Assessment of options for using coal seam gas water in the Central Condamine Alluvium: Business case

Size: px
Start display at page:

Download "Assessment of options for using coal seam gas water in the Central Condamine Alluvium: Business case"

Transcription

1 Healthy HeadWaters Coal Seam Gas Water Feasibility Study Assessment of options for using coal seam gas water in the Central : Business case Prepared for the Department of Natural Resources and Mines April 2013

2 This document presents outcomes of Activity 8.3 of the Healthy HeadWaters Coal Seam Gas Water Feasibility Study. The has analysed the opportunities for, and the risks and practicability of, using coal seam gas water to address water sustainability and adjustment issues in the Queensland section of the Murray-Darling Basin. The study was funded with $5 million from the Commonwealth Government, with support from the Queensland Government, as part of the Healthy HeadWaters Program, which is Queensland s priority project funded through the Commonwealth Government s Water for the Future initiative. The study was managed by the Queensland Department of Natural Resources and Mines (DNRM). This report was prepared by Arup for the State of Queensland. Disclaimers This document was prepared exclusively for the State of Queensland (Department of Natural Resources and Mines) and is not to be relied upon by any other person. Arup has made every effort to ensure that the information provided is accurate but errors and omissions can occur and circumstances can change from the time that the document was prepared. Therefore, except for any liability that cannot be excluded by law, Arup excludes any liability for loss or damage, direct or indirect, from any person relying (directly or indirectly) on opinions, forecasts, conclusions, recommendations or other information in this report or document. State of Queensland The State gives no warranty in relation to the contents of this report (including accuracy, reliability, completeness, currency or suitability) and accepts no liability (including without limitation, liability in negligence) for any loss, damage or costs (including consequential damage) relating to any use of the contents of this report. Acknowledgements The authors would like to acknowledge that this report builds on other work undertaken under Activity 8 of the. This includes reports by KBR Infrastructure options for delivering coal seam gas water to the Central, Klohn Crippen Berger Injection of coal seam gas water into the Central Site prioritisation, Schlumberger Water Services Field program design for injection trials in the Central and Tree Crop Technologies Assessment of alternative use options for coal seam gas water proposed for Central recharge schemes. In addition this report includes work by Schlumberger Water Services on modelling the response of the water levels to injection, which is included as Appendix C. The report also includes work by KBR on the design and costing of water delivery infrastructure within in the text and presented in Appendix D.

3 Executive Summary Coal seam gas (CSG) development in Queensland is expanding rapidly in order to supply an emerging liquefied natural gas export industry. The expansion in CSG development will result in significant quantities of groundwater being brought to the surface, presenting a challenge for the CSG industry for management and disposal. Initial phases of the Healthy HeadWaters Study (HHW Study) consisted of investigations aimed at understanding the impacts of extracting and using CSG water, as well as analyses on the likely supply of, and demand for, CSG water. The final phase of the HHW Study focussed primarily on options for large-scale beneficial use of CSG water. Several years ago, it was identified that there may be an opportunity to use treated CSG water to recharge the Central (CCA), which has been depleted by over-extraction for irrigation over several decades. Recharging the CCA could provide a disposal mechanism for a large volume of treated CSG water, while also helping to secure the sustainability of this important groundwater resource which supplies water to a $100 million agricultural area. This business case aims to examine this opportunity, and to provide a way forward for developing and implementing a CSG water recharge scheme in the CCA. Aquifer recharge can be achieved either through injection via bores and infiltration trenches or by substitution where water is supplied to groundwater users in lieu of groundwater allocations, thereby reducing take from the aquifer and allowing natural recharge. The method that provides the greatest recharge efficiency is obviously preferable. Investigations and subsequent stakeholder discussions have indicated that a substitution scheme would be impractical to implement unless it included injection as a means of dealing with CSG water when it is not required for irrigation (such as during wet periods or between growing seasons). The recommended option that has been identified in this business case is an injection only scheme to recharge the CCA. The option represents a superior approach both environmentally and relating to on-farm water practices. Securing Arrow Energy s commitment to an injection scheme in the CCA could result in recharge of approximately 40 per cent of the Cecil Plains area of the CCA. Injecting CSG water into the CCA under an approach of this nature provides a once-in-a-lifetime opportunity to improve the security of the groundwater resource in the alluvium. However if agreement on scheme design and a firm implementation path for an injection scheme are not committed to in the next six to twelve months, then it is likely that a substitution only scheme will be built. Once a substitution only scheme is built, it is unlikely that the additional capital costs to build an injection scheme would be supported, and therefore the opportunity for maximising recharge benefits for the CCA (and the Murray-Darling Basin) will be lost. Further, it is recommended that the recharge be a staged process, where following successful injection trials, a scheme is sized to inject water based on that produced by Arrow Energy s proposed water treatment facility near Cecil Plains. Final 30 April 2013 Arup Page i

4 The potential costs for deep and shallow injection site trials would be in the order of $2.4 million and $2.49 million per site, respectively. Concurrent with this scheme, work should commence on confirming the availability of additional CSG water, such that an expanded scheme that includes additional water from the Chinchilla South area can be progressed at a suitable stage in the near future. This expanded scheme would extend the life of the injection scheme and could fully recharge the Cecil Plains area. This expanded scheme could supply approximately 40 per cent of the current water deficit in the CCA and provide a key pathway for CSG water disposal. All stakeholders agree in principle that a scheme involving injection would provide the most potential benefits, both environmentally for the CCA (and Murray-Darling Basin), and from the perspective of minimising the disruption to existing water allocation and on-farm use of water. The following recommendations are proposed as the next steps in progressing with the implementation of an injection scheme in the CCA and to resolve any outstanding issues in relation to this scheme. Recommendation Recommendation 1 Recommendation 2 Recommendation 3 Recommendation 4 Recommendation 5 Recommendation 6 Recommendation 7 Description That the Queensland government identify and appoint a lead agency to be responsible for managing the next phases of work identified as a consequence of the opportunities identified in this business case. That the Queensland Government lead the development and execution of injection trials in the CCA (at a total cost of approximately $5 million) as a matter of priority so that feasibility of aquifer injection can be more clearly demonstrated. In support of Recommendation 2, the Queensland and Commonwealth Governments and Arrow Energy seek agreement on implementing an injection only scheme to enable the favoured injection option to be pursued. That Queensland Government and Arrow Energy commence discussions on an approvals process as well as a legal framework for the management of liability issues associated with an injection scheme in the CCA. That Queensland Government, Arrow Energy and other relevant CSG companies agree a community engagement process for the implementation of an injection scheme including the following stakeholders: The communities who draw all or part of their water supply from the Condamine alluvium; and Communities outside the CCA from which water could be exported if an expanded injection scheme were to be pursued That Government lead the development of a funding model for an injection scheme in the CCA. Implementing an injection scheme will involve considerable up front capital costs and operating costs. This funding model should agree the quantum of costs to be met by Arrow Energy. Additional consideration should also be given to additional sources of funding to meet the costs of the scheme and any subsequent commercial arrangements. That the Queensland Government engage with the western tenement holders to explore the scope and potential for expanding the injection scheme to conditions outlined in Option 1C. Final 30 April 2013 Arup Page ii

5 About this document This document presents a business case that assesses the feasibility of using treated CSG water to recharge the CCA, and identifies the steps that need to be taken to progress the development of a CCA recharge scheme. This business case is presented in three sections: 1. Part A Business case background and rationale, including an overview of precursor studies, a description of the regional context and drivers for the project, a review of relevant policy and legislative frameworks, and an overview of stakeholder consultation processes and outcomes; 2. Part B Assessment of the recharge scheme options, including a detailed description of the options, the methodology used to undertake the qualitative and quantitative assessments presented in this business case, and presentation and discussion of the results; and 3. Part C Critical analysis of the results, and a proposed mechanism to progress the recommended option, including an analysis of the benefits, challenges and opportunities presented by both the substitution and injection options. This section also recommends a preferred option and sets out a series of recommendations for the next stage of the process to implement a CCA recharge scheme. Technical inputs to the HHW Study A number of research activities were commissioned to contribute to specific elements of the HHW Study, and which have supported the development of this report. These activities, and the organisations which undertook them, are described below: Activity 2: Modelling and forecasting of CSG water production Klohn Crippen Berger (KCB) developed a Water Production Tool capable of forecasting, from an industry-wide perspective, where, when and how much CSG water will be produced in the Surat and southern Bowen basins. This tool was used to estimate where, when, and how much CSG water is likely to be produced over the next 40 years that could be transported to the CCA. For the purpose of the business case, these estimates were supplemented by estimates provided by Arrow Energy of the CSG water likely to be produced on its tenements close to the CCA. Activity 6: Aquifer injection feasibility KCB conducted a desktop assessment of the technical feasibility of injecting treated CSG water into the CCA. The assessment concluded that injection of reverse osmosis (RO) treated CSG water into the aquifers of the CCA is likely to be technically feasible. It also developed a prioritised list of the 12 highest potential injection targets across the CCA (seven shallow injection targets and five deep injection targets). In addition, it identified that a better understanding of the local hydraulic relationship between the Walloon Coal Measures (WCM) and the CCA was needed to assess the likely impacts and outcomes of injection at specific sites in the CCA. Final 30 April 2013 Arup Page iii

6 KCB s investigations concluded that a field program incorporating injection trials, groundwater monitoring and geophysical assessments was required to more definitively assess the feasibility of injecting CSG water into the CCA. Activity 8.2: Field program design for injection trials in the Central Schlumberger Water Services (SWS) designed and developed a detailed program of work to implement a field program for aquifer injection trials to contribute to the assessment of: a) The feasibility of injecting CSG water into the CCA; and b) The hydrogeological relationship between the WCM and the CCA. SWS also developed and costed an indicative design for the infrastructure required to operate long-term aquifer injection activities at one shallow and one deep site in the CCA. The design and costings have been used in the development of this business case. SWS also conducted additional work on modelling the response of the water levels in the CCA to injection. Activity 8.1: Infrastructure options for delivering CSG water to the Central Kellogg Brown and Root (KBR) was engaged to investigate and evaluate the physical infrastructure required to deliver CSG water to the CCA from the identified source area. This work also estimated approximate order of magnitude costs of the proposed schemes, including costs associated with the construction, operation and maintenance of pipeline infrastructure, expressed in absolute terms as well as per megalitre (per ML) of water delivered (Activity 8.3). Activity 8.3B: Comparative assessment of CSG water uses Tree Crop Technologies compared the benefits, costs and feasibility of proposed CCA recharge scheme options with a range of realistic alternative options for the same CSG water. Activity 8.3C: Business case development Arup was engaged to develop this business case and facilitate a number of workshops with stakeholders. These stakeholders were involved in the quantitative and qualitative assessments completed as part of this assessment. This business case incorporates all of the previous work completed as part of the HHW Study. Stakeholder consultation Formal and informal consultation in the development of this business case occurred through a Stakeholder Reference Group. This group included diverse stakeholders with an interest in the HHW Study and the associated technical and economic analysis presented in this business case. Involvement from industry, government and community stakeholders has been crucial to achieving the Final 30 April 2013 Arup Page iv

7 objectives and outcomes of earlier work and in developing the options presented in the business case. There remains considerable concern from the community in relation to the growing level of activity from CSG companies within the Surat Basin and the economic and social issues associated with the potential impacts on aquifers and management of CSG water. These concerns have been highlighted in this business case along with specific issues from major stakeholder groups who participated in the development of the business case. Current issues within the CCA Since the 1960s, the groundwater resources of the CCA have been developed intensively, and at a rate that is unsustainable in the long term. Irrigation in the CCA expanded dramatically in the 1960s, and by 1969 it became evident that the aquifer system in the central part of the area was becoming depleted. Various measures have since been introduced to reduce groundwater use, including metering, water charges, and announced annual allocations. Between 1990 and 2004, average annual groundwater use in the CCA was about 66 gigalitres (GL). Announced entitlements since 2010 have restricted the maximum allowable use to 55 gigalitres per annum (GL/a). Despite these reductions in use, depletion of the aquifer has continued. In the intensely developed area east of Cecil Plains, water levels are estimated to have fallen by as much as 26 m. The natural gradients of flow in the aquifer have been replaced by a large zone of depression east of Cecil Plains, and a smaller depletion zone around Macalister. Accessing groundwater in some areas has become more difficult and/or costly as the water table has fallen. Some groundwater users are now unable to access all of their licensed entitlement, and instead seasonally assign it to other groundwater users. In 2009 the Queensland Government commenced a process to amend the Condamine and Balonne Water Resource Plan to include the CCA. This amendment was initiated to provide a framework in which to address the overallocation of the groundwater system. The amendment to the water resource plan has been deferred to allow for the introduction of the Australian Government s Murray-Darling Basin Plan (the Basin Plan), which specifies limits on how much water can be taken from surface water and groundwater systems in catchments of the Murray-Darling Basin, including the CCA. These long-term average sustainable diversion limits (SDLs) reflect the maximum amount of water that can be taken without compromising the environmental integrity and productive base of the water resource. The Australian Government has also announced that it will purchase water entitlements to align current levels of use with SDLs throughout the Murray- Darling Basin. The Basin Plan, including the SDLs will be reviewed in 2019 to ensure the objectives of the plan are being achieved. There remains the possibility that the SDL could be further reduced if aquifer levels do not stabilise at acceptable levels. Final 30 April 2013 Arup Page v

8 CSG water production in the Surat Basin There are four major CSG companies operating in Queensland: Arrow Energy, Queensland Gas Company (QGC), Origin Energy and Santos. Most of Arrow Energy tenements are near the CCA, while Origin Energy and QGC tenements lie between Millmerran and Roma following the Walloon coal outcrop. The majority of tenements owned by Santos are around Roma and further north. CSG in the Surat Basin is sourced from the WCM, a sequence of layers of coal, mudstones and sandstones. The thickness of this sequence may be up to 700 m, but on average is of the order of 300 m. The WCM is also part of the Great Artesian Basin (GAB), and lies above and below several regionally significant GAB aquifers, such as the Hutton Sandstone and the Springbok Sandstone. Large volumes of water need to be extracted from the WCM in order to produce CSG. Under Queensland s regulatory framework for CSG water, CSG operators are responsible for finding an environmentally safe way to use or dispose of the water that they produce. CSG operators are required to present their strategies for managing the CSG water associated with a given project in the project s environmental impact statement (EIS) and environmental management plan (EMP). The EMP typically includes a separate CSG water management plan. A major challenge in managing CSG water, and in identifying opportunities for its use, is predicting how much will be produced over space and time as the industry develops. Rates of CSG water production vary considerably from one location to the next due to the variable physical properties of the coal measures. In addition, the industry s development plans are constantly evolving, so there will always be some uncertainty about which areas will be developed, and in which order. For these reasons, estimates of future CSG water volumes are always uncertain, and will change over time as new information becomes available. However, the water production tool developed for this study was used to develop spatial estimates of how much water could be available over time in the region surrounding the CCA. The findings are presented below. Source area Cumulative water production Chinchilla West 419 GL ( ) Chinchilla South 509 GL ( ) CCA North 99 GL ( ) CCA Central 56 GL ( ) CCA South 90 GL ( ) The extraction of these water volumes from the WCM in the Surat Basin to produce CSG is expected to result in the drawdown of water levels of the aquifers lying above or below the coal measures. Among the aquifers which may be affected is the CCA, which is incised into the eastern margin of the WCM. The nature of the hydraulic connectivity between the two units is a subject of ongoing investigation, but it is believed to be such that the reduced pressure in the WCM due to CSG water extraction will result in some water being drawn from the CCA down into the coal measures. Final 30 April 2013 Arup Page vi

9 On the basis of modelling undertaken, the Office of Groundwater Impact Assessment estimated that in the region of maximum impact, the extraction of CSG water from the underlying WCM will reduce groundwater levels within the CCA by up to 1.2 m. Potential for beneficial use of treated CSG water The primary driver for using CSG water to recharge the CCA is to help secure the long-term viability of the aquifer, both as an economic resource and an environmental asset. While there is now a process in place under the Basin Plan to reduce groundwater extraction to a sustainable level, there are still benefits to be gained by increasing the amount of water in the aquifer, above and beyond the rate of natural recharge. As discussed, groundwater modelling undertaken to date for the Office of Groundwater Impact Assessment suggests that some 110 GL could be lost from the CCA as a result of CSG water extraction over a 100 year period. CSG companies are obliged to make good any associated impacts to individual water bores. Impacts to individual bores aside, such losses will work against existing efforts to reduce groundwater extraction to a sustainable level. Assuming that licensed extraction for agriculture and other uses is brought in line with the SDL, the loss of additional water due to CSG operations could result in further depletion of the aquifer. Under the Basin Plan the State would have to account for all impacts due to CSG activities as part of the audit process. In principle, recharging the CCA aquifer directly (via injection) or indirectly (via substitution) using treated CSG water could offset the impacts of CSG operations on the CCA. The proposed injection arrangements would go beyond the predicted CSG impacts, resulting in amelioration of previous over extraction of the CCA. Legislative and policy context Community apprehension over the continued expansion of the CSG industry within the Surat Basin is well documented. Primarily, concerns relate to perceptions of the risks associated with CSG extraction causing water and air pollution, the release of fugitive emissions, land usage and access conflicts, and concerns over the adequacy of Government s assessment and regulation of these potential impacts. In recent years both the Queensland and Commonwealth Governments have continued to strengthen legislative and regulatory frameworks and oversight of the industry through various agencies and commissions in response to these community concerns. Any future proposals to use CSG water for any purpose in the CCA need to ensure that they are consistent with these policies and legislative and regulatory frameworks. CSG and CSG water extraction, management and disposal are primarily regulated by State (Queensland) legislation. However, the Commonwealth Government has recently announced its intention to extend the requirement for Commonwealth approval to apply to CSG or large coal mining projects where water resources have the potential to be impacted. If the legislative amendments are made this Final 30 April 2013 Arup Page vii

10 would mean that water resources impacted by CSG projects will form a Matter of National Environmental Significance under Part 3 of the Environmental Protection and Biodiversity Conservation Act A Water Management Plan applying to the groundwater resources of the Upper SDL area was declared on 10 August This plan qualifies as an interim Water Resource Plan (WRP) for the purposes of the Commonwealth Water Act 2007 and has been made to ensure that water users in the Upper s are eligible to participate in the Commonwealth water recovery program. The plan mirrors the requirements set for future management of groundwater in the established in the Basin Plan. The legislative and policy context for CSG water extraction and its relevance to this proposed recharge scheme is discussed extensively in this business case. Recharge scheme options considered by this business case Based on information about the likely availability of CSG water and the technical feasibility of aquifer injection and groundwater substitution, three recharge scheme options were developed for detailed consideration in this business case: Option 1 Injection only; Option 2 Injection plus substitution to licence-holders land abutting injection pipelines; and Option 3 Injection plus substitution to a greater area of licence-holders land to meet a peak delivery period of at least 20 years. These options were compared against a Baseline Substitution Option which is indicative of a groundwater substitution scheme which could be implemented by Arrow Energy supplying water from its water treatment facility. All three recharge scheme options have been developed to deliver water to five injection sites (two deep and three shallow) which were identified by an earlier site prioritisation study. These five sites were chosen for their proximity to the intensively irrigated Cecil Plains area and to Arrow Energy s proposed Water Treatment Facility 9 (WTF9), which is assumed to be a common supply point for all options. In addition to this infrastructure, a 145 km pipeline from an assumed water treatment facility in the Chinchilla South area to the off-take point from WTF9 was also included. Pipelines were sized to accommodate the peak delivery volumes for each scheme, and were located where possible within existing corridors, easements, road reserves or adjacent to cadastral boundaries, and to minimise high elevation areas and watercourse crossings. All aspects of this water delivery infrastructure for each of the options were designed and costed in earlier phases of this study. In addition to the recharge scheme options, three different water supply profiles were applied to each of the options, meaning a total of 10 options were considered (three injection only options and six hybrid injection-substitution options and the Baseline Substitution Option). These water supply profiles featured different Final 30 April 2013 Arup Page viii

11 benefit periods, peak supply periods and total water supply volumes, all of which impacted on the financial viability of the options. These profiles are as follows: Water supply profile A - all water is supplied by Arrow Energy from its WTF9 no Chinchilla South water import is considered. This water supply profile determines the peak supply rate of 21.4 GL/a (based on the peak volumes) adopted for all other profiles and options considered by the business case. A peak supply period of 10 years is assumed for this profile because the average production in of 18.8 GL/a is sufficiently close to 21.4 GL/a. In total 351 GL of treated CSG water is supplied over 35 years. Water supply profile B - builds on water supply profile A by importing treated CSG water from the Chinchilla South supply area according to the predicted CSG water production in that area commencing in Imported water is capped at the peak supply rate determined by water production profile A, i.e. not all the water available from Chinchilla South is imported (only 226 GL of a potential 503 GL). This extends the peak supply period to the CCA from 10 to 20 years. Under this profile 577 GL of treated CSG water is supplied over a period of 35 years. Water supply profile C - builds on water supply profile A by importing treated CSG water from the Chinchilla South area. However, in this case it is assumed that production in the Chinchilla South area may be delayed by a period of 10 years. Imported water is still capped at the peak supply rate determined by water supply profile A, but the delay in the Chinchilla South production allows more of this water to be imported, and extends the peak supply period from 10 years to 30 years. Under this profile, 846 GL of treated CSG water is supplied to the CCA over 50 years, extending the supply period by 15 years. The business case also considers the approximate water demand profile reflected in current water use practices (and therefore demand) on the CCA, particularly in the Cecil Plains area. This demand profile is particularly problematic for the Baseline Substitution Option. Quantitative and qualitative analysis In order to assess the benefits and key issues associated with each of the ten options discussed in this business case, a combined qualitative and quantitative assessment methodology was applied. The purpose of the combined qualitative and quantitative assessment was to develop an overall ranking for each of the options (with reference to a set of pre-determined objectives). The assessment process is broadly described overleaf, with the comprehensive list of assumptions and scoring approach detailed later in relevant sections of the business case. Final 30 April 2013 Arup Page ix

12 Key observations from the qualitative assessment showed that: Option 1 (injection only scheme), regardless of the water supply profile is qualitatively superior. This outcome reflects the objective of the scheme which is to restore water levels in the CCA and the lower administrative burden for implementing a pure injection scheme; and Scores for Option 2 and 3 (all water supply profiles) are also qualitatively superior to the Baseline Substitution Option, which is the least preferred option due to its poorer environmental outcomes. The quantitative assessment results are less open to interpretation with results presented at a Net Present Cost (NPC) and NPC per megalitre of water (NPC/ML) for each of the options and water supply profiles. The key findings are discussed below and presented in the table overleaf. The quantitative analysis indicated that the Baseline Substitution Option required the lowest investment across the life of the project (NPC of $93 million), compared with all other options. This would indicate that (using the assumptions applied in this business case), a substitution only scheme is less costly to build and operate than an injection scheme or a hybrid injection/substitution scheme. However, this represents the lowest possible cost for the Baseline Substitution Option and if the assumptions are not met (for example, if not all licence-holders are willing to accept substitution) the cost of this option could be significantly higher. The Baseline Substitution Option only uses the anticipated CSG water from Arrow Energy s CCA tenements. From Arrow Energy s perspective, this option potentially presents technically the most feasible option to implement because it is able to proceed immediately with no requirements to modify legislation and regulations and would be fully funded using its own investment. Notwithstanding the administrative challenges associated with contracting agreed water volumes with individual irrigators (and other potential users), this option is likely to be financially and legally attractive to some stakeholders. The most significant issue with a Baseline Substitution Option is that it delivers the poorest environmental outcome of all options considered by this business case. Additionally, this quantitative finding does not consider the challenges associated in negotiating with individual land owners/irrigators etc. or other scheme administrative requirements (this is why this option ranked lowest in the Final 30 April 2013 Arup Page x

13 Option qualitative assessment). In addition, whilst the Baseline Substitution Option has the potential to address Arrow Energy s anticipated impact on groundwater drawdown in the CCA, it may not provide a mechanism for Arrow Energy to beneficially use all of the water it produces. For seasonailty reasons, another usage or disposal option may be required, potentially resulting in additional costs. It also has the shortest benefit period of all the options considered as part of this business plan. The key quantitative elements of all of the options are described in the table below. Benefit Stream (years) Water Volume from WTF9 Water supply from the west Total Water Volume Peak Water Volume Peak supply period (years) NPC (capex and opex) $million NPC/ML ($/ML) Baseline Substitution Option 25years 330GL 0 330GL 21.4GL/a 5 years Option 1A 35 years 351GL 0 351GL 21.4GL/a 10 years Option 1B 35 years 351GL 226GL* 577GL 21.4GL/a 20 years Option 1C 50 years 351GL 495GL 846GL 21.4GL/a 30 years Option 2A 35 years 351GL 0 351GL 21.4GL/a 10 years Option 2B 35 years 351GL 226GL* 577GL 21.4GL/a 20 years Option 2C 50 years 351GL 495GL 846GL 21.4GL/a 30 years Option 3A 35 years 351GL 0 351GL 21.4GL/a 10 years Option 3B 35 years 351GL 226GL* 577GL 21.4GL/a 20 years Option 3C 50 years 351GL 495GL 846GL 21.4GL/a 30 years * only 226GL from a potential 503GL is imported from the Chinchilla South region The Options with the lowest the cost per megalitre of water delivered were Options 1C and 2C. This is because water supply profile C extends the peak water supply period and delivers water for up to fifty years meaning that the infrastructure costs are apportioned over a far longer period. These options however have significantly higher upfront costs, with an NPC of more than double the costs of the Baseline Substitution Option. This is because of the more extensive pipeline network that needs to be built, including the South Chinchilla pipeline (sourcing water from CSG companies in the Chinchilla South area) and an associated distribution network. Key reasons for recommending an injection scheme include: Greater recharge efficiency with opportunities for maximising volumes; Administrative simplicity of implementing an injection scheme; Providing flexibility for water extraction and use; and Reduced direct impact on land holdings and the environment due to a requirement for less physical infrastructure. Final 30 April 2013 Arup Page xi

14 Further, implementing the preferred Option 1A also has the following specific benefits: It has the lowest capital cost of all injection options considered in this business case; It allows for a staged development (managed capital investment) of a broader injection scheme, or a hybrid scheme involving both injection and limited substitution; Delivers the second best return on investment (NPC/ML) of all injection options considered in this business case; and It does not rely on additional water from outside of the CCA. Option 1A, although it represents a higher cost per megalitre of water delivered, has a far lower NPC than Option 1C or 2C. For this reason, Option 1A which only utilises water from Arrow Energy s WTF9 facility may provide the best opportunity to implement an injection scheme in the CCA. An additional advantage of Option 1A is that if there is additional water produced by either Arrow Energy (or other CSG companies) beyond the capacity of the initial distribution water pipelines and injection locations, the initial scheme could be readily augmented to inject additional water into the CCA. Conversely, under the indicative substitution option (Baseline Substitution), additional water produced would not necessarily benefit the CCA. It is foreseeable that additional CSG water would be provided to some users as supplies beyond their water allocations, or disposed of by alterantive means. Neither of these alternatives will directly benefit the CCA nor will they contribute to the broader Murray-Darling Basin outcomes. Implementing Option 1A as the preferred option, in the first instance could, at a suitable point in the future, be scaled to a deliver larger volumes of water which may improve further the benefits for stakeholders, the CCA and the Murray- Darling Basin. Implementing the preferred option Although this business case highlights a wide range of environmental, technical, social, infrastructure and financial outcomes associated different potential aquifer water recharge schemes, the key challenge which presents itself is how to ensure implementation of a scheme which optimises the outcomes for stakeholders and the environment. Clearly there are different challenges associated with each of the options considered in this business case there are no risk-free water recharge schemes and similarly none of the schemes will be supported by all stakeholders. However, all stakeholders agree in principle that a recharge scheme involving injection has the potential to demonstrate the greatest benefits, both environmentally for the CCA (and Murray-Darling Basin) and from the perspective of minimising the disruption to existing water allocation and on-farm use of water. If agreement on scheme design and a firm implementation path for an injection scheme, including injection trials, are not committed to in the near future then it is likely that a substitution only scheme (similar to the Baseline Substitution Option) Final 30 April 2013 Arup Page xii

15 will be built by Arrow Energy. Once a substitution only scheme is built, it is unlikely that the additional capital costs required to build an injection scheme would be supported by Arrow Energy, and therefore the opportunity for maximising recharge benefits for the CCA will be lost. To implement an injection scheme in the CCA, the following issues will need to be resolved in a timely manner: Urgent agreement between Queensland Government, Arrow Energy and any other stakeholders to enable injection trials and community engagement to occur leading to implementing an injection only scheme; Injection trials to confirm the expected technical feasibility. These trial will also require funding and based on the investigations of SWS (2013), the costs for deep and shallow injection sites would be in the order of $2.4 million and $2.49 million per site respectively; The need for Queensland Government involvement and leadership including the development of an approvals process as well as a legal framework for the management of potential corporate risks of an injection scheme; and The requirement for early and broad community engagement. Processes to resolve these issues have been set out in the recommendations contained within this report and provide a guide as to the scope of the next phase of the project. Final 30 April 2013 Arup Page xiii

16 Acronyms Acronyms a ADWG ANZECC BSA CA CAPM CCA CDIL CGMA CMA CPI CSG DEHP DERM DEWS DNRM EA EIS EMP EP Act EPCM GAB GDE GL HHW HHW Study IESC KBR KCB LNG m MAR MCA MDBA ML Annum Australian Drinking Water Guidelines Australian and New Zealand Environment Conservation Council Basin Sustainability Alliance Capital Asset Pricing Model Central Central Downs Irrigators Ltd Condamine Groundwater Management Area Cumulative Management Area Consumer Price Index Coal Seam Gas Queensland Department of Environment and Heritage Protection Queensland Department of Environment and Resource Management Queensland Department of Energy and Water Supply Queensland Department of Natural Resources and Mines Environmental Authority Environmental Impact Statement Environmental Management Plan Environmental Protection Act 1994 Queensland Engineering, Procurement, Construction Management Great Artesian Basin Groundwater dependent ecosystem Gigalitre Healthy Headwaters Healthy Headwaters Coal Seam Gas Water Feasibility Study Independent Expert Scientific Committee Kellogg Brown & Root Klohn Crippen Berger Liquefied Natural Gas Metres Managed Aquifer Recharge Multi Criteria Analysis Murray Darling Basin Authority Megalitre Final 30 April Arup Page xiv

17 MNES NPC NPV NRM NWI O&M OGIA P&G Act QGC QMDB QWC RBA SCER SDL SEWPaC SIMS SWS UWIR WCM WRP Matters of National Environmental Significance Net Present Cost Net Present Value Natural Resource Management National Water Initiative Operating and Maintenance Office of Groundwater Impact Assessment, Department of Natural Resources and Mines - Queensland Petroleum and Gas (Production and Safety) Act Queensland Queensland Gas Company Queensland Murray-Darling Basin Queensland Water Commission Reserve Bank of Australia Standing Council on Energy and Resources Sustainable Diversion Limit Commonwealth Department of Sustainability, Environment, Water, Population and Communities Spring Impact Management Strategy Schlumberger Water Services Surat Underground Water Impact Report Walloon Coal Measures Water Resources Plan WTF9 Arrow Energy s Water Treatment Facility 9 Final 30 April Arup Page xv

18 Contents Executive Summary Acronyms Page i xiv Part A 1 Introduction Purpose of this document Recharge scheme options examined by this business case Structure of the document 2 2 Inputs to the business case The Healthy HeadWaters CSG Water Feasibility Study Key HHW Study inputs to the business case Stakeholder Reference Group 7 3 Background and rational for using CSG water in the Central The Central The CSG industry in the Surat Basin Using CSG water in the Central Alternative uses for CSG water near the Central Condamine Alluvium 26 4 Legislative and policy context Environmental management of CSG projects Monitoring and management of groundwater impacts in the Surat 35 Cumulative Management Areas 4.3 Murray-Darling Basin reform Land access and management for CSG projects in Queensland Strategic Cropping Land 38 5 Stakeholder perspectives on CCA recharge Summary of regional stakeholder perspectives 42 Part B 6 Recharge scheme options considered by the business case Overview and rationale for recharge scheme options CSG water supply profiles Considerations for recharge schemes involving groundwater substitution 57 Final 30 April 2013 Arup

19 7 Description of options analysed as part of this business case The Baseline Substitution Option Option 1 - Injection only Option 2 - Injection plus substitution abutting injection pipelines Option 3 Injection plus a substitution network to meet a peak 69 delivery period of at least 20 years 7.5 Summary of options considered in this business case 72 8 Business case option assessment methodology Qualitative assessment methodology Qualitative assessment - criteria and weighting Quantitative (financial) assessment methodology 80 9 Results of qualitative and quantitative assessment Qualitative assessment results Summary of qualitative assessment results Results of the quantitative assessment Observations on the findings of the quantitative (financial) results 106 Part C 10 The feasibility of using treated CSG water to recharge the Central 10.1 Injection versus substitution Stakeholders views on injection and substitution Business case conclusions - injection versus substitution Critical analysis of options considered in this business case Qualitative and quantitative assessments of options Selecting an option Recommended business case option Implementing the preferred CSG recharge scheme in the CCA Injection trials to demonstrate technical viability Agreement among, and commitment by, stakeholders Funding arrangements Legal and governance responsibilities Contractual Engagement with other CSG Companies Spatial distribution of scheme options Risk analysis of the preferred option compared to the Baseline Substitution Option Final 30 April 2013 Arup

20 13 Recommendations References 135 Tables 1 Cumulative CSG water production from source areas identified in 20 Activity Full list of possible CSG water use options identified by Tree Crop 27 Technologies (2013) 3 Stakeholders relevant to the development of the business case 39 4 Queensland GasFields Commission submission on the Queensland 47 Government CSG Water Management Policy (GasFields Commission, 2012) 5 Summary of water supply profiles 56 6 Summary of assumptions applied to options within this business case 72 7 Summary of key water supply characteristics for all options considered 73 in this business case 8 Scoring scale used for assessment criteria 76 9 Qualitative assessment criteria Assessment weighting for each of the qualitative assessment criteria Summary of qualitative assessment results Ranking the options based on qualitative results Quantitative assessment (financial) results Summary of results of sensitivity analysis Summary of quantitative rankings of options Investment relative to cost per ML for Options 1B and 1C Relative advantages and disadvantages of injection only and substitution 111 only recharge schemes 18 Summary of key water supply characteristics for all options considered 115 in this business case 19 Break even volumes of water required to justify the additional cost of 120 the pipeline from the Chinchilla South area 20 Summary of key elements of Options 1A, 1C and Baseline Substitution 122 Option 21 Risk assessment of injection only and substitution only options for CCA 129 recharge 22 Distribution Pipework Rates D7 23 Break Tank Storage Rates D7 24 Pump Station Costs D8 25 Quantitative summary with inclusion of subsurface vault relative to base E1 results 26 Quantitative summary with discount rate of +1 per cent (9.55 per cent) E3 27 Quantitative summary with discount rate of -1 per cent (7.55 per cent) E3 28 Quantitative summary with capital expenditure + 10 per cent E5 Final 30 April 2013 Arup

21 29 Quantitative summary with capital expenditure -10 per cent E5 30 Quantitative summary with power costs -10 per cent E6 31 Quantitative summary with power costs + 10 per cent E7 Figures 1 Project design of the Healthy HeadWaters CSG Water Feasibility Study 4 2 Components of Activity 8 of the Healthy HeadWaters CSG Water 4 Feasibility Study 3 Location of the Central and the Murray-Darling 8 Basin 4 The extent and thickness of the Central (source: 9 KCB, 2011) 5 Concentration of total dissolved solids in the Central Condamine 10 Alluvium (source: KCB, 2011) 6 Cross section of the CCA showing the fall in water levels since the s (DNRM, 2012) 7 Changes in water levels and flows in the CCA as a result of overextraction 12 (DNRM, 2012) 8 Current and future CSG production (petroleum leases and petroleum 15 lease applications) and exploration areas in the Surat and southern Bowen basins as at 8 January The extent and ownership of tenements shown is indicative only and is subject to change. 9 Forecasted annual CSG water production for the Surat and southern 17 Bowen basins, based on a simulated development scenario (KCB, 2012) 10 Forecasted cumulative CSG water production for the Surat and southern 17 Bowen basins, based on a simulated development scenario (KCB, 2012) 11 Comparison of published CSG water production estimates Forecasted CSG water production and supply areas proposed by 19 Activity 8.1 of the HHW Study 13 CSG water production equivalents for the CCA Long-term drawdown impacts in the CCA, as modelled by QWC (2012) Strategically Managing Coal Seam Gas Water (source: Queensland 35 Government, 2012) 16 Water delivery infrastructure and supply areas for the recharge schemes 53 considered in the business case 17 Anticipated CSG water availability from Arrow Energy s WTF9 (near 54 Cecil Plains) and the Chinchilla South supply area (source: KBR, 2012) 18 Water supply profile A water only from Arrow Energy s WTF9 54 (source: KBR, 2012) 19 Water supply profile B water from Arrow Energy s WTF9 (profile A) 55 supplemented with water from the Chinchilla South supply area (source: KBR, 2012) 20 Water supply profile C water from Arrow Energy s WTF9 (profile A) 56 supplemented with water from Chinchilla South supply area but delayed by 10 years (source: KBR, 2012) 21 Assumed yearly water demand profile for substitution components of Options 2 and 3 59 Final 30 April 2013 Arup

22 22 Schematic for a Baseline Substitution Option Indicative water pipeline network for the Baseline Substitution Option Schematic of Option 1 (injection only scheme) Location of water pipelines and injection locations under Option Schematic showing a hybrid scheme Location of water pipelines, injection fields and properties receiving 68 substitution water under Option 2 28 Location of water pipelines, injection fields and properties receiving 70 substitution water under Option 3A 29 Location of water pipelines, injection fields and properties receiving 71 substitution water under Options 3B and 3C 30 Overview of options assessment methodology Generic steps in an MCA High level overview of quantitative (financial assessment) methodology Qualitative results comparing options and water supply profiles Total NPC ($ million) by option Total cost NPC per ML by option Qualitative results for the options Project cost: Net Present Cost ($million) of the options Return on investment: Net Present Cost ($ per megalitre) options Comparison of qualitative score and return on investment (Net Present 121 Cost/ML) for options using water supply profile C 40 Comparison of qualitative score and return on investment (Net Present 121 Cost/ML) for options using water supply profile A 41 Impact of inclusion of subsurface vault relative to base results E2 42 Impact of change in discount rate relative to base results E4 43 Impact of change in capital expenditure relative to base results E6 44 Impact of change in power costs relative to base results E7 Final 30 April 2013 Arup Appendices Appendix A Glossary of terms Appendix B Stakeholders Appendix C SWS Numerical modelling report Appendix D KBR Network methodology Appendix E Sensitivity analysis

Social impact assessment. Guideline to preparing a social impact management plan

Social impact assessment. Guideline to preparing a social impact management plan Social impact assessment Guideline to preparing a social impact management plan September 2010 Looking forward. Delivering now. The Department of Infrastructure and Planning leads a coordinated Queensland

More information

Forecasting coal seam gas water production in Queensland s Surat and southern Bowen basins Technical report

Forecasting coal seam gas water production in Queensland s Surat and southern Bowen basins Technical report Healthy HeadWaters Coal Seam Gas Water Feasibility Study Forecasting coal seam gas water production in Queensland s Surat and southern Bowen basins Technical report Prepared for the Department of Natural

More information

Quick Guide Make good obligations

Quick Guide Make good obligations Quick Guide Make good obligations September 2013 Prepared by: Energy Regulation and Implementation, Department of Environment and Heritage Protection State of Queensland, 2013. The Queensland Government

More information

Submission to the Queensland Competition Authority. Regulated Retail Electricity Prices 2013-14 Transitional Issues & Cost Components and Other Issues

Submission to the Queensland Competition Authority. Regulated Retail Electricity Prices 2013-14 Transitional Issues & Cost Components and Other Issues Submission to the Queensland Competition Authority Transitional Issues & Cost Components and Other Issues January 2013 Queensland Farmers Federation Ltd. A.C.N. 055 764 488 A.B.N. 44 055 764 488 PO Box

More information

Triple bottom line assessment to protect our regions

Triple bottom line assessment to protect our regions NSW Liberals & Nationals Strategic Regional Land Use Triple bottom line assessment to protect our regions Printed and Authorised by Mark Neeham, Level 9, 140 William Street, East Sydney, NSW 2011. The

More information

Guideline: Works that interfere with water in a watercourse watercourse diversions. September 2014

Guideline: Works that interfere with water in a watercourse watercourse diversions. September 2014 Guideline: Works that interfere with water in a watercourse watercourse diversions September 2014 This publication has been compiled by the Department of Natural Resources and Mines. State of Queensland,

More information

How To Manage A Gdf Project

How To Manage A Gdf Project Water resource management plan AE Enter Go back to contents Gas Field Development Project Water Resources Management Plan i Contents Gas Field Development Project 2014 Contents 1 Introduction 1 1.1 Purpose

More information

BB CONSTRAINTS MAPPING

BB CONSTRAINTS MAPPING BB CONSTRAINTS MAPPING ENTER HERE BACK TO CONTENTS The Bowen Gas Project (the Project) constraints analysis has been developed to support the environmental framework approach as detailed in the Environmental

More information

Project Evaluation Guidelines

Project Evaluation Guidelines Project Evaluation Guidelines Queensland Treasury February 1997 For further information, please contact: Budget Division Queensland Treasury Executive Building 100 George Street Brisbane Qld 4000 or telephone

More information

Water Resource (Great Artesian Basin) Plan 2006. Sale of general reserve unallocated water: Tender assessment report

Water Resource (Great Artesian Basin) Plan 2006. Sale of general reserve unallocated water: Tender assessment report Water Resource (Great Artesian Basin) Plan 2006 Sale of general reserve unallocated water: Tender assessment report This publication has been compiled by Water Services Support, Department of Natural Resources

More information

Guide to managing commodity risk

Guide to managing commodity risk Guide to managing commodity risk October 2012 ISBN: 978-1-921742-33-0 CPA Australia Ltd ( CPA Australia ) is one of the world s largest accounting bodies representing more than 139,000 members of the financial,

More information

Review of PIRSA s Cost Recovery Policy and practices, including their application to the Fisheries and Aquaculture Industries Primary Industries and

Review of PIRSA s Cost Recovery Policy and practices, including their application to the Fisheries and Aquaculture Industries Primary Industries and Review of PIRSA s Cost Recovery Policy and practices, including their application to the Fisheries and Aquaculture Industries Primary Industries and Regions SA 29 July 2015 Contents Executive Summary...

More information

Opportunities and Challenges for Australian Gas Presentation by James Baulderstone at the Australia Gas Conference

Opportunities and Challenges for Australian Gas Presentation by James Baulderstone at the Australia Gas Conference Santos Ltd ABN 80 007 550 923 Ground Floor, Santos Centre 60 Flinders Street Adelaide South Australia 5000 GPO Box 2455 Adelaide South Australia 5001 Direct: + 61 8 8116 5000 Facsimile: + 61 8 8116 6723

More information

Water Act 2007. Basin Plan [NOT FOR SIGNATURE]

Water Act 2007. Basin Plan [NOT FOR SIGNATURE] COMMONWEALTH OF AUSTRALIA Water Act 2007 Basin Plan I, Tony Burke, Minister for Sustainability, Environment, Water, Population and Communities, acting under subparagraph 44(3)(i) of the Water Act 2007,

More information

edms 8. AUSTRALIA 8.1 Water Resources Management Policies and Actions

edms 8. AUSTRALIA 8.1 Water Resources Management Policies and Actions 8. AUSTRALIA 8.1 Water Resources Management Policies and Actions In Australia, an Intergovernmental Agreement for a National Water Initiative (NWI) was signed by the Australian Government, all state and

More information

WILLOCHRA BASIN GROUNDWATER STATUS REPORT 2009-10

WILLOCHRA BASIN GROUNDWATER STATUS REPORT 2009-10 WILLOCHRA BASIN GROUNDWATER STATUS REPORT 2009-10 SUMMARY 2009-10 The Willochra Basin is situated in the southern Flinders Ranges in the Mid-North of South Australia, approximately 50 km east of Port Augusta

More information

Exploration for natural gas

Exploration for natural gas FACT SHEET NO. 42 Exploration for natural gas Quick facts QGC holds licences from the Queensland Government called Authorities to Prospect that allow us to explore in areas known as tenements We work with

More information

Water Security Action Plan 2011-2016

Water Security Action Plan 2011-2016 Water Security Action Plan 2011-2016 Approved on: 30 May 2011 Owner: Program Manager, Sustainable City 8203 7723 Trim Reference: ACC2011/59983 Net Review Date: 2013 1 1. Introduction Why Has Council Developed

More information

Department of Natural Resources and Mines Application for licence to take water Purpose of this form Part A Licence information

Department of Natural Resources and Mines Application for licence to take water Purpose of this form Part A Licence information Purpose of this form Department of Natural Resources and Mines Application for licence to take water To apply for a water licence to take and use the water on a parcel or contiguous parcels of land owned

More information

A guide to the water charge (infrastructure) rules: Tier 2 requirements

A guide to the water charge (infrastructure) rules: Tier 2 requirements A guide to the water charge (infrastructure) rules: Tier 2 requirements June 2011 Australian Competition and Consumer Commission 23 Marcus Clarke Street, Canberra, Australian Capital Territory, 2601 Commonwealth

More information

EU China River Basin Management Programme

EU China River Basin Management Programme Ministry of Water Resources Ministry of Environmental Protection EU China River Basin Management Programme Technical Report 075 Water Resource Supply Security Strategy Analysis Ben Piper, Zhang Wang and

More information

5.0. Establishing a comprehensive monitoring network Stage 2

5.0. Establishing a comprehensive monitoring network Stage 2 5.0 Establishing a comprehensive monitoring network Stage 2 56 5.0 Establishing a comprehensive monitoring network Stage 2 Conditions 49, 52 and 65 to 67 5.1 Introduction As planned, QGC has progressed

More information

HUNTER WATER CORPORATION. Greenprint For Sust ainable Urb an Wat er Managem ent

HUNTER WATER CORPORATION. Greenprint For Sust ainable Urb an Wat er Managem ent HUNTER WATER CORPORATION Greenprint For Sust ainable Urb an Wat er Managem ent NOVEMBER 2012 Table of Contents Message from the Managing Director 4 1. Introduction 5 1.1 Cities of the Future 5 1.2 Our

More information

PROJECT AGREEMENT FOR MENINDEE LAKES PROJECT MANAGEMENT

PROJECT AGREEMENT FOR MENINDEE LAKES PROJECT MANAGEMENT PROJECT AGREEMENT FOR MENINDEE LAKES PROJECT MANAGEMENT Council of Australian Governments An agreement between the Commonwealth of Australia and New South Wales The outputs of this project will be the

More information

NOTE FOR MINING AND OIL & GAS COMPANIES - JU N E 2 0 0 9

NOTE FOR MINING AND OIL & GAS COMPANIES - JU N E 2 0 0 9 NOTE FOR MINING AND OIL & GAS COMPANIES - JU N E 2 0 0 9 A G U I D E T O A I M U K TA X B E N E F I T S 2 AIM Note for Mining, Oil and Gas Companies Contents Introduction 1 Companies to which this Note

More information

2014 Residential Electricity Price Trends

2014 Residential Electricity Price Trends FINAL REPORT 2014 Residential Electricity Price Trends To COAG Energy Council 5 December 2014 Reference: EPR0040 2014 Residential Price Trends Inquiries Australian Energy Market Commission PO Box A2449

More information

Appendix 25. Content of a Competent Person s Report for Petroleum Reserves and Resources

Appendix 25. Content of a Competent Person s Report for Petroleum Reserves and Resources Appendix 25 Content of a Competent Person s Report for Petroleum Reserves and Resources (See rule 18.20) The Competent Person s Report for Petroleum Reserves and Resources must include the following: 1.

More information

Electricity network services. Long-term trends in prices and costs

Electricity network services. Long-term trends in prices and costs Electricity network services Long-term trends in prices and costs Contents Executive summary 3 Background 4 Trends in network prices and service 6 Trends in underlying network costs 11 Executive summary

More information

PRICING AND FINANCIAL PROJECTIONS FOR PRIVATE HEALTH INSURERS

PRICING AND FINANCIAL PROJECTIONS FOR PRIVATE HEALTH INSURERS PRACTICE GUIDELINE 699.01 PRICING AND FINANCIAL PROJECTIONS FOR PRIVATE HEALTH INSURERS September 2012 INDEX 1. INTRODUCTION 3 1.1 Application 3 1.2 Classification 3 1.3 Background 3 1.4 Purpose 3 1.5

More information

Developing Power Projects in Southern Africa. Cape Town Presentation 8 th February 2016

Developing Power Projects in Southern Africa. Cape Town Presentation 8 th February 2016 Developing Power Projects in Southern Africa Cape Town Presentation 8 th February 2016 Company Highlights AFR now participating in the development of three large-scale power projects in Botswana Completion

More information

Alternative infrastructure funding and financing

Alternative infrastructure funding and financing Alternative infrastructure funding and financing Research Paper (commissioned by the Queensland Government) 21 March 2016 Department Of Infrastructure, Local Government and Planning This page intentionally

More information

december 08 tpp 08-5 Guidelines for Capital Business Cases OFFICE OF FINANCIAL MANAGEMENT Policy & Guidelines Paper

december 08 tpp 08-5 Guidelines for Capital Business Cases OFFICE OF FINANCIAL MANAGEMENT Policy & Guidelines Paper december 08 Guidelines for Capital Business Cases OFFICE OF FINANCIAL MANAGEMENT Policy & Guidelines Paper Preface The NSW Government is committed to the ongoing improvement of public services by ensuring

More information

2014 Price Review Business Plan Supporting Appendices Network Management. Published 2 December 2013

2014 Price Review Business Plan Supporting Appendices Network Management. Published 2 December 2013 2014 Price Review Business Plan Supporting Appendices Network Management Published 2 December 2013 2 Executive Summary This appendix summarises our approach to Network Management. The appendix focuses

More information

A Guide For Preparing The Financial Information Component Of An Asset Management Plan. Licensing, Monitoring and Customer Protection Division

A Guide For Preparing The Financial Information Component Of An Asset Management Plan. Licensing, Monitoring and Customer Protection Division A Guide For Preparing The Financial Information Component Of An Asset Management Plan Licensing, Monitoring and Customer Protection Division July 2006 Contents 1 Important Notice 2 2 Scope and purpose

More information

Environmental Guidelines for Preparation of an Environmental Management Plan

Environmental Guidelines for Preparation of an Environmental Management Plan 2013 Environmental Guidelines for Preparation of an Environmental Management Plan Environmental Management Division Environmental Protection Agency 3/13/2013 ENVIRONMENTAL GUIDELINES FOR PREPARATION OF

More information

2 COMMENCEMENT DATE 5 3 DEFINITIONS 5 4 MATERIALITY 8. 5 DOCUMENTATION 9 5.1 Requirement for a Report 9 5.2 Content of a Report 9

2 COMMENCEMENT DATE 5 3 DEFINITIONS 5 4 MATERIALITY 8. 5 DOCUMENTATION 9 5.1 Requirement for a Report 9 5.2 Content of a Report 9 PROFESSIONAL STANDARD 300 VALUATIONS OF GENERAL INSURANCE CLAIMS INDEX 1 INTRODUCTION 3 1.1 Application 3 1.2 Classification 3 1.3 Background 3 1.4 Purpose 4 1.5 Previous versions 4 1.6 Legislation and

More information

National Electricity Amendment (Network Support Payments and Avoided TUoS for Embedded Generators) Rule 2011

National Electricity Amendment (Network Support Payments and Avoided TUoS for Embedded Generators) Rule 2011 RULE DETERMINATION National Electricity Amendment (Network Support Payments and Avoided TUoS for Embedded Generators) Rule 2011 Commissioners Pierce Henderson Spalding 22 December 2011 JOHN PIERCE Chairman

More information

UPPER SOUTH EAST DRAINAGE NETWORK MANAGEMENT STRATEGY. June 2011

UPPER SOUTH EAST DRAINAGE NETWORK MANAGEMENT STRATEGY. June 2011 UPPER SOUTH EAST DRAINAGE NETWORK MANAGEMENT STRATEGY June 2011 PREPARED UNDER SECTION 43A OF THE UPPER SOUTH EAST DRYLAND SALINITY AND FLOOD MANAGEMENT ACT 2002 Upper South East Drainage Network Management

More information

1.1 Objective 4. 1.2 Competencies and resources required 4. 1.3 Scope 4. 1.4 Related documents 5. 3.1 Defining the objectives and scope of projects 7

1.1 Objective 4. 1.2 Competencies and resources required 4. 1.3 Scope 4. 1.4 Related documents 5. 3.1 Defining the objectives and scope of projects 7 Contents 1.0 Introduction 3 1.1 Objective 4 1.2 Competencies and resources required 4 1.3 Scope 4 1.4 Related documents 5 2.0 Project evaluation 5 3.0 Project feasibility 7 3.1 Defining the objectives

More information

2013 Residential Electricity Price Trends

2013 Residential Electricity Price Trends FINAL REPORT 2013 Residential Electricity Price Trends 13 December 2013 Reference: EPR0036 Final Report Inquiries Australian Energy Market Commission PO Box A2449 Sydney South NSW 1235 E: aemc@aemc.gov.au

More information

Long Term Financial Planning

Long Term Financial Planning Long Term Financial Planning Framework and Guidelines Long Term Financial Planning Framework and Guidelines for Western Australian Local Governments p1. Contents Foreword 4 1. Introduction 7 2. Purpose

More information

Mandatory Provident Fund Schemes Authority COMPLIANCE STANDARDS FOR MPF APPROVED TRUSTEES. First Edition July 2005. Hong Kong

Mandatory Provident Fund Schemes Authority COMPLIANCE STANDARDS FOR MPF APPROVED TRUSTEES. First Edition July 2005. Hong Kong Mandatory Provident Fund Schemes Authority COMPLIANCE STANDARDS FOR MPF APPROVED TRUSTEES First Edition July 2005 Hong Kong Contents Glossary...2 Introduction to Standards...4 Interpretation Section...6

More information

Rule change request. 18 September 2013

Rule change request. 18 September 2013 Reform of the distribution network pricing arrangements under the National Electricity Rules to provide better guidance for setting, and consulting on, cost-reflective distribution network pricing structures

More information

Developing Power Projects in Southern Africa. Annual General Meeting Presentation 20 th November 2015

Developing Power Projects in Southern Africa. Annual General Meeting Presentation 20 th November 2015 Developing Power Projects in Southern Africa Annual General Meeting Presentation 20 th November 2015 2015 Company Highlights AFR now participating in the development of three large-scale power projects

More information

Stream 1 Regional Natural Resource Management Planning for Climate Change

Stream 1 Regional Natural Resource Management Planning for Climate Change Stream 1 Regional Natural Resource Planning for Climate Change in the Lachlan in the Southern Rivers NRM Lachlan This project will build on the strengths of the Lachlan (Kalare) Action Plan by providing

More information

Queensland s Unsustainable Electricity Pricing Methodology

Queensland s Unsustainable Electricity Pricing Methodology Queensland s Unsustainable Electricity Pricing Methodology Submission to the QCA and Queensland Government in relation to the 2011-12 BRCI Electricity Price Determination 10 February 2011 Page 1 of 12

More information

GOVERNMENT RESPONSE TO ESCOSA S FINAL REPORT INQUIRY INTO 2008-09 METROPOLITAN AND REGIONAL WATER AND WASTEWATER PRICING PROCESS

GOVERNMENT RESPONSE TO ESCOSA S FINAL REPORT INQUIRY INTO 2008-09 METROPOLITAN AND REGIONAL WATER AND WASTEWATER PRICING PROCESS TO ESCOSA S FINAL REPORT INQUIRY INTO 2008-09 METROPOLITAN AND REGIONAL WATER AND WASTEWATER PRICING PROCESS AREA OVERVIEW and ESCOSA identifies an alternative top-down approach to an input based, or bottom

More information

Energy Procurement Practice Guide

Energy Procurement Practice Guide Carbonproof Energy Procurement Practice Guide The material provided in this guide has been produced in conjunction with our partner Energetics Pty Ltd. 2011 Energetics Pty Ltd and AgriFood Skills Australia.

More information

Attachment 20.27 SA Power Networks: Network Program Deliverability Strategy

Attachment 20.27 SA Power Networks: Network Program Deliverability Strategy Attachment 20.27 SA Power Networks: Network Program Deliverability Strategy Network Program Deliverability Strategy 2015-20 Regulatory Control Period SA Power Networks www.sapowernetworks.com.au Internal

More information

Proposal for a RECOMMENDATION OF THE EUROPEAN COMMISSION

Proposal for a RECOMMENDATION OF THE EUROPEAN COMMISSION EUROPEAN COMMISSION Brussels, XXX [ ] (2013) XXX draft Proposal for a RECOMMENDATION OF THE EUROPEAN COMMISSION Providing minimum principles for the exploration and production of hydrocarbons (especially

More information

GasFields Commission Queensland. Annual Report 2014 2015

GasFields Commission Queensland. Annual Report 2014 2015 GasFields Commission Queensland Annual Report 2014 2015 About this Report This annual report reviews the activities and achievements of the GasFields Commission Queensland for the 2014-15 financial year

More information

Summary: Introduction

Summary: Introduction Summary: Melbourne Water has a range of responsibilities in the Port Phillip and Westernport region, including responsibilities for the protection and restoration of waterways and, in collaboration with

More information

Consultation paper. Domestic Gas Market Security of Supply

Consultation paper. Domestic Gas Market Security of Supply Consultation paper Domestic Gas Market Security of Supply September 2009 Introduction How to respond to this consultation paper The closing date for providing comment on this consultation paper is 15 October

More information

Submission on Proposed Approach to Key Modelling Assumptions for 2014 Review of Renewable Energy Target

Submission on Proposed Approach to Key Modelling Assumptions for 2014 Review of Renewable Energy Target Submission on Proposed Approach to Key Modelling Assumptions for 2014 Review of Renewable Energy Target Dear Sir/Madam Thank you for the opportunity to comment on the Consultation Paper on the Proposed

More information

LHT S ASSET MANAGEMENT STRATEGY 2015-20. It s My Home

LHT S ASSET MANAGEMENT STRATEGY 2015-20. It s My Home LHT S ASSET MANAGEMENT STRATEGY 2015-20 It s My Home 0 ASSET MANAGEMENT STRATEGY 2015-20 It s My Home Contents Page No 1. WHAT DOES OUR ASSET MANAGEMENT STRATEGY AIM TO DO? 2 2. WHY IS ASSET MANAGEMENT

More information

Review of the Energy Savings Scheme. Position Paper

Review of the Energy Savings Scheme. Position Paper Review of the Energy Savings Scheme Position Paper October 2015 Contents Executive summary... 3 Energy Savings Scheme Review Report package... 3 Expanding to gas... 3 Target, penalties and duration...

More information

Shine Corporate Limited (SHJ) Annual General Meeting 2014. Chairman s Address and Managing Director s Presentation

Shine Corporate Limited (SHJ) Annual General Meeting 2014. Chairman s Address and Managing Director s Presentation ASX Announcement Shine Corporate Limited (SHJ) Annual General Meeting 2014 Chairman s Address and Managing Director s Presentation Attached are the following documents, which will be presented at the Annual

More information

GROUNDWATER RESOURCES MANAGEMENT IN SAUDI ARABIA

GROUNDWATER RESOURCES MANAGEMENT IN SAUDI ARABIA GROUNDWATER RESOURCES MANAGEMENT IN SAUDI ARABIA Walid A. Abderrahman Professor, Water Resources Management President, Saudi Water Association Special Presentation at Water Conservation Workshop Khober,

More information

Indoor Water Conservation and I&I Reduction (EIR Alternatives 1 and 2)

Indoor Water Conservation and I&I Reduction (EIR Alternatives 1 and 2) SECTION 2 Description of Master Plan Alternatives The six alternatives that constitute the building blocks of the IRWP Master Plan are as follows: Indoor Water Conservation (EIR Alternative 1) I&I Reduction

More information

CHAPTER 24: ENVIRONMENTAL MANAGEMENT

CHAPTER 24: ENVIRONMENTAL MANAGEMENT Central Eyre Iron Project Environmental Impact Statement CHAPTER 24: ENVIRONMENTAL MANAGEMENT CHAPTER 24 ENVIRONMENTAL MANAGEMENT COPYRIGHT Copyright Iron Road Limited, 2015 All rights reserved This document

More information

Chapter 1 Introduction

Chapter 1 Introduction Chapter 1 Section 1421 of SDWA tasks EPA with protecting USDWs for all current and future drinking water supplies across the country (see section 1.3 for the complete definition of a USDW). EPA s UIC Program

More information

CSBI TIMELINE TOOL A TOOL FOR ALIGNING TIMELINES FOR PROJECT EXECUTION, BIODIVERSITY MANAGEMENT AND FINANCING CROSS- SECTOR BIODIVERSITY INITIATIVE

CSBI TIMELINE TOOL A TOOL FOR ALIGNING TIMELINES FOR PROJECT EXECUTION, BIODIVERSITY MANAGEMENT AND FINANCING CROSS- SECTOR BIODIVERSITY INITIATIVE CSBI TIMELINE TOOL A TOOL FOR ALIGNING TIMELINES FOR PROJECT EXECUTION, BIODIVERSITY MANAGEMENT AND FINANCING CROSS- SECTOR BIODIVERSITY INITIATIVE DECEMBER 2013 1 The Cross Sector Biodiversity Initiative

More information

Works Approval Conditions 1 General

Works Approval Conditions 1 General Works Approval Conditions 1 General 1.1 Interpretation 1.1.1 In the Works Approval, definitions from the Environmental Protection Act 1986 apply unless the contrary intention appears. 1.1.2 In the Works

More information

INDONESIA - LAW ON WATER RESOURCES,

INDONESIA - LAW ON WATER RESOURCES, Environment and Development Journal Law LEAD INDONESIA - LAW ON WATER RESOURCES, 2004 VOLUME 2/1 LEAD Journal (Law, Environment and Development Journal) is a peer-reviewed academic publication based in

More information

HIGH PEAK BOROUGH COUNCIL. Report to the Corporate Select Committee. 19th January 2016

HIGH PEAK BOROUGH COUNCIL. Report to the Corporate Select Committee. 19th January 2016 AGENDA ITEM 5 HIGH PEAK BOROUGH COUNCIL Report to the Corporate Select Committee 19th January 2016 TITLE: EXECUTIVE COUNCILLOR: CONTACT OFFICER: WARDS INVOLVED: Housing Revenue Account (HRA) Business Plan

More information

2017 19 TasNetworks Regulatory Proposal Expenditure Forecasting Methodology

2017 19 TasNetworks Regulatory Proposal Expenditure Forecasting Methodology 2017 19 TasNetworks Regulatory Proposal Expenditure Forecasting Methodology Version Number 1 26 June 2015 Tasmanian Networks Pty Ltd (ACN 167 357 299) Table of contents 1 Introduction... 1 2 Meeting our

More information

Senate Select Committee on Unconventional Gas Mining PO Box 6100 Parliament House Canberra ACT 2600

Senate Select Committee on Unconventional Gas Mining PO Box 6100 Parliament House Canberra ACT 2600 Senate Select Committee on Unconventional Gas Mining PO Box 6100 Parliament House Canberra ACT 2600 Dear Sir/Madam 22 February 2016 Please find attached a personal submission to the Senate Select Committee

More information

Expectations and Future Direction of MOP Guidelines Matthew Newton, Principal Officer Rehabilitation Standards Division of Resources & Energy

Expectations and Future Direction of MOP Guidelines Matthew Newton, Principal Officer Rehabilitation Standards Division of Resources & Energy Expectations and Future Direction of MOP Guidelines Matthew Newton, Principal Officer Rehabilitation Standards Division of Resources & Energy Mine Rehab Conference 2014 Best Practice Ecological Rehabilitation

More information

Environmental guidelines for preparation of an Environment Management Plan

Environmental guidelines for preparation of an Environment Management Plan Environmental guidelines for preparation of an Environment Management Plan Environment Protection Authority MAY 2013 Australian Capital Territory, Canberra 2013 This work is copyright. Apart from any use

More information

NECA response to Industry Engagement in Training Package Development Towards a Contestable Model Discussion Paper

NECA response to Industry Engagement in Training Package Development Towards a Contestable Model Discussion Paper NECA response to Industry Engagement in Training Package Development Towards a Contestable Model Discussion Paper Prepared by: Suresh Manickam Date: 19 th December, 2014 NECA National Office 1 19 th December

More information

Northern Territory Fisheries Resource Sharing Framework

Northern Territory Fisheries Resource Sharing Framework Northern Territory Fisheries Resource Sharing Framework Page 1 of 11 Introduction Fishing is important in the Northern Territory (Territory). Coastal Aboriginal people recognise sea country out to the

More information

WE RE HERE TO CHANGE BUSINESS ENERGY IN AUSTRALIA FOREVER.

WE RE HERE TO CHANGE BUSINESS ENERGY IN AUSTRALIA FOREVER. BUSINESS ELECTRICITY CAN BE BETTER. MUCH BETTER. ERM POWER HAS BEEN A QUIET ACHIEVER IN THE ENERGY INDUSTRY FOR MORE THAN 30 YEARS. WE SPECIALISE IN SELLING ELECTRICITY TO BUSINESS CUSTOMERS AND HAVE GROWN

More information

Analysing the Demand Supply Dynamics of the Australian South Eastern Gas Market Using PLEXOS

Analysing the Demand Supply Dynamics of the Australian South Eastern Gas Market Using PLEXOS Analysing the Demand Supply Dynamics of the Australian South Eastern Gas Market Using PLEXOS Executive Summary These are interesting times for the Eastern Australian gas market with the impending LNG play

More information

Ground Water Surveys and Investigation

Ground Water Surveys and Investigation Ground Water Surveys and Investigation By Gautam Mahajan ASHISH PUBLISHING HOUSE 8/81, PUNJABI BAGH, NEW DELHI-110 026 - Contents Preface List of Abbrivations (v) (vii) 1.1 1.2 1.3 1.4 1.5 1.6 1.7 1.7.1

More information

1 Fiscal strategy and outlook

1 Fiscal strategy and outlook 1 Fiscal strategy and outlook Features The 2015-16 Budget delivers the Government s election commitments, with key measures to revitalise the State economy and frontline service delivery, especially in

More information

SUBMISSION Performance Benchmarking of Australian Business Regulation: Planning, Zoning and Development Assessments

SUBMISSION Performance Benchmarking of Australian Business Regulation: Planning, Zoning and Development Assessments SUBMISSION Performance Benchmarking of Australian Business Regulation: Planning, Zoning and Development Assessments INTRODUCTION Cement Concrete and Aggregates Australia made a preliminary submission to

More information

Capital Works Management Framework

Capital Works Management Framework POLICY DOCUMENT Capital Works Management Framework Policy for managing risks in the planning and delivery of Queensland Government building projects Department of Public Works The concept of the asset

More information

Information Paper. Investigation into prices for electricity and water services in the ACT

Information Paper. Investigation into prices for electricity and water services in the ACT Information Paper Investigation into prices for electricity and water services in the ACT DECEMBER 2002 INDEPENDENT COMPETITION AND REGULATORY COMMISSION INFORMATION PAPER INVESTIGATION INTO PRICES FOR

More information

Information Paper 9. Local Government Financial Indicators

Information Paper 9. Local Government Financial Indicators Information Paper 9 Local Government Financial Indicators November, 2006 Introduction Formal financial statements contain a wealth of information. Unfortunately their detail and format often mean it is

More information

Environment Committee 11 January 2016

Environment Committee 11 January 2016 Environment Committee 11 January 2016 Title Whole Life Costing of Footway Maintenance Treatments and Scheme Prioritisation Report of Wards Status Urgent Key Enclosures Commissioning Director, Environment

More information

Australian Accounting Standards Board (AASB)

Australian Accounting Standards Board (AASB) Standards Board () FACT SHEET September 2011 1038 Life Insurance Contracts (This fact sheet is based on the standard as at 1 January 2011.) Important note: This standard is an Australian specific standard

More information

Purpose of the water security outlook

Purpose of the water security outlook Water Security Outlook December 2015 Purpose of the water security outlook The Water Security Outlook (WSO) is an annual update to Barwon Water s Water Supply Demand Strategy (WSDS), published in 2012.

More information

Specialist Cloud Services Lot 4 Cloud Printing and Imaging Consultancy Services

Specialist Cloud Services Lot 4 Cloud Printing and Imaging Consultancy Services Specialist Cloud Services Lot 4 Cloud Printing and Imaging Consultancy Services Page 1 1 Contents 1 Contents... 2 2 Transcend360 Introduction... 3 3 Service overview... 4 3.1 Service introduction... 4

More information

RE: Submission to the 30 Year Electricity Strategy Discussion Paper

RE: Submission to the 30 Year Electricity Strategy Discussion Paper 6 December 2013 The 30-year Electricity Strategy Discussion Paper Department of Energy and Water Supply PO Box 15456 CITY EAST QLD 4002 electricitystrategy@dews.qld.gov.au Dear Sir/Madam RE: Submission

More information

Water Resources Management Plan

Water Resources Management Plan Yorkshire Water Water Resources Management Plan 2014 1 Water Resources Management Plan Yorkshire Water Services Ltd August 2014 Yorkshire Water Water Resources Management Plan 2014 2 Yorkshire Water Water

More information

Procurement Strategy and Contract Selection

Procurement Strategy and Contract Selection GUIDELINE Capital Works Management Framework Procurement Strategy and Contract Selection The suite of Capital Works Management Framework documents is available online www.hpw.qld.gov.au: The Capital Works

More information

Water Forever: South West Margaret River Forum

Water Forever: South West Margaret River Forum Questions from the MRREC 1. How much water is currently being taken from each well/bore and region in the South West? This is a question for the water regulator the Department of Water. Please note information

More information

3 Year Financial Plan

3 Year Financial Plan 3 Year Financial Plan 2012-2015 Contents Executive Summary 3 Recommendation 4 1. Balanced budget 5 2. Overview of process and methodology 5 3. Transition strategy 6 4. Statement of Financial Position

More information

TAX AND SUPERANNUATION LAWS AMENDMENT (2014 MEASURES NO.#) BILL 2014: EXPLORATION DEVELOPMENT INCENTIVE EXPLANATORY MATERIAL

TAX AND SUPERANNUATION LAWS AMENDMENT (2014 MEASURES NO.#) BILL 2014: EXPLORATION DEVELOPMENT INCENTIVE EXPLANATORY MATERIAL TAX AND SUPERANNUATION LAWS AMENDMENT (2014 MEASURES NO.#) BILL 2014: EXPLORATION DEVELOPMENT INCENTIVE EXPLANATORY MATERIAL Table of contents Glossary... 1 Chapter 1 Exploration development incentive...

More information

A GUIDE TO UNDERSTANDING AUDITING AND ASSURANCE:

A GUIDE TO UNDERSTANDING AUDITING AND ASSURANCE: A GUIDE TO UNDERSTANDING AUDITING AND ASSURANCE: LISTED COMPANIES OCTOBER 2014 BE HEARD. BE RECOGNISED. 2 A GUIDE TO UNDERSTANDING AUDITING AND ASSURANCE CPA Australia Ltd ( CPA Australia ) is one of the

More information

City of Fort Collins Water Supply and Demand Management Policy

City of Fort Collins Water Supply and Demand Management Policy City of Fort Collins Water Supply and Demand Management Policy The City of Fort Collins Water Supply and Demand Management Policy provides a foundational framework for water supply and demand management

More information

Pocket Guide to Clinical Risk Management

Pocket Guide to Clinical Risk Management TOOLKIT FOR MANAGING RISK IN HEALTH CARE TOOLKIT Pocket Guide to Clinical Risk Management ACKNOWLEDGEMENTS The Pocket Guide to Clinical Risk Management is designed to support Area Health Service Executives

More information

Procurement of Goods, Services and Works Policy

Procurement of Goods, Services and Works Policy Procurement of Goods, Services and Works Policy Policy CP083 Prepared Reviewed Approved Date Council Minute No. Procurement Unit SMT Council April 2016 2016/0074 Trim File: 18/02/01 To be reviewed: March

More information

AGENDA ITEM: 8 SUMMARY

AGENDA ITEM: 8 SUMMARY AGENDA ITEM: 8 SUMMARY Report for: Housing and Community Overview and Scrutiny Committee Date of meeting: 28th January 2015 PART: 1 If Part II, reason: Title of report: Contact: Purpose of report: Recommendations

More information

D E PA R T M E N T O F B U S I N E S S, E C O N O M I C A N D R E G I O N A L D E V E L O P M E N T. Annual Report 2006/2007

D E PA R T M E N T O F B U S I N E S S, E C O N O M I C A N D R E G I O N A L D E V E L O P M E N T. Annual Report 2006/2007 D E PA R T M E N T O F B U S I N E S S, E C O N O M I C A N D R E G I O N A L D E V E L O P M E N T Annual Report 2006/2007 Purpose of this report This report is designed with two purposes in mind. Primarily

More information

New Energy Jobs Fund. Application Guidelines

New Energy Jobs Fund. Application Guidelines New Energy Jobs Fund Application Guidelines i Table of Contents 1. Background... 1 2. The Program... 1 2.1. Objectives... 1 2.2. Overview... 1 2.3. Program Timetable... 2 3. Funding... 3 4. Eligibility...

More information

COMPLIANCE REVIEW OF 2006/07 ASSET MANAGEMENT PLAN. Top Energy Limited

COMPLIANCE REVIEW OF 2006/07 ASSET MANAGEMENT PLAN. Top Energy Limited PB ASSOCIATES COMPLIANCE REVIEW OF 2006/07 ASSET MANAGEMENT PLAN Prepared for PB Associates Quality System: Document Identifier : 153162 Top Energy Final Report Revision : 2 Report Status : Final Date

More information

CENTRAL BANK OF KENYA (CBK) PRUDENTIAL GUIDELINE ON BUSINESS CONTINUITY MANAGEMENT (BCM) FOR INSTITUTIONS LICENSED UNDER THE BANKING ACT

CENTRAL BANK OF KENYA (CBK) PRUDENTIAL GUIDELINE ON BUSINESS CONTINUITY MANAGEMENT (BCM) FOR INSTITUTIONS LICENSED UNDER THE BANKING ACT CENTRAL BANK OF KENYA (CBK) PRUDENTIAL GUIDELINE ON BUSINESS CONTINUITY MANAGEMENT (BCM) FOR INSTITUTIONS LICENSED UNDER THE BANKING ACT JANUARY 2008 GUIDELINE ON BUSINESS CONTINUITY GUIDELINE CBK/PG/14

More information

Key Words: Flood Reconstruction, Resource Contracts, Coal Seam Gas, Contract Management, Project Management, Relationship Contracting

Key Words: Flood Reconstruction, Resource Contracts, Coal Seam Gas, Contract Management, Project Management, Relationship Contracting Rebuilding Flood Damaged Roads in South East Queensland in the middle of the Coal Seam Gas Expansion/Explosion - A Local Governments Experience and Learning's David Pemberton davep@logit.com.au Mobile

More information