interdisciplinary Response to Mine Water Challenges - Sui, Sun & Wang (eds) 2014 China University of Mining and Technology Press, Xuzhou, ISBN 978-7-5646-2437-8 Treatment Practice for Controlling Water
More informationMine Wide Risk Assessment What is the State of your Arteries. L.Human, J Doolan and L Potts Xstrata Zinc
Mine Wide Risk Assessment What is the State of your Arteries L.Human, J Doolan and L Potts Xstrata Zinc Abstract A geotechnical mine wide risk management approach is presented for the systematic inspection,
More informationDITCH WITCH MT12 MICROTRENCHER. ditchwitch.com
DITCH WITCH MT12 MICROTRENCHER ditchwitch.com Rule With An Iron Fist. ditchwitch.com DITCH WITCH MT12 MicroTrencher Throughout the world, demand is increasing for faster broadband communications, necessitating
More informationProceedings 2005 Rapid Excavation & Tunneling Conference, Seattle
Proceedings 2005 Rapid Excavation & Tunneling Conference, Seattle EPB-TBM Face Support Control in the Metro do Porto Project, Portugal S. Babendererde, Babendererde Engineers LLC, Kent, WA; E. Hoek, Vancouver,
More informationRaise boring equipment
Raise boring equipment Special gauge saddle system Segmented reaming heads Extendable reaming heads All components are bolted together Optimum button design Flexible spacing raise boring equipment Reaming
More informationEmbedded Parts Introduction - Anchors
In the plant construction or process plants such as chemical, petrochemical, gas or power plants various disciplines are brought into contact and built on each other. Civil, mechanical, electro technical
More informationThe Manitoba Water Services Board SECTION 022180 Standard Construction Specifications PIPE EXCAVATION, BEDDING AND BACKFILL Page 1 of 11
Page 1 of 11 Part 1 General 1.1 DESCRIPTION OF WORK.1 The work described herein shall consist of the excavation of trenches (or excavation of tunnels); the supply and placing of bedding and backfill materials;
More informationJune 2007 CHAPTER 7 - CULVERTS 7.0 CHAPTER 7 - CULVERTS 7.1 GENERAL
7.0 7.1 GENERAL For the purpose of this manual, culverts are defined as structures that are completely surrounded by soil and located below the surface of the roadway parallel to the general direction
More informationMembrane for tunnels and underground construction
System Platon Membrane for tunnels and underground construction Drainage Protection Waterproofing Dry and healthy buildings The Isola history quality through innovation CONTENT The Isola History Air Gap
More informationThere is no water, surface tension cracks, nor other environmental conditions present that reduce the stability of the excavation.
Part 1926 Subpart P Introduction The Occupational Safety and Health Administration (OSHA) issued its first Excavation and Trenching Standard in 1971 to protect workers from excavation hazards. Since then,
More informationTypes of Mining - Expert Table
See page 6 Minerals Downunder Teacher Guide (2002) - Activity 4a Types of Mining - Expert Table How to Jigsaw Information 1. Divide the class into Home Groups of five for the five different types of mining
More informationHigh Strain Dynamic Load Testing of Drilled Shafts
Supplemental Technical Specification for High Strain Dynamic Load Testing of Drilled Shafts SCDOT Designation: SC-M-712 (9/15) September 3, 2015 1.0 GENERAL This work shall consist of performing high-strain
More informationSource: Port Mann Bridge Plans Unveiled Today, CBC News, February 4, 2009.
Total project cost $2.5 billion (Canadian) Financed by tolls about $3 each direction. Total project length 37 km (McGill St in Vancouver to 216 th in Langley) The new Port Mann bridge 10 lanes (existing
More informationAmendment to OPSS 415 (Nov 2008) Construction Specification for Pipeline and Utility Installation by Tunnelling
Engineering and Construction Services Division Standard Specifications for Sewers and Watermains TS 415 April 2013 Amendment to OPSS 415 (Nov 2008) Construction Specification for Pipeline and Utility Installation
More informationSECTION 36 - CAST-IN-PLACE CONCRETE PIPE (CIPCP) TABLE OF CONTENTS
SECTION 36 - CAST-IN-PLACE CONCRETE PIPE (CIPCP) TABLE OF CONTENTS Section Page 36-1 GENERAL... 36.1 36-2 PIPEMAKING EQUIPMENT... 36.1 36-3 TRENCH EXCAVATION... 36.1 36-4 SPECIAL FOUNDATION TREATMENT...
More informationATLAS RESISTANCE Pier Foundation Systems
ATLAS RESISTANCE Pier Foundation Systems Foundation Repair Systems for Civil Construction Applications: Residential, Commercial, Industrial Atlas Resistance Piers have been used to restore and/or stabilize
More informationSPEEDROC D30. Surface Drill Rig for marble, granite, sandstone and limestone in the dimension stone industry.
SPEEDROC D0 Surface Drill Rig for marble, granite, sandstone and limestone in the dimension stone industry. SPEED UP YOUR PROFITS SPEEDROC D0 IS A VERSATILE AND FLEXIBLE DRILL RIG, TAILORMADE FOR THE DIMENSION
More informationOhio Department of Transportation Division of Production Management Office of Geotechnical Engineering. Geotechnical Bulletin PLAN SUBGRADES
Ohio Department of Transportation Division of Production Management Office of Geotechnical Engineering Geotechnical Bulletin GB 1 PLAN SUBGRADES Geotechnical Bulletin GB1 was jointly developed by the Offices
More informationGeotechnical Building Works (GBW) Submission Requirements
Building Control (Amendment) Act 2012 and Regulations 2012: Geotechnical Building Works (GBW) Submission Requirements Building Engineering Group Building and Construction Authority May 2015 Content : 1.
More informationTechnical Information
Technical Information This section of the catalogue provides technical information that will help specify, install and maintain Surelock McGill devices and components. The topics are listed below: Blast
More informationDUDERSTADT FOUNDATION & CONSTRUCTION, LLC.
DUDERSTADT FOUNDATION & CONSTRUCTION, LLC. Drilling since 1916 2215 Belknap Place Phone (210) 824-3800 San Antonio, TX 78212-1904 Fax (210) 824-9525 www.duderstadtfoundation.com ABOUT THE COVER: Drilled
More informationKWANG SING ENGINEERING PTE LTD
KWANG SING ENGINEERING PTE LTD 1. INTRODUCTION This report represents the soil investigation works at Aljunied Road / Geylang East Central. The objective of the soil investigation is to obtain soil parameters
More informationEstimation of Adjacent Building Settlement During Drilling of Urban Tunnels
Estimation of Adjacent Building During Drilling of Urban Tunnels Shahram Pourakbar 1, Mohammad Azadi 2, Bujang B. K. Huat 1, Afshin Asadi 1 1 Department of Civil Engineering, University Putra Malaysia
More informationagrees to replace at no charge any tree that dies and subsequent inspection shows that the wire basket was not properly removed.
Adopted 12/5/00; revised as of 1/2/07 Marietta Tree Commission Rules and Regulations I. Tree Planting A. Planting Specifications 1. Trees must be: A) of a minimum 1¼ inches caliper; B) single stem, straight,
More informationTECHNICAL NOTE Culvert Sliplining and Lining of Casings with HPPipe
TECHNICAL NOTE Culvert Sliplining and Lining of Casings with HPPipe TN 5.14 February 2010 Introduction It may be at times necessary, in an aging infrastructure, to rehabilitate drainage and sanitary lines
More informationhs2 Ground A non-technical guide
hs2 Ground Investigations A non-technical guide Contents HS2 ground investigations 1 Essential Q&A 2 2 In-ground investigation techniques 9 2.1 Cable percussion borehole 10 2.2 Rotary core borehole 12
More informationSan Antonio Water System Standard Specifications for Construction ITEM NO. 854 SANITARY SEWER LATERALS
San Antonio Water System Standard Specifications for Construction ITEM NO. 854 SANITARY SEWER LATERALS 854.1 DESCRIPTION: This item shall govern sanitary sewer laterals installed in accordance with these
More informationHydraulic Excavators
Chapter 8 Hydraulic Excavators Hydraulic excavators are designed to excavate below the ground surface on which the machine rests. These machines have good mobility and are excellent for general-purpose
More informationGUIDANCE NOTES FOR DEVELOPMENTS OR ENGINEERING WORKS IN THE VICINITY OF SPT SUBWAY INFRASTRUCTURE JULY 2005
GUIDANCE NOTES FOR DEVELOPMENTS OR ENGINEERING WORKS IN THE VICINITY OF SPT SUBWAY INFRASTRUCTURE JULY 2005 CONTENTS 1.0 INTRODUCTION 2.0 OVERVIEW OF SPT APPROACH TO DEVEOPMENTS/WORKS IN THE VICINITY OF
More informationCivil. 2. City of Seattle Supplement to the Specification for Road, Bridge and Municipal Construction, most current addition.
Design Guide Basis of Design This section applies to the design and installation of earthwork and backfill. Design Criteria No stockpiling of excavation materials is allowed unless the Geotechnical Engineer
More informationSystem. Stability. Security. Integrity. 150 Helical Anchor
Model 150 HELICAL ANCHOR System PN #MBHAT Stability. Security. Integrity. 150 Helical Anchor System About Foundation Supportworks is a network of the most experienced and knowledgeable foundation repair
More informationIH-635 MANAGED LANES PROJECT, SEG. 3.2
IH-635 MANAGED LANES PROJECT, SEG. 3.2 Location: Dallas, Texas Owner: Texas Department of Transportation Client: Ferrovial Agroman Construction Cost: $1 Billion Construction Completion Date: December,
More informationAtlas Copco Surface drill rigs. SmartROC T35/ T40. Hole diameter: SmartROC T35: 64 115 mm (2 1 /2 4 1 /2 ) SmartROC T40: 76 127 mm (3 5 )
Atlas Copco Surface drill rigs SmartROC T35/ T40 Hole diameter: SmartROC T35: 64 115 mm (2 1 /2 4 1 /2 ) SmartROC T40: 76 127 mm (3 5 ) When smart means easy and efficient Main benefits Combines low fuel
More informationSPECIFICATION FOR PIPE SUBSOIL DRAIN CONSTRUCTION
SPECIFICATION FOR PIPE SUBSOIL DRAIN CONSTRUCTION 1. SCOPE Pipe subsoil drains shall be constructed in accordance with this specification and in conformity with the lines, grades and cross-sections shown
More informationWorld Tunnel Congress 2008 - Underground Facilities for Better Environment and Safety - India
World Tunnel Congress 2008 - Underground Facilities for Better Environment and Safety - India Rehabilitation of concrete lined tunnels using a composite sprayed liner with sprayed concrete and sprayable
More informationMounting accessories TÖBB MINT VÁLASZTÉK
96 FOR ADHESIVE DISCS The adhesive discs with various dimension and shapes are easy to use for mounting. Because of their flexible types they are suitable for sanding of flat or curving surfaces. GRINDING
More information2013 WJTA-IMCA Conference and Expo September 9-11, 2013 Houston, Texas Paper REFRACTORY REMOVAL BY HIGH PRESSURE WATERJET
2013 WJTA-IMCA Conference and Expo September 9-11, 2013 Houston, Texas Paper REFRACTORY REMOVAL BY HIGH PRESSURE WATERJET D. Wright StoneAge, Inc. Durango, Colorado, U.S.A. ABSTRACT The removal of refractory
More informationNumerical Modelling for Shallow Tunnels in Weak Rock By Evert Hoek Unpublished Notes
Numerical Modelling for Shallow Tunnels in Weak Rock By Evert Hoek Unpublished Notes Introduction When designing a shallow tunnel in a poor quality rock mass, the designer has to face a number of problems
More informationCHAPTER 2 HYDRAULICS OF SEWERS
CHAPTER 2 HYDRAULICS OF SEWERS SANITARY SEWERS The hydraulic design procedure for sewers requires: 1. Determination of Sewer System Type 2. Determination of Design Flow 3. Selection of Pipe Size 4. Determination
More informationSolutions for tunneling and mining. Waterproofing. Expanding Horizons Underground. Expanding horizons underground
Solutions for tunneling and mining Waterproofing Expanding Horizons Underground Expanding horizons underground The Bonded Waterproofing Concept An innovative approach, the MASTERSEAL 345 waterproofing
More informationLIFE SCIENCE. Hoop House Construction for New Mexico: 12-ft. x 40-ft. Hoop House BRINGING TO YOUR HOME ECONOMICS COLLEGE OF AGRICULTURE AND
Hoop House Construction for New Mexico: 12-ft. x 40-ft. Hoop House COLLEGE OF AGRICULTURE AND HOME ECONOMICS BRINGING SCIENCE TO YOUR LIFE Hoop House Construction for New Mexico: 12-ft. x 40-ft. Hoop House
More informationBackfill for Bench Stoping Operations
Backfill for Bench Stoping Operations E. Villaescusa Professor of Mining Geomechanics, Western Australian School of Mines K. Kuganathan Senior Backfill Research Engineer, Mount Isa Mines ABSTRACT This
More informationSUPPORT IN UNDERGROUND HARD ROCK MINES
SUPPORT IN UNDERGROUND HARD ROCK MINES Evert Hoek, NSERC Industrial Research Professor, Department of Civil Engineering, University of Toronto, Toronto, Canada. David. F. Wood, Senior Engineer, Golder
More informationTunnelling and underground works in PPC hydro projects: Contracting practices & construction management Ioannis Thanopoulos Dr.
Tunnelling and underground works in PPC hydro projects: Contracting practices & construction management Ioannis Thanopoulos Dr. Civil Engineer Public Power Corporation, Greece Public Power Corporation
More informationSpecification for tunnelling third edition. The British Tunnelling Society and The Institution of Civil Engineers
Specification for tunnelling third edition The British Tunnelling Society and The Institution of Civil Engineers Published by Thomas Telford Limited, 40 Marsh Wall, London E14 9TP, UK. www.thomastelford.com
More informationGeotechnical Measurements and Explorations Prof. Nihar Ranjan Patra Department of Civil Engineering Indian Institute of Technology, Kanpur
Geotechnical Measurements and Explorations Prof. Nihar Ranjan Patra Department of Civil Engineering Indian Institute of Technology, Kanpur Lecture No. # 13 (Refer Slide Time: 00:18) So last class, it was
More informationSection 2100-Trenching and Tunneling
SECTION 5200 - STORM SEWER PART 1 - GENERAL 1.01 SCOPE: This Section covers installation of storm sewer mains and culverts. Topics include permits and fees, trench widths, pipe laying, bedding, initial
More informationSupplier ID: 26421. Local Office: GLASGOW 69 Buchanan Street Glasgow G1 3HL
M D & FOUNDATIONS MIDLANDS Supplier ID: 26421 MINI PILING PILING REINFORCED CONCRETE UNDERPINNING DRILLING & GROUTING SITE INVESTIGATION & PILE TESTING NATIONWIDE SPECIALIST PILING & FOUNDATION SERVICES
More informationShower and Floor Gullies Channel Drain and Tile Drain SECTION
Shower and Floor Gullies Channel Drain and Tile Drain SECTION 2 Shower and Floor Gullies, Channel Drain and Tile Drain 29 General Information Shower and Floor Gullies McAlpine has responded to market conditions
More informationSUPPLEMENTAL TECHNICAL SPECIFICATIONS BI-DIRECTIONAL STATIC LOAD TESTING OF DRILLED SHAFTS
July 14, 2015 1.0 GENERAL BI-DIRECTIONAL STATIC LOAD TESTING OF DRILLED SHAFTS This work shall consist of furnishing all materials, equipment, labor, and incidentals necessary for conducting bi-directional
More informationNew in the PFERD Product Line 204
COMBICLICK Fibre Discs COMBICLICK fibre discs Silicon carbide SiC D The silicon carbide SiC type is suitable for working on aluminium, copper, bronze, titanium, high-alloy steels and fibre reinforced plastics.
More informationEarth Retaining Structures
Earth Retaining Structures and Asset Management Earth Retaining Structures and Asset Management A Critical Component Tool in Maintaining Public Safety Earth Retaining Structures (ERS) are often an overlooked
More informationSHAFT CONSTRUCTION IN TORONTO USING SLURRY WALLS
SHAFT CONSTRUCTION IN TORONTO USING SLURRY WALLS Vince Luongo Petrifond Foundation Co., Ltd. PROJECT DESCRIPTION The York Durham Sanitary System (YDSS) Interceptor in the Town of Richmond Hill located
More informationMicropiles Reduce Costs and Schedule for Merchant RR Bridge Rehabilitation
Micropiles Reduce Costs and Schedule for Merchant RR Bridge Rehabilitation Jeff R. Hill, P.E. Hayward Baker Inc. 111 W. Port Plaza Drive Suite 600 St. Louis, MO 63146 314-542-3040 JRHill@HaywardBaker.com
More informationTunnelling & Underground. Specialists
Tunnelling & Underground Specialists Mined Tunnels Excavation at Ayer Rajah Avenue, Singapore Introduction Amberg & TTI Engineering Pte Ltd (AETTI) was established in Singapore in 2002 by Amberg Engineering
More informationSECTION 02150 REMOVAL OR ABANDONMENT OF EXISTING UTILITIES AND UNDERGROUND STRUCTURES. 1. Trench excavation, backfill, and compaction; Section 02250.
02150-1 of 6 SECTION 02150 REMOVAL OR ABANDONMENT OF EXISTING 02150.01 GENERAL A. Description Removal or abandonment of existing utilities and underground structures shall include, but not necessarily
More informationGOWANUS EXPRESSWAY TUNNEL PRIMER
GOWANUS EXPRESSWAY TUNNEL PRIMER T he New York State Department of Transportation is currently studying the replacement of the Gowanus Expressway with a tunnel. This investigation involves looking at a
More informationHow To Retaining Wall Guide
How To Retaining Wall Guide Before you start: Consents and Engineering Building Consent Retaining walls over 1.5m high will require a building consent from the Local Body Council. Walls that carry extra
More informationUNDERSTANDING UNDERGROUND INTELLIGENT SOLUTIONS FOR TUNNELING AND UNDERGROUND CIVIL ENGINEERING
UNDERSTANDING UNDERGROUND INTELLIGENT SOLUTIONS FOR TUNNELING AND UNDERGROUND CIVIL ENGINEERING CLEANER ENVIRONMENT WITH SAFE TUNNELING In the future, underground construction will be more and more essential
More informationMoving Small Mountains Vesuvius Dam Rehab
Moving Small Mountains Vesuvius Dam Rehab Susan L. Peterson, P.E., regional dams engineer, Eastern Region, Bedford, IN Note: The following article, Moving Small Mountains Vesuvius Dam Rehab, by Sue Peterson,
More informationSEBENICO ATSI COMPANY OVERVIEW
Capability Statement SEBENICO ATSI Sebenico ATSI in line with our Aboriginal principles will implement solid processes and good governance to bring together Indigenous and Non indigenous people to work
More information50AI01oe 02/15. Labko GRP cesspools. Instructions for installation, operation and maintenance
02/15 Labko GRP cesspools Instructions for installation, operation and maintenance Reliable solutions Wastewater treatment systems Contents 1 LABKO CESSPOOLS... 3 1.1 GENERAL... 3 1.2 IMPORTANT TO KNOW
More informationREQUIREMENTS AND SPECIFICATIONS FOR HIGH VOLTAGE CUSTOMER BUILT FACILITIES PEPCO ENGINEERING
REQUIREMENTS AND SPECIFICATIONS FOR HIGH VOLTAGE CUSTOMER BUILT FACILITIES PEPCO ENGINEERING Revised October, 2013 TABLE OF CONTENTS 1.0 INTRODUCTION... 3 2.0 REQUIRED DRAWINGS... 3 2.1 Site Plan... 3
More informationIt's large enough to handle most welding job shop projects, yet small enough to make it a worth while home-workshop tool
It's large enough to handle most welding job shop projects, yet small enough to make it a worth while home-workshop tool H Craft Print Project No. 272 ERE'S a metal bender that will enable you to bend
More informationTUNNEL boring was originally attempted over 150 years
The advantages of tunnel boring : a qualitative/quantitative comparison of D&B and TBM excavation by Peter J Tarkoy, PhD, Geotechnical and Tunnel Construction Consultant and James E Byram, PhD, Senior
More informationSECTION 55 PIPE FOR STORM DRAINS AND CULVERTS (FAA D-701)
SECTION 55 PIPE FOR STORM DRAINS AND CULVERTS (FAA D-701) 55-1 GENERAL The Contractor shall perform all work required by the plans for construction of pipe for storm drains, precast polymer trench drains
More informationTYPES OF PIERS USED IN NORTH AND EAST TEXAS RESIDENTIAL FOUNDATION REPAIR
TYPES OF PIERS USED IN NORTH AND EAST TEXAS RESIDENTIAL FOUNDATION REPAIR If you listen to the hype, it sounds like there must be 20 or 30 different types of piers out there. Company A says they have an
More informationInspection, Maintenance, and Repair of PaCT Canadian Pacific Rogers Pass Tunnels British Columbia, Canada
Inspection, Maintenance, and Repair of PaCT Canadian Pacific Rogers Pass Tunnels British Columbia, Canada by David N. Bilow, P.E., S.E., Director, Engineered Structures Portland Cement Association 5420
More informationIntegrated Manhole Ladder System
Application: This innovative product has been designed to provide safe access and egress to precast concrete manholes and inspection chambers. It can also be used within any other underground concrete
More informationFlash Butt Welding Machines
Flash Butt Welding Machines Types AS 15 - AS 320 Flash butt welding current brake current (ka) current time flattening reversal preheating welding time flash butting forging A reliable and economic process
More informationStructures Construction Pre-Work Checklist PRE-WORK SHEET FOR PROJECT MANAGERS
Structures Construction Pre-Work Checklist PRE-WORK SHEET FOR PROJECT MANAGERS 1 Proposal & Plans Received? 2 Review Proposal, highlight important facts. Know proposal well to be able to find answers quickly.
More informationHigh Capacity Helical Piles Limited Access Projects
High Capacity Helical Piles Limited Access Projects Tel 403 228-1767 Canada, USA, Russia Brendan ODonoghue 519 830-6113 Presentation Summary 1. Helical piles Background on large diameter shafts and helices
More informationReport on. Wind Resistance of Signs supported by. Glass Fiber Reinforced Concrete (GFRC) Pillars
Report on Wind Resistance of Signs supported by Glass Fiber Reinforced Concrete (GFRC) Pillars Prepared for US Sign and Fabrication Corporation January, 2006 SUMMARY This study found the attachment of
More informationState of Illinois Department Of Transportation CONSTRUCTION INSPECTOR S CHECKLIST FOR STORM SEWERS
State of Illinois Department Of Transportation CONSTRUCTION INSPECTOR S CHECKLIST FOR STORM SEWERS While its use is not required, this checklist has been prepared to provide the field inspector a summary
More informationHow to build raised beds page
This leaflet has information to help you if you want to build a raised bed yourself or if you need information to give to a professional contractor. This information should be read in conjunction with
More informationThe work of this Section includes furnishing and installing Reinforced Concrete Pressure Pipe as shown on the Drawings and as specified.
Section 33 0200- Page 1 of 4 PART 1 - GENERAL 1.1 DESCRIPTION OF WORK The work of this Section includes furnishing and installing Reinforced Concrete Pressure Pipe as shown on the Drawings and as specified.
More information2. THE TEORRETICAL OF GROUND PENETRATING RADAR:
Sixteenth International Water Technology Conference, IWTC 16 2012, Istanbul, Turkey 1 THE USE OF GROUND PENETRATING RADAR WITH A FREQUENCY 1GHZ TO DETECT WATER LEAKS FROM PIPELINES Alaa Ezzat Hasan Ministry
More informationCutting the World. Cutting tools. for rotary drum cutters
Cutting the World Cutting tools for rotary drum cutters Round attack picks, pick boxes, retaining clips for erkat rotary drum cutters and cutter wheels erkat rotary drum cutters work under extremely hard
More informationDIAMOND Retractable Rodding Robot Model SPRAYROD-R
2004-12-21 2 1 (23) DIAMOND Retractable Rodding Robot Model SPRAYROD-R 2004-12-21 2 2 (23) Table of contents 1 TECHNICAL DESCRIPTION...4 1.1 MAIN DETAILS...5 1.2 COMPONENTS DESCRIPTION...5 1.2.1 Pneumatic
More informationINSITU TESTS! Shear Vanes! Shear Vanes! Shear Vane Test! Sensitive Soils! Insitu testing is used for two reasons:!
In-situ Testing! Insitu Testing! Insitu testing is used for two reasons:! To allow the determination of shear strength or penetration resistance or permeability of soils that would be difficult or impossible
More informationBAUER Manufacturing Inc.
BAUER Manufacturing Inc. Conroe, Texas Supplying Equipment and Services to Industry 2/2013 BAUER Manufacturing Inc. BAUER Manufacturing Inc. (BMC) is located in the City of Conroe, Texas, approximately
More informationWelcome: What is U Drain? Drain Materials. Flow
Welcome: Thank you for looking into the U Drain floor drain system. This paper will explore the functional features of the U Drain and why it is superior to other grated systems in the marketplace. We
More informationHEAVY DUTY SEVERING AND BEVELLING MACHINE TNO FAB-SERIES
HEAVY DUTY SEVERING AND BEVELLING MACHINE TNO FAB-SERIES PROTEM USA LLC 29340 Industrial Way, # 402 Evergreen, CO 80439 USA Phone: +1 303 955 4862 Fax: +1 303 955 5904 contact@protemusa.com www.protemusa.com
More informationHow to Estimate the Cost of Support of Excavation for Foundation Installation. CPE Candidate No. 0113013. May 15, 2013
How to Estimate the Cost of Support of Excavation for Foundation Installation CPE Candidate No. 0113013 May 15, 2013 1 How to Estimate the Cost of Support of Excavation for Foundation Installation Table
More informationStability. Security. Integrity.
Stability. Security. Integrity. PN #MBHPT Foundation Supportworks provides quality helical pile systems for both new construction and retrofit applications. 288 Helical Pile System About Foundation Supportworks
More informationSPECIFICATION FOR DYNAMIC CONSOLIDATION / DYNAMIC REPLACEMENT
SPECIFICATION FOR DYNAMIC CONSOLIDATION / DYNAMIC REPLACEMENT 1.0 SOIL IMPROVEMENT 1.1 General Soil Investigation Information are provided in Part B1 annex as a guide to the Contractor for his consideration
More informationWanner,M.C. (IPA-Stuttgart), Baumeister,K. (IPA-Stuttgart), Kohler,G.W. (KFK-Karlsruhe), Walze,H. (KFK-Karlsruhe)
Applications of programmable handling-units in contracting companies Wanner,M.C. (IPA-Stuttgart), Baumeister,K. (IPA-Stuttgart), Kohler,G.W. (KFK-Karlsruhe), Walze,H. (KFK-Karlsruhe) 1. Introduction Following
More informationUnit Price Averages Reports
Unit Price Averages Reports 12/7/2015 UNIT PRICE AVERAGES REPORT Disclaimer The information provided in the following Unit Price Averages Report is only for the use of Alberta Infrastructure & Transportation
More informationIndex. protection. excavated drop inlet protection (Temporary) 6.50.1 6.51.1. Block and gravel inlet Protection (Temporary) 6.52.1
6 Index inlet protection excavated drop inlet protection (Temporary) 6.50.1 HARDWARE CLOTH AND GRAVEL INLET PROTECTION Block and gravel inlet Protection (Temporary) sod drop inlet protection ROCK DOUGHNUT
More informationMORE CARE. BUILT IN. VOLVO EXCAVATOR. hydraulic hammers
MORE CARE. BUILT IN. VOLVO EXCAVATOR hydraulic hammers For extra-tough conditions, Volvo hammers deliver high impact Stubborn rock. Concrete debris. Frost-locked earth. These are the kinds of conditions
More informationForensic engineering of a bored pile wall
NGM 2016 Reykjavik Proceedings of the 17 th Nordic Geotechnical Meeting Challenges in Nordic Geotechnic 25 th 28 th of May Forensic engineering of a bored pile wall Willem Robert de Bruin Geovita AS, Norway,
More informationValidation of Cable Bolt Support Design in Weak Rock Using SMART Instruments and Phase 2
Validation of Cable Bolt Support Design in Weak Rock Using SMART Instruments and Phase 2 W.F. Bawden, Chair Lassonde Mineral Engineering Program, U. of Toronto, Canada J.D. Tod, Senior Engineer, Mine Design
More informationTUBULAR Holing and Slotting Of Casing
TUBULAR Holing and Slotting Of Casing Holing and Slotting of Casing Introduction.................. 243-244 Slotting machines Hydraulic Handling System Holing Machines Deburring Pipe coating Banding QA
More informationHow Did These Ocean Features and Continental Margins Form?
298 10.14 INVESTIGATION How Did These Ocean Features and Continental Margins Form? The terrain below contains various features on the seafloor, as well as parts of three continents. Some general observations
More informationPVE Piling and Drilling Rigs Powerful, Versatile and Efficient. PVE Piling and Drilling Rigs B.V. Worldwide supply of specialized foundation machines
PVE Piling and Drilling Rigs Powerful, Versatile and Efficient PVE Piling and Drilling Rigs B.V. Worldwide supply of specialized foundation machines Member of the PVE Piling and Drilling Rigs PVE Piling
More informationEurocode 7 - Geotechnical design - Part 2 Ground investigation and testing
Brussels, 18-20 February 2008 Dissemination of information workshop 1 Eurocode 7 - Geotechnical design - Part 2 Ground investigation and testing Dr.-Ing. Bernd Schuppener, Federal Waterways Engineering
More information