Fire Damage Reinstatement Works to Rollit House, Newington Barrow
|
|
- Ernest Young
- 3 years ago
- Views:
Transcription
1 Housing and Adult Social Services 7 Newington Barrow Way, London N7 7P Decision of Corporate Director of Housing and Adult Social Services Meeting of: Date Ward(s) Officer key decision 25 September 2015 Highbury West Ward Delete as appropriate Exempt Non-exempt SUBJECT: Approval of the Procurement Strategy for Contract for Fire Damage Reinstatement Works to Rollit House 1 Synopsis 1.1 This report seeks pre-tender approval for the procurement strategy in respect of the Fire Damage Reinstatement Works to Rollit House in accordance with Rule 2.5 of the Council s Procurement Rules. A major fire occurred to Rollit House over the Easter weekend, causing significant damage to the whole building and particularly the top floor maisonettes and roof structure. All services are cut off and a scaffolding and temporary roof are in place to stabilise the building and prevent further weather damage. All residents have been moved to temporary accommodation. This contract is intended for the reconstruction and remediation works necessitated as a result of the extensive fire and water damage suffered. 2 Recommendation 2.1 To approve the procurement strategy for Fire Damage Reinstatement Works to Rollit House. as set out in this report Date the decision is to be taken: 25 September Background The works required are as follows: Page 1 of 7
2 3.1.2 Roof Structure : The roof has almost entirely been destroyed by fire and the remaining parts are unsafe. The works required involve the reconstruction of the entire roof (structure, roof covering and dormer windows). While the external appearance will look the same, it will be built to a higher standard of thermal performance and fire separation. The chimneys will remain but require some repairs Interior to Maisonette Flats : The top two floors of Rollit House are maisonette flats. Their upper storey is contained within the roof space, and has suffered fire damage. The lower floor of these flats has suffered substantial water damage. The top floor slab was also damaged by the collapsing roof tiles. The works required involve the reconstruction of the upper floor including partition walls, internal staircase and all fittings and finishes. It will also include reinstatement of all necessary fittings and finishes to the lower floor, including kitchens, bathrooms, internal partition walls, plasterboard, skirtings, etc, and repair and partial replacement of the top floor slab to an extent as yet to be determined Interior to Flats 1-13 : These have suffered water damage. Reinstatement of all necessary fittings and finishes including kitchens, bathrooms, internal partition walls, plasterboard, skirtings, etc Mechanical Services (Gas and Water) : Water tanks were all located in the roof void and are now severely damaged. Gas services are entirely disconnected as a safety precaution. Gas services need to be reinstated to modern standards which will necessitate the replacement of the entire gas network to the building. The flats have individual boilers and these will be replaced where they cannot be recovered. Water tanks will be entirely replaced and water pipes replaced as necessary Electrical Services (Including wiring, communications, lift, lighting) : These have been substantially water and fire damaged. Electrical services need to be reinstated to modern standards where they cannot be recovered. Where flats have inadequate quantities of electrical fittings, an increased number will be provided. New distribution boards will also be provided. Initial condition reports suggest the lift can be repaired, though replacement may still be necessary Works to the Exterior of the Building : The brick façade, communal walkways and windows have not suffered much damage, however, at the time of the fire the Council were arranging for cyclical works to be carried out to maintain the fabric of the building and it is proposed that these works should still be carried out. All front doors will be replaced to an increased fire safety standard. Repairs to the brickwork, windows and communal walkways as necessary. Repainting of all previously painted surfaces including railings and communal staircase. 3.2 Estimated Value The proposed works are subject to an insurance claim. The Council self-insures to 1m stg and expenditure related to the fire damage beyond that amount is borne by the insurer of the building structure The initial 1m stg expenditure on the entire fire damage remediation claim will be funded by the Council insurance fund. Other heads of expenditure have been incurred that are not included in this reconstruction works proposal. These include site security, alternative accommodation for residents and works to clear and make safe the building, and construction of a tin hat roof to ensure the building is water tight The proposed works to the exterior of the building that are not related to the fire damage will be funded through the HRA capital programme The value of the overall procurement is estimated at between 1.5m and 2m. It is estimated that works on site will last approximately 9-12 months. Retention of 10% will be applied of which 5% will be released on practical completion and 5% on successful completion of the defects at the end of the defects liability period. Therefore the overall time in which the money will be spent is two years. Page 2 of 7
3 3.2.5 This is a one-off procurement exercise and an insurance claim All planned works are required to be externally examined by the insurance loss adjustors to ensure that all the works are necessary and prices acceptable Advice is being taken from the loss adjustors as to likely costs. However, the unusual nature of these works means that they cannot be effectively benchmarked. The key cost driver is the extent of works required to remediate the extensive fire and water damage. Therefore there is limited potential to achieve savings through the scope of the works. Efforts to make savings are being done through efficient project delivery as the vacancy costs of the building are very high, as is scaffolding. Additionally measures undertaken in phase 1 of the works, such as security screens, the tin hat roof and scaffolding, reduce the risk of further building deterioration which avoids escalating costs in this procurement. 3.3 Timetable There are significant ongoing costs related to this building being empty, therefore it is very important that the programme for this project is progressed as quickly as possible Residents have been given an indicative date that they will be back in their homes by September 2016, However this is dependent upon works starting in January 2016 and a procurement exercise in October/November There are no statutory deadlines to achieve All residents were invited to a consultation meeting on the 1 st of July and this was well attended. Residents were also invited to attend an individual consultation in the second half of July. Most residents took up this opportunity. The housing capital team are working closely with the insurance manager in Finance and the council s external loss adjustors. 3.4 Options appraisal Redeveloping the site at a higher density and adding a floor has been considered but rejected as not viable The preferred procurement route is competitive tender via an open procedure. Collaboration is not considered to be possible for this project. A drawback of open tender is the potential for a very large number of tenderers to submit proposals. To mitigate this risk careful selection criteria have been drawn up to ensure that those contractors who are capable of carrying out this quite complex construction project are identified The benefit of the preferred route is speed. As residents have been left in temporary accommodation, and as vacancy costs of the building are very high it is very important that works commence as soon as practically possible It is not considered that costs of the construction itself would vary significantly with using an alternative procurement route. 3.5 Key Considerations The requirement to pay the London Living Wage will apply Best value is being considered in terms of balancing the need to deliver this project quickly with the need to deliver it at a competitive price. The external loss adjustors are key to examining this balance. Meetings are being held on a regular basis to achieve this. Page 3 of 7
4 3.5.3 Economic Sustainability: As stated in an exercise has been carried out to examine if the site can be developed more densely but this proved not viable. Otherwise this is being achieved through efficient project delivery so that vacancy costs are minimised Social Sustainability: This is being considered through making efforts to considerably improve the fire safety for residents in the building by going beyond the council s legal requirements under building regulations and achieving it in a cost neutral way. We are also working to ensure that all residents can move back into maintain the community cohesion in the block Environmental Sustainability: The new components of the building will be reinstated to modern building regulation standards. This particularly applies to the energy efficiency of new boilers and the thermal performance of the new roof. Additionally water appliances will also be installed to new water-saving standards There are no TUPE, pension or staffing implications. 3.6 Evaluation This contract will be procured using the Open Procedure. The Open Procedure means that all bidders who successfully express an interest will automatically be invited to tender and have access to the tender documents. Those who submit a tender and meet the minimum requirements will have their full tender, method statements and pricing evaluated. The contract will be awarded to the Most Economically Advantageous Tender (MEAT) in accordance with the Public Contracts Regulations. MEAT for this contract will be on the basis of quality 25% and cost 75% The tenderers will be asked to demonstrate experience against 5no. selection criteria which are central to the successful delivery of the project Quality award criteria will all have minimum standards which each contractor will be expected to achieve. The questions will be based on the following competencies: - Proposed approach to working on confined sites (5%). - Proposed approach to selection of roofing contractor (whether in-house or sub-contracted) (5%). - Proposed approach to resident liaison (5%). - Proposed approach to programme of works (5%). - Proposed approach to health and safety (5%). 3.7 Business Risks Business opportunities are unlikely as this is a one-off project, and time and cost are of great importance Currently all residents of the building are in temporary accommodation and so reconstruction of this building will allow them to move back home. There are also 2. void flats which will be available to be rented as two residents of Rollit House have accepted permanent rehousing elsewhere The Employment Relations Act 1999 (Blacklist) Regulations 2010 explicitly prohibit the compilation, use, sale or supply of blacklists containing details of trade union members and their activities. Following a motion to full Council on 26 March 2013, all tenderers will be required to sign the Council s anti-blacklisting declaration. Where an organisation is unable to declare that they have never blacklisted, they will be required to evidence that they have 'self-cleansed'. The Council will not award a contract to organisations found guilty of blacklisting unless they have demonstrated 'self-cleansing' and taken adequate measures to remedy past actions and prevent re-occurrences. 3.8 The following relevant information is required to be specifically approved by the Corporate Director in accordance with rule 2.6 of the Procurement Rules: Page 4 of 7
5 Relevant information Information/section in report 1 Nature of the service Reconstruction of Rollit House following extensive fire and water damage leaving the property uninhabitable. See paragraph [ 1.1 ] 2 Estimated value The contract has an estimated value of between 1.5m stg and 2m stg of Islington Council spend. See paragraph [ ] 3 Timetable The timetable is outlines within this report. Estimated contract start date is: January 2016 See paragraph [ ] 4 Options appraisal for tender procedure including consideration of collaboration opportunities Outcome of options appraisal are described within this report. See paragraph [ 3.4 ] 5 Consideration of: Outcomes are described within this report. Social benefit clauses; London Living Wage; See paragraph [ 3.5 ] Best value; TUPE, pensions and other staffing implications 6 Evaluation criteria The award criteria price/quality breakdown is more particularly described within the report. See paragraph [ ] 7 Any business risks associated with entering the contract 8 Any other relevant financial, legal or other considerations. Business risks are described within this report. See paragraph [3.7 ] See paragraph [ ] 4 Implications 4.1 Financial implications The reconstruction works required as a result of the fire at Rollit House are estimated at between 1.5m- 2m. The Council has an insurance policy excess of 1m which will be met by the Corporate Self- Insurance fund into which the HRA pays an annual premium. The balance of between 500k- 1m will met by the Council s insurers. At this stage the loss adjustor has indicated that the works as set out in this report are re-claimable. This is subject to full review of the finalised tender documentation by the loss adjustors, and their agreement that the tender procedure provided adequate value for money. For the purposes of the insurance claim the Leaseholders insures the building & Council s policy will be treated as one. The Council takes out buildings insurance on behalf of Leaseholders and recharges the premium to Leaseholders as part of their Annual Service charges. Page 5 of 7
6 4.2 Legal Implications The council is responsible for undertaking the repair of its housing estates pursuant to the Housing Act Accordingly the council may procure a contract for reinstatement works to Rollit House (section 1 Local Authorities Contracts Act 1997). The estimated value of the procurement for the reinstatement works to Rollit House is below the financial threshold for works contracts for the full application of the Public Contracts Regulations Although under threshold contracts do not need to strictly comply with the provisions of the Regulations, there is a requirement under EU rules for the procurement of such contracts to adhere to the principles of equal treatment, non-discrimination and fair competition. Further the council s Procurement Rules require contracts over the value of 100,000 to be subject to competitive tender. In this instance, it is proposed to advertise the contract in the London Tenders Portal using the open procedure in order to attract suitable constructors. On completion of the procurement process the contract may be awarded to the highest scoring tenderer. In deciding whether to appoint the selected contractor the Corporate Director of Housing and Adult Social Services, should be satisfied as to the competence of the chosen tenderer and that the tender price represents value for money for the Council and is acceptable to the council s loss adjuster for the purposes of the insurance claim. 4.3 Environmental Implications The reinstatement work will have several environmental impacts including resource use (new building materials), waste generation, energy use and travel to the site by the contractor. However, these can be mitigated to some extent; the contractor is legally obliged to follow the waste hierarchy, prioritising reuse and recycling. The choice of materials used will also be a key factor, and the use of sustainable materials (such as FSC- or PEFC-certified timber) should be specified. The works offer an opportunity to improve the environmental performance of Rollit House; the new roof will have a higher thermal performance, reducing energy use in the building. Where new boilers are installed, they are likely to be more efficient than the ones they replaced. Energy and water efficiency will also be improved by compliance with modern building regulations. In addition, there is an opportunity to improve local biodiversity by building in measures to the reconstructed roofline, including bat or bird nesting bricks and boxes. However, the opportunity to upgrade the thermal performance of the walls is not being taken. 4.4 Resident Impact Assessment The council must, in the exercise of its functions, have due regard to the need to eliminate discrimination, harassment and victimisation, and to advance equality of opportunity, and foster good relations, between those who share a relevant protected characteristic and those who do not share it (section 149 Equality Act 2010). The council has a duty to have due regard to the need to remove or minimise disadvantages, take steps to meet needs, in particular steps to take account of disabled persons' disabilities, and encourage people to participate in public life. The council must have due regard to the need to tackle prejudice and promote understanding A resident impact assessment has been carried out. The major impact will be a positive one of enabling residents to move back into their homes. The appointed contractors will also be subject to various measures to ensure the health, safety and safeguarding of residents while they are working on the building. 5 Conclusion and reasons for recommendations These works are necessary to reinstate the building so that the residents can be re-housed. Owing to the need to proceed with this work as quickly as possible, an open tender procedure is recommended. Page 6 of 7
7 6. Record of the decision: 6.1 I have today decided to take the decision set out in section 2 of this report for the reasons set out above. Signed by: Date Report Author: Sinéad Burke, Capital Programme Manager Tel: Sinead.Burke@islington.gov.uk Page 7 of 7
Procurement Strategy for Business Critical software contract
Key Decision Report of the Corporate Director of Finance and Resources Finance and Resources Digital Services Town Hall Islington N1 2UD Officer Key Decision Date:12/01/2016 Ward(s): All Delete as appropriate
More informationSUBJECT: Procurement Strategy for Substance Misuse Residential Detox and Rehabilitation Services
Housing and Adult Social Services 7 Newington Barrow Way, London, N7 7EP Report of: Executive Member for Health and Well-Being Meeting of: Date Ward(s) Executive 16 July 2015 All Delete as appropriate
More informationThe Future of Adventure Play in Islington
Children s Services 222 Upper Street, London N1 1XR Report of: Executive Member for Children and Families Meeting of: Date Ward(s) Executive 27 th November All Delete as appropriate Non-exempt SUBJECT:
More informationDate: 7 February 2013
Item No. Report title: Classification: Open Ward(s) or groups affected: From: Date: 7 February 2013 Meeting Name: Deputy Leader and Cabinet Member for Housing Management GW2: Leasehold and Ancillary Properties
More informationRepairs and looking after your home
A guide to Repairs and looking after your home Contents Page No. Introduction 1 Information for tenants 2 Information for homeowners 3-4 Information for onsite NHS workers 5 Information for students 5
More informationHOUSING REVENUE ACCOUNT KEY ISSUES CAPITAL OUTTURN 2014/15
APPENDIX 4 HOUSING REVENUE ACCOUNT KEY ISSUES CAPITAL OUTTURN 2014/15 The spend for the year is 30,225,000. This can be compared with the budgeted figure for 2014/15 of 34,929,000 resulting in an under
More informationHow To Manage Property In Tower Hamlets
2015 2020 Page 1 of 15 Contents 1 Introduction 2 What is Asset Management 3 Limitations 4 THCH Asset Profile 5 How the Asset Management Strategy Supports THCH s Strategic Priorities 6 How The Asset Management
More informationTSA Standards Review: Home Standard
TSA Standards Review: Home Standard Guidance note: This document sets out, in pink, what is expected of a landlord to meet the TSA s national standards. We then explain: Heantun s existing service standards
More informationREACTIVE REPAIRS, CYCLICAL & PLANNED MAINTENANCE POLICY
POLICY REF : AM05 Version No. 4.0 August 2012 REACTIVE REPAIRS, CYCLICAL & PLANNED MAINTENANCE POLICY 1.0 INTRODUCTION 1.1 This policy describes our arrangements for ensuring that our properties are well
More informationProcurement of Insurance Cover and Claims Handling for Islington
Finance Department 7 Newington Barrow Way London N7 7EP Report of: Executive Member for Finance Meeting of Date Agenda Item Ward(s) Executive 17 March 2011 D7 n/a Delete as appropriate Non-Exempt REASON
More informationHILLCREST HOUSING ASSOCIATION LIMITED MAINTENANCE POLICY
HILLCREST HOUSING ASSOCIATION LIMITED POLICY NO. AM14 MAINTENANCE POLICY 1.0 INTRODUCTION 1.1 This policy describes our arrangements for ensuring that our properties are well maintained and kept in good
More information14 October 2013. Home Ownership Services Islington Council Highbury House 4-5 Highbury Crescent London N5 1RN
14 October 2013 Leaseholder Islington Home Ownership Services 4-5 Highbury Crescent T 020 7527 7715 E homeownership@islington.gov.uk W www.islington.gov.uk Property reference: 000000 / ZZ Dear Leaseholder
More informationHome Improvement Insurance - UK Landlords
COMPENSATION POLICY LEAD OFFICER Bruce Johnson Director of Technical Services Board Approval: January 2011 Next Revieww Date: January 2013 CONTENTS 1.0 Introduction 2.0 Purpose 3.0 Right to Repair 4.0
More informationCABINET. 24 April 2012. Title: Term Contract for Maintenance, Repair and Minor Works on Security and Protection Systems
CABINET 24 April 2012 Title: Term Contract for Maintenance, Repair and Minor Works on Security and Protection Systems Report of the Cabinet Member for Finance and Education Open Report Wards Affected:
More informationHousing Policy Repairs and Maintenance
Housing Policy Repairs and Maintenance This policy affects: Tenants X Leaseholders X Other: TMO Tenants X TMO Leaseholders X PFI1 Tenants PFI2 Leaseholders PFI2 Tenants PFI2 Leaseholders Author: Service
More informationCompensation Policy Including statutory compensation, service failure and loss of amenities
Compensation Policy Including statutory compensation, service failure and loss of amenities Version Final By: Watkin Morgan Senior Manager Maria McCarron BOM approved: 22 March 2010 CONTENTS Section Page
More informationH 7. Factoring Policy. If you require this policy in a different format please ask a member of staff. Date of Approval Oct 12 Review Due Dec 15
H 7 Factoring Policy If you require this policy in a different format please ask a member of staff Date of Approval Oct 12 Review Due Dec 15 1.0 The Association s Objective 1.1 Elderpark Housing Association
More informationGeneral Functions Committee. Meeting Date 22 July 2013 Subject. Insource May Gurney Recycling TUPE Transfer StreetScene Director.
Meeting Date 22 July 2013 Subject Report of Summary General Functions Committee Insource May Gurney Recycling TUPE Transfer StreetScene Director This report relates to the transfer into Barnet of current
More informationAsset Protection Agreement Templates - Customer Explanatory Notes. Explanatory Notes on Asset Protection Agreement
Asset Protection Agreement Templates - Customer Explanatory Notes Explanatory Notes on Asset Protection Agreement Clause Heading Background The Asset Protection Agreement is intended for use where the
More informationOur repairs and maintenance service
Your repairs Being a GHA tenant gives you special rights when it comes to getting things fixed. This is called your Right to Repair. Here you ll find all you need to know about that, and much more. If
More informationCustomer Compensation Policy
Date approved: 5 May 2014 Approved by: Chief Executive 1. Introduction 1.1 Southway Housing Trust (Southway) will provide high quality services to our customers and aim to get things right first time.
More informationCowley Resident Management Organisation Ltd Cowley House, 147 Brixton Road London SW9 6LZ
Cowley Resident Management Organisation Ltd Cowley House, 147 Brixton Road London SW9 6LZ Tel: 020-7926 0690 Fax 020-7926 0692 www.cowleyrmo.org Gas Central Heating Contract for Homeowners Basic Service
More informationService Level Agreement (SLA)
Hertford College, Oxford Service Level Agreement (SLA) For Maintenance, Risk Management, and Domestic Accommodation Services At Hertford College, its residential annexes and non- residential properties
More informationCompensation Policy. When we have failed to carry out emergency or urgent repairs
Compensation Policy Hexagon aims to give good standards of service in housing and care, but occasionally things do go wrong. If a tenant makes a complaint, we will investigate and put the matter right
More informationJob Description. Empty Homes Project Officer
Job Description Post Title Post Number: Service Area / Department SDU Accountable To (Line Manager): Responsible For (Direct Reports Post Title): Empty Homes Project Officer BM01401 Housing Management
More informationAcceptance on the Approved List of contractors cannot however guarantee that any work orders will be issued to that contractor.
PROPERTY MANAGEMENT INTRODUCTORY GUIDANCE NOTES FOR THE APPLICATION TO THE APPROVED LIST OF CONTRACTORS CONTRACTORS GUIDANCE NOTES APPLICATION FORM ISSUED BY: PROPERTY MANAGEMENT UNIT WEST YORKSHIRE FIRE
More informationEnsuring a high quality maintenance service for the Council s housing stock.
Repairs and Maintenance 360 Scrutiny Review 1. Introduction 1.1 London Borough of Ealing own or manage around 18,000 properties. The stock is a mixture of housing and low and high rise flats, ranging in
More informationRESPONSIBILITY FOR REPAIRS AND MAINTENANCE FAIR FUNDING: April 2002
RESPONSIBILITY FOR REPAIRS AND MAINTENANCE FAIR FUNDING: April 2002 INDEX New Build Flat and Pitched Roofs Rainwater Goods Porches to Existing Buildings / Covered Links etc, Between Buildings Floors /
More informationHousing Asset Management Strategy 2013-2043
Housing Asset Management Strategy 2013-2043 1 Introduction 1.1 The asset management strategy sets out the approach Islington takes when deciding what types of long term investment are needed in our homes
More informationReport title : Waiver for the hire and installation of two temporary boilers and one new permanent commercial boiler at Brixton Recreation Centre
Officer delegated decision Report title : Waiver for the hire and installation of two temporary boilers and one new permanent commercial boiler at Brixton Recreation Centre Wards: Coldharbour Report Authorised
More informationYour new. repairs service 2011. www.linbrooks.co.uk
Your new repairs service 2011 0800 035 0003 www.linbrooks.co.uk Contents Your new repairs contractor 3 Our service standards 4 Linbrook: meet the team 6 Customer care 8 Landlord responsibilities 10 Tenant
More informationRepairs. If you smell gas call Transco on 0800 111 999. www.rooftopgroup.org 1
Repairs If you smell gas call Transco on 0800 111 999 www.rooftopgroup.org 1 This leaflet contains useful information about the repairs service for tenants, as well as both your rights, our rights and
More informationSchool or service safety advisor (SSA) role
School or service safety advisor (SSA) role Document control information Published document name: ssa-role-gn Date issued: January 2012 Version: 1.0 School or service safety advisor (SSA) role Previous
More informationulletin Canada Mortgage and Housing Corporation
B ulletin Canada Mortgage and Housing Corporation Replacement Reserve Guide WHAT IS THE REPLACEMENT RESERVE? The replacement reserve is a fund kept by each housing sponsor under the terms of its operating
More informationLeaseholders Handbook
Leaseholders Handbook January 2011 Contents Page 1 Introduction 1 Introduction 2 What is leasehold? 3 Repairs and improvements 4 Service charge 5 Consultation 6 Insurance 7 Selling and renting your home
More informationWRITTEN STATEMENT OF SERVICE /TERMS AND CONDITIONS OF SERVICE
WRITTEN STATEMENT OF SERVICE /TERMS AND CONDITIONS OF SERVICE Subjects covered by this written statement of service are These are the terms and conditions for the provision of a factoring service to owner
More informationMaintenance Strategy 2015 Owner: Kevin Bullimore Head of Infrastructure Next review 2020
Maintenance Strategy 2015 Owner: Kevin Bullimore Head of Infrastructure Next review 2020 Page 1 of 7 Maintenance Strategy Introduction The requirement for maintenance of premises, plant and equipment arises
More informationThis policy details Stonewater s approach to the payment of compensation.
Compensation Policy 1.0 Policy Summary This policy details Stonewater s approach to the payment of compensation. It applies to all tenants. Where differences in the contractual rights of these customers
More informationCode of Practice for Agents Undertaking Renovation Grants
Code of Practice for Agents Undertaking Renovation Grants July 1998 Contents Introduction Page 1 Approved List of Agents Page 1 Procurement Page 2 Approval Page 5 Works in Progress Page 6 Completion Page
More informationCapital Expenditure. The common definition of capital expenditure is
Capital Expenditure Under standard accounting practices local authorities are required to account for revenue expenditure and capital expenditure differently. Capital expenditure is defined in the Local
More informationOverview of the Transfer of Undertakings (Protection of Employment) Regulations 2006
TUPE Overview of the Transfer of Undertakings (Protection of Employment) Regulations 2006... 1 Service Provision Changes... 1 Employer Liability Information... 2 Liability for Failure to Inform and Consult
More informationTenant & Leaseholder Compensation Policy
Tenant & Leaseholder Compensation Policy Housing Landlord July 202 Version Control Version 3 Status of Policy Sponsor Author/Reviewer Approved Review Date Draft Mark Gaynor, Corporate Director of Housing
More information1.1 CHISEL's main activity is providing homes for our tenants to rent.
Maintenance Policies 1. Introduction 1.1 CHISEL's main activity is providing homes for our tenants to rent. 1.2 These homes have been provided with the aid of loans and are the security against which the
More informationThis document will be made available in different languages and formats on request, including Braille and audio formats.
Policy Title: Policy Manual Section: Policy Number: Performance Standards References: Factoring Housing Management HM21 AS5:2 Date Approved by Management Committee: 25 November 2010 Next Review Date: 3
More informationS.20. CONSULTATION for Private Landlords, Resident Management Companies and their Agents T HE L EASEHOLD A DVISORY S ERVICE
L E A S E T HE L EASEHOLD A DVISORY S ERVICE ASSOCIATION OF RESIDENTIAL MANAGING AGENTS CONSULTATION for Private Landlords, Resident Management Companies and their Agents S.20 Contents Purpose of this
More informationBIDDULPH MANSIONS RESIDENTS GUIDE
BIDDULPH MANSIONS RESIDENTS GUIDE The board of Biddulph Mansions West has put together this residents guide to help you get the most out of the block. It tells you: how Biddulph Mansions is managed services
More informationFyne Homes Ltd. Common Factoring Policy
Fyne Homes Ltd Common Factoring Policy First Approved : -- Policy Reviewed : November 2014 Next Review Date : Version No : 5 Page 1 of 11 Index 1. POLICY STATEMENT... 3 2. TERMS AND CONDITIONS... 3 3.
More informationY O U R A N N U A L S E R V I C E C H A R G E E X P L A I N E D
Y O U R E X P L A I N E D 02 Contents What is an annual service charge? 03 How we set up service chargeable accounts 04 Service chargeable items and descriptions 05 Understanding the paperwork 06 Annual
More informationEXECUTIVE SUMMARY. Bzar Groat Market Newcastle Upon Tyne. Date of inspection:
EXECUTIVE SUMMARY Bzar Groat Market Newcastle Upon Tyne On behalf of: Client Name Date of inspection: Reference: 05.194/CDL CONTENTS Page No EXECUTIVE SUMMARY 1 APPENDICES APPENDIX 1 PHOTOGRAPHIC SUMMARY
More informationAsbestos Management Policy
Asbestos Management Policy Originator: Approval date: Policy and Strategy Team Sovini Board PCHA Board OVH Board/EMT 3 rd December 2012 22 nd November 2012 25 th September 2012 Review date: December 2013
More informationB-1 Buildings & Service Maintenance
B-1 Buildings & Service Maintenance B-1 Buildings & Service Maintenance SAFETY, HEALTH AND ENVIRONMENTAL POLICY: B-1 DATE OF ISSUE: AUGUST 1994. BUILDINGS AND SERVICES MAINTENANCE 1. Introduction It is
More informationPage 5. The Adult Social Services and Health Committee. The Strategic Director of Adult Social Services, Housing and Health
Page 5 Agenda Item 5 Report to: The Adult Social Services and Health Committee Date: 20 th November 2012 Report of: The Strategic Director of Adult Social Services, Housing and Health Ward Location: All
More informationHealth and Safety Policy
Health and Safety Policy October 2014 1 October 2014 Contents: Introduction 1. STATEMENT OF INTENT AND POLICY OBJECTIVES 2. RESPONSIBILITIES AND ACCOUNTABILITIES FOR HEALTH AND SAFETY 2.1 The Director
More informationTHE VOID LETTABLE STANDARD
THE VOID LETTABLE STANDARD North West Leicestershire District Council is responsible for allocating empty Council owned homes. The Lettable standard has been agreed in consultation with the tenants of
More informationAGENDA ITEM: 8 SUMMARY
AGENDA ITEM: 8 SUMMARY Report for: Housing and Community Overview and Scrutiny Committee Date of meeting: 28th January 2015 PART: 1 If Part II, reason: Title of report: Contact: Purpose of report: Recommendations
More informationA Guide to... Home Renovation Incentive (HRI)
A Guide to... Home Renovation Incentive (HRI) About this guide This guide will tell you what you need to know if you are organising to have construction work done on your house and would like to avail
More informationDo you need something fixed? We re ready to help
Glasgow Housing Association www.gha.org.uk Your repairs Repairs and maintenance Do you need something fixed? We re ready to help Better homes, better lives Repairs and maintenance Because you re a GHA
More informationReview of Capital Expenditure. Sedgefield Borough Council Audit 2007/08 September 2008
Review of Capital Expenditure Sedgefield Borough Council Audit 2007/08 September 2008 Contents Summary report 3 Appendix 1 Action plan 10 Status of our reports The Statement of Responsibilities of Auditors
More informationAuthor: Adrian Pengelly Role: Director of Assets. Recommendations: 1. That the review of the Assets Directorate budget pressures for 2014/15 is noted.
Cornwall Housing Limited Report Template for DLT Agenda No: 7 Report to: The Board Part 1 Date: 27 July 2015 Title: Assets Directorate Budget Pressures 2014/15 Author: Adrian Pengelly Role: Director of
More informationRepair and Renew Grant. Croydon RRG Scheme
Repair and Renew Grant Croydon RRG Scheme Development & Environment April 2014 Croydon Repair and Renew Grant Scheme Support for independent businessess and property owners affected by flooding December
More informationDELEGATED POWERS REPORT NO. All reports 1. Governance Service receive draft report Name of GSO Paul Frost
DELEGATED POWERS REPORT NO. 1987 SUBJECT: Electoral Registration and Elections Management Software Contract Control sheet All of the following actions MUST be completed at each stage of the process and
More informationNumber 2 of 2011 MULTI-UNIT DEVELOPMENTS ACT 2011 ARRANGEMENT OF SECTIONS. 3. Conditions relating to sale of units in multi-unit developments.
Number 2 of 2011 MULTI-UNIT DEVELOPMENTS ACT 2011 Section 1. Interpretation. 2. Application of Act. ARRANGEMENT OF SECTIONS 3. Conditions relating to sale of units in multi-unit developments. 4. Transfer
More informationREPORT TO CABINET. To contribute towards the Council s ongoing cost reduction programme by reducing the cost of the procurement of goods and services.
REPORT TO CABINET Open Would any decisions proposed : Any especially affected Wards None Discretionary Be entirely within Cabinet s powers to decide Need to be recommendations to Council Is it a Key Decision
More information2. Subject to any special rules applied by the College's funding bodies, the tendering procedures will be applicable to:
HARPER ADAMS UNIVERSITY COLLEGE Code of Tendering Practice Introduction 1. The following guidelines are to be used in the conduct of tendering and contracting of major services and supplies commissioned
More informationSTANDARD SPECIFICATION. for. Plumbing, Heating, Hot Water, Cold Water & Electrical work. Sussex Lodge London W2 & 16 Stanhope Terrace London W2
STANDARD for Plumbing, Heating, Hot Water, Cold Water & Electrical work undertaken by owners within the building known as Sussex Lodge London W2 & 16 Stanhope Terrace London W2 BPME Consulting Engineers
More informationRepair Responsibilities A Guide for Sadeh Lok Residents
Repair Responsibilities A Guide for Sadeh Lok Residents Sadeh Lok is responsible for most of the repairs that may arise in and around your home, but not all. Each repair type is given a likely priority
More informationEstimated Cost of Repair
1 Applicant: Property: Home: Business: Assessor: Applicant Number: Type of Loss: Hurricane Date Contacted: 1/18/2014 Date of Loss: 10/29/2012 Date Received: 1/14/2014 Date Inspected: 2/4/2014 Date Entered:
More informationPage 97. Executive Head of Asset Planning, Management and Capital Delivery
Page 97 Agenda Item 7 Report to: Strategy and Resources Committee Date: 16 December 2013 Report of: Executive Head of Asset Planning, Management and Capital Delivery Ward Location: Not applicable Author
More information03 Your tenancy explained
03 Your tenancy explained Written Statement of Services Factored Owners Written Statement of Services under the Property Factors (Scotland) Act 2011 Revised version: April 2015 What is the Written Statement
More informationC, D Only if fitted by Sadeh Lok. A, B, C Category dependent upon impact on residents enjoyment of their home
Repair Responsibilities A Guide for Sadeh Lok Residents Sadeh Lok is responsible for most of the repairs that may arise in and around your home, but not all. Each repair type is given a likely priority
More informationJOB DESCRIPTION. Position Title and Number: Senior Procurement Officer (100618) Health, Wellbeing & Commissioning
JOB DESCRIPTION Position Title and Number: Senior Procurement Officer (100618) Grade: Department: Section: Responsible to: Responsible for: SO2 People Directorate Health, Wellbeing & Commissioning Team
More informationPractical Completion
Practical Completion Richard Davies CIBSE Home Counties SE Region 1 Practical Completion What is Practical Completion? A certificate of Practical Completion marks the point at which the Contractor has
More informationOur purpose is to empower you to confidently agree a fair price in one of life s most important purchases - your home.
Dear Client Thank you for instructing Allied Surveyors & Valuers to undertake a RICS HomeBuyer Report which is a service licensed by the Royal Institution of Chartered Surveyors (www.rics.org). The report,
More informationValue for Money Unit Local Government Audit Service
Value for Money Unit Local Government Audit Service Report on Spot Checks of Capital Projects funded by the Department of the Environment, Heritage and Local Government and undertaken by Local Authorities
More informationResponsive Repairs and Void Maintenance Strategy
Responsive Repairs and Void Maintenance Strategy Renewal: Nov. 2012 Contents: Page: 1. THE VISION 3 2. INTRODUCTION 3 3. DEFINITIONS 4 4. DELIVERY OF THE STRATEGY 5 5. TARGETS AND OBJECTIVES 6 6. MONITORING
More informationCABINET. 24 March 2015
CABINET 24 March 2015 Title: Procurement of Electricity and Gas Supplies Report of the Cabinet Member for Finance Open Report with Exempt Appendix 4 Wards Affected: All Report Author: Andrew Sivess Group
More informationLIABILITY INSURANCE AND LIABILITY CLAIMS HANDLING TENDER AND BROKERAGE SERVICES IN RESPECT THEREOF
LIABILITY INSURANCE AND LIABILITY CLAIMS HANDLING TENDER AND BROKERAGE SERVICES IN RESPECT THEREOF Cabinet Date 4 February 2015 Finance and Change Key Decision Background Documents Location/Contact for
More informationG. Common Defects in Buildings - Leakage
F. Common Defects in Buildings - Structural 32. Recently, some concrete chips have fallen from the ceiling in my kitchen. There are rusty steel bars and the area in question measures about 300 x 400mm.
More informationPolicy of Insurance under the HBCF (Home Building Compensation Fund)
Policy of Insurance under the HBCF (Home Building Compensation Fund) How to read the policy (i) The policy covers you for the types of loss, and for the amounts of loss, described in clause 1. (ii) Clause
More informationWhy Choose John Mortimer Property Management Limited
Why Choose John Mortimer Property Management Limited We come with a great deal of experience in the management of estates and blocks of flats in the South of England. You will benefit from a family company
More informationProject Athena Phase 1 Human Resources and Payroll
Executive 14 November 2011 Report from the Director of Finance and Corporate Services Project Athena Phase 1 Human Resources and Payroll Wards Affected: [ALL] 1.0 Summary 1.1 This report concerns the transfer
More informationPlease use a separate sheet for each location Date Notes taken / / By. Name of Company: Tel No: Mobile: Contact at Company: E mail Fax:
COMMERCIAL COMBINED FACT FIND M & N Insurance Service Ltd 248 Hendon Way London NW4 3NL Tel: 020 8202 4474 E Mail info@mninsure.com Fax: 020 8202 1943 Please use a separate sheet for each location Date
More informationEVS - Information Paper 1/13
EVS - Information Paper 1/13 ASSESSMENT OF VALUE OF INSURED DAMAGE 1 Introduction 2 Scope 3 Definitions 4 Recommendations 5 Assessment Methodology 6 Other Issues 7 References 1. Introduction 1.1. This
More informationPROCUREMENT PROGRAMME PROCUREMENT OF CONSULTANTS HEAD OF WASTE STRATEGY AND CONTRACTS
NORTH LONDON WASTE AUTHORITY Agenda Item No: REPORT TITLE: PROCUREMENT PROGRAMME PROCUREMENT OF CONSULTANTS REPORT OF: HEAD OF WASTE STRATEGY AND CONTRACTS FOR SUBMISSION TO: DATE: AUTHORITY MEETING 11
More informationLONDON CYCLE HIRE SCHEME AGREEMENT. Schedule 39 Service Provider Personnel. Schedule 39 Service Provider Personnel - REDACTED VERSION
Schedule 39 Service Provider Personnel - REDACTED VERSION LONDON CYCLE HIRE SCHEME AGREEMENT Schedule 39 Service Provider Personnel Transport for London - Version Final CCS0000151079 Schedule 39 Service
More informationEnvironment Committee 11 January 2016
Environment Committee 11 January 2016 Title Whole Life Costing of Footway Maintenance Treatments and Scheme Prioritisation Report of Wards Status Urgent Key Enclosures Commissioning Director, Environment
More informationOther useful information and guidance
Other useful information and guidance Insurance (see also section 3) We insure the property (including the garage if any) under a master insurance policy which covers the structural parts of the building.
More informationAsbestos Management Policy
Central Bedfordshire Council www.centralbedfordshire.gov.uk Asbestos Management Policy The Housing Service Version 1.0 Directorate Social Care Health and Housing Service Housing Service Approved by Director
More informationBuilding insurance frequently asked questions
Building insurance frequently asked questions April 2012 From 1 April 2011 until 31 March 2013 Ocaso S.A. U.K. Branch will provide building insurance for the leaseholders of Islington Council. The purpose
More information14 AUGUST 2007 NOT EXEMPT LOWER POLMAISE - WASTE TRANSFER STATION REINVESTMENT OF FIRE DAMAGE INSURANCE SETTLEMENT
STIRLING COUNCIL THIS REPORT RELATES TO ITEM ON THE AGENDA EXECUTIVE ENVIRONMENT SERVICES 14 AUGUST 2007 NOT EXEMPT LOWER POLMAISE - WASTE TRANSFER STATION REINVESTMENT OF FIRE DAMAGE INSURANCE SETTLEMENT
More informationHealth and Safety Policy
Health and Safety Policy Status: Final Next Review Date: Apr 2014 Page 1 of 16 NHS England Health and Safety: Policy & Corporate Procedures Health and Safety Policy Policy & Corporate Procedures Issue
More informationPRE-PURCHASE INSPECTION REPORT
PRE-PURCHASE INSPECTION REPORT PREPARED FOR: PROPERTY ADDRESS: Waiheke Island DATE: 21 November 2012 Page 1 of 13 (a) This is a report of a visual only, non-invasive inspection of the areas of the building
More informationCSENSE LTD. Block Management Agreement
CSENSE LTD Block Management Agreement For Guidance in this agreement The singular includes the plural and the plural includes the singular. Any obligation undertaken by more than one person is a joint
More informationExterior Elevated Elements Inspection Guidelines
Exterior Elevated Elements Inspection Guidelines Planning and Development 1. Guideline Purpose These guidelines are intended to assist practicing professionals in complying with Berkeley Municipal Code
More informationHEALTH & SAFETY POLICY
HEALTH & SAFETY POLICY 1. STATEMENT OF INTENT & POLICY OBJECTIVES The Council, as the governing body of the School, recognises and accepts the responsibilities placed on it as 'Employer' by the Health
More informationBuilding insurance frequently asked questions
Building insurance frequently asked questions Buildings insurance for Islington Council leaseholders is provided by Zurich Insurance plc (trading as Zurich Municipal). This factsheet is a summary of the
More informationRepairs and maintenance
Repairs and maintenance TO YOUR HOME HOUSING at the heart of the community Contents Your responsibilities Reporting a repair Other useful contacts Out-of-hours emergency service The repair process How
More informationCompensation Policy. 1 Statement of intent
Policy: Compensation Policy Author: Adrian Stones Signed off by: Board 27 Sept 07 Effective date: 1 October 2007 Policy last reviewed and approved: 27.09.07 Due for review: See corporate timetable Compensation
More informationASBESTOS CONTAINING MATERIALS POLICY
ASBESTOS CONTAINING MATERIALS POLICY Document Control Version 3 Ratified by Risk Management Sub Group Date Ratified 19 December 2012 Name of Originator/Author Head of Estates and Facilities Name of Responsible
More informationThe client organisation that was best at meeting residents needs in the provision of a maintenance service
Wolverhampton Homes NHMF Best Practice Awards 2009 Submission for: - The client organisation that was best at meeting residents needs in the provision of a maintenance service Leaseholders gas maintenance
More information