EXISTING MASONRY WALL TO REMAIN (TYP.). EXISTING PARTITION TO REMAIN PROVIDE 3'-3" W. X 8'-0"H. NEW PELLA WINDOWS AS INDICATED ON PLANS. (TYP.
|
|
- Johnathan Hunt
- 8 years ago
- Views:
Transcription
1 EXISTING MASONRY WALL TO REMAIN N EXISTING MASONRY WALL TO REMAIN (TYP.). PROVIDE COPPER THROUGH-WALL FLASHING DN EXISTING MASONRY PARTY CHIMNEY AND WALL TO REMAIN (TYP.). EXISTING MASONRY PARTY WALL TO REMAIN (TYP.). SEE NOTES EXISTING COMMERCIAL SPACE AS PER DOB JOB # TO REMAIN EXISTING PARTITION TO REMAIN EXISTING HR FIRE RATED DOOR TO REMAIN - EGRESS FROM FIRST FLOOR PROVIDE 3'-3" W. X 8'-0"H. NEW PELLA WINDOWS AS INDICATED ON PLANS. (TYP.) EXISTING STAIRCASE AND STAIRS TO REMAIN (NO WORK)-EGRESS FROM FIRST AND SECOND FLOOR EXISTING FIRE ESCAPE BALCONY AND DROP LADDER TO REMAIN BE RENOVATED AND MODIFIED TO A NEW LAYOUT, AS REQ. 3'-3" 3'-3" 3'-3" 3'-3" WEEP HOLES AT 24" O.C. PROVIDE SLOPED CONC. SILL TO MATCH EXISTING ADJACENT AT ELEVATION. SILL TO BE SET IN MORTAR. DRIP WEEP HOLES AT 24" O.C. ± 12" V.I.F. TYPICAL DETAIL AT NEW LINTEL AND WINDOW SILL FIRE-RATED COLUMN ENCLOSURE PROVIDE NEW STEEL LINTEL AND NEW STONE DECO LINTEL TO MATCH EXISTING ADJACENT. NEW STL. LINTEL TO BE DOUBLE 4"X6"X 5 16" STEEL LINTEL PROVIDE FIREPROOFING (AS PER NYC CODE FOR MASONRY OPENING WIDER THAN FOUR FEET) AT INSIDE LINTEL- MIN " SHOTCRETE ON WIRE MESH WFF. NEW WINDOW BY "PELLA" WD. CASING T.B.D. CCA TREATED WD. BLOCKING AS REQUIRED COPPER FLASHING. PROVIDE THE END DAMS. CONCRETE SILL RIGID INSULATION W/ VAPOR BARRIER These plans are an instrument of service and are the property of the Architect. Any infringements will be prosecuted TH AVENUE RIDGEWOOD, New York FAX PROVIDE 3'-3"W.X8'-0"H. NEW PELLA WINDOWS AS INDICATED ON PLANS. (TYP.) UP F.D. LOCATION 117 SECOND AVENUE NY, NY EXISTING FRSC DOOR TO REMAIN PARTIAL DEMOLITION EXISTING PARTY WALL TO REMAIN (TYP.). SEE NOTES BELOW PROVIDE 3'-3"W. X8'-0"H. NEW PELLA WINDOWS AS INDICATED ON PLANS. (TYP.) 3'-3" SECOND FLOOR 3'-3" 3'-3" 3'-3" W" x H" SEAL & SIGNATURE DATE: PROJECT No: SECOND FLOOR PLAN MASONRY/GYP. BD. EXTERIOR WALL DRAWING BY: A.W. CHK BY: W.O. DWG No: A PAGE: 4 of 5
2 16'-10" 13'-9" 10'-0" 10'-0" These plans are an instrument of service and are the property of the Architect. Any infringements will be prosecuted TH AVENUE RIDGEWOOD, New York FAX LOCATION 117 SECOND AVENUE NY, NY PARTIAL DEMOLITION SECOND AVENUE 7-TH STREET ELEVATIONS SEAL & SIGNATURE DATE: PROJECT No: DRAWING BY: A.W. CHK BY: W.O. DWG No: A PAGE: 5of 5
3 REPLACEMENT OF THE ALUMINIUM AND GLASS WALL WITH THE MASONRY WALL 117 2ND AVENUE, MANHATTAN, NY '-0" 21'-0" ONE STORY ENTRANCE 42'-8" 70'-0" 21'-8" 21'-8" CONC. SIDEWALK 2-ND AVENUE 70'-0" FIRE ESCAPE 7-TH STREET TWO STORY METAL AND GLASS CURTAIN WALL TO BE REMOVED AND REPLACED WITH THE MASONRY WALL WITH WINDOWS These plans are an instrument of service and are the property of the Architect. Any infringements will be prosecuted. Architecture PC PLOT PLAN LOCATION OF THE PROPERTY ZONING INFORMATION TH AVENUE RIDGEWOOD, New York FAX LOCATION 117 2ND AVENUE NEW YORK, NY DEMOLITION JOB # SIDEWALK BRIDGE 3. PIPE SCAFFOLDING NOTES: SCOPE OF WORK: DEMOLITION OF THE ALUMIN./GLASS CURTAIN WALL AND CONSTRUCTION OF THE MASONRY WALL WITH WINDOWS AND METAL STUD FURRING AT 2ND FLOOR LEVEL ONLY. ZONING INFORMATION PLOT PLAN LOCATION PLAN NO CHANGE IN USE, EGRESS, OR OCCUPANCY SEAL & SIGNATURE DATE: PROJECT No: DRAWING BY: A.W. CHK BY: W.O. LOCATION PLAN DWG No: G PAGE: 1 of 5
4 These plans are an instrument of service and are the property of the Architect. Any infringements will be prosecuted. Architecture PC TH AVENUE RIDGEWOOD, New York FAX LOCATION 117 2ND AVENUE NEW YORK, NY ENERGY CALCULATIONS AND STATEMENT ADA NOTES SEAL & SIGNATURE DATE: PROJECT No: DRAWING BY: A.W. CHK BY: W.O. DWG No: G PAGE: 2 of 5
5 Submitted for Review to: Landmarks Preservation Commission HISTORIC PHOTOGRAPHS 117 2ND AVENUE ND AVENUE ND AVENUE-1980 ORIGINAL PEAKED ROOF WAS EXPANED TO FULL FOURTH STORY IN 1883, QUEEN ANN CORNICE INSTALLED AT THE SAME TIME ARCH. JOBS HOFFMANN 42'-8" EXISTING ADJACENT 5 STORY BRICK BUILDING 21'-8" CONC. SIDEWALK CONC. SIDEWALK 21'-0" EXISTING ADJACENT 3 STORY BRICK BUILDING W/ CEMENT FACED FACADE 70'-0" EXISTING 4 STORY BRICK BUILDING W/ COLOR CEMENT FACED FACADE 70'-0" FIRE ESCAPE 7-TH STREET 115 2ND AVENUE 117 2ND AVENUE 119 2ND AVENUE 21'-0" ONE STORY ENTRANCE 21'-8" CONC. SIDEWALK 2ND STORY METAL AND GLASS CURTAIN WALL TO BE REMOVED AND REPLACED WITH THE MASONRY WALL WITH WINDOWS CONC. SIDEWALK 2-ND AVENUE FACADE RENOVATION AT 2ND, 3RD AND 4TH FLOOR LPC-01 Facade Renovation : 117 2nd Avenue, Manhattan, NY Block: 462 Lot: ND AVENUE ND AVENUE-2013 PLOT PLAN HISTORIC Street Facade and Plot Plan PATH ARCH. P.C TH AV., RIDGEWOOD, NY 11385
6 Submitted for Review to: Landmarks Preservation Commission 2ND AVENUE-EXISTING CONDITION 7TH STREET-EXISTING CONDITION 117 2ND AVENUE-EXISTING ELEVATION 1/8"=1'-0" EXISTING ELEVATION AT 7TH STREET 1/8"=1'-0" BLOCK DIAGRAM LPC-02 Facade Renovation : 117 2nd Avenue, Manhattan, NY Block: 462 Lot: 23 Street Facade and Block Diagram PATH ARCH. P.C TH AV., RIDGEWOOD, NY 11385
7
8 LPC-04 Facade Renovation : 117 2nd Avenue, Manhattan, NY Block: 462 Lot: 23 VIEW OF THE STREETSCAPE WITH THE BUILDING IN CONTEXT PATH ARCH. P.C TH AV., RIDGEWOOD, NY 11385
9 NEW WALL COATING BY BASF COLOR TO BE BRICK STONE 467-N (TYP.) EXISTING RELOCATED FIRE ESCAPE TO BE RENOVATED, PAINTED BLACK AND REMAIN. PAINT TO MATCH CORNICE. NEW WINDOWS (BRONZE ANODIZED ALUMINIUM ) BY CHAMPION (TYP. AT 2ND FLOOR) EXISTING ALUMINIUM COPING TO REMAIN EXISTING ALUMINIUM COPING TO REMAIN 1st FLOOR STOREFRONT UNDER SEPERATE APPLICATION BY MOJO-STUMER ARCHITECTS EXISTING TRIM AROUND THE ENTRY DOOR TO BE RENOVATED AND PAINTED. PAINT TO BE BM BLACK EXT. RM SEMI-GLOSS 1st FLOOR STOREFRONT UNDER SEPERATE APPLICATION BY MOJO-STUMER ARCHITECTS EXISTING GLASS AND ALUMINUM DOOR TO BE RE-FURBISH AND REPAIR AND REMAIN. (FINISH BRONZE ANODIZED ALUMINIUM) PROPOSED FRONT ELEVATION-2ND AVENUE 1/4"=1'-0" LPC-05 Facade Renovation : 117 2nd Avenue, Manhattan, NY Block: 462 Lot: 23 PROPOSED SIDE ELEVATION-7TH STREET 1/4"=1'-0" Proposed Elevations PATH ARCH. P.C TH AV., RIDGEWOOD, NY 11385
10 PARTIAL VIEW OF ELEVATION-2ND AVENUE SHOWING COLOR OF THE WALL COATINGS OF THE WALL, LINTELS AND SILLS OF THE WINDOWS AND BLACK PAINT AT ROOF CORNICE WALL COATING BY BASF, COLOR: BRICK STONE 467-N TEXTURE THOROCOAT FINE LINTELS AND SILLS OF THE WINDOWS ROOF CORNICE "BLACK" EXT. RM ( ) PAINT BY BENJAMIN MOORE FINISH GLOSS PROVIDE MOLDED STONE LINTEL TO MATCH HISTORIC EXISTING. LINTEL TO BE SET IN MORTAR. LINTEL TO BE PAINTED BLACK - BM EXT. RM PAINT SAMPLES OF THE WALL COATINGS COLOR OF THE WALL, LINTELS AND SILLS OF THE WINDOWS AND BLACK PAINT AT THE ROOF CORNICE EXISTING MASONRY WALL TO REMAIN PROVIDE COPPER THROUGH-WALL FLASHING WEEP HOLES AT 24" O.C. ±9" V.I.F. PROVIDE NEW STEEL LINTEL AND NEW STONE DECO LINTEL TO MATCH EXISTING ADJACENT. NEW STL. LINTEL TO BE DOUBLE 4"X6"X 5 16" STEEL LINTEL PROVIDE FIREPROOFING (AS PER NYC CODE FOR MASONRY OPENING WIDER THAN FOUR FEET) AT INSIDE LINTEL- MIN " SHOTCRETE ON WIRE MESH WFF. NEW BRICK VENEER W/ WALL COATING BY BASF COLOR TO BE BRICK STONE 467-N AND TEXTURE THOROCOAT FINE NEW WINDOW BY "CHAMPION" WD. CASING T.B.D. PROVIDE CONC. SILL TO MATCH HISTORIC EXISTING AT ADJACENT 3RD FLOOR WINDOWS. SILL TO BE SET IN MORTAR. CCA TREATED WD. BLOCKING AS REQUIRED COPPER FLASHING. PROVIDE THE END DAMS. EXISTING ALUMINUM WINDOWS AT 3RD AND 4TH FLOOR. FINISH BRONZE ANADIZED ELEVATION VIEW OF THE 2ND FLOOR WINDOWS. : 1" =1'-0" NEW WINDOWS TO BE LEGEND 9000 SERIES DOUBLE-HUNG ALUMINIUM WINDOWS BY CHAMPION. FINISH OF THE WINDOWS RO BE BRONZE ANODIZED ALUMINIUM TO MATCH EXISTING WINDOWS AT 3RD AND 4TH FLOOR DRIP SECTION THROUGH WINDOW, NTS CONCRETE SILL LPC-06 Facade Renovation : 117 2nd Avenue, Manhattan, NY Block: 462 Lot: 23 Proposed Elevations-Materials of the windows, coating of the facade and colors of the paints PATH ARCH. P.C TH AV., RIDGEWOOD, NY 11385
11 LPC-07 Facade Renovation : 117 2nd Avenue, Manhattan, NY Block: 462 Lot: 23 Photo of the building "Before" Renovation and Rendering of the "After" Renovation view PATH ARCH. P.C TH AV., RIDGEWOOD, NY 11385
12
13
Braselton Bros. Store Redevelopment 5134 HWY 53 BRASELTON, GA 30548 LEVEL 0 - DEMO & NEW PLAN. Room. Room. Room. Room. Room. Room. Room. Room.
1.d 2.d 3.d 4.d 1.d 2.d 3.d 4.d REMOVE, REPAIR, & REPLACE EXISTING STOREFRONT SYSTEMS D.1 D.2 REMOVE, REPAIR, & REPLACE EXISTING STOREFRONT SYSTEMS D.1 D.2 REMOVE STAIR & INFILL WALL C.1 REMOVE DOOR &
More informationSlavic Village Building Condition Review
Slavic Village Building Condition Review Slavic Village Development May 8, 2015 Page 1 EXECUTIVE SUMMARY City Architecture was commissioned by Slavic Village Development to review five existing facilities
More information29 Broadway- 14 th Fl Tel: 212.888.8334 New York NY 10006 Fax: 212.419.1939. Due Diligence Report. New York, New York
Due Diligence Report New York, New York Prepared for Mr. On February 8, 2010 P a g e 1 Table of Contents PAGE 3.. GENERAL INFORMATION PAGE 4 FILINGS PERMITS AND ENCUMBRANCES PAGE 6. CORE AND SHELL PAGE
More informationGUIDELINES FOR REHABILITATION OF TRADITIONAL COMMERCIAL BUILDINGS DESIGN GUIDELINES
GUIDELINES FOR REHABILITATION OF TRADITIONAL COMMERCIAL BUILDINGS DESIGN GUIDELINES PAGE 13 DESIGN GUIDELINES The following design guidelines have been developed to guide appropriate design in the Downtown
More information423 NORTH HOWARD ST. VISUAL STRUCTURAL ASSESSMENT
Urgent Needs II City of Baltimore No. 1099 423 NORTH HOWARD ST. 423 North Howard Street (circa 1880) is a multi-story building constructed second in row south of Franklin Street and between the vacant
More informationMemorandum. July 16, 2008. To: Plan Commission City of Madison
Memorandum July 16, 2008 To: Plan Commission City of Madison From: Marc Schellpfeffer Engberg Anderson Re: Structural/Architectural Assessment of Homes for Proposed Demolition Findorff Yards Office Lofts
More informationHistoric Preservation Certification Application Part 2 343-345 Main Street West South Haven, Vermont NPS Project No. 12345
Exterior Features 1 site and drainage 2 foundation 3 wood siding and trim 4 exterior doors 5 windows / storm windows 6 porches front and rear 7 chimneys 8 roofing Interior Features 9 frame 10 basement
More informationHEATING, VENTILATING, AND AIR CONDITIONING EQUIPMENT. Application Guidelines
HEATING, VENTILATING, AND Application Guidelines The Landmarks Preservation Commission (LPC) is the Mayoral agency charged with designating and regulating individual landmarks and historic districts. The
More information201 WATER STREET FORWARDERS MUSEUM AND VISITORS INFORMATION CENTRE
STRUCTURAL INSPECTION REPORT DRAFT 201 WATER STREET FORWARDERS MUSEUM AND VISITORS INFORMATION CENTRE TOWN OF PRESCOTT Date: November 2013 GENIVAR No.: 131-20617-00 2611 Queensview Drive, Suite 300, Ottawa,
More information1 RCNY 101-14 CHAPTER 100. (b) References. See Administrative Code sections 28-105.1, 28-105.4, item 6 and 28-105.4.2.1.
1 RCNY 101-14 CHAPTER 100 Subchapter A Administration 101-14 Categories of work that may or may not require a permit. (a) Scope. This rule establishes categories of work that may be classified as a minor
More informationRESIDENTIAL MASONRY A BEST PRACTICES GUIDE
RESIDENTIAL MASONRY A BEST PRACTICES GUIDE Build With Brick Build With Boral CONTENTS BRICK :01 MASONRY CEMENT :03 MASONRY SAND :04 WALL TIES :05 STEEL LINTELS :07 DRAINAGE WALL SYSTEM :09 FLASHING :11
More informationHISTORIC PRESERVATION COMMISSION ADMINISTRATIVE APPROVAL ISSUED JULY - SEPTEMBER 2014 DATE PROJECT ADDRESS PROJECT DESCRIPTION
HISTORIC PRESERVATION COMMISSION ADMINISTRATIVE APPROVAL ISSUED JULY - SEPTEMBER 2014 DATE PROJECT ADDRESS PROJECT DESCRIPTION 07/02/14 212A King George Street Remove existing picket fence from side yard
More information48. AQUARIUM. Aquarium. Classification: Cluster: Location: Close to junction of Inselrhue and Loiter Way, Belle Isle. Total Area: No.
Classification: Cluster: Location: Total Area: No. of Stories Aquarium Acreage Owned: Acquired: 1904 Most Recent Improvements: THE AQUARIUM Close to junction of Inselrhue and Loiter Way, Belle Isle Two
More informationNEW BUILDING CONSTRUCTION INTERIOR WORK & FINISHES EXTERIOR RESTORATION & WATERPROOFING. www.janbarinc.com
EXTERIOR RESTORATION & WATERPROOFING NEW BUILDING CONSTRUCTION INTERIOR WORK & FINISHES www.janbarinc.com Janbar Inc is a general contracting company located in Brooklyn NY. Started originally in 2002
More informationLINE OF EXISTING ADJACENT STRUCTURE 6" MIN. PROTECTION COURSE (NOT REQUIRED WHERE THERE IS NO ADJACENT BLDG. MOISTURE RESISTIVE MEMBRANE AT EXIST. AND NEW BLDG. AS OCCURS WATER STOP SLAB-ON-GRADE TERMINATION
More informationBuilding Condition Assessment: 215-219 West Lexington Street Baltimore, Maryland
KPA The Joint Venture of EBA Engineering, Inc. and Kennedy Porter & Associates, Inc. 4813 Seton Drive, Baltimore, MD 21215 Phone: (410-358-7171) Fax: (410)358-7213 Building Condition Assessment: Baltimore,
More informationREQUEST FOR PROPOSALS FOR: THE PURCHASE AND RENOVATION OF ADJOINING PROPERTIES AT 200/240 SOUTH 16 TH STREET ORD, NEBRASKA BY:
REQUEST FOR PROPOSALS FOR: THE PURCHASE AND RENOVATION OF ADJOINING PROPERTIES AT 200/240 SOUTH 16 TH STREET ORD, NEBRASKA BY: THE COMMUNITY DEVELOPMENT AGENCY OF THE CITY OF ORD JULY 2014 A. STATEMENT
More informationBuilding Condition Assessment: 109-111 North Howard Street Baltimore, Maryland
KPA The Joint Venture of EBA Engineering, Inc. and Kennedy Porter & Associates, Inc. 4813 Seton Drive, Baltimore, MD 21215 Phone: (410-358-7171) Fax: (410)358-7213 Building Condition Assessment: Baltimore,
More informationVer. 2. Guide to. Inspecting Residential Brick Veneer
Ver. 2 Guide to Inspecting Residential Brick Veneer 1. A guide created by industry professionals. The knowledgeable staff at MASONPRO together with technical support from the Masonry Institute of Michigan
More informationREQUEST FOR RESPONSE
Date: November 6, 2014 From: Staci Monroe, Land Use Services 503-823-0624 / staci.monroe@portlandoregon.gov REQUEST FOR RESPONSE Case File: LU 14-215153 DZ Lloyd Center Remodel Pre App: PC # 14-155864
More informationFriends Seminary Presentation to NYC Landmarks Preservation Commission 21 April 2015 Kliment Halsband Architects
Presentation to NYC Landmarks Preservation Commission 21 April 2015 Kliment Halsband Architects FRIENDS SEMINARY RE-DEVELOPMENT PROJECT NYC LPC SUBMISSION 16 APRIL 2015 INDEX 1 Project Description 2 Stuyvesant
More information2008-2009 Cost Comparisons for Common Commercial Wall Systems
An Independent Study LA MS KY TN AL GA SC NC FL 2008-2009 Cost Comparisons for Common Commercial Systems CAPITAL BUILDING CONSULTANTS PROFESSIONAL CONSTRUCTION ESTIMATORS 2008 2009 INDEPENDENT COST COMPARISONS
More informationArticle 11. Window Replacement Project Norman E. Day & Col. John Robinson Elementary Schools
Article 11 Window Replacement Project Norman E. Day & Col. John Robinson Elementary Schools MSBA Accelerated Repair Program Program targets replacement of roofs, windows, doors, and boilers Goal is to
More informationFacility Summary. Facility Condition Summary. Seattle School District David T. Denny International Infrastructure. Facility Components
Infrastructure Facility Condition Summary Weighted Avg Condition Score Facility Components Systems Surveyor/ Date Done Comments G Sitework.9 Site Improvements Parking Pedestrian Paving Site Development
More informationEstimating Database Checklist
Estimating Database Checklist If you are creating a new estimating database for projects, the following list offers a thorough listing of Main and Sub Categories. You can also use it as a checklist to
More informationHISTORIC DISTRICT RESTORATION PROGRAM APPLICATION INSTRUCTIONS
APPLICATION INSTRUCTIONS If you have any application or historic preservation questions, please contact the Planning & Community Development Department at (830) 249-9511. If you have any building or sign
More informationEAST LYME HIGH SCHOOL
Overview: 1971 N 1966 GYM 1966 CLASSROOM WING 1966 AUD. 1971 GYM 1998 1998 POOL EAST LYME HIGH SCHOOL Original 1966 Building: The original East Lyme High School was constructed in 1966 and was composed
More informationH:\forms\handouts\bldg049 1 of 11 Revised Mar 2/15/dh
Accessory Apartment Construction Guide For Single Detached Dwelling and Semi-Detached Dwellings that have been in existence for at least five (5) years Notes: Buildings that are less than five (5) years
More informationFacility Assessment for. 11801 East Main Street, Huntley, IL
Facility Assessment for 11801 East Main Street, Huntley, IL July 12, 2012 Prepared by: Dewberry Architects Inc. 25 S. Grove Avenue, Suite 500 Elgin, IL 60120 (847) 695-5840 The Village of Huntley requested
More informationBuilding Control Guidance Note
Issued 01/01/13 Rev Page 1 of 5 If you intend to convert an existing loft space into additional rooms you will need to apply for Building Regulation Approval. You may also need Planning Permission if you
More informationNEW YORK STATE OFFICE OF PARKS, RECREATION AND HISTORIC PRESERVATION HISTORIC HOMEOWNERSHIP REHABILITATION TAX CREDIT APPLICATION: PART 1
NEW YORK STATE OFFICE OF PARKS, RECREATION AND HISTORIC PRESERVATION HISTORIC HOMEOWNERSHIP REHABILITATION TAX CREDIT APPLICATION: PART 1 DISCLAIMER : The New York State Office of Parks, Recreation and
More information17,280 square feet Overview:
CENTRAL OFFICE Located at 167 Boston Post Road, East Lyme, Connecticut, the Central Office was built in 1916 as the original Flanders Elementary School and remains connected to the current school. The
More informationBasic Requirements for Residential Plan Review _
Basic Requirements for Residential Plan Review _ Below you will find the basic requirements for your plan submittal. General: Drawn to scale Plan Size minimum: 9 x 12 Designer, Engineer, or Architect name,
More informationAdditions and Alterations
Additions and Alterations Addition and alteration construction is a miscellaneous grouping of home improvement and renovation projects that are generally geared toward the enhancement of an existing principal
More informationBENTON PARK HISTORIC DISTRICT REHABILITATION AND NEW CONSTRUCTION STANDARDS
BENTON PARK HISTORIC DISTRICT REHABILITATION AND NEW CONSTRUCTION STANDARDS PART III HISTORIC DISTRICT DESIGN STANDARDS SECTION ONE. These (the "Standards") have been developed to establish a clear and
More informationExhibit C: Scope of Work and Schedule of Deliverables
Exhibit C: Scope of Work and Schedule of Deliverables Project Scope of Work Phases: A City Hall Envelope Renovations B City Hall Skylight Replacement C City Hall Chiller Replacement D City Hall Annex Plaza
More informationSAMPLE SCHEDULE OF VALUES APPLICATION & CERTIFICATE FOR PAYMENT
SAMPLE SCHEDULE OF S 1.00 General Conditions 1.01 Project Management 1.02 General Superintendent 1.03 Superintendents 1.04 Safety Engineer 1.05 Scheduling 1.06 Field Engineering 1.07 Bonds 1.08 Trailer
More informationBROWNSVILLE STRUCTURES STUDY. July 2012. Prepared by. LDA ARCHITECTS 33 Terminal Way, Suite 317 Pittsburgh, Pennsylvania 15219 1208
BROWNSVILLE STRUCTURES STUDY July 2012 Prepared by LDA ARCHITECTS 33 Terminal Way, Suite 317 Pittsburgh, Pennsylvania 15219 1208 TABLE OF CONTENTS I. SUMMARY OF BUILDING ANALYSIS.. 1 II. INDIVIDUAL BUILDING
More informationArchitectural Precedents of Style Facade Diagrams, Image Influences
120' - 2" 23' - 8" 66' - 10" 121' - 2 1/4" 29' - 8" 23' - 8" 12' - 0" 14' - 0" 19' - 4" 21' - 6" 29' - 8" 36' - 8" 13' - 0" 20' - 4" 21' - 6 1/4" 99' - 5 1/4" 41' - 3 1/4" 58' - 2" 29' - 0" 10' - 8" 1'
More informationENCROACHMENTS INTO THE PUBLIC RIGHT-OF-WAY
CHAPTER 32 ENCROACHMENTS INTO THE PUBLIC RIGHT-OF-WAY SECTION BC 3201 GENERAL 3201.1 Scope. The provisions of this chapter shall govern the encroachment of structures into the public right-of-way. 3201.1.1
More informationREVEWED BY: Ross Rogien B.O/P.R. ADDITIONAL REVIEW(S) REQ.-FIRE DEPT Y/N
PLAN REVIEW FOR: PROJECT NAME: OWNER: ARCH/DESIGNER: ADDRESS: Ph/Fx: Plans Dated: E-mail: Sealed By: Estimated Project Cost - $ REVEWED BY: Ross Rogien B.O/P.R. ADDITIONAL REVIEW(S) REQ.-FIRE DEPT Y/N
More informationPre-Drywall Inspection Report
SM MEDALLION INSPECTIONS helping people make informed decisions Pre-Drywall Inspection Report 5657 Garden Valley Place Milton, Georgia 30024 Prepared for Betsy and Paul Dougherty January12, 2015 Medallion
More information3. TOWN/NEAREST TOWN: Millsboro vicinity? 4. MAIN TYPE OF RESOURCE: building structure site object landscape district
DELAWARE STATE HISTORIC PRESERVATION OFFICE 15 THE GREEN, DOVER, DE 19901 CULTURAL RESOURCE SURVEY PROPERTY IDENTIFICATION FORM CRS # S-12215 SPO Map 16-17-08 Hundred Dagsboro Millsboro Quad Other 1. HISTORIC
More informationSECTION 3 ONM & J STRUCTURAL ANALYSIS
Historic Boynton Beach High School Existing Building Assessment City of Boynton Beach February 10, 2011 SECTION 3 ONM & J STRUCTURAL ANALYSIS STRUCTURAL ENGINEERS SPECIAL INSPECTORS STRUCTURAL CONDITION
More informationCERTIFICATE OF APPROPRIATENESS APPLICATION INSTRUCTIONS AND CHECK LIST
Certificate of Appropriateness Instructions and Checklist (revised 1/16) SYRACUSE LANDMARK PRESERVATION BOARD CERTIFICATE OF APPROPRIATENESS APPLICATION INSTRUCTIONS AND CHECK LIST INSTRUCTIONS: Applicants
More informationDESIGN GUIDELINES FOR COMMERCIAL, INDUSTRIAL AND MIXED-USE BUILDINGS
CITY OF CHICAGO DESIGN GUIDELINES FOR COMMERCIAL, INDUSTRIAL AND MIXED-USE BUILDINGS WALL MATERIALS Original wall materials such as brick, stone and terra cotta should be repaired and maintained. Dry-vit
More informationSubstantial Improvement/Damage (FEMA 50% Rule) Frequently Asked Questions and Information
SUBSTANTIAL IMPROVEMENT/DAMAGE WORKSHEET (FEMA 50% RULE) South County: Development Services North County: Development Services 4000 Tamiami Trail S. Room 122 1001 Sarasota Center Blvd Venice, Florida 34293-5076
More informationESSENTIAL CURRICULUM ARCHITECTURAL DESIGN ACADEMY
ESSENTIAL CURRICULUM ARCHITECTURAL DESIGN ACADEMY HOWARD COUNTY MARYLAND ARCHITECTURAL DESIGN ACADEMY Architectural Design 1 Introduction / Overview of Course This course will introduce the basic principles
More informationWilliamson and Associates, Inc. Report of Building Exterior Condition Evaluation, dated January 2 nd, 2013. (68 pages)
INNOVATIVE BUILDING AND ARCHITECTURE CONSULTANTS Mr. Bud Hall Senior Vice President of construction Turnberry Associates 19501 Biscayne Boulevard, Suite 400 Aventura, FL 33180 Subject: The Nashville Hilton
More informationMarch 19, 2014. Ms. Jean McDonald CAP Management 910 16th Street, Suite 1010 Denver, Colorado 80202
Ms. Jean McDonald CAP Management 910 16th Street, Suite 1010 Denver, Colorado 80202 Re: Prospector s Point Walkway/Façade Repairs Martin/Martin, Inc Project No.: 13.0358.S.02 Ms. McDonald: Per your request
More informationSOULARD NEIGHBORHOOD HISTORIC DISTRICT REHABILITATION AND NEW CONSTRUCTION STANDARDS
SOULARD NEIGHBORHOOD HISTORIC DISTRICT REHABILITATION AND NEW CONSTRUCTION STANDARDS ARTICLE 1: INTRODUCTION The character, size and quantity of the relatively unaltered historic buildings contained within
More informationDeKalb County Department of Planning & Sustainability
DeKalb County Department of Planning & Sustainability Lee May Interim Chief Executive Officer Andrew A. Baker, AICP Director APPLICATION FOR CERTIFICATE OF APPROPRIATENESS DeKalb County Historic Preservation
More informationA0 SHEET 1 OF 5 400 LOCUST STREET FRANKFORT, KANSAS 66427 FRANKFORT, KANSAS 66427 ROOF REPAIR OF THE 400 LOCUST STREET
POYNTZ AVENUE, STE 9 MANHATTAN, KS 0..0..9 FAX WEST th STREET JUNCTION CITY, KS.... FAX 0, Bruce McMillan AIA, Architects, P.A. HERITAGE TRUST FUND GRANT PROJECT NO. 0-0 ROOF REPAIR OF THE 00 LOCUST STREET
More informationMINUTES. Date: March 24, 2010 LPC 50/10 Location: 728 St. Helens, Tacoma Municipal Bldg North, Room 16
Members Mark McIntire, Chair Ross Buffington, Vice Chair Edward Echtle Ken House Imad Al Janabi, PhD. Fred King Megan Luce Bret Maddox, S.E. Ha Pham Pamela Sundell Kathryn Longwell, North Slope Ex-Officio
More informationSuperform Products Ltd.
TYPICAL CORNER REINFORCING NOTE : SEE ENGINEERED REBAR SCHEDULES SUPPLIED BY THE MANUFACTURER STEEL REINFORCEMENT WALL CORNER 90 Copyright 2012 Sept. 2012 5.1.1 Rebar Spacing 6" 12" Max. Load LB./FT. 2000
More informationPARKVILLE HIGH SCHOOL LIMITED RENOVATION
PARKVILLE HIGH SCHOOL LIMITED RENOVATION DESIGN BRIEFING For Dr. Joe A. Hairston BALTIMORE COUNTY PUBLIC SCHOOLS August 11, 2009 Smolen 3 Emr + Associates Architects 1355 Piccard Drive, Suite 200 Rockville,
More informationNew York State Office and Historic Homeownership Rehabilitation Tax Credit
NEW YORK STATE OFFICE OF PARKS, RECREATION AND HISTORIC PRESERVATION HISTORIC HOMEOWNERSHIP REHABILITATION TAX CREDIT APPLICATION: PART 1 DISCLAIMER : The New York State Office of Parks, Recreation and
More informationPresentation: Proposed Plan Amendments
Epstein s Rehabilitation Plan Presentation: Proposed Plan Amendments MORRISTOWN REDEVELOPMENT ENTITY March 14, 2013 Epstein s Rehabilitation Plan Presentation Part 1: Morristown Planning Division Neighborhood
More informationRDH Building Sciences Inc.
MAK LTR 2007 03 26 Proposal for Building Enclosure Consulting Services RDH Building Sciences Inc. 509 FAIRVIEW AVENUE N SEATTLE WA 98109-5507 TEL 206 324 2272 FAX 206 324 6339 SEA@RDHBE.COM WWW.RDHBE.COM
More informationSCHEMATIC AND PROJECT BUDGET APPROVAL EAST CAMPUS NURSING EDUCATION AND CLASSROOM
Shepherd University Board of Governors June 9, 2005 Agenda Item No. 9 SCHEMATIC AND PROJECT BUDGET APPROVAL EAST CAMPUS NURSING EDUCATION AND CLASSROOM In 1994 construction began on the Byrd Science and
More informationA site plan or floor plan clearly identifying the location(s) of all new replacement window(s)
WINDOW REPLACEMENT GUIDELINES Community Development Planning & Building 2263 Santa Clara Ave., Rm. 190 Alameda, CA 94501-4477 alamedaca.gov 510.747.6800 F: 510.865.4053 TDD: 510.522.7538 Hours: 7:30 a.m.
More informationCOMMONLY USED RESIDENTIAL BUILDING CODES
COMMONLY USED RESIDENTIAL BUILDING CODES INTERNATIONAL RESIDENTIAL CODE (2009) form revised 5/10 FOUNDATION 1. DESIGN OF FORMWORK. Section 1906.1 IBC 2009, Section R404.1.2.3.6 IRC 2009, ACI 318 Section
More informationREQUEST FOR PROPOSALS GENERAL CONTRACTOR, OFFICE RENOVATION PROJECT. A. Mission of the Lower East Side Business Improvement District
REQUEST FOR PROPOSALS GENERAL CONTRACTOR, OFFICE RENOVATION PROJECT I. GENERAL INFORMATION A. Mission of the Lower East Side Business Improvement District The Lower East Side Business Improvement District
More informationTAX APPRAISAL DISTRICT OF BELL COUNTY STORES & COMMERCIAL IMPROVEMENT CLASSIFICATION GUIDE
TAX APPRAISAL DISTRICT OF BELL COUNTY STORES & COMMERCIAL IMPROVEMENT CLASSIFICATION GUIDE 1/22/2008 1 STORES & COMMERCIAL BUILDINGS 1. General Construction Class Descriptions 2. Types a. Class A - Fireproofed
More informationCLIENT. Inspection Report. 271 Front St. Alert Bay, B.C. Island Building Inspections V ANCOUVER I SLAND B. C.
CLIENT Inspection Report 271 Front St. Alert Bay, B.C. Island Building Inspections 2013 V ANCOUVER I SLAND B. C. Elevation Photos For the Property at 271 Front Street Alert Bay, BC ELEVATION PICTURES Front
More informationThink Of Us First! When It s Time to Distribute Your Plans
Think Of Us First! When It s Time to Distribute Your Plans CONSTRUCTION NOTEBOOK WILL LIST YOUR PLANS AND SPECS FREE CALL TODAY FOR DETAILS 702-876-8660 Why use Experience We have over 60 years of experience
More informationSpring Garden Historic District. Inventory. Philadelphia Historical Commission
1 Spring Garden Historic District Inventory Designated 11 October 2000 Philadelphia Historical Commission 2 NORTH BOUVIER STREET - 600 Block Paving: granite block Sidewalks: concrete Curbs: concrete Light
More informationPRESERVATION PLANNING ASSOCIATES 519 Fig Avenue, Santa Barbara, CA 93101 Telephone (805) 450-6658 Email: accole5@yahoo.com
PRESERVATION PLANNING ASSOCIATES 519 Fig Avenue, Santa Barbara, CA 93101 Telephone (805) 450-6658 Email: accole5@yahoo.com June 17, 2015 Ms. Kimberley Heaton McCarthy Supervising Planner Building and Safety
More informationComment Form on Proposed Gut Rehabilitation Alternatives
Comment Form on Gut Rehabilitation Alternatives Name: Organization: Email: Instructions Submission: Please submit this form to energystarhomes@energystar.gov by October 10 th, 2012 with the subject line
More informationRESIDENTIAL ROOFING & RE-ROOFING, ROOF VENTILATION AND ROOF SHEATHING REQUIREMENTS MICHIGAN RESIDENTIAL CODE 2000
RESIDENTIAL ROOFING & RE-ROOFING, ROOF VENTILATION AND ROOF SHEATHING REQUIREMENTS MICHIGAN RESIDENTIAL CODE 2000 SECTION R905 REQUIREMENTS FOR ROOF COVERINGS R905.1 Roof covering application. Roof coverings
More informationTexas Historic Preservation Tax Credit Application Guide 1-26-2015
Texas Historic Preservation Tax Credit Application Guide 1-26-2015 The Texas Historical Commission (THC) administers the Texas Historic Preservation Tax Credit (THPTC) program with the office of the Texas
More informationDoughty Environmental Hygiene Associates
Top: Photo #1: View of the top of the elevator shaft from the roof. The open ventilation causes condensation to form inside on the sheetrock. It also allows for the access for insects. Note the discoloration
More informationNew Jersey City University Gilligan Student Union Center
New Jersey City University Gilligan Student Union Center The RBA Group worked with New Jersey City University in a major renovation of their Gilligan Student Union building. We were contracted to reassess,
More informationC I T Y O F P E A R S A L L
The Largest City Between San Antonio and Laredo COMMUNITY DEVELOPMENT C I T Y O F P E A R S A L L A Business-Friendly, Family-Oriented Community Building Department Application Information (Please read
More informationSaint Cloud Business Center
Saint Cloud Business Center 14 7th Avenue North Saint Cloud, MN 56303 For Sale Located on 7th Avenue in the heart of downtown across from the Court House Square. A large professional reception area with
More informationWASHROOM UPGRADE SIR CHARLES TUPPER BUILDING 2250 RIVERSIDE DRIVE, OTTAWA, ON SIR CHARLES TUPPER BUILDING A0.0 COVER SHEET / DRAWING LIST
0 RIVERSIDE DRIVE, OTTAWA, ON A0.0 COVER SHEET / DRAWING LIST A0. LEGEND AND GENERAL NOTES A0. GENERAL NOTES A0. GENERAL NOTES A0. TYPICAL WASHROOM WALL/SINK SECTION A0. DETAIL - CONTROL JOINT A0. DETAIL
More informationSCHOOL BUILDING RENOVATION REPORT I. BUILDING BEFORE RENOVATION
SCHOOL BUILDING RENOVATION REPORT I. BUILDING BEFORE RENOVATION Data of building before renovation in 2014: - year of renovation of the elevation 1997, - year of renovation of the roof 2000, - year of
More informationStructural Assessment Report
Report Dallas Township Elementary School Dallas, Pennsylvania (JBCI Project No. 144911) 1655 Suburban Station Building 1617 John F. Kennedy Boulevard Philadelphia PA 19103 215 665 0497 5 Sandwood Drive
More informationAn ordinance pertaining to the Maya Angelou Birthplace, located at 3130 Hickory Street (the
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 BOARD BILL NO. 76 INTRODUCED BY ALDERWOMAN MARLENE DAVIS, ALDERMAN TERRY KENNEDY ALDERMAN MARLENE DAVIS, ALDERMAN TERRY KENEDY, ALDERMAN FREEMAN
More informationEngineers, Civil Structural Survey
Engineers, Civil Structural Survey 317 STREET 0 6 3 6 0 886-1966 886-9165 FAX. September 1 1 Mr. Alan Bergren City Manager City of Norwich Broadway, Floor Norwich, 06360 Re: Limited Structural Condition
More informationBuilding Construction. Structural Systems 1. Load-bearing wall construction 2. Skeleton framing 3. Combination of the two
Structural Systems 1. Load-bearing wall construction 2. Skeleton framing 3. Combination of the two Factors governing type selection Economics not necessarily the one that requires the least structural
More informationCommercial And Industrial Steel Buildings
Commercial And Industrial Steel Buildings Arco Building Systems, Inc. Since 1979 Arco has been providing the highest quality steel buildings to contractors and owners throughout the United States. Leadership
More informationNicholas Vann, State Historical Architect
FEDERAL INVESTMENT TAX CREDIT B E L L I N G H A M M A Y 2 9, 2 0 1 3 Nicholas Vann, State Historical Architect DEPARTMENT OF ARCHAEOLOGY AND HISTORIC PRESERVATION FEDERAL INVESTMENT TAX CREDITS 20% Federal
More informationCode Requirements for Existing Buildings
Code Requirements for Existing Buildings Kevin S. Hastings, P.E., LEED AP R. W. Sullivan, Inc. 529 Main St., Suite 203 Charlestown, MA (617) 523-8227 www.rwsullivan.com R.W. Sullivan Engineering (RWS)
More informationCPED STAFF REPORT Prepared for the Heritage Planning Commission Agenda Item #1 July 14, 2015 BZH-28731
HERITAGE PRESERVATION APPLICATION SUMMARY CPED STAFF REPORT Prepared for the Heritage Planning Commission Agenda Item #1 July 14, 2015 BZH-28731 Property Location: 217 Main Street SE (219 Main Street SE)
More informationOPTIMUS WORK CLASSIFICATION LIST ENTER ALL THAT APPLY
Cost Code # Description Cost Code # Description 01 00 00.001 General Requirements 02 00 00.001 Existing Conditions 01 31 19.13.001 Preconstruction Meetings 02 21 00.001 Surveys 01 32 33.001 Photographic
More informationSTICKLEY AUDITORIUM RENOVATION Community and Stakeholder Presentation
STICKLEY AUDITORIUM RENOVATION Community and Stakeholder Presentation APRIL 30, 2014 SCHEMATIC DESIGN PROGRESS Code Study Analysis: key issues and resolutions Seating Analysis of sightlines, seating and
More informationConcept Design Synopsis
Washington Headquarters Services Facilities Services Directorate The Pentagon Electric Upgrade (Substation No. 2) Concept Design Synopsis September 4, 2014 Prepared for Consultations with VA SHPO, ACHP,
More informationVision Home Inspection
Vision Home Inspection 324 Rams Run Shepherdsville KY 40165-7877 Inspector: James McFadden Property Inspection Report Client(s): Property address: Inspection date: View report summary This report is the
More informationSWAN POINT YACHT & COUNTRY CLUB
SWAN POINT YACHT & COUNTRY CLUB PROJECT INFORMATION: SCOPE OF WORK: INTERIOR ALTERATIONS ABBREVIATIONS: VICINITY MAP 33 East Charles Street PO Box 598 30-934-8078 PROPERTY MANAGER: DOTTIE HARPER BROOKFIELD
More informationPHOTOGRAPHS REDUCED COPIES OF MEASURED DRAWINGS WRITTEN HISTORICAL AND DESCRIPTIVE DATA
Republic Building 429 W. Muhammed Ali Blvd. Louisville Jefferson County Kentucky HABS No. KY-140 ', Hf) K.y ^,' w n=»> _^> PHOTOGRAPHS REDUCED COPIES OF MEASURED DRAWINGS WRITTEN HISTORICAL AND DESCRIPTIVE
More informationHow To Find Out What Happened To Slave Housing
Slave Housing Data Base Building Name: Presquisle Brick Duplex 2 (northern building) Evidence Type: Extant Site ID: Historical Site Name: City or Vicinity: County: Culpeper State: Virginia UTM: Easting:
More informationENERGY STAR Qualified New Homes Thermal Enclosure Checklist. Water Management Checklist. Eli Caudill
ENERGY STAR Qualified New Homes Thermal Enclosure Checklist & Water Management Checklist Eli Caudill ENERGY STAR Version 3 Tighter Standards Whole Home Approach Better, More Sustainable Construction Surpasses
More informationChapter 5. In-depth Building Analyses and Recommendations. Planning Study for Downtown Revitalization City of Martinsville
75-77 East Washington Street In-depth Building Analyses and Recommendations Chapter 5 In-depth Building Analysis Overview Four of the nineteen downtown buildings selected for façade assessments and recommendations
More informationSOUTH END LANDMARK DISTRICT Standards and Criteria Revised April 27, 1999
SOUTH END LANDMARK DISTRICT Standards and Criteria Revised April 27, 1999 INTRODUCTION The statute creating the Boston Landmarks Commission (chapter 772 of the Acts of I of the Commonwealth of Massachusetts)
More informationBuilding Code Clarifications - 7. Fire Resistance
Building Code Clarifications - 7. Fire Resistance 7.1 (15-12-030) Use of combustibles in Type III construction roof assemblies Code Section (15-12-030) Use of Combustibles was revised on May 17, 2000,
More informationApplication for a Window Replacement Master Plan Curtis B. Wayne, Architect Ken Lustbader, Preservation Consultant
Application for a Window Replacement Master Plan Curtis B. Wayne, Architect Ken Lustbader, Preservation Consultant 37 West 12 th Street Between 5 th and 6 th Avenues Architectural History Architectural
More informationELIGIBLE REPAIR PROJECT PARAMETERS
THE DISTRICT MUNICIPALITY OF MUSKOKA ONTARIO RENOVATES PROGRAM FOR HOMEOWNERS ELIGIBLE REPAIR PROJECT PARAMETERS 1. To have your project considered and payment processed, all projects requiring a Building
More informationSODA SPRINGS JOINT SCHOOL DISTRICT NO. 150 RECOMMENDED REPAIRS, REPLACEMENT, AND ADDITIONS OPINIONS OF PROBABLE COST
SODA SPRINGS JOINT SCHOOL DISTRICT NO. 150 RECOMMENDED REPAIRS, REPLACEMENT, AND ADDITIONS OPINIONS OF PROBABLE COST SODA SPRINGS HIGH SCHOOL REPAIRS AND UPGRADES SITE Construction Estimate = $100,000
More informationPrior to submission of drawings for building permit, the architectural control process will be undertaken for the developer and/or builders.
6.0 Design Review process 6.0 Design Review Process The design review process will coordinate the public and private realm architecture for the community, i.e., the site planning, streetscape, and architecture
More information