IMO Submission to Electricity Market Review Discussion Paper. Available for Public Review September 2014

Size: px
Start display at page:

Download "IMO Submission to Electricity Market Review Discussion Paper. Available for Public Review September 2014"

Transcription

1

2

3 IMO Submission to Electricity Market Review Discussion Paper Available for Public Review September 2014

4 Executive Summary The Independent Market Operator (IMO) administers, operates and supports the evolution of the Wholesale Electricity Market (WEM) and Gas Services Information regime in Western Australia (WA). The IMO s primary purpose under both these regimes is to promote competition, transparency and accountability in the WA energy sector. These principles underpin the effectiveness and efficiency of competitive electricity markets, providing price signals for Market Participants and consumers to make optimal investment decisions, manage risks and minimise the long-term cost of energy to consumers. They are also fundamental tenets of the Wholesale Market Objectives, which have guided the evolution of the WEM and the IMO s operational role. Given its background, the IMO is well placed to comment on the key issues and questions raised in the Electricity Market Review (EMR). The IMO considers the EMR as an opportunity to address the root causes of the challenges and inefficiencies that exist in the WA energy industry, while addressing the structural deficiencies and policy gaps. The IMO understands that the EMR Discussion Paper has been designed to elicit comments, feedback and additional analyses to inform the government s decisions in relation to electricity market reform in WA. This submission provides the IMO s views on the reforms that affect the design, operation and administration of the WEM. The IMO has also taken the opportunity to provide further information with respect to some of the assumptions used to inform the reform options, particularly where the IMO has reached different conclusions than those presented. Encouraging competition The IMO supports the Discussion Paper s preference to resolve a number of challenges through increasing the level of competition (e.g. through the introduction of full retail contestability (FRC) and structural separation of Synergy). Encouraging competition is a fundamental tenet of the Wholesale Market Objectives and electricity markets elsewhere, with numerous studies quantifying the benefits of competition. Synergy s wholesale cost of energy The EMR has been driven by the government s need to reduce the large and growing subsidies to government-owned electricity utilities particularly the Tariff Adjustment Payment to Synergy which will total $495 million in The IMO agrees that ongoing subsidisation of Synergy is undesirable and inefficient. The Discussion Paper presents Synergy s cost of wholesale energy to residential customers at more than 18c/kWh. This is compared with an average cost of energy and capacity traded through the WEM of 12c/kWh. The Discussion Paper notes that Synergy s wholesale energy cost is the most significant driver of the growing government subsidy. This inefficient cost is, quite rightly, a key focus of the Discussion Paper. However, the IMO notes that little is Submission to Electricity Market Review Discussion Paper Page 2 of 121

5 provided in the way of supporting information to allow readers to understand the root causes of Synergy s high wholesale energy cost. The Discussion Paper states that this high cost is driven by contract prices and transfer prices across Synergy [that appear] unrelated to market outcomes (page 16) and postulates that Synergy has procured more energy than it required at prices exceeding market prices in the WEM. The Discussion Paper further suggests that the combination of Synergy s protected position in the retail market, its franchise customer base and its subsidy from government is likely to lead to inefficient management of Synergy s portfolio of generation and wholesale contracts, resulting in inflated costs. The IMO notes that generation investment and wholesale power contracts are typically, by their nature, long-term and are likely to continue to drive Synergy s cost of wholesale energy and the need for government subsidies for some time. Given these underlying drivers of Synergy s excessive cost of wholesale energy, which appear to be unrelated to market outcomes, the IMO considers it unlikely that structural and market reform alone would reduce Synergy s cost of wholesale energy to serve its residential customers and therefore reduce the government s subsidy burden. Having acknowledged that Synergy s high cost is a result of a combination of its contract portfolio and high generation costs (reflected in transfer prices), the IMO recommends that the EMR team carefully consider how Synergy s contracts and generation portfolio will be treated in the future particularly if Synergy is structurally separated or FRC is introduced as these will impede Synergy s ability to compete. Wholesale electricity costs in the WEM The Discussion Paper includes a number of price comparisons between Synergy s cost of wholesale energy to residential customers, WEM electricity costs and electricity costs in the National Energy Market (NEM). However, it does not include the necessary contextual information about the different characteristics of the prices and markets to allow any meaningful conclusions. For example: Wholesale market prices are set by the marginal generator, which is predominantly brown coal-fired generation in the NEM. By contrast, the marginal generator in the WEM is typically gas-fired, with higher short run marginal costs. The South West interconnected system (SWIS) faces significantly higher risks to system reliability than other markets, resulting from the volatility of demand in the SWIS, the relatively small size of the system and the lack of interconnection with neighbouring markets. As the Discussion Paper acknowledges (page 47), this has led to the WEM having a more stringent reliability standard than the NEM, which has significant implications for the cost of electricity. The IMO notes that the EMR Steering Committee, at the stakeholder workshop on 21 August 2014, highlighted the National Electricity Market of Singapore, amongst others (New Zealand and Texas), as a more appropriate comparative market to the WEM. Singapore has an energy-only market that is small, isolated (no material Submission to Electricity Market Review Discussion Paper Page 3 of 121

6 interconnection) and where the marginal generator is typically gas-fired. The average wholesale price in Singapore in 2013 was S$178/MWh (A$147/MWh), which is considerably higher than the WEM average of A$120/MWh (12c/kWh). The Discussion Paper has provided price comparisons based primarily on historic prices, even though there may be material future cost savings that are likely to be factored into WEM outcomes. These include a Reserve Capacity cost reduction of approximately $18/MWh in and a further $6/MWh in ($24/MWh in total) due to changes in the methodology used to calculate the Maximum Reserve Capacity Price (MRCP) and the retirement of the Kwinana C generation units. This capacity cost reduction combined with an average energy cost of 6c/kWh ($60/MWh, consistent with the average Balancing Price in ) would reduce the average cost of energy and capacity to below 10c/kWh by Excess capacity costs The Reserve Capacity Mechanism (RCM) has provided an investment regime that has encouraged significant growth in capacity, seeing the WEM transition from a capacity shortfall position in 2006 to a position of excess capacity today. However, it must be noted that the RCM was not the primary driver for the majority of the new investment, with more significant drivers including commitments made either before or around the time that the WEM commenced, renewable energy policies and government policy decisions. The fact that numerous markets with varying market design, including the energy-only NEM, are currently experiencing similar levels of excess capacity provides further evidence that the design of the WEM is unlikely to be a key contributor to the excess capacity situation. Recent forecasts suggest that the NEM does not require new generation investment in any of its regions for at least ten years, and by more than 4,500 MW of generation capacity could still be withdrawn from the NEM without affecting supply adequacy 1. The IMO notes the significant commentary on the additional cost imposed on consumers and taxpayers as a result of excess capacity. The IMO acknowledges that excess capacity has had a financial impact on the market, but considers that the Discussion Paper materially over-estimates this impact the IMO estimates the annual cost of excess capacity to the WEM in to be $45 million (one third of which would be allocated to Synergy s residential customers). Over the past two years the IMO has been working with Market Participants and other stakeholders on reforms to improve the RCM, in particular improving the Reserve Capacity Price (RCP) methodology to ensure it is more responsive to undersupply and oversupply conditions. The IMO recommends that considerably more analysis of the drivers of excess capacity be undertaken, including the extent to which previous investment and contracting decisions are likely to have been driven by expectations of higher electricity demand, before the EMR draws conclusions or makes recommendations. The IMO considers that, in particular, the exposure of Synergy s residential customers to high wholesale energy costs is likely to be driven by a number of other factors, including: 1 Media Release, No New Power Generation Needed for next 10 Years, Australian Energy Market Operator, 8 August 2014, available at accessed 18 September Submission to Electricity Market Review Discussion Paper Page 4 of 121

7 1. the significant increase in Western Power s transmission connection cost estimates which increased the RCP in and but roll off in October 2014; 2. Synergy buying more energy (and possibly capacity) from Verve Energy than required as a result of the Replacement Vesting Contract, which has now fallen away with the merger of Synergy and Verve Energy (although the financial impact has not); 3. the disproportionate exposure of Synergy s non-contestable residential customers to capacity costs contestable customers have responded to peak-related price signals incorporated in competitive tariffs while non-contestable residential customers receive no such price signal and now bear a greater share of the cost; and 4. a possible cross-subsidy of Synergy s contestable customers by its residential customers to make Synergy s competitive offerings comparable with those of private retailers. The IMO cautions that attributing the cause of Synergy s high cost of wholesale energy to excess capacity would seem too simplistic and, by overlooking root causes of the problem, likely to lead to incorrect conclusions and ineffective reform recommendations. Allocation of risks between generators and customers The existence of the RCM moderates the risks for both generators and customers in the WEM. This was by design, as an energy-only market particularly in a small, isolated and weather-sensitive electricity market can deliver very punitive outcomes to Market Participants and/or consumers. The Discussion Paper has not considered the impact of under-investment in capacity on risk allocation between generators and customers. This must be explored before any conclusions are drawn and recommendations made. While the RCM was designed to moderate the risks for both generators and customers in the WEM, it should be noted that a much greater influence on the allocation of market risk between Synergy and the independent power producers has been the terms and conditions of bilateral contracts. Anecdotal evidence suggests Synergy may have taken on a disproportionate level of market risk from its counterparties, through long-term contracts that are likely to continue to drive Synergy s cost of wholesale energy and the need for government subsidies for some time. The IMO therefore cautions that it is unlikely that modifications to the WEM design would materially reduce Synergy s exposure to market risk in the short to medium term. It should also be noted that Synergy s current dominant market share would subdue any interest in the development of a financial hedge market. Even when similar dominant market positions were resolved in Singapore and New Zealand (the EMR s benchmark markets), neither was easily able to establish a liquid financial hedge market. Over time, New Zealand has been successful in developing financial hedge trading, with the New Zealand Electricity Authority (NZEA) encouraging market-making from the six largest gentailers. The IMO notes Submission to Electricity Market Review Discussion Paper Page 5 of 121

8 that the NZEA s encouragement largely consists of the threat of mandatory regulation as a means for promoting voluntary market-making 2. Industry structure and regulation: common reform options The IMO supports many of the reforms considered in the Discussion Paper on the basis that they have the potential to provide material improvements in economic efficiency, encourage private sector investment and deliver significant long-term economic benefits to WA. In particular, the IMO encourages further development of the following reform options: The structural separation of Synergy would reduce the current dominance of Synergy, which remains a barrier to: o effective competition in the WEM, requiring material regulatory measures to mitigate its market power that are a suboptimal alternative to competition; and o new entrants, investors and financiers. The introduction of FRC would lead to improved economic efficiency through: o competition between retailers to deliver lower priced electricity to consumers; and o the introduction of tariffs that reflect the underlying costs of service so that consumers are able to respond appropriately to electricity price signals. The transition to a constrained network access model the assumption that the SWIS is unconstrained is no longer valid. The introduction of a constrained network access model would reduce long-term capital expenditure and significantly improve equity between incumbent and new entrants to the WEM. Without the adoption of a constrained network access model and a market redesign to support this change, the WEM s price-based dispatch prioritisation will increasingly be overridden based on the quality of network contracts, resulting in inefficient outcomes. The introduction of a gas supply hub would establish a transparent and consolidated domestic wholesale gas market, which the IMO considers is the logical next step in the development of the domestic gas sector in WA. Reliability standard The IMO supports informed debate on the appropriate reliability standard for setting the quantity of capacity required in the market. The IMO notes that the current WEM reliability standard (based on a reserve margin above the one-in-10-year peak demand forecast) requires more than 700 MW of additional capacity compared with the NEM reliability standard (which limits unserved energy to 0.002% of annual demand). Provided the community s expectations for reliability continued to be met or managed, a lowering of the reliability standard has the potential to materially reduce the long-term cost of electricity and improve economic efficiency. The IMO notes that a lower reliability standard, coupled with a more responsive RCP methodology, would significantly lower capacity costs. 2 The letter sent to the six largest gentailers, dated 5 June 2014 (available at accessed 19 September 2014) states that the NZEA is starting work on the mandatory approach now to minimise lost time if voluntary measures prove unsuccessful. Submission to Electricity Market Review Discussion Paper Page 6 of 121

9 The IMO recommends caution when considering lowering the reliability standard. Given the reliability risks faced by the SWIS, the adoption of the NEM reliability standard would run the risk of load shedding occurring at system peak, on the hottest summer afternoon. This may be regarded as an undesirable policy outcome. The reliability standard is a key policy setting for WA that materially influences the cost and reliability of electricity for consumers. The WEM reliability standard is currently contained in the Market Rules and is subject to a consultative five-yearly review by the IMO. The IMO considers that such an important policy setting is well beyond the scope of a market operator, and considers there may be merit in the suggestion in the Discussion Paper to establish a Reliability Panel with oversight of reliability standards in the WEM. Option One: Amend the current market mechanism The IMO considers that there are significant opportunities to evolve the current WEM design to deliver benefits for consumers. In particular, the IMO considers that changes to the RCM are required. Potential changes to the RCM In 2011, the IMO commenced investigations into improving the responsiveness of the RCP to market conditions. A range of capacity mechanism designs were considered, including a capacity auction. The IMO acknowledges that capacity auctions offer the appeal of allowing a competitive market to set the price; however, advice received indicated that other electricity markets with capacity auctions had difficulty with designing an effective auction mechanism. Capacity auctions have required a number of administrative measures to mitigate risks related to price volatility and the exercise of market power, needing judgement to be exercised in setting key design parameters not dissimilar to the judgement required in the current administered RCP formula. These judgements must consider the trade-offs between accuracy and investor certainty, and between cost and reliability. Capacity auctions have typically worked better in larger, more competitively structured markets. The current dominance of Synergy represents a significant impediment to the introduction of a capacity auction. Any material changes to the RCM, in particular the introduction of an auction, would likely result in a large value shift between some Market Participants. The IMO suggests that considerable care would be required to manage such a transition. Consequently, it is uncertain whether an auction-based RCM would deliver sufficient benefits to outweigh the risks it would introduce. Rather than immediately changing to an auction-based RCM, the IMO strongly recommends proposed improvements to the administered RCP formula, at least as an initial step, to increase its responsiveness to market conditions and improve incentives in relation to bilateral contracting. A decision to move toward an auction-based RCM could then be more fully considered as part of a longer-term road map. Improvements to the administered RCP formula could be implemented relatively swiftly under the current industry structure (prior to structural separation of Synergy) and would Submission to Electricity Market Review Discussion Paper Page 7 of 121

10 avoid the significant risks and transitional costs of immediately moving to an auction-based RCM while achieving similar outcomes. Making the WEM more efficient The IMO supports the recommendations to: introduce facility-based bidding for all Market Participants; reduce gate closure for the Balancing and Load Following Service (LFAS) markets; introduce co-optimisation of energy and Ancillary Services, which could include competitive markets for Spinning Reserve and Load Rejection Reserve Services; and review the risk-management tools for Market Participants, including the STEM. The IMO considers that these changes are broadly consistent with its Market Rules Evolution Plan 3. The IMO notes that there would be significant benefit in a coordinated implementation of these changes with a constrained network access model. Market governance The Discussion Paper notes that the current structure under which the IMO is both the rule administrator and market operator results in a perceived conflict of interest. This shared responsibility is consistent with the governance structure recommended by the Council of Australian Governments 2002 Parer Review and exists in numerous other electricity markets, reflecting the economies of scope between the functions. The IMO considers there are a number of checks and balances in place to ensure the IMO s activities and decision making functions are performed in a manner which is independent and consistent with the Wholesale Market Objectives. The IMO considers that the delegation of the rule administration function to either the Public Utilities Office (PUO) or Economic Regulation Authority (ERA) would result in other more substantial conflicts with their policy and oversight roles, including the PUO s responsibilities for advising the shareholding Minister in relation to the government-owned electricity companies. The IMO also notes that it has developed considerable experience and expertise in administering the rule change process for the last eight years. If the EMR team or government remains concerned about any potential conflict of interest, the IMO suggests instead that another body such as a Rule Change Panel could be established to approve rule changes. This panel could comprise the Deputy Director General of the PUO, the Chair of the ERA and the Chair of the IMO. Option Two: Adoption of the NEM energy-only market For some time there has been an ideological debate among electricity market commentators and academics regarding the relative merits of electricity market designs that trade capacity and energy as opposed to markets that trade only energy. Each market design relies on very different price signals for ensuring there is sufficient installed capacity to meet maximum system demand. 3 Available at accessed 12 September Submission to Electricity Market Review Discussion Paper Page 8 of 121

11 Energy-only markets rely on a high energy prices or price spikes to induce sufficient capacity. Energy and capacity markets rely on capacity requirements, a reliable income stream and associated incentives/penalties to induce sufficient capacity. In theory, an energy-only market provides an optimal level of capacity investment up to the level of reliability for which Market Participants or consumers are prepared to pay. While this may be theoretically appealing, particularly at a time when the WEM has excess capacity, energy-only markets are untenable if policy makers and governments are not able to tolerate potential public backlash in response to significant price spikes or the rolling blackouts associated with load-shed events. 4 Energy-only markets also require high levels of competition in both the wholesale and retail markets to protect against the abuse of market power. Energy-only markets rely on the risk of sustained high energy prices to signal the need for investment in new capacity. However, this requires a relatively reliable and stable peak demand profile for the price signal to endure long enough and be punitive enough to prompt new investment. WA is characterised by very infrequent and extreme weather events that increase peak demand considerably. Given this peak load profile, an extremely high energy price cap would be required for an energy-only market to be successful in WA. If a sufficiently high energy price cap was not adopted, Market Participants may view extreme weather events as unlikely to be commercially viable to service. The IMO considers that a liquid hedge market would be necessary to allow Market Participants to mitigate the increased price volatility in an energy-only market. As discussed above, developing a liquid hedge market has proven difficult in small energy-only markets. The IMO notes that the EMR does not consider the establishment of a stand-alone, energy-only market in the WEM. The IMO agrees that, if it was decided to move to an energy-only market, it would be more efficient for WA to join the NEM as an unconnected region, rather than to design a bespoke energy-only market requiring its own governance and institutions. The IMO advises that any decision to transition to the NEM should only be made after careful consideration of the potential impact and risks to system security, reliability of supply and market outcomes associated with an energy-only market. Lastly, it should be noted that the NEM, like the WEM, is facing significant challenges and uncertainty as it continues to evolve. Challenges faced by the NEM include falling demand, the continuing growth in embedded generation, the desire to improve demand side participation and the management of network congestion. 4 Capacity Markets Lessons Learned from the First Decade, Spees, Newell and Pfeifenberger, published by the International Association of Energy Economics in Economics of Energy and Environmental Policy, Volume 2, Issue 2, September Submission to Electricity Market Review Discussion Paper Page 9 of 121

12 Conclusion The EMR has highlighted a number of reform options that have the potential to deliver benefits to WA electricity consumers. However, some of these options may expose WA Market Participants and electricity consumers to significantly heightened risks. With careful consideration of the recommendations and effective implementation, WA should have a clear, long-term evolutionary road map for the energy sector that provides increased certainty for all stakeholders. The IMO will continue to work with the EMR team to assist further with analysis and the appropriate consideration of reform options. The IMO looks forward to the opportunity to assist the EMR team and government to implement the reforms adopted by the government. Submission to Electricity Market Review Discussion Paper Page 10 of 121

13 Table of Contents Executive Summary... 2 Table of Contents Market evolution since commencement of the WEM The IMO s role in evolution of the WEM Energy market reform Reserve Capacity Mechanism performance and proposed reforms MRCP review Demand forecasting review Reserve Capacity Mechanism Working Group (RCMWG) High-level comments on analysis and conclusions in the Discussion Paper Subsidisation of Synergy is undesirable, but projections not transparent Allocation of risks between generators and customers Synergy s high cost to serve reflects a problem of contracts and transfer pricing Unprecedented shifts in market expectations Benchmarking of costs against the NEM may be unrealistic Cost of excess capacity is over-estimated and its causes have not been analysed How much excess capacity do we have? Drivers for development of excess capacity in the WEM Financial impact of excess capacity Key policy issues not covered by the Discussion Paper Reliability standard Tariff structures Reference material not made available Consideration of reform options in Discussion Paper Industry structure and regulation: Common reform options Structural separation of Synergy Full retail contestability Constrained network access model Development of a gas supply hub in WA Merits and risks of energy-only and energy-plus-capacity market designs Market design options in the specific context of the WEM WEM reforms recommended by the IMO Move from administratively-derived capacity price to an auction mechanism Energy market improvements Institutional arrangements IMO s responses to the Discussion Questions Market structure Retail markets Wholesale Electricity Market Networks Submission to Electricity Market Review Discussion Paper Page 11 of 121

14 4.5. Fuel Institutional arrangements Summary Appendix A. About the IMO and this submission Appendix B. Comments on data and analysis in the EMR Discussion Paper Appendix C. Case Study Ability of extreme weather events to drive new investment in New Zealand Appendix D. Analysis of market price cap in energy-only market (ROAM Consulting) Submission to Electricity Market Review Discussion Paper Page 12 of 121

15 1. Market evolution since commencement of the WEM This chapter describes the significant evolutionary steps that have been taken since the commencement of the Wholesale Electricity Market (WEM) in This chapter is intended to supplement the historical information in Chapter 2 of the Electricity Market Review (EMR) Discussion Paper published on 13 August 2014 (Discussion Paper), which focused on changes to the industry structure but did not include information on the evolution of the WEM. The IMO considers that this information is valuable for the development of reform options and has drawn on this history in responding to the key issues highlighted in the Discussion Paper. Key points The introduction of the competitive Balancing Market in 2012, along with the competitive Load Following Service (LFAS) Market, was the first major reform to the WEM energy market since its commencement. The competitive Balancing Market is a gross dispatch pool, which determines the physical dispatch of Synergy and independent power producer (IPP) generators all available generators are required to offer their generation to meet demand in each Trading Interval. The competitive Balancing Market was found to have delivered benefits of $14.6 million in its first year of operation. The Reserve Capacity Mechanism (RCM) has provided an investment regime that has encouraged significant growth in capacity. However, it must be noted that the RCM was not the primary driver for the majority of the new investment more significant drivers include commitments and procurement decisions made either before or around the time that the WEM commenced (e.g. Western Power procurement and the Displacement Mechanism), renewable energy policies and government policy decisions (e.g. Muja AB). The WEM has transitioned from a capacity shortfall position in 2006 to a position of excess capacity today. This growth in capacity has ensured that growing energy needs were met during a period of sustained economic growth and has increased competition in the STEM and Balancing Market. More recently, the entry of new capacity has slowed considerably, with no material entry of new capacity for the last three capacity cycles. This slowing has been influenced by: o lower demand forecasts, influenced by refinements to block load forecasting in the last three years; and o the imminent reduction in capacity prices as a result of the Maximum Reserve Capacity Price (MRCP) review. A major review of the RCM was initiated by the IMO Board in September 2010 and continued by the RCM Working Group (RCMWG). The review identified that the current Reserve Capacity Price (RCP) formula does not respond sufficiently to market conditions and creates asymmetrical incentives in relation to bilateral contracting. The review recommended: o an improvement to the RCP formula to address issues with the current RCM design; o a dynamic Reserve Capacity refund regime to align incentives with system conditions; and o harmonisation of the treatment of demand-side and supply-side capacity providers. Significant reforms to the wholesale market require a considerable amount of time in the development of the market design, Wholesale Electricity Market Rules (Market Rules) and IT systems. Based on the IMO s experience, Market Participants must be allowed sufficient time to contribute to the design process, to adapt and test their own systems and to adjust contractual arrangements to ensure reforms gain the most efficient outcomes. Submission to Electricity Market Review Discussion Paper Page 13 of 121

16 1.1. The IMO s role in evolution of the WEM The IMO is responsible for developing amendments to, and replacements of, the Market Rules 5. The IMO also convenes the Market Advisory Committee (MAC), which advises the IMO in development of the WEM. These roles provide the IMO with unique insight into the design, operations and evolution of the electricity market in Western Australia (WA). Through these roles, the IMO works with Market Participants and other stakeholders to identify, develop and implement plans for the development and evolution of the WEM and the Market Rules. The IMO develops a Market Rules Evolution Plan (MREP) 6 every three years to identify and prioritise areas of the WEM which require review and further development. This plan draws on issues identified in consultation with industry stakeholders and is then prioritised by the MAC. The MREP guides the IMO s market development activities and informs the IMO s Allowable Revenue submission for the three-year period. The second MREP in 2009 identified the need to introduce greater competition in the energy market and review various aspects of the RCM. This resulted in significant work programmes in the following years, including the Market Evolution Program (MEP) and the RCMWG, which are described in sections 1.2 and respectively Energy market reform The Discussion Paper notes that Verve Energy was originally required to be the default provider of Balancing and Ancillary Services in the WEM. These arrangements required Verve Energy facilities to be dispatched to account for the differences between Market Participants Resource Plans (which account for bilateral contracts, self-supply and STEM trades) and actual system demand in real time. With Verve Energy providing 89 per cent of capacity at market commencement, this arrangement provided simplicity in the initial market design. However, as noted in the Discussion Paper, this was intended to be a transitional arrangement. By the end of 2009, Verve Energy s share of capacity had fallen to just above 60 per cent. A desire for greater competition, particularly the establishment of a competitive Balancing Market, was expressed by Market Participants in the development of the 2009 MREP. The Verve Energy Review commissioned by government to assess why Verve Energy was in a loss-making position critiqued the market similarly, highlighting the lack of competition in aspects of the WEM. In particular, the Verve Energy Review identified that responsibility for providing Balancing services had become increasingly challenging for Verve Energy as its market share had declined materially with the entry of IPPs into the market. The establishment of a competitive Balancing Market formed a central part of the MEP, which also included the establishment of a competitive market for LFAS. 5 Clause 2.1.2(i) of the Market Rules. 6 Available at accessed 12 September Submission to Electricity Market Review Discussion Paper Page 14 of 121

17 As Figure 1.1 below shows, the development of the MEP took place over a number of years. It commenced with the MREP in 2009 and included the establishment of the Rules Development and Implementation Working Group to develop the design of the new markets and the requisite amendments to the Market Rules. Following an extended period of market trials, the new markets went live in July 2012 and then became fully operational in December Figure 1.1: Timeline for developing the Market Evolution Program Market Evolution Plan established June 2009 MEP Design Process 2010 Work plan approved for Market Rules Evolution Plan Oct 2009 Amended Rules Approved by Minister for Energy 23 March 2012 Amended Rules and Regulations commenced 1 July 2012 Sapere s 2 nd report shows benefits estimated at $14.6m Oct Verve Energy/ Oates Review Completed Aug 2009 Trading System to Market Trial Dec 2011 Trading System to Production April 2012 Trading System Go Live on 1 July 2012 MEP Transition Completed on 5 Dec 2012 The MEP demonstrates that for significant reforms to the wholesale market to be successful, a considerable amount of time is required for development of the market design, Market Rules and IT systems. Market Participants must also be allowed time to contribute to the design process, to adapt and test their own systems and potentially to adjust contractual arrangements. There appears to be some confusion in the Discussion Paper about the nature and role of the Balancing Market. Contrary to the assertion on page 16 of the Discussion Paper, it is not the case that the Balancing Market s purpose is to account for the differences between Market Participants Resource Plans and actual outcomes. Since July 2012, Resource Plans no longer guide the physical dispatch of generation. The current Balancing Market is a gross energy pool which determines the physical dispatch of all Synergy and IPP generators. All generators are required to bid their available capacity into the market in near real-time. Synergy offers its capacity on a portfolio basis, meaning that it must determine an appropriate, economically efficient merit order within its portfolio. The IMO compiles a Balancing Merit Order (BMO) for each half hourly Trading Interval, stacking bids from the lowest price to the highest price. Then, on the basis of the BMO, 7 The full implementation at the end of the July-November 2012 transition period reduced gate closure from six hours to two hours and provided expanded submission flexibility for Market Participants. Submission to Electricity Market Review Discussion Paper Page 15 of 121

18 System Management dispatches facilities (and the Synergy portfolio) to meet the system load in real time (i.e. dispatches the cheapest generation first). This aims to minimise the cost of energy to customers in the SWIS by enabling the lowest-cost generation to be dispatched in every Trading Interval. There also appears to be some confusion about the distinction between a gross pool and a net pool. In terms of the dispatch of energy, a gross pool is one where all energy is bid into and dispatched by the market and priced at the market price. The National Electricity Market (NEM) and the WEM Balancing Market are both examples of gross pools. By contrast, a net pool is one in which generators are only required to bid in energy that has not already been traded under bilateral arrangements. Price caps can be a feature of both gross pools and net pools. While the Balancing Market is a gross dispatch pool, the IMO performs a net settlement in the WEM. Quantities that are covered by hedging tools bilateral contracts and STEM trades are netted off from the gross quantities in the Balancing Market. The principal advantage of the net settlement model is the materially lower level of prudential support that Market Participants must provide to the IMO (due to the lower amount of money cleared through the IMO). The implementation of the Balancing Market on 1 July 2012 coincided with the introduction of the carbon price. Because the Balancing Market provided a means for ensuring the lowest cost dispatch in every Trading Interval, the WEM did not experience a significant increase in prices to reflect carbon costs. Whereas the introduction of the carbon price was estimated to have increased NEM spot prices by $17.70/MWh in the mainland states and $10/MWh in Tasmania 8, the Balancing Price in the WEM only increased by $2.66/MWh from to The IMO engaged the Sapere Research Group (Sapere) to assess the costs and benefits of the MEP prior to its implementation. When Sapere revisited the benefits after 12 months of operation, it found benefits of $14.6 million for the period, up from the estimate of $9.6 million that had been determined prior to implementation 10. The highest priority issues identified in the current MREP 11, covering the period, are aimed at further improvements to the energy market and the extension of competition in the provision of Ancillary Services. The specific items listed in the plan are: improvements to the energy market, including: o reducing Balancing and LFAS gate closures to enable bids to be updated closer to the Trading Interval; o introducing facility-based bidding and dispatch for all Market Participants; and 8 Australian Energy Regulator, State of the Energy Market 2013, page 8, available at accessed 12 September The load-weighted average Balancing Price in (then known as the Marginal Cost Administered Price) was $50.93/MWh. The load-weighted average Balancing Price in was $53.59/MWh. These averages have been calculated from publically available data that can be downloaded from and both accessed 12 September For more information, see the presentations dated 9 October 2013 available at accessed 12 September Available at which should be read with the discussions of the MAC at the October 2013 meeting both accessed 12 September Submission to Electricity Market Review Discussion Paper Page 16 of 121

19 o a range of possible amendments to the STEM, ranging from removing the requirement to submit Resource Plans through to a complete re-design of the STEM to make it more fit for its current purpose, which is now to provide a day-ahead opportunity to manage exposure to Balancing Prices; and the introduction of a market for Spinning Reserve. Prior to the commencement of the EMR, the IMO, in consultation with the MAC, undertook some initial scoping of the improvements to the energy market outlined in the current MREP. However, these market developments have been deferred to enable Market Participants to focus on the EMR. The IMO welcomes the consideration of the above energy market improvements in section 5.2 of the Discussion Paper. In relation to the potential for reform of the STEM, the IMO notes that the introduction of the Balancing Market on 1 July 2012 has redefined the role of the STEM. Whereas the STEM previously determined dispatch outcomes, it now functions much like a day-ahead hedge market for Market Participants to trade around their Net Contract Positions. This change in function has led to Market Participants expressing mixed views as to the usefulness of the STEM in its current form. The IMO welcomes discussion with Market Participants on the value of the current STEM and whether this value would increase if it were reconfigured. The IMO s views on potential energy market improvements are further discussed in section of this submission Reserve Capacity Mechanism performance and proposed reforms The implementation of the WEM occurred against the backdrop of the 2004 blackouts in WA. Capacity inadequacy was identified at that time as a key cause of the load shedding that occurred. At the time that the WEM commenced operation in 2006, the SWIS had a capacity shortage of approximately 200 to 300 MW (based on the reliability standard that was implemented in the initial Market Rules). Even in the summer, continuing growth of peak demand and delays in the commissioning of new generation required Supplementary Reserve Capacity to be contracted to ensure capacity adequacy. However, as a result of a range of measures (see Table 2.3 on page 42), some of which were initiated prior to the WEM s commencement, capacity in the SWIS has grown by more than 70 per cent, from 3,531 MW in to 6,087 MW in Much of this investment was made at a time when it was widely expected that the trend of strong growth in electricity demand would continue, as is discussed in section 2.4 below. This growth in capacity reversed the earlier capacity shortfall and ensured that WA was able to cope with growing energy needs during a period of sustained economic and population growth. While the RCM may not have been the primary driver for the majority of this new investment, it provided a stable regime that accommodated the addition of new capacity when it was required. It is also important to note that the growth of capacity, particularly base load capacity in the early years of the WEM, significantly increased the level of competition in the STEM and the Submission to Electricity Market Review Discussion Paper Page 17 of 121

20 Balancing Market. This is reflected in Figure 3 of the Discussion Paper, which shows that STEM prices reached their lowest point in 2010 following the completion of the Bluewaters and NewGen Kwinana facilities. As discussed in section below, the level of investment has seen the WEM move into an excess capacity position, as has occurred in electricity markets in other developed economies. However, the entry of new capacity has slowed considerably and the number of Capacity Credits in the market will fall over the next two Capacity Years to 5,683 MW in The decline in new capacity is clearly identifiable in Table 1.1, which shows the amount of capacity offered each year during the Expression of Interest (EOI) process and the amount of new capacity that was assigned Capacity Credits in that year. Table 1.1: Capacity offered through EOI process compared to new capacity assigned Capacity Credits Capacity (MW) Capacity offered through EOI 1,192 1,036 1, New capacity assigned Capacity Credits N/A This decline in new capacity investment is consistent with what one would expect in any competitive market in an oversupplied position. In addition, the IMO notes that the design of the RCM, particularly the methodology for allocating capacity costs (the Individual Reserve Capacity Requirement (IRCR) mechanism), has provided an incentive for customers to reduce their demand during system peak demand periods. Reductions in the system peak demand of nearly two per cent have been observed as a result of this market-driven behaviour. This has led to lower demand forecasts, deferring the need for additional capacity investment. Analysis in section 2.3 indicates that this behaviour is dominated by contestable customers who are provided with stronger price signals to reduce their consumption at times of system peak demand, whereas volumetric retail tariffs (such as the A1 tariff) provide no such price signal. The RCM has faced challenges and has evolved to address emerging issues. The IMO notes the impact that a sequence of reviews may have had in slowing investment in new capacity. The following sections provide information about the: review of the MRCP methodology that was completed in 2011; review of demand forecasting processes in 2012; and review of the RCM, including the work of the MAC and RCMWG over 2011 to MRCP review Clause of the Market Rules requires the IMO to review the methodology for setting the MRCP at least once in every five year period. Submission to Electricity Market Review Discussion Paper Page 18 of 121

21 In its 2009 Annual Wholesale Electricity Market Report for the Minister for Energy 12, the Economic Regulation Authority (ERA) noted that the preceding MRCP determination (for the Capacity Year) had elicited a greater level of response through the public submission process than previous determinations. Many of these submissions had expressed concern at the sharp increase in the MRCP, driven particularly by an increase in the estimate of transmission connection costs, which is provided by Western Power. The higher MRCP in resulted in a 41 per cent increase in the RCP for Given these concerns, the ERA recommended that the IMO exercise its option to bring forward the five-yearly methodology review, which the IMO initiated in To assist in undertaking the review, the MAC established the MRCP Working Group (MRCPWG) in 2010 to consider, assess and develop any recommendations for changes to the methodology. The MRCPWG met on ten occasions between May 2010 and June The MRCPWG recommended a number of changes to the MRCP methodology, of which two had a material impact. An independent consultant assisting the MRCPWG identified that the high transmission connection cost estimates provided by Western Power for the and MRCPs were not reflective of the capital contributions actually being charged to project developers that secured connection or were provided with an Access Offer. A revised methodology was developed for estimating transmission connection costs that was based on actual connection costs. This revision reduced the estimated transmission connection cost by 64 per cent and the MRCP by 14 per cent 14. The specification of the reference power station was updated to incorporate an inlet air cooling system, consistent with standard industry practice in the WEM. This has the effect of increasing the Capacity Credit allocation to the facility for a relatively small increase in capital cost, thus reducing the cost per MW. This change reduced the MRCP by a further nine per cent 15. The IMO notes that the high RCPs for the and Capacity Years may have attracted unnecessary investment. However, the review of the MRCP methodology realigned the MRCP with standard industry practice and actual transmission connection costs. Following the implementation of the methodology changes in 2011, the MRCP and RCP reduced by 31 per cent from to This price reduction will take effect in October Available at accessed 12 September The proceedings of the MRCPWG are available at; accessed 12 September IMO, Final Report: Maximum Reserve Capacity Price for the 2014/15 Capacity Year, February 2012, pages 6 (Table 2) and 22. Available at Capacity/imo_final_report_max_reserve_capacity_price_2014_15CB08D52A9766.pdf?sfvrsn=0, accessed 12 September Ibid, page 6 (Table 2). A lower WACC also contributed to the reduction in the MRCP. Submission to Electricity Market Review Discussion Paper Page 19 of 121

Electricity Market Review: Submission to Discussion Paper

Electricity Market Review: Submission to Discussion Paper 06) Economic Regulation Authority OurRef: Contact: D128066 Elizabeth Walters Mr Paul Breslin Steering Committee Chair Electricity Market Review Public Utilities Office Locked Bag 11 Cloisters Square WA

More information

Phase 1 Terms of Reference (Amended May 2014)

Phase 1 Terms of Reference (Amended May 2014) (Amendments are shown in red type) Electricity Market Review Phase 1 Terms of Reference (Amended May 2014) Department of Finance Public Utilities Office January 2014 1. Introduction Regulated retail electricity

More information

Electricity Market Review

Electricity Market Review Submission September 2014 Electricity Market Review Department of Finance Public Utilities Office Contact Benjamin Hammer b.hammer@cmewa.com The Chamber of Minerals and Energy of Western Australia Level

More information

Secure, affordable and efficient electricity for business in Western Australia.

Secure, affordable and efficient electricity for business in Western Australia. Secure, affordable and efficient electricity for business in Western Australia. September 2012 Chamber of Commerce and Industry of Western Australia Contents Executive summary 3 Next steps for electricity

More information

Committee on the Northern Territory s Energy Future. Electricity Pricing Options. Submission from Power and Water Corporation

Committee on the Northern Territory s Energy Future. Electricity Pricing Options. Submission from Power and Water Corporation Committee on the Northern Territory s Energy Future Electricity Pricing Options Submission from Power and Water Corporation October 2014 Power and Water Corporation 1. INTRODUCTION On 21 August 2014, the

More information

2014 Residential Electricity Price Trends

2014 Residential Electricity Price Trends FINAL REPORT 2014 Residential Electricity Price Trends To COAG Energy Council 5 December 2014 Reference: EPR0040 2014 Residential Price Trends Inquiries Australian Energy Market Commission PO Box A2449

More information

June 2015. Position Paper Contribution to the debate on electricity market design and capacity markets

June 2015. Position Paper Contribution to the debate on electricity market design and capacity markets June 2015 Position Paper Contribution to the debate on electricity market design and capacity markets Eurogas is the association representing the European gas wholesale, retail and distribution sectors.

More information

Electricity Market Review. Discussion Paper

Electricity Market Review. Discussion Paper Steering Committee 25 July 2014 ii Disclaimer State of Western Australia The information, representations and statements contained in this publication have been prepared for the and are provided for discussion

More information

Submission to the Electricity Market Review September 2014

Submission to the Electricity Market Review September 2014 Submission to the Electricity Market Review September 2014 0 About CCI... 2 Executive summary... 3 Electricity market context... 4 Encouraging competition in wholesale and retail markets... 5 Restructuring

More information

Agenda. Balancing Review Industry Workshop Market Rules Design Team

Agenda. Balancing Review Industry Workshop Market Rules Design Team Balancing Review Industry Workshop Market Rules Design Team Agenda Welcome 1. Review context 2. Today s objectives and scope 3. High level options 4. Development pathways decision 5. System Management

More information

Market Procedure: Settlement VERSION 3. Market Procedure: Settlement V3 Page 1 of 24

Market Procedure: Settlement VERSION 3. Market Procedure: Settlement V3 Page 1 of 24 Settlement VERSION 3 Settlement V3 Page 1 of 24 ELECTRICITY INDUSTRY ACT 2004 ELECTRICITY INDUSTRY (WHOLESALE ELECTRICITY MARKET) REGULATIONS 2004 WHOLESALE ELECTRICITY MARKET RULES COMMENCEMENT: This

More information

Rule change request. 18 September 2013

Rule change request. 18 September 2013 Reform of the distribution network pricing arrangements under the National Electricity Rules to provide better guidance for setting, and consulting on, cost-reflective distribution network pricing structures

More information

Review of the Energy Savings Scheme. Position Paper

Review of the Energy Savings Scheme. Position Paper Review of the Energy Savings Scheme Position Paper October 2015 Contents Executive summary... 3 Energy Savings Scheme Review Report package... 3 Expanding to gas... 3 Target, penalties and duration...

More information

A new electricity market for Northern Ireland and Ireland from 2016 - Integrated Single Electricity Market (I-SEM)

A new electricity market for Northern Ireland and Ireland from 2016 - Integrated Single Electricity Market (I-SEM) A new electricity market for Northern Ireland and Ireland from 2016 - Integrated Single Electricity Market (I-SEM) Non-technical summary High level design Draft Decision Paper SEM -14-047 June 2014 1 INTRODUCTION

More information

Electricity Market Review ( EMR )

Electricity Market Review ( EMR ) Electricity Market Review ( EMR ) Market Participant Consultation Group Briefing 10 th April 2014 Department of Finance Overview The Case for Electricity Market Reform EMR Introduction Electricity Market

More information

AER Submission. Competition Policy Review Draft Report

AER Submission. Competition Policy Review Draft Report AER Submission Competition Policy Review Draft Report November 2014 1 Introduction The AER is Australia s national energy regulator and an independent decision-making authority. Our responsibilities are

More information

TABLE OF CONTENTS. Western Power: EMR Submission. NETWORKS Page 2 16

TABLE OF CONTENTS. Western Power: EMR Submission. NETWORKS Page 2 16 TABLE OF CONTENTS FOREWORD FROM THE CEO... 3 SECTION 1 BACKGROUND... 4 SECTION 2 ELECTRICITY MARKET REVIEW QUESTIONS... 9 SECTION 3 CONSIDERATIONS FOR THE FUTURE... 14 Note: All years noted in this document

More information

ESRI Research Note. The Irish Electricity Market: New Regulation to Preserve Competition Valeria di Cosmo and Muireann Á. Lynch

ESRI Research Note. The Irish Electricity Market: New Regulation to Preserve Competition Valeria di Cosmo and Muireann Á. Lynch ESRI Research Note The Irish Electricity Market: New Regulation to Preserve Competition Valeria di Cosmo and Muireann Á. Lynch Research Notes are short papers on focused research issues. They are subject

More information

PJM Overview and Wholesale Power Markets. John Gdowik PJM Member Relations

PJM Overview and Wholesale Power Markets. John Gdowik PJM Member Relations PJM Overview and Wholesale Power Markets John Gdowik PJM Member Relations PJM s Role Ensures the reliability of the high-voltage electric power system Coordinates and directs the operation of the region

More information

APRIL 2014 ELECTRICITY PRICES AND NETWORK COSTS

APRIL 2014 ELECTRICITY PRICES AND NETWORK COSTS APRIL 2014 ELECTRICITY PRICES AND NETWORK COSTS 1 WHAT MAKES UP THE RETAIL ELECTRICITY BILL? Retail electricity bills are made up of a number of components: Wholesale costs reflecting electricity generation

More information

Generator Optional. Timeline including the next steps. A practical example. Potential benefits of OFA? Key implications. How might OFA work?

Generator Optional. Timeline including the next steps. A practical example. Potential benefits of OFA? Key implications. How might OFA work? Generator Optional Firm Access Rights Australian Energy Market Commission announces terms of reference for detailed design work On the 6 March 2014, the Australian Energy Market Commission (AEMC) released

More information

Inquiry into the Efficiency of Synergy s Costs and Electricity Tariffs. Issues Paper

Inquiry into the Efficiency of Synergy s Costs and Electricity Tariffs. Issues Paper Inquiry into the Efficiency of Synergy s Costs and Electricity Tariffs Issues Paper 11 August 2011 Important Notice This document has been compiled in good faith by the Economic Regulation Authority (Authority).

More information

2013 Residential Electricity Price Trends

2013 Residential Electricity Price Trends FINAL REPORT 2013 Residential Electricity Price Trends 13 December 2013 Reference: EPR0036 Final Report Inquiries Australian Energy Market Commission PO Box A2449 Sydney South NSW 1235 E: aemc@aemc.gov.au

More information

Issues Paper. Investigation into Retail Prices for Non-Contestable Electricity Customers in the ACT

Issues Paper. Investigation into Retail Prices for Non-Contestable Electricity Customers in the ACT Issues Paper Investigation into Retail Prices for Non-Contestable Electricity Customers in the ACT December 2002 The Independent Competition and Regulatory Commission (ICRC) is established by the Independent

More information

Retail Operating Costs A REPORT PREPARED FOR THE ECONOMIC REGULATION AUTHORITY OF WESTERN AUSTRALIA. March 2012

Retail Operating Costs A REPORT PREPARED FOR THE ECONOMIC REGULATION AUTHORITY OF WESTERN AUSTRALIA. March 2012 Retail Operating Costs A REPORT PREPARED FOR THE ECONOMIC REGULATION AUTHORITY OF WESTERN AUSTRALIA March 2012 Frontier Economics Pty. Ltd., Australia. i Frontier Economics March 2012 Public Retail Operating

More information

ABOUT ELECTRICITY MARKETS. Power Markets and Trade in South Asia: Opportunities for Nepal

ABOUT ELECTRICITY MARKETS. Power Markets and Trade in South Asia: Opportunities for Nepal ABOUT ELECTRICITY MARKETS Power Markets and Trade in South Asia: Opportunities for Nepal February 14-15, 2011 Models can be classified based on different structural characteristics. Model 1 Model 2 Model

More information

Review of PIRSA s Cost Recovery Policy and practices, including their application to the Fisheries and Aquaculture Industries Primary Industries and

Review of PIRSA s Cost Recovery Policy and practices, including their application to the Fisheries and Aquaculture Industries Primary Industries and Review of PIRSA s Cost Recovery Policy and practices, including their application to the Fisheries and Aquaculture Industries Primary Industries and Regions SA 29 July 2015 Contents Executive Summary...

More information

3 August, 2015. Mr Simon Middleton Electricity Market Review Project Office Public Utilities Office Department of Finance

3 August, 2015. Mr Simon Middleton Electricity Market Review Project Office Public Utilities Office Department of Finance 3 August, 2015 Mr Simon Middleton Electricity Market Review Project Office Public Utilities Office Department of Finance By Email: electricitymarketreview@finance.wa.gov.au Dear Simon, I wish to thank

More information

AEMC Electricity Price Trends report released

AEMC Electricity Price Trends report released AEMC Electricity Price Trends report released AUSTRALIAN ENERGY MARKET COMMISSION LEVEL 5, 201 ELIZABETH STREET SYDNEY NSW 2000 T: 02 8296 7800 E: AEMC@AEMC.GOV.AU W: WWW.AEMC.GOV.AU The Australian Energy

More information

2017 19 TasNetworks Regulatory Proposal Expenditure Forecasting Methodology

2017 19 TasNetworks Regulatory Proposal Expenditure Forecasting Methodology 2017 19 TasNetworks Regulatory Proposal Expenditure Forecasting Methodology Version Number 1 26 June 2015 Tasmanian Networks Pty Ltd (ACN 167 357 299) Table of contents 1 Introduction... 1 2 Meeting our

More information

Energy Productivity & Pricing

Energy Productivity & Pricing Energy Productivity & Pricing Markets for energy, renewable energy and carbon Dr Jenny Riesz February 2014 2 Average electricity retail prices Electricity price rises CSIRO Future Grid (2013) Change and

More information

Electricity Spot Markets: The Singapore Experience

Electricity Spot Markets: The Singapore Experience Electricity Spot Markets: The Singapore Experience GCCIA 3 rd Regional Power Trade Forum Abu Dhabi 29 September 2014 Presented by Tan Liang Ching Vice President, Energy Market Company, Singapore 1 1 Presentation

More information

Disclaimer: All costs contained within this report are indicative and based on latest market information. 16 th March 2015

Disclaimer: All costs contained within this report are indicative and based on latest market information. 16 th March 2015 Disclaimer: All costs contained within this report are indicative and based on latest market information 16 th March 2015 FD SUMMARY The make up of the electricity bill is changing, with non-commodity

More information

How To Trade Electricity Derivatives

How To Trade Electricity Derivatives CEEM Specialised Training Program EI Restructuring in Australia Derivative Markets and the NEM Iain MacGill and Hugh Outhred Centre for Energy and Environmental Markets School of Electrical Engineering

More information

AER reference: 52454; D14/54321 ACCC_09/14_865

AER reference: 52454; D14/54321 ACCC_09/14_865 Commonwealth of Australia 2014 This work is copyright. In addition to any use permitted under the Copyright Act 1968, all material contained within this work is provided under a Creative Commons Attribution

More information

Response to the Energy White Paper Issues Paper PREPARED BY EMC ENGINEERING FOR THE AUSTRALIAN GOVERNMENT DEPARTMENT OF INDUSTRY

Response to the Energy White Paper Issues Paper PREPARED BY EMC ENGINEERING FOR THE AUSTRALIAN GOVERNMENT DEPARTMENT OF INDUSTRY Response to the Energy White Paper Issues Paper PREPARED BY EMC ENGINEERING FOR THE AUSTRALIAN GOVERNMENT DEPARTMENT OF INDUSTRY i P a g e www.energym adeclean.com CONTENTS

More information

Possible future retail electricity price movements: 1 July 2012 to 30 June 2015

Possible future retail electricity price movements: 1 July 2012 to 30 June 2015 ELECTRICITY PRICE TRENDS FINAL REPORT Possible future retail electricity price movements: 1 July 2012 to 30 June 2015 22 March 2013 Reference: EPR0029 Electricity price trends report EMBARGO until 22 March

More information

Competition in EU Electricity Markets The Role of Antitrust Policy

Competition in EU Electricity Markets The Role of Antitrust Policy Presentation at SNF-SESSA Conference, Bergen, March 4th, 2005. Competition in EU Electricity Markets The Role of Antitrust Policy Miguel de la Mano Member of the Chief Economist Team, DG Competition (*)

More information

IMO Board Room, Level 17, 197 St Georges Terrace, Perth

IMO Board Room, Level 17, 197 St Georges Terrace, Perth Minutes MEETING TITLE Market Advisory Committee MEETING NO 82 DATE TIME LOCATION 2:00 PM 3:55 PM IMO Board Room, Level 17, 197 St Georges Terrace, Perth Attendees Class Comment Allan Dawson Erin Stone

More information

MANDATORY ROLLOUT OF INTERVAL METERS FOR ELECTRICITY CUSTOMERS

MANDATORY ROLLOUT OF INTERVAL METERS FOR ELECTRICITY CUSTOMERS July 2004 Interval Meter Rollout MANDATORY ROLLOUT OF INTERVAL METERS FOR ELECTRICITY CUSTOMERS Final decision 2nd Floor, 35 Spring St Melbourne VIC 3000 Australia Phone: 61 3 9651 0222, Fax: 61 3 9651

More information

Updated SCER Demand Side Participation Program December 2013

Updated SCER Demand Side Participation Program December 2013 Updated SCER Demand Side Participation Program December 2013 The Standing Council on Energy and Resources (SCER) has adopted this framework to guide its demand side participation (DSP) work. The framework

More information

Australian Energy Market Commission

Australian Energy Market Commission Australian Energy Market Commission Level 6, 201 Elizabeth Street Sydney NSW 2000 PO Box A2449, Sydney South NSW 1235 P 02 8296 7800 F 02 8296 7899 E aemc@aemc.gov.au ABN 49 236 270 144 www.aemc.gov.au

More information

NSW Business Chamber Submission to the Special Commission of Inquiry into Electricity Transactions

NSW Business Chamber Submission to the Special Commission of Inquiry into Electricity Transactions 29 June 2011 Special Commission of Inquiry Electricity PO Box A1150 SYDNEY SOUTH 1235 1. The NSW Business Chamber welcomes the opportunity to make a submission to the NSW Government s Special Commission

More information

Principal risks and uncertainties

Principal risks and uncertainties Principal risks and uncertainties Our risk management approach We have a well-established risk management methodology which we use throughout the business to allow us to identify and manage the principal

More information

Changes in regulated electricity prices from 1 July 2012

Changes in regulated electricity prices from 1 July 2012 Independent Pricing and Regulatory Tribunal FACT SHEET Changes in regulated electricity prices from 1 July 2012 Based on Final Determination, 13 June 2012 The Independent Pricing and Regulatory Tribunal

More information

Manager, SCER Secretariat Department of Resources, Energy and Tourism GPO Box 1564 Canberra ACT 2601 Lodged via email: scer@ret.gov.

Manager, SCER Secretariat Department of Resources, Energy and Tourism GPO Box 1564 Canberra ACT 2601 Lodged via email: scer@ret.gov. Manager, SCER Secretariat Department of Resources, Energy and Tourism GPO Box 1564 Canberra ACT 2601 Lodged via email: scer@ret.gov.au Monday 15 July 2013 Dear Secretariat, Regulation Impact Statement

More information

WHOLESALE ELECTRICITY MARKET (WEM) REVIEW PERTH ENERGY SUBMISSION TO STEERING COMMITTEE ON DISCUSSION PAPER

WHOLESALE ELECTRICITY MARKET (WEM) REVIEW PERTH ENERGY SUBMISSION TO STEERING COMMITTEE ON DISCUSSION PAPER WHOLESALE ELECTRICITY MARKET (WEM) REVIEW PERTH ENERGY SUBMISSION TO STEERING COMMITTEE ON DISCUSSION PAPER September 2014 Introduction Perth Energy welcomes the WA Government s review of the Wholesale

More information

Overview 3 Electricity price increases 4 Capital and operating expenditure 6 Demand side management 7 Issues with sales/demand forecasts 8

Overview 3 Electricity price increases 4 Capital and operating expenditure 6 Demand side management 7 Issues with sales/demand forecasts 8 Overview 3 Electricity price increases 4 Capital and operating expenditure 6 Demand side management 7 Issues with sales/demand forecasts 8 2 Business SA is the State s leading business organisation, representing

More information

Port Jackson Partners

Port Jackson Partners Port Jackson Partners NOT JUST A CARBON HIT ON ELECTRICITY PRICES Many factors will drive a doubling of electricity prices in many states by 15. This will have a major impact on virtually all businesses.

More information

Electricity Business in the Asia-Pacific Region

Electricity Business in the Asia-Pacific Region Electricity Business in the Asia-Pacific Region Business Environment and Challenges (Regional) The opportunities in coming years for CLP to increase its presence in the power industry in the Asia-Pacific

More information

IMPACT OF GB S ELECTRICITY MARKET REFORM ON INTERCONNECTIONS, CONSEQUENCES ON NORDIC MARKET Michel Martin, 3 April 2014

IMPACT OF GB S ELECTRICITY MARKET REFORM ON INTERCONNECTIONS, CONSEQUENCES ON NORDIC MARKET Michel Martin, 3 April 2014 IMPACT OF GB S ELECTRICITY MARKET REFORM ON INTERCONNECTIONS, CONSEQUENCES ON NORDIC MARKET Michel Martin, 3 April 2014 PÖYRY MANAGEMENT CONSULTING ENERGY Pöyry offices (c) grafikdienst.com Pöyry Management

More information

Page 1 of 11. F u t u r e M e l b o u r n e C o m m i t t e e Agenda Item 7.1. Notice of Motion: Cr Wood, Renewable Energy Target 9 September 2014

Page 1 of 11. F u t u r e M e l b o u r n e C o m m i t t e e Agenda Item 7.1. Notice of Motion: Cr Wood, Renewable Energy Target 9 September 2014 Page 1 of 11 F u t u r e M e l b o u r n e C o m m i t t e e Agenda Item 7.1 Notice of Motion: Cr Wood, Renewable Energy Target 9 September 2014 Motion 1. That Council resolves that the Chair of the Environment

More information

Information Paper. Investigation into prices for electricity and water services in the ACT

Information Paper. Investigation into prices for electricity and water services in the ACT Information Paper Investigation into prices for electricity and water services in the ACT DECEMBER 2002 INDEPENDENT COMPETITION AND REGULATORY COMMISSION INFORMATION PAPER INVESTIGATION INTO PRICES FOR

More information

Quarterly Wholesale/Retail Price Report

Quarterly Wholesale/Retail Price Report Quarterly Wholesale/Retail Price Report February 29 Contents Overview 3 Summary of analysis 1. Customer bills, wholesale costs and margins 5 Electricity Gas 2. Scenario analysis: Impact of retail price

More information

The Power Market: E-Commerce for All Electricity Products By Edward G. Cazalet, Ph.D., and Ralph D. Samuelson, Ph.D.

The Power Market: E-Commerce for All Electricity Products By Edward G. Cazalet, Ph.D., and Ralph D. Samuelson, Ph.D. The Power Market: E-Commerce for All Electricity Products By Edward G. Cazalet, Ph.D., and Ralph D. Samuelson, Ph.D. Why not use the Web to buy and sell transmission rights at prices derived from bids

More information

Markets Infrastructure Team, Markets Policy Division, Central Bank of Ireland, Block D, Iveagh Court, Harcourt Road, Dublin 2

Markets Infrastructure Team, Markets Policy Division, Central Bank of Ireland, Block D, Iveagh Court, Harcourt Road, Dublin 2 30 th January 2015 Markets Infrastructure Team, Markets Policy Division, Central Bank of Ireland, Block D, Iveagh Court, Harcourt Road, Dublin 2 RE: Consultation on Supervision of Non-Financial Counterparties

More information

Electricity settlement reform moving to halfhourly

Electricity settlement reform moving to halfhourly Electricity settlement reform moving to halfhourly settlement Launch Statement Publication date 4 April 2014 Contact: Jonathan Amos and Jeremy Adams- Strump Team: Smarter Markets Tel: 0207 901 7000 Email:

More information

Comparative Study of Frameworks to protect the Long Term Interests of Pension Funds Investing in Public-Private Partnerships

Comparative Study of Frameworks to protect the Long Term Interests of Pension Funds Investing in Public-Private Partnerships EMAIL contact@fosterinfrastructure.com WEB www.fosterinfrastructure.com Comparative Study of Frameworks to protect the Long Term Interests of Pension Funds Investing in Public-Private Partnerships Pty

More information

An Introduction to Alberta s Financial Electricity Market

An Introduction to Alberta s Financial Electricity Market An Introduction to Alberta s Financial Electricity Market TABLE OF CONTENTS PAGE EXECUTIVE SUMMARY...1 1 INTRODUCTION...1 2 FINANCIAL ELECTRICITY MARKET...4 2.1 Trading Platforms of the Financial Electricity

More information

RE: Default Superannuation Funds in Modern Awards, Productivity Commission Draft Report

RE: Default Superannuation Funds in Modern Awards, Productivity Commission Draft Report Default Superannuation Funds in Modern Awards Productivity Commission LB2 Collins Street East Melbourne Vic 8003 Email: default.super@pc.gov.au 03 August 2012 Dear Sir or Madam, RE: Default Superannuation

More information

Western Australian Feed-In Tariff Discussion Paper

Western Australian Feed-In Tariff Discussion Paper Western Australian Feed-In Tariff Discussion Paper OVERVIEW In September 2008, the incoming State Government announced its intention to introduce a feed-in tariff as part of the Liberal Plan for Environmental

More information

Data Communications Company (DCC) price control guidance: process and procedures

Data Communications Company (DCC) price control guidance: process and procedures Guidance document Contact: Tricia Quinn, Senior Economist Publication date: 27 July 2015 Team: Smarter Metering Email: tricia.quinn@ofgem.gov.uk Overview: The Data and Communications Company (DCC) is required

More information

The UK Electricity Market Reform and the Capacity Market

The UK Electricity Market Reform and the Capacity Market The UK Electricity Market Reform and the Capacity Market Neil Bush, Head Energy Economist University Paris-Dauphine Tuesday 16 th April, 2013 Overview 1 Rationale for Electricity Market Reform 2 Why have

More information

I write in response to your request for feedback on SAPN s electricity tariff reforms. Executive Summary

I write in response to your request for feedback on SAPN s electricity tariff reforms. Executive Summary ABN 14 725 309 328 Level 1, 136 Greenhill Road Unley SA 5061 Telephone (08) 8300 0000 Fax 08 8300 0001 Email customerservice@business-sa.com www.business-sa.com 23 October 2015 Ms Jessica Vonthehoff Communications

More information

Australian Remote Renewables: Opportunities for Investment

Australian Remote Renewables: Opportunities for Investment Australian Remote Renewables: Opportunities for Investment The largely untapped remote clean energy market and funding support available from the Australian Government creates an attractive opportunity

More information

The Levy Control Framework

The Levy Control Framework Report by the Comptroller and Auditor General Department of Energy & Climate Change The Levy Control Framework HC 815 SESSION 2013-14 27 NOVEMBER 2013 4 Key facts The Levy Control Framework Key facts 2bn

More information

2. Executive Summary. Emissions Trading Systems in Europe and Elsewhere

2. Executive Summary. Emissions Trading Systems in Europe and Elsewhere 2. Executive Summary With the introduction of CO 2 emission constraints on power generators in the European Union, climate policy is starting to have notable effects on energy markets. This paper sheds

More information

Summary of Submissions Received on the Consultation on Strengthening Statutory Payment Oversight Powers and the Reserve Bank s Responses

Summary of Submissions Received on the Consultation on Strengthening Statutory Payment Oversight Powers and the Reserve Bank s Responses Summary of Submissions Received on the Consultation on Strengthening Statutory Payment Oversight Powers and the Reserve Bank s Responses October 2013 2 SECTION ONE: INTRODUCTION 1. In March 2013, the Reserve

More information

Revenue proposal 2014/15 2018/19. responsive efficient price aware

Revenue proposal 2014/15 2018/19. responsive efficient price aware Revenue proposal 2014/15 2018/19 responsive efficient price aware TRANSGRID REVENUE PROPOSAL 2014/15-2018/19 Contents 1. 2. 3. Executive Summary 1.1 Capital Expenditure 7 1.2 Operating Expenditure 9 1.3

More information

Transfer pricing in the Scottish water industry: Scottish Water s compliance with Regulatory Accounting Rule 5

Transfer pricing in the Scottish water industry: Scottish Water s compliance with Regulatory Accounting Rule 5 Transfer pricing in the Scottish water industry: Scottish Water s compliance with Regulatory Accounting Rule 5 A report to the Water Industry Commission for Scotland strategic management consultants ltd

More information

EnerNOC Pty Ltd ABN 49 104 710 278 Level 1, 250 Queen Street Melbourne VIC 3000

EnerNOC Pty Ltd ABN 49 104 710 278 Level 1, 250 Queen Street Melbourne VIC 3000 EnerNOC Pty Ltd ABN 49 104 710 278 Level 1, 250 Queen Street Melbourne VIC 3000 Tel: +61-3-8643-5900 www.enernoc.com.au info@enernoc.com Philip Weickhardt Electricity Network Inquiry Productivity Commission

More information

Promoting the long term interests of electricity customers. IPART s submission SCER on network policies and regulation

Promoting the long term interests of electricity customers. IPART s submission SCER on network policies and regulation Promoting the long term interests of electricity customers IPART s submission SCER on network policies and regulation Electricity October 2012 Inquiries regarding this document should be directed to a

More information

ELECTRICITY MARKET REFORM (EMR) & THE ENERGY BILL INENCO OVERVIEW

ELECTRICITY MARKET REFORM (EMR) & THE ENERGY BILL INENCO OVERVIEW ELECTRICITY MARKET REFORM (EMR) & THE ENERGY BILL INENCO OVERVIEW February 2014 ELECTRICITY MARKET REFORM (EMR) & THE ENERGY BILL The Energy Bill is the government s flagship energy policy. There have

More information

Executive insights. Shifting the Load: Using Demand Management to Cut Asia's Eletricity Bill. Shifting Load Away from Peak Times

Executive insights. Shifting the Load: Using Demand Management to Cut Asia's Eletricity Bill. Shifting Load Away from Peak Times Volume XVII, Issue 3 Shifting the Load: Using Demand Management to Cut Asia's Eletricity Bill Electric utilities and power retailers in Asia are feeling the heat from households and industrial users whose

More information

SUBMISSION BY THE AUSTRALIAN SECURITIES AND INVESTMENTS COMMISSION

SUBMISSION BY THE AUSTRALIAN SECURITIES AND INVESTMENTS COMMISSION SUBMISSION BY THE AUSTRALIAN SECURITIES AND INVESTMENTS COMMISSION Executive Summary ASIC has responsibility for the regulation of securities and some derivatives markets in Australia. These markets are

More information

Response by NIE Energy (PPB)

Response by NIE Energy (PPB) NIE Energy Limited Power Procurement Business (PPB) Review of K factors & Supply Margins and Tariff Structure Review Consultation Paper CER-09-093 Response by NIE Energy (PPB) 11 September 2009. Introduction

More information

COMPETITIVE ELECTRIC ENERGY MARKET IN GREECE

COMPETITIVE ELECTRIC ENERGY MARKET IN GREECE NATIONAL TECHNICAL UNIVERSITY OF ATHENS (NTUA) GREECE COMPETITIVE ELECTRIC ENERGY MARKET IN GREECE EVANGELOS DIALYNAS Professor NTUA Director of Electric Power Division 1 Competitive Electric European

More information

Options for Amending the ASIC Market Supervision Cost Recovery Arrangements. ASX Submission

Options for Amending the ASIC Market Supervision Cost Recovery Arrangements. ASX Submission Options for Amending the ASIC Market Supervision Cost Recovery Arrangements ASX Submission 1 February 2013 Contents Executive Summary... 3 Appendix 1 Detailed Responses to Treasury Questions... 4 Current

More information

Future Trading Arrangements 3 rd Forum. Giuseppina Squicciarini 18/11/13

Future Trading Arrangements 3 rd Forum. Giuseppina Squicciarini 18/11/13 Future Trading Arrangements 3 rd Forum Giuseppina Squicciarini 18/11/13 Agenda 1. The FTA process so far 2. Outline of potential workstreams 3. Criteria for prioritisation 4. Scope and prioritisation of

More information

Performance Metrics. For Independent System Operators And Regional Transmission Organizations

Performance Metrics. For Independent System Operators And Regional Transmission Organizations Performance Metrics For Independent System Operators And Regional Transmission Organizations A Report to Congress In Response to Recommendations of the United States Government Accountability Office April

More information

Energy White Paper at a glance

Energy White Paper at a glance and Science Energy White Paper at a glance WWW. i Energy White Paper at a glance The Australian Government made an election commitment to deliver an Energy White Paper to give industry and consumers certainty

More information

Economic Concepts for Pricing Electricity Network Services A Report for the Australian Energy Market Commission

Economic Concepts for Pricing Electricity Network Services A Report for the Australian Energy Market Commission Economic Concepts for Pricing Electricity Network Services A Report for the Australian Energy Market Commission 21 July 2014 Project Team Adrian Kemp Oliver Nunn Martin Chow Stephanie Gainger NERA Economic

More information

DRAFT DETERMINATION. Review of natural gas prices

DRAFT DETERMINATION. Review of natural gas prices DRAFT DETERMINATION Review of natural gas prices April 2001 INDEPENDENT COMPETITION AND REGULATORY COMMISSION Draft Determination Review of Natural Gas Prices April 2001 Submissions Public involvement

More information

Clean Energy Council submission to Queensland Competition Authority Regulated Retail Electricity Prices for 2014-15 Interim Consultation Paper

Clean Energy Council submission to Queensland Competition Authority Regulated Retail Electricity Prices for 2014-15 Interim Consultation Paper Clean Energy Council submission to Queensland Competition Authority Regulated Retail Electricity Prices for 2014-15 Interim Consultation Paper Executive Summary The Clean Energy Council (CEC) supports

More information

The remainder of this memo provides a summary of market performance and trends in 2014 through November.

The remainder of this memo provides a summary of market performance and trends in 2014 through November. California Independent System Operator Corporation Memorandum To: ISO Board of Governors From: Eric Hildebrandt, Director, Market Monitoring Date: December 10, 2014 Re: Market monitoring report This memorandum

More information

Electricity Costs White Paper

Electricity Costs White Paper Electricity Costs White Paper ISO New England Inc. June 1, 2006 Table of Contents Executive Summary...1 Highlights of the Analysis...1 Components of Electricity Rates...2 Action Plan for Managing Electricity

More information

Single Electricity Market (SEM) and interaction with EMIR. Central Bank of Ireland

Single Electricity Market (SEM) and interaction with EMIR. Central Bank of Ireland Single Electricity Market (SEM) and interaction with EMIR Central Bank of Ireland 11 th July 2014 About EAI Overview of SEM and its Participants The market is a gross mandatory pool and consists of generators

More information

Business Council of Australia

Business Council of Australia Business Council of Australia Submission to the Department of Broadband, Communications and the Digital Economy on Regulatory Reform for 21st-Century Broadband June 2009 Table of Contents Key points...

More information

The Ontario Energy Board's ( Board ) Decision and Order in the OPA's 2011 revenue requirement submission (EB-2010-0279) directed the OPA:

The Ontario Energy Board's ( Board ) Decision and Order in the OPA's 2011 revenue requirement submission (EB-2010-0279) directed the OPA: Filed: March, 0 EB-0-0 Tab Schedule Page of OPA EFFICIENCY METRICS 0 0.0 INTRODUCTION The Ontario Energy Board's ( Board ) Decision and Order in the OPA's 0 revenue requirement submission (EB-00-0) directed

More information

Department of Treasury and Finance. Northern Territory Electricity Market Reform. Information Paper

Department of Treasury and Finance. Northern Territory Electricity Market Reform. Information Paper Department of Treasury and Finance Northern Territory Electricity Market Reform Information Paper February 2014 Introduction As part of the 2012 Mini Budget, the Northern Territory Government commenced

More information

FACT SHEET. NEM fast facts:

FACT SHEET. NEM fast facts: (NEM) operates on one of the world s longest interconnected power systems, stretching from Port Douglas in Queensland to Port Lincoln in South Australia and across the Bass Strait to Tasmania a distance

More information

Wholesale power market liquidity: consultation on a Secure and Promote licence condition

Wholesale power market liquidity: consultation on a Secure and Promote licence condition Promoting choice and value for all gas and electricity customers Wholesale power market liquidity: consultation on a Secure and Promote Consultation Reference: 163/12 Contact: Phil Slarks, Senior Economist

More information

3 Electricity financial

3 Electricity financial 3 Electricity Thomas Lohnes (Getty Images) Spot price volatility in the National Electricity Market can cause significant risk to physical market participants. While generators face a risk of low prices

More information

Electricity Market Reform. Consultation by DECC. Response by E.ON. Summary

Electricity Market Reform. Consultation by DECC. Response by E.ON. Summary Electricity Market Reform Consultation by DECC Response by E.ON Summary We recognise that Government needs to provide stronger incentives to build new low carbon generating capacity to meet the UK s specific

More information

NATIONAL ELECTRICITY FORECASTING REPORT FOR THE NATIONAL ELECTRICITY MARKET

NATIONAL ELECTRICITY FORECASTING REPORT FOR THE NATIONAL ELECTRICITY MARKET NATIONAL ELECTRICITY FORECASTING REPORT FOR THE NATIONAL ELECTRICITY MARKET Published: JUNE 2014 Copyright 2014. Australian Energy Market Operator Limited. The material in this publication may be used

More information

ENERGY MARKET REFORM

ENERGY MARKET REFORM C A S E S T U D Y O F A S U C C E S S F U L A U S T R A L I A N N A T I O N A L E N E R G Y P R O G R A M M E / S T R A T E G Y ENERGY MARKET REFORM 1. The problem or issue addressed: Efficient and effective

More information

Harmonisation of electricity generation transmission tariffs. A EURELECTRIC contribution to ACER s scoping exercise

Harmonisation of electricity generation transmission tariffs. A EURELECTRIC contribution to ACER s scoping exercise Harmonisation of electricity generation transmission tariffs A EURELECTRIC contribution to ACER s scoping exercise December 2015 EURELECTRIC is the voice of the electricity industry in Europe. We speak

More information

sink asset load power pool ISO pool participant bids operating constraints ancillary service declarations

sink asset load power pool ISO pool participant bids operating constraints ancillary service declarations G1 DEFINITIONS In the ISO rules: acceptable operational reason means with respect to a source asset, any one or more of the following: i) a circumstance related to the operation of the generating asset

More information