Schedule Guidance Document

Size: px
Start display at page:

Download "Schedule Guidance Document"

Transcription

1 Schedule Guidance Document Contents 1. Purpose 2. Applicability 3. Preparation of Baseline Schedule 4. Preparation of Progress Schedule 5. Additional Guidance for Tier 4 and Tier 5 Schedules 6. Submittal of Schedules Attachment A - Work Breakdown Structure Attachment B - Example Tier 3 Baseline Consulting Schedule Attachment C - Example Tier 3 Progress Consulting Schedule Attachment D - Example Tier 3 Baseline Construction Schedule Attachment E - Example Tier 3 Progress Construction Schedule Attachment F- Schedule Submittal Process for Buzzsaw Desktop 1. Purpose The City of Fort Worth is committed to delivering quality, cost-effective infrastructure to its citizens in a timely manner. One of the most important tools the City uses to achieve this goal is accurate, updated, current schedules for its capital projects. Accurate and updated schedules allow the City to effectively track and manage its projects both in aggregate (at the program or city-wide level) and project-byproject. The City uses this schedule information to display project and program status to the City's elected officials, staff, and its citizens. The City's goal is to take every reasonable step to ensure that projects finish on time and within budget. Project schedules are the fundamental building blocks to planning and executing projects efficiently and on time. These schedules are best prepared by those closest to the work. Because the vast majority of capital project delivery at the City is performed by contractors and consultants, it is critical that contractors and consultants prepare schedules as part of performing their work for the City. This Schedule Guidance Document complements the City's Standard Agreement and Contract Documents to guide contractors and consultants in preparing and submitting acceptable schedules for use by the City. The City's Program Management Office is the owner of the schedule submittal process and associated reporting systems. 2. Applicability The City has developed a tiered approach to scheduling, recognizing that projects have a wide range of needs for schedule information. The City's Program Managers will determine the appropriate level of schedule needed for each project, and will include that designation and the associated requirements in the consultants' and contractors' contract documents. The schedule tiers that the Program Managers will select from are summarized as follows: City of Fort Worth, Texas Schedule Guidance Document PMO Release Date: Page 1 of 28

2 Tier 1. No schedule submittal required by contract. Small, brief duration projects. Tier 2. No schedule submittal required by contract, but will require some milestone dates. Small, brief duration projects. Tier 3. Schedule submittal required by contract as described in the specification and herein. Majority of City projects, including all bond program projects. Tier 4. Schedule submittal required by contract as described in the specification and herein. Large and/or complex projects with long durations. Examples might include a large water pump station project and associated pipeline with interconnection to another governmental entity. (Note: Applies almost exclusively to Contractor schedules) Tier 5. Schedule submittal required by contract as described in the specification and herein. Large and/or very complex projects with long durations, high visibility. Examples might include a water or wastewater treatment plant. (Note: Applies almost exclusively to Contractor schedules) Schedules for the Tier 1 and Tier 2 projects will be developed by City staff based on date and milestone information provided by the consultant or contractor. Contractors and consultants are responsible for preparing schedules as defined herein for Tier 3 through Tier 5 projects. Tier 3 projects and the associated schedules will be the "default" and most common. Therefore the schedule guidance that follows is focused on meeting Tier 3 requirements unless stated otherwise. There are three (3) basic elements to schedule submittals. 1. Baseline Schedule. Initial schedule submitted before work begins that will serve as the baseline for measuring progress and departures from the schedule. 2. Progress Schedule. Monthly submittal of a progress schedule documenting progress on the project and any changes anticipated. 3. Schedule Narrative. Concise narrative that highlights changes in the schedule, expected delays, key schedule issues, etc. The Baseline Schedule is prepared by the contractor or consultant at the beginning of the project (prior to the initial payment) and submitted to the City as defined herein. The Progress Schedule is prepared monthly by the contractor or consultant and submitted to the City as defined herein. The Schedule Narrative is submitted to the City monthly in conjunction with the Progress Schedule. 3. Baseline Schedule 3.1. General The contractor or consultant will develop a cost-loaded Schedule using approved software and the Critical Path Method (CPM). The schedule file project ID should be based on the five digit Capital Project Management System number and the name assigned to the project by the City in Buzzsaw. When submitting the first schedule add the word "Baseline" to the end of the project ID. Monthly updates moving forward should have the year and month at the end of the project ID. Refer to the following examples and Attachment F. City of Fort Worth, Texas Schedule Guidance Document PMO Release Date: Page 2 of 28

3 Baseline Format. City Project#-tracking log file name_baseline Example Flaxseed Drainage Improvements_Baseline Monthly Update Format. City Project#-tracking log file name-'yyyy_mm' Example Flaxseed Drainage Improvements_2009_01 The approved Baseline Schedule will become part of the contract. The contractor or consultant has the sole responsibility to correct any latent defects in its Baseline Schedule and perform to the subsequently revised schedule. The contractor or consultant will use the Baseline Schedule to coordinate and monitor the work (including the activities of subcontractors, equipment vendors and suppliers). The contractor or consultant must keep a copy of the approved Baseline Schedule Schedule Work Breakdown Structure and Activities Work Breakdown Structure (WBS) The scope of work to be accomplished by the contractor or consultant will be represented to the City of Fort Worth in the form of a Work Breakdown Structure (WBS). The WBS shall be the basis for the development of the schedule activities and shall be imbedded and depicted in the schedule. Attachment A shows the WBS for the City of Fort Worth Design The consultant's (engineer) schedule WBS should roll up under one or more of the following, as confirmed with the City's Project Manager and Project Controls Specialist: Project Planning Traffic Studies/Field Reconnaissance GIS Mapping Condition Assessments Hydraulic Assessments Design Conceptual Design Preliminary Design Final Design ROW/Land Survey Preliminary Survey Construction Staking Public Involvement Public Meetings Construction Project Management Construction Advertisement City of Fort Worth, Texas Schedule Guidance Document PMO Release Date: Page 3 of 28

4 Bid Preparation and Advertisement Contract Award Pre-Construction Activities Material/Soil Testing Inspection Construction Construction scope for each project should roll up under: Construction Construction Contract Construction Contract Construction Contract 3, etc. Within the contractor should organize the activities to logically represent the project (see 3.2.2). The goal is to have each project organized in a logical order by type of work that rolls up to the City of Fort Worth's Construction WBS level Activities Activities are the discrete elements of work that make up the schedule. They should be organized underneath the umbrella of the WBS as described in The following information will be provided for each activity: Activity Number Use a five-digit number between and 99995, left justified in the activity I.D. field. Alphanumeric activity numbers are NOT acceptable, unless specifically directed by the City of Fort Worth Project Manager or PMO for selected use. The initial network will be numbered by 10s or 20s with the following activity number greater than the preceding activity number Activity Description Activity descriptions should adequately describe the activity and in some cases the extent of the activity. Examples of acceptable descriptions might include "place concrete between Avenue A and Avenue B", "water line conceptual design", etc.) Activity Durations (Applies to Contractor Schedules Only) The activity duration will be based upon the physical amount of work that is to be performed for the stated activity and are limited to 20 working days. If work is to exceed 20 days, then break the work down so the work will be completed within a 20 day time frame Activity Start and Finish Dates Activity start and finish dates will only be accepted if calculated by the software. Actual activity start and finish dates may not be assigned in a baseline. However they must accurately be assigned in the working version of the schedule (see Section 4 Progress Schedule) Activity Dependencies All activities will be logically tied with a predecessor and a successor. The only exception to this rule will be for the project start and project finish milestones Milestone Activities City of Fort Worth, Texas Schedule Guidance Document PMO Release Date: Page 4 of 28

5 The following milestone activities (i.e., important events on a project that mark critical points in time) are of particular interest to the City of Fort Worth and should be reflected in the Project Schedule for all phases of work, as applicable: Consultant Schedule (Engineering Design Example) Notice to Proceed 30 percent Plans and Specification Submittal 60 percent Plans and Specification Submittal 90 percent Plans and Specification Submittal Design Complete Contractor Schedule Notice to Proceed (Construction) Preparation and submission of shop drawings, submittals, and any required re-submittals (if applicable) Mobilization Fabrication and delivery of equipment and materials (if applicable) Pre-final and final inspections Project Acceptance 3.3. Baseline Schedule Development The contractor or consultant will designate an authorized representative (Project Scheduler) responsible for developing and updating the schedule and preparing reports. It is recommended that a qualified scheduler develop the baseline schedule. The City will supply a template for download as an example of how to set up a project. The purpose of the template is to help the novice user develop schedules meeting the City's requirements. The contractor's or consultant's initial schedule submittal will contain NO progress and represent the planned work for the duration of the project. Once approved by the City of Fort Worth, this schedule will become the baseline against which all future variance analysis will be performed. The use of activity external constraint dates and lags on relationships is discouraged unless specified or approved by the City of Fort Worth. An example of an external constraint date is "concrete construction will begin no later than January 1." The reason for this requirement is that it creates an artificial (rather than calculated) critical path. The baseline Schedule will consider delivery lead times, construction and access constraints and the coordination of construction with The City of Fort Worth operations Safety Requirements Schedule performance should never take precedence over safety. Project schedules must allow work to be performed in a safe manner. The contractor or consultant cannot reduce safety or worker protection in order to shorten schedules, recover lost time or accelerate the work Project Calendars The baseline schedule will be based on a standard work week (the days of the week -typically five day week - the contractor or consultant plans to work) including City holidays as non-work days, unless it is the contractor's plan to work more than a 5 day work week. If the consultant or contractor plans to use a non-standard calendar (i.e. more or less than 5 day work week), then the City should be notified as part of the submittal of the baseline schedule. City of Fort Worth, Texas Schedule Guidance Document PMO Release Date: Page 5 of 28

6 Listed in the table below are typical City holidays that contractors and consultants will need to develop project calendars for that exclude these as work days. Refer to the City web site for additional City holiday schedules. Holiday 2009 Dates 2010 Dates 2011 Dates New Years Day January 1 January 1 January 1 Martin Luther King Day January 19 January 18 January 17 Memorial Day May 25 May 31 May 30 Independence Day July 3 July 5 July 4 Labor Day September 7 September 6 September 5 Thanksgiving November 26 November 25 November 24 Day after Thanksgiving November 27 November 26 November 25 Christmas Day December 25 December 25 December Inclement Weather Refer to climatology data for anticipating work that can be affected by inclement weather. Historical rain days can be reviewed from the following web site: 4. Preparation of Progress Schedule As described in Section 3, the baseline schedule is used to coordinate and monitor the work. The contractor or consultant is required keep a copy of the approved baseline schedule. The Progress Schedule is simply a copy of the approved baseline schedule that will be statused monthly. In other words, progress on the project will be shown monthly as an update of the schedule that will be compared to the approved baseline schedule Progress Updates The contractor or consultant should show on the progress schedule update the following: The actual dates that activities start The actual dates that activities finish The remaining duration of activities in progress The percent complete of all activities on the schedule (0 percent to 100 percent complete) Schedule Narrative The progress schedule will be accompanied monthly by a concise schedule narrative that explains the submitted schedule. The purpose of the schedule narrative is to: Speed review time Explain variances from baseline on critical path activities Explain to the City logic changes and potential schedule conflicts related to dependences. City of Fort Worth, Texas Schedule Guidance Document PMO Release Date: Page 6 of 28

7 If the project is on schedule, and no significant issues related to schedule exist, then the schedule narrative is extremely brief. On the other hand, if the project is falling behind, and/or there are significant conflicts and obstacles to meeting the baseline schedule, then the schedule narrative should describe these issues and what steps will be necessary for the project to recover. Sharing this information ensures that the entire project team will be aware of the issues and have opportunity to assist where applicable Change Orders and Amendments Change orders (contractors) and amendments (consultants) sometimes affect the schedule of a project. In these cases, change orders and amendments will be incorporated into the previously approved baseline schedule and clearly show impacts to the project timeline, if any. This "re-baselined" schedule will be submitted to the City for approval (See Section 6). In these re-baselined schedules, the following should be adhered to: Time extensions associated with approved contract modifications will be limited to the amount of time the project or critical phase of construction is actually delayed, unless approved by the Program Manager. The contractor or consultant will submit revisions within fifteen (15) workdays after the date of the change request. The changes in logic or durations approved by the City of Fort Worth will be used to analyze the impact of the change. This impact shall be included in the change order or amendment. On the re-baselined schedule, the Activity ID of a new activity added to the schedule for the change order or amendment should be coded in the Activity ID with the CO number or amendment number. Use as many activities as needed to accurately show the work of the change order or amendment. Use Activity IDs in this form. CO<Change Order Number><Activity ID> AM<Amendment Number><Activity ID> Revisions to the baseline schedule will not become effective until approved by the City. 5. Additional Guidance for Tier 4 and Tier 5 Schedules Applicable to Contractors Only As noted in Section 2, Tier 4 and Tier 5 schedules are required for more complex, schedule-dependent projects. Brief descriptions of the additional requirements (beyond Tier 3) are provided in this section, and are applicable to successful Contractors on Tier 4 and Tier 5 projects (not Consultants on these projects) Tier 4 Requirements for Contractors In addition to the Tier 3 requirements a Tier 4 schedule will include the following elements Schedule of Value Pay Items City of Fort Worth, Texas Schedule Guidance Document PMO Release Date: Page 7 of 28

8 Schedule of Values Pay Items (Work) shall be loaded into the scheduling software using the "NON- LABOR" resource type showing the quantity of work to be done along with the corresponding value of the work measured in dollars. (It is intended that Earned Value will be calculated as the schedule resources are progressed) Resource Naming Convention The resources assigned to the schedule activities will be derived from the pay items in each contract. Quantity of work times the unit price established in the resource dictionary will be the basis of the dollar value of the scheduled work.resource ID shall be CPMS Project Number.C.Bid Item. The C will be used for Construction contracts. If there should be more than one construction contract for that project, then the second contract would use C1, etc. Examples are as follows: C C Reports A Scheduled Earned Value Report reflecting the scheduled end of month earnings in dollars and percentages. The report shall also contain the following: Activity number Activity description Original duration Remaining duration Activity percent complete Early and late start dates Early and late finish dates Total float Budgeted cost Budgeted Cost of Work Scheduled (BCWS) Budgeted Cost of Work Performed (BCWP) 5.2. Tier 5 Requirements for Contractors In addition to the Tier 3 and Tier 4 requirements a Tier 5 schedule will include the following elements Man-Hour Resources Labor resources (Man-Hours) shall be loaded into the schedule software using the "LABOR" resource type with man-hours only, no costs Man-Hour Resource Naming Convention Labor Resource IDs shall be CPMS Project Number.TRADE Name. Examples are as follows: Electrican Cement Finisher The Contractor's initial schedule submittals shall include a project total planned manpower curve (expressed in man-days or men per day) based on early and late finish dates. The submittals will contain both tabular and graphic presentations. As progress is made on the project, the contractor shall update the progress line of the curve to show City of Fort Worth, Texas Schedule Guidance Document PMO Release Date: Page 8 of 28

9 how well the project is progressing according to plan. 6. Submittal of Schedules 6.1. Submittal File Formats Every time that a schedule or report is submitted (baseline and monthly progress) the following file formats are required Baseline Schedule Submit the schedule in native file format (see below). Also submit a.pdf of the bar chart schedule consisting of the following columns: Activity ID Activity Name Duration Start Date Finish Date Float Cost Progress Schedule Submit the schedule in native file format (see below). Also submit a.pdf of the bar chart schedule consisting of the following columns: Activity ID Activity Name Percent Complete Duration Start Date Finish Date Float Schedule Narrative Submit the schedule narrative in.pdf format Native Schedule File Formats The native file structure is to save the schedule as follows: In Microsoft Project (Phasing Out) Save the file as a Project MPP file. In Primavera 6 Save the file as an xer file Submittal Process City of Fort Worth, Texas Schedule Guidance Document PMO Release Date: Page 9 of 28

10 The City administers and manages their schedules through Buzzsaw. If you are not currently a registered Buzzsaw user please or contact: Fred Griffin, Buzzsaw Administrator City of Fort Worth Fred Griffin@ fortworthgov.org Once you have obtained a user name and password for Buzzsaw, log onto the system, locate and verify that the naming convention for the project file coincides with the name and project number setup within the Buzzsaw project folder. Draft project baseline schedules must be submitted within fifteen (15) calendar days after the formal notice to proceed from the City. All schedules must be submitted in their native format (either in an MPP, an xer file, or a concentric P3 file) as well as in a PDF format. The City will review and accept or reject the schedule within ten (10) days of submittal. Once the baseline schedule has been accepted, schedule updates will be due monthly no later than the last day of the month. For detailed step by step directions for uploading your files please reference Attachment F. City of Fort Worth, Texas Schedule Guidance Document PMO Release Date: Page 10 of 28

11 Attachment A City of Fort Worth Schedule Guidance Document Attachment A

12 Attachment A CFW Work Breakdown Structure WBS Code WBS Name 1 City of Fort Worth Project 1.10 Project Planning Pre-Contractural Packaging Traffic Studies/Field Reconnaissance Grant Application GIS Mapping Condition Assessments Hydraulic Assessments 1.20 Project Agreement Consultant Selection Process Consultant Contract Negotiation Draft Project Agreement Preparation 1.30 Design % Conceptual Design % Preliminary Design % Final Design Constructability Review Developer Plan Review City Floodplain/CLOMR 1.40 ROW/Land Right-of-Way/Land Costs Negotiations/Easements/Legal Fees Facility/Building Purchase Permits Environmental TxDOT Environmental (CE) 1.50 Survey Preliminary Survey Construction Staking Easement/ROW Document Preparation Platting 1.60 Public Involvement Public Meetings 1.70 Utilities

13 City Utility Relocation Costs Private Utility Relocation Costs Utility Coordination/Clearance Demolition 1.80 Construction Project Management Construction Advertisement Bid Preparation and Advertisement Contract Award Pre-Construction Activities Construction Contract Material/Soil Testing Inspection Landscaping Construction Contract Construction Contract Closeout Close-Out Report and Review As-Built Survey Mapping As-Built Plans

14 Attachment B CITY OF FORT WORTH SCHEDULE GUIDANCE DOCUMENT ATTACHMENT B

15 Example Consultant Baseline Schedule Print Date: Project: Consultant-BL-1 Attachment B - Example Tier 3 Baseline Consulting Schedule Activity ID Activity Name OD RD Percent Complete Consultant-BL-1 Sample Consultant Baseline Schedule Consultant-BL-1.30 Design - - Station 5+10 to Station Consultant-BL % Conceptual Design Start Finish Total Float Phase Issue Design Notice To Proceed 0 0 0% Pre-Design Corrdination Meeting 1 1 0% Prepare Conceptual Engineering Plans (30%) % Review Conceptual Engineering Plans (30%) % Incorporate Review Comments into Conceptual Engineering % % Conceptual Plan Submittal 0 0 0% Hold Project Reivew Meeting with the City 1 1 0% Address City Comments % Perform Geotechnical Investigation % Consultant-BL % Preliminary Design Prepare Preliminary Plans and Specifications (60%) % Review Preliminary Plans and Specifications (60%) % Incorporate Comments into Preliminary Plans and Specificati % % Preliminary Plan and Specification Submittal 0 0 0% Review 60% Preliminary Plans and Specifications (CoFW) % TWDB Review % Project review Meeting 1 1 0% Address Conmments % Submit Plans to Utilitiy Complanies 1 1 0% Consultant-BL % Final Design Prepare 90% Plans and Specifications % % Plan Submittal 0 0 0% Review 90% Plans and Specifications (CoFW) % Project Review Meeting 1 1 0% Incorporate Final Comments and Submit Final Plans and Sp % Final Plans and Speifications Submittal 0 0 0% Circulate Plans and Specifications for Signitures 5 5 0% Design Complete 0 0 0% Aquire TWDB Approval to Advertise % Consultant-BL Project Environmental Perform Archeological Investigation % Prepare Draft Environmental Informastion Document (EID) % Review Draft EID % Prepare Final EID % Review Final EID % Advertisement for EID Public Hearing % * EID Public Hearing 1 1 0% Respond to Comments and Submit Final EID to TWDB % Var Finish Date Sep Oct Nov Dec Jan F Mar Apr M Jun Jul Aug S Oct N Dec Jan F Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan F Mar Apr Actual Work Remaining Work Milestone Critical Milestones Remaining Level of Effort Actual Level of Effort Baseline Milest... Sample Consultant Baseline Schedule Page 1 of 2 Layout: FTW-01a - Project Schedule Critical Remaining Work Completed Milestones Project Baseline Bar

16 Example Consultant Baseline Schedule Print Date: Project: Consultant-BL-1 Attachment B - Example Tier 3 Baseline Consulting Schedule Activity ID Activity Name OD RD Percent Complete Start Finish Total Float Phase Prepare FONSI % Consultant-BL-1.40 ROW/Land Consultant-BL Negotiations/Easements/Legal Fees Prepare Right Of Way (ROW) Documents % Perform Appraisals % Review Appraisals and Prepare Offer % Present First Offer and Negotiation/Acceptance Period % Prepare Second Offer (If Needed) % Present Second Offer and Negotiation/Acceptance Period (If % Prepare & Deliver Condemnation Packet (If Needed) % Condemnation Period (If Needed) % Real Property Complete 0 0 0% Consultant-BL-1.50 Survey Consultant-BL Preliminary Survey Topographic (Field) Survey % Consultant-BL-1.80 Construction Consultant-BL Construction Advertisement Consultant-BL Bid Preparation and Advertisement Finalize Bid Package % Start Advertisement 0 0 0% Advertisement Period % Hold Pre-Bid Meeting 1 1 0% Issue Addenda (As needed) % Bid Opening - Review Bids - Bid Tabulations and Select Con % Consultant-BL Contract Award Start M&C Process - Construction 0 0 0% MWBE Submittal 5 5 0% Review and Approve MWBE Submittal % M&C Process % Execute Contract Documents % Issue Construction Notice To Proceed 0 0 0% Consultant-BL Pre-Construction Activities Hold Pre-Construction Meeting (with Contractor) 1 1 0% Submittals and Approvals % Start Construction 0 0 0% Consultant-BL Construction Contract Construction % Consultant-BL Inspection Final Inspection % Construction Complete 0 0 0% Var Finish Date Sep Oct Nov Dec Jan F Mar Apr M Jun Jul Aug S Oct N Dec Jan F Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan F Mar Apr Actual Work Remaining Work Milestone Critical Milestones Remaining Level of Effort Actual Level of Effort Baseline Milest... Sample Consultant Baseline Schedule Page 2 of 2 Layout: FTW-01a - Project Schedule Critical Remaining Work Completed Milestones Project Baseline Bar

17 Attachment C CITY OF FORT WORTH SCHEDULE GUIDANCE DOCUMENT ATTACHMENT C

18 Example Consultant Baseline Schedule Print Date: Project: Consultant-UD-6 Attachment C - Example Tier 3 Consulting Progress Schedule Activity ID Activity Name OD RD Percent Complete Consultant-UD-6 Sample Consultant Baseline Schedule Consultant-UD-6.30 Design - - Station 5+10 to Station Consultant-UD % Conceptual Design Start Finish Total Float Phase Issue Design Notice To Proceed % A Pre-Design Corrdination Meeting % A A Prepare Conceptual Engineering Plans (30%) % A A Review Conceptual Engineering Plans (30%) % A A Incorporate Review Comments into Conceptual Engineering % A A % Conceptual Plan Submittal % A Hold Project Reivew Meeting with the City % A A Address City Comments % A A Perform Geotechnical Investigation % A Consultant-UD % Preliminary Design Prepare Preliminary Plans and Specifications (60%) % A Review Preliminary Plans and Specifications (60%) % Incorporate Comments into Preliminary Plans and Specificati % % Preliminary Plan and Specification Submittal 0 0 0% Review 60% Preliminary Plans and Specifications (CoFW) % TWDB Review % Project review Meeting 1 1 0% Address Conmments % Submit Plans to Utilitiy Complanies 1 1 0% Consultant-UD % Final Design Prepare 90% Plans and Specifications % % Plan Submittal 0 0 0% Review 90% Plans and Specifications (CoFW) % Project Review Meeting 1 1 0% Incorporate Final Comments and Submit Final Plans and Sp % Final Plans and Speifications Submittal 0 0 0% Circulate Plans and Specifications for Signitures 5 5 0% Design Complete 0 0 0% Aquire TWDB Approval to Advertise % Consultant-UD Project Environmental Perform Archeological Investigation % Prepare Draft Environmental Informastion Document (EID) % Review Draft EID % Prepare Final EID % Review Final EID % Advertisement for EID Public Hearing % * EID Public Hearing 1 1 0% Respond to Comments and Submit Final EID to TWDB % Var Finish Date S Oct N Dec Jan F Mar Apr M Jun Jul Aug Sep Oct Nov Dec Jan F Mar Apr M Jun Jul Aug S Oct N Dec Jan F Mar Apr Actual Work Remaining Work Critical Remaining Work Milestone Critical Milestones Completed Milestones Remaining Level of Effort Actual Level of Effort Project Baseline Bar Baseline Milest... Sample Consultant Baseline Schedule Page 1 of 2 Layout: FTW-01b - Project Schedule - Statused

19 Example Consultant Baseline Schedule Print Date: Project: Consultant-UD-6 Attachment C - Example Tier 3 Progress Consulting Schedule Activity ID Activity Name OD RD Percent Complete Start Finish Total Float Phase Prepare FONSI % Consultant-UD-6.40 ROW/Land Consultant-UD Negotiations/Easements/Legal Fees Prepare Right Of Way (ROW) Documents % A Perform Appraisals % Review Appraisals and Prepare Offer % Present First Offer and Negotiation/Acceptance Period % Prepare Second Offer (If Needed) % Present Second Offer and Negotiation/Acceptance Period (If % Prepare & Deliver Condemnation Packet (If Needed) % Condemnation Period (If Needed) % Real Property Complete 0 0 0% Consultant-UD-6.50 Survey Consultant-UD Preliminary Survey Topographic (Field) Survey % A A 50 0 Consultant-UD-6.80 Construction Consultant-UD Construction Advertisement Consultant-UD Bid Preparation and Advertisement Finalize Bid Package % Start Advertisement 0 0 0% Advertisement Period % Hold Pre-Bid Meeting 1 1 0% Issue Addenda (As needed) % Bid Opening - Review Bids - Bid Tabulations and Select Con % Consultant-UD Contract Award Start M&C Process - Construction 0 0 0% MWBE Submittal 5 5 0% Review and Approve MWBE Submittal % M&C Process % Execute Contract Documents % Issue Construction Notice To Proceed 0 0 0% Consultant-UD Pre-Construction Activities Hold Pre-Construction Meeting (with Contractor) 1 1 0% Submittals and Approvals % Start Construction 0 0 0% Consultant-UD Construction Contract Construction % Consultant-UD Inspection Final Inspection % Construction Complete 0 0 0% Var Finish Date S Oct N Dec Jan F Mar Apr M Jun Jul Aug Sep Oct Nov Dec Jan F Mar Apr M Jun Jul Aug S Oct N Dec Jan F Mar Apr Actual Work Remaining Work Critical Remaining Work Milestone Critical Milestones Completed Milestones Remaining Level of Effort Actual Level of Effort Project Baseline Bar Baseline Milest... Sample Consultant Baseline Schedule Page 2 of 2 Layout: FTW-01b - Project Schedule - Statused

20 Attachment D CITY OF FORT WORTH SCHEDULE GUIDANCE DOCUMENT ATTACHMENT D

21 CONTRCT 32-FT WORTH 2951-Baseline FTW-13 Project Schedule Attachment D: Example Tier 3 Baseline Construction Schedule Activity ID Activity Name Physical % Complete OD Remaining Duration CONTRCT 32-FT WORTH 2951-Baseline May Apr-08 MOBILIZATION May Jun-07 MOBILIZATION May Jun Notice to Proceed 0% May-07* 0990 Mobilization 0% May Jun-07 LINE # 5041(CINDY) May Jun-07 SANITARY SEWER May Jun MAIN 0% May Jun SERVICE & CL OUTS 0% May Jun ' MNHS(SHALLOW & STAND) 0% Jun Jun REMOV EXIST MNHS 0% Jun Jun TEMP ASPH REPAIR 0% Jun Jun-07 LINE # 5044, 5045 & Jun Jun-07 SANITARY SEWER Jun Jun MAIN, MNHS & TEMP ASPH REPAIR 0% Jun Jun-07 LINE # 5789 (CINDY) Jun Jun-07 SANITARY SEWER Jun Jun MAIN 0% Jun Jun SER & CL OUTS 0% Jun Jun ' MNHS(INSTALL & REMOV) 0% Jun Jun TEMP ASPH 0% Jun Jun-07 LINE # 4648(LAKELAND) Jun Jul-07 SANITARY SEWER Jun Jul MAIN 0% Jun Jul SERVICE & CL OUTS 0% Jun Jul ' MNHS(INSTALL & REMOV) 0% Jul Jul TEMP ASPH REPAIR 0% Jul Jul-07 LINE # 4647(GAY ST) Jul Jul-07 SANITARY SEWER Jul Jul MAIN 0% Jul Jul SERVICES & CL OUTS 0% Jul Jul ' MNHS(INSTALL & REMOV) 0% Jul Jul TEMP ASPH REPAIR 0% Jul Jul-07 LINE # 4645(HEDRICK Jul Aug-07 SANITARY SEWER Jul Aug MAIN 0% Jul Aug SERVICES & CL OUTS 0% Aug Aug ' MNHS (INSTALL & REMOV) 0% Aug Aug TEMP ASPH REPAIR 0% Aug Aug-07 CINDY STREET Aug Oct-07 WATER Aug Oct TEMPORARY WATER 0% Aug Sep MAIN 0% Sep Sep MAIN 0% Sep Sep WATER LINE 0% Sep Sep SERVICES & BULL HEADS 0% Sep Sep SERVICE 0% Sep Sep & 2 TAPS 0% Sep Sep CONNECTIONS 0% Sep Oct FIRE HYDRANTS 0% Oct Oct TEMP HMAC PAVING REPAIR 0% Oct Oct TEMPORARY WATER REMOVAL 0% Oct Oct-07 LAKELAND STREET Oct Nov-07 WATER Oct Nov TEMPORARY WATER 0% Oct Oct MAIN 0% Oct Oct SINGLE & BULLHEAD SERVICES 0% Oct Oct FIRE HYDRANTS(INSTALL & REMOV) 0% Oct Oct TAPS 0% Oct Oct CONNECTIONS 0% Oct Nov TEMP HMAC PAVING REPAIR 0% Nov Nov TEMPORARY WATER REMOVAL 0% Nov Nov PERM PAVING REPAIR 0% Nov Nov-07 GAY STREET Nov Dec-07 WATER Nov Dec TEMPORARY WATER 0% Nov Nov-07 Start Finish May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Actual Work Remaining Work Critical Remaining Work Milestone Critical Milestone Primary Baseline Data Date: 20-May CONTRCT 32-FT WORTH 2951-Baseline 09-Jan-0908:25

22 CONTRCT 32-FT WORTH 2951-Baseline FTW-13 Project Schedule Attachment D: Example Tier 3 Baseline Construction Schedule Activity ID Activity Name Physical % Complete OD Remaining Duration MAIN 0% Nov Nov SINGLE & BULLHEAD SERVICES 0% Nov Nov TAPS 0% Nov Nov FIRE HYDRANTS(INSTALL & REMOV) 0% Nov Nov CONNECTIONS 0% Nov Nov TEMP HMAC PAVING REPAIR 0% Nov Dec PERMANENT ASPH REPAIR 0% Dec Dec TEMPORARY WATER REMOVAL 0% Dec Dec-07 HEDRICK STREET Dec Dec-07 WATER Dec Dec TEMPORARY WATER 0% Dec Dec MAIN 0% Dec Dec SINGLE & BULLHEADS SERVICES 0% Dec Dec FIRE HYDRANTS(INSTALL & REMOV) 0% Dec Dec CONNECTION 0% Dec Dec TEMP HMAC PAVING REPAIR 0% Dec Dec PERMANENT CONC REPAIR 0% Dec Dec TEMPORARY WATER REMOVAL 0% Dec Dec-07 7 CONC PAVING Feb Apr-08 PAVING Feb Apr REINF STEEL PLCMNT 0% Feb Mar SLIP FORM 0% Mar Mar HAND PLCMNT 0% Mar Apr MACHINE CHANGE 0% Mar Mar REMOV & RELOC LINK & WOOD FENCE 0% Mar Mar ADJUST WATER VALVES 0% Mar Mar ADJUST WATER METERS 0% Mar Mar-08 PERM HMAC PVMNT REPAIR Mar Apr-08 PAVING Mar Apr SAWCUT 0% Mar Mar FLOWABLE BACKFILL 0% Mar Apr ASPHALT 0% Apr Apr ADJUST SANITARY SEWER MNHS 0% Apr Apr TOPSOIL 0% Apr Apr-08 IN GENERAL Dec Jan-08 DIRT WORK Dec Jan UNCLASS EXCAVATION 0% Dec Jan CONC SIDEWALK REMOV 0% Dec Jan REMOV CURB & GUTTER 0% Dec Jan REMOV ST DR INLET & LATERAL 0% Dec Jan REMOV CONC DRIVEWAYS 0% Dec Jan REMOV CONC VALLEY GUTTER 0% Dec Jan-08 6 LIME Jan Feb-08 DIRT WORK Jan Feb STRINGLINE 0% Jan Feb MIX & COMPACT 0% Feb Feb FINAL MIX 0% Feb Feb FINISH GRADE 0% Feb Feb-08 PROJECT ACCEPTANCE Apr Apr-08 PROJECT ACCEPTANCE Apr Apr Construction Complete 0% Apr Final Inspection 0% Apr Apr Project Acceptance 0% Apr-08 No Area Dec Apr-08 STORM DRAIN Dec Dec STORM DRAIN 0% Dec Dec-07 SMALL STRUCTURES Feb Mar CONC RETAINING WALL 0% Feb Mar ' STORM DRAIN INLET 0% Feb Feb-08 FLAT WORK Feb Apr ADA RAMPS(TY 1 & TY 2) 0% Feb Mar CONC VALLEY GUTTER PLCMNT 0% Mar Mar ' CONC SIDEWALK 0% Feb Mar CONC DRIVEWAYS 0% Mar Apr-08 Start Finish May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Actual Work Remaining Work Critical Remaining Work Milestone Critical Milestone Primary Baseline Data Date: 20-May CONTRCT 32-FT WORTH 2951-Baseline 09-Jan-0908:25

23 Attachment E CITY OF FORT WORTH SCHEDULE GUIDANCE DOCUMENT ATTACHMENT E

24 CONTRCT 32-FT WORTH 2951-Progress FTW-13 Project Schedule Attachment E: Example Tier 3 Progress Construction Schedule Activity ID Activity Name Physical % Complete OD Remaining Duration Start Finish Total Float CONTRCT 32-FT WORTH 2951-Progress May-07 A 07-Apr-08 0 MOBILIZATION May-07 A 01-Jun-07 A MOBILIZATION May-07 A 01-Jun-07 A 0980 Notice to Proceed 100% May-07 A 0990 Mobilization 100% May-07 A 01-Jun-07 A LINE # 5041(CINDY) May-07 A 12-Jun-07 A SANITARY SEWER May-07 A 12-Jun-07 A MAIN 100% May-07 A 05-Jun-07 A SERVICE & CL OUTS 100% May-07 A 08-Jun-07 A ' MNHS(SHALLOW & STAND) 100% Jun-07 A 08-Jun-07 A 1030 REMOV EXIST MNHS 100% Jun-07 A 08-Jun-07 A 1040 TEMP ASPH REPAIR 100% Jun-07 A 12-Jun-07 A LINE # 5044, 5045 & Jun-07 A 14-Jun-07 A SANITARY SEWER Jun-07 A 14-Jun-07 A MAIN, MNHS & TEMP ASPH REPAIR 100% Jun-07 A 14-Jun-07 A LINE # 5789 (CINDY) Jun-07 A 25-Jun-07 A SANITARY SEWER Jun-07 A 25-Jun-07 A MAIN 100% Jun-07 A 18-Jun-07 A SER & CL OUTS 100% Jun-07 A 20-Jun-07 A ' MNHS(INSTALL & REMOV) 100% Jun-07 A 20-Jun-07 A 1090 TEMP ASPH 100% Jun-07 A 25-Jun-07 A LINE # 4648(LAKELAND) Jun-07 A 13-Jul-07 A SANITARY SEWER Jun-07 A 13-Jul-07 A MAIN 100% Jun-07 A 03-Jul-07 A SERVICE & CL OUTS 100% Jun-07 A 10-Jul-07 A ' MNHS(INSTALL & REMOV) 100% Jul-07 A 10-Jul-07 A 1130 TEMP ASPH REPAIR 100% Jul-07 A 13-Jul-07 A LINE # 4647(GAY ST) Jul-07 A 31-Jul-07 A SANITARY SEWER Jul-07 A 31-Jul-07 A MAIN 100% Jul-07 A 18-Jul-07 A SERVICES & CL OUTS 100% Jul-07 A 25-Jul-07 A ' MNHS(INSTALL & REMOV) 100% Jul-07 A 25-Jul-07 A 1170 TEMP ASPH REPAIR 100% Jul-07 A 31-Jul-07 A LINE # 4645(HEDRICK Jul-07 A 16-Aug-07 0 SANITARY SEWER Jul-07 A 16-Aug MAIN 0% Jul-07 A 03-Aug SERVICES & CL OUTS 0% Aug Aug ' MNHS (INSTALL & REMOV) 0% Aug Aug TEMP ASPH REPAIR 0% Aug Aug-07 0 CINDY STREET Aug Oct-07 0 WATER Aug Oct TEMPORARY WATER 0% Aug Sep MAIN 0% Sep Sep MAIN 0% Sep Sep WATER LINE 0% Sep Sep SERVICES & BULL HEADS 0% Sep Sep SERVICE 0% Sep Sep & 2 TAPS 0% Sep Sep CONNECTIONS 0% Sep Oct FIRE HYDRANTS 0% Oct Oct TEMP HMAC PAVING REPAIR 0% Oct Oct TEMPORARY WATER REMOVAL 0% Oct Oct-07 0 LAKELAND STREET Oct Nov-07 0 WATER Oct Nov TEMPORARY WATER 0% Oct Oct MAIN 0% Oct Oct SINGLE & BULLHEAD SERVICES 0% Oct Oct FIRE HYDRANTS(INSTALL & REMOV) 0% Oct Oct TAPS 0% Oct Oct CONNECTIONS 0% Oct Nov TEMP HMAC PAVING REPAIR 0% Nov Nov TEMPORARY WATER REMOVAL 0% Nov Nov PERM PAVING REPAIR 0% Nov Nov-07 0 GAY STREET Nov Dec-07 0 WATER Nov Dec TEMPORARY WATER 0% Nov Nov May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Actual Work Remaining Work Critical Remaining Work Milestone Critical Milestone Primary Baseline Data Date: 31-Jul CONTRCT 32-FT WORTH 2951-Progress 13-Jan-0913:35

25 CONTRCT 32-FT WORTH 2951-Progress FTW-13 Project Schedule Attachment E: Example Tier 3 Progress Construction Schedule Activity ID Activity Name Physical % Complete OD Remaining Duration Start Finish Total Float MAIN 0% Nov Nov SINGLE & BULLHEAD SERVICES 0% Nov Nov TAPS 0% Nov Nov FIRE HYDRANTS(INSTALL & REMOV) 0% Nov Nov CONNECTIONS 0% Nov Nov TEMP HMAC PAVING REPAIR 0% Nov Dec PERMANENT ASPH REPAIR 0% Dec Dec TEMPORARY WATER REMOVAL 0% Dec Dec-07 0 HEDRICK STREET Dec Dec-07 0 WATER Dec Dec TEMPORARY WATER 0% Dec Dec MAIN 0% Dec Dec SINGLE & BULLHEADS SERVICES 0% Dec Dec FIRE HYDRANTS(INSTALL & REMOV) 0% Dec Dec CONNECTION 0% Dec Dec TEMP HMAC PAVING REPAIR 0% Dec Dec PERMANENT CONC REPAIR 0% Dec Dec TEMPORARY WATER REMOVAL 0% Dec Dec CONC PAVING Feb Mar-08 0 PAVING Feb Mar REINF STEEL PLCMNT 0% Feb Mar SLIP FORM 0% Mar Mar HAND PLCMNT 0% Mar Mar MACHINE CHANGE 0% Mar Mar REMOV & RELOC LINK & WOOD FENCE 0% Mar Mar ADJUST WATER VALVES 0% Mar Mar ADJUST WATER METERS 0% Mar Mar-08 0 PERM HMAC PVMNT REPAIR Mar Apr-08 0 PAVING Mar Apr SAWCUT 0% Mar Mar FLOWABLE BACKFILL 0% Mar Apr ASPHALT 0% Apr Apr ADJUST SANITARY SEWER MNHS 0% Apr Apr TOPSOIL 0% Mar Mar-08 4 IN GENERAL Dec Jan DIRT WORK Dec Jan UNCLASS EXCAVATION 0% Dec Jan CONC SIDEWALK REMOV 0% Dec Jan REMOV CURB & GUTTER 0% Dec Jan REMOV ST DR INLET & LATERAL 0% Dec Jan REMOV CONC DRIVEWAYS 0% Dec Jan REMOV CONC VALLEY GUTTER 0% Dec Jan LIME Jan Feb-08 0 DIRT WORK Jan Feb STRINGLINE 0% Jan Feb MIX & COMPACT 0% Jan Feb FINAL MIX 0% Feb Feb FINISH GRADE 0% Feb Feb-08 0 PROJECT ACCEPTANCE Mar Apr-08 5 PROJECT ACCEPTANCE Mar Apr Construction Complete 0% Mar Final Inspection 0% Mar Apr Project Acceptance 0% Apr-08 5 No Area Dec Mar STORM DRAIN Dec Dec STORM DRAIN 0% Dec Dec-07 0 SMALL STRUCTURES Feb Mar CONC RETAINING WALL 0% Feb Mar ' STORM DRAIN INLET 0% Feb Feb-08 4 FLAT WORK Feb Mar ADA RAMPS(TY 1 & TY 2) 0% Feb Mar CONC VALLEY GUTTER PLCMNT 0% Mar Mar ' CONC SIDEWALK 0% Feb Mar CONC DRIVEWAYS 0% Feb Mar May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Actual Work Remaining Work Critical Remaining Work Milestone Critical Milestone Primary Baseline Data Date: 31-Jul CONTRCT 32-FT WORTH 2951-Progress 13-Jan-0913:35

26 Attachment F CITY OF FORT WORTH SCHEDULE GUIDANCE DOCUMENT ATTACHMENT F

27 Attachment F Schedule Submittal Process for Buzzsaw Desktop Client Users This Job Aid contains consultant and contractor instructions for submitting baseline schedules and schedule updates to the City of Fort Worth (CoFW). If you are not a registered CoFW Buzzsaw user, please or contact: Fred Griffin, Buzzsaw Administrator City of Fort Worth Fred.Griffin@fortworthgov.org Using your registered username and password log into the City s Buzzsaw Site Verify that the file name contains the 5-digit Project ID, Project Name, and Submittal Date and follows the standard naming convention. Initial schedule submittal will be labeled as Baseline for example: FlaxseedDrainageImprovements-Baseline Schedule submittal updates will be labeled with Schedule Submittal Date YYYY_MM for example: FlaxseedDrainageImprovements-2009_01 Expand or select the Schedules folder and add both the native file and PDF file to the directory. From the Toolbar Select Add Document Navigate to your Project Folder. Verify that your Project ID and Project Name are consistent with Project Folder Name. Navigate to the Schedule Directory under your Project Folder. The Flaxseed Drainage Improvements project is used for illustration. Select Browse and go to the location of the files on your desktop, select Open. Two files will be uploaded for each submittal. A native schedule file format either Primavera.xer or MS Project.mpp and a PDF version of the schedule will be uploaded.

28 Attachment F Schedule Submittal Process for Buzzsaw Desktop Client Users The file will appear in the Buzzsaw Add to Project Select Documents window. Select Next. Do not select Finish at this time. You will be placed into the Attach Comment window to enter a record into the Project Schedule Submittal Log. Select the Paste Comment button to copy the Comment into the body of the . Select Finish. Enter the Project ID-Project Name-Submittal in the Subject Line. Type Submittal and Company Name into the Comment window along with Contact Name and Contact Phone Number. Select Next. The schedule file is uploaded to the directory. An is sent to the Project Manager and Project Control Team. You will be placed into the Send Notification window. Select To and the Select Recipients window will appear with a list of Project Contacts. Select the Project Manager as the To Recipient and the Project Controls Group as the Copy Recipient. Upload the PDF file using the same guideline.

763XXX Timing Analysis, Critical Path Method (CPM) Project Schedule

763XXX Timing Analysis, Critical Path Method (CPM) Project Schedule 763XXX Timing Analysis, Critical Path Method (CPM) Project Schedule Description: This work shall reflect a Contractor s anticipated work plan for constructing the project using a Critical Path Method Project

More information

EXHIBIT 2-2-C PROGRESS SCHEDULES

EXHIBIT 2-2-C PROGRESS SCHEDULES EXHIBIT 2-2-C PROGRESS SCHEDULES PART 1 GENERAL 1.01 SUMMARY A. The work specified in this section consists of furnishing transportation, labor, materials, equipment and incidentals necessary for preparation,

More information

CRITICAL PATH METHOD (CPM) SCHEDULES

CRITICAL PATH METHOD (CPM) SCHEDULES 96 CRITICAL PATH METHOD (CPM) SCHEDULES How-to for Reading, Understanding, and Using CPM Schedules (without Direct Primavera Access.) 1 Objectives Learn to read, understand, and use CPM schedules (without

More information

SPECIFICATIONS - DETAILED PROVISIONS Section 01310 - Project Control Schedule C O N T E N T S

SPECIFICATIONS - DETAILED PROVISIONS Section 01310 - Project Control Schedule C O N T E N T S SPECIFICATIONS - DETAILED PROVISIONS Section 01310 - Project Control Schedule C O N T E N T S PART 1 - SCHEDULE REQUIREMENTS PROGRESS SCHEDULE... 1 PART 2 - SUBMITTAL PROCEDURES... 2 PART 3 - DEFINITIONS...

More information

MODEL SCHEDULING SPECIFICATION

MODEL SCHEDULING SPECIFICATION MODEL SCHEDULING SPECIFICATION Introduction (Not part of the specification) Before implementation, we recommend that your contract and this provision be reviewed and modified to ensure compatibility with

More information

SECTION 01310 COST LOADED CRITICAL PATH SCHEDULE

SECTION 01310 COST LOADED CRITICAL PATH SCHEDULE SECTION 01310 COST LOADED CRITICAL PATH SCHEDULE 1.0 General 1.1 Description The Work specified in this Section consists of developing and maintaining an accurate cost loaded critical path schedule in

More information

Spec. Standard: 11/27/06 01310-1 Revision: 11/27/06

Spec. Standard: 11/27/06 01310-1 Revision: 11/27/06 SECTION 01310 CONSTRUCTION SCHEDULES PART 1 - GENERAL 1.01 SCOPE: A. Construction Progress Schedule: The CONTRACTOR shall submit a detailed work progress schedule showing all work in a graphic format suitable

More information

SECTION 01 32 00 - PROJECT PLANNING AND SCHEDULING PART 1: GENERAL 1.1 DEFINITIONS

SECTION 01 32 00 - PROJECT PLANNING AND SCHEDULING PART 1: GENERAL 1.1 DEFINITIONS SECTION 01 32 00 - PROJECT PLANNING AND SCHEDULING PART 1: GENERAL 1.1 DEFINITIONS A. The term Baseline Schedule, as used throughout the contract documents, shall refer to a fixed projection of the project

More information

01 32 00 CONSTRUCTION PROGRESS DOCUMENTATION (SCHEDULING)

01 32 00 CONSTRUCTION PROGRESS DOCUMENTATION (SCHEDULING) 01 32 00 CONSTRUCTION PROGRESS DOCUMENTATION (SCHEDULING) PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other

More information

108-C-215 CRITICAL PATH METHOD SCHEDULE. (Revised 03-24-10)

108-C-215 CRITICAL PATH METHOD SCHEDULE. (Revised 03-24-10) CRITICAL PATH METHOD SCHEDULE (Revised 03-24-10) The Standard Specifications are revised as follows: SECTION 108, BEGIN LINE 177, INSERT AS FOLLOWS: 108.04.1 Critical Path Method Schedule (a) General Requirements

More information

MATERIALS: The Contractor shall provide the latest version of Primavera SureTrak software.

MATERIALS: The Contractor shall provide the latest version of Primavera SureTrak software. DESCRIPTION: '108-01, Start and Progress of Work, is hereby amended to require that the Contractor furnish and participate in a computerized CPM (critical path method) network scheduling system. The purpose

More information

UNIFIED FACILITIES GUIDE SPECIFICATIONS ************************************************************************** SECTION TABLE OF CONTENTS

UNIFIED FACILITIES GUIDE SPECIFICATIONS ************************************************************************** SECTION TABLE OF CONTENTS USACE / NAVFAC / AFCEC / NASA UFGS-01 32 16.00 20 (February 2015) Change 2-11/15 ----------------------------------- Preparing Activity: NAVFAC Superseding UFGS-01 32 16.00 20 (November 2009) UNIFIED FACILITIES

More information

Memorandum. Jeff Jasper, P.E. Director, Division of Design. Technical Support TEBM, Division of Construction. From: Jeremiah Littleton, P.E.

Memorandum. Jeff Jasper, P.E. Director, Division of Design. Technical Support TEBM, Division of Construction. From: Jeremiah Littleton, P.E. Memorandum To: Thru: Jeff Jasper, P.E. Director, Division of Design Rachel Mills, P.E. Technical Support TEBM, Division of Construction From: Jeremiah Littleton, P.E. Division of Construction Date: June

More information

U.S. Department of Veterans Affairs. Facilities Management. Critical Path Method. Guidelines for Preparation of CPM Schedule Volume I

U.S. Department of Veterans Affairs. Facilities Management. Critical Path Method. Guidelines for Preparation of CPM Schedule Volume I VA U.S. Department of Veterans Affairs Facilities Management Critical Path Method design DECEMBER 2012 Volume I Design Manual for & TABLE OF CONTENTS, Volume I 1. INTRODUCTION... 3 1.1. Purpose and Scope...

More information

PN 107-01/16/2009 - CRITICAL PATH METHOD PROGRESS SCHEDULE

PN 107-01/16/2009 - CRITICAL PATH METHOD PROGRESS SCHEDULE PN 107-01/16/2009 - CRITICAL PATH METHOD PROGRESS SCHEDULE A. General. The progress schedule required for this project is the critical path method schedule (CPM schedule). The Contractor shall designate

More information

Exhibit C: Scope of Work and Schedule of Deliverables

Exhibit C: Scope of Work and Schedule of Deliverables Exhibit C: Scope of Work and Schedule of Deliverables Project Scope of Work Phases: A City Hall Envelope Renovations B City Hall Skylight Replacement C City Hall Chiller Replacement D City Hall Annex Plaza

More information

Design Consultant Project Management Requirements

Design Consultant Project Management Requirements Design Consultant Project Management Requirements Version 2 April 25, 2013 AWTP Program Design Consultant Contents 1.0 Introduction... 1 2.0 General Management... 1 3.0 Project Management Plan... 1 4.0

More information

Alexandria National Cemetery SECTION 01 32 16.13 NETWORK ANALYSIS SCHEDULE

Alexandria National Cemetery SECTION 01 32 16.13 NETWORK ANALYSIS SCHEDULE SECTION 01 32 16.13 PART 1 - GENERAL 1.1 DESCRIPTION: A. The Contractor shall develop a Microsoft Project 2003 (or latest version) Bar Chart schedule demonstrating fulfillment of the contract requirements.

More information

UNIFIED FACILITIES GUIDE SPECIFICATIONS

UNIFIED FACILITIES GUIDE SPECIFICATIONS USACE / NAVFAC / AFCESA / NASA UFGS-01 32 01.00 10 (February 2015) ----------------------------------- Preparing Activity: USACE Superseding UFGS-01 32 01.00 10 (August 2008) UNIFIED FACILITIES GUIDE SPECIFICATIONS

More information

2015-16 BCOE Payroll Calendar. Monday Tuesday Wednesday Thursday Friday Jun 29 30 Jul 1 2 3. Full Force Calc

2015-16 BCOE Payroll Calendar. Monday Tuesday Wednesday Thursday Friday Jun 29 30 Jul 1 2 3. Full Force Calc July 2015 CM Period 1501075 July 2015 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 August 2015 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26

More information

Developing Critical Path Method Scheduling (CPM)

Developing Critical Path Method Scheduling (CPM) Developing Critical Path Method Scheduling (CPM) Pretest 1. An activity which is on critical path has a planned duration of 5 days. What is the total float for the activity? a. 0 b. 1 c. 2 d. 3 Pretest

More information

Jeff Haby, P.E. Director Sewer System Improvements. September 15, 2015. Agenda

Jeff Haby, P.E. Director Sewer System Improvements. September 15, 2015. Agenda SAWS Sanitary Sewer Overflow Reduction Program Jeff Haby, P.E. Director Sewer System Improvements SA Military Engineers Meeting Agenda SAWS Overview Consent Decree CD Compliance Programs Program Transition

More information

S-1 (1803) PROGRESS SCHEDULES-CRITICAL PATH METHOD (CPM) The provisions of MnDOT 1803 are deleted and replaced with these Special Provisions.

S-1 (1803) PROGRESS SCHEDULES-CRITICAL PATH METHOD (CPM) The provisions of MnDOT 1803 are deleted and replaced with these Special Provisions. S-1 (1803) PROGRESS SCHEDULES-CRITICAL PATH METHOD (CPM) The provisions of MnDOT 1803 are deleted and replaced with these Special Provisions. 1803.1 All SCHEDULES A General Requirements This section contains

More information

AT&T Global Network Client for Windows Product Support Matrix January 29, 2015

AT&T Global Network Client for Windows Product Support Matrix January 29, 2015 AT&T Global Network Client for Windows Product Support Matrix January 29, 2015 Product Support Matrix Following is the Product Support Matrix for the AT&T Global Network Client. See the AT&T Global Network

More information

PROJECT MANAGEMENT PLAN <PROJECT NAME>

PROJECT MANAGEMENT PLAN <PROJECT NAME> PROJECT MANAGEMENT PLAN TEMPLATE This Project Management Plan Template is free for you to copy and use on your project and within your organization. We hope that you find this template useful and welcome

More information

SECTION 013200a - CONSTRUCTION PROGRESS DOCUMENTATION

SECTION 013200a - CONSTRUCTION PROGRESS DOCUMENTATION SECTION 013200a - CONSTRUCTION PROGRESS DOCUMENTATION PART 1 - GENERAL 1.1 Related Documents A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other

More information

Close-Out Documents... 9

Close-Out Documents... 9 Water and Sanitary Sewer Service Connection Requirements Service Connection Requirements... 1 Application for Services... 2 Water Meter Application... 2 Wet Tap/Tie-in Connection Requirements... 3 Meter

More information

WORK PROGRAM GUIDELINES

WORK PROGRAM GUIDELINES Project Managed Change Program WORK PROGRAM GUIDELINES JABATAN KERJA RAYA MALAYSIA Cawangan Pengurusan Projek Kompleks (PROKOM) Ibu Pejabat JKR Malaysia 2 Document Ownership Section No Section Amendment

More information

SECTION 01320 - CONSTRUCTION PROGRESS DOCUMENTATION PART 1 - GENERAL 1.1 RELATED DOCUMENTS

SECTION 01320 - CONSTRUCTION PROGRESS DOCUMENTATION PART 1 - GENERAL 1.1 RELATED DOCUMENTS SECTION 01320 - CONSTRUCTION PROGRESS DOCUMENTATION PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division

More information

Construction Project Scheduling: Keys to Success

Construction Project Scheduling: Keys to Success View the online version at http://us.practicallaw.com/0-574-8625 Construction Project Scheduling: Keys to Success KELLY M. HEUER AND JAMES G. ZACK, JR., NAVIGANT CONSULTING, INC., WITH PRACTICAL LAW REAL

More information

1. Interpretation of this Schedule

1. Interpretation of this Schedule Schedule 6 Programming Requirements 1. Interpretation of this Schedule 1.1 Primavera The following capitalised terms used in this Schedule 6 have the meanings given to them in the proprietary computer

More information

SECTION 01311 - CONSTRUCTION SCHEDULE B. Part 1 - General... 1. 1.01 Work Included... 1. 1.02 Related Requirements... 1. 1.03 Reference Standards...

SECTION 01311 - CONSTRUCTION SCHEDULE B. Part 1 - General... 1. 1.01 Work Included... 1. 1.02 Related Requirements... 1. 1.03 Reference Standards... SECTION 01311 - CONSTRUCTION SCHEDULE B CONTENTS: Part 1 - General... 1 1.01 Work Included... 1 1.02 Related Requirements... 1 1.03 Reference Standards... 1 1.04 Quality Assurance... 1 1.05 Measurement

More information

Scheduling Best Practices

Scheduling Best Practices The eighth article in the Scheduling Best Practices series is How to Handle the Weather. Our colleague Beth Blair, a managing consultant in Warner s Disputes Resolution Group, has over 20 years of experience

More information

EXHIBIT A SCOPE OF SERVICES WATER SERVICE REPLACEMENT PROJECT. BROWARD OPERATIONS CENTER 5548 NW 9 th AVENUE FORT LAUDERDALE, FLORIDA 33309

EXHIBIT A SCOPE OF SERVICES WATER SERVICE REPLACEMENT PROJECT. BROWARD OPERATIONS CENTER 5548 NW 9 th AVENUE FORT LAUDERDALE, FLORIDA 33309 EXHIBIT A SCOPE OF SERVICES WATER SERVICE REPLACEMENT PROJECT BROWARD OPERATIONS CENTER 5548 NW 9 th AVENUE FORT LAUDERDALE, FLORIDA 33309 FLORIDA DEPARTMENT OF TRANSPORTATION DISTRICT FOUR 1.0 SCOPE OF

More information

Academic Calendar 2015-2018 Arkansas State University - Jonesboro

Academic Calendar 2015-2018 Arkansas State University - Jonesboro Shared Governance Proposal Any constituent (individual or group) may submit a proposal into the shared governance process. In order to be considered, each proposal must contain the following and be directed

More information

Contract / Construction Management. November 2006

Contract / Construction Management. November 2006 Contract / Construction Management November 2006 Presentation Outline I. Introduction Project Management II. Contract/Construction Management Stage 1: Construction Period Stage 2: Defects Liability Period

More information

COMPARISON OF FIXED & VARIABLE RATES (25 YEARS) CHARTERED BANK ADMINISTERED INTEREST RATES - PRIME BUSINESS*

COMPARISON OF FIXED & VARIABLE RATES (25 YEARS) CHARTERED BANK ADMINISTERED INTEREST RATES - PRIME BUSINESS* COMPARISON OF FIXED & VARIABLE RATES (25 YEARS) 2 Fixed Rates Variable Rates FIXED RATES OF THE PAST 25 YEARS AVERAGE RESIDENTIAL MORTGAGE LENDING RATE - 5 YEAR* (Per cent) Year Jan Feb Mar Apr May Jun

More information

COMPARISON OF FIXED & VARIABLE RATES (25 YEARS) CHARTERED BANK ADMINISTERED INTEREST RATES - PRIME BUSINESS*

COMPARISON OF FIXED & VARIABLE RATES (25 YEARS) CHARTERED BANK ADMINISTERED INTEREST RATES - PRIME BUSINESS* COMPARISON OF FIXED & VARIABLE RATES (25 YEARS) 2 Fixed Rates Variable Rates FIXED RATES OF THE PAST 25 YEARS AVERAGE RESIDENTIAL MORTGAGE LENDING RATE - 5 YEAR* (Per cent) Year Jan Feb Mar Apr May Jun

More information

Special Specification 7021 Water Main and Sewer Line Replacements

Special Specification 7021 Water Main and Sewer Line Replacements Special Specification 7021 Water Main and Sewer Line Replacements 1. DESCRIPTION Furnish, install, or replace water pipe, water valves, water meters and boxes, water service connections, fire hydrant assemblies,

More information

Analysis One Code Desc. Transaction Amount. Fiscal Period

Analysis One Code Desc. Transaction Amount. Fiscal Period Analysis One Code Desc Transaction Amount Fiscal Period 57.63 Oct-12 12.13 Oct-12-38.90 Oct-12-773.00 Oct-12-800.00 Oct-12-187.00 Oct-12-82.00 Oct-12-82.00 Oct-12-110.00 Oct-12-1115.25 Oct-12-71.00 Oct-12-41.00

More information

Project Time Management

Project Time Management Project Time Management Plan Schedule Management is the process of establishing the policies, procedures, and documentation for planning, developing, managing, executing, and controlling the project schedule.

More information

California Department Of Transportation. Class # G0C094

California Department Of Transportation. Class # G0C094 California Department Of Transportation ADVANCED CPM SCHEDULING WITH SURETRAK Class # G0C094 ADVANCED CPM SCHEDULING WITH SURETRAK September 2003 SureTrak is a registered trademark of Primavera Systems,

More information

PROJECT TIME MANAGEMENT

PROJECT TIME MANAGEMENT 6 PROJECT TIME MANAGEMENT Project Time Management includes the processes required to ensure timely completion of the project. Figure 6 1 provides an overview of the following major processes: 6.1 Activity

More information

Project Cost & Schedule Monitoring Process Using MS Excel & MS Project

Project Cost & Schedule Monitoring Process Using MS Excel & MS Project Project Cost & Schedule Monitoring Process Using MS Excel & MS Project Presented by: Rajesh Jujare About Us Solutions is founded with objectives a. To share its expertise and experiences to overcome the

More information

Scheduling Glossary Activity. A component of work performed during the course of a project.

Scheduling Glossary Activity. A component of work performed during the course of a project. Scheduling Glossary Activity. A component of work performed during the course of a project. Activity Attributes. Multiple attributes associated with each schedule activity that can be included within the

More information

Chapter 9 Computer Scheduling Projects should be scheduled one byte at a time

Chapter 9 Computer Scheduling Projects should be scheduled one byte at a time Chapter 9 Computer Scheduling Projects should be scheduled one byte at a time Computer Scheduling Critical path method (CPM) requires numerous computations to determine activity start and finish dates,

More information

Cost & Schedule Risk Assessment Using @Risk 6.0. Timothy J. Havranek, MBA, PMP Leigh Hostetter, PMP

Cost & Schedule Risk Assessment Using @Risk 6.0. Timothy J. Havranek, MBA, PMP Leigh Hostetter, PMP Cost & Schedule Risk Assessment Using @Risk 6.0 Timothy J. Havranek, MBA, PMP Leigh Hostetter, PMP 24 October 2012 What If? In Business and in Life: We always made the best possible decisions, and Implemented

More information

2013-2014. oct 03 / 2013 nov 12 / 2013. oct 05 / 2013. oct 07 / 2013. oct 21 / 2013. oct 24 / 2013. nov 07 / 2013 nov 14 / 2013.

2013-2014. oct 03 / 2013 nov 12 / 2013. oct 05 / 2013. oct 07 / 2013. oct 21 / 2013. oct 24 / 2013. nov 07 / 2013 nov 14 / 2013. 2013- ACADEMIC CALENDARS SOUTH UNIVERSITY 2013- ACADEMIC CALENDAR Fall 2013 Winter Spring Summer New Student Orientation Session II (Mid ) oct 03 / 2013 nov 12 / 2013 jan 09 / feb 18 / apr 03 / may 13

More information

Collaborative Scheduling using the CPM Method

Collaborative Scheduling using the CPM Method MnDOT Project Management Office Presents: Collaborative Scheduling using the CPM Method Presenter: Jonathan McNatty, PSP Senior Schedule Consultant DRMcNatty & Associates, Inc. Housekeeping Items Lines

More information

SOUTH FLORIDA WATER MANAGEMENT DISTRICT CONTRACTOR CPM SCHEDULE SUBMITTAL - DISTRICT REVIEW General Contractor CPM Schedule

SOUTH FLORIDA WATER MANAGEMENT DISTRICT CONTRACTOR CPM SCHEDULE SUBMITTAL - DISTRICT REVIEW General Contractor CPM Schedule Contract No. CPM Schedule Project Id SOUTH FLORIDA WATER MANAGEMENT DISTRICT General Contractor CPM Schedule Project Name NTP DATE Data Date CONTRACT DURATION 0 ORIGINAL CONTRACT AMOUNT Date Schedule Received

More information

Notes. Score. 1 Basic Services 1.1. A few instances; could have been more proactive

Notes. Score. 1 Basic Services 1.1. A few instances; could have been more proactive Jacobs Contract performance Tracking spreadsheet = Excellent 2 = Meets performance standards 1 = Improvement needed 0= Unsatisfactory Report for the time period: Annual report 210 Total average score 2.86

More information

Applied Project Management ( APM )

Applied Project Management ( APM ) Applied Project Management Applied Project Management ( APM ) TRAINING PROGRAM Page 1 Of 7 APPLIED PROJECT MANAGEMENT PRO PROGRAM OVERVIEW This course provides in-depth Project Management Training and

More information

Work Breakdown Structure & Schedules

Work Breakdown Structure & Schedules A Work Breakdown Structure (WBS) identifies tasks and deliverables associated with a project. Resources are identified for each item within the WBS that facilitates budgeting as well as assignment of responsibilities.

More information

Controlling Our Critical Path: A CDOT Guide to Better Project Management Practices

Controlling Our Critical Path: A CDOT Guide to Better Project Management Practices : A CDOT Guide to Better Project Management Practices Project Management practices have been a part of the CDOT culture for many years. However, with a transitioning workforce and increasing demands, it

More information

VILLAGE OF LOMBARD CONTRACT DOCUMENT NUMBER ST-09-06 BID PROPOSAL

VILLAGE OF LOMBARD CONTRACT DOCUMENT NUMBER ST-09-06 BID PROPOSAL VILLAGE OF LOMBARD CONTRACT DOCUMENT NUMBER ST-09-06 BID PROPOSAL I/We hereby agree to furnish to the Village of Lombard all necessary materials, equipment, and labor, to complete the North Industrial

More information

Enhanced Vessel Traffic Management System Booking Slots Available and Vessels Booked per Day From 12-JAN-2016 To 30-JUN-2017

Enhanced Vessel Traffic Management System Booking Slots Available and Vessels Booked per Day From 12-JAN-2016 To 30-JUN-2017 From -JAN- To -JUN- -JAN- VIRP Page Period Period Period -JAN- 8 -JAN- 8 9 -JAN- 8 8 -JAN- -JAN- -JAN- 8-JAN- 9-JAN- -JAN- -JAN- -JAN- -JAN- -JAN- -JAN- -JAN- -JAN- 8-JAN- 9-JAN- -JAN- -JAN- -FEB- : days

More information

Common File Server The secure common file server provided by the Department for storage of all contract documents.

Common File Server The secure common file server provided by the Department for storage of all contract documents. DESCRIPTION: Under this item the Contractor shall prepare, status, electronically file and send all project correspondence, Shop Drawings, Requests For Information, meeting minutes, and schedule narratives

More information

MnDOT Project Management Office Presents: Schedule Updates. Presenter: Eric Costantino Senior Schedule Consultant DRMcNatty & Associates, Inc.

MnDOT Project Management Office Presents: Schedule Updates. Presenter: Eric Costantino Senior Schedule Consultant DRMcNatty & Associates, Inc. MnDOT Project Management Office Presents: Schedule Updates Presenter: Eric Costantino Senior Schedule Consultant DRMcNatty & Associates, Inc. Housekeeping Items Lines will be muted during the webinar Questions

More information

CHAPTER 7: SUBDIVISION CONSTRUCTION, INSPECTION AND BONDING. 7.05 Subdivision Improvement Performance Bond Requirements

CHAPTER 7: SUBDIVISION CONSTRUCTION, INSPECTION AND BONDING. 7.05 Subdivision Improvement Performance Bond Requirements CHAPTER 7: SUBDIVISION CONSTRUCTION, INSPECTION AND BONDING 7.00 Construction 7.01 Inspection and Testing of Improvements 7.02 Approval of Improvements 7.03 City Engineer s Acceptance of All Improvements

More information

Basic Project Management & Planning

Basic Project Management & Planning Basic Project Management & Planning Dr. David K. Potter Director & Don Pether Chair in Engineering and Management em4a03@mcmaster.ca 1 What is Project Management? A set of principles, methods, tools, and

More information

PROJECT MANAGEMENT HANDBOOK, PART 1 - ISSUES COMMON TO ALL PROJECT MANAGERS. Table of Contents. Introduction... 2. Why Do We Need Schedules?...

PROJECT MANAGEMENT HANDBOOK, PART 1 - ISSUES COMMON TO ALL PROJECT MANAGERS. Table of Contents. Introduction... 2. Why Do We Need Schedules?... CHAPTER 15 - Scheduling Table of Contents Topic Page Introduction..... 2 Why Do We Need Schedules?.... 2 How Do We Use Schedules?...... 3 Responsibilities for Scheduling...... 3 The Basics of Scheduling........

More information

NASDAQ DUBAI TRADING AND SETTLEMENT CALENDAR 2015. 1. On US Federal Reserve Holidays, no settlements will take place for USD.

NASDAQ DUBAI TRADING AND SETTLEMENT CALENDAR 2015. 1. On US Federal Reserve Holidays, no settlements will take place for USD. NASDAQ Dubai Circular No. : 65/14 Date of Issue : December 22 nd 2014 Date of Expiry : Upon issue of replacement Circular NASDAQ DUBAI TRADING AND SETTLEMENT CALENDAR 2015 Issued pursuant to the NASDAQ

More information

Review of 01310 Schedule Specification Requirements District SAP/WBS breakdown Asset template Cost & Resource Loading Stored Material Costs

Review of 01310 Schedule Specification Requirements District SAP/WBS breakdown Asset template Cost & Resource Loading Stored Material Costs Agenda Topics: 1. Oracle/Primavera buyout Within the last year, Oracle bought Primavera. Primavera support has been tailored to Oracle s standard. stead of initially speaking to a support representative,

More information

New Road 11.0m Asphalt 23m ROW

New Road 11.0m Asphalt 23m ROW New Road 11.0m Asphalt 23m ROW Granular A - 150 mm sq. m. $5.35 $69.53 Granular B - 300 mm sq. m. $7.35 $95.54 Concrete Curb and Gutter m. $44.67 $89.34 HL3 Asphalt - 40 mm sq. m. $7.66 $84.23 HL 4 or

More information

REQUEST FOR QUALIFICATIONS. 2013 Concrete Rehabilitation Program. Various Locations within the City of Centennial PROJECT NO.

REQUEST FOR QUALIFICATIONS. 2013 Concrete Rehabilitation Program. Various Locations within the City of Centennial PROJECT NO. REQUEST FOR QUALIFICATIONS 2013 Concrete Rehabilitation Program Various Locations within the City of Centennial PROJECT NO. 2013-RFQ-13-01-01 Request for Qualifications due: Date: Friday, January 11, 2013

More information

Chapter 22. Lump Sum Project Guidelines

Chapter 22. Lump Sum Project Guidelines Chapter 22 Lump Sum Project Guidelines 22.1 General...22-1 22.2 Project Selection...22-3 22.3 Plans Preparation...22-5 22.4 Preliminary Estimate...22-7 22.5 Specifications...22-9 22.6 Contracts Administration...22-11

More information

City of Hilshire Village Pine Creek Ln Reconstruction

City of Hilshire Village Pine Creek Ln Reconstruction City of Hilshire Village Pine Creek Ln Reconstruction OVERVIEW The City will be soliciting bids for the Pine Creek Reconstruction Project with construction scheduled to begin in January 2015. This project

More information

Pre-Existing Structures at the Site Project Duration Type of Structure Under Construction Any Other Entities with Interests in the Property

Pre-Existing Structures at the Site Project Duration Type of Structure Under Construction Any Other Entities with Interests in the Property Speakers: Vice President, Global Risk Management & Insurance Starwood Hotels & Resorts Worldwide Senior Vice President - National Director National Property Claims - Strategic Outcomes Practice Willis

More information

Project Management Using Earned Value

Project Management Using Earned Value Project Management Using Earned Value Third Edition Gary C. Humphreys Earned Value Management Consulting Training 2002, 2011, 2014 Gary C. Humphreys Humphreys & Associates, Inc. All rights reserved. No

More information

2014 Inlet Rehab Project II Various Locations

2014 Inlet Rehab Project II Various Locations 2014 Inlet Rehab Project II Various Locations in the City of Sioux Falls, South Dakota Bid Request No. 14-1078 Prepared by: Engineering Division 224 West 9 th Street Sioux Falls, SD 57104 TABLE OF CONTENTS

More information

Developer s/consultants Field Services Guidelines

Developer s/consultants Field Services Guidelines Developer s/consultants Field Services Guidelines 2007 Engineering and Works Department DEVELOPER S/CONSULTANT S FIELD SERVICES GUIDELINES Fourth Electronic Edition February 2007 STATEMENT OF COMPLETION

More information

MISSISSIPPI STATE UNIVERSITY Office of Planning Design and Construction Administration

MISSISSIPPI STATE UNIVERSITY Office of Planning Design and Construction Administration SECTION 01 311 NETWORK ANALYSIS SCHEDULE Part 1.1 DESCRIPTION A. Scope: Provide projected network analysis schedules for the entire Work and revise periodically. This type of schedule is acceptable for

More information

Table 2-1: Elements of the Project Management Plan

Table 2-1: Elements of the Project Management Plan 2 PROJECT MANAGEMENT [NTA: DB Project Management requirements drop off at Project Opening and the O&M management requirements start. In Book 2A address projects that have periods of no DB or O&M Phase

More information

CPM Scheduling with Primavera Unifier

CPM Scheduling with Primavera Unifier CPM Scheduling with Primavera Unifier Don McNatty, PSP March 26, 2014 2014 Technical Webinar Series Thank you for joining today s technical webinar Mute all call in phones are automatically muted in order

More information

MONTHLY PROJECT CONSTRUCTION PROGRESS REPORT #5

MONTHLY PROJECT CONSTRUCTION PROGRESS REPORT #5 Rendering Provided by McKissick Associates MONTHLY PROJECT CONSTRUCTION PROGRESS REPORT #5 Additions and Alterations to Williamsport Area Middle School Williamsport Area School District 17 July 2012 Geo-Thermal

More information

Project Engineers and Supervisors Conference. CPM Scheduling

Project Engineers and Supervisors Conference. CPM Scheduling Project Engineers and Supervisors Conference March 15 th and 16 th 2010 CPM Scheduling Prepared and Presented By Project Engineers and Supervisors Conference Benefits of CPM Scheduling Lessons Learned

More information

GUIDE TO CREATING A CAPITAL CAMPAIGN PLAN: CONTENTS

GUIDE TO CREATING A CAPITAL CAMPAIGN PLAN: CONTENTS GUIDE TO CREATING A CAPITAL CAMPAIGN PLAN: CONTENTS NOTE (9-17-10): This Guide wasn t designed as a template for a capital campaign plan. It was originally created as a tool and proposal attachment for

More information

[UNIFIER USER MANUAL]

[UNIFIER USER MANUAL] 2015 [UNIFIER USER MANUAL] This manual is intended to provide HRSD commissioned Engineers and Contractors guidance on using the Unifier Enterprise Project Management System TABLE OF CONTENTS 1. UNIFIER

More information

Case 2:08-cv-02463-ABC-E Document 1-4 Filed 04/15/2008 Page 1 of 138. Exhibit 8

Case 2:08-cv-02463-ABC-E Document 1-4 Filed 04/15/2008 Page 1 of 138. Exhibit 8 Case 2:08-cv-02463-ABC-E Document 1-4 Filed 04/15/2008 Page 1 of 138 Exhibit 8 Case 2:08-cv-02463-ABC-E Document 1-4 Filed 04/15/2008 Page 2 of 138 Domain Name: CELLULARVERISON.COM Updated Date: 12-dec-2007

More information

Region of Waterloo Stage 1 Light Rail Transit Project. Design and Construction Performance Output Specifications Article 19 Project Schedule

Region of Waterloo Stage 1 Light Rail Transit Project. Design and Construction Performance Output Specifications Article 19 Project Schedule Region of Waterloo Stage 1 Light Rail Transit Project Design and Construction Performance Output Specifications Article 19 Project Schedule Table of Contents 19.1 General Requirements... 19-1 19.2 Project

More information

The work breakdown structure can be illustrated in a block diagram:

The work breakdown structure can be illustrated in a block diagram: 1 Project Management Tools for Project Management Work Breakdown Structure A complex project is made manageable by first breaking it down into individual components in a hierarchical structure, known as

More information

Develop Project Charter. Develop Project Management Plan

Develop Project Charter. Develop Project Management Plan Develop Charter Develop Charter is the process of developing documentation that formally authorizes a project or a phase. The documentation includes initial requirements that satisfy stakeholder needs

More information

The CM Perspective. Preconstruction Phase

The CM Perspective. Preconstruction Phase The CM Perspective The Elements of Project Management Preconstruction Phase Preconstruction: Setting the Project Up to Succeed Project Plan Critical Milestones Define all major deadlines and critical dates

More information

Guidelines for Accessing and Using the VDOT Scheduling Application (Primavera P6)

Guidelines for Accessing and Using the VDOT Scheduling Application (Primavera P6) Guidelines for Accessing and Using the VDOT Scheduling Application (Primavera P6) CONSTRUCTION DIVISION (SCHEDULING & CONTRACTS) 1. INTRODUCTION To establish standards and consistent scheduling practices

More information

Importance of Project Schedules. matter what happens on a project. projects, especially during the second half of projects

Importance of Project Schedules. matter what happens on a project. projects, especially during the second half of projects Project Time Management Chapter 6 Importance of Project Schedules Managers often cite delivering projects on time as one of their biggest challenges Time has the least amount of flexibility; it passes

More information

MnDOT Project Management Office Presents: Schedule Float. Presenter: Jonathan McNatty, PSP Senior Schedule Consultant DRMcNatty & Associates, Inc.

MnDOT Project Management Office Presents: Schedule Float. Presenter: Jonathan McNatty, PSP Senior Schedule Consultant DRMcNatty & Associates, Inc. MnDOT Project Management Office Presents: Schedule Float Presenter: Jonathan McNatty, PSP Senior Schedule Consultant DRMcNatty & Associates, Inc. Housekeeping Items Lines will be muted during the webinar

More information

REQUEST FOR PROPOSAL FOR PROFESSIONAL SERVICES (PS-0748-A) Appendix 1 Project Information. PS-0748-A Page 1 5/4/2016 Appendix 1

REQUEST FOR PROPOSAL FOR PROFESSIONAL SERVICES (PS-0748-A) Appendix 1 Project Information. PS-0748-A Page 1 5/4/2016 Appendix 1 REQUEST FOR PROPOSAL FOR PROFESSIONAL SERVICES (PS-0748-A) Project Information PS-0748-A Page 1 5/4/2016 Table of Contents Project Budget Worksheet Program Plan Project Location (Site Plan) Scope of Services

More information

Earned Value Management Tutorial Module 8: Reporting. Prepared by:

Earned Value Management Tutorial Module 8: Reporting. Prepared by: Earned Value Management Tutorial Module 8: Reporting Prepared by: Module 8: Government Required Reports Welcome to Module 8. The objective of this module is to introduce you to Government required reports.

More information

CD i -STREETS- Detail #

CD i -STREETS- Detail # -STREETS- Detail # 3000 Vertical Curb, Gutter and Sidewalk 3010 Low-Profile Curb, Gutter and Sidewalk 3020 Rolled Curb, Gutter and Sidewalk 3030 Separated Sidewalk, Curb & Gutter 3040 Sidewalk Staged Construction

More information

Manchester City Council Report for Information. Managing Attendance (Real Time Absence Reporting)

Manchester City Council Report for Information. Managing Attendance (Real Time Absence Reporting) Manchester City Council Report for Information Report to: Subject: Overview and Scrutiny Human Resources Subgroup - 25 January 2011 Managing Attendance (Real Time Absence Reporting) Report of: Assistant

More information

Section 100 Contractor Quality Control Program

Section 100 Contractor Quality Control Program 7/21/2014 AC 150/5370-10G Section 100 Contractor Quality Control Program 100-01 General. When the specification requires a Contractor Quality Control Program, the Contractor shall establish, provide, and

More information

Accounting System. Page 1 of 9

Accounting System. Page 1 of 9 Page 1 of 9 Accounting System In support of program management and Earned Value Management, the accounting system must be able to relate costs incurred to work accomplished. Not all accounting systems

More information

Project Management Planning

Project Management Planning Overview of Resource Planning Every organization has a limited number of resources to perform tasks. A project manager's primary role is to find a way to successfully execute a project within these resource

More information

EXHIBIT A SCOPE OF SERVICES CONSTRUCTION MANAGEMENT TEAM POSITIONS AND REQUIREMENTS

EXHIBIT A SCOPE OF SERVICES CONSTRUCTION MANAGEMENT TEAM POSITIONS AND REQUIREMENTS EXHIBIT A SCOPE OF SERVICES CONSTRUCTION MANAGEMENT TEAM POSITIONS AND REQUIREMENTS 1.0 SCOPE OF SERVICES 1.1 General Information LAUSD requires construction management services to manage and expedite

More information

SMALL GAS OPERATOR OPERATION AND MAINTENANCE PLAN

SMALL GAS OPERATOR OPERATION AND MAINTENANCE PLAN SMALL GAS OPERATOR OPERATION AND MAINTENANCE PLAN Facility Name: Address: QUALIFIED PERSONNEL All tasks shall be completed by a person that is qualified to that task (see operators qualification of individuals

More information

Resource Management Spreadsheet Capabilities. Stuart Dixon Resource Manager

Resource Management Spreadsheet Capabilities. Stuart Dixon Resource Manager Resource Management Spreadsheet Capabilities Stuart Dixon Resource Manager Purpose Single view of resource data Shows rolling demand vs supply for 14 months, 2 months back, current month, and 11 forward

More information

Academic Calendars. Term I (20081) Term II (20082) Term III (20083) Weekend College. International Student Admission Deadlines

Academic Calendars. Term I (20081) Term II (20082) Term III (20083) Weekend College. International Student Admission Deadlines Academic Calendars Term I (20081) Term II (20082) Academic Calendars Term III (20083) Weekend College International Student Admission Deadlines Final Examination Schedule Broward Community College Catalog

More information

DESCRIPTION OF WORK:

DESCRIPTION OF WORK: DEPARTMENT OF PUBLIC WORKS COUNTY OF HENRICO P.O. BOX 27032 RICHMOND, VIRGINIA 23273 PERMIT NO. One (1) copy of application and four (4) copies of plans are hereby made to the Director of Public Works

More information

Dashboards and Reporting for Program Management

Dashboards and Reporting for Program Management MnDOT Project Management Office Presents: Dashboards and Reporting for Program Management Presenter: Jonathan McNatty Senior Schedule Consultant DRMcNatty & Associates, Inc. Housekeeping Items Lines will

More information

JAGAN RAO ADELAIDE, TUESDAY, 3 DECEMBER 2013

JAGAN RAO ADELAIDE, TUESDAY, 3 DECEMBER 2013 JAGAN RAO ADELAIDE, TUESDAY, 3 DECEMBER 2013 Relate to this? Outline 1. Safety & Housekeeping 2. Aim 3. Introduction SKM and Jagan Rao 4. Project Controls Overview 5. Cost Estimating 6. Planning & Scheduling

More information