CONSTRUCTION TRAFFIC MANAGEMENT PLAN

Size: px
Start display at page:

Download "CONSTRUCTION TRAFFIC MANAGEMENT PLAN"

Transcription

1 CONSTRUCTION TRAFFIC MANAGEMENT PLAN IN SUPPORT OF THE PROPOSED ERECTION OF A SINGLE WIND TURBINE WITH MAXIMUM BLADE TIP HEIGHT OF 67M, FORMATION OF NEW VEHICULAR ACCESS, ACCESS TRACK AND ASSOCIATED INFRASTRUCTURE ON LAND AT BRIDGEMOOR, MILLBROOK, CORNWALL September 2015 Prepared By

2 Project Quality Control Sheet ORIGINAL Author Checked by Approved by Signature Date 03/09/ /09/ /09/2015 Company Aardvark EM Ltd Aardvark EM Ltd Aardvark EM Ltd Location: Land at Bridgemoor, Millbrook, Cornwall Grid Reference: , Project Manager: Nick Leaney Report Author: Kirsty Gibson BSc Hons Report Number: 1164e/R002 Report Status: Final Copyright: All copyright in this document is reserved. Liability: This document contains information and may contain conclusions and recommendations. Every effort has been made to ensure that the information is accurate and that the opinions expressed are sound. However, Aardvark EM Limited cannot be made liable for any errors or omissions or for any losses or consequential losses resulting from decisions based on the information. Report Written and Produced By Aardvark EM Limited, Higher Ford, Wiveliscombe, Taunton, Somerset, TA4 2RL Telephone: , Facsimile: Web:

3 Contents 1 General Public Engagement Construction Programme Working Times Construction Traffic Route to site Site Access Site Compound Deliveries Anticipated Vehicle Movements Traffic summary Lighting for Construction and Security Storage of Oils, Fuels and Pollution Prevention Oil and Fuel Other Hazardous Material Dust and Dirt Ecological and Habitat Protection Construction Period Operational Period Construction Programme Programme of Works Site Access Photos... 8 Appendix 1 - Method Statement for the Temporary Removal of the Hedge at Bridgemoor

4 1 General The Construction Traffic Management Plan is in connection with the development and installation of a single wind turbine and ancillary works on land at Bridgemoor, Millbrook. 2 Public Engagement The Parish Council and local highways department will be notified prior to commencement on site and provided with a copy of the Construction Traffic Management Plan. During construction the contact details for an on-site representative will be made available. 3 Construction Programme Site deliveries, utilising larger vehicles, of equipment to site will be phased over an eight week construction period, thereafter the majority of vehicles requiring access to the site will be small commercial vehicles and cars. Construction is anticipated to commence following receipt of planning consent and discharge of any pre-commencement conditions An overview of the project construction programme is set out in section 12 of this report. 4 Working Times Construction of the development will be undertaken 7 days a week. All deliveries will be between 7.30am and 5.30pm. Deliveries to the site will be staged within this time period with drivers given specific time windows for arrival at site. The anticipated number and frequency of vehicle movements are set out within section 8.1 below. 5 Construction Traffic Route to site The planned route for all major deliveries of materials is shown in Figure 1 below, the photographs are set out in sections at the end of the report. The identified construction traffic delivery route is proposed to leave the A38 at Trerulefoot, turning left onto the A374 following the road to Antony. Construction vehicles such as abnormal loads will be required to turn around at the A374/Trevol Road junction, approximately 1km east of the A374/Antony Hill junction). Once reaching Antony turning left onto A374/Antony Hill signposted to Millbrook. At the T junction vehicles will turn left continuing on the B3247 signposted Whitsand Bay. Turn right onto Withnoe Lane and proceed to the site entrance. The proposal will require a permanent new access track from the existing gateway to facilitate access to the turbine during the construction and operational phase (shown in photo 6 in section 15). A new temporary access will be constructed to allow the delivery vehicles of the main turbine component parts to safely enter and exit the site in forward gear. A condition survey will be undertaken and agreed with the local Highway Authority (Area Network Manager) prior to commencement of work on site and used as a reference following the construction period. The applicant undertakes to rectify any damage caused to the road or verges as a direct result of traffic associated with the construction of the development. Aardvark EM Limited September 2015 Page 1

5 Photo 1 Turning area for HGVs Photo 2 Photo 3 Photo 4 Photo 5 Photo 6 Figure 1 Proposed delivery route for construction period (blue line) 6 Site Access Access to the site is via an existing farm entrance from withnoe Lane south of the B3247. A permanent new access track will be constructed from the site entrance to facilitate access to the base of the proposed turbine during the operational period from the existing field gate, as illustrated in drawing ref: 1164e/D004. Whilst there is an existing access from the public highway, a new temporary access will be constructed for the construction period to safely accommodate construction traffic and in particular delivery of the main turbine component parts. This will be reinstated after the construction period has completed. A methodology has been provided in Appendix 1, which outlines the removal and reinstatement for the temporary access track. 7 Site Compound There will be a hard standing area as shown on the development layout drawings submitted with the application. This is for the temporary storage of equipment and materials during construction and parking for site vehicles as shown on the proposed site layout plan. The hard standing area has Aardvark EM Limited September 2015 Page 2

6 been sized, and will be managed, to allow two or more vehicles to enter the site at the same time and for vehicles to turn around. A temporary turning head has also been shown on the layout plan for the construction period and then removed thereafter for vehicles to turn around so they can exit the site in a forward gear. Aardvark EM Limited September 2015 Page 3

7 Figure 2 Development Plan Aardvark EM Limited September 2015 Page 4

8 8 Deliveries Site deliveries of equipment to the site, utilising larger vehicles, will be phased over an eight week construction period, thereafter the majority of vehicles requiring access to the site will be small commercial vehicles and cars. All deliveries will be between 7.30am and 5.30pm. Deliveries to the site will be staged within this time period with drivers given specific time windows for arrival at site. The anticipated number and frequency of vehicle movements are set out below. Due to the relative lack of neighbouring properties to the application site, it is not considered necessary to formally notify local residents of the construction phase period. However, as set out below appropriate traffic warning signs will be put in place (subject to prior notification of the Highways Authority). Access for emergency vehicles will be maintained at all times. 8.1 Anticipated Vehicle Movements Construction traffic will comprise delivery of the turbine and attendant infrastructure, concrete for the turbine base and sub-structure and materials for the access road. Delivery of the turbine and ancillary equipment to the site will comprise heavy and abnormal goods traffic and will comprise up to 10 vehicles over one or two days:- 1. The blades are fitted within transport frames, grouped into a set of three blades and are delivered in one telescopic semi-trailer truck load; 2. The blade hub, transformer and other auxiliaries are delivered in two truckloads; 3. The tower is delivered in two sections and two standard truck and trailer loads; 4. The nacelle is delivered in one truck load; 5. The large ring generator is delivered in one truck load; 6. One ton main crane and one 90 ton hydraulic tail crane. The materials for the new access road and hardstanding concrete for the turbine base/crane pad will generate approximately 10 HGV vehicle movements per day. Other vehicle movements associated with the development will comprise cars and small commercial vehicles for site workers. 8.2 Traffic summary Deliveries will be timed to prevent multiple HGV s arriving at once. This will prevent any potential for HGV s to park on the public highway. However the construction compound will also be able to accommodate more than one HGV if necessary as stated above. 9 Lighting for Construction and Security External lighting will be used during the construction period if required and only between the hours of and Aardvark EM Limited September 2015 Page 5

9 10 Storage of Oils, Fuels and Pollution Prevention 10.1 Oil and Fuel All oil and fuel will be stored in 1m³ fuel containers in accordance with specific UK Regulations e.g. The Control of Pollution (Oil Storage) (England) Regulations 2001 (OSR England) Other Hazardous Material No other hazardous material will be stored on site Dust and Dirt A temporary wheelwash will be located on site during the construction periods, for all vehicles exiting on to the public highway in wet periods to avoid depositing mud onto the road. Similarly, in excessively dry periods the section of the highway immediately either side of the access will be swept if there is excessive dust 11 Ecological and Habitat Protection The potential for impacts during the construction and operation phases are considered below Construction Period During the construction phases there are predictable adverse effects which are generally unavoidable; many are temporary or short term and can be minimised as part of the construction management, but some have the potential for more lasting effect. The potential for adverse effects arises largely from disturbance including noise, vibration, light, dust, and human presence. These would be minimised as far as possible through the application of good practice techniques and adherence to well-designed method statements. Whilst only minor earthworks are proposed such as levelling and cable trenching, there is potential to increase soil erosion from the site during periods of heavy rainfall. Drainage control measures will be applied to ensure that during construction contaminated water is not released off-site. However, it is likely that following construction normal flow rates would soon return as any additional sedimentation is transported downstream. This effect would be unlikely, temporary and minor adverse. There is potential that accidental spills during construction of fuel and/or chemicals could introduce pollutants into the receptor, particularly during periods of heavy rainfall. Should this occur the effect would be likely, temporary and minor adverse Operational Period It is anticipated that the majority of vehicle movements to the site will be during the construction phase period for the delivery of materials and technical equipment (turbine, inverter station, mounting structure, cables and materials for the construction of the access track and hard standing areas). Once construction is complete, the site will require only periodic visits, for occasional repair and maintenance work. The existing access is considered sufficient for this purpose. Aardvark EM Limited September 2015 Page 6

10 As set out in the submitted Design & Access statement the field will remain in agricultural use post development therefore the access will be retained and maintained for that purpose. 12 Construction Programme The proposed construction timeline is set out below and the construction of the site is anticipated to be approximately weeks. This may vary dependent on weather and other constraints unknown at this stage. Construction of the development will be undertaken 7 days a week. No activities audible from the boundary of the nearest noise sensitive receptor shall take place on Sundays during the construction period or at times outside 07:00 and 19:00. The proposed hours of working during the construction period will be between 7.30am and 5.30pm with the intention to avoid use of local highway network for deliveries during peak hours ( & ). Stage 1 Formation of temporary access track, cable trenches, casting substation foundations, security fence and CCTV cameras/poles Weeks 1-2 Stage 2 Installation of ground piles Weeks 2-4 Stage 3 Stage 4 Stage 5 Erection of mounting framework, fixing panels and routing of cables Installation of inverters, HV substations and all cabling and Commissioning Reinstatement of temporary tracks, hard standing and open storage areas Weeks 2-9 Weeks 9-10 Weeks Stage 6 Operation Weeks Programme of Works Once the Programme of Works has been confirmed with the preferred installer including the delivery schedule, it will be submitted in writing for approval by the LPA and Devon and Cornwall Police Abnormal Loads team for approval prior to commencement of development. Aardvark EM Limited September 2015 Page 7

11 14 Site Access Photos Photo 1: Exit from the A38 onto the A374 Photo 2: Turning area at the A374/Trevol Road junction Photo 3: Left turn onto on to A374/Antony Hill at Antony Aardvark EM Limited September 2015 Page 8

12 Photo 4: Left turn onto the B3247 Photo 5: Right turn onto Withnoe Lane Photo 6a: Construction Site Entrance Aardvark EM Limited September 2015 Page 9

13 Photo 6b: Operational Site Entrance Aardvark EM Limited September 2015 Page 10

14 Appendix 1 Method Statement for the Temporary Removal of the Hedge at Bridgemoor Aardvark EM Limited September 2015 Page 11

15 METHOD STATEMENT FOR THE TEMPORARY REMOVAL OF THE HEDGE AT BRIDGEMOOR RATIONALE The hedgerow adjacent to Withnoe Lane is to be taken down to allow access to the site for the turbine machinery. The hedgerow will be re-instated after all construction work has been completed. DESCRIPTION OF THE HEDGEROWS Generally the hedgebanks on site are over-managed and therefore structurally poor in terms of woody vegetation; they are all Cornish hedges (i.e. stone and earth banks to about 1m high). There is a single hedge that has to be partially removed. This is the hedge along Withnoe Lane. This is a heavily managed close-cropped flat-topped hedgebank. The road side is dominated by grasses such as Yorkshire Fog with Common Nettle, Lesser Celandine and Ivy also present. The field side is more overgrown and is dominated by Bramble with Hart stongue Fern and Blackthorn also present. In total, the hedge consists of 60% grassy and herbaceous species. The structural features are the height, width of the hedge and the materials used in its construction. The key ecological features are: Potential presence of reptiles especially Common Lizard and Slow Worm. Potential presence of small mammals including rats. The potential presence of nesting birds during the nesting season (March to August inclusive). RELEVANT LEGISLATION Wildlife and Countryside Act 1981 (as amended) The four widespread reptile species are listed under Schedule 5 of the Wildlife and Countryside Act 1981 (as amended) in respect of Section 9(5) and part of Section 9(1) whereby individual animals are protected from intentional killing or injury and also from sale or attempted sale. Section 1 of the Wildlife and Countryside Act 1981 prohibits the intentional killing, injuring or taking of any wild bird and the taking, damaging or destroying of the nest (whilst being built or in use) or eggs. Nests may be lawfully destroyed when not in use, i.e. outside the nesting season (September to February).

16 Wild Mammals (Protection) Act 1996 A wild mammal is defined as one which is neither domestic nor captive. This act makes it an offence to mutilate, kick, beat, nail or otherwise impale, stab, burn, stone, crush, drown, drag or asphyxiate any wild mammal with intent to inflict unnecessary suffering. METHOD FOR REMOVAL AND RE-INSTATEMENT The aim is to retain the materials for re-instatement and avoid adverse effects on protected species and habitats. The hedgerow should be taken down under a watching brief by a suitably qualified ecologist. The removal method of the hedge should be stone by stone by a small excavator with a toothed bucket, each time watching for small animals. Any small animals found should be caught by the ecologist, removed from the immediate work site and placed in a place of safety in one of the adjacent hedges. All material (stone earth and turf) should be retained for re-use. Stone material should be piled up together for re-use. Soils should be stored on an impermeable geo-textile membrane for re-use and sheeted-over to prevent wash-ff. Turf should be kept to one side and re-used, to be relaid on the upper face. The hedge should be rebuilt by hand so that it is contiguous with the adjacent hedgeline. The hedge should be replanted with locally sourced Blackthorn once it has been rebuilt.

Construction Phase Traffic Management Plan

Construction Phase Traffic Management Plan Construction Phase Traffic Management Plan The Construction Phase Traffic Management Plan is in connection with the application for the development of a single Wind Turbine and Ancillary Works on land

More information

Galloper Wind Farm Project. Traffic Management Plan May 2013 Draft v1 Document Reference GWF/TMP/100513. Galloper Wind Farm Limited

Galloper Wind Farm Project. Traffic Management Plan May 2013 Draft v1 Document Reference GWF/TMP/100513. Galloper Wind Farm Limited Galloper Wind Farm Project Traffic Management Plan May 2013 Draft v1 Document Reference GWF/TMP/100513 Galloper Wind Farm Limited Document title Galloper Wind Farm Project Traffic Management Plan Status

More information

Triton Knoll Offshore Wind Farm Limited Electrical System. Outline Traffic Management Plan

Triton Knoll Offshore Wind Farm Limited Electrical System. Outline Traffic Management Plan Triton Knoll Offshore Wind Farm Limited Electrical System Outline Traffic Management Plan October 2014 RWE Innogy UK Triton Knoll TMP Copyright 2014 RWE Innogy UK Ltd All pre-existing rights reserved.

More information

Construction Management Statement. Residential development at Bywell House, St Mary s Hill, Ascot

Construction Management Statement. Residential development at Bywell House, St Mary s Hill, Ascot Construction Management Statement Residential development at Bywell House, St Mary s Hill, Ascot Parking of Vehicles of Site Personnel, Operatives and Visitors Site staff, visitors to the development and

More information

TRAFFIC MANAGEMENT PLAN

TRAFFIC MANAGEMENT PLAN TRAFFIC MANAGEMENT PLAN For: The construction and operation of a Photovoltaic (PV) Facility in Dabenoris, South Africa Prepared for: Alternative Energy Solutions (Pty) Ltd PO Box 4939 Tygervalley, South

More information

Construction Traffic Management Plan

Construction Traffic Management Plan Construction Traffic Management Plan Proposed Additional Classroom Accommodation for Woolacombe Primary School Produced for and on behalf of Built Environments Team Devon County Council NPS South West

More information

APPLICATION FOR PLANNING PERMISSION FOR A SOIL TREATMENT FACILITY AT KINGS CLIFFE LANDFILL SITE, STAMFORD, NORTHAMPTONSHIRE

APPLICATION FOR PLANNING PERMISSION FOR A SOIL TREATMENT FACILITY AT KINGS CLIFFE LANDFILL SITE, STAMFORD, NORTHAMPTONSHIRE APPLICATION FOR PLANNING PERMISSION FOR A SOIL TREATMENT FACILITY AT KINGS CLIFFE LANDFILL SITE, STAMFORD, NORTHAMPTONSHIRE DESIGN AND ACCESS STATEMENT Report Reference: AU/KC/SPH/1449/01/D&A/FIN Baddesley

More information

1. Purpose and scope. 2. SEPA's role in hydropower and planning

1. Purpose and scope. 2. SEPA's role in hydropower and planning Page no: 1 of 10 1. Purpose and scope 1.1 The purpose of this note is to provide guidance on the approach that we will take when dealing with hydropower development management consultations. We welcome

More information

THIS PAGE INTENTIONALLY LEFT BLANK

THIS PAGE INTENTIONALLY LEFT BLANK THIS PAGE INTENTIONALLY LEFT BLANK Construction Traffic Management Plan 2 Contents 1. Introduction... 4 1.1 Conditions of Consent... 4 2. Goals of the CTMP... 6 2.1 Objectives... 6 2.2 Predicted Construction

More information

Rockhampton Office Brisbane Office Tarong Site. Barron Gorge Hydro PS Kareeya Hydro PS Mica Creek PS

Rockhampton Office Brisbane Office Tarong Site. Barron Gorge Hydro PS Kareeya Hydro PS Mica Creek PS Business Procedure Traffic Management Document Number OHS-PROC-130 This document applies to the following sites: All Sites Rockhampton Office Brisbane Office Tarong Site Barron Gorge Hydro PS Kareeya Hydro

More information

Construction Traffic Management Plan

Construction Traffic Management Plan Introduction This (CTMP) has been prepared in order to discharge Condition 20 of planning permission ref 07/02879/EFUL for the enabling site works associated with the wider Bath Western Riverside development.

More information

Liquid Effluent Treatment Plant (LETP) Land Clean-Up

Liquid Effluent Treatment Plant (LETP) Land Clean-Up Liquid Effluent Treatment Plant (LETP) Land Clean-Up Frequently Asked Questions What is proposed? Magnox Ltd is proposing to remove the redundant Liquid Effluent Treatment Plant (LETP) at Harwell and to

More information

APPENDIX 4. Risk Tables

APPENDIX 4. Risk Tables APPENDIX 4 Tables Preliminary Qualitative Criteria The qualitative risk assessment criteria have been developed to identify key risks to the environment, society, heritage and business reputation. The

More information

Pollution & Noise from Demolition & Construction Sites

Pollution & Noise from Demolition & Construction Sites CONTROL OF Pollution & Noise from Demolition & Construction Sites N oi se Co ns tru ct io n MAY 2008 THE LONDON BOROUGH 3 CONTENTS Part 1 Introduction Page 1. Background 4 2. Purpose of the code 5 3.

More information

SCHEDULE 2 TO THE DEVELOPMENT PLAN OVERLAY Shown on the planning scheme map as DPO2 WAVERLEY GOLF COURSE, LYSTERFIELD VALLEY

SCHEDULE 2 TO THE DEVELOPMENT PLAN OVERLAY Shown on the planning scheme map as DPO2 WAVERLEY GOLF COURSE, LYSTERFIELD VALLEY SCHEDULE 2 TO THE DEVELOPMENT PLAN OVERLAY Shown on the planning scheme map as DPO2 WAVERLEY GOLF COURSE, LYSTERFIELD VALLEY 1.0 Conditions and requirements for permits A permit to use and develop the

More information

LIQUID WASTE TREATMENT FACILITY MENDIS ROAD, HUDSON CREEK DRAFT GUIDELINES FOR A PUBLIC ENVIRONMENTAL REPORT

LIQUID WASTE TREATMENT FACILITY MENDIS ROAD, HUDSON CREEK DRAFT GUIDELINES FOR A PUBLIC ENVIRONMENTAL REPORT LIQUID WASTE TREATMENT FACILITY MENDIS ROAD, HUDSON CREEK DRAFT GUIDELINES FOR A PUBLIC ENVIRONMENTAL REPORT Introduction The purpose of this Public Environmental Report (PER) is to provide the Government

More information

Site Layout & Traffic Plan

Site Layout & Traffic Plan Location Site address: Norbury Manor Business Enterprise College, Kensington Avenue, Thornton Heath, Croydon CR7 8BT. The new block will be constructed on the existing hard play area. The construction

More information

Vehicle Tracking Control (VTC)

Vehicle Tracking Control (VTC) Vehicle Tracking Control (VTC) SM-4 Description Vehicle tracking controls provide stabilized construction site access where vehicles exit the site onto paved public roads. An effective vehicle tracking

More information

Application No: 5/11/9004 District: South Lakeland

Application No: 5/11/9004 District: South Lakeland DEVELOPMENT CONTROL AND REGULATION COMMITTEE 20 July 2011 A Report by the Assistant Director - Planning & Sustainability Application No: 5/11/9004 District: South Lakeland Applicant: United Utilities Clearwater

More information

CONSTRUCTION TRAFFIC MANAGEMENT PLAN (CTMP)

CONSTRUCTION TRAFFIC MANAGEMENT PLAN (CTMP) CONSTRUCTION TRAFFIC MANAGEMENT PLAN (CTMP) [Colston Budd Hunt & Kafes Pty Ltd AS AMENDED BY City of Sydney] 23 March 2010 1. PREAMBLE 1.1 This document constitutes the Demolition and Traffic Management

More information

Construction Site Set Up Requirements

Construction Site Set Up Requirements Process Code Number Revision COP A 035 B Document Title Construction Site Set Up Requirements B 1/11/10 SRC SAT DH Final A 1/10/10 SRC MI Draft comment Rev. Date Prepared Reviewed Approved Detail/Comment

More information

LANGHOPE RIG WINDFARM TRAFFIC MANAGEMENT AND HAULAGE ROUTE SCHEME

LANGHOPE RIG WINDFARM TRAFFIC MANAGEMENT AND HAULAGE ROUTE SCHEME LANGHOPE RIG WINDFARM TRAFFIC MANAGEMENT AND HAULAGE ROUTE SCHEME Rev No. : Revision Description : Date : 0 For Information 1 Draft Prepared for Scottish Borders Council (SBC) comments 2 Draft Post SBC

More information

PLANNING & REGULATION COMMITTEE 16 JANUARY 2012

PLANNING & REGULATION COMMITTEE 16 JANUARY 2012 Division(s): Sutton Courtenay & Harwell Contact Officer: John Duncalfe (john.duncalfe@oxfordshire.gov.uk) Tel: 01865 815356 PLANNING & REGULATION COMMITTEE 16 JANUARY 2012 TO CRUSH, SCREEN, BLEND AND STOCK

More information

Wellington Inner City Improvements National War Memorial Park (Pukeahu) Certification Review

Wellington Inner City Improvements National War Memorial Park (Pukeahu) Certification Review Wellington Inner City Improvements National War Memorial Park (Pukeahu) Air Quality (Dust) Certification Review 22 November 2012 [CAQMP1 TR] Prepared in association with: Document produced by: Apecx PO

More information

TRITON KNOLL ELECTRICAL SYSTEM CONSULTATION: QUESTIONNAIRE

TRITON KNOLL ELECTRICAL SYSTEM CONSULTATION: QUESTIONNAIRE RWE Innogy UK TRITON KNOLL ELECTRICAL SYSTEM CONSULTATION: QUESTIONNAIRE The Planning Act 2008 requires developers to undertake pre-application consultation before submitting an application for a Development

More information

Engineering Policy 146. Severe Weather Management Plans

Engineering Policy 146. Severe Weather Management Plans Engineering Policy 146 Severe Weather Management Plans January 2014 Contents Engineering Policy... 1 1 Policy statement... 1 2 Applicability... 1 3 Context... 1 4 Objectives and benefits... 1 5 Consultation...

More information

Pollution Incident Response Plan

Pollution Incident Response Plan Pollution Incident Response Plan Introduction Schmidt Quarries is committed to ensuring all aspects of our quarrying activities comply with the environmental legislative requirements in NSW. This Pollution

More information

Logo here. TRAFFIC MANAGEMENT PLAN Ref : xxxx Dated xxxxxx. Enter details. Delivery Address: Enter details

Logo here. TRAFFIC MANAGEMENT PLAN Ref : xxxx Dated xxxxxx. Enter details. Delivery Address: Enter details Logo here Ref : xxxx Dated xxxxxx Mandatory H&S 905 Rev 1: xxxxx Page 1 of 1 Project: Project No: Date: Prepared by: Enter details Enter details Enter details Enter details Delivery Address: Enter details

More information

Ardessie Hydro Electric Project

Ardessie Hydro Electric Project Ardessie Hydro Electric Project Appendix T - Traffic Management Plan 13 th December 2014 V1.0 Jacinta MacDermot DHG Hydro Ltd 7 St James s Gardens London W11 4RB Jacinta.macdermot@dhghydro.com 077 888

More information

Construction Traffic Management Plan

Construction Traffic Management Plan Construction Traffic Management Plan Proposed Additional Accommodation for SWDPLS Shinners Bridge Dartington Produced for and on behalf of Built Environments Team Devon County Council NPS South West Ltd

More information

Activity Yes No N/A Notes

Activity Yes No N/A Notes CE 2020 (Rev. 12/11) Page 1 of 5 PROJECT NAME AND SITE ADDRESS: CONTRACT NUMBER: ORACLE NUMBER: WDID NUMBER: CONTRACTOR NAME AND ADDRESS: PROJECT SITE RISK LEVEL: Risk Level 1 Risk Level 2 Risk Level 3

More information

CHAPTER 24: ENVIRONMENTAL MANAGEMENT

CHAPTER 24: ENVIRONMENTAL MANAGEMENT Central Eyre Iron Project Environmental Impact Statement CHAPTER 24: ENVIRONMENTAL MANAGEMENT CHAPTER 24 ENVIRONMENTAL MANAGEMENT COPYRIGHT Copyright Iron Road Limited, 2015 All rights reserved This document

More information

CITY OF VINCENT CONSTRUCTION MANAGEMENT PLAN GUIDELINES

CITY OF VINCENT CONSTRUCTION MANAGEMENT PLAN GUIDELINES CITY OF VINCENT CONSTRUCTION MANAGEMENT PLAN GUIDELINES INTRODUCTION What is a Construction Management Plan? The City of Vincent requires careful management of construction involving excavation and retention

More information

Approval Services Unit

Approval Services Unit Approval Services Construction Management Plan Pro-Forma Commercial Properties Please complete the enclosed form and return to:- By Mail: Approval Services Unit City of Perth Council House 27 St Georges

More information

CONSTRUCTION SEQUENCE & PROGRAMME

CONSTRUCTION SEQUENCE & PROGRAMME CONSTRUCTION SEQUENCE & PROGRAMME 2 CONTENTS 1.0 Introduction 7 2.0 Key activities 8 2.1 Airport related activities 2.2 Construction of new roads and accesses 2.3 Earthworks zone a 2.4 Earthworks zone

More information

CONSTRUCTION TRAFFIC MANAGEMENT PLAN Issue 2, V5, 11/11/13

CONSTRUCTION TRAFFIC MANAGEMENT PLAN Issue 2, V5, 11/11/13 Note: Please refer to the end of this document for guidance notes about completing this form Q1. What is the full postal address of the site? Your response Q2. Planning reference and revision number (if

More information

Figure 5.6a Construction worksites and corridor access Note: Indicative only, subject to detailed design.

Figure 5.6a Construction worksites and corridor access Note: Indicative only, subject to detailed design. A 0 NORTH 200 metres George Lane worksite North Strathfield Station worksite Strath eld Triangle A B Existing rail corridor Proposed underpass approach New/extended bridge Worksites Existing track Proposed

More information

AGENT(S) / APPLICANT(S): AGENT Dave Dickerson, DK Architects. APPLICANT Halton Housing Trust. DEVELOPMENT PLAN ALLOCATION: Greenspace.

AGENT(S) / APPLICANT(S): AGENT Dave Dickerson, DK Architects. APPLICANT Halton Housing Trust. DEVELOPMENT PLAN ALLOCATION: Greenspace. APPLICATION NO: 14/00168/FUL LOCATION: Land to the west of 19 Crow Wood Lane, Widnes. PROPOSAL: Proposed erection of 10 no. 1 bedroom apartments with individual access doors arranged in 2no. 2 storey height

More information

CALDER PARK PROJECT STAGE 1. EPBC Act Approval Compliance Report (EPBC 2012/6439)

CALDER PARK PROJECT STAGE 1. EPBC Act Approval Compliance Report (EPBC 2012/6439) CALDER PARK PROJECT STAGE 1 EPBC Act Approval Compliance Report (EPBC 2012/6439) Prepared for: METRO TRAINS MELBOURNE Level 28, 80 Collins Street, Melbourne, VIC 3000 Prepared by: Kellogg Brown & Root

More information

environment briefing02

environment briefing02 PRODUCED BY THE SAFETY, HEALTH & ENVIRONMENT GROUP OF THE ENERGY NETWORKS ASSOCIATION - JULY 2006 environment briefing02 transporting electricity Overhead Lines or Underground Cables? Introduction The

More information

DELIVERY & SERVICING PLAN. REDWOOD PARTNERSHIP Consulting Engineers Transportation Planners

DELIVERY & SERVICING PLAN. REDWOOD PARTNERSHIP Consulting Engineers Transportation Planners Redwood Partnership Transportation Limited Maritime House Basin Road North Portslade Brighton BN41 1WR T: 01273 414515 F: 01273 376824 E: consult@redwoodpartnership.co.uk www.redwoodpartnership.co.uk REDWOOD

More information

Appendix 14 Traffic Management Plan

Appendix 14 Traffic Management Plan Appendix 14 Traffic Management Plan Toms Gully Underground Project Table of Contents 1 Purpose... 3 2 Location & Production Overview... 3 3 Operations History... 3 4 Current Traffic Management & Traffic

More information

Proposed Terms of Reference for EIA studies

Proposed Terms of Reference for EIA studies 1 Proposed Terms of Reference for EIA studies Base line data collection will be collected for the Post-Monsoon season 2016 (September to November 2016) in study area and 10 kms radius from project site.

More information

Essex County Council Flood Investigation Report

Essex County Council Flood Investigation Report Essex County Council Stock City of Chelmsford Rev Date Details Author Checked and Approved By 01 February 2015 Draft report for stakeholder consultation Ed Clarke Flood Investigation Engineer Lucy Shepherd

More information

Application by National Grid Gas plc for the River Humber Gas Pipeline replacement (the application)

Application by National Grid Gas plc for the River Humber Gas Pipeline replacement (the application) Application by National Grid Gas plc for the River Humber Gas Pipeline replacement (the application) Examining Authority s (ExA) Record of Unaccompanied Inspection of Sites to Which the Application or

More information

Request for Quotation. Bridge Construction

Request for Quotation. Bridge Construction Request for Quotation Bridge Construction The Comox Valley Regional District (CVRD) is seeking quotations from contractors for the construction of two footbridges and some chainlink fencing at Masters

More information

2015 AVAGO 2D SEISMIC SURVEY ENVIRONMENTAL MANAGEMENT PLAN SUMMARY

2015 AVAGO 2D SEISMIC SURVEY ENVIRONMENTAL MANAGEMENT PLAN SUMMARY ENVIRONMENTAL MANAGEMENT PLAN SUMMARY TABLE OF CONTENTS 1. INTRODUCTION... 3 2. DESCRIPTION OF ACTIVITY... 4 3. DESCRIPTION OF THE ENVIRONMENT... 4 4. DESCRIPTION OF THE ACTIVITY IN RELATION TO THE ENVIRONMENT...

More information

Development proposals will require to demonstrate, according to scale, type and location, that they:-

Development proposals will require to demonstrate, according to scale, type and location, that they:- Appendix 2 : Relevant Development Plan Policies Angus Local Plan Review 2009 Policy S1 : Development Boundaries (a) Within development boundaries proposals for new development on sites not allocated on

More information

Construction Management Plan Template

Construction Management Plan Template Plan Template Planning Permit Number:... Date Planning Permit Issued:... Approval Stamp (Office Use only): Standard Plan Template Project details Company Operational Details.. Directors Name Company Name

More information

ANNEX 2 Emergency / Pollution Incident Response Plan

ANNEX 2 Emergency / Pollution Incident Response Plan ANNEX 2 Emergency / Pollution Incident Response Plan Volume 5 of 5 Appendix 21.1 Annex 2 EPIRP Page 1 of 9 1 WIND FARM CONSTRUCTION ENVIRONMENTAL EMERGENCY / POLLUTION RESPONSE PLAN... 3 1.1 Policy...

More information

VEHICLE CROSSOVER INFORMATION PACK

VEHICLE CROSSOVER INFORMATION PACK VEHICLE CROSSOVER INFORMATION PACK CONTENTS Introduction Section A Section B Section C Section D Section E Criteria for approving a vehicle crossover application (Diagrams to demonstrate measurement criteria)

More information

River Wensum Restoration Strategy Swanton Morley Restoration Scheme Reach 14a

River Wensum Restoration Strategy Swanton Morley Restoration Scheme Reach 14a River Wensum Restoration Strategy Swanton Morley Restoration Scheme Reach 14a At a glance River restoration benefits: Improved planform, channel cross-section, flow variation and sediment process. Improved

More information

LT McGuinness Site 10 Development, Wellington Waterfront. Construction Traffic Management Plan. 7 October 2014

LT McGuinness Site 10 Development, Wellington Waterfront. Construction Traffic Management Plan. 7 October 2014 LT McGuinness Site 10 Development, Wellington Waterfront Construction Traffic Management Plan 7 October 2014 TDG Ref: 12950 141007 ltm ctmp final report.docx LT McGuinness Site 10 Development, Wellington

More information

Welcome Welcome to the public exhibition for development at Bowman Field. This exhibition provides an overview of the proposals for the site.

Welcome Welcome to the public exhibition for development at Bowman Field. This exhibition provides an overview of the proposals for the site. Welcome Welcome to the public exhibition for development at Bowman Field. This exhibition provides an overview of the proposals for the site. Background & Planning Context The Site The site is an area

More information

Devonport EfW CHP Facility. CEMP Proposal for Non Destructive Testing Activities. 1. Introduction

Devonport EfW CHP Facility. CEMP Proposal for Non Destructive Testing Activities. 1. Introduction Devonport EfW CHP Facility CEMP Proposal for Non Destructive Testing Activities. 1. Introduction This application is issued in compliance with the principles of the approved Construction Environmental

More information

Beseck Switching Station Inspection

Beseck Switching Station Inspection Page 1 of 5 Docket No. 272 Development and Management Plan Inspection The Connecticut Light and Power Company Certificate of Environmental Compatibility and Public Need for the construction of a new 345-kV

More information

Construction Management Plan (CMP) Application

Construction Management Plan (CMP) Application About this form Principal Contractor (Applicant) Applicant Details (Person lodging application and main contact for CMP) DA and Site Details Development Consent for Works you are carrying out Construction

More information

SE-10 STORM DRAIN INLET PROTECTION. Objectives

SE-10 STORM DRAIN INLET PROTECTION. Objectives STORM DRAIN INLET PROTECTION SE-10 Objectives Erosion Control - EC Sediment Control - SE Tracking Control - TC Wind Erosion Control - WE Non-Storm Water Management - NS Waste and Materials Management -

More information

K A N S A S DEPARTMENT OF HEALTH AND ENVIRONMENT PERMIT APPLICATION FOR A RECLAMATION FACILITY. 1. Applicant's Name

K A N S A S DEPARTMENT OF HEALTH AND ENVIRONMENT PERMIT APPLICATION FOR A RECLAMATION FACILITY. 1. Applicant's Name K A N S A S DEPARTMENT OF HEALTH AND ENVIRONMENT PERMIT APPLICATION FOR A RECLAMATION FACILITY 1. Applicant's Name Address (Street or Rural Route) (City & State) (Zip) Person to contact Title Phone Fax

More information

Development Management Report

Development Management Report Committee and Date Central Planning Committee 5 th April 2012 Item 13 Public Development Management Report Responsible Officer: Stuart Thomas email: stuart.thomas@shropshire.gov.uk Tel: 01743 252665 Fax:

More information

Transportation of Abnormal Indivisible Loads. Rushy Mead Wind Farm. Prepared for

Transportation of Abnormal Indivisible Loads. Rushy Mead Wind Farm. Prepared for Transportation of Abnormal Indivisible Loads Rushy Mead Wind Farm Prepared for by February 2011 Shaftesbury House, High Street, Eccleshall, Staffs ST21 6BZ Telephone: +44 (0) 1785 850411 Fax: +44 (0) 1785

More information

CONSTRUCTION MANAGEMENT PLAN

CONSTRUCTION MANAGEMENT PLAN CONSTRUCTION MANAGEMENT PLAN for CHILDRENS CENTRE, PRIMARY CLASSROOM & REPLACEMENT PRESCHOOL AT CLYST ST MARY PRIMARY SCHOOL EXETER, DEVON EX5 1BG REVISION A 7 May 2010 1 P a g e Mansell have been appointed

More information

Sustainable Resource Management Ltd

Sustainable Resource Management Ltd 6.0 Predicted nvironmental Impacts 6. Stages and Impacts Considered An nvironmental Impact Analysis has been carried out whereby all the possible environmental, socio economic and health & safety aspects

More information

INTRODUCTION... 3. 1.0 Purpose... 4. 2.0 Policy... 4. Exception for Short-Term Workplace Visits... 4. Relevant Legislation and Regulations...

INTRODUCTION... 3. 1.0 Purpose... 4. 2.0 Policy... 4. Exception for Short-Term Workplace Visits... 4. Relevant Legislation and Regulations... March 2006 INTRODUCTION... 3 1.0 Purpose... 4 2.0 Policy... 4 Exception for Short-Term Workplace Visits... 4 Relevant Legislation and Regulations... 5 Definitions... 5 Contractor Safety Coordination Overview...

More information

Guide to agrichemical use in Resource Management Plans Northland Region as at October 2011

Guide to agrichemical use in Resource Management Plans Northland Region as at October 2011 Guide to agrichemical use in Resource Management Plans Northland Region as at October 2011 Northland Regional Air Quality Plan Note: This guide is intended to assist users and applicators understanding

More information

Construction Management Statement. Introduction. Contents

Construction Management Statement. Introduction. Contents Construction Management Statement Project Name Dee Point Primary School Introduction On all Morgan Sindall projects, the safety and welfare of all is of paramount importance. This document concentrates

More information

Permit Number: 3.1/062712/CP

Permit Number: 3.1/062712/CP POLLUTION PREVENTION AND CONTROL ACT 1999 ENVIRONMENTAL PERMITTING (ENGLAND AND WALES) REGULATIONS 2010 (amended) Permit Number: 3.1/062712/CP Installation Address: Bardon Concrete Warren Street Attercliffe

More information

FILM-MAKERS CODE OF PRACTICE BATHFILMOFFICE

FILM-MAKERS CODE OF PRACTICE BATHFILMOFFICE FILM-MAKERS CODE OF PRACTICE Produced by the BATHFILMOFFICE Bath Film Office, Abbey Chambers, Abbey Churchyard Bath, BA1 1LY Tel: 01225 477711 Fax: 01225 396442 E-Mail: bath_filmoffice@bathnes.gov.uk Any

More information

PROPOSED RESIDENTIAL DEVELOPMENT LAND OFF MACCLESFIELD OLD ROAD, BUXTON. Construction Management Plan

PROPOSED RESIDENTIAL DEVELOPMENT LAND OFF MACCLESFIELD OLD ROAD, BUXTON. Construction Management Plan PROPOSED RESIDENTIAL DEVELOPMENT LAND OFF MACCLESFIELD OLD ROAD, BUXTON Construction Management Plan May 2013 CONTENTS Page No: 1.0 INTRODUCTION 1 2.0 PROJECT ORGANISATION AND RESPONSIBILITIES 2 2.1 Client

More information

Development Management Officer Report Committee Application. Summary

Development Management Officer Report Committee Application. Summary Development Management Officer Report Committee Application Summary Committee Meeting Date: 15 Dec 2015 Item Number: Application ID: Z/2014/0978/F Target Date: 31 st October 2014 Proposal: Single storey

More information

SUSTAINABLE URBAN DRAINAGE SYSTEMS

SUSTAINABLE URBAN DRAINAGE SYSTEMS overflow can lead into a permeable conveyance system to increase further the benefit and reduce the need for pipe systems. Pollutant removal rates have been shown to be high, with some pollutants being

More information

Outlet stabilization structure

Outlet stabilization structure Overview of Sedimentation and Erosion Control Practices Practice no. 6.41 Outlet stabilization structure Erosion at the outlet of channels, culverts, and other structures is common, and can cause structural

More information

MBJ Environmental Programmes

MBJ Environmental Programmes MBJ Airports Limited Environmental Policy The following is MBJ Airports Limited s (MBJ) Environmental Policy for Sangster International Airport (SIA): Integrate environmental management measures with planning,

More information

City of Paso Robles Community Development Department Construction Site Storm Water Quality Requirements

City of Paso Robles Community Development Department Construction Site Storm Water Quality Requirements City of Paso Robles Community Development Department Construction Site Storm Water Quality Requirements Overview of the City s Construction Storm Water Program The City of Paso Robles is committed to protecting

More information

Recommendations for future developments

Recommendations for future developments C Recommendations for future developments C.1 Reducing flood risk through site layout and design C.1.1 C.1.2 Flood risk should be considered at an early stage in deciding the layout and design of a site

More information

1 Welcome. The exhibition comprises a series of boards which provide some background information to show you our initial ideas for the site.

1 Welcome. The exhibition comprises a series of boards which provide some background information to show you our initial ideas for the site. 1 Welcome Thank you for taking the time to attend this public exhibition of our proposals for residential development on Land at Daws Farm, Back Road, Writtle (site shown opposite). The exhibition comprises

More information

Emergency Spillways (Sediment basins)

Emergency Spillways (Sediment basins) Emergency Spillways (Sediment basins) DRAINAGE CONTROL TECHNIQUE Low Gradient Velocity Control Short-Term Steep Gradient Channel Lining Medium-Long Term Outlet Control Soil Treatment Permanent [1] [1]

More information

10.1 WILL HEY FARM WATFORD LANE NEW MILLS RETENSION OF NEW STABLE BLOCK, SAND PADDOCK AND ASSOCIATED EARTHWORKS AND LANDSCAPING (FULL - MINOR)

10.1 WILL HEY FARM WATFORD LANE NEW MILLS RETENSION OF NEW STABLE BLOCK, SAND PADDOCK AND ASSOCIATED EARTHWORKS AND LANDSCAPING (FULL - MINOR) HPK/2012/0207 03/04/2012 WILL HEY FARM WATFORD LANE NEW MILLS MR & MRS M WILSON KIRSTY WILSON EQUINE AND WILL HEY FARM BED & BREAKFAST RETENSION OF NEW STABLE BLOCK, SAND PADDOCK AND ASSOCIATED EARTHWORKS

More information

Environmental guidelines for preparation of an Environment Management Plan

Environmental guidelines for preparation of an Environment Management Plan Environmental guidelines for preparation of an Environment Management Plan Environment Protection Authority MAY 2013 Australian Capital Territory, Canberra 2013 This work is copyright. Apart from any use

More information

A2 Pepperhill to Cobham Highway Widening project, UK

A2 Pepperhill to Cobham Highway Widening project, UK Further information Skanska AB www.skanska.com Contact Noel Morrin, Senior Vice President Sustainability noel.morrin@skanska.se A2 Pepperhill to Cobham Highway Widening project, UK Case Study 40 Aspects

More information

Site Deliverability Statement Development at: Beech Lane, Kislingbury. Persimmon Homes Midlands March 2015

Site Deliverability Statement Development at: Beech Lane, Kislingbury. Persimmon Homes Midlands March 2015 Site Deliverability Statement Development at: Beech Lane, Kislingbury Persimmon Homes Midlands March 2015 Contents Site Deliverability Statement Development at: Beech Lane, Kislingbury 1.INTRODUCTION 1.1

More information

This document must be read in conjunction with the Permit to Work and Service Interruption Notice policy.

This document must be read in conjunction with the Permit to Work and Service Interruption Notice policy. UNIVERSITY OF HERTFORDSHIRE HIGHER EDUCATION CORPORATION SITE RULES FOR CONTRACTORS The University s Site Rules for Contractors are issued on the authority of the Director of Estates, Hospitality and Contract

More information

Reference: 05/00928/FUL Officer: Mr David Jeanes

Reference: 05/00928/FUL Officer: Mr David Jeanes DEVELOPMENT CONTROL BOARD 5 January 2006 Reference: 05/00928/FUL Officer: Mr David Jeanes Location: Proposal: Applicant: Whiffens Farm Clement Street Sutton-At-Hone Kent BR8 7PQ Retrospective application

More information

23.1 RENEWABLE ENERGY

23.1 RENEWABLE ENERGY Proposed Hastings District Plan as Amended 23.1 Renewable Energy 23.1 RENEWABLE ENERGY 23.1.1 INTRODUCTION The use of energy is of fundamental importance to the function and development of our society.

More information

HIGHWAYS ACT 1980 SECTION 171 : LICENCE APPLICATION PACK. Consent to deposit building materials and making of excavations in the Public Highway

HIGHWAYS ACT 1980 SECTION 171 : LICENCE APPLICATION PACK. Consent to deposit building materials and making of excavations in the Public Highway HIGHWAYS ACT 1980 SECTION 171 : LICENCE APPLICATION PACK Consent to deposit building materials and making of excavations in the Public Highway All Correspondence to : Reading Borough Council Highways Department

More information

3. QUALITY ASSURANCE REQUIREMENTS

3. QUALITY ASSURANCE REQUIREMENTS 3. QUALITY ASSURANCE REQUIREMENTS 3.1 General This section covers the Kaipara District Council requirements for monitoring and testing of physical asset construction to ensure that the final asset delivered

More information

Chapter 12: Impacts, Mitigation, Cumulative Impacts and Residual Effects

Chapter 12: Impacts, Mitigation, Cumulative Impacts and Residual Effects Chapter 12: Impacts, Mitigation, Cumulative Impacts and Residual Effects REnescience Northwich Quality Management Prepared by: Tom Dearing Senior Environmental Consultant 02/10/15 Reviewed & checked by:

More information

White Rose Carbon Capture and Storage (CCS) Project Document Ref: 8.5 - Rev. 2 PINS Ref: EN10048

White Rose Carbon Capture and Storage (CCS) Project Document Ref: 8.5 - Rev. 2 PINS Ref: EN10048 White Rose Carbon Capture and Storage (CCS) Project Document Ref: 8.5 - Rev. 2 PINS Ref: EN10048 The White Rose CCS (Generating Station) Order Land adjacent to and within the Drax Power Station, Drax,

More information

ENVIRONMENTAL CODE OF PRACTICE FOR CONCRETE BATCH PLANT & ROCK WASHING OPERATIONS

ENVIRONMENTAL CODE OF PRACTICE FOR CONCRETE BATCH PLANT & ROCK WASHING OPERATIONS ENVIRONMENTAL CODE OF PRACTICE FOR CONCRETE BATCH PLANT & ROCK WASHING OPERATIONS PREPARED BY: DEPARTMENT OF ENVIRONMENT AND LANDS INDUSTRIAL ENVIRONMENTAL ENGINEERING DIVISION APRIL 16, 1992 - TABLE OF

More information

TRAFFIC MANAGEMENT PLAN AND TRUCK DRIVER CODE OF PRACTICE

TRAFFIC MANAGEMENT PLAN AND TRUCK DRIVER CODE OF PRACTICE TRAFFIC MANAGEMENT PLAN AND TRUCK DRIVER CODE OF PRACTICE Gunnedah Quarry Products Pty Ltd Gunnedah, NSW AUGUST 2014 QUALITY ASSURANCE This document has been prepared, checked and released in accordance

More information

Health and Safety Office

Health and Safety Office Health and Safety Office Topic: Driving at Work Policy Date: January 2010 Version: 3.0 Revision Date; Revision Date 2012 Scope: The following policy and guidance outlines health and safety precautions

More information

FALLING OBJECTS EXCESSIVE NOISE CHAINSAW & CHIPPER WORK AT HEIGHTS MANUAL HANDLING

FALLING OBJECTS EXCESSIVE NOISE CHAINSAW & CHIPPER WORK AT HEIGHTS MANUAL HANDLING JOB NO: PROJECT: DATE: SWMS NO: SWMS 001.1 PREPARED BY: Ian Hartley REVISED BY: Nick Bragg & Cameron McNeil ACTIVITY: TREE REMOVAL & PRUNING SIGNED BY: REVISION DATE: December 2015 MINIMUM PERSONAL PROTECTIVE

More information

Celebrating over 50 years of service MEMORANDUM

Celebrating over 50 years of service MEMORANDUM Celebrating over 50 years of service MEMORANDUM TO: Town of Tyre Ronald F. McGreevy, Supervisor JN. 1650.001.001 FROM: Adam Cummings, P.E., BCEE DATE: 3 September 2015 SUBJECT: Project Proposal SEQRA Documentation

More information

Construction Site Inspection. Inspecting to Keep You in Compliance

Construction Site Inspection. Inspecting to Keep You in Compliance Construction Site Inspection Inspecting to Keep You in Compliance Inspection/Monitoring/Reporting Know if your plan is working Document corrective actions Ketchikan A Contractor that destroys their site

More information

G9 Offshore wind health and safety association

G9 Offshore wind health and safety association G9 Offshore wind health and safety association 2013 annual incident data report www.g9offshorewind.com About the G9 Offshore wind health and safety association The primary aim of the G9 is to deliver world

More information

Managing Public Use of Freeway Emergency Access Gates and Median Crossovers

Managing Public Use of Freeway Emergency Access Gates and Median Crossovers Managing Public Use of Freeway Emergency Access Gates and Median Crossovers Operational Instruction Transport Services Division TRAFFIC MANAGEMENT Operational Instructions Managing Public Use of Freeway

More information

NON-TECHNICAL SUMMARY OF ENVIRONMENTAL AND SOCIAL IMPACT ASSESSMENT FOR THE BAHCE WINDFARM PROJECT (135 MW)

NON-TECHNICAL SUMMARY OF ENVIRONMENTAL AND SOCIAL IMPACT ASSESSMENT FOR THE BAHCE WINDFARM PROJECT (135 MW) Zorlu Plaza, 34310 Avcılar ISTANBUL / TURKIYE Tel: + 90 (212) 456-2300 Fax: +90 (212) 422-0099 www.zorlu.com.tr NON-TECHNICAL SUMMARY OF ENVIRONMENTAL AND SOCIAL IMPACT ASSESSMENT FOR THE BAHCE WINDFARM

More information

Compliance Noise Monitoring

Compliance Noise Monitoring Monitoring Byron Centre The Manse Road Myocum HEALTH SCIENCE ENVIROMENTAL EDUCATION ENVIRONMENTAL AUDITOR Monitoring Byron Centre The Manse Road Myocum Prepared for: Byron Shire Council Version 1.0 Date:

More information

UNDERGROUND TELECOMMUNICATIONS CABLES ACROSS PRIVATE LAND

UNDERGROUND TELECOMMUNICATIONS CABLES ACROSS PRIVATE LAND FACT SHEET TELEPHONE 0800 327 646 I WEBSITE WWW.FEDFARM.ORG.NZ UNDERGROUND TELECOMMUNICATIONS CABLES ACROSS PRIVATE LAND BACKGROUND The Rural Broadband Initiative envisages substantially improved broadband

More information

Physical Security Assessment Form

Physical Security Assessment Form Physical Security Assessment Form Security Self-Assessment T Wake 10 February 2012 Security Assessment Contents Facility / Site Security Assessment Form... 3 Identification Details... 3 Facility Details...

More information